cek - master's thesis1 introduction the 20th century saw a rapid increase in population as well...
TRANSCRIPT
UNIVERSITY OF LJUBLJANA
FACULTY OF ECONOMICS
MASTER'S THESIS
AN ANALYSIS OF THE TURKISH ELECTRICITY MARKET
Ljubljana, September 2015 TANJA MIMOVIĆ
AUTHORSHIP STATEMENT
I, the undersigned Tanja Mimović, a student at the University of Ljubljana, Faculty of
Economics, (hereafter: the FELU), hereby declare that I am the author of the master’s thesis
entitled “An Analysis of the Turkish Electricity Market”, written under the supervision of
Professor doc. dr. Matej Švigelj.
In accordance with the Copyright and Related Rights Act (Official Gazette of the Republic of
Slovenia, No. 21/1995 with changes and amendments), I hereby allow the text of my master’s
thesis to be published on the FELU’s website.
I further declare that:
the text of my master’s thesis is based on the results of my own research;
the text of my master’s thesis is language-edited and technically compliant with the
FELU’s Technical Guidelines for Written Works, meaning that I
o cited and/or quoted the works and opinions of other authors in my master’s thesis
in accordance with the FELU’s Technical Guidelines for Written Works, and
o obtained (and referred to in my master’s thesis) all the necessary consents to use
the works of other authors that are entirely (in written or graphical form) used in
my text;
I am aware of the fact that plagiarism (in written or graphical form) is a criminal offence
and may be prosecuted in accordance with the Criminal Code (Official Gazette of the
Republic of Slovenia, No. 55/2008 with changes and amendments); and
I am aware of the consequences a proven charge of plagiarism based on the submitted
master’s thesis could have for my status at the FELU in accordance with the relevant
FELU Rules on Master’s Thesis.
Ljubljana, 25 September 2015 Author’s signature:
i
TABLE OF CONTENTS
INTRODUCTION
………………………………………………………….….….….....……..1
1 EUROPEAN UNION ELECTRICITY MARKET ………………………..….……….…….3
1.1 Establishment of a European Union internal electricity market …….….….………….…..4
1.2 Regional electricity markets in the European Union
…………….………..………...........10
1.2.1 Electricity Regional Initiative
………………………………………...………............10
1.2.2 South East Europe ………………………………………………….….………….….13
1.3 Turkish electricity market overview and its interconnection with the SEE region
…..…...……………………………………………………………………………………15
2 ELECTRICITY MARKET REFORM IN TURKEY
……………….…….……….…….…17
2.1 Turkish electricity market prior to reform
………………………….….…………..……..17
2.2 Institutional framework ……………………………………………….………...….….…19
2.2.1 Electricity Market Law No. 4628
……………………………….…………….……...19
2.2.2 New Electricity Market Law No. 6446
….…………...…….……………….....……...22
2.3 Privatization
……………………………….……………………….…………...…..…….23
2.3.1 Privatization of distribution companies
……………..……….…………......….….…..23
2.3.2 Privatization of generation assets
……………………………………………….….....25
3 TURKISH ELECTRICITY MARKET ANALYSIS ……………………………...….……27
3.1 Generation …………………………………………………………………………….….27
3.1.1 Natural gas ………………………….…………………………………………….…..29
3.1.2 Coal
…….……………………………………………………………………….….…33
3.1.3 Hydroelectric power ….…………………………………………………...……….…34
3.1.4 Renewables ..…………………………………………………………..……….……..35
3.2 Transmission…….………………………………………………....………….…….……37
3.3 Wholesale market…………………………………………………….…………….……..40
3.3.1 Bilateral contracts and the role of TETAS ……………………...……………………41
3.3.2 Derivatives
…….…………………………………………,…………………………..45
3.3.3 Day-ahead market
……….……………………………….…………………………...45
ii
3.3.4 Balancing market ………..…………………………………………………….……...47
3.3.5 Price determination and market data ……………………………………….….……..47
3.3.6 Expected future market developments ………………………………….........………50
3.4 Distribution and retail market….…………………………………………………………51
4 ASSESSMENT OF ELECTRICITY MARKET DEVELOPMENTS IN TURKEY ………
56
4.1 Level of harmonization of Turkey’s electricity market with EU legislation and
practices…………………………………………………………….………………………...56
4.2 Future challenges……….. ……………………………………………………………….58
CONCLUSION ………………………………………………………………………………61
REFERENCE LIST ………………………………………………………………………….63
LIST OF FIGURES
Figure 1. Electricity supply chain – competitive and regulated activities ............................................... 5
Figure 2. Population of Turkey and GDP growth rates for Turkey, the Euro Area and OECD countries
............................................................................................................................................................... 15
Figure 3. Turkish electricity demand 1975-2013 .................................................................................. 16
Figure 4: Unbundling of public assets ................................................................................................... 19
Figure 5. Proportion of Turkey’s total installed capacity accounted for by EUAS 2006-2013 ............ 27
Figure 6. Electricity generation in Turkey by primary resources, 2013 in percentages ........................ 29
Figure 7. Turkish natural gas market structure ...................................................................................... 30
Figure 8. Lignite and hard coal rich regions in Turkey ........................................................................ 34
Figure 9. Production, consumption and import of coal in Turkey, 2005-2012 ..................................... 34
Figure 10. Turkey’s installed renewable capacity and thermal capacity 2006-2013 ............................ 38
Figure 11. Turkey’s interconnection with neighbouring countries ....................................................... 38
Figure 12. Total electricity imports and exports by Turkey 2003-2013 ................................................ 40
Figure 13. Current structure of the wholesale electricity market .......................................................... 41
Figure 14. Bilateral contracts electricity market and energy flow ........................................................ 43
Figure 15. Market share of TETAS 2002-2013, in percentages ............................................................ 44
Figure 16. Proportion of the Turkish wholesale electricity market accounted for by bilateral contracts,
and bilateral contracts by sector (on 9 October 2014), in percentages .................................................. 45
Figure 17. Private and bilateral contracts .............................................................................................. 45
Figure 18. Volume and value of base load electricity futures (2011–2013) ......................................... 46
Figure 19. Price determination on the day-ahead market (left) and balancing market (right) .............. 49
Figure 20. Turkish wholesale electricity market price .......................................................................... 50
Figure 21. Wholesale electricity market prices of the EU REM (Q2 2013).......................................... 51
Figure 22. Retail market opening in Turkey ........................................................................................ 53
Figure 23. Retail prices for household customers in Turkey and EU countries (2013) ........................ 56
Figure 24. Retail prices for industrial customers in Turkey and EU countries (2013) .......................... 56
Figure 25. Retail prices for industrial and household customers in Turkey (2010–2014) .................... 57
Figure 26. Distribution losses (loss and theft ratios), 2013 in percentages ........................................... 60
Figure 27. Share of natural gas in electricity generation ....................................................................... 62
iii
LIST OF TABLES
Table 1. Electricity Regional Initiative (ERI) .......................................................................... 10
Table 2. 2014 SEE region status (integration with the EU’s IEM) .......................................... 14
Table 3. Electricity distribution regions in Turkey, distribution companies and the
privatization thereof ................................................................................................................. 23
Table 4. Privatization of major thermal power plants 2013-2014 ............................................ 26
Table 5. Distribution of installed capacity by primary energy resources and market share of
electric utilities in Turkey, 2013 .............................................................................................. 28
Table 6. Natural gas and LNG sale and purchase agreements (BOTAS) ................................ 30
Table 7. Natural gas prices for Turkey 2012–2013 (for BOTAS) ........................................... 31
Table 8. TETAS trading portfolio in 2013 (purchase) ............................................................. 44
Table 9. Generation company X’s portfolio ............................................................................. 47
Table 10. Example of flexible sales/bids of generation company X ........................................ 48
Table 11. Comparison of the current and new wholesale electricity market structure ............ 52
Table 12. Harmonization with EU legislation and practices .................................................... 59
Table 13. System losses by SEE contracting parties, 2013 in percentages .............................. 61
1
INTRODUCTION
The 20th
century saw a rapid increase in population as well as industrialization. This resulted
in a huge demand for energy across the world (Baris & Kucukali, 2012, p. 377). Global total
net electricity generation reached 17,331 terawatt hours (TWh) in 2005 and is projected to
increase to 39,034 TWh in 2040 at a growth rate of 2.2% (2010–2040), as reported in an
International Energy Outlook 2013 reference case (U.S. Energy Information Administration,
2013). In the same reference case, global energy consumption (liquids, natural gas, coal,
nuclear and other) is projected to grow at a rate of 1.5% in the period 2010–2040.
Data regarding the Turkish electricity market is comparable to the upward global electricity
generation trend. Electricity generation in Turkey totalled 162 TWh in 2005 compared with
240 TWh in 2013. This is a 50% increase in the period 2005–2013 (TurkStat, 2014). The
country’s electricity demand has historically been high, except in 1999 when Turkey suffered
a devastating earthquake, and in 1994, 2001, 2008 and 2009, years in which the country faced
a severe economic crisis. An increase in electricity demand is expected, from 242,020
gigawatt hours (GWh) in 2010 to 499,490 GWh in 2020, as a consequence of the projected
increase in the population and the country’s economic growth (Atiyas, Çetin, & Gülen, 2012,
p. 15; Baris & Kucukali, 2010, p. 2441).
Electricity plays an important role in every country’s economy, since it represents a crucial
factor to economic and social development (Toklu, 2013, p. 456). The main features of the
electricity market have been economies of scale in generation and the fact that generated
electricity must pass through an extensive transmission and distribution network to be
delivered to the end-customer (Kopsakangas – Savolainen & Svento, 2012, p. 5). Due to these
natural monopolistic characteristics, international electricity sectors were operated by the state
as a natural monopoly (also referred to as a state monopoly) during the 20th
century, resulting
in a situation where a state-owned company dominated the entire electricity supply chain,
including generation, transmission and distribution.
It was later determined, however, that introducing competition to potentially competitive
segments of the industry might increase its overall efficiency. This meant that network
activities such as transmission and distribution (with its natural monopolistic characteristics)
should be segregated from generation, wholesale and retail sales activities (which were
recognized as potentially competitive activities) (Kopsakangas-Savolainen & Svento, 2012, p.
5).
This led to the start of energy market1 reform at the international level. “Since each country
differed in terms of their geography, availability of domestic resources, energy trade balance,
composition of their economy, and socio-political conditions, the restructuring approach
differed” from country to country (Atiyas et al., 2012, p. 1). Nevertheless, reform comprises
four fundamental elements common to all countries: “privatization of publicly owned
electricity assets; the opening of the market to competition; the extension of vertical
1 In literature, the term energy markets usually refers to gas and electricity markets. In this master’s thesis, the
term refers to electricity markets.
2
unbundling of transmission and distribution activities from generation and retail activities;
and the introduction of an independent regulator” (Pollitt, 2009, p. 4).
One of the first countries to reform its electricity sector was Chile (1987). Just two years later,
England and Wales also initiated a massive privatization and restructuring process (1989).
The motivation behind the reform was to make the energy sector cost efficient through the
introduction of competition (Sioshansi, 2006, p. 70). Alongside the economic motivation for
reform, there were also political incentives such as distaste for strong unions and the urge to
attract foreign investment, as well as environment concerns (Woo, Loyd & Tishler, 2003, p.
1104).
With its strategic and political goals, as well as economic concerns, the EU has also been
engaged in a debate on the restructuring of energy markets (Baha Karan & Kazdağli, 2011).
The main idea was to create an internal electricity market with effective competition that
mainly benefits customers (by lowering prices) and companies (by reducing the possibility of
the abuse of market power by dominant companies). These benefits were the underlying
principle for the liberalization of European energy markets (Böckers, Haucap & Heimeshoff,
2013, p. 7).
As an EU candidate country, Turkey also followed the global trend of energy sector
restructuring, with its own triggers for reform. One of the main reasons was the rapid growth
in electricity demand and the government’s inability to meet that demand. Another significant
trigger for reform was foreign influence. Firstly, electricity market reform is one of the
preconditions for EU membership. Secondly, international institutions (IMF, World Bank and
OECD) that have supported Turkey through its economic crises highlighted the need for
energy market reform. Moreover, inefficient state monopolies were problematic in many other
developing countries, as well (Erdogdu, 2006, p. 986).
The purpose of this thesis is to analyse the Turkish electricity market following the major
reform thereof, and to assess its current level of harmonization with EU legislation and
practices.
This thesis has five main objectives. The first is to review the EU internal electricity market
and its regional electricity markets, and to compare the Turkish electricity market with the
countries of the South East Europe (SEE) region. The second objective is to identify all
triggers and the historical background of Turkish electricity market reform. The third
objective is to analyse the Turkish electricity market by separately regulated (transmission
and distribution) and competitive (generation, wholesale and retail sales) activities. The fourth
objective is to assess the level of competition and to analyse possible entry barriers for new
market entrants. The final and most important objective is to assess the level of harmonization
of Turkey with EU’s rules, legislation and practices, and to identify future challenges for the
Turkish electricity market.
This thesis has four main chapters that are further divided into several subchapters. The first
chapter describes the EU internal electricity market and its three energy packages. Regional
3
electricity markets are also presented in order to illustrate the connection between Turkey and
the SEE regional market. At the end of the chapter, an overview of the Turkish electricity
market is presented, as well a comparison of the market to the electricity markets of SEE
countries. The implementation of the three electricity directives in Member States is used as a
benchmark for Turkey in order to explain the current status of Turkey and its target model for
the future.
In order to understand the current market structure, the second chapter covers the process of
electricity market reform in Turkey, beginning with an analysis of the market prior to reform.
Triggers and the institutional framework of reform are presented, as well as the privatization
process. Generation and distribution assets for privatization are presented, together with an
overview of the progress of the privatization process.
The third chapter is the most important, since it analyses the current structure and functioning
of the Turkish electricity market. The first subchapter presents an analysis of electricity
generation, in terms of the resources used for electricity generation, as well as the ownership
of generation assets. The role of government and publicly owned companies is also presented.
The next subchapter explains the transmission system and the links between Turkey and
neighbouring countries. Further on, electricity trading is presented in the subchapter on the
wholesale electricity market, which covers the major market player TETAS, as well as
Turkish wholesale market prices and their comparison with other EU regional market prices.
The connection between the natural gas and electricity markets is explained throughout the
chapter. In the last subchapter, an analysis of distribution and retail activities is presented,
together with a graphical presentation of retail prices.
Recent developments on the Turkish electricity market are assessed in chapter four. First, the
level of harmonization of Turkey’s electricity market with EU legislation and practices is
reviewed, followed by a presentation of future challenges for the country. At the end of the
thesis, the main findings are summed up in the conclusion.
The main research methods applied are the descriptive method, together with inductive and
deductive reasoning, and the comparative method. In addition, extensive literature on the
electricity market and the reform thereof was used in order to better understand the topic. For
a detailed explanation, the following databases were used: Turkish Statistical Institute
(TurkStat), Ministry of Energy and Natural Resources Turkey (MENR), Energy Market
Regulatory Authority (EMRA), U.S. Energy Information Administration (EIA), European
Network of Transmission System Operators for Electricity (ENTSO-E), International Energy
Agency (IEA), EU Commission and Eurostat.
1 EUROPEAN UNION ELECTRICITY MARKET
The European Union (EU) electricity market is part of the EU’s wider energy policy.
Historically, the founding Member States highlighted the need for a common approach to
energy with the Coal and Steel Treaty in 1952 and the Euratom Treaty in 1957. Energy
markets have changed significantly since then, and the need for an efficient common energy
policy has grown with the EU’s increasing energy challenges such as climate change,
4
increasing dependence on imports and higher energy prices (Commission of the European
Communities, 2007). The EU is committed to addressing these challenges, primarily through
the establishment of a real Internal Energy Market (IEM), i.e. the creation of an internal
electricity market and an internal gas market.
European energy policy is currently focused on achieving sustainability (to reduce EU and
global greenhouse emissions), the security of supply (investments in additional generation
and the establishment of an effective internal electricity and gas market) and competitiveness
(stimulation of fair and competitive prices) (Commission of the European Communities,
2007; European Parliament, 2014).
1.1 Establishment of a European Union internal electricity market
Historically, the main features of the electricity industry have been economies of scale in
generation and the fact that generated electricity must pass through an extensive transmission
and distribution network to be delivered to the end-customer (Kopsakangas-Savolainen &
Svento, 2012, p. 5). Due to these natural monopolistic characteristics, international electricity
markets were operated by the state as a natural monopoly (also referred to as a state
monopoly) or by a large monopolistic company during the 20th
century, resulting in a situation
where only one (state-owned) company dominated the entire electricity supply chain.
In practice, this meant that the state regulated the electricity sector by setting prices and
defining technical frameworks. The state was usually the regulator, as well as the owner and
manager of electricity companies. Typical examples are the French company EDF, Great
Britain’s CEGB (Central Electricity Generating Board), ENEL in Italy and Verbund in
Austria (Hrovatin & Zorić, 2011, p. 3).
Nevertheless, there was a growing ideological and political disaffection with these vertically
integrated monopolies. Moreover, successful liberalization processes were carried out in other
network industries, and thus led to initiatives to liberalize the electricity industry worldwide
(Meeus, Purchala & Belmans, 2005, p. 25). The EU was no exception. With its strategic and
political goals, as well as economic concerns, it has been actively engaged in a debate on the
restructuring of energy markets (Karan & Kazdağli, 2011, p. 12).
The EU’s main idea was to create an internal electricity market with effective competition
that mainly benefits customers (by lowering prices) and companies (by reducing the
possibility of the abuse of market power by dominant companies). These benefits were the
underlying principles for the liberalization of European energy markets (Böckers et al., 2013,
p. 7). In terms of introducing competition to the electricity market, the generation, trade
(wholesale) and supply of electricity were seen as potential competitive activities, while
network activities (transmission and distribution) were regarded as activities that require
regulatory control (due to their natural monopolistic characteristics), as shown in Figure 1.
5
Figure 1. Electricity supply chain – competitive and regulated activities
Source: N. Hrovatin & J. Zorić, Reforme elektrogospodarstva v EU in Sloveniji, 2011, p. 4.
In the process of reforming a vertically integrated electricity industry into a competitive
industry, there are some general features that can be observed among countries. As explained
by Jamasb & Pollitt (2005, p. 13), four main steps usually occur:
a. Restructuring: Vertical unbundling of generation, transmission, distribution and retail
sales activities.
b. Competition and markets: Creation of a wholesale market as well as retail competition.
Allowing new entrants into generation and retail supply.
c. Regulation: Establishment of an independent regulator. Provision of third-party network
access. Incentive regulation of transmission and distribution networks.
d. Ownership: Allowing in new private actors, by privatizing existing publicly owned
businesses.
The above noted steps were promoted among EU Member States in the scope of European
reform, which was carried out at two parallel levels. First, were the EU electricity market
directives issued by the European Parliament and Council, which brought the liberalization of
national electricity markets. These were significant contributions to the creation of an internal
electricity market. Second, the European Commission encouraged the expansion of cross-
border transmission links, as well as the improvement of cross-border trading rules with the
aim of promoting efforts to improve interfaces between national markets (Karan & Kazdagli,
2011, p. 13; Jamasb & Pollitt, 2005, p. 17).
The EU’s electricity directives were part of the so-called energy packages introduced in 1996,
2003 and 2009, which included a set of regulations and directives in the area of EU energy
policy, all with the aim of creating an IEM.
6
First Electricity Directive – 1996
The legal framework that provided the initiative for the creation of the EU internal electricity
market was Directive 96/92/EC of the European Parliament and of the Council of 19
December 1996 concerning common rules for the internal market in electricity. The main
objective of the aforementioned directive was the introduction of competition on the
electricity market. It represented a set of common rules for all Member States in the areas of
generation, transmission, distribution and supply of electricity.
According to Directive 96/92/EC (OJ L 027), Member States were required to designate
transmission and distribution system operators (TSOs and DSOs) who are responsible for
operating, maintaining and developing transmission and distribution systems.
In terms of restructuring (vertical unbundling), the first directive focused on unbundling and
the transparency of accounts. This was the first step toward the gradual unbundling of
generation, transmission and distribution activities. The first directive instructed Member
States to ensure that their integrated electricity companies keep separate accounts for their
generation, transmission, distribution and supply activities within their internal accounting
records. The aim of such unbundling was to avoid discrimination, cross-subsidization and the
distortion of competition (Directive 96/92/EC, OJ L 027).
Moreover, Directive 96/92/EC facilitated competition in generation in such way that Member
States are able to choose between a tendering or authorization procedure for the construction
of new generating capacities (Directive 96/92/EC, OJ L 027). An authorization procedure
allows anyone to build a power plant, under the condition that they comply with certain
criteria such as safety of installation, environmental protection and the use of public land. A
tendering procedure allows Member States to maintain centralized planning of the power
system, while allowing them to tender out the construction of new capacities (Pellini, 2014, p.
12).
In order to enter the market and to sell and deliver electricity, new suppliers and producers
needed access to the grid. Consequently, Directive 96/92/EC presented three third-party
access models (Directive 96/92/EC, OJ L 027):
a) Negotiated third-party access (nTPA): Eligible customers and suppliers negotiate a
transmission fee (access to the system). Where eligible customers are connected to the
distribution system, access is the subject of negotiations with the relevant network
operator. To ensure transparency, indicative prices for the use of the network must be
published by the network operator.
b) Regulated third-party access (rTPA): Access rights may be granted on the basis of pre-
determined published tariffs.
c) Single-buyer model: Creation of a mandatory power pool for producers, with one entity
acting as a single buyer in the pool (e.g. a system operator may be a single buyer).
7
The concept of ‘‘eligible customer” was introduced for the first time with Directive 96/92/EC.
An eligible customer is defined as a customer who has the legal capacity to contract volumes
of electricity from any supplier. The aim of the directive was the slow, gradual and partial
opening of Member States’ electricity markets in such way that customers and producers
would be able to negotiate the purchase and sale of electricity freely. The first phase opens the
market for end-customers who consume more than 40 GWh per year. After three years, the
degree of market opening increases with a consumption threshold of 20 GWh, followed by 9
GWh after six years (Directive 96/92/EC, OJ L 02).
Although the first directive initiated changes to the electricity markets of Member States, it
also featured some serious shortcomings. In terms of market concentration, monopolies and
oligopolies were still present. Since the form of unbundling required by the directive was
weak, vertically integrated companies still presented a barrier to competition. Overall, there
was a lack of transparency and technical barriers to accessing the grid. Moreover, trading was
not fully established in all countries and balancing markets were not fully developed, while
some markets were too small or isolated. In order to ensure competitive prices and a real
internal electricity market and to increase the standards of service for customers, the Second
Electricity Directive replaced Directive 96/92/EC (Kovács, 2011).
Second Electricity Directive – 2003
Directive 2003/54/EC concerning common rules for the internal market in electricity and
repealing Directive 96/92/EC enforced the unbundling of TSOs as well as the unbundling of
DSOs, in terms of the legal separation of activities. The separation of the ownership of assets
of the transmission/distribution system operator from the vertically integrated company was
not mandatory. The criterion only referred to the legal status and functional activities of TSOs
and the management of DSOs (Directive 2003/54/EC, OJ L 176).
Directive 2003/54/EC (OJ L 176) also enforced the adoption of an authorization procedure for
all Member States for generation, as the only option. The procedure and related criteria
required publishing, while the results were to be objective and non-discriminatory.
Moreover, retail markets were opened as the result of Directive 2003/54/EC, since all non-
household customers were considered eligible from 1 July 2004, while all customers were
deemed eligible from 1 July 2007 (Meeus et al., 2005, p. 27).
In addition, Directive 2003/54/EC (OJ L 176) instructed Member States to designate a
regulatory authority to be responsible for “ensuring non-discrimination, effective competition,
efficient functioning of the market and monitoring of the market”. The aforementioned
authority is wholly independent from the interests of the electricity industry.
Since the Second Electricity Directive was not specific in terms of how to ease the
monopolistic situation on the market and how to introduce wholesale electricity markets,
several shortcomings remained to be resolved. Although almost all Member States ensured
competition in generation via a transparent authorization procedure, some issues remained
unresolved and the generated electricity was not entirely sold on the market. Access to the
grid was no longer a problem. On the other hand, there was no incentive to enter the market
8
due to the lack of competitive and liquid wholesale markets. In addition, TSOs and DSOs
were required to legally separate the functioning of their network from generation and/or
retail activities. In practice, TSOs or DSOs were still owned by a company involved in
generation or retail activities, which represented a barrier to competition. Moreover, one of
the most serious and unresolved problems was the presence of dominant companies, and the
unclear measures set out in the aforementioned directive regarding how and to what extent the
problem can be resolved. In general, it seemed that there was a lack of will among Member
States and on behalf of the Commission to reduce the market power of dominant companies
(Thomas, 2006; Jakovac, 2012, p. 321).
With the Third Energy Package, Directive 2009/72/EC came into force and updated the
previous two electricity directives with the goal of accelerating the process of creating an EU
internal electricity market.
Third Electricity Directive – 2009
According to Directive 2009/72/EC, Member States have the possibility to choose among
three alternative models of unbundling. The first model is ownership unbundling, meaning
that supply and production companies cannot hold a majority stake in a TSO, nor exercise
voting rights or appoint board members. On the other hand, supply and production companies
are allowed to choose to whom and at what price they sell their networks. The second model
allows supply and production companies to own the physical network. In such cases,
however, they are obliged to delegate any operation, maintenance and investment decision to
an independent company, i.e. an independent system operator. The third model, which
employs an independent transmission system operator, allows supply and production
companies to own the network, under the condition that it is operated by a subsidiary of the
parent company that makes decisions independently of the latter (Pellini, 2014, pp. 15-16).
The Third Directive also imposes a high standard of public service obligations on Member
States, while a high level of customer protection is promoted (DG Energy – European
Commission, 2011). Member States are also obliged to define the concept of vulnerable
customers. Therefore, the categories of consumer that will qualify as a vulnerable customer
must be specified. For example, elderly consumers with extremely low income may be
considered as vulnerable in special circumstances, such as a severe winter (when they use
electricity to heat their home). A prohibition of disconnection may apply for such customer, in
the form of licence condition or obligation (European Commission, 2010, p. 6).
Within the framework of the Third Energy Package, Regulation 713/2009/EC established the
Agency for the Cooperation of Energy Regulators (ACER). ACER plays an important role
in the process of completing the IEM. It mainly complements and coordinates the work of
national energy regulators at the EU level. ACER was also allocated additional tasks
concerning wholesale energy market integrity and transparency (REMIT), as well as
guidelines for the trans-European energy infrastructure. It plays a central role in the creation
of the IEM and the enhancement of competition. Its main tasks are the coordination of
9
regional and cross-regional initiatives that favour market integration, and monitoring the IEM
in general, as well as wholesale energy trading activities (ACER, 2014).
Moreover, Regulation 714/2009/EC established the European Network of Transmission
System Operators (ENTSO): ENTSO-E for electricity and ENTSO-G for gas. ENTSO-E’s
mission is to offer security through the coordinated, reliable and secure operation of the
interconnected electricity transmission network. Its objectives are to provide a platform for
the market and to promote sustainability by facilitating the secure integration of new
generation sources. In line with its mission, it also promotes the requisite development of the
interconnected European grid (Entsoe, 2014). The work of ENTSO-E and its network
development plans are monitored by ACER.
In addition to the work of ACER and ENTSO-E, many other EU agencies and institutions
play an important role in the creation of the EU’s IEM. The first are the Directorate-Generals
(DGs) of the European Commission, which formulate and implement European policies. The
specific DGs for energy are DG Energy and Transport (DG TREN), DG Competition and DG
Environment. The second is the Electricity Regulatory Forum (Florence Forum), a forum
where parties meet twice a year to discuss the creation of the IEM. Participants include
regulatory authorities, representatives of the governments of Member States, the European
Commission, TSOs, electricity traders, customers, network users and power exchanges. The
Council of European Energy Regulators (CEER) also contributes to the facilitation of a
single, competitive and sustainable EU IEM. CEER is a non-profit organization established in
2000 to promote cooperation between independent energy regulators in Europe (Meeus et al.,
2005, p. 27; CEER, 2014; European Commission – Energy, 2014).
Each year, ACER and CEER draft a Market Monitoring Report that assesses developments on
the electricity and gas markets, as well as progress in the implementation of the Third Energy
Package. There is still room for improvement in terms of the completion of the IEM.
With regard to retail electricity markets,2 the latest Market Monitoring Report (ACER/CEER,
2014) exposed the heterogeneity of national energy policies. This is reflected in electricity
prices that are influenced by taxation and network charges, which in most cases represent
more than one half of the bill. There are major differences across the EU concerning this
issue. Moreover, on the largest EU markets (Denmark, Finland, Germany, Italy etc.), retail
markets are moderately concentrated, and thus perform relatively well (the main performance
indicators used were choice of suppliers and offers, entry-exit activity etc.). The Market
Monitoring Report reveals that customers do not participate actively in terms of supplier
switching, and consequently do not choose among different products offered on the market.
Worthy of note with regard to market players is the need to ensure transparent and reliable
online price comparison tools, as well as transparent energy invoices. This is also one of the
key barriers to entering retail markets, as perceived by suppliers. Additional barriers to enter
the market are a lack of harmonization of regulatory frameworks among Member States, the
2 Progress on the wholesale electricity markets is described in Subchapter 1.2 (Section 1.2.1 Electricity Regional
Initiative).
10
regulation of retail prices3 and the low liquidity of wholesale markets (particularly on less
developed markets) (ACER, 2014).
1.2 Regional electricity markets in the European Union
Regionally, countries share a similar economic and political environment. It is thus normal
that common rules and methods are first created and applied within a region, followed later by
pan-European integration.
In this respect, regional electricity markets (REMs) are considered a natural step in the
evolution of national electricity markets towards a fully integrated internal electricity market.
Through REMs, barriers to trade can be removed and practical solutions can be found to
increase competition within regions (Mercados, 2010, p. 20).
1.2.1 Electricity Regional Initiative
In 2006, National Regulatory Authorities (NRAs) set up the Electricity Regional Initiative
(ERI) with the support of the European Commission. The project was intended to speed up
the integration of national energy markets in Europe, and is perceived as an interim step to
complete the IEM. Initially, Regional Initiatives were launched by European Regulators’
Group for Electricity and Gas (ERGEG), following the “bottom-up” approach. The project
brought together NRAs, the European Commission, transmission system operators (TSOs)
and other relevant stakeholders in seven electricity and three gas regions (Table 1). Regional
Initiative brought good results such as the implementation of network codes, and the
exchange of information and best practices. Nevertheless, after implementation of the Third
Energy Package (2009) and with the creation of ACER, a new approach was introduced.
ACER took over the Regional Initiatives project, and now employs a new “top-down”
regulatory approach (ACER, 2013, p. 16).
Table 1. Electricity Regional Initiative (ERI)
Source: CEER, 2014.
3 “As of 31 December 2013, household end-user price regulation existed in 15 countries (out of 29)”, as follows:
Croatia, Bulgaria, Spain, France, Hungary, Latvia, Lithuania, Poland, Slovakia, Romania, Denmark, Cyprus,
Estonia, Malta, Belgium (ACER, 2014).
Region Countries
Baltic Region Estonia, Latvia, Lithuania
Central-East (CEE) Austria, Czech Republic, Germany, Hungary, Poland, Slovakia, Slovenia
Central-South (CSE) Austria, France, Germany, Greece, Italy, Slovenia
Central-West (CWE) Belgium, France, Germany, Luxembourg, Netherlands
Northern (NE-NWE) Denmark, Finland, Germany, Norway, Poland, Sweden
South-West (SWE) France, Portugal, Spain (Spain and Portugal are also called MIBEL region)
France-UK-Ireland France, Ireland, United Kingdom
11
ACER’s project promotes cooperation and the early implementation of rules at the regional
and cross-regional level. This new approach accelerates the completion of the IEM, which
was planned by the end of 2014. It started in 2010, and the goal is for electricity markets
across Europe to share a set of common features that are linked by the efficient management
of interconnection capacities (ACER, 2014).
To that end, four Target Models have been defined for electricity market integration. All
Member States are expected to implement the below described Target Models in order to
achieve improved market integration between themselves, and to facilitate cross-border
trading in all timeframes (ACER/CEER, 2014).
First Target Model: market coupling (for the day-ahead and intraday timeframe)
Using the market coupling method, energy and capacity are allocated together, while energy
prices reflect both congestion costs and energy costs. According to this method, energy flow
is always from a low price region to a high price region (Deloitte Consulting, 2013, p. 26).
Market coupling will be used instead of the method of separate capacity allocation via explicit
auctions and energy purchases/sales via an energy exchange.
The target model for the day-ahead timeframe is the European Price Coupling (EPC) model
that simultaneously determines volumes and prices for all price zones in Europe (ACER
Coordination Group for Electricity Regional Initiatives, 2015, p. 5). The markets of Austria,
Belgium, Denmark, Estonia, Finland, France, Germany, Great Britain, Latvia, Lithuania,
Luxemburg, the Netherlands, Norway, Poland and Sweden have been coupled since February
2014. Spain and Portugal have also been using the same market coupling platform since 2014,
while the aforementioned markets have been coupled since 2010. This means that market
coupling has been implemented between the NWE, MIBEL and CSE regions (ACER, 2014a).
There are ongoing discussions between Croatian, Hungarian and Slovenian counterparties
regarding the decision on which border the coupling will be implemented first. The Croatian
Power Exchange (CROPEX) was established prior to discussions. Coupling has been in place
on the Italian-Slovenian border for a few years already. Bulgaria-Romania market coupling is
in its initial phase and is expected to go live after 2015 (ACER Coordination Group for
Electricity Regional Initiatives, 2015, pp. 5-6). The exception is the Greek market, whose
wholesale market requires restructuring in the future in order to achieve harmonization with
the rest of the region.
Second Target Model: cross-border intraday
The goal is to implement an Intraday Target Model on all borders in Europe. Implementation
is based on two phases: (i) implicit continuous intraday trading and (ii) intraday capacity
recalculation, capacity pricing and the trading of sophisticated products (ACER, 2014). The
second phase actually represents the evolution of implicit continuous intraday trading.
Implementation of the Second Target Model is first planned in the NWE region. This pilot
project is run by Ofgem (UK). Later, the model will also be implemented in other regions.
12
Currently, there are major delays with the NWE pilot project, since it was planned to go live
in 2014. Certain operational and legal challenges are causing the delay (ACER Coordination
Group for Electricity Regional Initiatives, 2014, p. 7).
Third Target Model: long-term (LT) transmission rights
The objective of this project is to offer participants an opportunity to hedge against congestion
costs and day-ahead congestion pricing. In order to achieve this objective, allocation rules, the
allocation platform and nomination procedures must be harmonized. There exists a possibility
that a shift will be made to Financial Transmission Rights (FTRs) (ACER Coordination
Group for Electricity Regional Initiatives, 2014, p. 9).
Regarding the harmonization of allocation rules, ENTSO-E has prepared a set of harmonized
auction rules (EU HAR) that will be applicable from 2016. To date, the first version has been
published and is available for public consultation. With regard to the allocation platform, the
merger of the Capacity Allocation Office (CAO) and Capacity Allocation Service Company
(CASC) is planned. CASC and CAO are two major regional allocation platforms and, once
merged, will function under a new entity called the Joint Allocation Office (JAO). It is
expected that JAO will be organising the 2016 auctions.
Fourth Target Model: capacity calculation
The final objective is to implement a fully coordinated capacity calculation methodology, in
the form of an Available Transmission Capacity (ATC) or a Flow-Based (FB) method. The
second is preferable for short-term capacity calculation (ACER, 2014).
The progress made by wholesale electricity markets is assessed in the Market Monitoring
Report (ACER/CEER, 2014). The Four Target Models are therefore included as a main
component of the final IEM. As stated in the aforementioned report, one of the indicators of
market integration is the convergence of wholesale electricity prices. For example, when
market coupling was extended from the Czech Republic and Slovakia to Hungary in 2012,
electricity prices on these three markets converged significantly. Although an increase in price
convergence was expected across all EU regions, this was not the case in 2013. The CWE
region experienced a significant decrease, of 32% compared to 2012. The underlying reason
was German prices (mostly driven by renewables and coal-fired plants), which were lower
than elsewhere in the region due to cheap coal on international markets and the penetration of
renewables. Nevertheless, the recent NWE price coupling initiative “is expected to improve
price convergence across all the regions in the coming years” (ACER/CEER, 2014, p. 14).
Another positive effect of market coupling is the efficient use of interconnectors, which
recorded an efficiency rate of 77% in 2013 in the day-ahead timeframe. Nevertheless, the full
implementation of the four electricity Target Models remains a priority. The report also
highlights the need for efficient and well-integrated gas markets in order to achieve flexibility
on electricity markets. In addition, it is reported that demand-side participation can also
contribute to the flexibility of electricity markets (ACER/CEER, 2014, p. 16).
13
1.2.2 South East Europe
The so-called 8th
region or South East Europe (SEE) region covers the Energy Community
contracting parties (Albania, Bosnia and Herzegovina, the former Yugoslav Republic of
Macedonia, Kosovo, Moldova, Montenegro, Serbia and Ukraine) as well as the seven
neighbouring EU Member States (Bulgaria, Croatia, Greece, Italy, Hungary, Romania and
Slovenia) (Energy Community, 2014). Georgia is an Energy Community candidate country,
while Turkey, Armenia and Norway have been granted the status of observer.
Historically, the countries of the SEE region have shared the same energy problems such as
small energy markets, energy intensive economies and regional energy prices below
economic levels, inappropriate pricing/tariffs and poor infrastructure, as well as energy
policies that differ significantly from the EU’s policy. These common challenges triggered the
need for regional energy cooperation (Karova, 2011, p. 81).
The creation of a regional SEE energy market was proposed in 2002 with the so-called
Athens Process that included a plan to integrate the SEE market with the EU’s IEM.
Following several memorandums of understanding, the Energy Community Treaty was
finally signed in 2005, and entered into force in 2006 with ratification by all signatories
(Karova, 2011, p. 81). This was the first ever multilateral treaty signed between the EU and
South East Europe (EU candidate and potential candidate countries), with the goal of boosting
energy integration. In addition, the Energy Community Treaty will extend the EU’s IEM to
the Balkan Peninsula as a whole. Consequently, the relevant acquis communautaire4 on
energy, the environment and competition is also planned to be implemented in this area
(European Commission, 2005).
In terms of the creation of the SEE regional market and its subsequent integration with the
EU’s IEM, a special document has been developed in line with the elements of the European
Electricity Target Model, called the Regional Action Plan for Wholesale Market Opening in
South East Europe (SEE RAP). Since implementation of the EU’s IEM was planned for 2014,
the target for the SEE region is 2015. Prior to the RAP, the Third Energy Package was
incorporated into the Energy Community back in 2011, with a transposition deadline of
January 2015 (ACER Coordination Group for Electricity Regional Initiatives, 2014, pp. 19-
20). In its reports, ACER also provides details about the progress of the SEE region. The 2014
status is presented in Table 2.
4 Acquis communautaire is a term that refers to EU laws, and includes all treaties, regulations and directives
passed by European institutions, as well as the judgements handed down by the European Court of Justice. This
term is most often used in preparations by EU candidate countries, since they must adopt and implement the
entire acquis to be able to join the EU (Eurofound, 2014).
14
Table 2. 2014 SEE region status (integration with the EU’s IEM)
Source: ACER Coordination Group for Electricity Regional Initiatives, ERI Progress Report, April 2014 –
September 2014, 2014.
As presented in Table 2, progress in the regional implementation of common practices and
rules is slow. The main characteristic of the SEE region is significant heterogeneity in its
market and regulatory framework. There are some major obstacles to creating an efficient
regional market. The SEE region’s legal basis lacks harmonization and requires
implementation. Consequently, a number of legislative provisions in some countries (related
to public supply, single-buyer models, regulated energy prices, and monopolistic positions in
electricity generation and supply) are preventing the effective opening of the market.
Moreover, additional commitment is needed from major regional players in order to achieve
further improvements (ACER Coordination Group for Electricity Regional Initiatives, 2014).
There is also a need for the development of harmonized cross-border balancing and overall
transparency.
As mentioned in Table 2, an important step forward was the establishment of the SEE CAO in
2014. The office conducted its first yearly auctions for 2015 for the Bosnia-Montenegro and
Bosnia-Croatia borders, offering 200 MW and 400 MW of available capacities (in both
directions) respectively. The SEE CAO targets the harmonization of allocation and
nomination rules for long- and short-term transmission rights in the SEE region. Coordinated
NTC-based capacity allocation is initially planned, with a subsequent switch to flow-based
capacity auctioning. The office is located in Montenegro, and the shareholders of the SEE
CAO are TSOs of Greece (IPTO), Montenegro (CGES), Croatia (HOPS), Kosovo (KOSTT),
RAP element Project - Progress and issues
Harmonization of allocation and
nomination rules for long-term
(LT) and medium-term
transmission rights.
There is a lack of regional coordinated capacity allocation
mechanisms, as well as insufficient transmission
interconnection capacity with neighbouring systems.
Nevertheless, an important step was the establishment of a
coordinated auction office, the SEE CAO, which conducts
centralized and multilaterally coordinated auctions for the
largest parts of the region.
Day-ahead (DA) capacity
allocation (market coupling)
The aim is to achieve single Price Coupling (PC), which
simultaneously determines volumes and prices in all relevant
zones (marginal pricing principle). The first step is to establish
power exchanges. Announcement of a power exchange in
Serbia by EMS and EPEX spot. Greece, Italy, Slovenia,
Romania, Croatia and Hungary have established trading hubs.
Continuous mechanisms for
implicit cross-border intraday
trading
A specific cross-border continuous intraday trading system at
all borders of the 8th region has not begun to function yet,
although it was required under the EU’s Second Energy
Package.
Capacity calculation No concrete milestones for the implementation of the flow-
based allocation have been defined to date, and no concrete
steps have been taken.
15
Bosnia and Herzegovina (NOS-BIH), Albania (OST) and Turkey (TEIAS). It was pointed out
in the recent Athens Forum that the TSOs of Bulgaria, Macedonia and Serbia should
participate, and were required to draw up concrete plans for their integration (SEE CAO,
2014; ACER Coordination Group for Electricity Regional Initiatives, p. 27).
1.3 Turkish electricity market overview and its interconnection with the
SEE region
Turkey is the 16th
largest economy in the world, with its GDP reaching $820 billion in 2013,
and would have ranked as the 6th
largest economy in the EU in 2013 had it been a member. Its
population is about 76.7 million, with an annual growth rate of 1.12%. Half of the population
is under the age of 30. Projections indicate that Turkey’s population will reach 84 million by
2023 (Invest in Turkey, 2014; TurkStat, 2014).
As shown in the graphs below (Figure 2), Turkey is a growing economy, since its GDP has
grown at an exceptional rate relative to other OECD5 countries over the last decade. The
decline in GDP in 2008 and 2009 was a result of the international financial crisis, from which
Turkey recovered in 2010 (IEA, 2009, p. 2).
Figure 2. Population of Turkey and GDP growth rates for Turkey, the Euro Area and OECD
countries
Source: OECD.Stat Extracts, 2014.
The country’s energy demand is driven by increasing GDP and population. Its main energy
policy concern is thus ensuring a sufficient energy supply. In the coming years, Turkey’s
energy consumption is expected to double due to its economic growth. In 2011, its energy
production was 32.06 Mtoe, while its energy consumption was 112.46 Mtoe. The difference
5 Organization for Economic Cooperation and Development. OECD Members: Australia, Austria, Belgium,
Canada, Chile, Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hungary, Iceland,
Ireland, Israel, Italy, Japan, Korea, Luxembourg, Mexico, Netherlands, New Zealand, Norway, Poland, Portugal,
Slovak Republic, Slovenia, Spain, Sweden, Switzerland, Turkey, United Kingdom, United States (OECD, 2014).
0
0,2
0,4
0,6
0,8
1
1,2
1,4
1,6
1,8
58
60
62
64
66
68
70
72
74
76
Population of Turkey
Population (in millions) Growth rate
-6
-4
-2
0
2
4
6
8
10
2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
GDP growth of OECD countires, Euro area and
Turkey
TurkeyEuro area (15 countries)OECD - Total
16
of 80.16 Mtoe was imported (IEA, 2009, p. 1; IEA, 2013, p. 56). The data reveal that Turkey
is dependent on imported energy, since it is limited in terms of primary energy resources.
Nevertheless, it enjoys a position as a natural bridge between the demand-rich west and
supply-rich east. Turkey’s importance on the world energy markets is growing in line with its
growth as an energy consumer (Deloitte, 2013, p. 9; IEA, 2014).
With its growing electricity demand driven by industrialization and urbanization, the Turkish
electricity market is one of the fastest growing in the world. As can be seen from Figure 3, its
electricity demand doubled over more than decade, from 128 TWh in 2000 to 246 TWh in
2013 (Deloitte, 2014, p. 5; Electricity generation & transmission statistics of Turkey for 2013,
2014). The majority of the electricity produced is distributed for industrial use (around 47%),
while the remainder goes to households (around 20%), for commercial consumption,
government consumption, illumination and other consumption needs such as the agriculture
and fishery sector (TurkStat, 2014).
Figure 3. Turkish electricity demand 1975-2013
Note: Gross demand = gross generation + import - export; net consumption = supply - network loss
Source: TurkStat, 2014.
On average, 45% of electricity is produced from natural gas, while 25% is produced from
coal. Around 20% to 25% is produced from hydro and the remaining 5% is produced from
renewable sources. Turkey does not have any nuclear energy (Electricity generation &
transmission statistics of Turkey for year 2013, 2014).
Turkey and the SEE region
As mentioned in the previous subchapter, Turkey has the status of Energy Community
observer, and has also formally expressed its interest in full membership. As an observer, it
has the right to be represented at institutional meetings and to receive any information
distributed at those meetings. Once the Energy Community Treaty is signed, Turkey agrees to
0
50000
100000
150000
200000
250000
300000
1975 1980 1990 2000 2007 2008 2009 2010 2011 2012 2013
Gross demand (GWh) Net consumption (GWh)
17
adapt EU energy standards and practices, which is also in line with its status as EU candidate
country and the related requirements (Energy Community, 2014).
Turkey is also a shareholder in the SEE CAO, and is interconnected with the SEE region via
Bulgaria and Greece. Interconnection and trading among those countries is described in
Chapter 3.2. The ENTSO-E connection6 offers Turkey new trading opportunities, while it is
widely discussed that Turkey increases the liquidity of the SEE region, since the Turkish
market is large (see Appendix C) and ENTSO-E interconnection capacities are to be 1,200
MW in the future.
Compared with the other markets of Energy Community contracting parties, Turkey’s
generation is by far the largest. In 2013, Turkey generated 240,154 GWh of electricity, while
Albania, Bosnia and Herzegovina, Macedonia, Moldova, Montenegro and Serbia produced
5,956 GWh, 16,303 GWh, 5,676 GWh, 748 GWh, 3,809 GWh, and 27,537 GWh respectively.
Markets also differ in terms of the number of end-customers. For example, Turkey has
approximately 66,505,050 end-customers, while Serbia has 3,580,579 end-customers. Since
liquidity is a key component of the wholesale electricity market, Turkey is a positive
influence for the SEE region is this respect (Appendix C).
As cross-border trading activities among Greece, Bulgaria and Turkey develop, the Turkish
electricity market will also become a role model or a benchmark for Georgia. In this way, the
Georgian electricity market can develop rapidly and its hydro potential can fully be utilized
(Deloitte Consulting, 2013. p. 23). Georgian traders will be able to access the European
electricity market and vice versa.
2 ELECTRICITY MARKET REFORM IN TURKEY
2.1 Turkish electricity market prior to reform
Prior to reform efforts, a vertically integrated company dominated the entire Turkish
electricity industry, as was the case in many other countries worldwide. The company was
called the Turkish Electricity Authority (Türkiye Elektrik Kurumu – TEK). TEK was founded
in 1970 with the main goal of unifying electricity generation, transmission, distribution and
trade under one integrated system of a state-owned enterprise (TEIAS, 2014). Subsequently in
1993, TEK was separated into two companies: the Turkish Electricity Generation Company
(TEAS) and the Turkish Electricity Distribution Company (TEDAS).
As Atiyas et al. (2012, pp. 20-21) explain, there were attempts to attract private capital to the
electricity industry in the 1980s and 1990s. In the post-World War II era, Turkey had a policy
regime that was characterized by a high level of involvement by the state in economic
activities such as the ownership of enterprises in key industries, one of them being the energy
industry. In addition, the state also played an important role in the allocation of financial
resources via state-owned banks. This regime collapsed as a result of a major balance of
payments crisis in the 1970s. The 1980s brought the liberalization of domestic markets,
6 ENTSO-E connection is the term used to refer to the Continental Europe Synchronous Area, which is an area
of interconnected markets (a TSO must be a member of ENTSO-E) that are in compliance with common
technical standards and the management of operational issues (Entsoe, 2014).
18
international trade and finance, as well as privatization being seen as a “substitute” to the
inefficient public sector. Moreover, Turkey had high public deficit in the 1990s. The Turkish
government thus wanted to attract private capital to the electricity industry to cover the high
costs of investments needed to build new electricity capacities. These new capacities were
needed due to forecasts of high growth in electricity demand.
The privatization of TEK was envisaged through different development plans over the years,
with an important attempt to privatize TEK in 1994 through the sale of ownership rights. The
privatization was blocked by the Constitutional Court due to its concerns regarding foreign
ownership in a strategic industry, and possible monopolization and cartelization. Private-
sector presence in Turkey’s electricity industry was legally enabled for the first time in 1984
under Law No. 3096. The aforementioned law introduced two types of contracts, BOT (build-
operate- transfer) contracts for new generation facilities and TOR (transfer of operating
rights) contracts for existing generation and distribution facilities. An autoproducer system
was also formed for companies to produce their own electricity. Subsequently, under Law No.
4283, a third type of contract was introduced, the BOO (build-operate-own) model (Atiyas et
al., 2012, p. 21; Cetin & Oguz, 2007, p. 1763).
BOT, TOR and BOO contracts were signed between a private company and state-owned
TEAS or TEDAS. They all included an exclusive “take or pay” obligation with fixed
quantities and prices (or price formulas) for a period of 15 to 30 years (Atiyas & Dutz, 2005,
p. 8).
The specifics of each contracts are as follows (Cetin & Oguz, 2007, p. 1763):
BOT (build-operate-transfer)
Under such a contract, concession is granted to a private company, whereby the company may
build and operate a power plant for up to 99 years (later reduced to 49 years). After this
period, it is transferred to the state at no cost. In 1994, these contracts also included treasury
guarantees and tax exemptions, making them more interesting.
TOR (transfer of operating rights)
This type of contract enables a private company to operate an already existing government-
owned facility via a lease-type agreement.
BOO (built-operate-own)
This type of contract entails the construction and operation of new thermal power plants,
introduces a licensing system rather than concession, and also provides treasury guarantees.
At the end of the contract period, the investor retains ownership of the facility.
There were several serious shortcomings related to these contracts, as some of contracts were
awarded on the basis of bids from preselected companies. There were irregularities in both the
design and implementation of the contracts. Overall, they did not contribute to the
development of competitive electricity markets, since producers did not need to compete on
the market due to the “take or pay” clause. This structural problem and dissatisfaction with
the BOT, TOR, BOO model led to the search for more competitive electricity supply models
19
(Atiyas et al., 2012, p. 23). In 2001, a more fundamental approach for introducing competition
to the market was adopted under the Electricity Market Law (EML) No. 4628. The EML was
accompanied by the Strategy Paper of 2004 (Bagdadioglu & Odzakmaz, 2009, p. 145). Both
documents will be explained in more detail in the following chapter of this thesis.
In addition, foreign influence also played an important role in the introduction of competition
to the market and the implementation of structural changes. Various international institutions
such as the International Monetary Fund (IMF), World Bank and OECD, which supported
Turkey during its economic crises, highlighted the need for energy market reform. Moreover,
reform is a precondition for Turkey’s longer-term objective of EU membership (Erdogdu,
2006, p. 986). Consequently, the EML was also drafted in line with the EU Energy Acquis.
2.2 Institutional framework
2.2.1 Electricity Market Law No. 4628
The regulatory framework that introduced competition to the Turkish electricity market is
Electricity Market Law (EML) No. 4628, published in 2001. It set out a new framework for
the organization of the Turkish electricity market, and was the first law to bring concrete
reform to the market. It was in line with the 1996 EU Electricity Directive. The main
principles and objectives of the EML are described below.
Unbundling of public assets
Through reform measures, public assets were unbundled into separate public companies.
TEAS was separated into three companies: Electricity Generation Company (EUAS) for
electricity generation, Turkish Electricity Trading and Contracting Company (TETAS) for
wholesale trade activities and Turkish Electricity Transmission Company (TEIAS) for
transmission activities (Figure 4). The assets of EUAS and TEDAS were earmarked for
privatization (Bahce & Taymaz, 2007, p. 1604; Atiyas et al., 2012, p. 24). All unbundled
companies remained publicly owned at that time.
Figure 4: Unbundling of public assets
2001 1994 1970
TEK - vertically integrated
TEDAS - Distribution
TEDAS - Distribution
TEAS - Generation,
Transmission and Trade
TEİAS - Transmission
TETAS - Trade
EUAS - Generation
20
Source: EMRA, Electricity Market Report 2010, n.d., p. 3.
Establishment of an independent regulator
The Electricity Market Regulatory Authority (EMRA) was established under the EML as an
“independent, administratively and financially autonomous public institution” as described by
the aforementioned law itself. It has its own board comprising nine members and a president,
all appointed by the Council of Ministers for a period of six years. EMRA was also given the
authority over the natural gas and oil market, and was thus renamed the Energy Market
Regulatory Authority (Atiyas et al., 2012, p. 23). Its main objectives are to ensure the
development of financially sound and transparent energy markets, to promote a competitive
environment and to deliver environmentally friendly, low-cost energy to customers. In order
to pursue its objectives and to ensure that market participants comply with the relevant rules
and regulations, EMRA supervises and imposes penalties if necessary. It also assures non-
discriminatory third-party access to grids and other monopolistic infrastructures (EMRA, n.d.,
p. 11).
EMRA also drafts secondary legislation and is responsible for the implementation of a new
transmission and distribution code. Another of its tasks is to determine the threshold level for
eligible customers over time and the protection of customers’ rights (Erdogdu, 2006, p. 987).
New wholesale market model
The market model presented under the EML comprises two elements, one being a market for
bilateral contracts and the other being a balancing mechanism, established in order to ensure
balancing between the demand side and supply side. This new model became operational in
2006, while no spot market was mentioned in the law (Atiyas et al., 2012, p. 24).
In 2004, an “Electricity Sector Reform and Strategy Paper” was released by the Turkish
government, outlining the major steps to be taken (at that time) in order to achieve
liberalization of the sector. The Strategy Paper states that the balancing and settlement
mechanism is in line with the objective of creating a spot market and includes price signals to
attract new investments. In addition, the balancing and settlement regime offers the possibility
of buying and selling the non-contracted generation (Republic of Turkey – High planning
Council, 2004, p. 5). In practice, the system functioning under this model was not transparent,
since no crucial information was published (e.g. maintenance of generation units, volume of
concluded transactions etc.). There was no spot market at that time, but only a platform that
enabled balancing between the demand side and supply side.
Licensing framework for market participants
Any legal entity wanting to engage in any electricity market activity is obliged to obtain a
license. Licenses are issued for a minimum period of 10 years and a maximum period of 49
years. There are five types of licenses (Electricity Market Law No. 4628, Official Gazette,
No. 24335):
21
a. Generation license: Each facility must obtain a generation license, except for autoproducer
groups and those entities that generate electricity only to meet their own needs and do not
operate in parallel with the transmission and distribution system. Generation companies are
also allowed to enter into an affiliate relationship7 with distribution companies, without
exercising control over them.
b. Transmission license: The license obtained by TEIAS in order to perform its transmission-
related activities. It is also pointed out that TEIAS can not engage in any other activities on
the market.
c. Distribution license: The license obtained by any legal entity that wishes to engage in
distribution activities in a specific region.
d. Retail sales license: The license obtained by legal entities in order to sell electricity and
offer retail sales services to the market. In addition, the import of electricity below the
transmission level is permitted, taking into account technical issues. Retail sales are allowed
in any region, while distribution companies that hold a retail license may only sell electricity
and capacities to an eligible customer in another distribution company’s region if their retail
license includes such a provision.
e. Autoproducer and Autoproducer Group License: The license obtained by an autoproducer
that generates electricity for its own needs.
Eligible customer concept
The EML also initiated the liberalization of the demand side. The concept of an eligible
customer was defined, while the board of EMRA determines the threshold level each year.
Customers who consume more than 9 GWh a year were designated as eligible customers free
to choose their suppliers (Atiyas & Dutz, 2004, p. 10). The threshold level was later decreased
gradually. The current status of market openness is explained in Chapter 3.4.
Although the EML brought changes to the market, amendments to the aforementioned law
were necessary in order to achieve a higher level of competition on the market. In 2008, the
EML was amended by Law No. 5784. Under the amended EML, the development of
competition is stipulated in several provisions, including a provision requiring accounting
separation for operators who hold more than one license (operators must keep different
accounts for different activities or plants). Another important provision is that the total market
share of a generating company and its affiliates cannot exceed 20% of total installed market
capacity. Moreover, holders of a distribution or transmission license are required to provide
non-discriminatory system access and the use of system rights to all natural persons and legal
entities (Atiyas et al., 2012, p. 25).
7 An affiliate relationship is a situation where one company owns less than a majority of another company’s
shares. It can also be a type of relationship where at least two companies are subsidiaries of a larger company. In
Turkey, for example, a generation company could have owned a part of a distribution company (Investopedia
dictionary - Affiliate, 2015).
22
With regard to the amended EML, the Energy Community Secretariat reported full
compliance with EU Directive 2003/54/EC in November 2008, except for cross-border
trading (EBRD, n.d., p. 165).
2.2.2. New Electricity Market Law No. 6446
In 2013, a new law regulating the Turkish electricity market was enacted: Electricity Market
Law No. 6446 (new EML). It repealed and replaced all provisions of the previous EML. The
primary objective of the new EML is the establishment of a financially robust, stable,
competitive and transparent electricity market, with an independent regulatory and auditing
mechanism. The new EML is also expected to create an environment that will attract
investments in the electricity generation sector. Another important aim is to increase private-
sector presence in the electricity sector (Karaduman & Avcisert, 2013). The main new
features in the sector are explained below.
New licensing framework
The new EML focuses more on types of electricity market activities rather than types of
licences. Article 4 of the new EML lists generation, transmission, distribution, wholesale,
retail sales, market operation, export and import as activities that require a license. In contrast
to the previous EML, it does not mention retail sales services and trade activities, and
introduces market operation as a new type of activity (Erdem & Erdem, 2013).
There is a new, preliminary license for generation required for any legal entity that plans to
commence generation activities. The aforementioned license applies to the performance of
electricity generation activities. The preliminary license is issued for a specific term, not to
exceed 24 months. During this period, a legal entity must obtain the necessary permits,
approvals and licenses, and acquire ownership of or usufruct rights relating to the land where
the facility is to be constructed or located (Erdem, 2013).
A supply license is an additional amendment to the types of licences. It combines wholesale
and retail sales activities under one license type. Holders of this license have no regional
restrictions in regards to eligible customers (Çakmak Avukatlık Bürosu, 2013, p. 1).
In summary, there are several types of licenses under the new EML: preliminary license,
generation license, supplier license, distribution license, transmission license, market
operation license, OIZ8 preliminary license, OIZ generation license and OIZ distribution
license. Currently, all market players are operating under the new license system.
Electricity market operation activities
8 OIZ – “Organized industrial zone legal entities established in accordance with Organized Industrial Zones Law
No. 4562 may engage in distribution and/or generation activities in approved areas to meet the needs of its
participants, without the obligation of incorporation according to the Turkish Commercial Code No. 6762,
provided that they obtain a license from EMRA. OIZ legal entities are deemed eligible customers regardless of
their consumption quantities. Customers exceeding the eligibility threshold have the right to choose their
suppliers, provided that they pay a distribution fee to the OIZ.” EMRA (2012).
23
Activities relating to the organization of the wholesale market and the financial settlement of
wholesale market activities are planned to be performed by the newly established Energy
Markets Operation Joint Stock Company (Enerji Piyasaları İşletme Anonim Şirketi, EPIAS),
instead of TEIAS (Ergun Benan & Burcu Tuzcu, 2014).
Competition
The new EML also aims to create a competitive environment and to prevent monopolistic
situations on the market. In this regard, three important provisions are included in the
aforementioned law and affect all license holding companies. One is that generation
companies “may not hold a total installed capacity of more than 20% of the previous year’s
calculated total installed capacity in Turkey”. Another important provision is that supply
license holders may not purchase electricity from generation or export companies that exceeds
20% of the previous year’s total consumption in Turkey. The third provision, aimed at
encouraging competition, is that supply companies may not sell electricity at the wholesale or
retail level that exceeds 20% of the previous year’s total consumption of electricity in Turkey
(Erdem, 2014).
2.3. Privatization
The reform of the Turkish electricity market is based on the privatization of distribution assets
(TEDAS), followed by the privatization of generation assets (EUAS) as a resulting step. The
privatization strategy is presented in the “Electricity Sector Reform and Privatization Strategy
Paper” (Strategy Paper) from 2004. The Privatization Administration of the Republic of
Turkey is responsible for all procedures relating to the implementation the privatization
strategy.
2.3.1 Privatization of distribution companies
The privatization of TEDAS started with the division of the Turkish electricity distribution
network into 21 regions. TEDAS then established 20 new companies (one region – Kayseri –
was already privately run), based on technical, financial and geographical factors. Each of the
21 companies was engaged in distribution and retail sales activities to end-customers, and
operated as a regional monopolist in its own region. According to the Strategy Paper, these
companies were to be privatized by no later than the end of 2006. Due to some delays in the
privatization process, additional procedures were initiated in 2008 and a new Strategy Paper
was published in 2009. Today, all regions are run by private companies (Çelen, 2013, pp.
675-676). The regions and companies established by TEDAS are shown in Table 3, together
with their privatization status. It can be noted that regions no. 18, 19 and 20 were privatized in
2009 separately from the privatization procedure of the Privatization Administration. The
remaining 18 companies were privatized via tender procedures.
Table 3. Electricity distribution regions in Turkey, distribution companies and the
privatization thereof
Region Provinces Status
24
1 Diyarbakir, Mardin, Siirt, Sanliurfa, Batman,
Sirnak (Dicle Elektrik Dağıtım A.Ş.)
Privatized by Is Kaya
2 Bitlis, Hakkari, Mus, Van (Van gölü Elektrik
Dağıtım A.Ş)
Privatized by Türkerler
Table continues
continued
Region Provinces Status
3 Agri, Erzincan, Erzurum, Kars, Bayburt,
Ardahan, Igdir (Aras Elektrik A.Ş.)
Privatized by Kiler Holding – Çalık
Enerji
4 Artvin, Giresun, Gumushane, Rize, Trabzon
(Çoruh Elektrik Dağıtım A.Ş.)
Privatized by Aksa Elektrik Perakende
Satış A.Ş
5 Bingol, Elazig, Malatya, Tunceli (Fırat Elektrik
Dağıtım A.Ş)
Privatized by Aksa Elektrik Perakende
Satış A.Ş.
6 Sivas, Tokat, Yozgat (Çamlıbel Elektrik
Dağıtım A.Ş)
Privatized by Kolin-Limak-Cengiz
7 Adana, Mersin, Osmaniye, Hatay, Gaziantep,
Kilis (Toroslar Elektrik Dağıtım A.Ş.)
Privatized by Enerjisa (Sabancı – E-
on)
8 Kirsehir, Nevsehir, Nigde, Aksaray, Konya,
Karaman (Meram Elektrik Dağıtım A.Ş.)
Privatized by Alarko-Cengiz
9 Ankara, Kirikkale, Zonguldak, Bartin, Karabuk,
Cankiri, Kastamonu (Başkent Elektrik A.Ş.)
Privatized by Enerjisa (Sabancı – E-
on)
10 Antalya, Burdur, Isparta (Akdeniz Elektrik A.Ş.) Privatized by Kolin-Limak-Cengiz
11 Izmir, Manisa (Gediz Elektrik Dağıtım A.Ş.) Privatized by Elsan-Tümaş- Karaçak
12 Balikesir, Bursa, Canakkale, Yalova (Uludağ
Elektrik Dağıtım A.Ş)
Privatized by Kolin-Limak-Cengiz
13 Edirne, Kirklareli, Tekirdag (Trakya Elektrik
Dağıtım A.Ş)
Privatized by IC Holding
14 Istanbul Ili Anadolu Yakasi (İstanbul Anadolu
Yakası Elektrik Dağıtım A.Ş)
Privatized
15 Sakarya, Bolu, Duzce, Kocaeli (Sakarya Elektrik
Dağıtım A.Ş.)
Privatized by
Akkök-Akenerji-CEZ
16 Afyon, Bilecik, Eskisehir, Kutahya, Usak
(Osmangazi Elektrik Dağıtım A.Ş.)
Privatized by Yıldızlar SSS Holding
17 Istanbul Ili Rumeli Yakasi (Boğaziçi Elektrik
Dağıtım A.Ş.)
Privatized by Kolin-Limak-Cengiz
18 Kayseri Keyseri Elektrik Dağıtım A.Ş. - the
distribution company of Kayseri region was
already partially private.
The company has held operating rights
since 1990. In 2009, the contract of
the company was renewed and a
license was granted.
19 Aydin, Denizli, Mugla (Menderes Elektrik
Dağıtım A.Ş)
Privatized under Law No. 3096
20 Adiyaman, Kahramanmaras (Göksu Elektrik
Dağıtım A.Ş)
Privatized under Law No. 3096
21 Amasya, Corum, Ordu, Samsun, Sinop
(Yeşilırmak Elektrik Dağıtım A.Ş)
Privatized by Çalık Enerji
25
Source: Republic of Turkey – High planning Council, Electricity sector reform and privatization strategy paper ,
2004; A. Çelen, The effect of merger and consolidation activities on the efficiency of electricity distribution
regions in Turkey, 2013, p. 675; Atiyas et al., Competition and Regulatory Reform in the Turkish Electricity
Industry. 2012, p.32; Deloitte Türkiye, The Energy Sector: A Quick Tour for the Investor, 2013.
The privatization of distribution companies was carried out using a TOR-backed Share Sale
model (TSS model). Following the TSS model, an investor is the sole owner of the shares of
the distribution company and is granted a license for the distribution of electricity in the
designated region. On the other hand, the investor does not hold ownership of the distribution
network; that remains with TEDAS (Lazard, pp. 1-3).
As explained by Mr Mustafa Gozen (September 2014), from EMRA, via email
communication, distribution companies were required to unbundle retail sales and generation
activities under Law No. 4628, which coincided with the privatization procedure. Distribution
companies were required to establish a separate company for retail sales activities, and to
obtain a retail sales license. Effective at the beginning of 2013, distribution utilities were
legally unbundled, meaning that distribution companies operate under a distribution license,
while retail companies perform retail activities under a supplier license. Prior to 2013,
distribution companies covered all of the above mentioned activities. Effective January 2016,
distribution companies will not be permitted to purchase administrative and support services
such as accounting or finance from the companies under the control of the main company.
They will also be required to use a different physical environment and information systems
infrastructure for their distribution and retail companies.
With regard to revenues from the privatization of distribution assets, it is estimated that total
revenue reached the primary goal of raising 10.4 billion Turkish Liras (approximately $7
billion) in order to boost investment in the industry (Invest in Turkey, 2014).
2.3.2 Privatization of generation assets
The privatization of distribution assets was given priority in the privatization process. After a
delay, all assets were finally privatized in 2013, while the privatization of generation assets
continues.
In 2008, the Privatization Administration (PA) grouped larger power plants into nine
portfolios that comprised three thermal portfolios, four hydro portfolios and two mixed
portfolios. Although the plan was to sell assets by portfolios, the PA shifted from a portfolio
model to the tendering of large-scale thermal power plants separately with the aim of
maximizing value and avoiding the risk of tenders being cancelled (as was the case with
motorways and bridges because bids were too low). According to the new model, the Kangal
(457 MW), Kemerköy (630 MW), Yeniköy (420 MW) and Çatalağzı (300 MW) thermal
plants, in addition to the Hamitabat (1,156 MW) and Seyitömer (600 MW) plants, were
tendered separately, as presented in Table 4. Thermal power plants are the priority for the PA
in the privatization process (Durakoğlu, 2014; EUAS, 2015).
26
Table 4. Privatization of major thermal power plants 2013-2014
Source: Republic of Turkey Prime Ministry – Privatization Administration, 2014; Today's Zaman – Business,
2015; Invest in Turkey – The Republic of Turkey prime ministry investment support and promotion agency, 2014.
In addition to the above successful privatization procedures, three thermal power plants were
privatized in 2015. Konya Seker privatized the 990 MW Soma thermal power plant with a bid
of $685.5 million. In addition, Celikler Taahhut privatized the 210 MW Orhaneli and 365
MW Tuncbilek thermal power plants with a bid of $ 521 million (Konya Seker also bid for
these two plants, but the highest bidder was Celikler Taahhut) (Equities.com, 2015).
Many other smaller plants (all hydroelectric or so-called “run-of-river” power plants) have
also been privatized. In 2008, nine power plants with a total installed capacity of 141 MW
were privatized. Later in 2010, 18 portfolios with a total installed capacity of 140 MW were
also tendered. However, only 10 portfolios were actually privatized, while other tenders were
cancelled. Those were tendered again in 2012 and all were successfully privatized. The most
recent successful privatization of hydroelectric power plants was completed in 2014. This
include five hydroelectric power plants: Esendal, Isıklar (Visera), Kayaköy, Dere and İvriz.
All were privatized under the TOR model for a period of 49 years (Republic of Turkey Prime
Ministry – Privatization Administration, 2014).
Power plant Privatization process and new owners Value
Kangal (457 MW) Privatized by Konya Seker (local sugar producer that offered $985
million for privatization) via the “asset sale” method. Privatization
was completed in August 2013.
$985
million
Kemerköy
(630MW) and
Yeniköy (420
MW)
The movable properties of the plant will be privatized via the
“asset sale” method, while the immovable properties used by the
Kemerköy and Yeniköy thermal power plants and the immovable
properties used by YLİ were privatized via the same method. The
procedures were completed in December 2014. The plant operates
as a subsidiary of ICTAS Energy Generation and Trade Inc.
$4.3
billion
Çatalağzı (300
MW)
Privatized by Çates Elektrik Üretim A.Ş. via the “asset sale”
method. Privatization was completed in December 2014.
$351
million
Hamitabat (1,156
MW)
Privatized by Limak Doğalgaz Elektrik Üretim A.Ş. via a block
sale in the form of the sale of 100% of shares. Agreements were
signed in August 2013.
$105
million
Seyitömer (600
MW)
Privatized by Elektrik Üretim A.Ş. via the “asset sale” method,
while mine fields were privatized using the TOR model.
Agreements were signed in June 2013.
$2.24
billion
27
Through past successful privatization procedures, the market share of EUAS has been
gradually reduced, from 57% in 2006 to 37% in 2013 (Figure 5), and continues to decline.
The private sector is expected to hold a higher market share in the future.
Figure 5. Proportion of Turkey’s total installed capacity accounted for by EUAS 2006-2013
Source: Electricity generation & transmission statistics of Turkey for year 2013, 2014.
3 TURKISH ELECTRICITY MARKET ANALYSIS
3.1 Generation
There are five types of market players on the Turkish electricity generation market (Ergun
Benan & Burcu Tuzcu, 2014):
1. State-owned EUAS with its subsidiaries and affiliated partnerships.
2. Build-operate-transfer (BOT) and build-operate-own (BOO) companies. These companies
operate under a concession (BOT) or license (BOO) agreement signed between the state
and a private company. They do not require a generation license, since their operations are
based on agreements with the Ministry of Energy and Natural Resources (MENR) and
public authorities.
3. Companies operating under a transfer-of-operating-rights (TOR) agreement. The
generation utility is owned by the state and operated by a private entity.
4. Independent power producers (private entities).
5. Autoproducers.
0%
10%
20%
30%
40%
50%
60%
2006 2007 2008 2009 2010 2011 2012 2013
EUAS AFFILIATED PARTNERSHIPS OF EÜAŞ
PRODUCTION COMP. AUTOPRODUCERS+TOOR
28
As Table 5 illustrates, around 37% of installed capacity in Turkey is owned by EUAS or its
affiliated partnerships and subsidiaries. The remaining 63% of installed capacity is managed
(and in some cases owned) by private companies. From a management point of view, the
sector is dominated by private companies. However, when BOT and TOR agreements are
taken into account (i.e. the state is or will be the owner of these utilities), the state is a major
player on the generation market in terms of ownership.
Table 5. Distribution of installed capacity by primary energy resources and market share of
electric utilities in Turkey, 2013
Source: Electricity generation & transmission statistics of Turkey for year 2013, 2014.
According to MENR (2014), BOO, BOT and TOR contracts enjoyed market shares of 9.5%,
3.6% and 1.5% respectively in 2013. Most of the capacities added to the system in 2013 were
built by the private sector. In total, this is 6,985 MW of installed capacity, comprising 86
hydro power plants, 29 thermal plants, 11 wind plants, 10 landfill gas and biogas plants and
four geothermal plants (MENR, 2014). Turkey is therefore promoting a higher private sector
presence and is making an effort to reduce the market share of EUAS.
Currently, a large proportion (44%) of electricity consumed in Turkey is generated from
natural gas power plants, followed by coal (27%) and hydropower (25%) electricity
generation. A smaller proportion (4%) is generated from renewable energy sources such as
wind and geothermal energy (see Figure 7). Turkey is planning to make specific changes in its
UTILITIES
PRIMARY ENERGY RESOURCES
(MW)
EUAS AFFILIATED
PARTNERSHIPS
OF EUAS
AUTOPRODUCERS
& PRODUCTION
COMPANIES (BOO,
BOT included) &
TOR
TOTAL
(MW)
COAL: HARD COAL + IMPORTED COAL + ASPHALTITE 300 4,083 4,383
COAL: LIGNITE 3,690 2,714 1,819 8,223
LIQUID FUELS: FUEL OIL + DIESEL OIL + LPG +
NAPHTHA
50 566 616
LIQUID FUELS: NATURAL GAS 1,432 15,739 17,171
RENEWABLES AND WASTES 0 235 235
TOTAL SINGLE FUEL-FIRED 5,472 2,714 22,442 30,628
SOLID + LIQUID 367 367
NATURAL GAS + LIQUID 2,676 4,731 7,407
NATURAL GAS + LIQUID + SOLID 245 245
TOTAL MULTI FUEL-FIRED 2,676 0 5,343 8,019
THERMO TOTAL (SINGLE FUEL-FIRED + MULTI FUEL-
FIRED)
8,149 2,714 27,785 38,648
HYDRO TOTAL 12,918 9,371 22,289
GEOTHERMAL TOTAL 311 311
WIND TOTAL 2,760 2,760
GENERAL TOTAL (MW) 21,067 2,714 40,227 64,008
ELECTRIC UTILITY MARKET SHARE (%) 32.9 4.2 62.9 100
29
electricity generation mix by 2023. The country is aiming to increase the proportion of total
energy sources accounted for by renewable energy sources from 20% to 30% by 2023 (Baris
& Kucukali, 2012, p. 390). It is also aiming to make two nuclear power plants operational
over the long term, although Turkey currently does not have any nuclear power plants. Two
major planned projects are the Akkuyu nuclear power plant project (4,800 MW planned
installed capacity) and the Sinop power plant project (4,480 MW planned installed capacity).
The target is to produce 5% of electricity from nuclear energy by 2020 (MENR, 2014). The
primary goal is to reduce the country’s dependency on imports.
Figure 6. Electricity generation in Turkey by primary resources, 2013 in percentages
Source: Electricity generation & transmission statistics of Turkey for year 2013, 2014.
A well-functioning generation segment of the electricity market, which complies with EU
legislation, is essential for the whole electricity industry, since it represents the basic
component of the final retail and wholesale price. Current arrangements of the Turkish
electricity generation market are presented by the type of energy source below.
3.1.1 Natural gas
As presented in Figure 6, the majority of electricity in Turkey is produced from natural gas.
This link between the two markets affects electricity prices (as presented in the Chapter 4.2).
It is therefore necessary to present an overview of natural gas market dynamics and to
understand the functioning of the market.
Prior to reform in 2001, the Turkish natural gas market was dominated by the vertically
integrated, state-owned BOTAS. The company built natural gas pipelines and related
facilities, signed long-term natural gas sale and purchase agreements, and also purchased
natural gas on foreign spot markets. At that time, distribution companies (state and privately
owned) were able to distribute gas, but were unable to import gas from another supplier by
bypassing BOTAS. Consequently, the main driver of reform was the introduction of
competition on the wholesale market (Atiyas et al., 2012, p. 65).
[CATEGORY
NAME]
26.6
[CATEGORY NAME]
43.8
[CATEGORY NAME]
1.20
[CATEGORY
NAME]
24.70
[CATEGORY NAME]
0.60
[CATEGORY NAME]
3.10
30
In 2001, Natural Gas Market Law No. 4646 entered into force with the aim of restructuring
the market from a monopolistic structure to a liberalized market with competitive elements.
Although the aforementioned law required the state-owned BOTAS to reduce its market share
in the import, wholesale and distribution segments, it continues to remain a dominant market
player (IEA, 2013b, p. 14; EMRA, 2012, p. 8). The current market structure is presented in
Figure 7.
Figure 7. Turkish natural gas market structure
Source: Deloitte Türkiye, The Energy Sector: A Quick Tour for the Investor 2013, 2013, p. 42.
Turkey’s domestic production contributes only 2% to total natural gas consumption. The
country therefore imports the remaining 98% of natural gas, meaning it is completely
dependent on natural gas imports. Its natural gas and LNG import partners are Russia, Iran,
Azerbaijan, Algeria and Nigeria. As shown in Table 6, Turkey’s first international agreement
was signed with Russia, which led to the construction of the first main natural gas
transmission line, extending from the Bulgarian border to Ankara (Melikoglu, 2013, p. 394;
Natural Gas Europe, 2014). Russia is also the largest natural gas contract partner of Turkey,
since more than 55% of total Turkish natural gas consumption is imported from Russia.
Table 6. Natural gas and LNG sale and purchase agreements (BOTAS)
Original contract volumes/maximum
capacity
Consumption estimates and costs
for 2013 – major natural gas
contracts
Exploration, production and
import Transmission Storage Wholesale
Distribution and retail
Private sector NG
import companies
BOTAS – trade
Private sector LNG
import companies
Eligible
customers
BOTAS –
balancing and
gas for own use
NG distribution
companies
Private sector
wholesale
companies
Storage
companies
Local
production
31
Agreement Volume (bcm/year) Date of
signature/end date
Consumption (bcm) –
as % of total natural
gas consumption
Cost ($
billion) – as
% of import
costs
Algeria (LNG) 4.4 1988/October 2024 - -
Nigeria (LNG) 1.3 1995/October 2021 - -
Iran 9.6 1996/July 2026 8.568 bcm – 18% $4.88 billion
– 21.2%
Table continues
Continued
Agreement Volume (bcm/year) Date of
signature/end date
Consumption (bcm) –
as % of total natural
gas consumption
Cost ($
billion) – as
% of import
costs
Russian Fed. (Black
Sea) – “Blue
Stream”
16 (1986 – first
agreement)
1997/end of 2025
27.132 bcm – 57% $11.02
billion –
47.9%
Russian Fed.
(western line)
14 (4 by BOTAS,
10 transferred to
private sector)
1998/end of 2021
Azerbaijan (Phase –
I)
6.6 2001/April 2021 4.284 bcm – 9% $1.63 billion
– 7.1%
Azerbaijan (Phase –
II)
6 2011/start in
2017/2018, until
2032/2033
- -
Domestic natural
gas
- - 0.952 bcm – 2% n/a
SPOT LNG - - 6.664 bcm – 14% $5.47 billion
– 23.8%
Source: Botas, 2014; Natural Gas Europe, 2014.
As evident from Table 7, Iranian gas is the most expensive for Turkey, and represents a
source of tension between the two countries. Turkey buys gas from Iran at a price of
$507/tcm. This price was agreed after an arbitration procedure in 2009 that was concluded in
favour of BOTAS. The procedure covered retrospective price revision in the framework of a
discount rate determined by the International Court of Arbitration.9 Turkey was also awarded
$800 million in compensation relating to natural gas purchases from Iran. Moreover, BOTAS
filed a request in 2012 for the cessation of gas imports from Iran due to low gas quality, while
arbitration procedures are in progress at the ICC, since Turkey wants to lower the Iranian
price (Oxford, 2014, p. 29).
Table 7. Natural gas prices for Turkey 2012–2013 (for BOTAS)
9 The court is a branch of the International Chamber of Commerce (ICC).
Agreement Price in 2012, $/tcm Price in 2013, $/tcm (Discount in 2013)
32
Source: G. Rzayeva, Natural Gas in the Turkish Domestic Energy Market: Policies and Challenges 2014, p. 29;
Table adopted from ZAMAN.
In addition, Turkey buys Russian gas at a discount rate, since Russia applied discounts to its
European customers in 2013. Nevertheless, the cheapest natural gas is imported from
Azerbaijan, at a price of $349/tcm (Table 7).
All gas contracts are characterized by a “take or pay” obligation, meaning that Turkey is
obliged to take a minimum pre-specified proportion of the contracted volume each year, or it
pays for the gas even if not taken (Rzayeva, 2014, p. 22).10
As reported by the “Natural Gas
Europe” organization (Natural Gas Europe, 2014), Turkey will abandon this obligation for
Azerbaijani gas in the coming year, and for Iranian gas in the coming months. It has also been
reported that Turkey abandoned similar clauses for gas supplies from Russia in 2013.
The above described import dependency is leading to concerns about meeting seasonally
volatile gas demand, with an absence of sufficient underground storage capacity. In addition,
supplier or transit countries could curtail agreed volumes for economic or political reasons (as
was the case in 2006, when Ukraine and Iran cut gas exports to Turkey, and in January 2007
and 2008, when Iran reduced the supply of gas twice). When such gas supply interruptions
occur, there is a risk of power shortages due to the interdependence of the natural gas and
electricity markets. This can be mitigated by the construction of new storage facilities and the
diversification of sources (Atiyas et al., 2012, p. 66).
Import dependency is crucial for understanding the Turkish natural gas market and its
connection to the electricity market. Nevertheless, other segments of the natural gas market
are also important in order to understand the market fully, as explained below (IEA, 2013b,
pp. 14-17, Rzayeva, 2014, p. 32; Atiyas et al., 2012; EMRA, 2012, p. 34; PwC Turkey, 2014,
p. 8):
BOTAS market share: Under the law passed in 2001, BOTAS is obliged to gradually
transfer its import contracts with the aim of reducing its market share to 20% of annual
consumption. Consequently, a small portion of natural gas imports from Russia was
transferred to seven private companies (in total 10 bcm).11
Nevertheless, BOTAS
currently holds an 80% market share, while the remaining 20% is in the hands of private
companies. It is a widely accepted view that it is unrealistic to expect the market share of
BOTAS to be reduced to 20%. The amended law from 2013 proposes a reduction to 50%,
while there is no specified deadline for BOTAS.
10
Gas not taken may, however, be taken in a make-up period of 4-5 years. 11
Enerco Enerji (2.5 bcm), Bosphorus Gaz (0.75 bcm; additional 1.75 mcm in 2012 tender), Avrasya Gaz (0.5
bcm), Shell Enerji (0.25 bcm), Akfel (2.25 mcm, Kibar Enerji (1 mcm), Bati Hatti (1 mcm).
Iran 530 507 (4.34%)
Russia (Western Line) 446 429 (3.81%)
Russia (Blue Stream) 445 428 (3.82%)
Azerbaijan 354 349 (1.41%)
33
LNG imports: There are two LNG terminals in Turkey (used for storage, gasification and
transmission). One is the Marmara Ereglisi LNG Terminal, owned and operated by
BOTAS (in operation since 1994 under agreement with Algeria). The second is the Ege
Gaz A.Ş. LNG Terminal at Aliaga (in operation since 2006 and operated by the private
company Ege Gaz).
Storage: The country has approximately 3 bcm of storage capacity, which is planned to be
increased due to the increasing demand for gas.
Wholesale market: There are 42 wholesale companies in Turkey that are not allowed to
engage in transmission and distribution activities. Their sales quantities are limited to less
than 20% of projected consumption, while they are also required to maintain storage
capacities.
Retail market: There are 63 distribution companies that are obliged to purchase natural
gas from at least two different sources.
Eligible customers: The threshold level is set to zero for all household customers, except
for those who consume less than 100 tcm a year. Inner-city distribution companies have
an eligible customer limit of 15 mcm per year for the first five years of operations (since
they charge a higher distribution fee to non-eligible customers). Ankara’s recently
privatized, Baskent Gaz inner-city distribution network enjoys a special eligible customer
limit of 800 tcm until August 2017.
Pricing (BOTAS): In 2008, BOTAS was included in a cost-based pricing mechanism that
applies to state-owned enterprises. BOTAS was able to set its wholesale prices for
distribution companies and for eligible customers, and was therefore required to publish
its tariffs on a monthly basis (reflecting import prices and TL/USD parity). Later, BOTAS
was exempted from the mechanism, and began charging subsidized prices to distribution
companies and eligible customers, while power plants under BOO and TOR contracts
remained unsubsidized.
Pricing (wholesale companies): Wholesale prices are freely negotiated between the buyer
and seller. Nevertheless, BOTAS’ tariff is used as a benchmark in the pricing process.
Such a market situation illustrated that BOTAS’ pricing policy caused a distortion of
competition, and has also affected its financial position.
3.1.2 Coal
In 2013, installed power plant capacity dependent on coal was 12,606 MW, equivalent to 20%
of total installed capacity. Capacity using hard coal and imported coal was 4,383 MW, while
capacity using lignite was 8,223 MW (Table 5). The only location in Turkey where hard coal
is extracted is the Zonguldak basin (Figure 8). Hard coal resources in the basin are estimated
at some 1,314 million tonnes. Although there are no legal restrictions on private sector
involvement, the state-owned Turkish Hard Coal Enterprise (TTK) has a de facto monopoly
in the production, processing and distribution of hard coal (EUROCOAL, 2015).
34
Figure 8. Lignite and hard coal rich regions in Turkey
Source: EUROCOAL, 2015.
Turkey mainly produces lignite, which is its most important indigenous energy resource.
Turkey’s lignite fields are spread across all regions of the country, with approximately 46% of
reserves being located in the Afsin-Elbistan basin (EUROCOAL, 2015; MENR, 2014).
Domestically produced lignite accounts for approximately 75% of the country’s coal supply
(Figure 9).
Figure 9. Production, consumption and import of coal in Turkey, 2005-2012
Source: U.S. Energy Information Administration, International Energy Outlook 2013 with projections to 2040,
2014.
3.1.3 Hydroelectric power
Turkey’s hydroelectric power sources are the most important among its renewable energy
potentials. According to MENR, total economic hydroelectric power potential in Turkey is
140 billion kWh/year, while currently 35% of that potential is utilized. In 2013, total installed
hydroelectric power capacity was 22,289 MW (Table 5), with a total of 467 hydroelectric
power plants (HEPPs). In the same year, 25% of total electricity production was generated
from hydro sources (Figure 6).
Most of the country’s economically feasible hydroelectric power potential is distributed to 14
river basins. The most important is the Euphrates River, which accounts for 30% of county’s
0
20000
40000
60000
80000
100000
120000
2005 2006 2007 2008 2009 2010 2011 2012
Th
ou
san
d S
ho
rt
To
ns Consumption
Production
Import
35
hydroelectric power potential and is where Turkey’s largest HEPPs were constructed: Ataturk
(power of 2,400 MW), Karakaya (power of 1,800 MW) and Keban (power of 1,330 MW).
There is also considerable potential in the Black Sea region, where 20% of total projects in
Turkey were developed by the private sector (Baris & Kucukali, 2012, p. 381).
In the future, an increase in the number of HEPPs would contribute to reducing Turkey’s
dependence on foreign sources of energy. Nevertheless, Turkey also faces a challenging
problem in this area, i.e. maximizing the utilization of hydroelectric power while maintaining
environmental consciousness and sustainable development. The EML (2001) provided for the
planning and construction of small HEPPs by the private sector. Consequently, this created a
market for companies that draft feasibility reports, for construction companies and for the
owners/managers of small HEPPs. Their inadequate water resource management strategies
led to the disruption of the natural flows of rivers, since their aim was to generate electricity,
with little heed paid to components of the ecosystem and the needs of local residents (Kentel
& Alp, 2013, p. 34). In 2008, a regulation was issued concerning HEPPs with installed
capacity of between 0.5 and 25 MW. The regulation instructs such HEPPs to draw up an
Environmental Impact Assessment (EIA) report if they want to obtain a small HEPP license.
Nevertheless, this regulation did not have the intended effect, since many of the licenses for
small HEPP were granted prior the entry into force of the regulation (Baris & Kucukali, 2012,
p. 382).
Despite the challenges, installed hydroelectric power capacities have developed over the last
decade. In 2006, installed hydroelectric power capacity totalled 13.1 GW, while that number
reached 22.3 GW in 2013. Turkey’s long-term target is to have 180 GW of installed
hydroelectric power capacity by 2030 (Figure 13).
3.1.4 Renewables
As already mentioned above, Turkey is heavily dependent on expensive imported energy, in
terms of electricity generation, mainly in the form of natural gas and high-quality coal. Its
main domestic energy resources are coal (lignite) and hydroelectric power.
Turkey’s advantageous geographical location provides for the possible use of several
renewable energy sources. The first major source is hydroelectric power, which was presented
in the previous subchapter. The other potential renewable energy sources are solar, thermal,
wind, geothermal and photovoltaic energy (Yuksel, 2013, p. 1038). In terms of renewable
energy sources, 25% of electricity is currently generated from hydropower (59,421 GWh), 1%
from geothermal sources (1,364 GWh) and 3% from wind (7,557 GWh), while the remainder
(71%) is produced from fossil fuels (Figure 5).
In addition to dependency on imports of fossil fuels, which affects the country’s current
account deficit and price stability, air pollution also gives rise to severe environmental issues
in Turkey as the result of increasing energy consumption. Turkey is addressing these issues in
parallel with the need to comply with the Kyoto protocol and EU Directives (Bölük, 2013, p.
153).
36
The main instruments that promote renewable energy use in the EU are purchase guarantees
by feed-in-tariffs, quota applications and energy tax exemptions. Meanwhile, in Turkey, the
first instrument was the EML, which allows individuals and small corporate entities to build
electricity generation facilities with a maximum installed capacity of 500 KW from renewable
energy sources that are exempt from licensing obligations (Baris & Kucukali, 2012, p. 385).
With the new EML, maximum installed capacity has been raised to 1 MW, while the Council
of Ministers is authorized to increase that level to 5 MW. The second instrument was the Law
on the Utilization of Renewable Energy Sources for Electricity Generation (No. 5346, Official
Gazette, No. 25819). Under the aforementioned law, several mechanisms were developed in
Turkey to support the use of renewable sources (Baris & Kucukali, 2012, p. 386; Atiyas et al.,
2012, p. 120):
a) Licensing: In addition to a license exemption for a maximum of 1 MW of installed
capacities (from renewable sources) for those who do require a license, only 1% of the
licensing cost is paid by the applying entity, which is exempt from annual licensing costs
for the first eight years.
b) Land appropriation: Real properties that are deemed forest or the private property of the
Treasury receive the right of easement, usage permits or are leased. Moreover, an 85%
discount is applied to rent, the right of easement and usage permits, while several costs are
not charged for the first ten years.
c) Purchase guarantees: Government guarantees to buy electricity offering a feed-in-tariff of
5-5.5 €c/kWh for utilities that are less than 10 years old.
Law No. 5346 was amended in 2010 by the Law Amending the Law on the Utilization of
Renewable Energy Sources for Electricity Generation (No. 6094). One major change related
to feed-in-tariffs, which were deemed very low. Although much higher feed-in-tariffs were
proposed in 2009, the following were confirmed in the framework of Law No. 6094. The new
tariffs are applicable to plants built or to be built between 18 May 2005 and 31 December
2015, offering an amount of 5.6 €c/kWh for hydropower and wind, 8 €c/kWh for geothermal,
and 10.2 €c/kWh for solar and biomass power plants. Moreover, the domestic manufacturing
of equipment used is promoted via feed-in-tariffs ranging from 0.3 to 2.7 €c/kWh (Atiyas et
al., 2012, pp. 113-123).
A comparison of Turkey’s feed-in-tariffs and those of selected EU Member States is shown in
Appendix D. As discussed by Baris & Kucukali (2012, p. 385), Turkey’s mechanisms are
deemed to be inadequate compared with leading EU countries in the utilization of renewable
energy sources. On the other hand, taking into account the opinion of Atiyas (et al., 2012, p.
123) with regard to the difficulties faced by Spain, Germany and Italy, which are considered
the highest feed-in-tariffs countries since the financial crisis of 2008, Turkish tariffs may
actually be reasonable in terms of long-term stability.
The current utilization of renewable sources in Turkey is analysed below.
Wind energy
Data show that 2,760 MW of wind capacity was installed in Turkey in 2013 (Table 5).
Installed wind capacity is expected to grow at a rate of between 500 and 1,000 MW per year
37
to reach more than 5 GW by 2015, while the country’s goal is to install up to 20 GW by 2023.
For this ambitious target to be reached, the transmission structure will have to be upgraded in
the future in order to allow such large scale development to be connected to the power grid
(Toklu, 2013, p. 462).
According to MENR (2014), wind energy potential in Turkey is estimated to be 48,000 MW.
Plants with a capacity of 5 MW can be built in Turkey in areas with a wind speed exceeding
7.5 m/s. Also, as noted in Figure 11, the country is aiming to achieve 40 GW of installed wind
capacity by 2030.
Geothermal energy
With its location on the Alpine-Himalayan belt, Turkey has a high geothermal potential. It has
been estimated that 2,000 MW of electricity can potentially be generated via geothermal
energy. Current data indicate a total of 706.4 MW of potential capacities for which licenses
were obtained from EMRA. Nevertheless, current installed capacity is 404.9 MW, generated
by 15 geothermal power plants (MENR, 2014).
Other potential renewable sources
Turkey is suitable for the use of solar energy, with gross solar potential calculated at 117 GW
per year, 40% of which can be used economically (Toklu, 2013, p. 461). There are currently
some small-scale photovoltaic solar energy systems in the country that were established
primarily for research purposes. MENR is planning to install 3,000 MW of photovoltaic
power plants in 2023 in several stages. Licenses for 600 MW will be issued in the first phase,
followed by an increase in capacity to reach the 2023 target (MENR, 2014).
Bioenergy potential, which covers biodiesel, bioethanol, biogas and biomass, is also
important for Turkey. Biomass has an annual potential of 42 GW, while 10 GW was actually
produced from biomass in 2010. A projection for 2030 indicates that the aforementioned
number will increase to 11 GW (Baris & Kucukali, 2012, p. 384).
38
2006 2007 2008 2009 2010 2011 2012 2013
THERMAL 27.4 27.3 27.6 29.3 32.3 33.9 35.0 38.6
HYDRO 13.1 13.4 13.8 14.6 15.8 17.1 19.6 22.3
GEOTHERMAL 0.1 0.2 0.0 0.1 0.1 0.1 0.2 0.3
WIND 0.0 0.0 0.4 0.8 1.3 1.7 2.3 2.8
0.0
5.0
10.0
15.0
20.0
25.0
30.0
35.0
40.0
45.0
Insta
lled
ca
pa
cit
y (
GW
)
2030 Renewables Target (GW)Hydropower: 180.0Wind energy : 40.0Geothermal: 4.2Solar energy : 10.0Biomass : 2.2
Figure 10. Turkey’s installed renewable capacity and thermal capacity 2006-2013
Source: Electricity generation & transmission statistics of Turkey for year 2013; I. Yuksel, Renewable energy
status of electricity generation and future prospect hydropower in Turkey 2013, 2013, p. 1040.
3.2 Transmission
Transmission activities are performed by the state-owned TEIAS, which has a complete
monopoly over this segment of the electricity market due to the natural monopolistic
characteristics of the transmission infrastructure. TEIAS works under a transmission license
and is responsible for all transmission facilities in the country. It also plans load dispatch and
operational services (TEIAS, 2014). As stated in the 2013 TEIAS statistical report (2013),
Turkey has 51,344 km of transmission lines with several projects in progress. The current
lengths of the transmission lines at 380 kV (also referred to as 400 kV), 220 kV, 154 kV and
66 kV voltages are 16,808 km, 84.5 km, 33,942.5 km and 509.4 km respectively (Appendix
E).
Turkey is currently interconnected with Greece, Bulgaria, Georgia, Iran, Iraq and Syria. One
of the most important interconnections for the country in terms of commercial exchange is the
ENTSO-E connection with Greece and Bulgaria. There are two 400 kV transmission lines on
the Turkey-Bulgaria interconnection (one 145 km long and the other 136 km long), while
there is a 130 km long 400 kV transmission line on the Greece-Turkey interconnection
(Figure 11).
Figure 11. Turkey’s interconnection with neighbouring countries
BULGARIA
145 km 400kV
136 km 400kV
GEORGIA
28 km 220kV (Hopa-Batumi)
160 km 400kV (Borcka-Akhaltsikhe)
39
Source: F. Kölmek, Turkish Power Balancing Market 2014; 2014; Deloitte Consulting, Turkey import and
export expectations – project report 2, 2013.
Following several stand-alone operational tests, the Turkish system was synchronously
connected to Continental Europe in September 2010. A test of the parallel synchronous
interconnection was subsequently planned. However, due to technical problems within the
Turkish network, trial operations were extended in order to achieve satisfactory compliance
with Continental European rules by TEIAS. In June 2011, limited commercial exchanges
were successfully performed on the interconnection. Moreover, the capacity available for
trade has been gradually increasing, and is currently 550 MW for imports to Turkey and 412
MW for exports from Turkey (Staschus, 2014, p. 41). The long-term plan is to reach 1,200
MW on the both the import and export side, as well as a permanent synchronous connection
with Continental Europe.
The first commercial exchange with Greece and Bulgaria in 2011 resulted in two changes in
overall Turkish cross-border electricity exchange activities. The first was an increase in total
electricity imports from 2,288 GWh in 2010 to 9,112 GWh in 2011 (an increase of 300%),
and an increase in electricity exports from 3,635 GWh in 2010 to 7,289 GWh in 2011.
Secondly, Turkey became a net electricity importer, while it was a net electricity exporter
prior to the ENTSO-E connection. In 2013, imports reached 14,858 GWh, with 64% of
electricity imported from Greece and Bulgaria. On the other side, exports during the same
year were much lower than in 2011 or 2012, reaching 2,453 GWh, with 64% of electricity
exported to Continental Europe (Figure 12).
TURKEY
SYRIA
124 km 400kV
GREECE
130 km 400kV IRAQ
NACHIVAN-AZERBAIJAN
87 km 154kV
IRAN
73 km 154kV
100 km 400kV
ARMENIA
80.7 km 154kV
412 MW
550 MW
15-80 MW
0 MW
40 MW
40 MW
150 MW
380 MW
400 kV Existing
400 kV Under construction
220 kV Existing
154 kV Existing
700 MW
40
Figure 12. Total electricity imports and exports by Turkey 2003-2013
Source: Electricity generation & transmission statistics of Turkey for year 2013, 2013.
The available transmission capacity (ATC) on both borders is allocated via the explicit
auction method. Market participants can submit their bids for capacity via an auction platform
and, if the volume of offered capacity is higher than the volume of required capacity, the
auction price is €0/MWh. In the opposite case, when congestion occurs, capacity is payable.
Capacity auctions are conducted by each country’s TSO. A total of 50% of interconnection
capacity is auctioned by TEIAS, 32.5% by the Bulgarian TSO (ESO) and 17.5% by the Greek
TSO (HTSO) (Deloitte Consulting, 2013, p. 12).
Another important interconnection is Georgia-Turkey. Turkey is interested in increasing
electricity trade with Georgia, particularly because of Georgia’s rich renewable energy
sources, and also because of the Turkey’s increasing electricity demand (Deloitte Consulting,
2014, p. 2). Interconnection comprises two lines: the first is the Hopa (Turkey)-Batumi
(Georgia), 28 km-long 220 kV transmission line. The second is the Borcka (Turkey)-
Akhaltsikhe (Georgia) 400 kV transmission line, which is 160 km long (Figure 12). There is
no possibility of synchronous parallel operation between the two countries on this
interconnection, since Georgia is not an ENTSO-E member. Two different methods are
currently applied on the Hopa-Batumi line (Deloitte Consulting, 2013, p. 18, Electricity
Market Import and Export Regulation, Official Gazette, No. 29003):
a) Directed unit method: Operation of a generation facility or a unit of a generation facility
in the electricity system of the country that electricity is to be imported from/exported to,
0
2000
4000
6000
8000
10000
12000
14000
16000
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
GW
h
Imports Exports
41
in parallel with the national electricity system. No capacity was allocated under this
method in 2014.
b) Isolated region method: An isolated region is formed in the country that electricity is to be
exported to via interconnection lines. In October 2013, EMRA amended the license issued
to the private company that holds the right to export on this line. However, the company
declared it will start exporting after May 2015. On the other hand, TETAS cannot export
energy at present, since its energy trade agreement has not yet been renewed.
For the Borcka (Turkey)-Akhaltsikhe (Georgia) line, the asynchronous parallel operation
method will apply. The interconnection has been constructed and tests completed. There was
610 MW of capacity available for electricity transmission in December 2014. As a rule
between the countries, the exporting country determines to whom the ATC will be allocated,
in this case Georgia as it is in the position of exporter. (Deloitte Consulting, 2014). Georgia
does not have a day-ahead electricity market and no auction platform. Auctions for the ATC
are therefore oral.
With regard to other neighbouring countries, the Iran-Turkey line (600 MW) back-to-back
station is expected to be completed by 2016. In addition, reinforcement of the Iraq-Turkey
interconnection line continues, while trade is currently possible via the isolated region
method. There is no trade on the Syria-Turkey border.
3.3 Wholesale market
The Turkish electricity market is still in the process of restructuring. Consequently, its current
wholesale market structure has not yet shifted to the final phase. Nevertheless, the final
market structure proposed under electricity regulations is in line with the EU Internal Energy
Market. Figure 13 illustrates the current wholesale electricity market structure in Turkey. It
can be noted that the market is based on a bilateral contracts market complemented by a
balancing mechanism. An analysis of each segment of the wholesale market will be presented
in the following subchapters (Deloitte Consulting, 2012, p. 8).
As a tradable commodity, electricity is unusual in that it cannot be easily stored. The
maximum capacity of all electricity-producing plants in a region determines the maximum
supply of electricity in that region at a given moment. For a certain region (the so-called
control area), demand and supply are first matched. Any excess power may then be sold to
other control areas. This excess power constitutes the wholesale electricity market (Hull,
2009, p. 584). Electricity can be traded either physically or financially. Physical trading refers
to a situation when the electricity traded is actually produced and delivered, while the purpose
of financial trading is to hedge against price volatility (physical delivery does not occur)
(Verdugo Penados, 2008, p. 14). In Turkey, most electricity trade is physical, while the
financial markets are expected to develop additionaly with novelties in the market, which are
explained in Subchapter 3.3.6.
Figure 13. Current structure of the wholesale electricity market
42
Bilateral contract Balancing mechanism
More than 1 year 1 year
Source: Deloitte Consulting, Turkish electricity market review, 2012, pp. 9-10.
3.3.1 Bilateral contracts and the role of TETAS
The majority of Turkish electricity contracts in place are between a generation company or a
wholesale company and a distribution12
company or an end-customer (bilateral energy sales
contracts). Bilateral contracts are not standardized. European Federation of Energy Traders
(EFET) standard contracts are therefore not commonly used. Consequently, the form and
terms are subject to negotiations between parties, and EMRA has no supervisory power over
these contracts. On the other hand, in contrast to private sector wholesale companies, all
public contracts of TETAS are subject to EMRA’s approval (Ergün & Gökmen, 2013, p. 17).
Figure 15 illustrates the bilateral contracts system of Turkey, and its energy flow.
Specifically, three types of bilateral contracts exist on the market (Deloitte Consulting, 2012,
p. 10; TETAS, 2013, pp. 20-22):
a) Long-term contracts between BOO/BOT/TOR and TETAS. These private sector power
plants have contracts with TETAS, starting from 1989, and are valid for a period of
between 15 and 30 years.
b) Transition period contracts (TPCs) between EUAS, TETAS and distribution companies.
The energy flow goes from EUAS to TETAS, and the electricity is delivered to the non-
eligible customers of 20 distribution companies. Currently, they operate separately on the
market; distribution activities are performed under a distribution license, while retail
activities are performed under a supply license (Figure 14). In 2006, an agreement was
12
Before unbundling, distribution companies also performed retail activities on the market. Since 2013,
distribution companies operate under a distribution license (they maintain the distribution network), while
electricity is sold to customers by retail companies under a supply license.
Plant
investment
Fuel
agreement
Maintenance
plan
Fuel supply
Supply and demand
planning
Operating
reserves
planning
Day-ahead
balancing and
optimization
Bilateral contracts and financial
markets Day-ahead market Balancing power
market
Ancillary services
1 day-ahead 15-1 minutes 8-6 hours
Real
time
Bilateral: Contracts between
BOO/BOT/TOR plants and TETAS,
and freely negotiated contracts
between market participants and
between market participants and
eligible customers.
Financial markets: Borsa Istanbul
Operated by market
operator (PMUM,
department within
TEIAS); hourly
settlement.
Operated by transmission system operator (MYTM,
department within TEIAS).
43
made (a transition period contract) under which TETAS purchased 20-23 billion kWh of
electricity from EUAS on an annual basis. The agreement was valid until the end of 2012.
However, in 2013, new agreements were concluded, and 68,614,230,100 kWh of
electricity energy was purchased from EUAS by TETAS.
c) Freely negotiated contracts between market participants and eligible customers.
Figure 14. Bilateral contracts electricity market and energy flow
Source: Deloitte Consulting, Turkish electricity market review, 2012, p. 11.
State-owned TETAS plays an important role in the wholesale trading system as it was
established in the scope of electricity market reform to carry out wholesale trading and
contracting activities. TETAS therefore purchases electricity from EUAS, BO/BOT/TOR
plants, other countries (based on import contracts) and the balancing market. It sells energy to
electricity distribution companies, electricity retail sales companies, customers connected to
the transmission system, other countries (under export contracts) and the balancing market
(TETAS, 2013, p. 16).
Generation
Transmission Wholesale Distribution Retail
EUAS HEPP
BOO/BOT/TOR
EUAS
PORTFOLIOS
TETAS
TRANSMISSION
CONNECTED
ELIGIBLE
CUSTOMERS
KAYSERI distrib.
company
TEDAS/ NON-
ELIGIBLE
CUSTOMERS (20
distrib. companies)
EXPORT/IMPORT
PRIVATE
PRODUCERS
PRIVATE
WHOLESALE
COMPANIES
ELIGIBLE
CUSTOMERS
EXPORT/IMPORT
Transition contracts
Long-term agreements
Bilateral contracts
44
2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013
ELECTRICITY PURCHASED FROM
PRODUCTION COMPANIES82 81 80 80 69 47 44 43 41 36 35 55
IMPORT OF ELECTRICITY 100 100 100 100 100 100 100 100 81 9 5 4
EXPORT OF ELECTRICITY 100 68 33 23 25 50 14 21 33 0.5 0.9 0.01
SALES OF ELECTRICITY 77 77 78 78 68 46 43 43 41 35 34 53
0
20
40
60
80
100
120
Sh
are
of
TE
TA
S
Market share of TETAS 2002-2013
Table 8. TETAS trading portfolio in 2013 (purchase)
Source: TETAS, 2013 Annual Activity Report, 2013, p. 33.
In is evident from the TETAS trading portfolio in 2013 (Table 8) that 98% of electricity
purchased in 2013 by TETAS was based on either TPCs or BOO/BOT/TOR contracts.
According to a TETAS report (2013, p. 33), a major portion of purchased electricity was sold
to retail or distribution companies, while a smaller portion was sold either directly to eligible
customers, on the market (PMUM) or was exported.
Figure 15. Market share of TETAS 2002-2013, in percentages
Source: TETAS, 2013 Annual Activity Report, 2013, p. 34.
Since TETAS was expected to help the Turkish electricity market to transition smoothly to a
competitive structure, the company retained around 75% of national electricity trade between
2002 and 2006. Despite the enforcement of transition period contracts in 2006, its market
share had declined to 35% by 2012 (Karahan in Toptas, 2013, p. 617). In 2013, its market
share of national electricity trade exceeded 50%, probably due to additional contracts with
Electricity purchased from Quantity (GWh) Percentage
EUAS 68,614 52.3
BOO 42,939 32.8
BOT 13,293 10.1
TOR 3,715 2.8
PMUM (MFSC) 2,242 1.8
IMPORT 227 0.2
TOTAL 131,079 100
45
EUAS. In terms of international electricity trade, its market share has fallen significantly due
to reform efforts and also due to the possibility given to all the market participants to obtain
cross-border transmission capacities. Moreover, only 4% of electricity imports were carried
out by TETAS in 2013 and 0% of exports. The remainder of international trade is carried out
by wholesale traders. It is expected that TETAS will operate with lower market shares in the
sector in the coming years (Figure 15).
The majority of the Turkish wholesale electricity market comprises bilateral contracts. As
seen in Figure 16, bilateral contracts accounted for 75% of market volume on a selected date
in October 2014. A total of 21% of the electricity was traded on the organized day-ahead
market, while a small proportion (4%) was traded via the balancing market. The public and
private sectors accounted for 67% and 33% of the bilateral contracts market respectively.
Figure 16. Proportion of the Turkish wholesale electricity market accounted for by bilateral
contracts, and bilateral contracts by sector (on 9 October 2014), in percentages
Source: PMUM – General Reports, 2014.
Figure 17 shows the increasing proportion of private bilateral contracts on the market in the
period 2011 to 2014. On the other hand, public bilateral contracts dominate the market, with
the number of public bilateral contracts in 2014 exceeding the number in 2011. It is a fact that
public-sector presence is high on the market, where TETAS plays an important role.
Figure 17. Private and bilateral contracts
0,00
5.000.000,00
10.000.000,00
15.000.000,00
20.000.000,00
dec
.11
feb.1
2
apr.
12
jun
.12
avg.1
2
okt.
12
dec
.12
feb.1
3
apr.
13
jun
.13
avg.1
3
okt.
13
dec
.13
feb.1
4
apr.
14
jun
.14
avg.1
4
Public B.C.
Private
B.C.
46
Source: PMUM – General Reports, 2014.
3.3.2 Derivatives
Electricity can also be traded financially with the aim of hedging against price volatility. In
such cases, physical delivery does not occur. Derivatives traded via the organized market in
Turkey are referred to as future power contracts or “base load electricity futures”.
Power futures have been traded on the Turkish Derivatives Exchange (TurkDex) since trading
started on 26 September 2011. In 2013, trading was transferred to the Borsa Istanbul Futures
and Options Market. Power futures represent a small proportion of the total market volume. In
2012, for example, the total traded volume of all contracts on the TurkDex was 62 million,
with a total value of $200 billion. In the same year, electricity futures recorded a volume of
928 contacts or 0.0015% of total traded volume (Borsa Istanbul, 2013). The value of those
928 contracts was $9.5 million.
Figure 18. Volume and value of base load electricity futures (2011–2013)
Source: Borsa Istanbul, Borsa Istanbul and the Energy Market, 2013, p. 13.
The reference price for base load electricity futures is the average of the day-ahead hourly
prices of the maturity month obtained from TEIAS (Borsa Istanbul – Base load electricity
futures, 2015). In practice, these contracts do not attract much interest. It seems that investors
believe that prices on the day-ahead market do not reflect the real supply-demand balance.
The main reason is the large proportion of state-owned utilities in power generation, and the
fact that natural gas market prices are regulated (Bademli, 2013). The low volumes of
electricity futures can be seen in Figure 18.
Developed markets, such as Germany with one of the leading energy exchanges in Europe
(EEX), have much higher trading volumes for comparable products. At least 200 electricity
futures contracts are traded in a single day on the EEX (EEX, 2014).
3.3.3 Day-ahead market
47
The Turkish day-ahead electricity market began functioning on 1 December 2011. It is “an
organized wholesale electricity market for the purchase and sale of electricity to be delivered
in the day-ahead timeframe on the basis of a settlement period” (hourly) (Camdan & Kolmek,
2013, p. 63). The day-ahead market is operated by the market operator, Electricity Market
Financial Settlement Centre – MFSC (Piyasa Mali Uzlas¸ tırma Merkezi – PMUM). MFSC is
a part of the state-owned TEIAS (a department within TEIAS). The law laying down
principles and procedures on the day-ahead market is the Electricity Market Balancing and
Settlement Regulation drafted by EMRA.
Daily bids and offers are submitted to the market on a portfolio basis. Participants submit
their price-volume pairs, with the responsibility to balance their whole portfolio. Both the
supply and demand sides may compete on the market, with producers on one side and
wholesale or retail companies on the other (Deloitte Consulting, 2012, p. 12).
Participants may submit their offers/bids in three different ways (Electricity Market Balancing
and Settlement Regulation, 2009, pp. 33-34; Deloitte Consulting, 2012, p. 15):
a) Single hour purchase or sales
Market participants submit a bid (price-quantity pair) for each hour of the following day
(maximum of 32 different price levels for each purchase and sale). Bid quantities are
submitted in lots representing 0,1 MW and its folds, while the minimum price limit is “0
TL/MWh” and the maximum limit is “2,000 TL/MWh”.
b) Block purchase
The term “block” refers to a constant purchase/sales volume, in terms of hourly MWh, that a
market participant is willing to buy/sell for a certain time interval. Market participants are
able to offer their customized block bids/offers or to bid/offer a predefined period of time
determined by the system operator. The blocks span at least four hours, and participants are
allowed to submit at least 50 block bids/offers in a day. For example, a trader may submit a
bid covering the hours 2 am to 8 am (block) to purchase 100 MWh at a price of 100
TL/MWh.
c) Flexible sales
These are single hour sales bids that are not associated with a certain hour, and differ from
single hour purchase and sales bids. Flexible sales are used by producers, since they allow
them to utilize their flexible generation capacity (for example hydro power plants). Bids and
offers are submitted in such a way that the technical aspect of the plant is considered, as well
as marginal costs for the portfolio. A producer may submit an offer when it is economical to
generate at that price, or it may submit a bid when it is more economical to purchase from the
market (instead of generating itself). For example, a producer has three power plants in a
portfolio with a total capacity 130 MW, and signed bilateral contracts for 80 MW (Table 9).
Table 9. Generation company X’s portfolio
Capacity Marginal Cost (TL/MWh)
48
Source: Deloitte Consulting, Turkish electricity market review, 2012, p. 15.
Considering its marginal costs, it is economical for it to generate the 80 MW when the price
on the market is higher than 60 TL/MWh. On the other hand, when the price is 0 TL/MWh, it
is more economical to buy the 80 MW on the market. Table 10 shows its bids/offers on the
market, which are flexible according to the producer’s portfolio.
Table 10. Example of flexible sales/bids of generation company X
Note: 1 MW = 10 LOT
Source: Deloitte Consulting, Turkish electricity market review, 2012, p. 15.
As Table 10 shows, generation company X may sell 50 MW when the price is higher than 90
TL/MWh. It produces the contracted 80 MW at a lower price, and then it uses its remaining
capacity to sell it on the market, since its marginal costs are lower than the market price.
3.3.4 Balancing market
The balancing market is operated by the system operator, the National Load Dispatch Centre
– NLDC (Milli Yük Tevzi Merkezi, MYTM). NLDC is a part of state-owned TEIAS (a
department within TEIAS).
The balancing market is needed to maintain physical supply and demand equilibrium.
Although the system is theoretically in balance after the day-ahead market is closed, market
participants may produce below or above their daily accepted bids/offers for different reasons,
leading to imbalances in real time. However, in such cases, flexible producers who can load
or reload the system on short notice to balance the system are able to submit their bids/offers
through a transparent market application, the so-called balancing market (Deloitte Consulting,
2012, p. 19).
Market participants who are able to participate on the market are those who are regarded as
balancing entities, meaning that they can independently load or reload the system with 15
minutes’ notice. Such entities are gas-fired plants and hydro storage plants, since they have
the requisite generation flexibility. Unfortunately, producers who use renewable sources do
not have the flexibility required, but are still required to participate on the balancing market,
via their finalized daily generation schedules, instead of submitting bids/offers (Deloitte
Consulting, 2012, p. 19).
Power plant 1-60 MW 60
Power plant 2-40 MW 80
Power plant 3-30 MW 90
TOTAL : 130 MW *Signed contract with its customer for six months (for 80 MW)
Price
(TL/MWh)
0 40 60 70 80 90 100 110
Participant
(LOT)
800 800 200 200 0 -500 -500 -500
49
3.3.5 Price determination and market data
The price on the day-ahead market is determined at the intersection of supply and demand.
For each trading hour, a supply curve is formulated from a combination of price-quantity
pairs that are listed in ascending order and combined into one offer. The demand curve is
formulated in the same manner, but the pairs are listed in descending order. The intersection
of the supply-demand curves determines the price of the relevant hour, the so-called market
clearing price (MCP) (Figure 19 – left).
Figure 19. Price determination on the day-ahead market (left) and balancing market (right)
Source: F. Kölmek, Turkish Power Balancing Market, 2014; Deloitte Consulting, Turkish electricity market
review, 2012, p. 17.
The price of the balancing market depends on whether there is an energy deficit or energy
surplus in the system. First, all offers/bids submitted to the balancing market are ranked
according to their prices. If there is an energy deficit in the system, the maximum accepted
hourly offer price in the system is accepted as the system marginal price (SMP). This situation
where a balancing entity sells energy to the system is called up-regulation. On the other hand,
when there is a surplus, the minimum accepted bid price is accepted as the SMP. The situation
where an entity buys energy from the system in order to correct an imbalance is referred to as
down-regulation (Electricity Market Balancing and Settlement Regulation, 2009, pp. 6-7).
Figure 19 (right) gives an example where there was an energy deficit in the system, and the
SMP was higher than the MCP for the relevant hour after up-regulation instructions.
The wholesale electricity price is influenced by several factors, since electricity cannot be
stored and is always produced at the exact moment of demand. Supply and demand drivers
therefore have an immediate impact on spot prices. Consequently, the electricity price
formulated for the following day is subject to many fluctuations. The main factors affecting
the supply side are fuel prices (for coal, gas and oil) and the prices for CO2 allowances. For
power plants using renewable sources, wind and weather are very important as they determine
the quantity of generated electricity. In addition, on the supply side, the capacities of power
plants, their current technical condition and planned or unplanned outages have an effect on
the price. Weather also plays an important rule on the demand side. Customer behaviour is
0
40
80
120
160
200
-30 10 50 90 130 170 210 250
TL
/MW
h
MW
Day-ahead market
Demand Supply
60 MW
MCP = 90 TL/MWh
0
20
40
60
80
100
120
-30 20 70 120 170 220
TL
/MW
h
MW
Balancing market
Supply Demand
120 MW
SMP= 95 TL/MWh
50
directly influenced by the temperature and cloud cover. Other demand side price drivers are
major public or school holidays. Another important factor is the global economy. For
example, demand fell due to the economic crisis, resulting in a drop in electricity prices
(RWE – Press and News, 2015).
Based on all relevant findings regarding the Turkish electricity market, the main electricity
wholesale price drivers in Turkey are as follows:
High generation costs: A large proportion of electricity is produced from natural gas. The
supply of natural gas is tied to expensive import contracts. In addition, the BOTAS pricing
system distorted competition on the market, since there is no competitive pricing on the
natural gas market.
High electricity demand driven by industrialization and urbanization.
Weather: Demand is higher in the summer due to hot weather and the usage of cooling
devices. A similar situation occurs during the cold winter months, when the usage of
heating devices increases.
Islamic holidays: The most important holiday is Kurban Bayram. Electricity consumption
is expected to be very low on this day, resulting in low wholesale prices.
Political influence: The high market share of state-owned companies distorts competition.
High system losses, especially distribution losses (explained in Subchapter 3.4.).
Figure 20 illustrates the development of the Turkish wholesale electricity market price. Peaks
are noted during the coldest winter months or on the hottest summer days, probably due to the
increased demand arising from increased usage of heating or cooling devices. Turkey’s
average prices are higher than those of the CEE region. For example, the average CEE
wholesale price in February 2012 was €62/MWh compared with €73/MWh in Turkey. Later,
in June 2013, CEE prices fluctuated at around €30/MWh, which is much lower than in Turkey
where the price was €55/MWh (Figure 22). According to EC quarterly reports (DG Energy –
Market Observatory for Energy, 2013), the CEE region is the most dynamic power trading
region in Europe. The reason for its low prices in 2013 lies in the limited industrial demand
for electricity, which was impacted by the sluggish economic recovery, decreasing generation
costs (cheap coal imports and low carbon prices) and abundant renewable supply in Germany.
Figure 20. Turkish wholesale electricity market price
51
Source: PMUM – General Reports, 2014.
On the other hand, if we compare Turkish prices to the SEE region, more specifically to
Greek electricity prices, some similarities are seen in the dynamics of the price curve,
although the peaks in 2012 are higher and prices were lower in Greece in 2013. In April 2013,
electricity production and consumption were close to their lowest levels in decades in Greece
due to the economic situation and weather conditions in that country (DG Energy – Market
Observatory for Energy, 2013).
Figure 21. Wholesale electricity market prices of the EU REM (Q2 2013)
Source: DG Energy – Market Observatory for Energy, Quarterly Report on European Electricity Markets,
second quarter 2013, 2014, p. 10.
3.3.6 Expected future market developments
52
The new EML stimulates and accelerates the process of establishing a competitive and fully
liberalized market. There are several market changes and developments expected in the near
future.
The wholesale market will be operated by three market operators, namely the newly
established EPIAS (which holds a market operation license), which will cover the day-ahead
and intra-day markets, while the Borsa Istanbul will be responsible for standardized electricity
contracts and derivatives markets. The balancing power market and ancillary services market
will continue to be operated by TEIAS. Moreover, spot transactions and derivatives will be
under one exchange (Boden Law Company, 2013, p. 2). In addition, EPIAS will cover
financial settlement obligations for the markets operated by TEIAS and EPIAS.
EPIAS was established as a joint-stock company at the beginning of 2015, with total capital
of 61,572,779 Turkish liras (approximately €21 million). A total of 30% of shares were
bought by TEIAS (Type-A shares) and BOTAS equally, while 30% of shares were bought by
the Istanbul Stock Exchange (Type-B shares). The remaining 40% of shares (Type-C shares)
were bought by private energy companies. The main agreements are currently being signed.
Following the registration of shares, EPIAS will be able to start with its first transactions
(Herdem, 2015).
Table 11 shows the difference between the old and new market structure.
Table 11. Comparison of the current and new wholesale electricity market structure
Source: Own
Market Current structure New EML structure
Wholesale market organization Hybrid: bilateral contracts,
day-ahead and balancing
market covered by TEIAS
(MFSC; NLDC); derivatives on
Borsa Istanbul.
EPIAS covering day-ahead
(including bilateral contracts)
and intraday exchange, TEIAS
covering balancing market and
Borsa Istanbul operating the
derivatives market. Clearing
house is Taksabank.
Market operators TEIAS (MFSC and NLDC),
Borsa Istanbul.
EPIAS, TEIAS and Borsa
Istanbul.
OTC markets Not defined by the EML,
energy transactions under
bilateral contracts.
Also not defined by the new
EML.
Licensing Generation, transmission, retail
sales, distribution,
autoproducer and autoproducer
group license.
Preliminary license, generation
license, supply license, market
operation license, autoproducer
license.
53
Although the new EML brings positive changes for the organized wholesale market, OTC
markets have been left out. The aforementioned law excludes OTC markets from the
definition of wholesale markets. Electricity trading is recognized based on bilateral contracts,
as it was under the 2001 EML (Boden Law, 2013, p. 2). Moreover, all contracts relating to the
organized wholesale markets are exempt from the stamp tax duty. Because OTC markets are
not defined by the EML, they cannot benefit from that exemption (Bademli, 2013).
In addition to the aforementioned changes and updates expected in the near future, there has
already been some progress in terms of market transparency. The current platform used for
day-ahead and balancing market bids (operated by TEIAS – NLDC and MFSC) has been
upgraded. In the past, it was possible to enter bids and see the prices of the day-ahead and
balancing market, while the platform is now more transparent and offers information about:
daily reports, Outage and Maintenance Notification Reports, Congestion Cost Reports and
Market Development Reports (number of eligible customers, types of licenses and number of
market players etc.). With such information available, analysts and traders have the
opportunity to evaluate the forecasted market price better, and to understand the functioning
of the overall market (PMUM – General Reports, 2014).
3.4 Distribution and retail markets
The distribution and retail markets were explained to some extent in Chapter 2.3. To
summarize, distribution and retail activities were legally unbundled in 2013. There are 21
distribution regions in the country, while each region has its own distribution company that
was initially publicly owned and later privatized using a TOR model. There are currently 21
private distribution companies operating under distribution licenses. Nevertheless, TEDAS is
the sole owner of distribution assets. The same companies are also entitled to perform retail
activities under a separate license. The market is also open to any private company that
obtains a supply license to sell electricity to eligible customers. On the other hand,
wholesalers are also allowed to sell electricity to eligible customers.
The Turkish retail market is not yet fully liberalized. The eligible customer threshold level
was gradually decreased from its initial level of 9 GWh/year to 4,500 kWh/year in 2014. Full
opening of the market is expected by the end of 2015 (Deloitte, 2013, p. 30, Enerjisa, 2015).
The data for October 2014 shows that the number of eligible customers in Turkey exceeded
one million (Figure 22), meaning that the degree of market opening is currently 85%.
Figure 22. Retail market opening in Turkey
54
Source: PMUM – General Reports, 2014.
With the gradual opening of the market and increased cross-border trading with Continental
Europe, we can see an increase in the number of registered private-sector retail and wholesale
market participants. There are currently 42 private companies operating on the retail market
under supply licenses, and 152 companies operating on the wholesale market, likewise under
supply licenses. In terms of distribution, 21 privatized companies are operating the
distribution network under distribution licenses (PMUM – General reports, 2014).
Expectations from privately run distribution companies include a reduction in system losses
and an improvement in reliability. Turkey incurs high system losses (technical and illegal
use). According to TEIAS data, distribution losses have been historically high, from 6.9% in
1984 to the highest level of 16.8% recorded in 2000. A 13.3% distribution loss was recorded
in 2013, higher than the 12.7% loss in 2011 and 2012. In addition, transmission losses
average 2.5%, meaning that total system losses (distribution and transmission) account for an
average of 16.5% of total consumed electricity. Power outages are also common in Turkey
and affect economic activity. Interruptions are most common in eastern and south-eastern
Anatolia. With regard to illegal use, households that report no expenditure are located in
provinces with high network losses (Atiyas et al., 2012, p. 6, p. 55; Electricity generation &
transmission statistics of Turkey for year 2013).
Tariffs and prices
As stated in the Electricity Market Tariffs Regulation, transmission and distribution activities
on the market, as well as the sale of electricity or capacity or the provision of retail services to
non-eligible customers are regulated by EMRA through tariffs. There are six types of
regulated tariffs as follows (Electricity Market Tariffs Regulation, Official Gazette, No.
25929, p. 4; Atiyas et al., 2012, p. 27):
1. Transmission connection tariff: The tariff is drawn up and proposed by TEIAS.
0
200.000
400.000
600.000
800.000
1.000.000
1.200.000
12/2
00
9
02/2
01
0
04/2
01
0
06/2
01
0
08/2
01
0
10/2
01
0
12/2
01
0
02/2
01
1
04/2
01
1
06/2
01
1
08/2
01
1
10/2
01
1
12/2
01
1
02/2
01
2
04/2
01
2
06/2
01
2
08/2
01
2
10/2
01
2
12/2
01
2
02/2
01
3
04/2
01
3
06/2
01
3
08/2
01
3
10/2
01
3
12/2
01
3
02/2
01
4
04/2
01
4
06/2
01
4
08/2
01
4
10/2
01
4
October 2014:
1,056,185 eligible
customers in Turkey
55
2. Distribution connection tariff: The tariff is drawn up and proposed by a licensed
distribution company. Distribution and transmission connection tariffs are both intended
to cover costs incurred when users connect to the grid. Moreover, users of the distribution
system are subject to a standard connection charge (depending on connection capacity and
distance).
3. Transmission tariff: The tariff is drawn up by TEIAS and includes three additional
components. The first is the “use of transmission” price, which covers the investment,
operation and maintenance of the network. It is calculated separately for each region, and
separately for customers and producers. The second is the “transmission system
operation” price, which covers the costs of operating the NLDC and ancillary services
(uniform prices across all regions). The third component is the “market management”
price, which covers and reflects the costs of operating the MFSC. All of the components
are regulated using a revenue cap method.
4. Distribution tariff: The tariff is drawn up by licensed distribution companies and includes
the use of a distribution system price. It is subject to a hybrid revenue and price cap.
5. Retail tariff: The tariff is drawn up by supply license holders for the sale of electricity
and/or capacity to non-eligible customers, and includes retail prices and service prices.
The retail sales price reflects the average cost of energy purchased by retail companies
plus a gross profit margin cap. The retail service price covers the costs associated with the
provision of retail services, and is regulated via a revenue cap. The retail tariff also
includes an average loss and theft price cap. It is quite problematic in terms of the model
due to the different loss ratios between regions.
6. Wholesale tariff of TETAS: This tariff is intended to cover the average cost of wholesale
electricity bought by TETAS and to ensure the financial viability of TETAS.
All of the above listed tariffs must be approved by EMRA. Retail tariffs only apply to non-
eligible customers and to those eligible customers who haven’t chosen their own suppliers yet
via bilateral contracts. All tariffs for bilateral contracts at the retail level are determined freely
(Atiyas et al., 2012, p. 26). This also means that retail prices for eligible customers are
determined freely.
With regard to tariffs drawn up by distribution license holders, the so-called “transitional
price equalization mechanism” is applied in order to protect customers against price
differences that may arise due to cost differences between distribution areas. The transitional
period for the price equalization mechanism has been extended until the end of 2015 (Ergun
Benan & Burcu Tuzcu, 2014).
In addition to the tariffs described above that are determined freely (eligible customers) or
that are regulated (non-eligible customers), the final retail price also includes taxes. Value-
added tax (VAT) accounts for 18% of the consumption bill, and is calculated on the basis of
consumed quantity of electricity. Other taxes specific for the sale and consumption of
electricity include an electricity consumption tax (at rates of 1% and 5%, depending on the
type or purpose of electricity consumption) and the Turkish Radio and Television Corporation
(TRT) tax (tax is calculated on the consumed quantity of electricity at a rate of 2%)
(Eurelectric, 2012, p. 69).
56
In 2014, the European Commission published its “Energy prices and costs in Europe” report,
in which primarily data for 2012 are analysed. The report covers EU Member States, Turkey
and other selected countries. The report shows that the final price paid by electricity
customers in Turkey was €0.147/kWh. The price includes the cost of energy, network costs
and taxes. Energy represents 56% of the final price or €0.083/kWh. This part of the price is
negotiated freely for eligible customers, while this tariff is approved by EMRA for non-
eligible customers. The total amount of network-related costs was €0.034/kWh or 23% of the
total retail price. The remaining 20%, or €0.03/kWh, is accounted for by taxes (European
Commission, 2014a, p. 183).
The data for 2013 show that the average retail price (excluding taxes) for household
customers in Turkey was €0.1186/kWh, which is slightly above the EU 28 average. The price
falls in the range of prices of Portugal, Greece, Poland and the Czech Republic (Figure 23). In
addition, the average retail price (excluding taxes) for industrial customers was €0.0891/kWh
in the same year. Turkey is below the EU 28 average, and falls in the range of the prices of
Poland and Denmark (Figure 24).
Figure 23. Retail prices for household customers in Turkey and EU countries (2013)
Note: Average national price in €/KWh, excluding taxes, applicable for the first semester of the year for
medium-sized household customers.
Source: Eurostat – Energy price statistics, 2014.
Figure 24. Retail prices for industrial customers in Turkey and EU countries (2013)
0
0,05
0,1
0,15
0,2
0,25
Irel
and
Sp
ain
Un
ited
Kin
gd
om
Bel
giu
m
Ital
y
Ger
man
y
Lu
xem
bou
rg
Au
stri
a
Slo
vak
ia
No
rway
EU
(28
co
un
trie
s)
Sw
eden
Net
her
lan
ds
Den
mar
k
Cze
ch R
epu
bli
c
Po
rtu
gal
Tu
rkey
Slo
ven
ia
Gre
ece
Po
lan
d
Lit
hu
ania
Fin
lan
d
Cro
atia
Hu
ngar
y
Fra
nce
Est
on
ia
Lat
via
Rom
ania
Mo
nte
neg
ro
Icel
and
Bulg
aria
€/k
Wh
Turkey: €0.1186/kWh
EU 28: €0.137/kWh
57
Note: Average national price in €/kWh, excluding taxes, applicable for the first semester of the year for medium-
size industrial customers.
Source: Eurostat – Energy price statistics, 2014.
Figure 25 illustrates prices for industrial and household customers between 2010 and 2014.
Figure 25. Retail prices for industrial and household customers in Turkey (2010–2014)
Note: Average national price in €/kWh, excluding taxes and levies, for medium-sized industrial and household
customers. The average price of two published Eurostat estimates is calculated for a selected year.
Source: Eurostat – Energy price statistics, 2014.
0,0874
0,0745
0,0876 0,084
0,07495
0,10795
0,09485
0,11065 0,11195
0,09975
0
0,02
0,04
0,06
0,08
0,1
0,12
2010 2011 2012 2013 2014
€/K
WH
Industrial consumers Household consumers
0
0,02
0,04
0,06
0,08
0,1
0,12
0,14
Irel
and
Slo
vak
ia
Lit
hu
ania
Sp
ain
Un
ited
Kin
gd
om
Ital
y
Gre
ece
Po
rtu
gal
Cze
ch R
epu
bli
c
Lat
via
Cro
atia
EU
(28
co
un
trie
s)
Lu
xem
bou
rg
Bel
giu
m
Hu
ngar
y
Rom
ania
Den
mar
k
Tu
rkey
Po
lan
d
Au
stri
a
Ger
man
y
Est
on
ia
Slo
ven
ia
No
rway
Bulg
aria
Sw
eden
Net
her
lan
ds
Fra
nce
Fin
lan
d
€/k
Wh
Turkey: €0.0891/kWh
EU 28: €0.094/kWh
58
4 ASSESSMENT OF ELECTRICITY MARKET DEVELOPMENTS IN
TURKEY
4.1 Level of harmonization of Turkey’s electricity market with EU
legislation and practices
Turkey’s first alignment with the EU acquis on electricity market liberalization came with the
enactment of the 2001 EML (No. 4628). In terms of vertical unbundling, TEAS was divided
into TEIAS, TETAS and EUAS. Each of the new entities was organized as a separate legal
entity. The elements of unbundling required under the First Electricity Directive were the
separation of management and the unbundling of accounts. Hence, the EML exceeded this
requirement through legal unbundling. In addition, the TSO requirement was also met, since
TEIAS was responsible for transmission facilities, investments in the transmission
infrastructure, and balancing and settlement procedures. TEDAS was responsible for the
distribution of electricity, but it also covered some retail trading activities (which were later
transferred to TETAS) (Atiyas & Dutz, 2004, p. 11).
The EML also met the target regarding market opening. All customers who consumed more
that 9GWh a year were designated as eligible customers. Moreover, the newly established
authorization procedure provided entry opportunities in the areas of generation, wholesale,
distribution, retail, import and export. This was also in line with First Electricity Directive
requirements. In addition, the EML required an rTPA regime to access the transmission and
distribution networks. The EML also brought about a new market structure based on bilateral
contracts, but did not envisage a power exchange in the near future (Atiyas & Dutz, 2004, pp.
10-12).
As was the case in EU Member States, many challenges remained to be overcome following
the implementation of the Fist Electricity Directive. Monopolies on the market and a lack of
competition were major problems. According to Atiyas & Dutz (2004, p. 14), the main
challenge in Turkey was to find an exit from the old system. The state was the owner of
generation assets, and was also involved in other parts of the electricity industry, including
trade, transmission and distribution. For this reason, competition was not enabled. In addition,
financial difficulties arose in the distribution segment due to an inefficient tariff system.
Although EU Member States were required to designate an independent regulator under the
Second Electricity Directive, Turkey fulfilled this condition with the 2001 EML through the
establishment of EMRA. Moreover, amendments to the EML adopted in 2008 brought full
compliance with the Second Electricity Directive (EBRD, n.d., p. 165). The exceptions were
cross-border trading and the market opening rate. Nevertheless, Turkey has accelerated the
liberalization process since 2008. The privatization of distribution companies has been
completed. Generation companies are also in the process of privatization, while the market
opening rate reached 85%. The main reasons for the delayed privatization of distribution
assets are the insufficient infrastructure in distribution regions, highly divergent loss and theft
ratios between regions and increasing electricity demand (Cetinkaya, Basaran & Bagdadioglu,
2015b).
59
Cross-border trading has increased as well. Moreover, Turkey’s electricity network has been
fully and permanently integrated with Continental Europe since April 2014. With expected
100% market openness in 2016, Turkey is moving towards integration with the EU and its
practices. In 2013, a new EML was enacted with the primary objective of establishing a
stable, competitive and transparent market. With the implementation of all recent
amendments to the relevant legislation, Turkey is expected to be compliant with the Third
Electricity Directive.
Nevertheless, there is still room for improvement on the market. Each year, the European
Commission prepares a Turkey Progress Report, as a part of its Enlargement Report, in which
it assess the progress made over the last year by candidate countries for EU accession. Such
reports reflect a country’s ability to assume the obligations of membership outlined in the 33
chapters of the acquis, one of them being the Energy Chapter, which has not yet opened due
to a veto by the Republic of Cyprus (Öztürk, 2014). Table 12 summarizes the current status of
Turkey regarding the Energy Chapter, with a focus on electricity.
Table 12. Harmonization with EU legislation and practices
Harmonization with
EU standards
Current status (2014)
Electricity market
prices
Automatic pricing mechanisms that link end-user prices to a cost-based
methodology are envisaged. Nevertheless, the government continues to
set end-user prices (the period was extended until the end of 2015) and
has thus effectively suspended automatic pricing mechanisms.
Privatization Privatization activities were stepped up (total volume of completed
transactions increased from €2.3 billion in 2012 to €9.2 billion in 2013).
The privatization of generation assets has remained limited due to
difficulties experienced by potential investors in securing the necessary
financing.
Security of supply Completion of electricity interconnections with Bulgaria and Georgia.
Turkey contributed to the energy security stress test carried out by the
EC.
Internal energy market Turkey’s legislation is in line with the EU acquis; the majority of
pending implementing regulations were adopted with the new EML.
Customer eligibility Threshold level is 4,500kWh for 2014, which corresponds to a
theoretical market opening rate of 85%. The aim is to reach full market
opening by 2016 to be in line with EU practices.
Energy exchange EPIAS was established (privately and publicly owned).
Renewables – feed-in
tariffs
Prolonged for 10 years, starting in 2016.
Other activities and
instruments related to
renewables
EMRA issued an invitation for pre-licence applications for 3,000 MW of
wind power plants. Evaluation of the pre-license applications for 600
MW continued.
Nuclear energy Turkey and Japan signed an agreement in October 2013 to build the
country’s second nuclear power plant in Sinop (4,500 MW). Turkey and
Japan also signed an agreement to use the nuclear energy for peaceful
purposes.
Source: European Commission, Turkey Progress Report, 2014b, pp. 23-28.
60
Specifically, improvements need to be made in the areas of electricity prices, privatization,
transparency and market openness. Cross-subsidization between customers in the wholesale
and retail electricity markets should be further avoided.
4.2 Future challenges
Although Turkey took concrete steps related to the development of its electricity market,
particularly with the adoption of the new EML, several challenges remain to be overcome in
the future.
At the retail level, there are still some shortcomings that are causing a distortion of
competition. Two major deficiencies are the high level of distribution losses (loss and theft
ratio) and the current tariff regulation. There are major regional differences between the loss
and theft ratios of the 21 distribution regions. For example, regions in Eastern Turkey, such as
Dicle and Vangolu, are the most challenging, since they recorded loss and theft ratios of 75%
and 55% respectively in 2012. Annual electricity consumption was approximately 61 million
MWh in 2012, while overall distribution losses were 25% or 24 million MWh. The highest
losses were between June and August, which are the hottest months of the season (Cetinkaya
et al., 2015b). Figure 26 shows loss and theft ratios for 2013, where again the Dicle and
Vangolu regions recorded extremely high losses. The majority of other regions recorded
losses was below 10 %.
Figure 26. Distribution losses (loss and theft ratios), 2013 in percentages
Source: M. Cetinkaya et al., Barriers to competition in the Turkish electricity market, 2015a, p. 12.
In 2013, Turkey experienced total system losses equal to 16.5% (13.3% in distribution and
2.5% in transmission) of total electricity output (TurkStat, 2014). Those numbers are much
lower in EU Member states. For example, Germany, Italy, Slovenia, Austria, Finland and
61
Greece recorded losses of 4%, 7%, 5%, 6%, 3% and 5% respectively (World Bank data,
2014). On the other hand, all SEE contracting parties are experiencing the same problems as
Turkey in terms of high system losses. As shown in Table 13, all countries have system losses
above 10%, with Albania recording exceptionally high losses of more than 45%.
Table 13. System losses by SEE contracting parties, 2013 in percentages
Source: Energy Community Secretariat, Annual Implementation Report 2013/2014, 2014.
According to the paper of Tasdoven, Fiedler & Garayev (2012, pp. 230-232), grants and
public information could be an effective solution to the illegal use of electricity in Turkey, in
addition to economic regulation and privatization. The paper proposes government-awarded
grants that should be given to private institutions and universities. They would carry out a
three-stage research project. The first stage involves research of the real reasons for
distribution losses. Although there is statistical data available regarding the number of losses
and underlying reasons, the experiences of many developing countries have shown that
government-affiliated agencies may provide biased information if they want to limit public
knowledge of theft. The second stage would involve identifying fraudulent use. The aim of
stage three is to design and conduct surveys in order to determine to what extent citizens are
aware of consumption that is harnessed separately from regulated transmission lines and is
thus considered a crime. All of these data would then be publicly disclosed or delivered to
customers via public campaigns aimed at influencing the behaviour of the target audience.
The most important issue relating to loss and theft ratios is the current tariff structure. Since
an equalization mechanism is applied, prices are the same for all regions. Consequently, the
losses incurred by higher-cost regions are borne in part by the customers of low-cost regions.
The costs of regions with high losses are cross-subsidized by regions with low losses. Such a
policy is not sustainable in the long run, although it is acceptable in the short term for
privatized firms, whose interest it is to recoup the high amount of investments required for the
privatization process. Privatized distribution companies have a regulatory obligation to
achieve target annual loss and theft ratios. However, actual ratios are not in line with the
commitments made by those companies. Current EMRA policy is therefore not appropriate
for overcoming the problem of high distribution losses (Cetinkaya et al., 2015a, p. 12).
In term of electricity generation, the completion of the privatization process for generation
assets and source diversification represent future challenges, as well. The Turkish
Contracting
parties
Ukraine Serbia Montenegro Moldova Macedonia Bosnia and
Herzegovina
Albania
Losses in
transmission
2.42 2.40 4.28 2.90 2.00 1.81 2.3
Losses in
distribution
10.17 14.90 18.96 10.70 16.40 11.55 45.04
Total system
losses
12.59 17.3 23.24 13.6 18.4 13.36 47.34
62
government has tried to attract foreign investors to participate in tenders for generation assets.
Interest, however, was very limited. In the end, mainly domestic construction and energy
companies submitted bids in 2014, with much lower figures than in 2013. This was due to the
depreciation of the Turkish lira vis-à-vis foreign currencies. In terms of financing,
international banks have not been active, while the political elections in 2014 also slowed
several economic activities (Durakoğlu, 2014). The successful completion of the privatization
process can help reduce the government’s influence over the electricity market, resulting in
increased competition (Cetin, 2014, p. 104).
Turkey’s population is forecasted to exceed 83 million in 2020. The country also faces
increasing electricity demand, which will have reached 435 TWh by 2020 (Bilgili, 2009, p.
246). To that end, it is important to ensure a sufficient electricity supply for the future.
Currently, Turkey is highly dependent on imported natural gas (Figure 27). This is a very big
challenge in terms of source diversification and the security of supply. One of the problems of
natural gas dependency is that when natural gas supply becomes limited, the price of
electricity on the spot market is expected to rise due to the associated scarcity, resulting in the
increased use of alternative (and expensive) generation sources (Camdan & Kolmek, 2013, p.
68). In 2012 (13 February), for example, there were heavy winter conditions, resulting in a
significant decrease in the natural gas supply from Azerbaijan and Iran, which was
accompanied by a simultaneous sharp rise in domestic consumption. Thus, gas-fired power
plants faced problems in generation, and the price on the day-ahead market reached 2,000
TL/MWh, which is 10 times higher than the average high level of 200 TL/MWh (Camdan &
Kolmek, 2013, p. 68).
Figure 27. Share of natural gas in electricity generation
Source: TurkStat, 2014.
0,00%
10,00%
20,00%
30,00%
40,00%
50,00%
60,00%
Share of natural gas in electricity
generation
63
It is therefore important for Turkey to strive to reduce its dependence on natural gas imports.
The aim of its national energy strategy is to further increase the use of hydro, wind and solar
energy resources, since its potential for renewable energy resources is substantial. Secondly,
the gradual introduction of nuclear power into the country’s energy mix is also a part of the
strategy (Republic of Turkey – Ministry of Foreign Affairs, 2015). Nevertheless, the
liberalization of the natural gas market also plays an important role, particularly in terms of
reducing the market share of BOTAS and thus enabling competition.
The wholesale market is rapidly transforming into a competitive market, which has resulted in
the identification of manipulation risks. In general, electricity markets can be manipulated for
several reasons, including: (i) a lack of elasticity on the electricity markets, which results in
unexpected price volatility when a small decrease in distribution occurs; (ii) storage
difficulties, which lead to an obligatory well-balanced electricity market; (iii) generation
companies may gain market power as price determinants when transmission issues arise; (iv)
producers usually operate at maximum capacity with regard to their marginal cost, and are
thus unable to adapt to price increases (Herdem, 2014).
Due to the potential manipulation risks stated above, it is necessary to have an authorized
body that deals with such potential manipulation. The EU has enacted the Regulation on
Energy Market Integrity (REMIT), while ACER is authorized to collect data and observe
markets. In Turkey, there is a lack of REMIT-type rules that require market participants to
regularly report their wholesale market contracts. Thus, new secondary legislation is urgently
needed in the future to stimulate market confidence (Herdem, 2014; Santos, 2015).
CONCLUSION
This master’s thesis offers an analysis of the Turkish electricity market following the major
reform thereof. Turkey’s harmonization with EU legislation and practices is also reviewed.
The EU restructured its energy markets via three energy packages adopted in 1996, 2003 and
2009. The three electricity directives were the main instruments in the process of introducing
competition to national markets. The main objective of the electricity directives was to
introduce competition to the market, and to ensure the transparency and financial stability of
the markets and the security of supply. Regional markets represented the next step towards
creating an internal electricity market. EU Member States formed seven electricity regions
that share a similar economic and political environment.
In addition to the seven electricity regions, which cover the electricity markets of EU Member
States, an eighth region was also established. It is also referred to as the SEE region and
covers the Energy Community contracting parties, as well as neighbouring EU countries.
Turkey has the status of Energy Community observer, with the goal of becoming an EU
Member State, as well as Energy Community contracting party. Turkey is thus following EU
practices in order to ensure competition on the market.
64
The first major change on the Turkish electricity market occurred with the enactment of the
EML in 2001. The EML vertically unbundled TEAS into the following new publicly owned
entities: TEIAS (transmission), TETAS (trading) and EUAS (generation). In addition, the
regulator EMRA was established and the concept of eligible customer defined. A new market
structure was also introduced, comprising bilateral contracts and a balancing mechanism. The
EML was subsequently amended in 2008, while a new EML entered into force in 2013. Both
were aimed at accelerating the liberalization process and achieving compliance with EU
legislation and practices.
The role of the publicly owned EUAS is decreasing in the generation segment, where a higher
private-sector presence is expected in the future, since new plants are being built by the
private sector. In addition, several EUAS power plants are currently included in the
privatization process. Electricity is mainly generated from natural gas, coal and hydro
sources. Although the country is historically dependent on imported natural gas, renewables
are gradually achieving a higher market share and enabling Turkey to diversify its resources
for electricity generation. In addition, two nuclear power plants are expected to be built and
operational in the future.
Transmission lines are operated by the publicly owned TEIAS, Turkey’s TSO. It maintains
the transmission network and it conducts auctions for transmission capacities.
Major changes have occurred recently on the wholesale market. The market is currently being
transformed into a competitive, financially stable and transparent wholesale market. The
current hybrid model, which comprises bilateral contracts and a balancing mechanism, will be
replaced by the EPIAS power exchange, which will cover the spot market on a day-ahead and
intraday basis. Derivatives will continue to be traded on the Borsa Istanbul, while TEIAS will
be responsible for the balancing market. With more available capacities expected on the
Bulgarian and Greek borders (ENTSO-E connections), through improved transparency and
with its own power exchange, the Turkish power market is likely to become a leader in the
region.
The retail and distribution markets were recently unbundled. There are now 21 privatized
distribution companies, each acting as a DSO for its own region. The retail market has been
separated, and enables private companies to enter the market and sell electricity to eligible
customers. The current rate of market opening is 85%, with the market expected to be fully
open in 2016.
As can be noted, Turkey has put major efforts into the process of transforming its former
vertically integrated electricity market into a fully competitive and transparent electricity
market. It is following the example of EU Member States, and is trying to offer market
players a competitive market place. Nevertheless, this is a complex process and Turkey still
has many challenges to overcome.
The most concerning are the level of distribution losses, which are extremely high in some
regions (up to 75%). Related to those losses are inappropriate regulated tariffs that are equal
for all the regions. This is not efficient over the long run, since the losses of higher-cost
regions are borne by the customers of the low-cost regions.
65
Moreover, dependence on imported natural gas should be reduced, since electricity prices are
affected by potential changes on the gas market. Accordingly, the natural gas market in
Turkey should be liberalized and made more competitive with the aim of achieving more
competitive prices. Wholesale electricity markets are also exposed to manipulation risks, and
should implement REMIT-type rules in order to stimulate market confidence.
REFERENCE LIST
1. ACER – Agency for the Cooperation of Energy Regulators. Retrieved February 20, 2014
from http://www.acer.europa.eu/Pages/ACER.aspx
2. ACER (2013). Final steps towards the 2014 deadline – regional initiatives status review
report 2013. Ljubljana: ACER.
3. ACER (2014a, February 4). ACER welcomes the day-ahead market coupling in North-
West Europe (press release). Retrieved June 28, 2015 from
http://www.acer.europa.eu/Media/Press%20releases/ACER%20PR-01-14.pdf
4. ACER Coordination Group for Electricity Regional Initiatives (2015, May 29). ERI
Progress Report, October 2014 – March 2015. Retrieved June 28, 2015 from
http://www.acer.europa.eu/Official_documents/Acts_of_the_Agency/Publication/2nd%20
ERI%20Progress%20Report.pdf
5. ACER Coordination Group for Electricity Regional Initiatives (2014, October 24). ERI
Progress Report, April 2014 – September 2014. Retrieved January 20, 2015 from
http://www.acer.europa.eu/Official_documents/Acts_of_the_Agency/Publication/1st%20
ERI%20Progress%20Report.pdf
6. ACER/CEER (2014, October). Annual Report on the Results of Monitoring the Internal
Electricity and Natural Gas Markets in 2013. Ljubljana: ACER; Brussels: CEER.
7. Atiyas, I., & Dutz, M. (2004, September). Competition and Regulatory Reform in the
Turkish Electricity Industry. Retrieved May 22, 2014 from
http://myweb.sabanciuniv.edu/izak/files/2008/10/atiyas-dutz-electricity-2004.pdf
8. Atiyas, I., Çetin, T., & Gülen, G. (2012). Reforming Turkish Energy Markets: Political
Economy, Regulation and Competition in the Search for Energy Policy. New York:
Springer.
9. Bademli, I. (2013, May 29). Turkey: Regulations In The New Turkish Electricity Market
Law Regarding The Organised Wholesale Power Markets. Retrieved January 22, 2015
from
http://www.mondaq.com/x/241894/Commodities+Derivatives+Stock+Exchanges/Regulat
ions+In+The+New+Turkish+Electricity+Market+Law+Regarding+The+Organised+Whol
esale+Power+Markets
10. Bagdadioglu, N., & Odzakmaz, N. (2009). Turkish electricity reform. Utilities Policy,
147(1), 144-152.
11. Baha Karan, M., & Kazdağli, H. (2011). The Development of Energy Markets in Europe.
In Dorsman, A., Westerman, W., Karan, M.B., & Arslan, Ö. (Eds.), Financial Aspects in
Energy (pp. 11-32).
66
12. Bahce, S., & Taymaz, E. (2007). The impact of electricity market liberalization in
Turkey,”Free consumer” and distributional monopoly cases. Energy Economics 20(4).
1603-1624.
13. Baris, K., & Kucukali, S. (2010). Turkey’s short-term gross annual electricity demand
forecast by fuzzy logic approach. Energy Policy, 38(2010), 2438–2445.
14. Baris, K., & Kucukali, S. (2012). Availability of renewable energy sources in Turkey:
Current situation, potential, government policies and the EU perspective. Energy policy,
42 (2012), 377-391.
15. Bilgili, M. (2009). Present Status and Future Projections of Electrical Energy in Turkey.
Retrieved June15, 2015 from file:///C:/Users/Administrator/Downloads/225-550-2-PB.pdf
16. Böckers, V., Haucap, J., & Heimeshoff, U. (2013). Cost of Non-Europe in the Single
Market for Energy, Annex IV, Benefits of an integrated European electricity market: the
role of competition. Retrieved May 14, 2014 from
http://www.europarl.europa.eu/RegData/etudes/etudes/join/2013/504466/IPOL-
JOIN_ET(2013)504466(ANN04)_EN.pdf
17. Bölük, G. (2013). Renewable Energy: Policy Issues and Economic Implications in
Turkey. International Journal of Energy Economics and Policy, 3(2), 153-167.
18. Borsa Istanbul – Base load electricity futures. Retrieved February 15, 2015 from
http://www.borsaistanbul.com/en/products-and-markets/products/futures/energy-
futures/base-load-electricity-futures
19. Borsa Istanbul (2013, September 16). Borsa Istanbul and the Energy Market. Retrieved
July 02, 2015 from http://www.oicexchanges.org/docs/seventh-meeting-istanbul-
presentations/borsa-istanbul-and-energy-market.pdf
20. BOTAS. Retrieved 25.10.2014 from http://www.botas.gov.tr/index.asp
21. Çakmak Avukatlık Bürosu (2013, March 22). The New Electricity Market Law. Retrieved
February 10, 2015 from
http://www.cakmak.av.tr/articles/Power/The%20New%20Electricity%20Market%20Law.
22. Camdan, E., & Kolmek, F. (2013). A Critical Evaluation of Turkish Electricity Reform.
The Electricity Journal 26(1), 59-70.
23. CEER – Council of European Energy Regulators. Retrieved February 20, 2014 from
http://www.ceer.eu/portal/page/portal/EER_HOME
24. Çelen, A. (2013). The effect of merger and consolidation activities on the efficiency of
electricity distribution regions in Turkey. Energy Policy 59, 674-682.
25. Cetin, T. (2014). Structural and regulatory reform in Turkey: Lessons form public utilities.
Utilities Policy 31(2014), 94-106.
26. Cetin, T., & Oguz, F. (2007). The politics of regulation in the Turkish electricity market.
Energy Policy 35(3), 1761–1770.
27. Cetinkaya, M., Basaran, A.A., & Bagdadioglu, N. (2015a). Barriers to competition in the
Turkish electricity market. Network Industries Quarterly, 17(1), 10-12.
28. Cetinkaya, M., Basaran, A.A., & Bagdadioglu, N. (2015b). Electricity reform, tariff and
household elasticity in Turkey. Utilities Policy, 2015, 1-7.
29. Commission of the European Communities (2007, January 10). An energy policy for
Europe. Communication from the Commission to the European Council and the European
67
Parliament. Retrieved November 10, 2015 from http://eur-lex.europa.eu/legal-
content/EN/ALL/?uri=CELEX:52007DC0001
30. Deloitte Consulting (2012, November 30). Turkish electricity market review. Georgia:
Deloitte.
31. Deloitte Consulting (2013, February). Turkey import and export expectations – project
report 2. Georgia: Deloitte Consulting.
32. Deloitte Consulting (2014, June 2). Trade opportunities between Georgia and Turkey.
Georgia: Deloitte Consulting.
33. Deloitte Türkiye (2013, November). The Energy Sector: A Quick Tour for the Investor.
Retrieved July 13, 2014 from http://www.invest.gov.tr/en-
US/infocenter/publications/Documents/ENERGY.INDUSTRY.pdf
34. DG Energy – Market Observatory for Energy (2013). Quarterly report on European
Electricity Markets, second quarter 2013. Brussels: European Commission.
35. Directive 2003/54/EC of the European Parliament and of the Council of 26 June 2003
concerning common rules for the internal market in electricity and repealing Directive
96/92/EC. Official Journal of the European Union no. L 176/37.
36. Directive 2009/72/EC of the European Parliament and of the Council of 13 July 2009
concerning common rules for the internal market in electricity and repealing Directive
2003/54/EC. Official Journal of the European Union no. L 211/55.
37. Directive 96/92/EC of the European Parliament and of the Council of 19 December 1996
concerning common rules for the internal market in electricity. Official Journal of the
European Union no. L 027.
38. Durakoğlu, M. (2014, August). Turkey’s efforts to privatise its electricity generation
assets: challenges ahead. Retrieved January 12, 2015 from
http://www.financierworldwide.com/turkeys-efforts-to-privatise-its-electricity-generation-
assets-challenges-ahead/#.VTDGw_msWd4
39. EBRD (n.d.). Turkey country profile. Retrieved September 11, 2014 from
http://www.ebrd.com/downloads/legal/irc/countries/turkey.pdf
40. EEX. Retrieved September 12, 2014 from https://www.eex.com/en#/en
41. Electricity generation & transmission statistics of Turkey for year 2013 (n.d.) In Turkish
electricity generation – transmission statistics. Retrieved November 10, 2014 from
http://www.teias.gov.tr/T%C3%BCrkiyeElektrik%C4%B0statistikleri/istatistik2013/istati
stik2013.htm
42. Electricity market balancing and settlement regulation. Official Gazette No. 27200 dated
15/04/2009.
43. Electricity Market Import and Export Regulation. Official Gazette of Republic of Turkey
no. 29003.
44. Electricity Market Law no. 4628. Official Gazette of Republic of Turkey no. 24335 dated
3/3/2001.
45. Electricity market tariffs regulation. Official Gazette of Republic of Turkey no. 25929
dated 7 September 2005.
46. EMRA – Natural Gas Market Department (2012). Natural Gas Market – Sector Report
2011. Ankara: EMRA – Natural Gas Market Department.
68
47. Energy Community Secretariat (2014, August 1). Annual Implementation Report
2013/2014. Vienna: Energy Community Secretariat. Energy Community. Retrieved July
18, 2014 from https://www.energy-community.org/portal/page/portal/ENC_HOME
48. Energy Market Regulatory Authority (EMRA) (n.d.). Electricity Market Report 2010.
Retrieved June 15, 2014 from
http://www.emra.org.tr/documents/electricity/publishments/ElectricityMarketReport2010.
49. Energy Market Regulatory Authority (EMRA) (n.d.). Turkish Energy Market: An
Investor’s Guide 2012. Ankara: EMRA.
50. Enerjisa. Retrieved February 10, 2015 from http://www.enerjisa.com.tr/tr-
TR/Pages/default.aspx
51. Entsoe. Retrieved February 20, 2014 from https://www.entsoe.eu/Pages/default.aspx
52. Equities.com. Retrieved July 02, 2015 from
http://www.equities.com/index.php?option=com_k2&view=newsdetail&id=171894
53. Erdem, E. (2013, March). The New Electricity Market Law. Retrieved September 22,
2014 from http://www.erdem-erdem.com/fr/articles/the-new-electricity-market-law-2/
54. Erdogdu, E. (2006). Regulatory reform in Turkish energy industry: An analysis. Energy
Policy, 35 (2007), 984–993.
55. Ergun Benan, E. & Burcu Tuzcu, E. (2014, April). Electricity regulation in Turkey:
overview. Retrieved February 05, 2015 from http://uk.practicallaw.com/0-523-
5654?q=Turkey#
56. Ergün, C. E. & Gökmen (2013). Electricity regulation in Turkey: overview. Energy and
Natural Resources multi-jurisdictional guide 2013. Retrieved February 14, 2014 from
http://www.cakmak.av.tr/articles/Power/Turkey_Power.pdf
57. EUAS – Electricity Generation Company. Retrieved January 12, 2015 from
http://www.euas.gov.tr/Sayfalar/Eng/AnaSayfa.aspx
58. Eurelectric (2012, September). Taxes and Levies on Electricity in 2011. Brussels:
Eurelectric.
59. Eurocoal. Retrieved September 11, 2014 from
http://www.euracoal.be/pages/home.php?idpage=1
60. European commission – Energy. Retrieved February 20, 2014 from
http://ec.europa.eu/energy/index_en.htm
61. European Commission (2005, October 25). The EU and South East Europe sign a historic
treaty to boost energy integration (press release). Retrieved May 10, 2014 from
http://europa.eu/rapid/press-release_IP-05-1346_en.htm
62. European Commission (2010, January 22). Interpretative note on Directive 2009/72/EC
concerning common rules for the internal market in electricity and Directive 2009/73/EC
concerning common rules for the internal market in natural gas – retail markets. Retrieved
October 10, 2015 from
https://ec.europa.eu/energy/sites/ener/files/documents/2010_01_21_retail_markets.pdf
63. European Commission (2014a, January 29). Energy prices and costs in Europe.
Communication from the Commission to the European Parliament, the Council, the
European Economic and Social Committee and the Committee of the Regions. Brussels:
European Commission.
69
64. European Commission (2014b, October). Turkey Progress Report. Retrieved March 25,
2015 from http://ec.europa.eu/enlargement/pdf/key_documents/2014/20141008-turkey-
progress-report_en.pdf
65. European Parliament. Retrieved June 22, 2014 from
http://www.europarl.europa.eu/aboutparliament/en
66. Eurostat – Energy price statistics. Retrieved May 2, 2014 from
http://ec.europa.eu/eurostat/statistics-explained/index.php/Energy_price_statistics
67. Herdem, S. (2014, January 4). A test for Turkish Electricity Market: Fraud-Based
Manipulation. Retrieved July 02, 2015 from
http://www.mondaq.com/turkey/x/285156/Oil+Gas+Electricity/A+Test+for+Turkish+Ele
ctricity+Market+FraudBased+Manipulation
68. Herdem, S. (2015, March 30). Turkey: A New Era For Turkish Energy Market: EPIAs.
Retrieved April 11, 2015 from
http://www.mondaq.com/x/384880/Oil+Gas+Electricity/A+New+Era+For+Turkish+Ener
gy+Market+EPIAs
69. Hrovatin, N., Zorić, J. (2011). Reforme elektrogospodarstva v EU in Sloveniji. Ljubljana:
Ekonomska fakulteta.
70. Hull, J. (2009). Options, futures and other derivatives. Upper Saddle River (NJ) : Prentice
Hall.
71. International enegry statistics (n.d.). In EIA Independent Statistics & Analysis. Retrieved
November, 17, 2014 from
http://www.eia.gov/cfapps/ipdbproject/iedindex3.cfm?tid=1&pid=1&aid=2&cid=TU,&sy
id=2005&eyid=2012&unit=TST
72. International Energy Agency (IEA) (2009). Energy Policies of IEA Countries, Turkey
2009 Review. Paris: OECD/IEA.
73. International Energy Agency (IEA) (2013a). Key World Energy Statistics. Paris: IEA.
74. International Energy Agency (IEA) (2013b). Oil and gas security, Emergency response of
IEA countries (Turkey). Paris: IEA.
75. Invest in Turkey – The Republic of Turkey prime ministry investment support and
promotion agency. Retrieved June 14, 2014 from http://www.invest.gov.tr/en-
US/Pages/Home.aspx
76. Investopedia dictionary - Affiliate. Retrieved July 02, 2015 from
http://www.investopedia.com/terms/a/affiliate.asp
77. Jakovac, P. (2012). Electricity Directives and evolution of the EU internal electricity
market. Retrieved June 18, 2015 from
file:///C:/Users/Administrator/Downloads/21_Jakovac.pdf
78. Jamasb, T. & Pollitt, M. (2005). Electricity Market Reform in the European Union:
Review of Progress toward Liberalization & Integration. The Energy Journal, European
Energy Liberalization Special Issue (26), 11-41.
79. Karaduman, O. & Avcisert, T. (2013, April 24). Reorganising Turkey’s electricity market.
Retrieved January 25, 2015 from http://www.iflr.com/Article/3196418/Reorganising-
Turkeys-electricity-market.html
70
80. Karahan, H. & Toptas, M. (2013). The effect of power distribution privatization on
electricity prices in Turkey: Has liberalization served the purpose? Energy Policy 63, 614-
621.
81. Karova, R. (2011). Regional electricity markets in Europe: Focus on the Energy
Community. Utilities Policy 19 (2), 80-86.
82. Kentel, E. & Alp, E. (2013). Hydropower in Turkey: economical, social and
environmental aspects and legal challenges. Environmental Science & Policy 31, 34-43.
83. Kölmek, F. (2014, January 27). Turksih Power Balancing Market. Retrieved November
11, 2014 from
http://www.naruc.org/international/Documents/Fkolmek_TrPowerBalancingMechanism.p
df
84. Kopsakangas-Savolainen, M. & Svento, R. (2012). Modern Energy Markets – Real-Time
Pricing, Renewable Resources and Efficient Distribution. New York: Springer.
85. Kovács, K. (2011, June 10). The EU internal energy market: past, present and future.
Presentation for conference ““Multi-Sector Regulation – Present and Future
Challenges” by DG Energy. Retrieved September 15, 2014 from
http://www.sprk.gov.lv/uploads/doc/04KristofsKovacs.pdf
86. Law on the Utilization of Renewable Energy Sources for Electricity Generation no. 5346.
Official Gazette of Republic of Turkey no. 25819 dated 18/5/2005.
87. Lazard (n.d.). Privatization of Turkey’s Electricity Distribution Industry. Retrieved
January 18, 2015 from http://www.oib.gov.tr/tedas/teaser_english.pdf
88. Legal sources on renewable energy. Retrieved March 03, 2015 from http://www.res-
legal.eu/home
89. Market & Financial Settlement Centre (PMUM) – General Reports. Retrieved September
11, 2014 from https://rapor.pmum.gov.tr/rapor//xhtml/index.xhtml;jsessionid=YfKa9-
q9maZCstEgluQCnXjf
90. Meeus, L., Purchala, K., & Belmans R. (2005). Development of the Internal Electricity
Market in Europe. The Electricity Journal 18(6), 25-35.
91. Mercados (2010, April 28). From Regional Markets to a Single European Market.
Retrieved January 30, 2015 from
http://ec.europa.eu/energy/sites/ener/files/documents/2010_gas_electricity_markets.pdf
92. Natural Gas Europe. Retrieved July 15, 2014 from http://www.naturalgaseurope.com/
93. New Electricity Market Law no. 6446. Official Gazette of Republic of Turkey no. 28603
dated 03/30/2013.
94. OECD.StatExtracts. Retrieved September 11, 2014 from http://stats.oecd.org/
95. Öztürk, C.N. (2014, November 18). EU seeks to expand energy cooperation with Turkey.
Retrieved March 10, 2015 from http://www.turkishweekly.net/news/175697/eu-seeks-to-
expand-energy-cooperation-with-turkey.htm
96. Pellini, E. (February, 2014). Essays on European Electricity Market Integration. Submitted
for the degree of Doctor of Philosophy in Energy Economics, Surrey Energy Economics
Centre (SEEC). Retrieved October 05, 2015 from
http://www.seec.surrey.ac.uk/PGProgs/PhDTheses/2014ElisabettaPelliniThesis.pdf
71
97. Pollitt, M. (2009). Electricity Liberalization in the European Union: A Progress Report.
University of Cambridge, working paper in economics. Retrieved May 14, 2014 from
http://www.econ.cam.ac.uk/research/repec/cam/pdf/cwpe0953.pdf
98. PwC Turkey (February, 2014). Liberilising natural gas in Turkey. Retrieved July 02, 2015
from http://www.pwc.com.tr/tr_TR/tr/publications/industrial/energy/assets/turkiyede-
dogalgaz-piyasasinin-liberallesmesi-raporu.pdf
99. Regulation (EC) no 713/2009 of the European Parliament and of the Council of 13 July
2009 establishing an Agency for the Cooperation of Energy Regulators. Official Journal
of the European Union no. L 211/1.
100. Republic of Turkey – High planning Council (2004, March 17). Electricity sector
reform and privatization strategy paper. Retrieved June 22, 2014 from
http://www.oib.gov.tr/program/2004_program/2004_electricity_strategy_paper.htm
101. Republic of Turkey – Ministry of energy and natural resources (MENR). Retrieved
July 25, 2014 from http://www.enerji.gov.tr/en-US/Mainpage
102. Republic of Turkey – Ministry of Foreign Affairs. Retrieved July 02, 2015 from
http://www.mfa.gov.tr/turkeys-energy-strategy.en.mfa
103. Republic of Turkey – Secretariat of the Higher Board of Planning (2009, May 21).
Electricity Energy Market and Supply Security Strategy Paper. Ankara: Republic of
Turkey – Secretariat of the Higher Board of Planning.
104. Republic of Turkey Prime Ministry – Privatization Administration. Retrieved
November 03, 2014 from http://www.oib.gov.tr/index_eng.htm
105. RWE – Press and news. Retrieved July 02, 2015 from
http://www.rwe.com/web/cms/en/403722/rwe/press-news/specials/energy-trading/how-
the-electricity-price-is-determined/
106. Rzayeva, G. (2014, February). Natural Gas in the Turksih Domestic Energy Market:
Policies and Challanges. Oxford: Universtiy of Oxford – The Oxford institiute for energy
studies.
107. Santos, A.J. (2015, June 5). Turkey: Turkish Energy Market 2015. Retrieved July 02,
2015 from
http://www.mondaq.com/turkey/x/395770/Oil+Gas+Electricity/Turkish+Energy+Market+
2015
108. SEE CAO. Retrieved February 05, 2015 from http://www.seecao.com/
109. Sioshansi, F. (2006). Electricity market reform: what have we learned? what have we
gained? Electricity Journal, 19(9), 70–83.
110. Staschus, K. (2014). TSO cooperation and the internal energy market – Annual report
2013. Brussels: ENTSO-E AISBL.
111. Tasdoven, H., Fiedler B.A. & Garayev, V. (2012). Improving electricity efficiency in
Turkey by addressing illegal electricity consumption: A governance approach. Energy
Policy 43, 226-234.
112. Thomas, S.D. (2006). Electricity industry reforms in smaller European countries and
the Nordic experience. Energy 13, 788-801.
113. Today's Zaman - Business. Retrieved July 02, 2015 from
http://www.todayszaman.com/business
72
114. Toklu, E. (2013). Overview of potential and utilization of renewable energy sources in
Turkey. Renewable Energy 50, 456-463.
115. Turkish Electricity Trading and Contracting Co. Inc. – TETAS. 2013 Annual Activity
Report. Retrieved November 14, 2014 from
http://www.tetas.gov.tr/File/?path=ROOT%2f1%2fDocuments%2fFaaliyet+Raporu%2fT
ETA%C5%9E_2013_Y%C4%B1l%C4%B1_Faal_Raporu2.pdf
116. Turkish Electricity Transmission Company – TEIAS. Retrieved September 11, 2014
from http://www.teias.gov.tr/Eng/Default.aspx
117. Turkish Statistical Institute – TurkStat. Retrieved May 14, 2014 from
http://www.turkstat.gov.tr
118. U.S. Energy Information Administration (2013, July). International Energy Outlook
2013 with projections to 2040. Retrieved March 27, 2014 from
http://www.eia.gov/forecasts/ieo/pdf/0484%282013%29.pdf
119. Verdugo Penados, C. (2008, October 8). Role of the Physical Power Exchanges in the
Electricity Wholesale Market (Master’s thesis). Madrid: Universidad Pontificia Comilla.
120. Woo, C.K., Lloyd, D. & Tishler, A. (2003). Electricity market reform failures: UK,
Norway, Alberta and California. Energy Policy, 31(11), 1103–1115.
121. Yuksel, I. (2013). Renewable energy status of electricity generation and future
prospect hydropower in Turkey. Renewable Energy 50, 1037-1043.
0
APPENDIXES
0
LIST OF APPENDIXES
Appendix A: Summary – Povzetek v slovenskem jeziku (na osnovi magistrskega dela)
……..……………………………………………………..…………………………………….1
Appendix B: List of abbreviations …………….…………………………………….……….10
Appendix C: Table illustrating the Turkish electricity market and selected SEE electricity
markets ………………………………………………..……………………………………...11
Appendix D: Table of feed in tariffs (for selected countries)
………………………………………………………………………………………...…...…13
Appendix E: Transmission lines in Turkey ………………………………………………….16
1
APPENDIX A: Summary – Povzetek v slovenskem jeziku (na osnovi magistrskega dela)
Glavni lastnosti trgov z električno energijo sta bili ekonomija obsega v proizvodnji električne
energije in dejstvo, da mora slednja preko obsežnega prenosnega in distribucijskega sistema,
preden je dobavljena končnim odjemalcem. Zaradi teh karakteristik so v dvajsetem stoletju
trge električne energije obvladovala podjetja, ki so bila v državni lasti. Obenem so bila ta
podjetja vertikalno integrirana v vse dejavnosti elektrogospodarstva in imela monopol na trgu
(Kopsakangas – Savolainen in Svento, 2012, p. 5).
Zaradi velikega nezadovoljstva, povezanega s takšno organiziranostjo trga, je veliko držav
začelo z reorganizacijo delovanja trgov električne energije. Obstajalo je veliko empiričnih in
teoretičnih dokazov, predvsem o prednostih konkurence in o nevmešavanju države v
delovanje trga. Dejavniki, ki so omogočili reforme v elektrogospodarstvu, pa so bili: nove
proizvodne tehnologije (te so zmanjšale optimalno velikost elektrarn), zahteve po povečanju
stroškovne učinkovitosti monopolnih podjetij in splošno prepričanje, da država ni ustrezen
lastnik (predvsem zaradi prepočasnega odzivanja na ekonomske in tehnološke spremembe)
(Hrovatin in Zorić, 2011).
Skupaj z globalnim trendom je tudi Evropska unija (EU) začela s prestrukturiranjem trgov
električne energije v državah članicah. Glavni cilj EU je ustvariti notranji trg z učinkovito
konkurenco, ki prinaša dobrobit potrošnikom (zaradi konkurence se cene električne energije
nižajo) in udeležencem na trgu (zaradi preprečevanja monopolistične situacije na trgu)
(Bockers et al., 2013, str. 7). Splošno gledano se v procesu liberalizacije trgov z električno
energijo odvijejo štirje glavni koraki, ki vodijo k bistvenih spremembam na trgu (Jamasb in
Pollit, 2005, str. 13):
- Prestrukturiranje: vertikalna ločitev proizvodnje, prenosa, distribucije in dobave električne
energije končnim kupcem.
- Konkurenca in trgi: oblikovanje trga na debelo in trga na drobno, uvedba konkurence.
- Regulacija: ustanovitev neodvisnega regulatorja trga, dostop do omrežja, regulacija za
distribucijsko in prenosno omrežje.
- Lastnina: privatizacija državnih podjetij in omogočanje vstop novim, zasebnim podjetjem
na trgu.
Vsi zgoraj navedeni koraki so bili v državah članicah EU sproženi z reformo, ki je bila
izvedena z dvema vzporednima procesoma. Prvi je bil uvedba smernic za vzpostavitev
notranjega trga električne energije v EU (Direktiva 96/92/EC, Direktiva 2003/54/EC in
Direktiva 2009/72/ES). Drugi proces pa je bil vzpodbujanje razširitve čezmejnih prenosnih
povezav skupaj z izboljšavo pravil za čezmejno trgovanje (Karan in Kazdagli, 2011, str. 13;
Jamasb in Pollitt, 2005, str. 17).
Zahteve Direktiv EU o oblikovanju notranjega trga z električno energijo so predstavljene v
tabeli 1.
2
Tabela 1. Direktive EU o oblikovanju notranjega trga z električno energijo
Določbe Prva direktiva
(1996) Druga direktiva
(2003)
Tretja direktiva
(2009)
Proizvodnja (gradnja
novih proizvodnih
zmogljivosti)
Omogoča novim
igralcem na trgu
izgradnjo na podlagi
dovoljenja ali razpisa
Dovoljenje Dovoljenje
Razpis (energetska
učinkovitost,
menedžment
povpraševanja)
Prenos (T) ,
distribucija (D)
(dostop do omrežja)
Regulirani TPA,
izpogajani TPA, edini
kupec
Regulirani TPA Regulirani TPA
Dobava (vertikalna
ločitev)
Ločitev računovodskih
izkazov
Funkcionalna ločitev
od prenosa in
distribucije
Funkcionalna ločitev
od prenosa in
distribucije
Uporabniki
(odpiranje trga)
Izbira za upravičene
odjemalce (do 1/3
končne porabe)
Vsi negospodinjski
odjemalci od leta
2004, vsi odjemalci od
leta 2007
Vsi
Ločitev T
Ločitev D
Računovodski izkazi Pravna ločitev Lastniška (T)
Pravna (vertikalno
integrirana podjetja
(T) in upravljavska,
neodvisna SOPO (T)
Pravna (D)
Čezmejna trgovina Pogajanja Regulirana Regulirana, ENTSO
Regulacija Ni določena Regulatorni organ
(NRA)
European Regulators'
Group for Electricity
and Gas (ERGEG)
Močno povečana
neodvisnost in
pristojnosti NRA
Ustanovljena ACER
Vir: N. Hrovatin in J. Zorič, 2011, Reforme elektrogospodarstva v EU in Sloveniji, str. 7.
Kot je prikazano v tabeli 1, so se spremembe v EU uvajale postopoma. Po uvedbi prve
direktive (1996) je bilo na trgu namreč še veliko pomanjkljivosti, predvsem gre omeniti
pomanjkanje transparentnosti in tehnične težave, ki so onemogočale dostop do omrežja.
Polega tega pa so bili monopoli še vedno prisotni na trgu (Kovacs, 2011). Z uvedbo druge
direktive sta bila omogočena konkurenca na trgu proizvodnje električne energije in dostop do
omrežja, vendar je bilo prisotno veliko pomanjkanje konkurenčnih in likvidnih trgov prodaje
električne energije na debelo. Sistemski operaterji prenosnega omrežja (SOPO) in sistemski
operaterji distribucijskega omrežja (SODO) v praksi še vedno niso bili vertikalno ločeni,
monopolistične situacije pa so še vedno predstavljale težave za nemoteno delovanje trga, saj
so onemogočale konkurenco (Thomas, 2006; Jakovac, 2012, str. 321). Z uvedbo tretje
direktive so se razmere na trgih električne energije v EU občutno izboljšale, saj so danes vsi
trgi liberalizirani, prisotna je večja transparentnost in zanesljivost. Stopnja konkurence je
občutno višja, prav tako pa so trgi bolj likvidni.
3
Ne glede na dosežke prestrukturiranja trgov električne energije v EU so prihodnji izzivi za
trge prodaje električne energije na drobno predvsem: heterogenost nacionalnih energetskih
politik, ki se odraža v raznolikosti cen električne energije znotraj EU (katerih sestavni del so
davki in dajatve za omrežje), nesodelovanje potrošnikov pri menjavi dobavitelja električne
energije in potreba po platformi, ki bi omogočala primerjavo cen v EU. Poudariti pa je
potrebno tudi pomembnost transparentnih računov, ki jih potrošniki prejmejo na dom (ACER,
2014).
Nekaj priložnosti za izboljšavo delovanja trga je tudi na trgih prodaje električne energije na
debelo. Za namen integracije nacionalnih trgov, na poti do notranjega trga električne energije
EU, so se izoblikovali regionalni trgi. Ti so sestavljeni iz držav, ki jih druži predvsem
podobno ekonomsko in politično okolje. Oblikovanih je sedem regionalnih trgov, ki
združujejo delovanje NRA, komisije in SOPO-ov. Tako imenovane Regionalne iniciative (RI)
prinašajo izmenjavo informacij in dobrih praks kot tudi implementacijo Kodeksov omrežja
(ACER, 2013, str. 16). ACER želi na regionalnih trgih doseči implementacijo štirih ciljnih
modelov, ki bi izboljšali čezmejno sodelovanje in integracijo trgov. Ti modeli se navezujejo
na spajanje trgov, trgovanje znotraj dneva, dolgoročne čezmejne prenosne zmogljivosti (ČPZ)
in metode za izračun kapacitet. Pozitivni učinki uvedbe teh modelov so predvsem učinkovita
uporaba ČPZ in zvišanje konvergence cen električne energije na debelo (ACER/CEER, 2014,
str. 16). V prihodnje se torej pričakuje implementacija ciljnih modelov na vseh regionalnih
trgih na debelo.
Poleg sedmih regionalnih trgov pa je nastala tudi tako imenovana osma regija ali regija
Jugovzhodne Evrope (regija SEE). Države SEE združujejo podobni energetski problemi, kot
so: majhni energetski trgi, energetsko intenzivna gospodarstva, slaba infrastruktura in
razlikovanje nacionalnih energetskih politik od politik EU (Karova, 2011, str. 81). Države
SEE so vse podpisnice Energetske skupnosti (ang. Energy Community) (Albanija, Bosna in
Hercegovina, Makedonija, Kosovo, Moldavija, Črna gora, Srbija in Ukrajina), poleg pa so še
sosednje države članice EU (Bolgarija, Hrvaška, Grčija, Italija, Madžarska, Romunija in
Slovenija). Gruzija ima status kandidatke, medtem ko imajo Turčija, Armenija in Norveška
status opazovalke (Energy Community, 2014).
Turčija je šestnajsto največje gospodarstvo na svetu in šesto največje gospodarstvo v
primerjavi z EU v 2013. V letu 2013 je bil njen BDP 820 milijarde USD, populacija pa 76,7
milijonov ljudi z 1,12-odstotno stopnjo rasti (Invest in Turkey, 2014; TurkStat, 2014). Glavna
razloga za visoko povpraševanje po energiji v Turčiji sta torej naraščajoč BDP in naraščajoča
populacija. Slednja naj bi po ocenah dosegla 84 milijonov do leta 2023. Zaradi naraščajočega
povpraševanja po električni energiji, ki temelji na industrializaciji in urbanizaciji, ima Turčija
enega od najhitreje rastočih trgov električne energije na svetu. Povpraševanje po električni
energiji se je v zadnjih desetih letih podvojilo. Leta 2000 je bilo povpraševanje 128 TWh, v
letu 2013 pa 246 TWh (Deloitte, 2014, str. 5; Statistical data, 2013).
V primerjavi z ostalimi državami regije SEE ima Turčija največjo proizvodnjo električne
energije, saj je v letu 2013 proizvedla približno 240 TWh (240.154 GWh), medtem ko je bila
proizvodnja v regiji SEE sledeča: Albanija (5.956 GWh), Bosna in Hercegovina (16.303
GWh), Makedonija (5.676 GWh), Moldavija (748 GWh), Črna gora (389 GWh) in Srbija
4
(27.537 GWh) (priloga C). Glede na to, da je likvidnost ena bistvenih komponent trgov za
trgovanje z električno energijo na debelo, Turčija pozitivno vpliva na regijo SEE, saj ji
povečuje likvidnost.
V preteklosti je na turškem trgu električne energije (kot tudi drugod po svetu) delovalo
vertikalno integrirano podjetje, monopolist na trgu z imenom Turkiye Elektrik Kurumu
(TEK). Ta je bil ustanovljen leta 1970 z namenom združitve proizvodnje, prenosa, distribucije
in dobave električne energije pod en integriran sistem. Kasneje je bil TEK ločen na dve
podjetji, TEAS (podjetje za proizvodnjo električne energije) in TEDAS (podjetje za
distribucijo, prenos in dobavo električne energije) (TEIAS, 2014).
Izvedenih je bilo veliko poskusov, ki bi lahko pritegnili zasebni kapital na trg, a v večini
primerov je bila privatizacija blokirana, ker država ni želela tujih investitorjev v tako strateški
industriji. Prisotnost zasebnega sektorja na trgu električne energije je bila omogočena šele v
letu 1984 z zakonom št. 3096, ki je vpeljal dva nova tipa pogodb na trg (Cetin in Oguz, 2007,
str. 1763):
- BOT (ang. Build-Operate-Transfer): S to pogodbo je zasebnemu podjetju podeljena
koncesija za izgradnjo in upravljanje elektrarne za obdobje do 99 let (kasneje skrajšano na
49 let). Po izteku tega obdobja se sredstva predajo državi, in sicer brez stroškov.
- TOR (ang. Transfer of operating rights): Ta pogodba omogoča zasebnemu podjetju, da
upravlja z že obstoječo elektrarno ali distribucijskim omrežjem, ki je v lasti države.
Z zakonom št. 4283 je bil vpeljan še en tip pogodbe, in sicer BOO (ang. Built-Operate-Own).
Ta pogodba se nanaša na termoelektrarne, in sicer je zasebnemu podjetju dodeljena licenca, s
katero lahko izgradi, upravlja in si na koncu tudi lasti elektrarno.
Zgoraj opisane pogodbe so imele veliko pomanjkljivosti, predvsem pa niso prispevale k
oblikovanju konkurence na trgu. Poleg tega je bil tu prisoten še vpliv iz tujine, predvsem s
strani mednarodnih institucij, kot so IMF, OECD in Svetovne banke. Le-te so poudarjale
potrebo po reformah na trgu električne energije v Turčiji. Ravno tako pa je reforma trga
električne energije eden od predpogojev za izpolnitev dolgoročnega cilja, in sicer članstva v
EU (Erdogdu, 2006, str. 986). Vsi ti sprožilci so pripeljali do prvih resnejših ukrepov, ki so
omogočali konkurenco na trgu.
Leta 2001 je bil sprejet zakon št. 4628, EML (ang. Electricity Market Law). Ta je prvi
pripeljal konkretne reforme na turški trg električne energije. Tako kot v drugih državah je
imela tudi Turčija kar nekaj težav z izhodom iz starega sistema delovanja. Sledil je
posodobljen zakon v letu 2008. Tudi za tem je ostalo kar nekaj pomanjkljivosti na trgu, zato
je bil leta 2013 sprejet zakon št. 6446, novi EML. Določbe zakonov so predstavljene v tabeli
2.
Kot je predstavljeno v tabeli 2, je turška zakonodaja sledila zgledu EU in skušala biti
usklajena s prakso EU. Proces prestrukturiranja trga z električno energijo je kompleksen in
dolgotrajen, zato so se spremembe na trg uvajale postopoma. Turčija je vzporedno z
določbami EML izvajala tudi privatizacijo državnih podjetij, zato je v letu 2008 začela s
privatizacijo proizvodnih enot (EUAS) in distribucijskih podjetij (TEDAS).
5
Tabela 2. EML 2001, 2008 in 2013
Določbe EML 2001
(in posodobitev v letu 2008) EML 2013
Vertikalna ločitev
državnih podjetij
TEAS je bil pravno ločen na TEIAS
(prenos), TETAS (trgovanje) in EUAS
(proizvodnja).
TEDAS je določen za distribucijo.
Sredstva TEDAS so privatizirana,
elektrarne EUAS pa so v procesu
privatizacije. Vsa podjetja, ki
imajo več kot eno licenco, morajo
imeti ločene računovodske
izkaze, distribucija in dobava pa
morata biti z 2016 popolnoma
ločeni (lastniško, upravljavsko).
Regulacija Ustanovljena EMRA (neodvisni
regulator).
EMRA
Trg električne
energije na debelo
Nov model delovanja: bilateralne
pogodbe in izravnalni trg z električno
energijo.
Nov model delovanja:
Ustanovitev EPIAS (borza za
trgovanje z električno energijo,
fizično), finančno trgovanje na
Borsa Istanbul, izravnalni trg pa
ima TEIAS.
Licence Nove licence: proizvodnja, prenos,
distribucija, dobava končnim kupcem,
proizvajalci, ki proizvajajo za lastno
rabo.
Nove licence: predhodna licenca
za proizvodnjo, licenca za oskrbo,
licenca za upravljanje trga. Poleg
navedenih so ostale še: licenca za
proizvodnjo, prenos, distribucijo.
Uporabniki Opredeljen je upravičen odjemalec. Vsi
ki porabijo več kot 9 GWh na letni
ravni.
Meja za upravičene odjemalce se
je znižala na 4500 kWh porabe na
leto, trenutno je trg odprt 85-
odstotno. V 2016 se pričakuje
100-odstotno odprtost.
Dostop do omrežja Regulirani TPA Regulirani TPA
Čezmejna trgovina Monopol državnih podjetij (TETAS,
TEIAS)
Sinhronizirana povezava z
omrežjem ENTSO-E (Bolgarija,
Grčija), omogočeno komercialno
čezmejno trgovanje, vsem
akterjem na trgu
Proizvodnja
(gradnja novih
proizvodnih
zmogljivosti)
Dovoljenje Dovoljenje
Vir: EMRA, Electricity Market Report 2010, n.d., str. 3; Atiyas et al., Competition and Regulatory Reform in the
Turkish Electricity Industry, 2012, str. 23; Electricity market law No.4628, Official Gazette No. 24335.
Najprej se je, v letu 2008, začela izvedba privatizacije distribucijskih podjetij. Turško
distribucijsko omrežje se je razdelilo na 21 regij. TEDAS je nato ustanovil 20 novih podjetij,
saj je bilo eno podjetje oziroma regija že predhodno v privatni lasti – Kayseri. Vsako podjetje
se je takrat obnašalo kot regionalni monopolist na svojem območju in je izvajalo tako
6
distribucijske aktivnosti kot samo dobavo električne energije. 18 podjetij je bilo privatiziranih
preko javni pisnih ponudb za nakup, ostali dve pa sta bili privatizirani v sklopu drugih
postopkov (Celen, 2013, str. 675 – 676). Privatizacija je bila izvedena z modelom TOR, torej
je TEDAS ostal lastnik distribucijskega omrežja, zasebno podjetje pa upravljalec omrežja.
Privatizirana podjetja so morala ustanoviti ločeno podjetje za izvajanje dobave električne
energije končnim potrošnikom, to dejavnost opravljajo z licenco za oskrbo. Za distribucijske
aktivnosti jim je bila dodeljena distribucijska licenca. Z letom 2016 pa se zahteva tudi fizična
ločitev delovanja, torej uporaba ločenih prostorov ter ločenih računovodskih in pravnih služb.
Uspešni privatizaciji distribucijskih podjetij je sledila privatizacija proizvodnih enot EUAS-a,
vendar je tu prišlo do zamud, zato je še danes veliko postopkov v teku. Kljub temu so bile
večje elektrarne privatizirane, in sicer: Kangal (457 MW), Kemerkoy (630 MW), Yenikoy
(420 MW), Catalgzi (300 MW), Hamitabat (1156 MW), Seyitomer (600 MW), Soma (990
MW), Orhaneli (210 MW), Tuncbilek (365 MW).
V nadaljevanju sledi pregled trenutnega delovanja trga v obdobju po reformah in privatizaciji.
Proizvodnja električne energije
Z vidika lastništva je na trgu proizvodnje pet vrst akterjev, in sicer: državno podjetje EUAS,
podjetja ki delujejo s pogodbami BOO in BOT, podjetja, ki delujejo s pogodbami TOR,
neodvisni proizvajalci in proizvajalci, ki proizvajajo za lastno rabo. Velik igralec na trgu je še
vedno EUAS, čeprav se situacija spreminja. Od privatizacijskih postopkov, ki so še v teku, pa
pričakujejo večjo prisotnost zasebnih podjetij na trgu. Poleg tega pa so vse novo izgrajene
elektrarne v letu 2013 v lasti zasebnikov, in sicer gre za približno 7000 MW nameščenih
zmogljivosti (MENR, 2014).
V letu 2013 je skupna proizvodnja električne energije v Turčiji znašala 240 TWh. Večina
električne energije je bila proizvedena iz zemeljskega plina (105 TWh), sledita premog (64
TWh) in voda (59 TWh). Manjši delež v proizvodnji predstavljata veter (8 TWh) in
geotermalna energija (1 TWh) (Electricity generation & transmission statistics of Turkey for
year 2013, 2014).
44 % električne energije v Turčiji je proizvedene iz zemeljskega plina. Ta je večinoma uvožen
iz Alžirije, Nigerije, Irana, Azerbajdžana in Rusije. Največji pogodbeni partner je ravno
Rusija, s katero je podpisana dobava skupno 30 bcm na leto, in sicer do leta 2025. Odvisnost
od uvoza zemeljskega plina je zaskrbljujoča, saj povezanost med trgoma vpliva na cene
električne energije (Botas, 2014). Na primer: ko postane dobava zemeljskega plina omejena,
je pričakovan dvig cene na trgih električne energije. Takšen primer se je zgodil 13. 2. 2012,
ko se je zaradi težkih vremenskih pogojev znižala dobava plina iz Azerbajdžana in Irana, na
drugi strani pa se je močno dvignila domača potrošnja. Posledično so imele termoelektrarne
težave pri proizvodnji, cena na trgih z električno energijo pa je dosegla 2000 TL/MWh, kar je
desetkrat višje od povprečnih cen (Camdan in Kolmek, 2013, str. 68). Zaradi opisanega je
dolgoročni cilj Turčije zmanjšati odvisnost od uvoza in doseči večjo konkurenco na trgu
plina.
7
Drugi največji vir proizvodnje je premog (26 % v letu 2013). Turčija ima bogate vire lignita,
ki prispevajo 75 % k celotni oskrbi z premogom. Črni premog pa se nahaja samo v regiji
Zonguldak, kjer je državno podjetje TTK monopolist pri pridobivanju in distribuciji le-tega
(EUROCOAL, 2015).
Eden izmed zelo pomembnih virov za proizvodnjo električne energije pa je tudi voda. Turčija
ima bogate vodne vire, njen potencial vodne energije naj bi bil 140 milijarde kWh na leto, le
35 % tega potenciala pa je dejansko izkoriščenega. V letu 2013 je bila skupna nameščena
zmogljivost 467 hidroelektrarn, to je 22.289 MW. Leta 2006 je bilo v Turčiji nameščenih le
13,1 GW zmogljivosti, medtem ko se je v letu 2013 številka dvignila na 22,3 GW.
Dolgoročno ima Turčija namen namestiti 180 GW skupnih zmogljivosti hidroelektrarn (do
leta 2030).
Za zagotovitev diverzifikacije svojih virov proizvodnje pa se Turčija zanaša tudi na ostale
obnovljive vire energije, predvsem na veter, sonce, geotermalno energijo in biomaso. Cilji za
leto 2030 so, da bi imeli nameščenih 40 GW vetrnih, 4,2 GW geotermalnih in 10 GW sončnih
zmogljivosti ter 2,2 GW biomase (Yuksel, 2013, str. 1040). Da bi se zmanjšala odvisnost od
uvoženega zemeljskega plina, načrtuje Turčija tudi izgradnjo dveh nuklearnih elektrarn s
skupno zmogljivostjo 9280 MW, do leta 2020 pa naj bi se 5 % električne energije proizvedlo
z nuklearno energijo (MENR, 2014).
Prenos električne energije
Oskrba prenosnega omrežja in ostale aktivnosti, povezane z omrežjem, so odgovornost
državnega podjetja TEIAS (TEIAS, 2014). Turčija ima 51.344 km daljnovodov, povezana je z
Grčijo, Bolgarijo, Gruzijo, Iranom, Irakom in s Sirijo. Najpomembnejši povezavi sta Grčija in
Bolgarija, saj je preko njiju Turčija povezana z omrežjem ENTSO-E, kar ji omogoča
trgovanje z državami regije SEE.
Turčija je neto uvoznik električne energije. V letu 2013 je namreč uvozila preko 14.000 GWh
električne energije, izvozila pa le nekaj več kot 2.000 GWh. V preteklosti, pred povezavo z
ENTSO-E, je bila neto izvoznik (do leta 2011). Ena izmed zanimivih povezav za Turčijo je
tudi Gruzija, predvsem zaradi bogatih obnovljivih virov, ki se nahajajo v tej državi, in pa
zaradi visokega povpraševanja po električni energiji v Turčiji (Deloitte Consulting, 2014, str.
2).
Veleprodajni trg električne energije
Trg električne energije na debelo je v fazi razvoja, pričakovati je namreč spremembe,
predvsem z začetkom delovanja EPIAS-a. Trenutno trg deluje na dveh ravneh, ena je trg za
bilateralne pogodbe, druga je izravnalni trg. Pomemben akter na trgu je državni TETAS, ki s
starimi pogodbami z EUAS-om in s podjetji, ki delujejo s pogodbami BOO, zavzema velik
tržni delež. V letu 2013 je imel preko 50 % celotnega nakupa in prodaje na trgu, medtem ko
so se čezmejne aktivnosti TETAS-a zmanjšale zaradi komercialnih avkcij ČPZ.
Poleg fizičnega trgovanja z električno energijo, ki vključuje fizično dobavo električne
energije, pa obstajajo tudi finančni trgi, ki služijo za zavarovanje, predvsem pred cenovnimi
8
tveganji na trgu. Finančno trgovanje z električno energijo se je v Turčiji začelo šele v letu
2011 na TurkDex (ang. Turkish Derivatives Exchange), kasneje pa se je trgovanje prestavilo
na Istanbulsko borzo (Borsa Istanbul).
V letu 2012 je bil celoten volumen trgovanja na Istanbulski borzi 62 milijonov pogodb, s
skupno vrednostjo 200 milijard USD. V istem letu je bil volumen trgovanja s terminskimi
pogodbami za električno energijo le 928 pogodb z vrednostjo 9,5 milijonov USD (Borsa
Istanbul, 2013). Te vrste pogodb ne pritegnejo dovolj interesa, predvsem zato, ker investitorji
menijo, da cene na trgu ne odražajo realnega ravnovesja ponudbe in povpraševanja (Bademli,
2013).
Kar se tiče veleprodajnih cen na turškem trgu električne energije, so v povprečju višje kot
tiste v regijah SEE in CEE (DG Energy – Market Observatory for energy, 2014, str. 10). V
Turčiji je kar nekaj dejavnikov, ki vplivajo na veleprodajne cene. Vreme vpliva tako na
ponudbo kot tudi na povpraševanje po električni energiji. Ko so poletja vroča, se zaradi večje
uporabe klimatskih naprav poveča povpraševanje po električni energiji. Enak učinek imajo
tudi hladne zime, ki povzročijo večjo uporabo naprav za ogrevanje. Vreme sicer vpliva tudi
na nivo ponudbe, predvsem na trgih, kjer je velik delež obnovljivih virov energije. V Turčiji
tako lahko vpliva na proizvodnjo v hidroelektrarnah in na vetrno proizvodnjo. Velik vpliv
predstavljata tudi odvisnost od uvoženega zemeljskega plina in slabo razvita konkurenca na
trgu plina. Uvozne pogodbe so drage, cene na trgu plina pa zaradi slabe razvitosti trga
nekonkurenčne. Poleg navedenega se v času verskih praznikov, kot je na primer bajram,
povpraševanje zelo zmanjša, kar lahko pripelje tudi do cene 0 TL/MWh v določenih urah
dneva. Za Turčijo so značilne tudi visoke izgube v omrežjih, ki posredno vplivajo na
veleprodajne in maloprodajne cene električne energije.
Distribucija in dobava električne energije končnim potrošnikom
Distribucijska dejavnost je ločena od dejavnosti dobave električne energije šele od leta 2013.
V državi je 21 distribucijskih regij, v vsaki je eno podjetje z distribucijsko licenco, ki upravlja
omrežje. Ne glede na to pa je država (TEDAS) še vedno lastnik omrežja.
Največja težava, s katero se spoprijemajo podjetja za distribucijo in posledično tudi podjetja
za dobavo, so visoke izgube električne energije v distribucijskem omrežju. Med regijami so
velike razlike v izgubah, najbolj težavni pa sta Dicle s 75-odstotnimi in Vangolu s 55-
odstotnimi izgubami v letu 2012. Izgube v ostalih regijah znašajo v povprečju okrog 10 % ali
manj. Gre predvsem za tehnične izgube in krajo električne energije iz omrežja (Cetinkaya et
al., 2015 b). Skupaj z izgubami pa obstaja še dodaten problem, in sicer neprimerne tarifne
strukture. V Turčiji je v veljavi mehanizem izenačevanja (ang. equalization mechanism), kar
pomeni, da je končna tarifa enake za vse regije. Stroške regij posledično - z visokimi
izgubami - financirajo regije, ki imajo nizke izgube. Takšna politika je dolgoročno
nesprejemljiva, kljub temu da trenutno zadovoljuje podjetja, ki so veliko investirala v procesu
privatizacije (Cetinkaya et al., 2015a, str. 12). Spremembe pričakujejo v letu 2016, ko naj bi
bil mehanizem izenačevanja ukinjen.
9
Za neupravičene odjemalce so cene regulirane, medtem ko so cene za upravičene odjemalce
(tisti, ki imajo potrošnjo vsaj 4500 kWh na leto) svobodno izpogajane med kupcem in
prodajalcem (Atiyas et al., 2012, str. 26).
Cena električne energije pa je le sestavni del končne maloprodajne cene, ki jo plača potrošnik.
Cena električne energije torej predstavlja 57 % računa za električno energijo, 23 % gre za
dajatve za omrežje, preostalih 20 % pa so davki. Ti davki so: DDV, davek na porabo
električne energije in davek TRT – Radio in televizija (European Commission, 2014, str.
183).
V povprečju so turške maloprodajne cene tako za gospodinjstva kot tudi za industrijske
odjemalce malo pod povprečjem EU 28. V zadnjih treh letih pa lahko opazimo tudi upadanje
maloprodajnih cen v Turčiji. Za gospodinjske odjemalce so v letu 2012 cene padle z 0,11065
€/kWh na 0,09975 €/kWh. Za industrijske odjemalce pa so cene padle z 0,0876 €/kWh, na
0,07495 €/kWh (Eurostat – Energy price statistics, 2014).
Kljub napredkom na trgu električne energije v Turčiji čaka državo še kar nekaj dela in izzivov
v prihodnosti, da bi lahko zagotovila višji nivo konkurence na trgu in večjo transparentnost
oziroma zaupanje trgu. Komisija EU predvsem opozarja, da so potrebne izboljšave na
področju cen (neprimerne tarife), zaključek privatizacijskih postopkov, več transparentnosti in
seveda 100-odstotna odprtost trga (European Comission, 2014 b, str. 28).
10
APPENDIX B: List of abbreviations
Abbreviation Definition
ACER Agency for the Cooperation of Energy
Regulators
BOO Build – operate – own
BOT Build – operate – transfer
BOTAS Petroleum Pipeline Corporation
CEE region Central East European region
DSO Distribution system operator
EML Electricity Market Law
EMRA Energy Market Regulatory Authority
ENTSO-E European Network of Transmission System
Operators for Electricity
EPC European Price Coupling
EPIAS Energy Markets Operation Joint Stock Company
ERGEG European Regulators’ Group for Electricity and
Gas
ERI Electricity Regional Initiative
EU European Union
EUAS Electricity Generation Company
GDP Gross domestic product
IEM Internal energy market
MCP Market clearing price
MENR Ministry of Eenergy and Natural Resources
MFSC Market Financial Settlement Centre (tr. PMUM)
NLDC National Load Dispatch Centre (tr. MYTM)
NRA National Regulatory Authorities
nTPA / rTPA Negotiated third-party access / Regulated third-
party access
SEE region South East Europe region
SMP System marginal price
TEAS Turkish Electricity Generation Company (before
EUAS)
TEDAS Turkish Electricity Distribution Company
11
TEIAS Turkish Electricity Transmission Company
TEK Turkish Electricity Authority
TETAS Turkish Electricity Trading and Contracting
Company
TOR Transfer of operating rights
TPC Transition period contracts
TSO Transmission system operator
APPENDIX C: Table illustrating the Turkish electricity market and selected SEE
electricity markets (the Energy Community Contracting Parties)
Country Electricity generation / Gross
electricity consumed / Total
electricity customers
Installed capacity by energy sources in 2013
(%)
Turkey 240,154 GWh /
194,923 GWh /
66,505,050
Albania 5,956 GWh /
7,957 GWh /
1,161,626
Bosnia and
Herzegovina
16,303 GWh /
11,088 GWh /
1,492,215
Oil;
5.2
Hydro;
94.8
[CATEG
ORY
NAM…
[CATEG
ORY
NAM…
[CATEG
ORY
NAM…
[CATEG
ORY
NAM…
[CATEG
ORY
NAM…
[CATE
GORY
NAM…
[CATE
GORY
NAM…
[CATE
GORY
NAM…
12
Coal; 41
Gas; 15
Oil; 11
Hydro;
33
Renewabl
es 0
Former
Yugoslav
Republic of
Macedonia
5,676 GWh /
6,989 GWh /
682,356
Moldova 748 GWh /
3,551 GWh /
1,319,706
Montenegro 3,809 GWh /
3,323 GWh /
378,073
100; Hydro
Table continues
continued
Country Electricity generation / Gross
electricity consumed / Total
electricity customers
Installed capacity by energy sources in 2013
(%)
Serbia 37,537 GWh /
27,998 GWh /
3,580,579
Source: Electricity generation & transmission statistics of Turkey for year 2013, 2014; Energy Community
Secretariat, Annual Implementation Report 2013/2014, 2014.
[CATEG
ORY
NAM…
[CATEG
ORY
NAM…
[CATEG
ORY
NAM…
[CATEG
ORY
NAM… Gas; 5
Hydro;
40.2
Renewa
bles; 0.1
13
APPENDIX D: Table of feed in tariffs (for selected countries)
Country Feed-in-tariff wind Feed-in-tariff hydro Feed-in-tariff geothermal
Turkey On and offshore: approx. €ct 5.3 per kWh
Local-content bonus: approx. €ct 0.4-2.7 per kWh
Feed-in tariff: approx. €ct 5.6 per
kWh
Local-content bonus: approx. €ct
0.7-1.8 per kWh
Feed-in tariff: approx. €ct 8.1 per
kWh)
Local-content bonus: approx. €ct
0.5-2.1 per kWh
Denmark Onshore: €ct 4.95 – 8.90 per kWh (according to duration of payment) (§ 49 par. 1
EEG 2014) minus €ct 0.4 per kWh
Offshore: €ct 3.9 – 19.4 per kWh (according to duration of payment and scheme
chosen by plant operator) (§ 50 par. 1-3 EEG 2014) minus €ct 0.4 per kWh (§ 37
par. 3 no. 2 EEG 2014).
/ /
Greece NS=no support,
WS= with
support of
government
(fiscal,
financial,
subsidy)
Wind Interconnected systems Non-interconnected islands
€/MWh NS WS WS
up to 5 MW 105 85 90
> 5MW 105 82 90
Hydro NS WS
up to 1 MW 105 85
1 MW-5 MW 105 83
5 MW-15 MW 100 80
€/MWh NS WS
Low-
temperat
ure
(between
25°C -
90°C)
143 130
High-
temperat
ure
(above
90°C)
110 100
Hungary Wind power plants over 50 kVA can be connected to the grid only if there is a call
for tender. The tariff is set by the result of the tender.
Plants below 5 MW:
peak period: approx. € 0.12
valley period: approx. € 0.10
deep-valley period: approx. € 0.04
Plants of more than 5 MW
peak period: HUF 22.58 per kWh
(approx. € 0.07)
valley period: HUF 14.45 per kWh
(approx. € 0.05)
deep-valley period: HUF 14.45 per
kWh (approx. € 0.05)
Plants below 20 MW:
peak period: approx. € 0.12
valley period: approx. € 0.10
deep-valley period: approx. €
0.04
Plants between 20 and 50 MW:
peak period: approx. € 0.09
valley period: approx. € 0.08
deep-valley period: approx. €
0.03
14
Plants of more than 50 MW
peak period: approx. € 0.07
valley period: approx. € 0.05
deep-valley period: approx. €
0.05
Slovenia The uniform annual price is €ct 9.538 per kWh for all plant sizes Uniform annual price: €ct 9.261 –
10.547 per kWh, depending on the
capacity of the plant.
Uniform annual price: €ct 15.247
per kWh.
Great
Britain
Capacity GBP per kWh
≤ 1.5kW 0.16 (approx. 0.2 €/kWh)
1.5 kW - 15 kW 0.16 (approx. 0.2 €/kWh)
15kW - 100kW 0.16 (approx. 0.2 €/kWh)
100kW - 500kW 0.1334 (approx. 0.17 €/kWh)
500kW - 1.5MW 0.0724 (approx. 0.092 €/kWh)
> 1.5MW 0.0307 (approx. 0.039 €/kWh)
Capacity GBP per kWh
up to
15kW
0.1901 (approx. 0.2411
€/kWh)
15kW -
100kW
0.1775 (approx. 0.2252
€/kWh)
100kW -
500kW
0.1403 (approx. 0.1780
€/kWh)
500kW-
2MW
0.1096 (approx. 0.1390
€/kWh)
> 2MW 0.0299 (approx. 0.0379
€/kWh)
/
15
Source: Legal sources on renewable energy, 2015.
Portugal Indicative average rate for existing installations is € 74-75 per MWh. For existing traditional hydro
power plants (up to 10 MW), the
indicative average rate is € 91-95
per MWh.
For existing wave hydro power
plants (pilot-projects) up to 4 MW,
the indicative average rate is € 260
per MWh.
Plants (pre-commercial) up to
20MW: Indicative average rate: €
191 per MWh.
Commercial plants: Indicative
average rate: € 131 per MWh for
the first 100MW and € 101 per
MWh for the subsequent 150MW
For existing installations (i.e.
plants up to 3 MW), the
Indicative average rate is € 270
per MWh.
Croatia / For capacities below 5 MW:
≤ 300 kW: approx. €ct 13.9 per
kWh
> 300 kW and ≤ 2 MW: approx.
€ct 12.1 per kWh
> 2 MW: approx. €ct 11.4 per kWh
For capacities above 5 MW the
amount of the tariff depends on the
reference price
The tariff amounts to approx. €ct
15.6.
16
APPENDIX E: Transmission lines in Turkey
Source: Entose, 2014