Centro de Estudos e Sistemas Avançados do Recife

PMBOK - Chapter 4

Project Integration Management

Page 2: Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management

Contents

Introduction to Project Integration Management Project Plan Development Project Plan Execution Integrated Change Control Glossary

Page 3: Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management

Introduction to Project Integration Management

Includes processes required to ensure that the various elements of the project are properly coordinated.

Making tradeoffs

meet or exceed stakeholders needs

and expectations

competitive objectives and alternatives

Page 4: Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management

Carrying out the project plan

Integrating and coordinating project plans: creating a consistent and coherent document

Coordinating changes across the entire project

Introduction to Project Integration Management

Major processes of Project Integration Management

Project Plan Development

Project Plan Execution

Integrated Change Control

Page 5: Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management

Some characteristics of these processes– They are primarily integrative

– They interact with each other and with the processes in the other knowledge areas

– They occur at least once in every project phase

– They may overlap

Focus of this chapter– Processes, tools and techniques used to integrate these

processes

Introduction to Project Integration Management

Page 6: Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management

Project Integration Management Overview

Project Plan Execution

Integrated Change Control

Project IntegrationManagement

InputsTools and TechniquesOutputs

Project Plan Development

Page 7: Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management

Create a consistent and coherent document that can be used to guide both project execution and project control

This process is almost always iterated several times– Capture and decompose the work of the project: Work

Breakdown Structure (WBS)

– The defined work is planned, estimated and scheduled, and authorized: Control Account Plans (CAPs)

Project Plan Development

The sum of all the integrated management control planswill constitute the total project scope

Page 8: Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management

Project Plan is used to– Guide project execution

– Document project planning assumptions

– Document project planning decisions regarding alternative chosen

– Facilitate communication among stakeholders

– Define key management reviews as to content, extent and timing

– Provide a baseline for progress measurement and project control

Project Plan Development

Page 9: Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management

Other planning outputs – in the other knowledge areas

– base documents, such as WBS

– application area-specific inputs Historical information Organizational policies

– Quality management

– Personnel administration

– Financial controls

Project Plan Development - Inputs

Page 10: Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management

Constraints– Applicable restriction that will affect the performance of the

project Assumptions

– Factors that are considered to be true, real or certain, for planning purposes

– Generally involve a degree of risk

Project Plan Development - Inputs

Page 11: Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management

Project planning methodology– structured approach used to guide project team during

development of the project plan

– it can be simple or complex

– makes use of hard and soft tools Stakeholder skills and knowledge

– environment in which stakeholders can contribute appropriately

Project Plan Development - Tools and Techniques

Page 12: Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management

Project management information system (PMIS)– tools and techniques used to gather, integrate and

disseminate the outputs of project management processes

– from initiating through closing

– manual and automated systems Earned value management (EVM)

– Integrates project’s scope, schedule and resources

– Measures and reports project performance

Project Plan Development - Tools and Techniques

Page 13: Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management

Project plan– formal and approved document used to guide both project

execution and project control

– It may be summary or detailed

– the same as Integrated project plan, in some application areas

– Project plan X Project performance measurement baselines Supporting details

Project Plan Development - Outputs

Page 14: Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management

InputsTools and TechniquesOutputs

Project Integration Management Overview

Project Plan Execution

Integrated Change Control

Project IntegrationManagement

Project Plan Development

Page 15: Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management

Some characteristics of this process– Primary process for carrying out the project plan

– The vast majority of the project’s budget is expended in performing this process

– It is the project process that is most directly affected by the project application area

– Performance against the project baseline must be continuously monitored

Corrective actions Periodic forecast of the final cost and schedule results

Project Plan Execution

Page 16: Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management

Project plan and supporting details– Output of the project plan development process

Organizational policies– It is also Input to the project plan development process

Preventive action– Anything that reduces the probability of potential

consequences of project risk events Corrective action

– Anything done to bring expected future project performance in line with the project plan

– Output of the various control processes

Project Plan Execution - Inputs

Page 17: Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management

General management skills– Essential to effective project plan execution

Product skills and knowledge Work authorization systems

– Formal procedure for sanctioning project work to ensure that work is done at the right time and in the proper sequence

– Value of the control X Cost of the control

Project Plan Execution - Tools and Techniques

Page 18: Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management

Status review meetings– They will be held at various frequencies and on different

levels Project management information system (PMIS) Organizational procedures

Project Plan Execution - Tools and Techniques

Page 19: Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management

Work results– Information on work results is collected and fed into the

performance reporting process

– Tangible and intangibles deliverables Change requests

Project Plan Execution - Outputs

Page 20: Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management

InputsTools and TechniquesOutputs

Project Integration Management Overview

Project Plan Execution

Integrated Change Control

Project IntegrationManagement

Project Plan Development

Page 21: Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management

This process is concerned with– Influencing the factors that create changes to ensure that

changes are agreed upon

– Determining that a change has occurred

– Managing the actual changes when and as they occur It requires

– Maintaining the integrity of the performance measurement baselines

– Ensuring that changes to the project scope are reflected in the definition of the project scope

– Coordinating changes across knowledge areas

Integrated Change Control

Page 22: Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management

Project plan– Provides the baseline against which changes will be

controlled Performance reports

– Provide information on project performance Change requests

– Oral / Written

– Direct / Indirect

– Externally / Internally initiated

– Legally mandated / Optional

Integrated Change Control - Inputs

Page 23: Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management

Change control system– Collection of formal and documented procedures that define

how project performance will be monitored and evaluated

– Includes the steps by which official project documents may be changed

– Some characteristics Group responsible to approving or rejecting proposed

changes Procedures to handle changes that may be approved

without prior review

Integrated Change Control - Tools and Techniques

Page 24: Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management

Configuration management Performance measurement Additional planning

– Projects seldom run exactly according to plan Project management information system (PMIS)

Integrated Change Control - Tools and Techniques

Page 25: Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management

Project plan updates Corrective action Lessons learned

– Include causes of variances, reasoning behind the corrective action chosen and other types of lessons learned should be documented

Integrated Change Control - Outputs

Page 26: Centro de Estudos e Sistemas Avançados do Recife PMBOK - Chapter 4 Project Integration Management

Assumptions and Constraints Baseline Control Account Plans (CAPs) Earned Value Management (EVM) Earned Value (EV) Project charter Project management information system (PMIS) Project management software Project plan Work Breakdown Structure (WBS)

Glossary