ch 7 qm
DESCRIPTION
TRANSCRIPT
1
CHAPTER 7
QM PILLAR
Contents
7.1 Objective Background and aim
7.1.1 Vision and Goal
7.1.2 Targets and Master Plan
7.2 QM Approach and Concept
7.2.1 QM Defect Identification
7.2.2 QA & QM Matrix\
7.2.3 Defect Reduction Activities
7.3 KAI Cumulative Trends
7.4 QM Results
7.5 QM Future Plan
MR.BALAJI
1
QM PILLAR CHAIRMAN
2
TPM ACTIVITY
REPORTSub Title : AFTER PRE AUDIT , QM ACTIVITY FLOW
Slide Title : 7 QM PILLAR
Vision & Goal
KMI / KPI / KAIKMI / KPI / KAIKMI / KPI / KAI
Organization Chart
Back Ground
QM Target
QM Master Plan
Type of defects
QA / QM Matrix
Assessor Observation and
Background
New Addition
New Addition
New Addition
New Addition
A
3
TPM ACTIVITY
REPORTSub Title : AFTER PRE AUDIT , QM ACTIVITY FLOW
Slide Title : 7 QM PILLAR
A
Defect reduction
4M Condition
Q Component
PM analysis
Kaizen Samples
KK Results
Future Plan
Case studyNew Kaizen added
Improvement after pre assessment
New addition after pre audit
Assessor Comments and Countermeasures
Updated
New Addition
New Addition
4
TPM ACTIVITY
REPORTSub Title : 7.1.1 VISION AND GOAL
Slide Title : 7 QM PILLAR
VISION AND GOAL
VISION (KMI) GOAL (KPI) KAI ResponsibilityPrimary / Secondary
P – Enhance Productivity
Q – Meet Quality
C – Reduce Cost
D – On time
S – Environment
M – High for Employees QM / PM
QM / SHE
QM / PM
QM / PM
QM / AM
QM / PM
TO GROW BUISSNESS
WITH DIGNITY AND
RESPECT INTEGRITY
CUSTOMER LOYALTY
CONTINUAL IMP
IMPROVEMENT AND INNOVATION
UNCOMPROMISING QUALITY EMPOWERMENT TO INDIVIDUALS
5
TPM ACTIVITY
REPORTSub Title : 7.1.2 QM PILLAR ORGANISATION CHART
Slide Title : 7 QM PILLAR
7.1.2 - QM PILLAR ORGANISATION CHART
C
PILLAR CHAIRMANMR.BALAJI New members
6
TPM ACTIVITY
REPORTSub Title : 7.1.3 - QM PILLAR Background
7.1.3 - QM PILLAR Background
Slide Title : 7 QM PILLAR
Assessor Comments: 1. How many people really understood on QM Concept?2. What is the time taken for all the quality testing and what is the time reduction done need to be identified
7
TPM ACTIVITY
REPORTSub Title : 7.1.4 - QM TARGETS
7.1.4 - QM TARGETS
Slide Title : 7 QM PILLAR
After pre audit – new targets
8
TPM ACTIVITY
REPORTSub Title : 7.1.5 - MASTER PLAN
7.1.5 - MASTER PLAN
Slide Title : 7 QM PILLAR
C
After pre audit – New process included - Welding
9
TPM ACTIVITY
REPORTSub Title : 7.2.1- QM PILLAR CONCEPT
7.2.1- QM PILLAR CONCEPT
Input Raw Materials
Inspection Send back to supplier
Process
O/p Products
Inspection
Dispatch to Customer
CustomerProblem if any
Investigation / Analysis
Kaizen / Countermeasures
Update 4M Conditions
ok
Defect
Man
Method
Material
Machine
Monitor 4M Conditions
DO NOT SEND A DEFECT
DO NOT PRODUCE A DEFECT
DO NOT ACCEPT A DEFECT
Not ok
ok
Not ok
QA Activities
QM Activities
Input Raw Materials
Inspection
Slide Title : 7 QM PILLAR
10
TPM ACTIVITY
REPORTSub Title : 7.2.2 - CONCEPT QC, QA, QM
Slide Title : 7 QM PILLAR
7.2.2 - CONCEPT QC , QA , QM
Input control Output control No control
Maintaining 4M basic conditions Re-setting process conditions No control mechanism
Zero defects Few defects More defects
By Operator By Operator By QC inspector
Continuous monitoring of 4M conditions
Periodic sample inspection of products Extensive inspection of products
Defect PreventionDefect DetectionDefect Detection
On-line InspectionOn-line InspectionOff-line Inspection
Quality Maintenance (QM)Quality Assurance (QA)Quality Control (QC)
AFTER TPMBEFORE TPM
After pre audit – Zero flash improvements
11
TPM ACTIVITY
REPORTSub Title : 7.2.3 – STATUS BEFORE / AFTER TPM IMPLEMENTATION
Slide Title : 7 QM PILLAR
7.2.3 – STATUS BEFORE / AFTER TPM IMPLEMENTATION
S. No.
DESCRIPTION
BEFORE TPM IMPLEMENTION
AFTER TPM IMPLEMENTION
BENCH MARK PRESENT STATUS TARGETUPTO 2005
( QC CONCEPT )
2006 - 2009
( QA CONCEPT )
2010 - 2011 ( QM
CONCEPT )
1Customer complaint
More, No Clear
Structure For Approach
Few, Clear Structure For
ApproachNo
2 Quality Defects
3Control
MechanismNo Approach Reactive Approach Pro active Approach
4Understanding of
DefectsNo understanding Defect Phenomena
Action plan for eliminating chronic
defects.
5Defects
Identifications QC Inspector Plant Supervisor Plant Operator
6 Quality skill QC Department Supervisor Operator
7Quality depends
on Inspector Functional heads Operator
8 Inspection OFF-Line OFF-Line
With Quick Measurement
ON -Line
OFF-LINE MEASUREMENT ON-LINE MEASUREMENT
12
TPM ACTIVITY
REPORT
7.2.4 - Step 1 : Preparation of QA matrix
Sub Title : 7.2.4 - Step 1 : Preparation of QA matrix
Slide Title : 7 QM PILLAR
Seriousness Past Occurrence
Đ Develop into major defects Δ Frequent
Ψ Reprocessing possible @ Occasional
Ø Not occurred
Đ
Đ
13
TPM ACTIVITY
REPORT
7.2.5 - Step 2 : Prepare production – input condition analysis table
Sub Title : 7.2.5 - Step 2 : Prepare production – input condition analysis table
Slide Title : 7 QM PILLAR
Target
LSL
USL
Adjustment
C – Type
First-Off Inspection
Stabilisation
First Piece of setting.
W/O Adj.
A – Type
ACTION TAKEN by the operator. Adjustment of the equipment / tools / jigs / fixtures to achieve stabilisation.
Measurement & Adjustment
1/3 of Tolerance
Caused during change overDue to inadequate setup procedures and lack of skills in fixturing & setting of equipments, tools, measuring instruments, etc. and also wrong selection of the above.
Stabilization
Mass production
B – Type
UCL
LCL
ACTION NOT TAKEN by the operator. No adjustments made.
Setting
Defect - Abnormal
Accepted - Normal
Target = (LSL+USL) / 2
Defect - Abnormal
Chance / Chronic Causes Identify root cause using PM analysis.
To
lera
nc
e
Assignable / Sporadic CausesIdentify root cause using Why-Why analysis.
14
TPM ACTIVITY
REPORTSub Title : 7.2.5.1 - TYPE OF DEFECTS
7.2.5.1 - TYPE OF DEFECTS
Slide Title : 7 QM PILLAR
After pre audit – defect type added
15
TPM ACTIVITY
REPORTSub Title : 7.2.5.2 - UNDERSTANDING OF QUALITY DEFECT
7.2.5.2 - UNDERSTANDING OF QUALITY DEFECT
Slide Title : 7 QM PILLAR
After pre audit – Zero flash improvements
16
TPM ACTIVITY
REPORT
7.2.5.3 - DEFECT REDUCTION ACTIVITIES
Sub Title : 7.2.5.3 DEFECT REDUCTION ACTIVITIES
Activities
• 4M Condition set for Major Defects • Why – Why Analysis done
• Counter measures Plan
• One Point Lesson
• Training
• Kaizens
• 4M Conditions Revisions plan
• Visual Control
• Poke - Yoke
0
200
400
600
800
1000
PPM 858 324 185 92
High wall thickness
Blow holes
Warpage Sink mark
0
100
200
300
400
500
600
PPM 482 215 92
Insufficient pressure
High Inj speed
High MB proportion
DEFECTWISE IND PRODUCT SCRAP PPM PARETO ANALYSIS : AVG JAN 2011 – SEP 2011
Split up of IND product Scrap Split up of high wall thickness
A type
High wall thickness dueto A type defect
Slide Title : 7 QM PILLAR
17
TPM ACTIVITY
REPORT
7.2.6 - Step 3: Prepare Problem chart
Sub Title : 7.2.6 - Step 3: Prepare Problem chart
Slide Title : 7 QM PILLAR
S.No. Details of Case Study Tools Used
1 Wall thickness variation in TT tub. PM Analysis
2 Gate point shift on Jumbo crates Why ? Why ? Analysis
3 Blow holes on TT tub. Why ? Why ? Analysis
4 Warpage on Rad tub. Why ? Why ? Analysis
18
TPM ACTIVITY
REPORT
7.2.7 - Step 4: Evaluate seriousness of problems ( FMEA 1)
Sub Title : 7.2.7 - Step 4: Evaluate seriousness of problems ( FMEA 1)
Slide Title : 7 QM PILLAR
19
TPM ACTIVITY
REPORT
7.2.8 - Step 5 : Use PM Analysis to track down causes of problemsGrasping Quality defect phenomena
Sub Title : 7.2.8 Step 5 : Use PM Analysis to track down causes of problems Grasping Quality defect phenomena
Slide Title : 7 QM PILLAR
PHENOMENA MECHANISM ANALYSIS FOR WALL THICKNESS
20
TPM ACTIVITY
REPORT
7.2.8.1 - STEP 5 – PHENOMENA MECHANISM ANALYSIS FOR WALLTHICKNESS
Sub Title : 7.2.8.1 - STEP 5 – PHENOMENA MECHANISM ANALYSIS FOR WALL THICKNESS
Slide Title : 7 QM PILLAR
S No. Contributing Condition Primary 4M Condition Secondary 4M Condition
a) MB Dosageb) Weighta) RM Mixb) End of Speed drop
3) Consistent Pressure Drop pressure setup Pressure Saturation
Setting speed
Mixing ratio1)
2)
Higher Master batch proportion
Higher Injection Speed
21
TPM ACTIVITY
REPORT
7.2.9 – STEP 6: Assess impact of the countermeasures taken (FMEA 2)
Sub Title : 7.2.9 – STEP 6: Assess impact of the countermeasures taken (FMEA 2)
Slide Title : 7 QM PILLAR
FMEA OF VARIATION OF WALLTHICKNESS IN TT
22
TPM ACTIVITY
REPORTSub Title : 7.2.9.1 - QM MATRIX
7.2.9.1 - QM MATRIX
Slide Title : 7 QM PILLAR
After pre audit – QM Matrix revised for SSR part
23
TPM ACTIVITY
REPORT
7.2.9.2 - “ Q” COMPONENTS IN INJECTION MOLDING MACHINES
Slide Title : 7 QM PILLAR
Sub Title : 7.2.9.2 DEFECT REDUCTION ACTIVITIES
After pre audit – Mold manifold heater - Q Component added
24
TPM ACTIVITY
REPORT
7.2.9.3 - “ Q” COMPONENTS IN INJECTION MOLDING MACHINES
Slide Title : 7 QM PILLAR
Sub Title : 7.2.9.3 DEFECT REDUCTION ACTIVITIES
TOTAL Q COMPONENT – 8 NOS
MOLD Heater
After pre audit – Q component added
25
TPM ACTIVITY
REPORT
7.2.9.4 - DEFECT REDUCTION ACTIVITIES
Sub Title : 7.2.9.4 DEFECT REDUCTION ACTIVITIES
Slide Title : 7 QM PILLAR
360-370kgf.cm2
60- 80%
180 - 220oC
180 – 200 kg/cm2
4 – 5 mm
250 – 300 kg.cm2
120-150kgf.cm2
CONTROL VALUES
Flash
Shrink
Shortfill
Shrinkage
Shortfill
FLASH
FLASH
CONTROL QUALITY
Pressure Q 7
SpeedInjectInjection speed mmiQ 6
Temp of materialBarrel HeaterQ 5
PRESSUREInjection pressureQ 4
SIZENozzle IDQ 3
Plattern movingMoving plattern open / close
GaugeQ 2
Core pressureMold Core in / out gaugeQ 1
CONTROL
PARAMETERSCOMPONENT NAME
Progress
Injection speed
Mold locking gauge
Mold locking gauge
12 to 15 ohms FlashTemperature Q 8 Mold Heater
After pre audit – Q 8 added
26
TPM ACTIVITY
REPORTSub Title : 7.2.10 - STEP 7 – IMPLEMENT IMPROVEMENTS
Slide Title : 7 QM PILLAR
7.2.10 - STEP 7 – IMPLEMENT IMPROVEMENTS
Valve
seal Changed
Focus on seal by QM
Pillar
Oil to Inj mode
Oil Retraction
27
TPM ACTIVITY
REPORTSlide Title : 7 QM PILLAR
Sub Title : 7.2.10.1 - QM KAIZEN
7.2.10.1 - QM KAIZENAfter pre audit – Kaizen added
28
TPM ACTIVITY
REPORT
7.2.10.2 - DEFECT REDUCTION - OPL SAMPLE
Slide Title : 7 QM PILLAR
Sub Title : 7.2.10.2 DEFECT REDUCTION ACTIVITIES
After pre audit – OPL added
29
TPM ACTIVITY
REPORTSub Title : 7.2.11 - Step 8: Review production – input conditions
Table for Wall thickness
Slide Title : 7 QM PILLAR
7.2.11 - Step 8: Review production – input conditionsTable for Wall thickness
Quality test is performed
Quality test of R/D product is
performed every shift
Optimum blend ratio
implemented.
1300
Optimum material blend ratio,
Plant D
Material Machine Method
(man)Defect mode
Sub process
Main process
Th
ick
ne
ss
va
ria
tio
n
Ma
teri
al
mix
, p
ara
me
trs
In
pu
t c
on
dit
ion
Additivedosage
As per StandardStandard need improvement ? Standard need x Std Impossible to follow
30
TPM ACTIVITY
REPORT
7.2.11.1 - 4M CONDITION EXAMPLE
Slide Title : 7 QM PILLAR
Sub Title : 7.2.11.1 DEFECT REDUCTION ACTIVITIES
190 ± 10 kgf/cm2
After pre audit – PART added in 4M Condition
31
TPM ACTIVITY
REPORTSub Title : 7.2.12 - Step 9: Consolidate and confirm checkpoints
Quality Check Matrix
Slide Title : 7 QM PILLAR
7.2.12 - Step 9: Consolidate and confirm checkpointsQuality Check Matrix
Batch formation
Retain the inspection
Thickness
Seal
Every ShiftChecking interval
Right level of MixingStandard
PPCPCheck Item
Raw materials Equipment part
32
TPM ACTIVITY
REPORTSub Title : 7.2.12.1 DEFECT REDUCTION ACTIVITIES
Slide Title : 7 QM PILLAR
7.2.12.1 - TT Tub : QM Check sheet
TT Tub : QM Check sheet
Quality Component
Control Conditions
ConditionChecking
MethodChecking Standard
TT TUB
Injection Pressure GaugeInjection Pressure to with stand up
to full cycleThickness
Fall rate should be in permissible limits
(180 - 200 kg/cm2)
33
TPM ACTIVITY
REPORTSub Title : 7.2.12 DEFECT REDUCTION ACTIVITIES
Slide Title : 7 QM PILLAR
7.2.12 STEP 10 – Quality Component for wall thickness
Data are entered in Plant operating log Result
LaboratoryChecking method
Setting Speed and PressureChecking Standard
Per ShiftChecking interval
Quality Component : Seal, MB Mixing
34
TPM ACTIVITY
REPORTSub Title : 7.2.12 DEFECT REDUCTION ACTIVITIES
Slide Title : 7 QM PILLAR
Question & Answers
Question & Answer
Q 5.1: How many people really understood on QM
Concept?
Yokoo Kazuyuki san
Countermeasures - 83% of our members are aware of QM concept (our quality rate by
the customer is 99.7%). This is happened because of TPM way of quality improvement.
Our members understanding regarding the quality is based on input controls. They also
understood the Q component, process point and process characteristics. Our operators
jointly working with QM Pillar. The mindset of quality checking in finished product is
converted in to in-build quality process.
Gemba Q1: What is the time taken for all the quality
Testing and what is the time reduction done, need to be
Nakano Tsuneo san identified.
Countermeasures: As per assessor advice we started monitoring the time taken for
each and every testing process carried out the laboratory included with both raw
material and performance testing on products. So far there are four issues were taken
for higher time consuming and we reduced up to average time of around 30minutes
from existing around 1 hr.
Pre audit Assessor Comments
35
TPM ACTIVITY
REPORTSub Title : 7.3 KAI CUMULATIVE TREND
Slide Title : 7 QM PILLAR
KAI CUMULATIVE TREND
KAI CUMULATIVE TREND
WHY – WHY ANALYSISNos OPL DONENos TRAININGS CONDUCTEDNos
POKE YOKENos COUNTERMEASURESNos KAIZENSNos
C
TPM ACTIVITY
REPORTSub Title : 7.3.1 KAIZEN SAMPLE SHEETS
Slide Title : 7 QM PILLAR
85 QM K
AIZEN
IMPLEMENTED
After Pre audit – kaizen updated
37
TPM ACTIVITY
REPORTSub Title : 7.4 QM RESULTS
Slide Title : 7 QM PILLAR
P.1.1.12 – CRATE PRODUCTS SCRAP
PPM
Better
FROM 4365 PPM TO 98 PPM
BM – 4365 (JUN 07 )
38
TPM ACTIVITY
REPORTSub Title : 7.4 QM RESULTS
Slide Title : 7 QM PILLAR
P.1.1.13 – FURNITURE PRODUCTS SCRAP
PPM
FROM 15002 PPM TO 501 PPM
BM – 15002 (JUN 07 )
Better
39
TPM ACTIVITY
REPORTSub Title : 7.4 QM RESULTS
Slide Title : 7 QM PILLAR
P.1.1.14 – INDUSTRIAL PRODUCTS SCRAP
Better
%
FROM 1% TO 0.26%
BM – 15002 (JUN 07 )
40
TPM ACTIVITY
REPORTSub Title : 7.4 QM RESULTS
Slide Title : 7 QM PILLAR
P.1.1.15 – FURNITURE REWORK
%Better
FROM 12% TO 2.52%
BM – 12 (JUN 07 )
41
TPM ACTIVITY
REPORTSub Title : 7.5 QM RESULTS
Slide Title : 7 QM PILLAR
C 3.1.1 – INPROCESS SCRAP
%Better
FROM 3.9% TO 0.64%
BM – 3.9% (JUN 07 )
42
TPM ACTIVITY
REPORTSub Title : 7.5 QM FUTURE PLAN
FUTURE PLAN
Sl No Activity Target Date
1
2
3
4
5
To achieve 85 PPM in Crate Product Scrap
To achieve 350 PPM in Furniture Product Scrap
To achieve 0.15% in Industrial Product Scrap
To achieve 1.55% in Furniture Rework
To achieve 0.4% in in process Scrap
Dec 2011
Jan 2012
Feb 2012
Mar 2012
Feb 2012
Slide Title : 7 QM PILLAR
C
43
CHAPTER 8
DM – PILLAR
Presentation By
Mr. Ramesh Kumar