challenges in material specification - concrete institute...case study –concrete requirements to...

37
Greg van Rooyen | Technical Director - Material Technology Challenges in material specification

Upload: others

Post on 12-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Greg van Rooyen | Technical Director - Material Technology

Challenges in material specification

Page 2: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Introduction

Page 3: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Introduction

1. Shortfalls in the standards – Why specify

2. Understanding local constraints

3. Supply chain issues

4. Types of specifications

5. Durability and sustainability

6. Common issues

7. Discussion

Page 4: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Australian Standards

Page 5: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Standards for concrete

• AS 1379 Specification and supply of concrete

• AS 1012 Methods of testing concrete

• AS 1141 Methods for sampling and testing

aggregates

• AS 1289 Methods of testing soils for

engineering purposes

• AS 3550 Methods for the analysis of water

• AS 1478.1 Admixtures for concrete

• AS 2758.1 Concrete aggregates

• AS 3582.1 SCM’s Fly ash

• AS 3582.2 SCM’s Slag

• AS 3582.3 SCM’s Amorphous silica

• AS 3972 Portland and blended cements

Page 6: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Standards for concrete

• Lets take a closer look as AS 1379

• Density range 2100 to 2800 kg/m3

• Chloride content below 0.8 kg/m3

• Sulfate content below 50 g/kg of cement

• Drying shrinkage below 1000 microstrain

• Minimum 7 day strength

• Cement and aggregate comply to relevant

standards

•Standard N-grades

• N20, N25, N32, N40, N50

• Slump 20 to 120 mm in 10 mm increments

• Maximum nominal aggregate 10, 14 or 20 mm

• Air content up to 5.0%

Page 7: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Standards for concrete structures

• AS 2159 Piling

• AS 3600 Concrete structures

• AS 5100.5 Bridge design – Concrete

• AS 3735 Concrete structures retaining liquids

• AS 4997 Guidelines for the design of maritime

structures

• AS 2876 Concrete kerbs and channels (gutters) –

manually or machine placed

Page 8: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Standards for concrete structures AS3600

Page 9: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Standards for concrete AS5100.5

Page 10: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Types of specifications

• Drawings

• Reference to standards

• Supplementary Specifications

• Reference to Client / Authority standards

• Comprehensive Specifications

• Stand alone documents with limited

external references

Page 11: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Types of specifications

Page 12: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Understanding local constraints

Page 13: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Material availability

A common problem facing specifiers is

knowing what local materials are available.

Consider airport pavement

Traditionally this required:

• Basalt aggregate, then

• Basaltic aggregate + performance

requirements, then

• Performance requirements only.

Page 14: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

SCM’s are a critical material with regard

durability

Queensland is fortunate in availability of

SCM’s

Not everything is available everywhere

The specifier should work with the

supplier – Early engagement to

establish availability and options.

This does require the specification to be

broad.

Material availability – SCM’s

High performance precast boats

70 MPa GP + FA + SF

Low heat, late age infill

40 MPa GP + FA

Page 15: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

What performance is achievable

Generally avoid issues by specifying

N-grades or as per relevant standard.

As noted this is not always possible or

desirable.

Contractual problems

• Unclear specification

• Creating partnership

• Dealing with non-conformance

Page 16: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Supply chain issues – a consultants view

Page 17: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Development of the specification

Client requirements (SWTC)

Design requirements

Durability requirements

Review panel requirements

Final Specification

Page 18: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Case Study – Concrete requirements

A project required remediation of several concrete elements (near Brisbane)

The structural design identified three concrete mixes for various elements

The mix requirements table from the Specification looked like this:

Class N20 S32 S40

Use Mass infill General

concrete

Structural &

Mass

concrete

Max w/c

ratio

0.5 0.5 0.5

Min fly ash 25% 25% 25%

Min cement 190 320 390

Page 19: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Case Study – Concrete requirements

After review by the review panel and client concerns with high in-situ

strength (as experienced on another project and heat of hydration

were raised). The requirements were amended as follows:

Class N20 S32 S40

Use Mass infill General

concrete

Structural &

Mass concrete

Max w/c ratio 0.5 0.5 0.5

Min fly ash 25% 25% 25%

Min cement 190 320 390

Minimum strength

(28 days)

20 32 40

Maximum strength

(56 days)

28 38 48

Page 20: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Case Study – Concrete requirements

Issues – Part 1

Class N20 S32 S40

Use Mass infill General

concrete

Structural &

Mass concrete

Max w/c ratio 0.5 0.5 0.5

Min fly ash 25% 25% 25%

Min cement 190 320 390

Minimum strength

(28 days)

20 32 40

Maximum strength

(56 days)

28 38 48

Page 21: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Case Study – Concrete requirements

Issues – Part 2

Class N20 S32 S40

Use Mass infill General

concrete

Structural &

Mass concrete

Max w/c ratio 0.5 0.5 0.5

Min fly ash 25% 25% 25%

Min cement 190 320 390

Minimum strength

(28 days)

20 32 40

Maximum strength

(56 days)

28 38 48

Page 22: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Case Study – Concrete requirements

Neither the design nor expert panel specified the actual required

performance.

But wait things get worse….

Page 23: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Case Study – Concrete requirements

Concrete supplier mix performance:

N20 – 220 kg cementitious 30% fly ash – 24 to 28 MPa

S32 – 0.55 w/c 320 kg/m3 cementitious – 45 to 50 MPa

S40 – 0.45 w/c 390 kg/m3 cementitious – 55 to 60 MPa

In short the current mix performance exceeds all of the nominated

criteria.

However the client cannot ignore expert panel advise therefore

designer has to relax requirements.

Page 24: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Case Study – Concrete requirements

After discussion with client, consultant, contractor and supplier

the following was agreed:

Class N20 S32 S40

Use Mass infill General

concrete

Structural &

Mass concrete

Max w/c ratio 0.85 0.70 0.55

Min fly ash 25% 25% 25%

Min cement 190 320 390

Average strength (28

days)

20 32 40

Maximum strength

(56 days)

28 38 48

Page 25: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Case Study – Concrete requirements

To actually achieve the required performance the following

could have been specified:

Class N20 S32 S40

Use Mass infill General

concrete

Structural &

Mass concrete

Max w/c ratio - 0.60 0.50

Min fly ash - 25% 25%

Min / Max cement - 320 / 380 380 / 420

Maximum in-situ

peak temperature

- 80 80

Characteristic

strength

- 32 MPa at 28

days

40 MPa at 56

days

Page 26: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Durability, sustainability and performance

Page 27: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Durability

• Specifying performance criteria

• Chloride testing

• Special testing

• Mix design “deemed to comply” criteria

Cement Admixture Rebar Surface Electrochem

PC Plasticisers Carbon Steel Rebar Extended Curing Chloride Monitoring

Micro-silica Self-compacting agents Non-reinforced Design Controlled Permeability

Formwork

Corrosion Monitoring

FA / SFA Water-proofers Stainless Steel Rebar Penetrating Sealers Provision for Future CP

GGBFS Corrosion Inhibitors GRP reinforcement Surface Coatings Cathodic Prevention

Page 28: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Sustainability

Current requirements focus on CO2 or embodied

energy reduction.

Most easily achieved through use of SCM’s

Great deal of research into alkali activated /

geopolymer concrete.

This has not translated into standards yet.

Development ongoing.

Page 29: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Common areas of concern

Page 30: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Standard testing

Data availability

Data never (hardly ever) available but:

Page 31: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Standard testing

Page 32: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Heat of hydration and temperature control

• Common issue is dealing with temperature control

• Requirements not allowed for – becomes contractual cost issue

• How do we get the right technical soluton

Page 33: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Heat of hydration and temperature control

Page 34: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Water addition to concrete

• AS1379 Specification and

supply of concrete

• Need to consider the

conditions

• Large number of variables

involved, simplest solution is

to not permit water additions

Page 35: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

Concrete placement time

Page 36: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Discussion

Page 37: Challenges in material specification - Concrete Institute...Case Study –Concrete requirements To actually achieve the required performance the following could have been specified:

Challenges in material specification CIA 2018

www.ghd.com