change orders in construction projects in saudi arabia presented by samer al-jishi & hussain...

32
Change Orders in Change Orders in Construction Projects in Construction Projects in Saudi Arabia Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation CEM 520 Term Presentation January 2007

Upload: rolf-oneal

Post on 18-Dec-2015

216 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

Change Orders in Change Orders in Construction Projects in Construction Projects in

Saudi ArabiaSaudi Arabia

Presented by

Samer Al-Jishi & Hussain Al-Samer Al-Jishi & Hussain Al-MarzougMarzoug

CEM 520 Term PresentationCEM 520 Term Presentation

January 2007

Page 2: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

1. Change Order

• A change is defined in literature as any deviation from an agreed upon well-defined scope and schedule.

• Stated differently; a change is any modification to the contractual guidance provided to the contractor by the owner or owner's representative.

Page 3: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

2. Literature Review

Divided into four parts:

1. The basics of changes and their terminology.

2. The legal aspects of changes.3. Evaluation and cost aspect.4. Controls.

Page 4: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

2.1 Initiation/Classification of change order

Initiation parties of change order: Owner may request a change. Engineer because of differing site condition or new

governmental regulation. Project management firm usually in schedule. Contractor may due to design errors, value engineering

,or field requirement.

Changes can be classified in terms of net effect on scope: Additive change. Deductive change. Rework-due to quality deficiency Force majeure change

Page 5: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

2.2 The legal Aspects

The major legal aspects:

Selecting the best delivery system Drafting and interpreting change clauses Documenting change orders

The choice of the type of contract (Fixed cost Vs. cost reimbursable) should be heavily influenced by four circumstances:

The extent to which work is defined. The desired allocation of risk between owner and contractor The availability of owner expertise and effort on the project The need to accommodate fast-tracking of design and

construction The general market place conditions

Page 6: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

Cont’d: Selecting the delivery system

The commonly accepted ideas with respect to contract strategy as follows:

Risk allocation is considered to be, primarily directed toward the contractor in fixed price contracts.

Risk allocation is considered to primarily directed toward the owner in cost reimbursable contracts.

More owner administrative time is required in cost reimbursable contracts.

Documentation and scope definition effect is more critical in fixed price contracts.

Fixed price contract provide less incentive for high quality work. Cost plus contracts provide more flexibility to change design or

scope Cost reimbursable contract assist in minimizing the schedule while

fixed price contracts minimize costs

Page 7: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

Cont’d: Drafting & interpreting change clauses It defined how the two parties will handle changes

and change orders and form the basis of any legal claims.

Some times owner or an engineer may attempt to avoid responsibility for changes by using disclaimer clause or risk shifting clause in the

contract.

Page 8: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

2.3 Cost Aspect

This type of study about cost aspects can be classified as either :

Qualitative studies discuss the various attributes of cost and schedule impact without Quantifying them.

Quantitative studies on the other hand attempt to quantify the various attributes of cost and schedule impacts.

The impact of a change on a cost are classified in the literature as follows

Direct cost impact Direct schedule impact Indirect or Consequential Impacts

Page 9: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

Cont’d..

There are two components to the cost of change: labor and material cost. Material cost is easy to estimate and predict to certain accuracy. However it is difficult to estimate labor cost due to

The effect of changes on the productivity rate itself The uncertainty about a the scope o a change

Direct cost impact

Page 10: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

It is easy to document a schedule impact of a change after change work is done, because all data is available regardless of its accuracy

Most project are planned using a critical path method

Cont’d..Direct Schedule Impact

Page 11: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

Cont’d..

Occur later in other work packages and thus on the total project.

Possible consequential effects:1. Effects on the methods or procedures used in other

work packages due to a change in a previous task or package.

2. Degradation of productivity in subsequent packages or activity.

3. Increase in overhead cost.4. Impact on subcontractors.

This situation is called ripple effect

Indirect Impacts

Page 12: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

Cont’d..

The following procedures are used in costing changes:

1. Price and schedule adjustment are negotiated prior to the start implementation.

2. If unit prices are part of the contract, they will be used as the basis of change work pricing. Unit prices quoted in the contract should not be used to cost changes without consideration to change variation.

3. The contractor is directed to proceed with after the fact adjustment.

Costing Changes

The first technique is in wide use in the construction industry. However, it requires a commitment form both parties to expedite and carry change procedure in an open and trustworthy environment.

Page 13: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

2.4 Management Aspects

To help in controlling changes: The owner should define his needs and project objectives

easily in the project life. Forming a change review committee which includes

owner's project engineer, Business manager and process engineer to carry out the owner's commitment to reduce change effects.

A team effort by all parties to promote recognition, reporting ,and resolution of a change is required throughout the life of the project

Freezing the design is a strong control method. All changes must be justified from a cost point of view. Efficient change procedures must be followed to avoid

any delay in evaluation.

Change Control

Page 14: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

4. SURVEY QUESTIONNAIRE

Questionnaire Design

Brainstorming Meeting with key members in

industry English/Arabic versions

Page 15: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

4.1 Contents

The questionnaire has six sections:

I. Instruction to respondentsII. General information about respondentsIII. General industry CharacteristicsIV. Causes of change ordersV. Effects of change ordersVI. Controls of change orders

Page 16: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

4.2 Statistical SampleFour restrictions were imposed on the selection process of respondents:1. Large projects (>= SR 20MM)2. Large contractors (>= grade 2)3. Building projects4. Projects at Eastern Province of KSA

To determine the sample size form each population, the below equations were used:

n0 = (p*q)/V2 -------------------------- (1)n = n0/[1+(n0/N)] -------------------- (2)A sample size of 16 was used

Page 17: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

4.3 Gathering Data

17 responses were used for both contractors and consultants

Standard error assumed to be less than 10%

Page 18: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

4.4 ScoringCauses, Effects, and Controls sections are scored based on the following:

Very often = 100%

Often = 75%

Sometimes = 50%

Seldom = 25%

Never = 0 %

Importance Index, Prevalence Index and Utilization Index of each causes, effects and controls are calculated as follows:

IIc1 = 100 x1 + 75x2 + 50x3 + 25x4 + 0x5 / (x1 + x2 + x3 + x4 + x5)

II: Importance Index, C1: Cause one

Page 19: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

5. RESULTS AND FINDINGS5. RESULTS AND FINDINGS

Data analysis about causes are categorized by Importance Index (II)

Data analysis about effects are categorized by Prevalence Index (PI)

Data analysis about controls are categorized by Utilization Index

Hypothesis “Contractors and consultants don’t agree on the causes of

change orders” was tested.

Page 20: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

5.1 General Info & Industry Characteristics

Contractors Consultants

Size Mostly > 200 employees Mostly < 200 employees

Level of Experience Mostly > 15 years Mostly > 15 years

Types of Construction contracts 65% LSTK, 18% LS-LBR, 0% D&B

CO's over construction crafts >60% Civil/Struct, 23% Elect, Least Mech

Relation of prencipal parties 62% Excell/V.G , 3 cases Fair/Poor

Owner Involvement 41% in both D&C , 22% Design only, 35% Const only

Page 21: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

Cont’d..

Cost Over run Schedule Over run

>50% of respondents 6-10% over run

26% of respondents 11-25% over run

>55% of respondents <10% over run

35% of respondents 10-20% over run

<1% of respondents >20% over run

Page 22: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

5.2 Causes of Change OrdersRanking of causes

Page 23: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

5.3 Effects of Change OrdersRanking of effects

Page 24: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

5.4 Controls of Change OrdersRanking of controls

Page 25: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

Cont’d..The most important causes, effects and controls

Page 26: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

5.5 Test & Agreement The null & alternative hypothesis (H0 & HA) are formulated

and the degree of agreement or disagreement between consultants and contractors on the causes, effects and controls of change orders is tested.

Results:

Contractors & Consultants do agree on the causes of CO’s.

Contractors & Consultants do agree on the effects of CO’s.

Contractors & Consultants do agree on the controls of CO’s.

Page 27: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

5.6 Comments from Respondents

By Consultants

1. Accuracy of documents, drawings, specs and BOQ’s is required.

2. Coordination is very helpful.

3. Improvement of project management in governmental project is necessary.

4. Use of project management consultants (PMC) is recommended.

5. All finishing materials and equipment should be selected & approved prior to construction.

Page 28: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

Cont’d..

By Contractors

1. Consultants should explain the design to the owner clearly to have full understanding.

2. Site conditions and design packages should be studied carefully by the owner.

3. Cost of change order should be negotiated before commencement of any work.

4. Owners should consider the negative effect of CO’s and try to avoid it by doing a good design before calling for bidding.

Page 29: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

6.1 SUMMARY6.1 SUMMARY

Chapter 11: Introduction, Objectives, Scope,

Limitations

Chapter 22: Basics, Legal aspects, Cost aspects,

Management aspects of CO’s.

Chapter 33: Parameters to be measured

Chapter 44: Process of developing the questionnaire,

scoring methods

Chapter 55: Results & Findings

Page 30: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

6.2 CONCLUSION6.2 CONCLUSION

Changing the plans by the owners is the main source of change orders.

That is due to lack of involvement in the design development and

inability to visualize it while not appreciating the negative effect of it.

Because of new materials are becoming available in the market or

change in mind, substituting materials and/or procedures is the 2nd

source of CO’s.

Consultants are the 2nd major contributor to changes by generating

conflicting design documents or through change in design afterwards.

Increase in project cost and duration are the main two effects being

noted for change orders.

Clarity of scope of CO’s ranked the 1st among controls adopted.

Page 31: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

6.3 RECOMMENDATIONS6.3 RECOMMENDATIONS Make use of 3D models to help owners see their

project before construction starts. Animation would be greater!

Owners to make a good financial planning during planning stage.

Owners are advised to have PMC to supervise both design and construction to ensure that owner’s expectations are met by the design.

Consultants to specify the materials in a detailed matter or use performance specs.

Owners to use the control of “freezing the design” more often to avoid the problem of creeping scope.

Page 32: Change Orders in Construction Projects in Saudi Arabia Presented by Samer Al-Jishi & Hussain Al-Marzoug CEM 520 Term Presentation January 2007

THANK YOUTHANK YOUQUESTIONS?