Page 1: Chaplin - Avenue Construction Liaison Committee Meeting - June 2017

CROSSTOWN LRTConstruction Liaison

CommitteeJune 6, 2017

Page 2: Chaplin - Avenue Construction Liaison Committee Meeting - June 2017

2

Agenda

• Avenue Station Update

• Chaplin Station Update

Page 3: Chaplin - Avenue Construction Liaison Committee Meeting - June 2017

3

Year Quarter Construction Activity / Closure

2017

Q1

(Jan-March)

• Piling at Main and Secondary entrances

• Enclosure of park and tree removals

• Geotechnical Instrumentation and Monitoring Phase 2

Q2

(April-June)

• Excavation at Main and Secondary entrances

• Geotechnical Instrumentation and Monitoring Phase 2

• Dewatering system installation

• Temporary Site Services Connections

Q3

(July-Sept)

• Utilities mitigation (Sewer lining and water main replacement)

• Dewatering system installation continues

• Excavation continues at both entrances

• Crane installation at both entrances

Q4

(Oct-Dec)

• Excavation continues at both entrances

• Dewatering system operating

• Start of mining operations

Avenue Station: What to Expect in 2017

Page 4: Chaplin - Avenue Construction Liaison Committee Meeting - June 2017

4

Avenue Station Updates

June 2017• Excavation is underway at Main & Secondary Entrance

• Excavation is completed one level at a time with tie backs and supports installed before moving to next level

• Truck traffic to the site will be approximately 5 trucks per hour per site

• Secondary Entrance sidewalk to remain open

• Sound Barrier Installation at both entrances (main entrance north side erected)

• Monitoring instrument installations continue from Lascelles Blvd to Braemar Ave ongoing; over 70 instruments being installed

• Line painting refresh completed

• Dewatering well installations – underway

• Details on next slides

• Utilities mitigation works – upcoming

• Sewer & Watermain works

Page 5: Chaplin - Avenue Construction Liaison Committee Meeting - June 2017

5

Support Works - Dewatering

• At Eglinton Avenue West and Avenue Road, dozens of small wells will be drilled around the entire station box where excavation will be taking place.

• The volume of soil that requires dewatering is significant.

• System will operate for the duration of construction (2020).

• The term “dewatering” means pumping from the ground water at a site where there will be excavation.

Page 6: Chaplin - Avenue Construction Liaison Committee Meeting - June 2017

6

Support Works - Dewatering

• 72 wells will be drilled approximately every 10 metres and shallow trenches will be required to lay the pipes, pumps, wells and valves to do the work.

• The drills installing the wells and the trenches for the piping will encircle the

station box.

• Installation work will occur between May 2017 and Fall 2017.

Page 7: Chaplin - Avenue Construction Liaison Committee Meeting - June 2017

7

Support Works – Dewatering

• Four dewatering wells are required to be installed in Eglinton Park.

• Wells are to the west of the pedestrian pathway.

• Tree protection will be installed during the works; no trees will be injured or removed.

• Pedestrian pathway through the park will be maintained during the works.

Page 8: Chaplin - Avenue Construction Liaison Committee Meeting - June 2017

8

Support Works – Utilities Mitigation

What to expect: Sewer Lining

• Sewer lining is a process intended to increase the durability of the sewers.

• A section of the sewer system is cleaned and vacuumed and a CCTV inspection is completed. Then a liner is inserted into the sewer section from within the maintenance holes

• The process is designed to be generally non-disruptive and eliminates the need for excavation of the entire sewer section.

• Maintenance holes that will be accessed are located on Eglinton Avenue West between Braemar Avenue and Lascelles Boulevard.

• Lane closures will be required for this work. Pedestrian access will be maintained.

• Above ground pipes will be in place between maintenance holes to bypass pump around the sewer lines during the liner installation.

• Due to the nature of the work, an unpleasant chemical odour may be noticeable in the vicinity of the maintenance holes and, in some circumstances, in the home. It is not harmful, however it can be limited by covering floor drains while the sewers are being lined.

A public notice with additional details will be distributed prior to work beginning.

Page 9: Chaplin - Avenue Construction Liaison Committee Meeting - June 2017

9

Support Works – Utilities Mitigation

What to expect: Sewer Lining

Sewer Lining Activity Examples

Page 10: Chaplin - Avenue Construction Liaison Committee Meeting - June 2017

10

Support Works – Utilities Mitigation

What to expect: Watermain Replacement

• Water main replacement work will include trenching and removing and replacing pipes.

• This work will occur on watermains on Eglinton Avenue West between Avenue Road and Oriole Parkway South.

• Lane closures will be required for this work. At least one lane in each direction will be maintained.

• Pedestrian access will be maintained.

A public notice with additional details will be distributed prior to work beginning.

Page 11: Chaplin - Avenue Construction Liaison Committee Meeting - June 2017

11

Avenue Station Concept: Aerial View

Main Entrance (accessible entrance)

Secondary Entrance

*60% rendering

N

Page 12: Chaplin - Avenue Construction Liaison Committee Meeting - June 2017

12

Avenue Station Concept: Main Entrance

*60% rendering

Page 13: Chaplin - Avenue Construction Liaison Committee Meeting - June 2017

13

Avenue Station Concept: Secondary Entrance

*60% rendering

Retail Space

Secondary entrance height has increased from the 30% design.

Page 14: Chaplin - Avenue Construction Liaison Committee Meeting - June 2017

14

Construction Progress Picture

Page 15: Chaplin - Avenue Construction Liaison Committee Meeting - June 2017

15

Construction Progress Picture

Page 16: Chaplin - Avenue Construction Liaison Committee Meeting - June 2017

16

Construction Progress Picture

Page 17: Chaplin - Avenue Construction Liaison Committee Meeting - June 2017

17

Construction Progress Picture

Page 18: Chaplin - Avenue Construction Liaison Committee Meeting - June 2017

18

Chaplin Station Construction Update

June 2017

• Continue piling at the Tertiary Entrance

• Continue piling at the southeast side of the station box

• Continue Bell utilities relocation west of Chaplin Crescent

• Reroute south pedestrian detour onto Russell Hill Road

• Secondary Entrance site setup

Page 19: Chaplin - Avenue Construction Liaison Committee Meeting - June 2017

19

Chaplin Station: Updated Construction Stage 1

Began February 28 for approximately five (5) months

Page 20: Chaplin - Avenue Construction Liaison Committee Meeting - June 2017

20

Russell Hill Pedestrian Detour

• Beginning as early as mid-June 2017 to accommodate piling at the Tertiary Entrance (pending approvals)

Page 21: Chaplin - Avenue Construction Liaison Committee Meeting - June 2017

21

Chaplin Station Concept: Aerial View

Main Entrance

Secondary Entrance

*60% rendering

Tertiary Entrance

Page 22: Chaplin - Avenue Construction Liaison Committee Meeting - June 2017

22

Chaplin Station Construction Progress

22

BELL DUCT EXCAVATION

GUIDEWALL CONSTRUCTION

Page 23: Chaplin - Avenue Construction Liaison Committee Meeting - June 2017

23

Chaplin Station Construction Progress

23

STEEL BEAM DELIVERY

TEMPORARY THE EGLINTON

WAY BIA SIGNAGE

Page 24: Chaplin - Avenue Construction Liaison Committee Meeting - June 2017

24

Chaplin Station Construction Progress

24

Page 25: Chaplin - Avenue Construction Liaison Committee Meeting - June 2017

25

Local Area Map

Station(s) under construction