chaplin - avenue construction liaison committee meeting - march 28, 2017

18
EGLINTON CROSSTOWN LRT Chaplin Avenue Construction Liaison Committee March 28, 2017

Upload: crosstown-to

Post on 21-Apr-2017

179 views

Category:

Government & Nonprofit


0 download

TRANSCRIPT

Page 1: Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017

EGLINTON CROSSTOWN LRTChaplin Avenue Construction Liaison Committee March 28, 2017

Page 2: Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017

2

Agenda

• Avenue Station Update• Chaplin Station Update

Page 3: Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017

3

Avenue Station Updates

March/April 2017• Piling is complete at the main and secondary entrance• Monitoring instrument installations from Lascelles Blvd to Braemar Ave

ongoing; over 70 instruments being installed• Excavation will begin at each entrance – starting at Secondary Entrance

– Excavation is completed one level at a time with tie backs and supports installed before moving to next level

– Truck traffic to the site will be approximately 5 trucks per hour per site

2017• Excavation works will continue at Secondary entrance until late

summer, followed by tunneling works• Excavation works will continue at Main entrance until late 2017,

following by tunneling works

Page 4: Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017

4

Construction Staging Update

• Removal of pedestrian detour at secondary entrance under review.

Page 5: Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017

5

Avenue Station Aerial Rendering

Page 6: Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017

6

Construction Progress Picture

Page 7: Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017

7

Construction Progress Picture

Page 8: Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017

8

Construction Progress Picture

Page 9: Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017

9

Construction Progress Picture

Page 10: Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017

10

Construction Progress Picture

Page 11: Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017

Chaplin Station Construction Update

Spring 2017• Continue piling at the Tertiary Entrance• Continue piling at the south side of the station box• Subsurface Utility Engineering (SUE) investigation for

wet utilities relocation• Secondary Entrance site setup• Commence wet utilities relocation

Page 12: Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017

Chaplin Station: Current Construction Stage 1

Began February 28 for approximately five (5) months

Page 13: Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017

TTC Changes

Page 14: Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017

Chaplin Station Concept: Aerial View

Main Entrance

Secondary Entrance

*60% rendering

Tertiary Entrance

Page 15: Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017

Chaplin Station Construction Progress

15

Demolition of 321 Chaplin Cres

Page 16: Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017

Chaplin Station Construction Progress

16

Demolition of 641 Eglinton

Ave W

Page 17: Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017

Chaplin Station Construction Progress

17

Piling at the Main Entrance

site

Page 18: Chaplin - Avenue Construction Liaison Committee Meeting - March 28, 2017

Chaplin Station Construction Progress

18