chemical profile (phase 1) summary general site history · 2007-08-10 · emergency incidents. site...

17
BURN PIT CHEMICAL PROFILE (PHASE 1 ) Reference : Bjorklund letter to Regional Water Quality Control Board, 4 March 1901 (81RC02364), Re : Inactive Burning and Disposal Site ("Burn Pit" ) SUMMAR Y This work plan delineates in detail how the site will be examined on a "first pass" basis to appropriately estimate the level of effort that will be required for cleanup . In addition, this presentation includes the labor estimate for this assignment . A proposed work schedule is submitted with targeted completion dates to provide flexibility according to the chemical analysis results . BACKGROUN D General Site Histor y The "Burn Pit" site was established in approximately 1958 for the safe disposal of chemical fuels by combustion in order to minimize potential public exposure which could result from transport across public highways to dispose in a conven- tional landfill . This site was operated by qualified Rocketdyne Protective Services personnel until 1971 . At that time, the site was closed because of air pollution considerations . Since its closure, the site has been essentially in- active with the exception of a few fire department demonstrations and training exercises to maintain their proficiency in dealing with chemical fires and emergency incidents . Site Descriptio n Located in Rocketdyne's 2,400-acre Santa Susan Test Facility (SSFL) is a six- acre area which is referred to as the "Burn Pit" . Within the bounds of the six-acre area are six pits which range in volume from approximately 200 gallons to 10,000 gallons . Of these six pits, three of them are lined with concrete and three unlined earthen pits . The enclosed maps give the p :'nraphic location, topography, draining outfalls and a rough plan of the "Bu- "it" . Area Water Run Off A preliminary review of the water runoff has led the Rocketdyne Environmental Control Office to believe that no dischargeable hazardous residues resulted from the combustion processes . Routine sampling at the adjacent perimeter pond has not shown any unusual concentrations of any of the substances required to be sampled by the current NPDES permit . It is believed, therefore, that surface runoff is not the problem . u I I I I I I III I BNA0035443 3 I H u H D M Se00038985

Upload: others

Post on 13-Apr-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CHEMICAL PROFILE (PHASE 1) SUMMARY General Site History · 2007-08-10 · emergency incidents. Site Description Located in Rocketdyne's 2,400-acre Santa Susan Test Facility (SSFL)

BURN PIT CHEMICAL PROFILE (PHASE 1 )

Reference :Bjorklund letter to Regional Water Quality Control Board, 4 March 1901(81RC02364), Re : Inactive Burning and Disposal Site ("Burn Pit" )

SUMMARY

This work plan delineates in detail how the site will be examined on a "firstpass" basis to appropriately estimate the level of effort that will be requiredfor cleanup . In addition, this presentation includes the labor estimate forthis assignment . A proposed work schedule is submitted with targeted completiondates to provide flexibility according to the chemical analysis results .

BACKGROUND

General Site History

The "Burn Pit" site was established in approximately 1958 for the safe disposalof chemical fuels by combustion in order to minimize potential public exposurewhich could result from transport across public highways to dispose in a conven-tional landfill . This site was operated by qualified Rocketdyne ProtectiveServices personnel until 1971 . At that time, the site was closed because of airpollution considerations . Since its closure, the site has been essentially in-active with the exception of a few fire department demonstrations and trainingexercises to maintain their proficiency in dealing with chemical fires andemergency incidents .

Site Descriptio n

Located in Rocketdyne's 2,400-acre Santa Susan Test Facility (SSFL) is a six-acre area which is referred to as the "Burn Pit" . Within the bounds of thesix-acre area are six pits which range in volume from approximately 200 gallonsto 10,000 gallons . Of these six pits, three of them are lined with concrete andthree unlined earthen pits . The enclosed maps give the p :'nraphic location,

topography, draining outfalls and a rough plan of the "Bu- "it" .

Area Water Run Of f

A preliminary review of the water runoff has led the Rocketdyne EnvironmentalControl Office to believe that no dischargeable hazardous residues resultedfrom the combustion processes . Routine sampling at the adjacent perimeter pondhas not shown any unusual concentrations of any of the substances required to besampled by the current NPDES permit . It is believed, therefore, that surfacerunoff is not the problem .

u I I I I I I III IBNA0035443 3

I H u

H D M Se00038985

Page 2: CHEMICAL PROFILE (PHASE 1) SUMMARY General Site History · 2007-08-10 · emergency incidents. Site Description Located in Rocketdyne's 2,400-acre Santa Susan Test Facility (SSFL)

Ground Wate r

The Rocketdyne SSFL is serviced by one well which is maintained byRockedyne . Two additional wells are planned to be brought on line in six (6)months . None of these wells are located near the burn pit area and are upgradient .Rocketdyne believes that there has been no ground water contamination resultingfrom the past activities in the burn pit area . This conclusion is based on anevaluation of the type of the disposal practices which were employed and a 1958geologic and hydrologic survey of the underground water conditions . The study

was performed by C . C . Killingsworth, a consulting geologist from Los Angeles,whose findings revealed that "the overall average effective porosity appears tobe less than one percent (1%) over the 2,000 acres of property" . Furthermore,of the wells that have been driven or that are currently in operation, the dis-tance from the surface to reach the aquifer is in the order of 415 feet .

WORK STATEMENT

The California Department of Health Services prepared a document on "Samplersand Sampling Procedures for Hazardous Waste Streams" that offers the approachconsistent with the Burn Pit chemical profile . Thus, the attached proceduressubmit a plan of action to maximize safety of sampling personnel, minimizesampling time and cost, reduce errors in sampling, and protect the integrityof the samples after sampling .

1 . The background information about the Burn Pit has been researched and issubmitted as Table 1, ("SUMMARY OF MATERIALS AND DISPOSAL METHODS") . Recordshave been kept for years on the general pond/Later system/runoff chemicalconstituency, so that Rocketdyne's pollution control program has voluminousdocumentation on constituents that required reporting under the NPDES permitcurrently held . These records substantiate that surface runoff has been mon-

itored continually .

2. A list is attached that describes the constituents for which the analyses I li abe performed . See Table 2, ("SUMMARY OF CHEMICAL CONSTITUENT TESTS" ), that hasbeen compiled from the data assembled and tabulated as in. Table 1 .

3 . The proper samplers will be selected in accordance with the State and EPASW-846 manuals, as well as devices that are uniquely suited to the SSFL terrain .

4 . The proper sample containers and closures will be obtained using the refer-enced regulatory documents as guides .

5 . The sampling plan will include the choice of proper sampling points, andthe number and volume of the samples to be taken, including the boring depth .

6 . All proper sampling precautions will be observed .

7 . The samples will be handles properly with the appropriate chain of custodypaperwork .

u I uII

H D M Se00038986

Page 3: CHEMICAL PROFILE (PHASE 1) SUMMARY General Site History · 2007-08-10 · emergency incidents. Site Description Located in Rocketdyne's 2,400-acre Santa Susan Test Facility (SSFL)

WORK STATEMENT (Continued )

8 . All samples will be identified correctly and protected from tampering .

9 . All sample information will be recorded and identified in a field notebook .

10. The chain of custody record will be completed .

11 . The sample analysis request sheet will be filled out .

12 . The samples will be submitted to the appropriate laboratory .

13 . The results of the selected testing will be reviewed and decisions madewhere there are questions that need to be answered or issues resolved . If ad-ditional samples are required or further pretreatment or sample preparationnecessitated, then actions will be taken to .complete these tasks .

14 . A report will be written su,mnarizing the work performed, data generated,results found, and recommendations tendered . This report will be submitted tothe Rocketdyne Environmental Control Office as the document covering PHASE I .

DISCUSSION

The sample collection would be performed by maintenance personnel specificallyinstructed in and assigned the task by Rocketdyne Facilities and IndustrialEngineering management . A minimum of 50 samples would be obtained over thesix-acre area . The specific sampling sites would be chosen by the RocketdyneF & IE Burn Pit Project Engineer on the advice and counsel of those who haveknowledge of the area and its history and drainage patterns so that representa-tive sampling could be performed . The Rocketdyne Environmental Control Officewould approve of the sampling grid prior to the execution of the undertakingso that the historical data on past events would provide guidance and directionfor the sample handling . The choice of the chemical tests to accomplish thechemical profile of the Burn Pit area would be the responsibility of the Managerof. the Rocketdyne M & P SSFL analytical Chemistry Unit . If, in her opinion,samples were to be sent out to other laboratories, these decisions would bemade and subsequent actions taken to accommodate the best technical resolutionof the problem in the most expeditious and economical way .

u I I I I I I III IBNA0035443 5

I H uI

H D M Se00038987

Page 4: CHEMICAL PROFILE (PHASE 1) SUMMARY General Site History · 2007-08-10 · emergency incidents. Site Description Located in Rocketdyne's 2,400-acre Santa Susan Test Facility (SSFL)

TABLE 1 - SUMMARY OF MATERIALS AND DISPOSAL* METHOD S

Type of Materia l

A. Fuel s

1 . Nitrogen Tetroxid e2 . Misc .- Contaminated Fuels3 . Pentaborane4 . RP-1 (Kerosene Base)5 . JP-4 (Kerosene Base)6. Hydrazine s7 . Triethyl Aluminu m8 . Triethyl Aluminum Boran e

B . Igniters

C . Process Chemicals

1 . Acid s2 . Base s

D. Reactive Metal s

1 . Aluminum2 . Magnesium3. Sodium4. Potassium

E . Organic Solvents

1 . Tetraisobutylene2 . Alcohol s3. Heptane

F . Explosives

1 . Nitrocellulose2 . Mix Oxide s3. Dynamit e

G . Tox ic Gases

1 . Oxygen Difluoride Gas2 . Fluorine Gas3 . Chlorine Gas

H . Heavy Metal Toxic s

1 . Leaded Paint ( 189 gallons)2 . Potassium Cyanide3 . Sodium Arseni to4 . Mercury

Volume or Mass Disposal Method

450,000 gallon s

#6924

21,300 gallon s

13,810 pounds

31,717 gallons

5,121 pounds

32,932 feet3

191 gallons

CombustionCombustionCombustionCombustionCombustionCombustionCombustionCombustion

Detonation

Dilute and placein earthen pits

BurningBurningBurningBurning

CombustionCombustionCombustio n

DetonationDetonationDetonatio n

CombustionCombustionCombustion

Combustion

CombustionDilutionDilutio n

*140TE : From Fed . Register , May 19 , 1980, p . 33119 : "A material is 'disposed of' if it isdischarged, deposited, iriPcted, dumred, spilled, leaked or placed into or or 1 .--.,-,y 1&r- cwater so thc:t such material or o'Y constituent h reo`• y er the enviro nt or be.emitted into the air or discharged into ground or surface waters . "

u I I I I I I III I HBNA00354436

I u

H D M Se00038988

Page 5: CHEMICAL PROFILE (PHASE 1) SUMMARY General Site History · 2007-08-10 · emergency incidents. Site Description Located in Rocketdyne's 2,400-acre Santa Susan Test Facility (SSFL)

TABLE 2 - SUMMARY OF CHEMICAL CONSTITUENT TEST S

METALS 1

AluminumArsen i cBari urnBerylliumBoronr~Iadm. umChromiumCopperIro nLeadMagnesiumMercurv +

yhcfenumNickee lPros P ,hmrusPotassiumSe lenfur;SiliconSilverSO 3d I U :71Sul furTi nTitaniumZinc

VOLATILE ORGANICS2

CarLn tetrachlorideChlorobenzeneChloroformChl orome thaneDichiorobenzeneDi tirornometfaneEthyl etherFormaldehydeMothanol -Methyl ethyl ketoneMethyl isobutyl ketoneTetrachloroethaneTetrachlcroetheneTrichloroetheneTrichiaropropaneVinyl chlorideVinylidine chlorid e

VOLATILE AROMATICS, KETONESPx E l_l f !~11PiU l(kRES-z-Acetonitri i eBenzeneChlorobenzeneDir_hlnrohenzene

Ethyl ethe rMethyl ethyl ketoneMethyl isobuytl ketoneToluen eXylene

OTHER ORGANICS 3

Benz ( a) anthracene , pyreneBenz ( b) fluorantheneChryseneCreosoteMercaptansNapthalenePhenolsPyridineToluene diisocyanat e

1 . By atomic absorption spectroscopy or emission spectrography .2 . By gas chromatography or high pressure liquid chromatography .3 . By sample preparation followed by gas chromatography .4 . By specific ion electrode/classical wet chemical techniques .5 . By calorimetric tests .

ANIONS4

ChlorideFluorideNitratePhosphateSul fate

AMINES5

HydrazineMonomethylhydrazin e

OR EQUALLY SUITABLE METHODS

Page 6: CHEMICAL PROFILE (PHASE 1) SUMMARY General Site History · 2007-08-10 · emergency incidents. Site Description Located in Rocketdyne's 2,400-acre Santa Susan Test Facility (SSFL)

I

i

SCALE : 1 ' ~- 10 0

ii

Colic-

f, T

EPA t •i , r to - r .. 1711

r

t L 1~ C r L! t-tE --

I

:-a

?''~l;lf(i;'EF:'ONE

u

Page 7: CHEMICAL PROFILE (PHASE 1) SUMMARY General Site History · 2007-08-10 · emergency incidents. Site Description Located in Rocketdyne's 2,400-acre Santa Susan Test Facility (SSFL)

P O TASSIU M LOO P AREA l

u I I u

Page 8: CHEMICAL PROFILE (PHASE 1) SUMMARY General Site History · 2007-08-10 · emergency incidents. Site Description Located in Rocketdyne's 2,400-acre Santa Susan Test Facility (SSFL)

r

L `I! D!

2I '.~ 6-,AL

NOT LU .

e

L 77 EA

u I E u

H D M Se00038992

Page 9: CHEMICAL PROFILE (PHASE 1) SUMMARY General Site History · 2007-08-10 · emergency incidents. Site Description Located in Rocketdyne's 2,400-acre Santa Susan Test Facility (SSFL)

€~ i O F

ENGiN E. RING CHENAl S TRY LAS AR E

N C L u-Jnc'

u I u

Page 10: CHEMICAL PROFILE (PHASE 1) SUMMARY General Site History · 2007-08-10 · emergency incidents. Site Description Located in Rocketdyne's 2,400-acre Santa Susan Test Facility (SSFL)

GHANh?Ej-

LETF AREA

LF.TF P®NP

u I u

Page 11: CHEMICAL PROFILE (PHASE 1) SUMMARY General Site History · 2007-08-10 · emergency incidents. Site Description Located in Rocketdyne's 2,400-acre Santa Susan Test Facility (SSFL)

r40,

Cc lC . L11 Q l PTr-C A,P C17Y AT `2' F° RE ~' C-' CIA- R, t>Ifb 42. 0co CS&L .-

L-Corks . L. 1 vi 0 wD> {CA,Pta, C %-r`v AT =R r:

G f .,R

4z 8 .QOO G EL .

AF- F AREA

u I I I I I I III I I II EBNA00354443

u

H D M Se00038995

Page 12: CHEMICAL PROFILE (PHASE 1) SUMMARY General Site History · 2007-08-10 · emergency incidents. Site Description Located in Rocketdyne's 2,400-acre Santa Susan Test Facility (SSFL)

P-°

STO

n

V5 t0,O)O c.~L .

4

RABLE PROPELLANT ARE A

u I uII

H D M Se00038996

Page 13: CHEMICAL PROFILE (PHASE 1) SUMMARY General Site History · 2007-08-10 · emergency incidents. Site Description Located in Rocketdyne's 2,400-acre Santa Susan Test Facility (SSFL)

MX PROPELLANT- LOAD FACILITY ARE A

u I u

Page 14: CHEMICAL PROFILE (PHASE 1) SUMMARY General Site History · 2007-08-10 · emergency incidents. Site Description Located in Rocketdyne's 2,400-acre Santa Susan Test Facility (SSFL)

ALFA / BRAVO SKIM PON D

u I I u

Page 15: CHEMICAL PROFILE (PHASE 1) SUMMARY General Site History · 2007-08-10 · emergency incidents. Site Description Located in Rocketdyne's 2,400-acre Santa Susan Test Facility (SSFL)

WASTE DISPOSAL STORAGE ARE A

u I u

Page 16: CHEMICAL PROFILE (PHASE 1) SUMMARY General Site History · 2007-08-10 · emergency incidents. Site Description Located in Rocketdyne's 2,400-acre Santa Susan Test Facility (SSFL)

1~ .t

11. 7

T-~ z tt~l~ C+

15 1

1 tlt ` : lip

u I I I I I I III I I II HBNA00354448

u

H D M Se00039000

Page 17: CHEMICAL PROFILE (PHASE 1) SUMMARY General Site History · 2007-08-10 · emergency incidents. Site Description Located in Rocketdyne's 2,400-acre Santa Susan Test Facility (SSFL)

SSFL N T I N T ION CONTROL SYSTE M

N

EXISTING

L,VS7 pANYpw PAE0.)ILr' /CR P

~~ ~ Lp 9CIWL ARE A

t ~_ ~RCaGCC

- CAD o93365" 3 5

ltcF~ K - CA IBDxx?oolo

g .59F L WATC- RCCIAAATI- 1-i S ' y r

Q SSfL RCRA S-aFt,<-c- lmpovjjr>

I r

110