chief of international energy cooperation division
TRANSCRIPT
![Page 1: Chief of International Energy Cooperation Division](https://reader034.vdocument.in/reader034/viewer/2022042401/625d70488226b178005de181/html5/thumbnails/1.jpg)
Dr. Poonpat Leesombatpiboon
Chief of International Energy Cooperation Division International Energy Cooperation Office,
Ministry of Energy, Thailand
Hosted by the Energy Regulatory Commission of Thailand (ERC)
Inter Continental Hotel, Bangkok 1 October 2015
![Page 2: Chief of International Energy Cooperation Division](https://reader034.vdocument.in/reader034/viewer/2022042401/625d70488226b178005de181/html5/thumbnails/2.jpg)
LTMS – PIP A greater step to regional
Power Integration in ASEAN
Outlines:
Potential
Demand & Supply
Infrastructure Readiness
Market integration possibility existing
Status of LTMS
![Page 3: Chief of International Energy Cooperation Division](https://reader034.vdocument.in/reader034/viewer/2022042401/625d70488226b178005de181/html5/thumbnails/3.jpg)
Background
Refer to the Lao PDR, Thailand, Malaysia, Singapore (LTMS) Power Integration Project (LTMS-PIP) was initiated during the Special Senior Official Meeting on Energy (SOME) convened on 9 – 11 December 2013 in Manado, Indonesia.
Consequently, in the ASEAN 32nd SOME and Its Associated Meetings under the Theme of Power Integration for ASEAN Prosperity held during 9 – 13 June 2014 in Luang Prabang, Lao PDR, the Meeting welcomed the initiation on the Energy Connectivity Project among Lao PDR, Thailand, Malaysia, and Singapore, which provides the framework for the cross border power trade from Lao PDR to Singapore via Thailand’s grid and Malaysia’s grid.
In addition, the 32nd AMEM during 21 – 23 September 2014 in Vientiane, Lao PDR, the Meeting stated the progress of the initiation by setting up the LTMS PIP Working Group to conduct the study and report to SOME.
![Page 4: Chief of International Energy Cooperation Division](https://reader034.vdocument.in/reader034/viewer/2022042401/625d70488226b178005de181/html5/thumbnails/4.jpg)
THAILAND
Installed cap. = 37,612 MW Peak Demand = 26,942 MW
LAO PDR Installed cap. = 3,246 MW
Peak Demand = 899 MW
MALAYSIA (Peninsula)
Installed cap. = 21,060 MW Peak Demand = 16,901 MW
SINGAPORE Installed cap. = 13,182 MW Peak Demand = 6,880 MW
![Page 5: Chief of International Energy Cooperation Division](https://reader034.vdocument.in/reader034/viewer/2022042401/625d70488226b178005de181/html5/thumbnails/5.jpg)
5
Voltage
Level
115 kV 1 5 6
230 kV 1 2 3
500 kV 2 2
Total 0 1 1 9 11
TotalEDC EVN CSG Thailand
Remarks:
115kV – Exchange
230kV – Purely Export
500kV – Purely Export
![Page 6: Chief of International Energy Cooperation Division](https://reader034.vdocument.in/reader034/viewer/2022042401/625d70488226b178005de181/html5/thumbnails/6.jpg)
6
Existing Interconnection between Thailand and Lao PDR
115 kV Nong Khai (Thailand) – Vientian (Lao PDR)
115 kV Bueng Kan (Thailand) – Pakxan (Lao PDR)
115 kV Nakhon Phanom (Thailand) – Thakhek (Lao PDR)
115 kV Mukdahan 2 (Thailand) – Savannakhet (Lao PDR)
115 kV Sirindhorn (Thailand) – Bang Yo (Lao PDR)
![Page 7: Chief of International Energy Cooperation Division](https://reader034.vdocument.in/reader034/viewer/2022042401/625d70488226b178005de181/html5/thumbnails/7.jpg)
7
Future Interconnection between Thailand and Lao PDR
500 kV Nan (Thailand) – Hong Sa (Lao PDR)
500 kV Udon Thani 3 (Thailand) – Nabong (Lao PDR)
500 kV Udon Ratchathani 3 (Thailand) – Pak Se (Lao PDR)
![Page 8: Chief of International Energy Cooperation Division](https://reader034.vdocument.in/reader034/viewer/2022042401/625d70488226b178005de181/html5/thumbnails/8.jpg)
8
500 kV Main Grid (Existing)
500 kV Main Grid (Future)
![Page 9: Chief of International Energy Cooperation Division](https://reader034.vdocument.in/reader034/viewer/2022042401/625d70488226b178005de181/html5/thumbnails/9.jpg)
9
1
TNB – EGAT
Interconnection
(Gurun - Khlong Ngae and Chuping - Sadao)
2
TNB – PGL
Interconnection
(Plentong-Senoko)
TNB-EGAT Interconnection
Gurun – Khlong Ngae 300kV HVDC Monopole Capacity of 300MW Mode of Operation: Power
Purchase
Chuping - Sadao 132kV HVAC Capacity of 80MW Mode of Operation: Energy
Transaction
1
Plentong-Senoko 275kV HVAC Capacity of 2x250MVA
(450MA) Mode of Operation: Energy
Exchange
2 TNB-PGL Interconnection
![Page 10: Chief of International Energy Cooperation Division](https://reader034.vdocument.in/reader034/viewer/2022042401/625d70488226b178005de181/html5/thumbnails/10.jpg)
2 x 275kV 250MVA HVAC circuits, comprising of underground cable and overhead line
Bi-directional power flow
Interconnection is for mutual support between 2 systems during system disturbances.
Not meant for energy exchange during normal operation, Total Energy Exchange within calendar month is settled on a monthly basis by netting to zero.
![Page 11: Chief of International Energy Cooperation Division](https://reader034.vdocument.in/reader034/viewer/2022042401/625d70488226b178005de181/html5/thumbnails/11.jpg)
The 1st Multilateral power trade in ASEAN
Size of Pilot project up to 100 MW
Representatives in LTMS-PIP Government
Electricity Utilities
Regulatory Commission
Mechanism LTMS WG (Working Group)
LTMS TTF (Technical Task Force)
![Page 12: Chief of International Energy Cooperation Division](https://reader034.vdocument.in/reader034/viewer/2022042401/625d70488226b178005de181/html5/thumbnails/12.jpg)
Technical Viability (Malaysia)
Commercial Arrangement (Thailand)
Legal & Regulatory (Singapore)
Tax & Tariff Structure (Lao PDR)
![Page 13: Chief of International Energy Cooperation Division](https://reader034.vdocument.in/reader034/viewer/2022042401/625d70488226b178005de181/html5/thumbnails/13.jpg)
Power Flow Control through interconnection:
Between Lao-Thailand: without power flow control (without ACE)
Between Thailand – Malaysia: controlled by pole control of HVDC
Between Malaysia – Singapore: AGC setting of Area Control Error (ACE)
Lao PDR
(L) Thailand
(T) Malaysia
(M) Singapore
(S)
115 kV HVAC 275 kV HVAC
450 MW 300 kV HVDC
300 MW
Note:
Lao-Thailand: TNL and PHT to NK, Paxan-BKN, Thakhek-NN, Pakbo-MD2, Bangyo-SRD all are 115 kV
Thailand – Malaysia: KNE-Gurun 300 kV 300 MW HVDC
Between Malaysia – Singapore: Plentong-Senoko 275 kV HVAC
TNL and PHT - NK
Paxan-BKN
Thakhek-NN
Pakbo-MD2
Bangyo-SRD
Plentong-Senoko KNE-Gurun
![Page 14: Chief of International Energy Cooperation Division](https://reader034.vdocument.in/reader034/viewer/2022042401/625d70488226b178005de181/html5/thumbnails/14.jpg)
Agreements :
1. Lao PDR and Singapore Power Purchase Agreement (L-S PPA)
2. Thailand and Singapore Wheeling Charge Agreement (T-S WCA)
3. Malaysia and Singapore Wheeling Charge Agreement (M-S WCA)
Lao PDR
(L) Thailand
(T) Malaysia
(M) Singapore
(S)
L-S
PPA
M-S
WCA
T-S
WCA
Wheeling Charge Agreement (WCA)
Power Purchase Agreement (PPA)
Conceptual energy flow from Lao PDR to Singapore through Thailand Grid and Malaysia Grid Seller
Country Purchaser
Country
Transit
Country Transit
Country
![Page 15: Chief of International Energy Cooperation Division](https://reader034.vdocument.in/reader034/viewer/2022042401/625d70488226b178005de181/html5/thumbnails/15.jpg)
Lao PDR
(L) Thailand
(T) Malaysia
(M) Singapore
(S)
Balancing Mechanism or Balancing Agreement
• To handle the energy difference, balancing mechanism is required.
• Due to performance of system control, an appropriate band for energy difference is
necessary and the energy difference which is not over the band may be treaded as energy
exchange between two countries.
• An extra charge (Balancing Charge) should apply on a period that the difference between
the scheduled energy and the exported energy (Δ1 for Seller Country), or the imported
energy and the exported energy (Δ2 and Δ3 for Transit Country) are exceed the band. In
addition, PPA between Seller and Purchaser should have the same balancing mechanism
to handle the difference between scheduled energy and imported energy (Δ4 for Purchaser
Country).
• Otherwise, all parties should have Balancing Agreement(s).
Δ2 x Balancing Charge Δ3 x Balancing Charge Δ1 x Balancing Charge Δ4 x Balancing Charge
![Page 16: Chief of International Energy Cooperation Division](https://reader034.vdocument.in/reader034/viewer/2022042401/625d70488226b178005de181/html5/thumbnails/16.jpg)
Wheeling
Charge
Transmission
Charge Loss Charge
Balancing
Charge
Administration
Charge + + ±
• Cost per MWh for
difference energy between
imported energy from Laos
and exported energy from Thailand to Malaysia
• General costs including
scheduling, system control,
coordination services, and billing
• Cost per MWh of
transferred energy
• Estimated from simulated
losses from importing and
exporting 100 MW and
forecasted system marginal cost
• Cost of transmission system
usage, which is based on MW-Mile concept
![Page 17: Chief of International Energy Cooperation Division](https://reader034.vdocument.in/reader034/viewer/2022042401/625d70488226b178005de181/html5/thumbnails/17.jpg)
TNB Wheeling Charge
Single Buyer Operations
System Operation and
Admin
Transmission Usage Charge
and Losses
Tax & Tariff
Balancing Charge
To recover the costs of billing, meter reading and administering of power purchase and power transfer contracts
To recover the costs of operating the power system and administering the safe and secure operation of the power system including but not limited to the cost of ancillary services
To recover the cost of transporting electricity through the power grid i.e. CAPEX, congestion cost, losses etc.
Applicable tax and tariff
Cost per MWh for difference energy between imported energy from Laos and exported energy from Thailand to Malaysia
(as proposed by EGAT, Thailand)
![Page 18: Chief of International Energy Cooperation Division](https://reader034.vdocument.in/reader034/viewer/2022042401/625d70488226b178005de181/html5/thumbnails/18.jpg)
EGAT
Wheeling
Charge
Transmission
Charge Loss Charge
Balancing
Charge
Administration
Charge + + ±
Transmission Usage Charge and Losses Single Buyer Operations
System Operation and Admin
Balancing Charge
TNB
![Page 19: Chief of International Energy Cooperation Division](https://reader034.vdocument.in/reader034/viewer/2022042401/625d70488226b178005de181/html5/thumbnails/19.jpg)
Import and Export TAX :
1. Import
• Import Duty • VAT
2. Export • Export Duty • VAT
Border
Thailand Foreign
Countries
Import : • Import Duty = 0% • VAT = 7%
Border
Thailand Foreign
Countries
Export : • Export Duty = 0% • VAT = 0%
- Lao PDR - Malaysia
- Lao PDR - Malaysia - Cambodia
![Page 20: Chief of International Energy Cooperation Division](https://reader034.vdocument.in/reader034/viewer/2022042401/625d70488226b178005de181/html5/thumbnails/20.jpg)
Purchasing Price
=
Proposed Selling Price
Wheeling Charge
+ Others
Wheeling Charge
+ Others
+ +
Singapore
Lao PDR
Malaysia Thailand
Concept of Electricity Tariff “Preliminary”
![Page 21: Chief of International Energy Cooperation Division](https://reader034.vdocument.in/reader034/viewer/2022042401/625d70488226b178005de181/html5/thumbnails/21.jpg)
Great hydropower potential from Lao PDR
A well established power pool market in Singapore
Reliable power transmission lines from
Lao PDR-Thailand, Thailand-Malaysia and Malaysia-Singapore
Existing Bilateral Power Purchase Agreement and experiences in cross – border power trade
Technical Expertise
Close Coordination among Governments, Public Utilities and Regulatory Commissions
Political Commitment
Sign MOU on LTMS – PIP by 4 Ministers
![Page 22: Chief of International Energy Cooperation Division](https://reader034.vdocument.in/reader034/viewer/2022042401/625d70488226b178005de181/html5/thumbnails/22.jpg)
ขอบคุณครับ