city council presentation may 4, 2016- foothill parkway westerly extension project

9
Simon Wong Engineering for Construction Management and Inspection Services

Upload: city-of-corona

Post on 11-Apr-2017

284 views

Category:

Government & Nonprofit


0 download

TRANSCRIPT

Simon Wong Engineering for 

Construction Management and Inspection Services

PROJECT IS NOW MORE THAN 70% COMPLETEAND WITHIN THE APPROVED BUDGET

Award of Contract on December 18, 2013Construction ……………………………………………………………….. $40,357,586.00Construction Management Services ……………………………… $2,500,000.00Environmental Mitigation & Support …………………………….  $4,000,000.00Geotechnical & Material Testing ……………………………………  $1,500,000.00QA/QC Surveying …………………………………………………………….. $250,000.00Contingency ………………………………………………………………….. $6,500,000.00Total Construction Cost ……………………………………………….. $55,107,586.00

Funding SourceSLPP Formula Fund ……………………………………………………….  $7,000,000.00Measure A Regional Arterial Fund ………………………………. $28,000,000.00Transportation Uniform Mitigation Fee Fund ………………… $9,000,000.00Street and Signal Fund …………………………………………………….. $505,000.00Gas Tax Fund ……………………………………………………………………. $754,586.00General Fund ………………………………………………………………… $5,000.000.00Water Utility Fund …………………………………………………………  $2,424,000.00Reclaimed Water Fund ………………………………………………….  $2,424,000.00

Negotiated Contract with Simon Wong Engineering for Construction Management and Inspection Services:

Term of the contract services:February 2014 through December 2015 for a total of 23 months.

$1,999,949.71

Anticipated Start Date May 2014Anticipated Completion Date December 2015

Foothill Parkway Westerly ExtensionTimeline

Notice to Proceed Issued 03/24/2015404 Permit issued by Corps of Engineers 03/26/2015New Required Start Date 03/30/2015Revised Required Completion Date 09/15/2016

Contractor  allowed to construct Improvements on  09/03/2014Border Avenue and Green River Road

All work complete that can be done without 404 Permit 11/10/2014

Ground Breaking Ceremony 03/26/2014Notified that Corps of Engineer’s 404 Permit not issued

Negotiated Contract with Simon Wong Engineering for Construction Management and Inspection Services $1,999,949.71

Term of the contract services from February 2014 through December 2015 for a total of 23 months.

Simon Wong reviewed submittals and changes to the plans prior to the start of construction as intended under the original scope of work.  They removed their team for several months when construction activity stopped, but did continue providing construction management support by reviewing additional changes to the project.

Length of contract services extended to December 2016 for a revised total of 36 months.   The negotiated increased amount of $493,160.88 represents 24% of the current contract, but is still within the budgeted amount approved by City Council for the project.

The revised total contract is now:  $2,493,110.59

Incurred costs are based upon actual expenditures.

Simon Wong Engineering will continue to provide Construction Management and Inspection Services that include:

• Review of change order requests• Resolution of claims• Processing monthly progress payments• Inspection of the bridge, road and landscaping

Anticipated Construction Completion is October 2016