Page 1: City Council Presentation May 4, 2016- Local Project Updates

1

Nelson D. NelsonPublic Works Director

May 4, 2016

Page 2: City Council Presentation May 4, 2016- Local Project Updates

2

Southwest Quadrant of Grand Boulevard Waterline Project – Phase 1Construction anticipated to be complete this month

Page 3: City Council Presentation May 4, 2016- Local Project Updates

3

2015-2016 CDBG Sidewalk ImprovementsConstruction continues through June

Page 4: City Council Presentation May 4, 2016- Local Project Updates

4

Sixth Street – Bridge work complete and final stripingMonday, May 9th

Page 5: City Council Presentation May 4, 2016- Local Project Updates

5

Grand Boulevard – Bridge, road and traffic signal completeMonday, May 9th

Page 6: City Council Presentation May 4, 2016- Local Project Updates

6

Lincoln Avenue – Closed nightly, lane reduction later in May

Page 7: City Council Presentation May 4, 2016- Local Project Updates

7

BNSF Closing 3 Roads For MaintenanceSmith Avenue – May 22nd to May 24th

Page 8: City Council Presentation May 4, 2016- Local Project Updates

8

BNSF ClosingSheridan Street – May 22nd to May 24th

Page 9: City Council Presentation May 4, 2016- Local Project Updates

9

BNSF ClosingRadio Road – May 22nd to May 24th

Page 10: City Council Presentation May 4, 2016- Local Project Updates

107

SR-91 CLOSURES2-WEEK LOOK AHEAD AT A GLANCE

Page 11: City Council Presentation May 4, 2016- Local Project Updates

11

Westbound SR-91: 2-Week Look Ahead8

Page 12: City Council Presentation May 4, 2016- Local Project Updates

12

Eastbound SR-91: 2-Week Look Ahead9

Page 13: City Council Presentation May 4, 2016- Local Project Updates

13

May 4, 2016