city of delano · t:\0564 delano\180 - 2016 pavement project\01-feasibility report\final...
TRANSCRIPT
CITY OF DELANO
REQUEST FOR ACTION
Department Head
Vince Vander Top, City Engineer
City Council Date
January 5, 2016
Agenda Item
2016 Infrastructure Improvements Feasibility Report
ACTION REQUESTED Accept Feasibility Report and order plans and specifications BACKGROUND The City Council and staff have discussed the 2016 Infrastructure Improvements on several occasions. Discussions have centered on:
- Street reconstruction including street width options and pavement rehabilitation options - Prioritization of streets - Sidewalks and trails - Storm sewer Improvements - Sanitary sewer and water main improvements - Parking lot improvements - Downtown Streetscape plans
The council has held joint meetings with the Water, Light, and Power Commission to discuss project scope, projected costs, and revenues. Assessments will not be used as a revenue source, with the exception of 1 property located on a project street which is part of Franklin Township. Council requested that a neighborhood meeting be held to present the preliminary information in the feasibility report. A neighborhood meeting is scheduled for January 5th, at 7:00 pm or soon after during the regular council meeting. All properties along the proposed improvements have been notified. A copy of the notification is attached. We will present the feasibility report and feedback received from the neighborhood meeting at the regular council meeting on January 5th. We request that council discuss the contents of the report and recommend changes if desired. After discussion, we will request that council accept the feasibility report by motion and authorize the preparation of plans and specs including the completion of soil investigations (borings). ATTACHMENTS Neighborhood meeting notification letter. Feasibility Report
WENCK File #0564-0180 December 2015
Prepared for:
City of Delano
234 2nd Street North Delano, MN 55328
Prepared by: WENCK Associates, Inc. 1800 Pioneer Creek Center Maple Plain, MN 55359 Phone: 763-479-4200 Fax: 763-479-4242
Feasibility Report for 2016 Infrastructure Project
November 2015 i
T:\0564 Delano\180 - 2016 pavement project\01-feasibility report\final report\Final_Feasibility Report_2015.docx
Table of Contents 1.0 INTRODUCTION ................................................................................ 1-1
1.1 Background: ............................................................................. 1-1 1.2 Purpose of this Report ............................................................... 1-2
2.0 FIELD OBSERVATIONS AND MEASUREMENTS ................................... 2-1
2.1 General .................................................................................... 2-1 2.2 Street (Pavement) and Curb Condition ......................................... 2-1 2.3 Sanitary Sewer Condition ........................................................... 2-2 2.4 Watermain Condition ................................................................. 2-3 2.5 Storm Sewer Condition .............................................................. 2-4
3.0 IMPROVEMENTS ............................................................................... 3-1
3.1 Street (Pavement), Sidewalks and Curb ....................................... 3-2 3.1.1 Width .......................................................................... 3-2 3.1.2 Parking ........................................................................ 3-2 3.1.3 Sidewalks and Trails ...................................................... 3-2 3.1.4 Alleys .......................................................................... 3-3
3.2 Sanitary Sewer ......................................................................... 3-3 3.2.1 All Castings and Adjustment Rings .................................. 3-3 3.2.2 Sanitary Sewer Service Inspection .................................. 3-3 3.2.3 Franklin Ave/1st Street Area ............................................ 3-3 3.2.4 Merriman Dr./Buffalo St/Elk St/Bridge Ave ....................... 3-3 3.2.5 2nd Street/3rd Street/Railroad Ave .................................... 3-4
3.3 WaterMain ................................................................................ 3-4 3.3.1 Franklin Ave/1st Street Area ............................................ 3-4 3.3.2 Merriman Dr./Buffalo St/Elk St/Bridge Ave ....................... 3-4 3.3.3 2nd Street/3rd Street/Railroad Ave .................................... 3-5
3.4 Storm sewer ............................................................................. 3-5 3.4.1 Franklin Ave/1st Street Area ............................................ 3-5 3.4.2 Merriman Dr./Buffalo St/Elk St/Bridge Ave ....................... 3-5 3.4.3 2nd Street/3rd Street/Railroad Ave .................................... 3-6
3.5 Other Improvements ................................................................. 3-6 3.5.1 Downtown Streetscape Plan ........................................... 3-6 3.5.2 Downtown Parking Lot ................................................... 3-6 3.5.3 Ditch Improvements ...................................................... 3-7
4.0 EASEMENTS AND RIGHT OF WAY ...................................................... 4-1
5.0 PERMITS ........................................................................................... 5-1
6.0 ASSESSMENTS .................................................................................. 6-1
7.0 REVENUES AND EXPENSES ............................................................... 7-1
November 2015 ii
T:\0564 Delano\180 - 2016 pavement project\01-feasibility report\final report\Final_Feasibility Report_2015.docx
8.0 FEASIBILITY AND RECOMMENDATIONS ........................................... 8-1
9.0 PROJECT SCHEDULE .......................................................................... 9-1
TABLE Table 1 – Summary of Cost Table 2 – Detailed Cost Estimate Table 3 – Summary of Right of Way/Easement Needs Table 4 – Preliminary Assessment Role FIGURES Figure 1 – Capital Improvement Plan (CIP) Figure 2 – Typical Streetscape Details Figure 3a – Trail improvements Figure 3b – Trail Improvements Figure 4 – Ditch Improvements Figure 5 – Franklin Ave Right of Way/Easement Needs Figure 6 – Railroad Ave Right of Way/Easement Needs APPENDICES Appendix A – Project Area Improvement Detail Sheets G-101 ................................. Cover Sheet G-102 ............. Pavement Ranking System G-103………………….Typical Street Sections C-101 ........... Railroad Ave E 0+00-10+50 C-102 ......... Railroad Ave E 10+50-21+50 C-103 .................. Railroad Ave E 21+50 - C-104 ........................................ S 2nd St C-105 .................. 1st Street 0+00-10+50 C-106 .... 1st Street/Franklin 10+50-20+50 C-107 ............................ Franklin 20+50-
C-108 .............Bridge Ave W 0+00-10+50 C-109 .................... Bridge Ave W 10+50- C-110 ............ Buffalo Street 0+00-10+50 C-111 .......... Buffalo Street 10+50-20+50 C-112 ................... Buffalo Street 20+50- C-113 ......... Merriman Drive 0+00-11+50 C-114 ....... Merriman Drive 11+50-19+90 C-115 .................. Merriman Ct and Elk St
Wenck Associates, Inc. | 1800 Pioneer Creek Center | P.O. Box 249 | Maple Plain, MN 55359-0249
Toll Free 800-472-2232 Main 763-479-4200 Email [email protected] Web wenck.com
January 5, 2016 Phil Kern City Administrator City of Delano 234 2nd Street North Delano, MN 55328 RE: Feasibility Report for 2016 Infrastructure Project Wenck File #0564-180 Dear Mr. Kern: Enclosed is the Feasibility Report for the 2016 Infrastructure Improvements Project. Sincerely, Wenck Associates, Inc. Heather Libby, PE Shawn Louwagie, EIT MN Registration #45801
December 2015 1-1
T:\0564 Delano\180 - 2016 pavement project\01-feasibility report\final report\Final_Feasibility Report_2015.docx
1.0 Introduction
The City of Delano has evaluated the overall condition of its infrastructure including pavement, curb & gutter, sidewalks, sanitary sewer, and storm sewer in recent years. This evaluation has occurred over several years and now serves as the basis for the City’s infrastructure management plan. 1.1 BACKGROUND:
In 2003, the City hired a consultant to rank the pavement condition of all city streets. The final report also included the evaluation of some utilities including sanitary sewer. Recommendations were provided for pavement rehabilitation and general costs were estimated.
Starting in 2009, the City revisited and updated previous rankings. Recommendations for pavement rehabilitation were updated and construction costs estimated. Several iterations of Pavement Capital Improvement Plans (CIPs) were produced to evaluate project staging and impacts to the City’s general budget and bonding capacity.
The City of Delano was added to the State of MN Municipal State Aid (MSA) system in 2007/08. Since that time, the City has been evaluating the best possible local state aid road system to maximize revenues through the state and enable efficient use of the funds toward the rehabilitation/reconstruction of key city streets. The state will be modifying the MSA needs calculation in the upcoming year. This report and project will include modifications to the City MSA system in anticipation of those changes.
In 2009, City staff and Council revisited the City’s special assessment policy. The Council concluded to not include special assessments as a revenue source for street and infrastructure reconstruction
The Capital Improvement Plan (CIP) staging plan was finalized in 2012 and the first project was started in 2013. The staging plan anticipates 4 additional infrastructure projects, including the 2016 project, staged over a period of 15 years. A CIP staging map is attached as Figure 1. This report addresses possible streets to be included in Project #2 (the 2016 project). This Council and future Councils will maintain the flexibility to advance or delay streets pending needs and the City’s financial capacity.
Delano Public Works revaluated all street pavement conditions in 2015. These rankings served as the basis for the CIP. The City Street Superintendent utilized MN Asphalt Pavement Association (MAPA) ranking method. Pavement ranking information was entered into the City’s GIS database. Utilizing City staff to complete these rankings was cost-effective and enables the same individuals to update the rankings at any time the City chooses.
Delano Public Works has televised the entire sanitary sewer identified within the limits of Project #2, and is finishing the televising of the storm sewer within the project.
Delano Public Works has located all manhole structures with a GPS unit. Staff has also completed a visual inventory of all manhole structures documenting the condition of the structure, rings, and castings. All data is kept and is accessible in the City’s GIS. This field work and data collection was completed in 2012 and is updated as necessary.
December 2015 1-2
T:\0564 Delano\180 - 2016 pavement project\01-feasibility report\final report\Final_Feasibility Report_2015.docx
All curb and gutter and sidewalk within the area identified as Project Area #2 to be anticipated for work in 2016 were evaluated in the fall of 2015. Estimates for repair and replacement are included in this report.
The anticipated streets to be improved in this project have been shared with Delano Municipal Utility (DMU) staff. Several meeting with DMU staff have identified water main replacement/upgrades deemed necessary in this project area.
1.2 PURPOSE OF THIS REPORT This report is based on the previous work completed by City staff and Council. The purpose of this report is to identify necessary infrastructure improvements, options for improvement, estimated construction and project costs, possible sources of revenue to complete the project, as well as, a project schedule to complete the work. This report presents our finding on the proposed infrastructure improvements for the area identified as Project #2 in previous plans, including 3rd Street N from Railroad Ave to Bridge Ave. This street segment was not previously identified to be included in Project #2.
December 2015 2-1
T:\0564 Delano\180 - 2016 pavement project\01-feasibility report\final report\Final_Feasibility Report_2015.docx
2.0 Field Observations and Measurements
2.1 GENERAL Public Works, DMU staff and Engineering staff have evaluated the existing condition of the overall infrastructure for Project #2 including pavement, curb & gutter, sidewalks, sanitary sewer, storm sewer and water main. 2.2 STREET (PAVEMENT) AND CURB CONDITION Public Works staff rated all the city streets in 2015 based on the Minnesota Asphalt Pavement Association (MAPA) pavement rating system. The pavement ratings were categorized as following:
80-100, normal maintenance 69-79, mill and overlay 33-69, reclamation 0-32, reconstruction
The 2016 infrastructure improvements are initially based on the street ratings. Sheet G-102 displays the overall project plan area and identifies the type of repair proposed for that section of roadway. The curb for the entire project area was visually evaluated. The table below summarizes the existing street ratings and the condition of the existing curb:
Street Name From/To Bituminous
Rating Curb
Condition
Street Improvement
(based on bituminous rating)
1st Street County Rd 30 to Franklin 21 Replace Reconstruct 2nd Street Bridge Ave to Railroad Ave 25 Replace Reconstruct 3rd Street Bridge Ave to Railroad Ave 25 Replace Reconstruct 72nd Street HWY 12 to Merriman Drive Gravel N/A Reconstruct Bridge Ave Hwy 12 Merriman Dr. 72 Spot Repair Mill/Overlay Bridge Ave Buffalo to End 17 Replace Reconstruct
Buffalo St 72nd Street To Merriman Dr. 46 No curb Reclaim
Buffalo St Merriman Dr. to Bridge Ave 50 Spot Repair Reclaim Elk St Merriman Dr. to end 48 Replace Reclaim
Franklin Ave 1st St to East End 22 Partial Replace Reconstruct
Franklin Ave West End to 1st Street 32 Replace Reconstruct Merriman Ct Merriman Dr. to Cul-de-sac 29 Replace Reconstruct Merriman Dr. Buffalo to Elk 38 Replace Reclaim Merriman Dr. Elk to Merriman Ct 16 Replace Reconstruct Merriman Dr. Merriman Ct to End 83 Spot Repair Routine Maint.
December 2015 2-2
T:\0564 Delano\180 - 2016 pavement project\01-feasibility report\final report\Final_Feasibility Report_2015.docx
Street Name From/To Bituminous
Rating Curb
Condition
Street Improvement
(based on bituminous rating)
Merriman Dr. End to 72nd St N/A N/A New Construction Railroad Ave River St to 2nd St 32 Replace Reconstruct Railroad Ave 2nd St to 3rd St 32 Replace Reconstruct Railroad Ave 3rd St to 4th St 32 Replace Reconstruct Railroad Ave 4th St to Tiger Dr. N/A N/A New Construction
2.3 SANITARY SEWER CONDITION Public Works performed televising of the sanitary sewer for the entire project area. Additionally each manhole was rated. The data is maintained in the City’s GIS and is available for further evaluation. Based on the televising and manhole ratings the sanitary sewer has been rated as follows:
Street Name From/To Type of Sewer
Sewer Condition
Street Improvement
(based on sewer repair needs)
1st Street County Rd 30 to Franklin Clay Replace Reconstruct 2nd Street Bridge Ave to Railroad Ave Clay Line Reconstruct
3rd Street Bridge Ave to Railroad Ave Clay Line w/ Spot
Repairs Reconstruct 72nd Street HWY 12 to Merriman Dr. N/A Install New Reconstruct Bridge Ave Hwy 12 Buffalo St PVC Acceptable Mill/Overlay
Bridge Ave Buffalo St to End Clay Line w/ Spot
Repairs Reconstruct Buffalo St 72nd St To Merriman Dr. Clay/PVC Line Reclaim Buffalo St Merriman Dr. to Bridge Ave Clay Line Reclaim Elk St Merriman Dr. to end N/A Install New Reconstruct* Franklin Ave 1st St to East End Clay Replace Reconstruct Franklin Ave West End to 1st Street Clay Replace Reconstruct Merriman Ct Merriman Dr. to Cul-de-sac PVC Acceptable Reconstruct Merriman Dr. Buffalo to Elk Clay Remove Sewer Reconstruct* Merriman Dr. Elk to Merriman Ct PVC Replace Section Reconstruct Merriman Dr. Merriman Ct to End PVC Acceptable Reconstruct Merriman Dr. End to 72nd St N/A Install New New Construction Railroad Ave River St to 2nd St Clay Line Reconstruct Railroad Ave 2nd St to 3rd St Clay Replace Reconstruct Railroad Ave 3rd St to 4th St N/A Install line Reconstruct Railroad Ave 4th St to Tiger Dr. N/A Install New New Construction
* indicates that street improvement changed as a result of sewer repair need
December 2015 2-3
T:\0564 Delano\180 - 2016 pavement project\01-feasibility report\final report\Final_Feasibility Report_2015.docx
2.4 WATERMAIN CONDITION The condition of the watermain in the project area was determined by meeting with Delano Municipal Utility interim general manager Paul Twite, and other staff. Further revisions to the watermain improvement are being considered. The table below outlines the existing condition and recommended improvement for the watermain in each street:
Street Name From/To
Approx. Install Year
Pipe Material Water
Condition
Street Improvement
(based on water repair needs)
1st Street County Rd 30 to Franklin 1970’s CIP Replace Reconstruct 2nd Street Bridge Ave to Railroad Ave 1960’s Transite Replace Reconstruct 3rd Street Bridge Ave to Railroad Ave 1960’s CIP Replace Reconstruct 72nd Street HWY 12 to Merriman Dr. N/A N/A New Construct Reconstruct Bridge Ave Hwy 12 to Buffalo St 1960’s CIP Replace Reconstruct* Bridge Ave Buffalo St to End 1960’s CIP Replace Reconstruct Buffalo St 72nd Street To Merriman Dr. 1985 DIP Partial Replace Reclaim Buffalo St Merriman Dr. to Bridge Ave 1960’s CIP Replace Reconstruct* Elk St Merriman Dr. to end 1960’s CIP Replace Reconstruct*
Franklin Ave 1st St to East End 1960’s Transite Replace
(upsize) Reconstruct
Franklin Ave West End to 1st Street 1970’s CIP Replace
(upsize) Reconstruct Merriman Ct Merriman Dr. to Cul-de-sac 1985 DIP Acceptable Reconstruct Merriman Dr. Buffalo to Elk 1960’s CIP Replace Reconstruct* Merriman Dr. Elk to Merriman Ct 1985 DIP Acceptable Reconstruct Merriman Dr. Merriman Ct to End 1985 DIP Acceptable Reconstruct Merriman Dr. End to 72nd St N/A N/A Install New New Construction Railroad Ave River St to 2nd St 1960’s CIP Replace Reconstruct Railroad Ave 2nd St to 3rd St 1960’s CIP Replace Reconstruct Railroad Ave 3rd St to 4th St N/A N/A Install New Reconstruct Railroad Ave 4th St to Tiger Dr. 1960’s Transite Replace New Construction
* indicates that street improvement changed as a result of water repair need
December 2015 2-4
T:\0564 Delano\180 - 2016 pavement project\01-feasibility report\final report\Final_Feasibility Report_2015.docx
2.5 STORM SEWER CONDITION The storm sewer manholes, visible pipes and catch basins have been surveyed and are shown on the Drawings. Below is a summary of the currently condition of storm sewer in the project area. Public Works is still televising pipes to determine condition of storm sewer pipes and connections. Street Name From/To Condition Recommended Action
1st Street County Rd 30 to Franklin Fair Partial replacement, add inlets, install draintile
2nd Street Bridge Ave to Railroad Ave Good Minor repairs 3rd Street Bridge Ave to Railroad Ave Fair Replace structures, piping 72nd Street HWY 12 to Merriman Dr. -- No action needed, rural section Bridge Ave Hwy 12 to Buffalo St Fair Partial replacement, add inlets Bridge Ave Buffalo to End Poor Replacement, add inlets Buffalo St 72nd Street To Merriman Dr. -- No action needed, rural section Buffalo St Merriman Dr. to Bridge Ave -- Add inlets Elk St Merriman Dr. to end -- No action required
Franklin Ave 1st St to East End Fair Partial replacement, add inlets, install draintile
Franklin Ave West End to 1st Street -- Add inlets, install draintile Merriman Ct Merriman Dr. to Cul-de-sac Fair Partial replacement Merriman Dr. Buffalo to Elk -- No action required Merriman Dr. Elk to Merriman Ct Fair Partial replacement Merriman Dr. Merriman Ct to End Good Minor repairs Merriman Dr. End to 72nd St -- No action required Railroad Ave River St to 2nd St Good Minor repairs Railroad Ave 2nd St to 3rd St Good Minor repairs Railroad Ave 3rd St to 4th St Poor Partial replacement
Railroad Ave 4th St to Tiger Dr. -- Install new storm sewer system
Good – no repairs required Fair – spot repairs required
Poor – major repairs required -- No existing storm sewer is present
December 2015 3-1
T:\0564 Delano\180 - 2016 pavement project\01-feasibility report\final report\Final_Feasibility Report_2015.docx
3.0 Improvements
Based on the analysis of the infrastructure condition; a summary table of the proposed improvements is as follows:
Street Name From/To
Curb and Gutter
Sanitary Sewer Watermain
Storm Sewer
Resulting Street
Improvement
1st Street County Rd 30 to Franklin Replace Replace Replace
Partial Replacement Reconstruct
2nd Street Bridge Ave to Railroad Ave Replace
Able to line
Replace
Minor Repairs Reconstruct
3rd Street
Bridge Ave to Railroad Ave
Replace
Line w/ Spot Repairs
Replace
Partial Replacement
Reconstruct
72nd Street HWY 12 to Merriman Dr. N/A (rural)
New Construction
New Construction
N/A, Rural Section Reconstruct
Bridge Ave Hwy 12 to Buffalo St Replace
No issues
Replace
Partial Replacement Reconstruct*
Bridge Ave Buffalo to End Replace Line w/ Spot Repairs
Replace
Partial Replacement Reconstruct
Buffalo St 72nd Street To Merriman Dr. N/A (rural)
Able to line
Partial Replace
N/A, Rural Section Reclaim
Buffalo St Merriman Dr. to Bridge Ave Replace
Able to line
Replace Add inlets Reconstruct*
Elk St Merriman Dr. to end Replace
Install New
Replace No action Reconstruct*
Franklin Ave 1st St to East End Partial replace
Replace
Replace (upsize)
Partial Replacement Reconstruct
Franklin Ave West End to 1st Street Replace
Replace
Replace (upsize)
Partial Replacement Reconstruct
Merriman Ct Merriman Dr. to Cul-de-sac Replace
Acceptable
Acceptable
Partial Replacement Reconstruct
Merriman Dr. Buffalo to Elk Replace
Remove segment
Replace No action Reconstruct*
Merriman Dr. Elk to Merriman Ct Replace
Replace segment
Acceptable
Partial Replacement Reconstruct
Merriman Dr. Merriman Ct to End
Spot Repairs
Acceptable
Acceptable
Minor repairs Reclaim
Merriman Dr. End to 72nd St
New Construction
New Construction
New Construction No action
New Construction
Railroad Ave River St to 2nd St Replace Able to line Replace Minor
repairs Reconstruct
Railroad Ave 2nd St to 3rd St Replace Replace Replace Minor
repairs Reconstruct
Railroad Ave 3rd St to 4th St Replace Install line Install New Partial
Replacement Reconstruct
Railroad Ave 4th St to Tiger Dr. New Construction
New Construction
Replace
New Construction
New Construction
* indicated that street improvement changed as a result of a utility improvement
December 2015 3-2
T:\0564 Delano\180 - 2016 pavement project\01-feasibility report\final report\Final_Feasibility Report_2015.docx
3.1 STREET (PAVEMENT), SIDEWALKS AND CURB The pavement section for each street is based on the City of Delano standard street detail as shown in Appendix A. The pavement sections shown are from the 2013 Infrastructure Improvements Project, which contains similar traffic loading and assumed subgrade material. Actual pavement sections may vary depending on soil boring results which would be obtained during the design phase. 3.1.1 Width Measurements were taken of the existing street width during the street ratings process. On streets that are slated for reconstruction, the road will be reconstructed to the city standard width of 32-feet measured from face of curb to face of curb. The exceptions to this are the east end of Franklin Ave and the west end of Bridge Ave, which will be reconstructed to a rural section with a width of 24-feet measured from the edges of the bituminous. Downtown streetscape areas will be constructed in accordance with the approved streetscape plans. Streets that are identified as reclamation will be restored to the existing street width. 3.1.2 Parking Below is a summary of street widths and available street parking. Additionally, if a street is identified as a local collector the guidelines for State Aid should be followed for parking requirements.
Total Width* with No
Parking (feet)
Total Width* with Parking on One
Side (feet)
Total Width* with Parking on Both
Sides
City Standard 24 28 32 Local Collector Roads1 (State Aid Standard) 26 32 38 *total width is from face-to-face of curbs 1Railroad from River Street to Tiger Dr. is identified as a local collector road
Parking would be available with all proposed street widths with the exception of the portions of Franklin Avenue and Bridge Avenue identified to have a width of 24-feet, and Buffalo Street. 3.1.3 Sidewalks and Trails Existing sidewalk condition was evaluated along roads within the project area. Replacement areas are shown on Sheets included in Appendix A. In general, sidewalks will not be added on streets where a sidewalk does not currently exist. However a pedestrian sidewalk is recommended along 1st Street and Franklin Avenue and is shown in Appendix A. The following trail connections have been included as improvements (see Figures 3a and 3b):
1. 2nd St SW (located in Clover Springs) to the west end of Franklin Avenue 2. The east end of Franklin Avenue to Hwy 12 3. Along Hwy 12, north of the railroad bridge to Bridge Ave. (west side of Hwy 12) 4. Railroad Ave/Tiger Dr. intersection to Elm Ave. (west side of Tiger Dr.)
December 2015 3-3
T:\0564 Delano\180 - 2016 pavement project\01-feasibility report\final report\Final_Feasibility Report_2015.docx
3.1.4 Alleys Consistent with past projects, the city has tried to pave existing gravel alley ways which are located close to infrastructure improvements projects. The alley located between Railroad Ave/Bridge Ave and 3rd Street/4th Street has been identified to be paved. 3.2 SANITARY SEWER The condition of the existing sanitary sewer has been evaluated. Inspections were conducted the fall of 2015 on all of the structures located in the project streets to evaluate the condition of the structure, steps, rings and castings. The sanitary sewer mains have been televised and the tapes reviewed for issues.
3.2.1 All Castings and Adjustment Rings All sanitary castings and adjustment rings within Project #2 will be removed and replaced, including castings on structures not identified for replacement. This will not only assist with matching the new pavement surface, but also reduce infiltration/inflow (I/I) sources. 3.2.2 Sanitary Sewer Service Inspection The City Council has adopted an ordinance that will require video inspection of sanitary sewer services at the time of a street reconstruct. This inspection will be done regardless if the main will be replaced as part of the street project or is identified for a future lining project. If a service line is identified as in need of repair, the homeowner will be given the option to have the work done by the contractor which is awarded the reconstruct project, or to hire a contractor themselves to complete the work.
3.2.3 Franklin Ave/1st Street Area Lowering the existing sanitary sewer through the wetland between Rockford Road and 1st Street should be considered. When the HWY 12 project was completed the manhole at Rockford Ave. was constructed with an outside drop in the structure, which allows the upstream pipe to be lowered. The current sanitary pipe through the wetland has minimal cover, lowering this pipe would increase the burial depth. Additional sanitary improvements in this area include replacement of all sanitary structures, sanitary sewer main, and services to the Right of Way along 1st street and Franklin Ave. 3.2.4 Merriman Dr./Buffalo St/Elk St/Bridge Ave The existing sanitary sewer between Buffalo Street and Elk St currently does not have any services attached to it. All properties along this segment of Merriman Dr. have sewer service stubs from other streets. This section of pipe is able to be removed. A section of sanitary sewer main to the west of Elk St will be replaced to eliminate a backflow issue in the line. Sanitary sewer work on Buffalo St and Bridge Ave is minimal with a recommended replacement of a structure, the placement of a new structure, and a spot repair on the main to fix an offset joint. There is currently no sanitary sewer located in Elk St. A sanitary main is recommended to be installed beyond the end of Elk St to allow for a future connection.
December 2015 3-4
T:\0564 Delano\180 - 2016 pavement project\01-feasibility report\final report\Final_Feasibility Report_2015.docx
3.2.5 2nd Street/3rd Street/Railroad Ave It was discovered during the 2013 infrastructure improvements project that there are sanitary sewer services connected to the storm sewer. These services are assumed to be located along Railroad Ave between 2nd and 3rd Street. The sanitary/storm connection will be removed and the sanitary sewer service will be connected to the sanitary main. The sanitary sewer in 3rd St is clay and has no major issues, and is a good candidate for a future lining project. There is a service wye that is protruding into the main and should be corrected to prevent infiltration issues or begins to takin in material which would undermine the street. The sanitary sewer in Railroad Ave to the east of 4th St is served through a main that runs through the Mt. Olive property, and ends at the property owned by RNP Properties. It is recommended to extend the sanitary sewer main to the east and the west along Railroad Ave and provide future connections for the properties which currently do not have city sewer. 3.3 WATERMAIN City staff has collaboratively worked with DMU staff to assess and determine watermain issues, age, materials, and corrective actions needed. The majority of the watermain located in the project streets is approximately 50+ years old, with three streets known to have transite watermain still in place. 3.3.1 Franklin Ave/1st Street Area The water service connections to the watermain located on 1st St are known to have issues, and are prone to leak. The watermain and service lines have been in place since the 1970’s. The existing watermain in Franklin Ave consists of a 6” transite main. As part of the Hwy 12 project, a 12” watermain connection stub was installed. The Highland Ridge development to the west of Franklin Ave also installed a 12” watermain. Replacing the existing 6” transite watermain to a 12” and making a connection to the watermain located in Highland Ridge would improve balanced water pressure and improve the system through this area. 3.3.2 Merriman Dr./Buffalo St/Elk St/Bridge Ave The majority of the watermain located in this area has been in place since the 1960’s. The exception to this is the watermain located in the north end of Buffalo St and in Merriman Dr. to the west of Elk Ave, which was installed in 1985. The replacement of the watermain, service lines, curb stops, and hydrants for all of the watermain installed prior to 1985 should be considered. The watermain located on Elk St and Bridge Ave are dead end lines. The installation of a watermain loop from the south end of Elk St to the west end of Bridge Ave would loop these two systems and improve the water quality and pressure to the residents serviced from these lines.
December 2015 3-5
T:\0564 Delano\180 - 2016 pavement project\01-feasibility report\final report\Final_Feasibility Report_2015.docx
3.3.3 2nd Street/3rd Street/Railroad Ave The watermain located in 2nd St is transite material and has been in place since the 1960’s. A section of the transite main was replaced near Bridge Ave as part of the 2013 Infrastructure Improvements project. It is recommended to replace the transite watermain through this area. The watermain in 3rd St was installed at the same time as the surrounding area and has been in place since the 1960’s. It is recommended to replace the watermain, service lines, curb stops, and hydrants located along 3rd St during the reconstruction process. The watermain located in Railroad Ave has been in place since the 1960’s, with no existing watermain between 3rd St and 4th St. The replacement of the watermain, service lines, curb stops, and hydrants throughout from River St to Tiger Dr. should be considered with new watermain installed between 3rd and 4th St. 3.4 STORM SEWER Partial evaluation of the existing storm sewer system located in the project area has been completed to include inspection of the existing structures. There are areas which are known to have drainage issues, inlet capacity issues, and high water tables. 3.4.1 Franklin Ave/1st Street Area This area is known to have high groundwater elevation which impacts subgrade and pavement conditions. An existing sump line connection is run along the west side of 1st St to directly connect sump lines from the residents directly to the storm sewer system, which reduces the amount of moisture introduced into the subgrade. Additionally, there is a limited capacity and ponding issue during rain events. It is recommended to replace the existing storm sewer system, install additional inlets at the intersection of Franklin Ave/1st St, and at the sanitary sewer crossing through the wetland. 3.4.2 Merriman Dr./Buffalo St/Elk St/Bridge Ave There is a minimal amount of storm sewer located throughout this area, with drainage conveyed in and out of the wetlands located near these streets. The intersection located at Bridge Ave/Buffalo St is known to have limited capacity and ponding issues during rain events. This is due to the fact that it is the only inlet location for Bridge Ave, Buffalo Ave located between Bridge and Merriman, and Merriman to the east of Elk St. The only other storm sewer in this area is located on Merriman Dr. from Merriman Ct to the south where it discharges into a wetland located behind the property at 523 Merriman Dr. There is a capacity issue during storm events near this property. The replacement of the existing storm sewer located at the intersection of Buffalo St/Bridge Ave is recommended, with upsized pipes to accommodate increased storm water capacity. Additional inlets are recommended to be installed on Bridge Ave to the west of this intersection, and on Buffalo St to the north of this intersection. The portion of Buffalo St to the north of Merriman Dr. is currently a rural section with ditches located along the road for drainage. This is proposed to remain the same with no change in storm water flows from this area.
December 2015 3-6
T:\0564 Delano\180 - 2016 pavement project\01-feasibility report\final report\Final_Feasibility Report_2015.docx
The replacement of the storm sewer system located on Merriman Dr. is recommended, with further investigation to determine the cause for the capacity issue. The issue may be due to pipe sizing or an obstruction located at the pipe outlet. 3.4.3 2nd Street/3rd Street/Railroad Ave There is a known sanitary sewer service connection to the storm sewer system located on 2nd St. Further investigation as to the number of connections and the location of connections is required. The storm sewer running along Railroad Ave between River St and 4th St is located approximately 8.5’ south of the south curb line, with stubs to catch basins located in the curb line. The condition of the main line is good with one spot repair done by public works employees. There is storm sewer located in the alley between 3rd St/4th St and Railroad Ave/Bridge Ave. This storm sewer line is shallow and is in need of repair. From conversations with Public Works staff, it is possible that the storm sewer located in this alley may connect to the storm sewer system on 3rd St. Additional investigation into existing connections from buildings and other storm lines needs to be completed. It is recommended at a minimum to replace the storm lines and structures located in the alley. The extension of Railroad Ave to Tiger Dr. will require the installation of a new storm sewer system. This would be installed in conjunction with the new street extension. In addition, the Minnesota Pollution Control Agency requires any project that creates over 1 acre of additional impervious surface to construct a permanent stormwater treatment system, or a stormwater pond. The extension of Railroad Ave from 4th St to Tiger Dr. would require the construction of a stormwater pond. The exact location of the stormwater pond has not been determined. 3.5 OTHER IMPROVEMENTS 3.5.1 Downtown Streetscape Plan Costs have been provided to reconstruct the downtown areas (Railroad Avenue from River Street to 3rd Street and 2nd Street) in accordance with the “Downtown Streetscape Plan” prepared by SRF in 2006. See the attached Figure 2 depicting the nature of the streetscape improvements. The improvements include sidewalks, street width of 39-feet which is consistent with the streetscape plan, decorative lighting, and trees. Additionally, the parking lot located at the southeast corner of River St and Railroad Ave has been included in the cost estimate. The revisions to the parking lot are shown in Appendix A and utilize drive in angled parking as shown in Figure 2. 3.5.2 Downtown Parking Lot The City is working towards executing leases with the property owners of the parking lot located between River Street/2nd Street & Railroad Ave/Bridge Ave. to take over management of this lot. If successful, the city would like to include work on this parking lot and reconfigure striping to maximize the number of parking spaces. Improvements to this lot would include the reconstruction of the pavement section and evaluation and potential replacement of the storm sewer system.
December 2015 3-7
T:\0564 Delano\180 - 2016 pavement project\01-feasibility report\final report\Final_Feasibility Report_2015.docx
3.5.3 Ditch Improvements City Public Works staff has been performing maintenance on the ditch located south of Elm Avenue to the west of Tiger Drive. This ditch abuts the rear yards of residential properties located along the ditch. The construction techniques needed and equipment necessary to complete the ditch cleaning often results in disturbance to the surrounding properties. Figure 4 shows a proposed alignment to install piping through the ditch section, and eliminate the need for ditch cleaning through this area.
December 2015 4-1
T:\0564 Delano\180 - 2016 pavement project\01-feasibility report\final report\Final_Feasibility Report_2015.docx
4.0 Easements and Right of Way
There are two areas identified in the project area where there is an existing roadway but an easement or right of way over the area is not defined. The areas identified include the east end of Franklin Ave, and Railroad Ave between 4th Street and Tiger Drive. Figures 5 and 6 show the right of way or easement needs for these two areas. The City Council has adopted a resolution declaring the existence of public right-of-way at Railroad Avenue between 4th St and Tiger Dr. This resolution is in regards to an existing “cartway” that has been identified in a License Agreement from the Great Northern Railroad Company for a roadway. This resolution applies to the properties along the south edge of the proposed street extension to Tiger Dr. The remaining properties along Railroad Avenue and Franklin Avenue will require temporary and permanent easements for the construction of the proposed streets. Easement/Right of Way costs are currently being negotiated with each property owner. Table 3 summarizes the right of way and easement needs for the project.
December 2015 5-1
T:\0564 Delano\180 - 2016 pavement project\01-feasibility report\final report\Final_Feasibility Report_2015.docx
5.0 Permits
Permits are required from the following agencies:
Minnesota Pollution Control Agency (MPCA) o Construction Stormwater Permit o Sanitary Sewer Extension Permit
Minnesota Department of Health o Watermain Extension Permit
Minnesota Department of Transportation o Work with in MNDOT right of way
Department of Natural Resources o Permit for temporary wetland impacts
No public or private utilities within privately held easements are known to be impacted with the proposed improvements.
December 2015 6-1
T:\0564 Delano\180 - 2016 pavement project\01-feasibility report\final report\Final_Feasibility Report_2015.docx
6.0 Assessments
In 2010 the city council reviewed the city’s assessment policy. The 2013 project was completed without assessments. It is proposed that this project be completed without assessments to the individual property owners. An exception to this is the address of 407 Buffalo Street. This property is currently in Franklin Township and therefore does not pay taxes to the city of Delano. The city would propose to assess this property for the improvements to Buffalo Street. The assessment policy is to charge on a per unit basis for strictly residential projects. The assessment rate for this parcel has been determined by dividing the total improvement cost of the street by the number of units abutting Buffalo Street. Corner units with the street address on the abutting street will be considered ½ units. This parcel currently is not connected to city sewer and water so would not be charged improvement costs associated with sewer in water rather would be charge city connection costs when/if a connection to city sewer and water is sought. Below is a summary of the cost:
Number of Parcels 36
Street Improvement Construction Cost for Buffalo Street $ 449,925.13
Preliminary Assessment Amount $ 12,497.92
A preliminary assessment role is included as Table 4.
December 2015 7-1
T:\0564 Delano\180 - 2016 pavement project\01-feasibility report\final report\Final_Feasibility Report_2015.docx
7.0 Revenues and Expenses
A summary of the project revenues and expenses for the recommended improvements is listed in the table below.
Estimated Revenues are based on estimated expenses for the correlating cost. Actual Revenues will be limited by funds available in various accounts (e.g. Sanitary Sewer Fund, Storm Sewer Fund). Detailed cost estimates are available in Table 1 and Table 2.
Street Name Improvement Street Storm Sewer Sanitary Sewer Watermain Total
Franklin Avenue Reconstruct 427,879.50$ 12,740.00$ 116,701.00$ 164,177.00$ 721,497.50$ 1st Street Reconstruct 560,016.39$ 38,837.50$ 218,660.00$ 148,694.00$ 966,207.89$
987,895.89$ 51,577.50$ 335,361.00$ 312,871.00$ 1,687,705.39$
Merriman Drive Reconstruct 584,402.88$ 34,125.00$ 70,670.60$ 35,178.00$ 724,376.48$ Merriman Court Reconstruct 80,046.63$ 520.00$ -$ -$ 80,566.63$ Elk Street Reconstruct 55,990.32$ -$ 13,390.00$ 20,748.00$ 90,128.32$ Buffalo Street Reconstruct/Reclaim 449,925.13$ 6,825.00$ 9,828.00$ 148,733.00$ 615,311.13$ Bridge Avenue Reconstruct 381,357.04$ 24,570.00$ 15,834.00$ 112,515.00$ 534,276.04$ 72nd Street New Construction 63,668.31$ -$ -$ 26,884.00$ 90,552.31$
1,615,390.31$ 66,040.00$ 109,722.60$ 344,058.00$ 2,135,210.91$
2nd Street Reconstruct 260,944.79$ 650.00$ 5,642.00$ 42,790.80$ 310,027.59$ 3rd Street Reconstruct 144,829.48$ 7,475.00$ 7,046.00$ 43,443.40$ 202,793.88$ Railroad Avenue (River to 4th St) Reconstruct 1,113,153.28$ 44,915.00$ 33,293.00$ 113,425.00$ 1,304,786.28$ Railroad Avenue (4th St to Tiger Dr) New Construction 610,666.04$ 77,675.00$ 54,535.00$ 70,772.00$ 813,648.04$
2,129,593.59$ 130,715.00$ 100,516.00$ 270,431.20$ 2,631,255.79$
Additional Watermain Loops New Construction -$ -$ -$ 66,690.00$ 66,690.00$ -$ -$ -$ 66,690.00$ 66,690.00$
4,732,879.79$ 248,332.50$ 545,599.60$ 994,050.20$ 6,520,862.09$
4,732,879.79$ 4,732,879.79$ 248,332.50$ 248,332.50$
545,599.60$ 545,599.60$ 994,050.20$ 994,050.20$
4,732,879.79$ 248,332.50$ 545,599.60$ 994,050.20$ 6,520,862.09$
Estimated Revenues
Estimated Total Expenses
General Funds/Debt LevyStorm Sewer Funds
Sanitary Sewer FundsDMU Funds
Subtotal
Subtotal
Subtotal
Subtotal
Estimated Total Expenses
Estimated ExpensesFranklin Avenue/1st Street
Merriman Drive/Buffalo Street/Elk Street/Bridge Avenue
2nd Street/3rd Street/Railroad Avenue
Other Improvements
December 2015 7-2
T:\0564 Delano\180 - 2016 pavement project\01-feasibility report\final report\Final_Feasibility Report_2015.docx
Cost Estimate Assumptions:
All costs include a 30% contingency. This includes a 10% construction cost contingency as well as a 20% contingency for indirect costs. Indirect costs include administration, engineering, and legal expenses.
The current fund balances in the Sanitary Sewer and Storm Sewer may not be sufficient to fully provide the necessary revenues as identified in the table. Any shortages would need to be covered by General Street Levy funds.
Watermain Expenses and Watermain Funding are shown to be born entirely by Delano Municipal Utilities. A portion of these costs may be borne by the City where new development is occurring. The north end of Merriman Drive is one such instance, with the proposed street connection from the existing dead end to 72nd Street.
December 2015 8-1
T:\0564 Delano\180 - 2016 pavement project\01-feasibility report\final report\Final_Feasibility Report_2015.docx
8.0 Feasibility and Recommendations
The project, as reviewed herein, is feasible as it relates to general engineering principles and construction procedures and is in accordance with Delano’s overall Pavement Management Plan. This project is necessary to properly maintain existing streets and the safe flow of traffic including sidewalks for pedestrians. The utility improvements for sanitary and storm sewer are required in order to maintain and improve the current system. The project is cost effective based on existing conditions and acceptable reconstruction standards for street and utility improvements. The following specific recommendations are provided for Council consideration:
1. As the Council considers which streets to include in the 2016 project, certain streets will be moved forward or backward in the current CIP. It is recommended that the Council update the CIP and City budget forecasts after each Infrastructure Improvement project.
2. The Council has discussed a schedule to complete infrastructure improvement projects. This first project was completed in 2013. The second project planned for 2016 consistent with the plan of a project completed every third year (i.e. the next project would occur in 2019). It is recommended that public works staff update the pavement rankings on an annual basis.
3. It is recommended that the City continue to communicate with DMU. Revisions to the CIP should be shared such that the Utility can properly plan for efficient upgrades/repairs to the water supply and electrical distribution systems.
4. The City has started a GIS mapping and database program to assist in tracking infrastructure data and evaluation information. This has proved to be useful in the preparation of this report and will continue to be useful in maintenance activities. It is recommended that pavement condition rankings, manhole inventories, and sewer videos continue to be updated. As this information is updated, it should be stored in the City’s GIS.
Specific infrastructure and project design recommendations: 5. It is recommended that Public Works continue to televise the storm sewer
system. Components within this project area should be the first priority. 6. It is recommended that downtown streetscape improvements be included in
this project. It would be efficient to include these improvements in conjunction with the pavement reclamation and storm sewer improvements.
7. It is recommended that all sanitary, watermain and storm sewer extensions in reconstruct streets be approved. It is timely to complete the drainage improvements in conjunction with the pavement and curb reconstruction.
It is recommended that the City proceed with soil borings in streets that area proposed for reconstruction.
December 2015 9-1
T:\0564 Delano\180 - 2016 pavement project\01-feasibility report\final report\Final_Feasibility Report_2015.docx
9.0 Project Schedule
Order Feasibility Study - Council Mtg 9/15/2015 Hire Appraiser to determine impact/valve of ROW 11/4/2015 Submit public hearing notice to legal (due prev Fri @ noon) 12/16/2015 Publish public hearing notice (2x)(Thurs) Dec 21 & 28 3 days after 2nd publication 1/1/2016 Mail public hearing notices (min 10 days prior to PH) 12/23/2015 Establish value offering for ROW/easement 12/31/15 Meet individually with property owners on ROW/easement 12/31/15 Hold Public Hearing – Council mtg 1/5/2016 Approve Feasibility Study – Council mtg 1/5/2016 Order Plan/Specs - Council Mtg 1/5/2016 Neighborhood meeting with all affected residents 1/20/2016 Approve plans/Authorize Ad for Bid – Council mtg 2/2/2016 Submit Ad for Bid to legal (due prev Fri @ noon) 2/5/2015 Publish Ad for Bid (2x)(Thurs) Feb 11 & 18 21 days after 1st publication 3/3/2016 Open bids 3/8/2016 Submit Bid Tab for Council Packet 3/9/2016 Review Bids/Award Contract – Council mtg 3/15/2016 Begin Construction 5/1/2016 Order Assessment Hearing – Council mtg 9/6/2016 Submit Assessment Hearing notice to legal 9/9/2016 Publish Assessment Hearing notice (1x)(Thurs) 9/15/2016 Mail Assessment Hearing notices 9/15/2016 14 days after mailings AND published notice 9/29/2016 Hold Assessment Hearing - Council mtg 10/4/2016 Substantial Completion 11/1/2016 Final Completion 12/1/2016
TABL
E 1
CIT
Y O
F D
ELA
NO
2016
INFR
AS
TRU
CTU
RE
IMPR
OV
EM
ENT
PR
OJE
CT
SU
MM
ARY
OF
CO
STS
STR
EET
STO
RM
SAN
ITAR
YW
ATER
TOTA
LS1S
T ST
REE
T43
0,78
1.84
$
29
,875
.00
$
168,
200.
00$
11
4,38
0.00
$
74
3,23
6.84
$
2N
D S
TREE
T20
0,72
6.76
$
50
0.00
$
4,34
0.00
$
32
,916
.00
$
23
8,48
2.76
$
3R
D S
TREE
T11
1,40
7.29
$
5,
750.
00$
5,42
0.00
$
33
,418
.00
$
15
5,99
5.29
$
72
ND
STR
EET
48,9
75.6
2$
-
$
-$
20
,680
.00
$
69
,655
.62
$
BR
IDG
E AV
E29
3,35
1.57
$
18
,900
.00
$
12,1
80.0
0$
86
,550
.00
$
41
0,98
1.57
$
BU
FFAL
O S
T34
6,09
6.25
$
5,
250.
00$
7,56
0.00
$
11
4,41
0.00
$
47
3,31
6.25
$
EL
K ST
43,0
69.4
8$
-
$
10,3
00.0
0$
15
,960
.00
$
69
,329
.48
$
FR
AN
KLI
N32
9,13
8.08
$
9,
800.
00$
89,7
70.0
0$
12
6,29
0.00
$
55
4,99
8.08
$
M
ER
RIM
AN
CT
61,5
74.3
3$
40
0.00
$
-$
-
$
61
,974
.33
$
M
ER
RIM
AN
DR
449,
540.
68$
26,2
50.0
0$
54
,362
.00
$
27,0
60.0
0$
557,
212.
68$
RA
ILR
OA
D (R
iver
to 4
th)
856,
271.
75$
34,5
50.0
0$
25
,610
.00
$
87,2
50.0
0$
1,00
3,68
1.75
$
RA
ILR
OA
D (4
th to
Tig
er)
469,
743.
11$
59,7
50.0
0$
41
,950
.00
$
54,4
40.0
0$
625,
883.
11$
ADD
ITIO
NA
L W
M L
OO
PS51
,300
.00
$
51
,300
.00
$
TOTA
L3,
640,
676.
76$
19
1,02
5.00
$
419,
692.
00$
76
4,65
4.00
$
5,
016,
047.
76$
10
% C
ON
STR
UC
TIO
N C
ON
TIN
GEN
CY
364,
067.
68$
19,1
02.5
0$
41
,969
.20
$
76,4
65.4
0$
501,
604.
78$
20%
IND
IRE
CTS
728,
135.
35$
38,2
05.0
0$
83
,938
.40
$
152,
930.
80$
1,00
3,20
9.55
$
TOTA
L ES
TIM
ATED
CO
NS
TRU
CTI
ON
CO
ST
4,73
2,87
9.79
$
248,
332.
50$
54
5,59
9.60
$
994,
050.
20$
6,52
0,86
2.09
$
GR
AND
TO
TAL
6,52
0,86
2.09
$
SUBT
OTA
LS
TABL
E 2
CIT
Y O
F D
ELAN
O20
16 IN
FRAS
TRU
CTU
RE
IMPR
OVE
MEN
TS P
RO
JEC
TD
ETAI
LED
CO
ST B
REA
KOU
T
UN
ITS
UN
IT P
RIC
ETO
TAL
QTY
STR
EET
STO
RM
SAN
ITAR
YW
ATER
QTY
STR
EET
STO
RM
SAN
ITAR
YW
ATER
QTY
STR
EET
STO
RM
SAN
ITAR
YW
ATER
QTY
STR
EET
STO
RM
SAN
ITAR
YW
ATER
STR
EET
1M
OBI
LIZA
TIO
NLU
MP
SUM
$180
,000
.00
10.
1$1
8,00
0.00
$0.0
0$0
.00
$0.0
02
TRAF
FIC
CO
NTR
OL
LUM
P SU
M$6
0,00
0.00
10.
1$6
,000
.00
$0.0
0$0
.00
$0.0
03
CLE
ARIN
G&G
RU
BBIN
GTR
EE$5
00.0
060
$0.0
0$0
.00
$0.0
0$0
.00
4R
EMO
VE C
UR
B AN
D G
UTT
ERLI
N F
T$5
.00
1350
330
70$1
5,35
0.00
623
$3,1
12.5
062
3$3
,112
.50
$0.0
05
REM
OVE
SEW
ER P
IPE
(STO
RM
)LI
N F
T$1
0.00
1355
40$4
00.0
050
$500
.00
50$5
00.0
0$0
.00
6R
EMO
VE S
EWER
PIP
E (S
ANIT
ARY)
LIN
FT
$6.0
046
9524
40$1
4,64
0.00
$0.0
0$0
.00
$0.0
07
REM
OVE
CIP
WAT
ER M
AIN
LIN
FT
$6.0
061
5015
35$9
,210
.00
$0.0
041
5$2
,490
.00
$0.0
08
REM
OVE
TR
ANSI
TE W
ATER
MAI
NLI
N F
T$6
.00
2198
$0.0
042
3$2
,538
.00
$0.0
0$0
.00
9BI
TUM
INO
US
PAVE
MEN
T R
ECLA
MAT
ION
SQ Y
D$1
.50
3604
657
99$8
,698
.33
2075
$3,1
12.5
014
76$2
,213
.33
$0.0
010
REM
OVE
CO
NC
RET
E D
RIV
EWAY
PAV
EMEN
TSQ
YD
$6.0
012
9648
0$2
,880
.00
0$0
.00
0$0
.00
$0.0
011
REM
OVE
BIT
UM
INO
US
DR
IVEW
AY P
AVEM
ENT
SQ Y
D$4
.00
2002
448
$1,7
92.0
016
0$6
40.0
032
$128
.00
$0.0
012
REM
OVE
CO
NC
RET
E W
ALK
SQ Y
D$5
.00
1381
$0.0
042
3$2
,115
.00
461
$2,3
05.5
6$0
.00
13R
EMO
VE C
ASTI
NG
EAC
H$1
00.0
013
$0.0
03
$300
.00
$0.0
0$0
.00
14R
EMO
VE M
ANH
OLE
OR
CAT
CH
BAS
INEA
CH
$800
.00
3510
$8,0
00.0
0$0
.00
$0.0
0$0
.00
15SA
WIN
G B
ITU
MIN
OU
S PA
VEM
ENT
LIN
FT
$3.0
024
6241
8$1
,254
.00
215
$645
.00
89$2
67.0
040
$120
.00
16C
OM
MO
N E
XCAV
ATIO
N -
ON
SIT
E (E
V)C
U Y
D$1
4.00
3051
339
52$5
5,33
3.43
844
$11,
812.
7710
69$1
4,95
9.85
772
$10,
814.
3517
SUBG
RAD
E EX
CAV
ATIO
N (E
V)C
U Y
D$1
4.00
2969
395
$5,5
33.3
484
$1,1
81.2
810
7$1
,495
.99
77$1
,081
.44
18SE
LEC
T TO
PSO
IL B
OR
RO
W S
PEC
IAL
(LV)
CU
YD
$25.
0021
4428
1$7
,035
.42
$0.0
076
$1,9
02.0
855
$1,3
75.0
019
GEO
TEXT
ILE
FABR
IC, T
YPE
V N
ON
-WO
VEN
SQ Y
D$2
.00
4744
960
55$1
2,10
9.44
$0.0
016
37$3
,273
.89
1183
$2,3
66.6
720
SELE
CT
GR
ANU
LAR
BO
RR
OW
(MO
DIF
IED
) (C
V)TO
N$1
0.00
2916
239
96$3
9,96
1.17
$0.0
010
80$1
0,80
3.83
781
$7,8
10.0
021
AGG
REG
ATE
BASE
CLA
SS 5
100
% C
RU
SHED
TON
$12.
5022
322
2664
$33,
300.
9712
93$1
6,16
7.71
720
$9,0
03.1
952
1$6
,508
.33
22D
RAI
N T
ILE
LF$1
0.00
2063
030
70$3
0,70
0.00
830
$8,3
00.0
083
0$8
,300
.00
$0.0
023
BITU
MIN
OU
S M
ATER
IAL
FOR
TAC
K C
OAT
GAL
$4.0
021
0724
7$9
89.2
283
$332
.00
67$2
67.4
448
$193
.33
24BI
TUM
INO
US
WEA
R C
OU
RSE
MIX
TON
$68.
0036
4342
7$2
9,00
8.94
143
$9,7
35.9
011
5$7
,842
.81
83$5
,669
.50
25BI
TUM
INO
US
BASE
CO
UR
SE M
IXTO
N$6
6.00
4855
569
$37,
540.
9819
1$1
2,59
9.40
154
$10,
149.
5211
1$7
,337
.00
26TY
PE S
P 9.
5 W
EAR
ING
CO
UR
SE M
IX (S
PWEA
240B
) DR
IVEW
AYTO
N$8
5.00
335
67$5
,702
.08
24$2
,036
.46
5$4
07.2
9$0
.00
27TY
PE S
P 9.
5 W
EAR
ING
CO
UR
SE M
IX (S
PWEA
240B
) TR
AIL
TON
$85.
0011
33$0
.00
$0.0
0$0
.00
$0.0
028
4" C
ON
CR
ETE
WAL
KSQ
FT
$5.0
033
286
7675
$38,
375.
0065
36$3
2,68
1.25
4150
$20,
750.
00$0
.00
29C
ON
CR
ETE
CU
RB
& G
UTT
ER D
ESIG
N B
618
LIN
FT
$11.
5019
640
3070
$35,
305.
0083
0$9
,545
.00
830
$9,5
45.0
0$0
.00
306"
CO
NC
RET
E D
RIV
EWAY
PAV
EMEN
TSQ
FT
$6.0
011
664
4320
$25,
920.
00$0
.00
$0.0
0$0
.00
31PE
DES
TRIA
N C
UR
B R
AMP
EAC
H$4
00.0
020
2$8
00.0
04
$1,6
00.0
02
$800
.00
$0.0
032
TRU
NC
ATED
DO
MES
SQ F
T$4
5.00
240
24$1
,080
.00
48$2
,160
.00
24$1
,080
.00
$0.0
033
TEM
POR
ARY
MAI
LBO
XES
INC
L SA
LVAG
E &
REI
NST
ALL
LUM
P SU
M$3
0,00
0.00
10.
1$3
,000
.00
0.1
$3,0
00.0
0$0
.00
0.1
$3,0
00.0
034
TEM
POR
ARY
SIG
NAG
E - B
USI
NES
S AC
CES
SLU
MP
SUM
$2,0
00.0
01
0.1
$200
.00
0.1
$200
.00
$0.0
00.
1$2
00.0
035
DO
WN
TOW
N P
ARKI
NG
LO
TLU
MP
SUM
$130
,000
.00
1ST
OR
M S
EWER
3615
" RC
PIP
E SE
WER
CLA
SS V
LIN
FT
$35.
0029
7558
5$2
0,47
5.00
$0.0
040
$1,4
00.0
0$0
.00
3718
" RC
PIP
E SE
WER
CLA
SS V
LIN
FT
$38.
0020
0$0
.00
$0.0
0$0
.00
$0.0
038
CO
NST
DR
AIN
AGE
STR
UC
TUR
E - 2
' x 3
' CB
EAC
H$1
,600
.00
13$0
.00
$0.0
01
$1,6
00.0
0$0
.00
39C
ON
ST D
RAI
NAG
E ST
RU
CTU
RE
- 4' D
IA C
BMH
EAC
H$2
,250
.00
164
$9,0
00.0
0$0
.00
1$2
,250
.00
$0.0
0SA
NIT
AR
Y SE
WER
40C
ON
NEC
T TO
EXI
STIN
G S
ANIT
ARY
MAN
HO
LEEA
CH
$1,5
00.0
07
2$3
,000
.00
$0.0
0$0
.00
$0.0
041
INST
ALL
4' D
IA S
ANIT
ARY
MAN
HO
LEEA
CH
$2,5
00.0
029
6$1
5,00
0.00
1$2
,500
.00
1$2
,500
.00
$0.0
042
8"x
6" P
VC W
YEEA
CH
$150
.00
5932
$4,8
00.0
0$0
.00
$0.0
0$0
.00
43R
ECO
NN
ECT
SAN
ITAR
Y SE
WER
SER
VIC
EEA
CH
$500
.00
5932
$16,
000.
001
$500
.00
1$5
00.0
0$0
.00
448"
PVC
PIP
E SE
WER
SD
R 3
5LI
N F
T$3
6.00
5135
2440
$87,
840.
00$0
.00
30$1
,080
.00
$0.0
045
6" P
VC S
ANIT
ARY
SER
VIC
E PI
PELI
N F
T$2
8.00
1789
640
$17,
920.
0030
$840
.00
30$8
40.0
0$0
.00
46PU
MPI
NG
- SA
NIT
ARY
SEW
ER B
YPAS
SLU
MP
SUM
$5,0
00.0
01
0.2
$1,0
00.0
00.
1$5
00.0
00.
1$5
00.0
0$0
.00
WA
TER
MA
IN47
6" G
ATE
VALV
E AN
D B
OX
EAC
H$1
,900
.00
182
$3,8
00.0
01
$1,9
00.0
01
$1,9
00.0
02
$3,8
00.0
048
6" W
ATER
MAI
N D
UC
TILE
IRO
N C
L 52
(MAI
N)
LIN
FT
$36.
0076
2815
40$5
5,44
0.00
423
$15,
228.
0042
3$1
5,22
8.00
310
$11,
160.
0049
12" G
ATE
VALV
E AN
D B
OX
EAC
H$3
,000
.00
3$0
.00
$0.0
0$0
.00
$0.0
050
12" W
ATER
MAI
N D
UC
TILE
IRO
N C
L 52
(MAI
N)
LIN
FT
$40.
0016
90$0
.00
$0.0
0$0
.00
$0.0
051
CO
NN
ECT
TO E
XIST
ING
WAT
ER M
AIN
EAC
H$2
,000
.00
111
$2,0
00.0
01
$2,0
00.0
01
$2,0
00.0
0$0
.00
52IN
STAL
L H
YDR
ANT
& VA
LVE
EAC
H$5
,000
.00
224
$20,
000.
00$0
.00
1$5
,000
.00
1$5
,000
.00
531"
TYP
E "K
" CO
PPER
PIP
ELI
N F
T$2
0.00
2330
640
$12,
800.
0015
0$3
,000
.00
90$1
,800
.00
$0.0
054
6" W
ATER
MAI
N D
UC
TILE
IRO
N C
L 52
(HYD
LEA
DS)
LIN
FT
$36.
0044
080
$2,8
80.0
0$0
.00
$0.0
020
$720
.00
55TE
MPO
RAR
Y W
ATER
SER
VIC
ELU
MP
SUM
$50,
000.
001
0.16
5$8
,250
.00
0.16
5$8
,250
.00
0.1
$5,0
00.0
0$0
.00
STR
EETS
CA
PE IT
EMS
56LI
GH
TIN
G U
NIT
TYP
E A
EAC
H$7
,500
.00
226
4500
00
57LI
GH
T BA
SE D
ESIG
N A
EAC
H$7
00.0
022
642
000
58C
ON
DU
IT A
ND
WIR
ING
LIN
FT
$15.
0031
0085
012
750
059
OVE
RST
OR
Y TR
EES
TREE
$600
.00
237
4200
060
TREE
GR
ATE
EAC
H$1
,500
.00
237
1050
00
ERO
SIO
N C
ON
TRO
L61
ERO
SIO
N C
ON
TRO
L-G
ENER
ALLU
MP
SUM
$15,
000.
001
0.1
$1,5
00.0
00.
1$1
,500
.00
0.1
$1,5
00.0
00.
1$1
,500
.00
62TE
MPO
RAR
Y R
OC
K C
ON
STR
UC
TIO
N E
NTR
ANC
EEA
CH
$1,0
00.0
08
1$1
,000
.00
1$1
,000
.00
1$1
,000
.00
1$1
,000
.00
63ST
OR
M D
RAI
N IN
LET
PRO
TEC
TIO
N -
MAI
NTA
INED
EAC
H$1
50.0
025
6$9
00.0
02
$300
.00
2$3
00.0
0$0
.00
64SO
DD
ING
TYP
E LA
WN
SQ Y
D$4
.50
1451
525
58$1
1,51
2.50
$0.0
0$0
.00
$0.0
0$4
30,7
81.8
4$2
9,87
5.00
$168
,200
.00
$114
,380
.00
$200
,726
.76
$500
.00
$4,3
40.0
0$3
2,91
6.00
$111
,407
.29
$5,7
50.0
0$5
,420
.00
$33,
418.
00$4
8,97
5.62
$0.0
0$0
.00
$20,
680.
00Su
btot
als
72N
D S
TREE
T - R
econ
stru
ct2N
D S
TREE
T - M
odifi
ed R
ecla
im1S
T ST
REE
T - R
econ
stru
ct3R
D S
TREE
T - R
econ
stru
ct
TABL
E 2
CIT
Y O
F D
ELAN
O20
16 IN
FRAS
TRU
CTU
RE
IMPR
OVE
MEN
TS P
RO
JEC
TD
ETAI
LED
CO
ST B
REA
KOU
T
UN
ITS
UN
IT P
RIC
ETR
EET
1M
OBI
LIZA
TIO
NLU
MP
SUM
$180
,000
.00
2TR
AFFI
C C
ON
TRO
LLU
MP
SUM
$60,
000.
003
CLE
ARIN
G&G
RU
BBIN
GTR
EE$5
00.0
04
REM
OVE
CU
RB
AND
GU
TTER
LIN
FT
$5.0
05
REM
OVE
SEW
ER P
IPE
(STO
RM
)LI
N F
T$1
0.00
6R
EMO
VE S
EWER
PIP
E (S
ANIT
ARY)
LIN
FT
$6.0
07
REM
OVE
CIP
WAT
ER M
AIN
LIN
FT
$6.0
08
REM
OVE
TR
ANSI
TE W
ATER
MAI
NLI
N F
T$6
.00
9BI
TUM
INO
US
PAVE
MEN
T R
ECLA
MAT
ION
SQ Y
D$1
.50
10R
EMO
VE C
ON
CR
ETE
DR
IVEW
AY P
AVEM
ENT
SQ Y
D$6
.00
11R
EMO
VE B
ITU
MIN
OU
S D
RIV
EWAY
PAV
EMEN
TSQ
YD
$4.0
012
REM
OVE
CO
NC
RET
E W
ALK
SQ Y
D$5
.00
13R
EMO
VE C
ASTI
NG
EAC
H$1
00.0
014
REM
OVE
MAN
HO
LE O
R C
ATC
H B
ASIN
EAC
H$8
00.0
015
SAW
ING
BIT
UM
INO
US
PAVE
MEN
TLI
N F
T$3
.00
16C
OM
MO
N E
XCAV
ATIO
N -
ON
SIT
E (E
V)C
U Y
D$1
4.00
17SU
BGR
ADE
EXC
AVAT
ION
(EV)
CU
YD
$14.
0018
SELE
CT
TOPS
OIL
BO
RR
OW
SPE
CIA
L (L
V)C
U Y
D$2
5.00
19G
EOTE
XTIL
E FA
BRIC
, TYP
E V
NO
N-W
OVE
NSQ
YD
$2.0
020
SELE
CT
GR
ANU
LAR
BO
RR
OW
(MO
DIF
IED
) (C
V)TO
N$1
0.00
21AG
GR
EGAT
E BA
SE C
LASS
5 1
00%
CR
USH
EDTO
N$1
2.50
22D
RAI
N T
ILE
LF$1
0.00
23BI
TUM
INO
US
MAT
ERIA
L FO
R T
ACK
CO
ATG
AL$4
.00
24BI
TUM
INO
US
WEA
R C
OU
RSE
MIX
TON
$68.
0025
BITU
MIN
OU
S BA
SE C
OU
RSE
MIX
TON
$66.
0026
TYPE
SP
9.5
WEA
RIN
G C
OU
RSE
MIX
(SPW
EA24
0B) D
RIV
EWAY
TON
$85.
0027
TYPE
SP
9.5
WEA
RIN
G C
OU
RSE
MIX
(SPW
EA24
0B) T
RAI
LTO
N$8
5.00
284"
CO
NC
RET
E W
ALK
SQ F
T$5
.00
29C
ON
CR
ETE
CU
RB
& G
UTT
ER D
ESIG
N B
618
LIN
FT
$11.
5030
6" C
ON
CR
ETE
DR
IVEW
AY P
AVEM
ENT
SQ F
T$6
.00
31PE
DES
TRIA
N C
UR
B R
AMP
EAC
H$4
00.0
032
TRU
NC
ATED
DO
MES
SQ F
T$4
5.00
33TE
MPO
RAR
Y M
AILB
OXE
S IN
CL
SALV
AGE
& R
EIN
STAL
LLU
MP
SUM
$30,
000.
0034
TEM
POR
ARY
SIG
NAG
E - B
USI
NES
S AC
CES
SLU
MP
SUM
$2,0
00.0
035
DO
WN
TOW
N P
ARKI
NG
LO
TLU
MP
SUM
$130
,000
.00
TOR
M S
EWER
3615
" RC
PIP
E SE
WER
CLA
SS V
LIN
FT
$35.
0037
18" R
C P
IPE
SEW
ER C
LASS
VLI
N F
T$3
8.00
38C
ON
ST D
RAI
NAG
E ST
RU
CTU
RE
- 2' x
3' C
BEA
CH
$1,6
00.0
039
CO
NST
DR
AIN
AGE
STR
UC
TUR
E - 4
' DIA
CBM
HEA
CH
$2,2
50.0
0A
NIT
AR
Y SE
WER
40C
ON
NEC
T TO
EXI
STIN
G S
ANIT
ARY
MAN
HO
LEEA
CH
$1,5
00.0
041
INST
ALL
4' D
IA S
ANIT
ARY
MAN
HO
LEEA
CH
$2,5
00.0
042
8"x
6" P
VC W
YEEA
CH
$150
.00
43R
ECO
NN
ECT
SAN
ITAR
Y SE
WER
SER
VIC
EEA
CH
$500
.00
448"
PVC
PIP
E SE
WER
SD
R 3
5LI
N F
T$3
6.00
456"
PVC
SAN
ITAR
Y SE
RVI
CE
PIPE
LIN
FT
$28.
0046
PUM
PIN
G -
SAN
ITAR
Y SE
WER
BYP
ASS
LUM
P SU
M$5
,000
.00
WA
TER
MA
IN47
6" G
ATE
VALV
E AN
D B
OX
EAC
H$1
,900
.00
486"
WAT
ERM
AIN
DU
CTI
LE IR
ON
CL
52 (M
AIN
)LI
N F
T$3
6.00
4912
" GAT
E VA
LVE
AND
BO
XEA
CH
$3,0
00.0
050
12" W
ATER
MAI
N D
UC
TILE
IRO
N C
L 52
(MAI
N)
LIN
FT
$40.
0051
CO
NN
ECT
TO E
XIST
ING
WAT
ER M
AIN
EAC
H$2
,000
.00
52IN
STAL
L H
YDR
ANT
& VA
LVE
EAC
H$5
,000
.00
531"
TYP
E "K
" CO
PPER
PIP
ELI
N F
T$2
0.00
546"
WAT
ERM
AIN
DU
CTI
LE IR
ON
CL
52 (H
YD L
EAD
S)LI
N F
T$3
6.00
55TE
MPO
RAR
Y W
ATER
SER
VIC
ELU
MP
SUM
$50,
000.
00TR
EETS
CA
PE IT
EMS
56LI
GH
TIN
G U
NIT
TYP
E A
EAC
H$7
,500
.00
57LI
GH
T BA
SE D
ESIG
N A
EAC
H$7
00.0
058
CO
ND
UIT
AN
D W
IRIN
GLI
N F
T$1
5.00
59O
VER
STO
RY
TREE
STR
EE$6
00.0
060
TREE
GR
ATE
EAC
H$1
,500
.00
RO
SIO
N C
ON
TRO
L61
ERO
SIO
N C
ON
TRO
L-G
ENER
ALLU
MP
SUM
$15,
000.
0062
TEM
POR
ARY
RO
CK
CO
NST
RU
CTI
ON
EN
TRAN
CE
EAC
H$1
,000
.00
63ST
OR
M D
RAI
N IN
LET
PRO
TEC
TIO
N -
MAI
NTA
INED
EAC
H$1
50.0
064
SOD
DIN
G T
YPE
LAW
NSQ
YD
$4.5
0Su
btot
als
QTY
STR
EET
STO
RM
SAN
ITAR
YW
ATER
QTY
STR
EET
STO
RM
SAN
ITAR
YW
ATER
QTY
STR
EET
STO
RM
SAN
ITAR
YW
ATER
QTY
STR
EET
STO
RM
SAN
ITAR
YW
ATER
0.05
$9,0
00.0
00.
1$1
8,00
0.00
$0.0
00.
1$1
8,00
0.00
0.05
$3,0
00.0
00.
1$6
,000
.00
$0.0
00.
1$6
,000
.00
40$2
0,00
0.00
$0.0
0$0
.00
$0.0
010
00$5
,000
.00
900
$4,5
00.0
020
0$1
,000
.00
1600
$8,0
00.0
032
0$3
,200
.00
$0.0
0$0
.00
70$7
00.0
030
$180
.00
30$1
80.0
0$0
.00
1050
$6,3
00.0
011
00$6
,600
.00
1590
$9,5
40.0
017
0$1
,020
.00
585
$3,5
10.0
0$0
.00
$0.0
0$0
.00
975
$5,8
50.0
034
00$5
,100
.00
6267
$9,4
00.0
065
8$9
86.6
739
22$5
,883
.33
32$1
92.0
00
$0.0
00
$0.0
00
$0.0
025
6$1
,024
.00
0$0
.00
42$1
66.6
732
0$1
,280
.00
222
$1,1
10.0
0$0
.00
$0.0
0$0
.00
1$1
00.0
06
$600
.00
$0.0
0$0
.00
5$4
,000
.00
1$8
00.0
0$0
.00
8$6
,400
.00
234
$702
.00
398
$1,1
94.0
089
$267
.00
250
$750
.00
3232
$45,
253.
0637
70$5
2,78
0.00
450
$6,2
93.1
429
24$4
0,93
3.58
323
$4,5
25.3
137
7$5
,278
.00
45$6
29.3
129
2$4
,093
.36
165
$4,1
25.0
043
1$1
0,77
0.83
34$8
47.9
232
5$8
,125
.00
4675
$9,3
50.0
066
00$1
3,20
0.00
730
$1,4
59.4
446
56$9
,311
.11
3088
$30,
880.
0022
00$2
2,00
0.00
482
$4,8
16.1
730
73$3
0,72
6.67
2057
$25,
712.
5030
54$3
8,17
5.00
321
$4,0
13.4
720
48$2
5,60
5.56
1800
$18,
000.
0023
00$2
3,00
0.00
370
$3,7
00.0
016
00$1
6,00
0.00
201
$805
.00
313
$1,2
53.3
330
$119
.22
196
$783
.56
347
$23,
606.
6354
1$3
6,75
4.00
51$3
,496
.19
337
$22,
938.
6746
3$3
0,54
9.75
721
$47,
564.
0069
$4,5
24.4
845
0$2
9,72
9.33
38$3
,258
.33
67$5
,702
.08
5$4
07.2
948
$4,0
72.9
2$0
.00
$0.0
0$0
.00
525
$44,
625.
0030
00$1
5,00
0.00
$0.0
0$0
.00
4000
$20,
000.
0018
00$2
0,70
0.00
2300
$26,
450.
0037
0$4
,255
.00
1600
$18,
400.
0028
8$1
,728
.00
0$0
.00
$0.0
0$0
.00
2$8
00.0
0$0
.00
$0.0
02
$800
.00
24$1
,080
.00
$0.0
0$0
.00
24$1
,080
.00
0.1
$3,0
00.0
00.
1$3
,000
.00
0.1
$3,0
00.0
00.
1$3
,000
.00
0.1
$200
.00
0.1
$200
.00
0.1
$200
.00
0.1
$200
.00
320
$11,
200.
0040
$1,4
00.0
0$0
.00
40$1
,400
.00
$0.0
0$0
.00
$0.0
0$0
.00
$0.0
01
$1,6
00.0
0$0
.00
2$3
,200
.00
2$4
,500
.00
1$2
,250
.00
$0.0
02
$4,5
00.0
0
$0.0
0$0
.00
1$1
,500
.00
$0.0
03
$7,5
00.0
02
$5,0
00.0
01
$2,5
00.0
07
$17,
500.
00$0
.00
$0.0
0$0
.00
13$1
,950
.00
$0.0
0$0
.00
$0.0
013
$6,5
00.0
0$0
.00
30$1
,080
.00
175
$6,3
00.0
011
90$4
2,84
0.00
$0.0
0$0
.00
$0.0
026
0$7
,280
.00
0.1
$500
.00
0.1
$500
.00
$0.0
00.
2$1
,000
.00
3$5
,700
.00
3$5
,700
.00
1$1
,900
.00
$0.0
012
60$4
5,36
0.00
1590
$57,
240.
0017
0$6
,120
.00
$0.0
0$0
.00
$0.0
0$0
.00
3$9
,000
.00
$0.0
0$0
.00
$0.0
016
90$6
7,60
0.00
1$2
,000
.00
1$2
,000
.00
$0.0
02
$4,0
00.0
02
$10,
000.
004
$20,
000.
001
$5,0
00.0
04
$20,
000.
0036
0$7
,200
.00
440
$8,8
00.0
060
$1,2
00.0
026
0$5
,200
.00
40$1
,440
.00
80$2
,880
.00
20$7
20.0
080
$2,8
80.0
00.
165
$8,2
50.0
00.
165
$8,2
50.0
0$0
.00
0.16
5$8
,250
.00
0.1
$1,5
00.0
00.
1$1
,500
.00
0.1
$1,5
00.0
00.
1$1
,500
.00
1$1
,000
.00
1$1
,000
.00
$0.0
01
$1,0
00.0
02
$300
.00
1$1
50.0
0$0
.00
2$3
00.0
015
00$6
,750
.00
3916
.666
667
$17,
625.
0030
8$1
,387
.50
1333
$6,0
00.0
0$2
93,3
51.5
7$1
8,90
0.00
$12,
180.
00$8
6,55
0.00
$346
,096
.25
$5,2
50.0
0$7
,560
.00
$114
,410
.00
$43,
069.
48$0
.00
$10,
300.
00$1
5,96
0.00
$329
,138
.08
$9,8
00.0
0$8
9,77
0.00
$126
,290
.00
FRAN
KLIN
- R
econ
stru
ctEL
K ST
- R
econ
stru
ctBU
FFAL
O S
T - C
ity R
ecla
im/D
MU
Rec
onst
ruct
BRID
GE
AVE
- Rec
onst
ruct
TABL
E 2
CIT
Y O
F D
ELAN
O20
16 IN
FRAS
TRU
CTU
RE
IMPR
OVE
MEN
TS P
RO
JEC
TD
ETAI
LED
CO
ST B
REA
KOU
T
UN
ITS
UN
IT P
RIC
ETR
EET
1M
OBI
LIZA
TIO
NLU
MP
SUM
$180
,000
.00
2TR
AFFI
C C
ON
TRO
LLU
MP
SUM
$60,
000.
003
CLE
ARIN
G&G
RU
BBIN
GTR
EE$5
00.0
04
REM
OVE
CU
RB
AND
GU
TTER
LIN
FT
$5.0
05
REM
OVE
SEW
ER P
IPE
(STO
RM
)LI
N F
T$1
0.00
6R
EMO
VE S
EWER
PIP
E (S
ANIT
ARY)
LIN
FT
$6.0
07
REM
OVE
CIP
WAT
ER M
AIN
LIN
FT
$6.0
08
REM
OVE
TR
ANSI
TE W
ATER
MAI
NLI
N F
T$6
.00
9BI
TUM
INO
US
PAVE
MEN
T R
ECLA
MAT
ION
SQ Y
D$1
.50
10R
EMO
VE C
ON
CR
ETE
DR
IVEW
AY P
AVEM
ENT
SQ Y
D$6
.00
11R
EMO
VE B
ITU
MIN
OU
S D
RIV
EWAY
PAV
EMEN
TSQ
YD
$4.0
012
REM
OVE
CO
NC
RET
E W
ALK
SQ Y
D$5
.00
13R
EMO
VE C
ASTI
NG
EAC
H$1
00.0
014
REM
OVE
MAN
HO
LE O
R C
ATC
H B
ASIN
EAC
H$8
00.0
015
SAW
ING
BIT
UM
INO
US
PAVE
MEN
TLI
N F
T$3
.00
16C
OM
MO
N E
XCAV
ATIO
N -
ON
SIT
E (E
V)C
U Y
D$1
4.00
17SU
BGR
ADE
EXC
AVAT
ION
(EV)
CU
YD
$14.
0018
SELE
CT
TOPS
OIL
BO
RR
OW
SPE
CIA
L (L
V)C
U Y
D$2
5.00
19G
EOTE
XTIL
E FA
BRIC
, TYP
E V
NO
N-W
OVE
NSQ
YD
$2.0
020
SELE
CT
GR
ANU
LAR
BO
RR
OW
(MO
DIF
IED
) (C
V)TO
N$1
0.00
21AG
GR
EGAT
E BA
SE C
LASS
5 1
00%
CR
USH
EDTO
N$1
2.50
22D
RAI
N T
ILE
LF$1
0.00
23BI
TUM
INO
US
MAT
ERIA
L FO
R T
ACK
CO
ATG
AL$4
.00
24BI
TUM
INO
US
WEA
R C
OU
RSE
MIX
TON
$68.
0025
BITU
MIN
OU
S BA
SE C
OU
RSE
MIX
TON
$66.
0026
TYPE
SP
9.5
WEA
RIN
G C
OU
RSE
MIX
(SPW
EA24
0B) D
RIV
EWAY
TON
$85.
0027
TYPE
SP
9.5
WEA
RIN
G C
OU
RSE
MIX
(SPW
EA24
0B) T
RAI
LTO
N$8
5.00
284"
CO
NC
RET
E W
ALK
SQ F
T$5
.00
29C
ON
CR
ETE
CU
RB
& G
UTT
ER D
ESIG
N B
618
LIN
FT
$11.
5030
6" C
ON
CR
ETE
DR
IVEW
AY P
AVEM
ENT
SQ F
T$6
.00
31PE
DES
TRIA
N C
UR
B R
AMP
EAC
H$4
00.0
032
TRU
NC
ATED
DO
MES
SQ F
T$4
5.00
33TE
MPO
RAR
Y M
AILB
OXE
S IN
CL
SALV
AGE
& R
EIN
STAL
LLU
MP
SUM
$30,
000.
0034
TEM
POR
ARY
SIG
NAG
E - B
USI
NES
S AC
CES
SLU
MP
SUM
$2,0
00.0
035
DO
WN
TOW
N P
ARKI
NG
LO
TLU
MP
SUM
$130
,000
.00
TOR
M S
EWER
3615
" RC
PIP
E SE
WER
CLA
SS V
LIN
FT
$35.
0037
18" R
C P
IPE
SEW
ER C
LASS
VLI
N F
T$3
8.00
38C
ON
ST D
RAI
NAG
E ST
RU
CTU
RE
- 2' x
3' C
BEA
CH
$1,6
00.0
039
CO
NST
DR
AIN
AGE
STR
UC
TUR
E - 4
' DIA
CBM
HEA
CH
$2,2
50.0
0A
NIT
AR
Y SE
WER
40C
ON
NEC
T TO
EXI
STIN
G S
ANIT
ARY
MAN
HO
LEEA
CH
$1,5
00.0
041
INST
ALL
4' D
IA S
ANIT
ARY
MAN
HO
LEEA
CH
$2,5
00.0
042
8"x
6" P
VC W
YEEA
CH
$150
.00
43R
ECO
NN
ECT
SAN
ITAR
Y SE
WER
SER
VIC
EEA
CH
$500
.00
448"
PVC
PIP
E SE
WER
SD
R 3
5LI
N F
T$3
6.00
456"
PVC
SAN
ITAR
Y SE
RVI
CE
PIPE
LIN
FT
$28.
0046
PUM
PIN
G -
SAN
ITAR
Y SE
WER
BYP
ASS
LUM
P SU
M$5
,000
.00
WA
TER
MA
IN47
6" G
ATE
VALV
E AN
D B
OX
EAC
H$1
,900
.00
486"
WAT
ERM
AIN
DU
CTI
LE IR
ON
CL
52 (M
AIN
)LI
N F
T$3
6.00
4912
" GAT
E VA
LVE
AND
BO
XEA
CH
$3,0
00.0
050
12" W
ATER
MAI
N D
UC
TILE
IRO
N C
L 52
(MAI
N)
LIN
FT
$40.
0051
CO
NN
ECT
TO E
XIST
ING
WAT
ER M
AIN
EAC
H$2
,000
.00
52IN
STAL
L H
YDR
ANT
& VA
LVE
EAC
H$5
,000
.00
531"
TYP
E "K
" CO
PPER
PIP
ELI
N F
T$2
0.00
546"
WAT
ERM
AIN
DU
CTI
LE IR
ON
CL
52 (H
YD L
EAD
S)LI
N F
T$3
6.00
55TE
MPO
RAR
Y W
ATER
SER
VIC
ELU
MP
SUM
$50,
000.
00TR
EETS
CA
PE IT
EMS
56LI
GH
TIN
G U
NIT
TYP
E A
EAC
H$7
,500
.00
57LI
GH
T BA
SE D
ESIG
N A
EAC
H$7
00.0
058
CO
ND
UIT
AN
D W
IRIN
GLI
N F
T$1
5.00
59O
VER
STO
RY
TREE
STR
EE$6
00.0
060
TREE
GR
ATE
EAC
H$1
,500
.00
RO
SIO
N C
ON
TRO
L61
ERO
SIO
N C
ON
TRO
L-G
ENER
ALLU
MP
SUM
$15,
000.
0062
TEM
POR
ARY
RO
CK
CO
NST
RU
CTI
ON
EN
TRAN
CE
EAC
H$1
,000
.00
63ST
OR
M D
RAI
N IN
LET
PRO
TEC
TIO
N -
MAI
NTA
INED
EAC
H$1
50.0
064
SOD
DIN
G T
YPE
LAW
NSQ
YD
$4.5
0Su
btot
als
QTY
STR
EET
STO
RM
SAN
ITAR
YW
ATER
QTY
STR
EET
STO
RM
SAN
ITAR
YW
ATER
QTY
STR
EET
STO
RM
SAN
ITAR
YW
ATER
QTY
STR
EET
STO
RM
SAN
ITAR
YW
ATER
$0.0
00.
1$1
8,00
0.00
0.5
$90,
000.
000.
05$9
,000
.00
$0.0
00.
1$6
,000
.00
0.5
$30,
000.
000.
05$3
,000
.00
$0.0
0$0
.00
$0.0
020
$10,
000.
0040
0$2
,000
.00
3450
$17,
250.
0022
60$1
1,30
0.00
$0.0
040
$400
.00
$400
.00
350
$3,5
00.0
048
5$4
,850
.00
$0.0
0$0
.00
765
$4,5
90.0
038
0$2
,280
.00
$0.0
0$0
.00
370
$2,2
20.0
080
0$4
,800
.00
$0.0
0$0
.00
$0.0
0$0
.00
800
$4,8
00.0
085
0$1
,275
.00
6441
$9,6
61.6
766
35$9
,952
.17
$0.0
096
$576
.00
288
$1,7
28.0
025
0$1
,500
.00
150
$900
.00
64$2
56.0
051
2$2
,048
.00
200
$800
.00
$0.0
00
$0.0
0$0
.00
736
$3,6
80.5
6$0
.00
1$1
00.0
0$0
.00
2$2
00.0
0$0
.00
$0.0
07
$5,6
00.0
04
$3,2
00.0
0$0
.00
90$2
70.0
046
8$1
,404
.00
260
$780
.00
$0.0
056
0$7
,840
.00
4787
$67,
013.
4442
89$6
0,05
1.25
4932
$69,
054.
4656
$784
.00
396
$5,5
44.0
042
9$6
,005
.13
493
$6,9
05.4
550
$1,2
50.0
036
1$9
,029
.17
69$1
,726
.39
372
$9,3
04.1
795
0$1
,900
.00
7771
$15,
541.
1168
23$1
3,64
6.22
8007
$16,
014.
4462
7$6
,270
.00
5129
$51,
285.
6745
02$4
5,01
8.33
5285
$52,
847.
6741
8$5
,225
.00
3419
$42,
738.
0630
03$3
7,53
6.11
3523
$44,
039.
7240
0$4
,000
.00
3940
$39,
400.
0022
60$2
2,60
0.00
4060
$40,
600.
0043
$170
.00
317
$1,2
69.5
630
1$1
,204
.00
327
$1,3
08.2
282
$5,5
71.7
554
7$3
7,22
9.72
520
$35,
349.
8056
4$3
8,36
3.62
109
$7,2
10.5
073
0$4
8,17
9.63
690
$45,
526.
8075
2$4
9,64
7.03
10$8
14.5
877
$6,5
16.6
7$0
.00
$0.0
0$0
.00
$0.0
0$0
.00
608
$51,
708.
33$0
.00
$0.0
012
075
$60,
375.
00$0
.00
400
$4,6
00.0
029
50$3
3,92
5.00
2260
$25,
990.
0040
60$4
6,69
0.00
864
$5,1
84.0
025
92$1
5,55
2.00
2250
$13,
500.
0013
50$8
,100
.00
$0.0
0$0
.00
7$2
,800
.00
3$1
,200
.00
$0.0
0$0
.00
84$3
,780
.00
36$1
,620
.00
0.1
$3,0
00.0
00.
1$3
,000
.00
0.05
$1,5
00.0
00.
05$1
,500
.00
0.1
$200
.00
0.1
$200
.00
0.05
$100
.00
0.05
$100
.00
1$1
30,0
00.0
0
$0.0
043
0$1
5,05
0.00
400
$14,
000.
0011
60$4
0,60
0.00
$0.0
0$0
.00
$0.0
020
0$7
,600
.00
$0.0
02
$3,2
00.0
05
$8,0
00.0
03
$4,8
00.0
0$0
.00
2$4
,500
.00
2$4
,500
.00
3$6
,750
.00
$0.0
0$0
.00
2$3
,000
.00
2$3
,000
.00
$0.0
06
$15,
000.
00$0
.00
3$7
,500
.00
$0.0
010
$1,5
00.0
03
$450
.00
1$1
50.0
0$0
.00
10$5
,000
.00
3$1
,500
.00
$0.0
0$0
.00
$0.0
045
0$1
6,20
0.00
850
$30,
600.
00$0
.00
774
$21,
672.
0060
$1,6
80.0
025
$700
.00
$0.0
00.
2$1
,000
.00
0.1
$500
.00
$0.0
0
$0.0
02
$3,8
00.0
02
$3,8
00.0
02
$3,8
00.0
0$0
.00
370
$13,
320.
0011
65$4
1,94
0.00
800
$28,
800.
00$0
.00
$0.0
0$0
.00
$0.0
0$0
.00
$0.0
0$0
.00
$0.0
0$0
.00
1$2
,000
.00
3$6
,000
.00
1$2
,000
.00
$0.0
01
$5,0
00.0
03
$15,
000.
002
$10,
000.
00$0
.00
$0.0
024
0$4
,800
.00
180
$3,6
00.0
0$0
.00
20$7
20.0
060
$2,1
60.0
040
$1,4
40.0
0$0
.00
$0.0
00.
18$8
,750
.00
$0.0
0
16$1
20,0
00.0
016
$11,
200.
0022
50$3
3,75
0.00
16$9
,600
.00
16$2
4,00
0.00
0.1
$1,5
00.0
00.
1$1
,500
.00
0.05
$750
.00
0.05
$750
.00
$0.0
00
$0.0
01
$1,0
00.0
01
$1,0
00.0
0$0
.00
5$7
50.0
07
$1,0
50.0
0$0
.00
262
$1,1
77.5
032
83$1
4,77
5.00
$0.0
013
53$6
,090
.00
$61,
574.
33$4
00.0
0$0
.00
$0.0
0$4
49,5
40.6
8$2
6,25
0.00
$54,
362.
00$2
7,06
0.00
$856
,271
.75
$34,
550.
00$2
5,61
0.00
$87,
250.
00$4
69,7
43.1
1$5
9,75
0.00
$41,
950.
00$5
4,44
0.00
RAI
LRO
AD (4
th to
Tig
er) -
New
Con
stru
ctio
nR
AILR
OAD
(Riv
er to
4th
) - R
econ
stru
ctM
ERR
IMAN
DR
- C
ompl
ete
Rec
onst
ruct
MER
RIM
AN C
T - R
econ
stru
ct
Tabl
e 3
Sum
mar
y of
Rig
ht o
f Way
/Eas
emen
t Nee
dsC
ity o
f Del
ano
2016
Infra
stru
ctur
e Im
prov
men
t Pro
ject
PID
Addr
ess
Pro
perty
Ow
ner
Exis
ting
Car
tway
/ Li
cens
e A
gree
men
t Ar
ea (S
F)P
erm
anen
t R
OW
(SF)
Tem
pora
ry
Con
stru
ctio
n E
asem
ent (
SF)
Trai
l Eas
emen
t (S
F)1
1075
0011
4203
27 F
RAN
KLIN
AVE
WPE
PIN
, JEN
NA
2,97
6
1,48
8
1,48
8
-
2
1075
0011
4201
23 F
RAN
KLIN
AVE
WW
ILLI
AMS,
TR
AVIS
2,19
0
1,09
5
1,09
5
-
3
1075
0011
4200
19 F
RAN
KLIN
AVE
WSC
HR
UPP
, TIM
OTH
Y &
HO
LLY
3,09
2
1,54
6
1,54
6
-
4
1075
0011
4202
15 F
RAN
KLIN
AVE
WES
TBY,
WAY
NE
& TH
ELM
A4,
014
3,
042
2,
168
-
110
7016
0020
22C
ITY
OF
DEL
ANO
-
5,
689
-
-
2
1070
1600
2030
SWAN
SON
, TER
RY
& R
OSE
MAR
Y-
2,00
0
-
-
310
7016
0020
31C
ITY
OF
DEL
ANO
-
2,
910
-
-
4
1070
1600
2050
510
RAI
LRO
AD A
VE N
FUTU
RE
DEV
ELO
PMEN
T PR
OP
LLC
-
3,
948
-
-
5
1070
9300
1020
MT
OLI
VE E
VAN
G L
UTH
ERAN
-
6,
294
-
-
6
1075
0012
3121
616
RAI
LRO
AD A
VE E
JOR
DAN
, WIL
LIAM
A
-
2,
854
-
-
7
1075
0012
3115
RN
P PR
OPE
RTI
ES-
2,41
0
-
-
810
7500
1231
2562
6 R
AILR
OAD
AVE
EJO
HN
SON
, GIN
O &
AM
Y-
4,43
6
-
-
910
7500
1231
0363
3 R
AILR
OAD
AVE
ER
IED
ER, B
ETTY
-
53
,300
-
-
1010
7500
1232
19SP
IKED
WO
LFE,
LLC
12,3
63
-
-
-
1110
7500
1231
2651
1 R
R L
LC15
,862
-
-
-
12
1079
9944
4100
BU
RLI
NG
TON
NO
RTH
ER
N22
,308
-
-
-
Table 4Preliminary Assessment Role2016 Infrastructure Improvement Project
PID Property Owner Address Rate/UnitNo. Assessable Units
Total Assessment
208200112400 Fred and Cheryl Gordon 407 Buffalo Street $12,497.92 1 $12,497.92
Pro
ject
2a
(201
5)P
roje
ct 2
(201
6)P
roje
ct 3
P
roje
ct 4
Pro
ject
5P
roje
ct 6
Figu
re 1
Cap
ital I
mpr
ovem
ent P
lan
Railroad AveRiver St to 2nd St
Railroad Ave - 2nd St to 3rd St2nd St - Railroad Ave to Bridge Ave
Figure 2
Street ScapeDetails
Figu
re 3
a
Trai
l Im
prov
emen
ts
Seg
men
t 1
Seg
men
t 2
Seg
men
t 3
200
ft
Figu
re 3
b
Trai
l Im
prov
emen
ts
Seg
men
t 4
200
ft
Figure 4
DitchImprovements
Pipe to beinstalled inthis segmentof ditch
150 ft
1
2
3
4
FRAN
KLI
N AV
ENUE
W
1ST ST SW
2ND ST SW
BABCOCK BLVD W/HWY 12
RO
CK
FOR
D A
VE
W
FRA
NK
LIN
AVE
NU
E W
EX
HIB
IT O
VE
RV
IEW
SE
1/4
SE
CTI
ON
11,
TW
P 1
18 N
, RA
NG
E 2
5 W
, WR
IGH
T C
OU
NTY
, MN
1
24
5
6
7
8
9
1011
12
4TH ST N
BR
IDG
E A
VE
E
FRA
NK
LIN
AV
E E
TIGER DRIVE
3
5TH ST S
RA
ILR
OA
D A
VE
WM
APL
E R
IDG
E D
R
RA
ILR
OA
D A
VEN
UE
WE
XH
IBIT
OV
ER
VIE
W
SW
1/4
SE
CTI
ON
12,
TW
P 1
18 N
, RA
NG
E 2
5 W
, WR
IGH
T C
OU
NTY
, MN
RA
ILR
OA
D A
VE
E
RA
ILR
OA
D A
VE
E
RA
ILR
OA
D A
VE
E
RA
ILR
OA
D A
VE
E
RA
ILR
OA
D A
VE
E
RA
ILR
OA
D A
VE
E
S 2
ND
STR
EE
T
1ST
STR
EE
T
1ST
STR
EE
T
1ST
STR
EE
T
FRA
NK
LIN
AV
E W
FRA
NK
LIN
AV
E W
FRA
NK
LIN
AV
E W
BR
IDG
E A
VE
W
BR
IDG
E A
VE
W
BR
IDG
E A
VE
W
BU
FFA
LO S
TRE
ET
BU
FFA
LO S
TRE
ET
BU
FFA
LO S
TRE
ET
BU
FFA
LO S
TRE
ET
BU
FFA
LO S
TRE
ET
ME
RR
IMA
N D
RIV
E
ME
RR
IMA
N D
RIV
E
ME
RR
IMA
N D
RIV
E
ME
RR
IMA
N D
RIV
E
ME
RR
IMA
N C
OU
RT
ELK
STR
EE
T
Toll Free: 800-472-2232 Email: [email protected] Web: wenck.com
MINNESOTA COLORADO GEORGIA NORTH DAKOTA SOUTH DAKOTA WYOMING
Maple Plain Golden Valley New Hope Denver Roswell Fargo Pierre Cheyenne 763-479-4200 763-252-6800 800-368-8831 602-370-7420 678-987-5840 701-297-9600 605-222-1826 307-634-7848 Windom Woodbury Fort Collins Mandan Sheridan 507-831-2703 651-294-4580 970-223-4705 701-751-3370 307-675-1148