civil en ineering studies - ideals.illinois.edu

91
'[V B- 3 CIVIL EN INEERING STUDIES HYDRAULIC ENGINEERING SERiES NO. 3 SI 5 5 A Preliminary lnvesfiqation By JOHN C. GUnlOU end VEN ire CHOW Metz Referenoe University of: I1Jinoig 13106 ReEL 208 i-T Q Romine Illinois 61801 June 1954 DEPARTMENT OF CIVIL ENGINEERING UNIVERSITY OF ILUNOIS URBANA, ILLINOIS

Upload: others

Post on 02-Oct-2021

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CIVIL EN INEERING STUDIES - ideals.illinois.edu

'[V

X~'1 B­3 CIVIL EN INEERING STUDIES

HYDRAULIC ENGINEERING SERiES NO. 3

SI

5 5

A Preliminary lnvesfiqation

By

JOHN C. GUnlOU

end

VEN ire CHOW

Metz Referenoe RQ.o~ University of: I1Jinoig

13106 ReEL 208 i-T Q Romine

Mrb~~a~ Illinois 61801

June 1954

DEPARTMENT OF CIVIL ENGINEERING

UNIVERSITY OF ILUNOIS

URBANA, ILLINOIS

Page 2: CIVIL EN INEERING STUDIES - ideals.illinois.edu

DESILTING STRUCTURES FOR HIGHWAY DRAINAGE SYSTEMS

By

JO~ C. GUILLOU Research Assistant Professor of Hydraulic Engineering

and

VEN TE CHOW Research Assistant Professor of Civil Engineering

A Report of a Preliminary Investigation Conducted by

THE ENGINEERING EXPERThtENT STATION UNIVERSITY OF ILLmOIS

In Cooperation with

Metz B~t~~~fi@~ ~@§~

THE DIVI8 ION OF HIGHWAYS .Universi't.;y

STATE OF ILLINOIS 208 N. Romine street

and Urbana\)

THE BUREAU OF PUBLIC ROADS U. S. DEPARTMENT OF COMMERCE

Project IHR ...4 HIGHWAY DRAINAGE

ILLINOIS COOPERATIVE HIGHWAY RESElffiCn PROGRAM

Urbana) Illinois June 1954

Page 3: CIVIL EN INEERING STUDIES - ideals.illinois.edu

I

ABSTRA:CT

The search for a well-designed desilting structure becomes very desirable due to the requirements of high efficiency and best economy in the planning of rapidly expanding program of the modern expressway construction. The study reported herewith covers a comprehensive review of literature related to various subjects of the investigation, an analytical study of a topic area ~elected from the portion of the Congress Street Expressway at Chic~go) Illinois, a comparative stUdy of the conventional Itinlet ,box-catCh basin H

system as designed for the topic area and the "Ln.l.et box-desilting chambe r " system as applied to the area, and other aspects concerning the hydraulic design of a desilting chamber.

The results of this investigation reveal that for a rainfall having a two-year design frequency; the desilting efficiency for the inlet box-catch basin system amounts to less than 30% based on inlet grates having bars parallel to the direction of the flow~ As it pertains to· the Congress Street

.. "proposed Improvemerrt J 'this would cause 70% or more of the silt to be carried into the main drain. For greater amounts of rainfall a larger percentage of silt would be carried to the main drain. In order to overcome this objection­able feature due to the inefficiency of the catch basin design) two alternatives are suggested. The first alternative is to provide more than dopble the number of inlets and catch basins in. order to reduce the intensity of flow. The-second alternative is to suggest the construction of a desilting chamber.at each of selected low points in the highway grade line-in lieu of the numerous catch basins for a project such as the proposed Congress Street Expressway. For the first alternative method, the study shows that this is unsatisfactory from the viewpoints of economy and efficiency. For the second alternative method, further investigation on the comparison of efficiency and cost between the desilting chamber and the catch basin system is required. A possible kinetic sedimentation type structure utilizing the principle of a vortex-tube is developed and proposed for laboratory investigation. As this suggested structure requires additional investigation and research on both its design principle and its prototype and model tests, its description is included in appendix for the purpose of reference only.

i

Page 4: CIVIL EN INEERING STUDIES - ideals.illinois.edu

CONTENTS

I. INTRODUCTION

1. Significance of the Study

2. Objective of the Study

3. Scope of the Study

4. Sources of Information for the Study

5. Acknowledgments

II. THE DRAINAGE SYSTEMS

6. The Topic Area

7. Origination of the Surface Runoff

8. Function of the Catch Basin as Designed for the Topic Area

9. Application of the Desilting Chamber to the Topic Area

III. THE DESILTING STRUCTURES

10. Desilting Chamber

a. General

b. Flow Requirements for Hydraulic Design

c. Particle Size Requirements for Hydraulic Design

11. Intercepting Sewer

a. General

b. Hydraulic Characteristics

c. Intercepting Sewer Particle Size Determined by Grit Chamber Principle

d. Intercepting Sewer Particle Size Determined by Sample Analysis

ii

Page iv

vi

vii

1-5

1

2

2

3

4

6-14

6

7

9

-11

14-40

14

14

15

16

17

17

17

19

21

Page 5: CIVIL EN INEERING STUDIES - ideals.illinois.edu

Page Sedimentation Chamber Z7 a. General 27

b. Design by the Camp Method 28

c. Design by the Kivell and Lund Method 31

Study of Other Separation Methods

A. Desilting Structure Developed in Sanit~ry

Engineering 35

a . Aeration Type Grit Chamber 35

b. Micro-Straining 36

B" DesiltingStructures Developed in Hydraulic Engineering 36

~. Riffle-Vane Deflector 37

b. Vortex-Tube 38

APPENDIX I THEORY OF GRAVITY SEPARATION FOR GRIT CHAMBER DESIGN 40-44

APPENDIX II - THEORY OF SEDIMENT DISTRIBUTION 45-52

A. Studies at Cornell University 45

B. Studies at University of California 47

C'c. Studies at U. u. Waterways Experiment Station 48

D. Studies at University of Iowa 50

APPENDIX III - EVOLUTION OF A POSSIBLE KINETIC­SEDIMENTATION TYPE DES ILTING STRUCrURE 53-59

A. The Proposed System 53

B. Critical Design Elements 54

a. The Approach Channel 54

b. The Vortex-Tube 55

c . The Sedimentation Chamber 55

G. Proposed Laboratory Investigation 56

D. HC@OHiHlG1':lQatiofiS ~

60-61APPENDIX IV - BIBLIOGRAPHY

iii

Page 6: CIVIL EN INEERING STUDIES - ideals.illinois.edu

FIGURES

Figure 1 - Roadway Plan and Profile of the Topic Area.

Figure 2 - Elements of North Half Ty-pical Roadway Cross Sec-cion of the Topi-c Area

Figure 3 = Trapping Efficiency of Catch Basin.

Figure 4 _. Application of the Inlet Box-Desilting Chamber Design to the Topic Area.

Figure 5 - Profile of the Ma.in Intercepting Sewer for the Congress Street Expressway, from Austin Street to Junction Manhole, Chicago.

Figure 6 ... Cross Section of the 8,,00 ft. by 7020 fto Main Intercepting Sewer.

Figure 7 - Hydraulic Elements of the 8.00 ft. by 7.20 ft. Main Intercepting Sewer Section.

Figure 8 = Velocity and Discharge Curves for the 8.00 ft. by 7.20 ft. Main Intercepting Sewer Section.

Figure 9 - Hydra,ulic Gr.ade Line Computed for the Intercepting Sewer for the Congress Street Expressway, from Campbell Street to Junction Manhole, ChLcago ,

F,i;gure.10 - Velocity and Discha.rge Curves for the 8.00 ft. by 7.20 ft. Main Intercepting Sewer Section.

Figure 11 ... Critical Scouring Velocity.

Figure 12 ... Particle Size Distribution Curves for Champaign-Urbana Samples.

Figure 13 - Particle Size Distribution Curves for Chicago Samples) Nos. 1) 2 7 and 3.

Figure i4 Particle Size Distribution Curves for Chica.go Samples) Nos. 4 .and 5.

Figure 15 ... Particle Size Distribution Curves for Chicago Samples, Nos. 6, 7 and 8.

Figure"16 - Theoretical Settling Velocities of Spherical Particles.

Figure 17 ... Desi1ting Chamber Design Curve by the Camp Method.

iv

Page 7: CIVIL EN INEERING STUDIES - ideals.illinois.edu

18 - Desilting Chamber Design Curve by the Kivell and Lund Method.

19 - Settling Principle of.Ideal Settling Zone.

20 - Design Charts for Approach Channel Dimensions.

21 - Schematic Drawing of the Kinetic-Sedimentation Type Desilting Structure.

v

Page 8: CIVIL EN INEERING STUDIES - ideals.illinois.edu

1

2

3

4

5

6

TABLES

- Sediment Samples from Champaign-Urbana.

- Sediment Samples from Chicago Calumet Expressway.

- Characteristics of Sediment Samples.

- Settling Velocities of Granular Materials.

- Chamber Dimensions Determined by the Camp Method.

- Chamber Dimensions Determined by the Kivell and Lund Method.

vi

Page 9: CIVIL EN INEERING STUDIES - ideals.illinois.edu

NOMENCIATURE

drainage area in sq. ft.; surface area of the settling zone of a settling tank; or projected area of a particle.

B ::: Shields f experimental constant for settling of particles in liquid.

c = runoff coefficient.

CD ~ drag coefficient.

D ::: diameter of pipe.

d ::: diameter of a sphere. de. -;:= Cf'J'';,'ud de.t~. FD ::: drag force.

F ::: settling force. s

f. == Darcy-Weiabach friction factor.

g == gravitational acceler.ation.

H == depth of flow in ft.

I == rainfall intensity in in. per hr.

K grit size in terms of Tyler mesh number .

L == length of the .settling zone of a settling tank.

N' == L/W.

Q == discharge in cf's .

s specific gravity.

T == detention time.

v == velocity of flow in ft. per sec.

V == critical velocity in ft. per sec.c

V == horizontal through velocity.H

Vo == settling velocity in ft. per sec.

W == width of the settling zone of a settling tank.

p absolute viscosity of fluid

I' == mass density of particle.

1'1 == mass density of fluid.

vii

Page 10: CIVIL EN INEERING STUDIES - ideals.illinois.edu

1

I. INTRODUCTION

1, 2Jgnificance of the Study

The desilting structure considered in the highway drainage system is an

element which is installed in the system for the purpose of removing objec­

tionable solid materials from flow before they reach the-main intercepting

sewer, and, thus, to prevent silt deposits in sewers and avoid injury to pumping

machinery.

Due to the requirements of high efficiency and best economy in the planning

of rapidly expanding program of the modern highway construction, the search for

a well-designed desilting structure is very desirable. The need for such study

for possible improvement of the~onventional type .of desilting structure, or

catch basin, has become particularly apparent upon completion of the tests of

the catch basin currently designed for use on the Congr'eas street Expressway

in the City of Chicago. The tests were made at the Hydraulic Engineering

Laboratory of the University of Illinois. They consisted ofa series of 1:2

model tests of subsurface drainage facilities for a portion of the Congress

Street Expressway. The results indicate that the conventional type of cat.cli

basin will not operate effectively when inlet grates of modern design are used

to intercept the water from the gutter. The parallel bar type of grate has a

very high intercepting efficiency which increases the flow into the catch basin

to such a degree that the desilting function -is destroyed or materially reduced

by an excessive: volumeof:o_Tlow,.

It was the suggestion of the Technical Advisory Committee of the Project

Page 11: CIVIL EN INEERING STUDIES - ideals.illinois.edu

2

that exploratory studies on methods to be employed in desilting storm water be

made and a preliminary report thereon be prepared.

2. Objective of the Study

This study was made to conform with the recommendation of the Technical

Advisory Committee as stated above. The objective is to investigate the

theoretical aspects of design, constructio~and'operation of a desilting

system and structures and to utilize such knowledge gained by the investigation

for exploring possibilities of improving certain subsurface drainage structures

currently employed in the drainage of highways, particularly expressways,

or q.eveloping a new type of desilting system and structures.

This report presents the results of the study and terminates the recommended

exploratory investigation.

3. Scope of the Study

This study covers the following major items: (1) A comprehensive review

of literature related to sBbjects~of the investigation, (2) an analytical

study of a topic area which is a portion of the westbound roadway of the Congress

Street Expressway between South Laflin street and South Throop Street, (3) a ~

comparative study of the conventional "Ln.Let box-catch basin11 system as designed

for the topic area and the "LnLet box-desilting cnamber " system as applied to

the area, (4) a study of the desilting chamber &nd the flow and particle size

requirements for its hydraulic design, (5) an investigation o~ the intercepting

sewer with respect to its hydraulic characteristics and particle carrying

capacity, (6) an appraisal of the function of a sedimentation chamber and its

design theories and methods, (7) the development of a possible kinetic-

Metz Reference Rco.i University of IIJ.inol.:;

Bl06 NeEL 208 N. Romine street

Urbana, Illinois61~

Page 12: CIVIL EN INEERING STUDIES - ideals.illinois.edu

3

sedimentation type structure with the consideration of its critical design

elements and the proposed laboratory investigation, and (8) recommendations

for the prosecution of future studies required for the proposed type of structure.

A survey of literature of the theory of sediment distribution was also made and

a bibliography was prepared.

4. Sources of Information for the Study

Owing to the rare nature of the structure under study, a wealth of pertinent

data is not available. However, the information which constitutes the background

of this study was obtainable from various sources. Applicable existing

information was found as follows:

(1) Data for the Topic Area--This was obtained from the Department of

Subways and Superhighways of the City of Chicago. A drawing showing the roadway

plan and profile for the topic area was furnished by that Department.

(2) Samples of Storm Sewer Sediments--These were collected in the Champaign­

Urbana area and along the Calumet Expressway in the City of Chicago. Size

distributions of the samples were analyzed in the University Hydraulic Engineering

Laboratory.

(3) Existing Catch Basin Design--'There is a mass of material in 'the

literature of this field dealing with the maintenance of ty~ical, standard type

facilities. It is believed that the only available information relating to

the desilting operation of catch basins is that obtained from the tests made

at the U~iversity of Illinois as a part of the current cooperative research

project.

Page 13: CIVIL EN INEERING STUDIES - ideals.illinois.edu

4

(4) Sedimentation Chamber Design--This material is almost entirely in

field of sanitary engineering. At almost every large sewage treatment

plant the sa:nitary engineer is faced with the problem of removing the

larger particles of grit, or detritus, before passing the flow to primary

treatment tanks. The theory developed for grit chamber design was used for

the study of sedimentation chamber design.

(5) Bedload Removal Type Design--This type of design is intended

principally for the removal of bedload in irrigation and delivery canals.

Several devices have been developed for this purpose. The principles

involved were investigated for the present study.

All the most pertinent available literature and data have been collected

and studied in an effort to develop a background theory and principle for the

design of a satisfactory highway drainage desilting structure.

5. Acknowledgments

The studies reported in this publication were a part of Project IHR-4,

investigation under the Illinois Cooperative

Highway Research Program. This investigation was conducted by the Hydraulic

Engineering Staff of the Department of Civil Engineering as a part of the work

of the Engineering Experiment Station of the University of Illinois and was

'sponsored by the Division of Highways of the State of Illinois with the coopera­

tion of the Bureau of Public Roads of the U. S. Department of Commerce.

The following persons were responsible for th~ general administrative

supervision of the investigation covered by this report~

For the University of Illinois:

Dean W. L. Everitt, Director of the Engineering Experiment Station Professor W. C. Huntington, Head of the Department of Civil Engineering Ellis Danner, Professor of Highway Engineering, in charge of the Illinois

Cooperative Highway Research Program

Page 14: CIVIL EN INEERING STUDIES - ideals.illinois.edu

5

For the Division of Highways:

F. N. Barker, then Chief Highway Engineer W. La Esmond, Engineer of Research and -Planning Wa E .. Chastain, Sr., Engineer of Physical Research

For the Bureau of Pub-lie Roads:

H. S. Fairbank, Deputy Commi~sioner, in Charge of Research C. F. Izzard, Chief, Hydraulics Branch F. L. Anthony, Materials Engineer, Illinois District

The direct supervision and technical direction of the investigation \

were provided by the following:

Professor J. J. Doland, Project Supervisor Professor John C. Guillou, Project Investigator

Technical advice and suggestions for work programming were provided

for the studies covered by this report by a Project Advisory Committee consisting

of following members:

Representing the University of Illinois:

J. Ja Doland, Professor of Hydraulic Engineering H. L. Larrghaar, Prof'es sor of TheDretical and Applied Mechanics

Representing' the Division of Highways:

H. E. Surman, Assistant Engineer of Design W. E. Howland, Professor of Sanitary Engineering, Purdue University

Representing the Bureau of Public Roads:

c. F. Izzard, Chief, Hydraulics Branch Wallis S. Hamilton, Professor of Civil Engineering" Northwestern'University

Specialackrrowledgmerrt' is' made to Mr, E', R. Baumann, Research Associate in

the Department of Ciyil Engineering for his work on certain phases of the

investigation. Acknuwledgments are also gratefully made to Messrs, Dick Van

Gorp and W. E. Rasmus of the City of Chicago, Department of SUbways and Super­

highways for their help in obtaining silt samples from inlet boxes and gutters on

the Calumet Expressway in that city. The analysis was reviewed and the report

prepared by Dr. V. T. Chow.

Page 15: CIVIL EN INEERING STUDIES - ideals.illinois.edu

II. THE DRAINAGE SYSTEMS

6. The Topic Area

The portion of the highway structure which provides for drainage of storm

water that falls within the right-of-way area generally includes the following

items: the roadway pavement, shoulder and side slopes, longitudinal ditches

and gutters, inlet grates and boxes, desilting structures, manholes, collecting

sewers, intercepting sewer, and outlet. These items combined in various ways

of design constitute the drainage system of the highway.

Owing to the fact that the Highway Drainage Research Project was originally

established to study features of the. Congress Street Expressway in the City of

Chicago and also because a study of the prototype will best be an aid in the

preparation and comprehension of a typical design of the structure, a portion

of the westbound roadway of the Congr'es sBt.r-eet Expressway between South Laflin

Street and South Throop street was selected as the topic area for this study.

This area centers on the South Loomis Street bridge over the expressway. It

has the advantage that the section under consideration is typical of the major

portion of the depressed roadway in so far as the total right-of-way, roadway

and median strip development are concerned. The length of the drainage area at

this particular location is one-quarter mile which distance is close to the

maximum satisfactory length or the optimum, when considering only the undular

profile portion of entire expressway developmen~. The Department of Subways

and Superhighways of the City of Chicago furnished a rather complete set of

drawings, showing typical roadway development, grades; cross sections, surface

drainage plan and main intercepting sewer details for this portion of the roadway.

Page 16: CIVIL EN INEERING STUDIES - ideals.illinois.edu

7

Figure 1 shows the roadway plan and profile for the topic area and Fig. 2

shows the corresponding cross section", These figures were prepared from the

Department of Subways and Superhighways Drawing Nos. CP 1208 and CP 1294. It

should be noted that the depressed Expressway profile is a compromise between

the minimum excavation and the required clearance beneath the cross-over bridges.

The result of meeting these conflicting requirements is the undular profile,

as shown, with summits between cross-over structures and a sag beneath the

structure. The figure also shows that the roadway is symmetrical ~bout the

centerline of the median strip (or the right-of-way reference line as originally

indicated on the City of Chicago J Department of Sllbway~ and Superhighways Drawing

No. CP 1230), except for the main intercepting sewer which occurs only adjacent

to the northside, or westbound, roadway. Drainage from the south roadway is

carried under the median strip to the intercepting sewer.

As indicated on Fig. 1, the drainage design is based upon the use of inlet

boxes discharging through a connecting sewer to a catch basin. The catch basins,

located at close intervals, are intended to desilt both the flow supplied by the

inlet boxes and the flow intercepted by the catch basin itself. The flow

through the catch basin in turn discharges into a collecting sewer which conducts

the flow to the drop manhole and the interceptor.

7. Origination of the.?urface Runoff

The sur-f'ace runoff within the right-of-way area of the highway originates

from the five sub-areas A, B, C, D and E in Figs. 1 and 2. The description and

the flow path for each of the sub-aFeas ,are as follows:

(1) Sub-area A-·--This area is composed of the depressed highway

cut slope which occurs between the back of the toe-of-slope gutter and the back

of the access road curb. This area, as indicated on Fig. 2, is approximately

66 feet wide. The exact width varies considerably along the length of the

entire roadway. The flow path is do~n the turf cut slope and into the toe­

of-slope gutter.

Page 17: CIVIL EN INEERING STUDIES - ideals.illinois.edu

8

(2) Sub-area B---This area, between the mountable pavement-edge gutter

and the back of the-toe--of-slope-gut-ter, is approximately 12 feet wide.

The surface of the area is' expected to bee-ither stabilized turf on a stone

base or bit.umfnous paving. The rainfall intercepted on this area' is discharged

into the toe-of-slope gutter. This area also serves as a channel for the water

originating on sub-area C, which over-flows when the capacity of the mountable

pavement edge gutter is exceeded. The toe-of-slope gutter conducts this flow

to a catch basin for combined interception and desilting before it passes to

the collecting sewer and main intercepting sewer.

T3) Sub-area C---This area is composed of two concrete travel lanes,

each 12 feet -wide. Runoff which originates on the area flows to the pavement­

edge gutter.

That portion of the runoff which originates on this area up to the capacity

of the edge of pavement-edge gutter is carried by this gutter to an inlet box.

Runoff in the excess of the capacity of the pavement-edge gutter is passed over

sub-area B and into the toe-of-slope gutter. The flow entering the inlet box

discharges t.ovthe catch basin beneath the toe-of-sl,ope gutter for desilting

before passing to the collecting sewer. It is noted that regardless of rate

of runoff all flows which originate On sub-areas A and B pass through the toe­

of-slope gutter catch basin for desilting prior to the introduction of flow

into the main intercepting sewer.

(4) Sub-area D---Similar to sub-area C, this area is composed of two

12-ft. wide travel lanes and a gutter. All flows originating on this sub-area

a:re conducted to the inlet boxes located at frequent intervals beneath the gutter.

From the inlet box the flow is carried in a sewer to a catch basin which also

serves to collect and desilt water from an open ditch which is located parallel

with and adjacent to the median strip.

Page 18: CIVIL EN INEERING STUDIES - ideals.illinois.edu

9

(5) Sub-area E---This area is composed of the surface between the barrier

curb and the centerline of the median strip. The surface treatment consists of

turf except the trackage and ballast of the Chicago Rapid Transit.

It is noted that discharge originating on any of the five sub-areas is

conducted through circular catch basins for desilting purposes. Flows originating

on sub-areas A, B, and C pass through the toe-of-slope gutter catch basins, and

those originating on sub-areas Dand E pass through the open ditch catch basins.

In all cases the flows pass from catch basins to the collecting -sewers which

convey the water to the main intercepting sewer.

Function of the Catch Basin as Designed for the Topic Area

The drainage £ystem of the topic area as shown in Fig. I involves the use

of catch basin and inlet box. The catch basin ia intended to remove .from the

flow all debris which would cause serious deposition in the main intercepting

sewer. The ability of the catch basin to perform this function depends on the

design of the particular basin.

The operation of the catch basin used in the topic area has been studied

in the Hydraulic Engineering Laboratory of the University. The resulting

relationship between the discharge passing through the basin and the percent

of sand retained in the basin is shown in Figure 3. It should be understood

that the study from which the figure was developed was based upon a 1:2 scale

model and that the sand used to simulate silts in the prototype situation is

actually coarser than would be expected in most cases. Consequently, the

relationship shown in the figure is not exact, but it does serve as a qualitative

indication of the prototype action. The figure indicates that rates of flow

through the prototype basin in excess of about 1 cfs. will decrease the percent of

sand .re'ta.tned in..the basin. to .Leas ;than ·54%','91" s Ln..other 'Words,i;!'lill reduce the sane

Page 19: CIVIL EN INEERING STUDIES - ideals.illinois.edu

10

trapping, desilting efficiency to less than 54%. While the efficiency value of

is far below the desirable operational value, the maximum design rate of

flow for the basin is therefore limited to less than 1 cfs.

Considering the desilting function only, Fig. 1 indicates that a runoff

area of approximately 30,000 sq. ft. contributes flow to the cat~ basin beneath

the toe-of-slope gutter. The probable time of concentration for the area,

considering a maximum length of flow path of about 400 ft. and an average

'Velocity equal to 0.75 ft. per sec., is 533 sec. or about 9 min. According

to the intensity-duration-frequency curves of rainfall intensities at Chicago

""'developed by the hydrologic frequency .studj..es at the University of Illinois*,

the 2-yr. design frequency for a duration of 9 min. is 4 in. per hr.

Assuming a runoff coefficient of C = 0.80, the discharge from the drainage

area A = 30,000 sq. ft. or 0.688 acre:..: and a design rainfall intensity I = 4.0 in.

per hr. may be estimated by the rational formula as follows:

Q = CIA

= 0.80 X 4&0 X 0.688

= 2.2 cfs.

This figure represents the minimum expected runoff from the individual catch

basin drainage area when considering a 2-yr. design Etorm.

A runoff rate of 2 .2cfs. is well above the maximum allowable design flow

rate of 1 cfs. as determined from the catch basin desilting considerations.

For a rate of 2.2 cf's . , Ff.g, 3 shows a trapping efficiency of only about 30%.

As the curve in the figure indicates a sudden drop in efficiency by'increasing

the. discharge to above 2.5 .cf's , , a slight increase in the present rate of flow,

say, 0.5 cfs., would result in a trapping efficiency of only about 5%.

"Frequency Analysis of Hydrologic Data with SJ)ecial Application to Rainfall Intensities" by Ven Te Chow, University of Illinois Engineering Experiment Station, Bulletin Series No. 414; July 1953, p. 48.

Page 20: CIVIL EN INEERING STUDIES - ideals.illinois.edu

11

It is therefore- obvious that the catch basin system (as indicated in Fig. 1)

under consideration is unsatisfactory from the desilting viewpoint. This is true

for the 2-yr. design rat-e of flow, and apparently also for r;ates of flow higher

than thedesigrr frequency.

9. Application of the Desilting Chamber to the Topic Area

The previous article describes the fact that a combined inlet box-catch

basin syst-em, designed to eliminate troublesome deposits in the main inter­

cepting sewer, cannot function satisfactorily with the basin interval equal

to an average of 330 ft" as shownin Fig. 1. However J it seems- that the

situation may be improved by either of the two alternatives,: first, to

decrease the s-pacing,and thus reduce the ra-te of flow passing through the

structure, or second, to redesign the system making use of structures with more

efficient functional design.

Satisfying the design~function by reducing the inlet interval will make

the system operable. However, this .alternative is unsatisfactory from vie-:wpoip.ts

of economy and effi6iency.

Assuming, for illustrative ~urposes that a discharge of 1.0 cfs. is at

least partiaJ:.ly_· satisfactory and considering the rainfall intensity, the runoff

coefficient and the width of the drainage area to be constant, the rate of flow

estimated by means of the rational formula is directly proportional to the

length of the drainage area or the basin spacing. Therefore, the rate of flow

through the basin may be reduced from the estimated minimunr expected runoff

of 2.2 cfs .. to thema.ximum desigp. rate of 1 cfs .. by decreasing the basin interval

from 330 ft. to appr-oxfmat-e'Ly 150 ft. It is noted that changing the system in

this manner will increase the number of catch has ins to more than double the

eXisting number and thus will raise the cost of performing the desilting function

by more than 100%. Furthermore, the adoption of a short design interval equal

Page 21: CIVIL EN INEERING STUDIES - ideals.illinois.edu

12

to 150 ft. voids the advantages gained by the use of high efficiency gutters

and inlet grates. Therefore$ the alternative of decreasing the design basin

interval is not the answer because it is a move toward' less efficient and more

costly drainage facilities.

The second alternative toward meeting the design desilting function is to

develop a new system of more efficient overall characteristics. Laboratory

inves~igation has shown that the major cause of inefficient desilting function

in the circular catch basin is due to the formation of a nappe of flow coming

in from the Ln.Le t , Accordingly, the structure is not capable of performing

satisfactorily both the functions of flow interception and sediment removal.

The most logical solution to this problem seems to be the separation of these

two functions. This can be accomplished by the application of an inlet box­

desilting chamber design in which the inlet box is used to intercept flow only

while the desilting chamber does the job of separating the entrained silt.

The application of the inlet box-desilting chamber design to the topic

area is shown in Fig. 4~ The dra~nage sub-areas applied to this design are

the same as those for the inlet box-catch basin design discussed in Art. 7.

Considering flow collected in the toe-of-slope gutter, the operation of the

system is, as follows:

Flow in the gutter passes through the grate and enters into the inlet

box. The inlet grate removes all of the larger trash (i.e., twigs, newspapers,

large leaves, et c . ) which is carried along by the gutter flow. Discharge from

the inlet box consists of storm water with entrained suspended material, but

is free from large debris which could cause stoppage in the underground system.

The collecting sewer delivers the storm water, with its silt load, to the

desilting chamber located at the bottom of the vertical sag of the roadway

profile. The function of the desilting chamber is to remove all particles of

Page 22: CIVIL EN INEERING STUDIES - ideals.illinois.edu

13

silt which could deposit in the main intercepting sewer, at the condition of

the minimum design velocity in the intercepting sewer. After the removal of

the objectionable material in the desilting chamber, the flow passes to the

interceptor for final disposal, that is, by pumping the flow into the Chicago

River.

This system differs from the existing system in two respects: First,

catch basins }3!,re replaced by inlet boxes, and second, a desilting chamber is.

provided at the point of entry to the main intercepting sewer. The design and

,QP~ration of the inlet boxes may be ,accepted ,as readily feasible since such

structures are now used to a great extent in drainage systems in all parts of

the country. The desilting chamber, however, represents a new feature in this

type of drainage. The review of literature reveals that no such structure has been

designed for this partiCUlar purpose, and consequently, no operational data

are available ..

Before passing to the design consideration of the desilting chamber, some

comments regarding the, economic aspects of the two systems are desirable. It

(.' has been shown previously that catch basins must be installed at intervals of

150 ft. in order to attain ~ desilting efficiency of higher than 50% and to

even reasonably perform their design desilting function. According to Fig .. 1,

the topic area includ.es two series of catch basins, one beneath the toe-of­

slope gutter and the other beneath the open ditch in the median strip.. Each

of these series serves a length of 1,320 ft .. ' Using the required interval of

l50 ft .. , 'each series requires 9 basins and consequently, the topic area requires

18 catch bas Lns , Since the topic area considers only one half the total express­

way Width, 36 basins will be required between the summits of the quarter-mile

section of the roadway. Cons fder Ing the aLternate design, Fig . .4 shows that

12 inlet boxes are needed to inte.rcept the total flow which otherwise might he

Page 23: CIVIL EN INEERING STUDIES - ideals.illinois.edu

14

by catch basins. It follows that, for no extra cost, the cost of

desilting chamber be equal to the construction" cost of 24 catch basins

twelve times the difference in unit;cost of a catch basin over that of an

box. Assuming that the inlet box construction costs one-half of that of

the catch basin, the desilting chamber may cost thirty times the cost of one

catch basin in order to make the capital cost for structures in the two schemes

equal. Actually, the total cost in this case will be still in favor of the desilting

chamber because of the decrease in piping and i.maf.ntienance Basts in the new ays t.em.

III. THE DESILTING STRUCTURES

10. Desilting Chamber

a. General - From the standpoint of operational costs, and in most cases

from the standpoint of construction costs, it is reasonable to expect that the

most efficient desilting operation will be that operation which treats satis­

factorily the maximum rate of system flow. In the case of highways drained

by long continuous interceptors the maximum flow will always occur at the~""

intercepting outfall. Then, the logical location for the desilting chamber in

the Expressway drainage system is immediatelyupstrealTIfrom trhevpumpfng station

wet well. At this location, all flows may·be treated in a single structure

and all deposited sediments may be removed at a single point. It is believed

that such a system would lead to a maximum economy. This type of operation,

however, imposes certain limits on the entire storm flow collecting system.. It

is required that all the tributary sewerage be designed in such a way that the

major deposition of sediments will occur at a single desiltingchamber, and

also that the latter be so located that backwater and consequent· depositions

would not occur in the intercepting sewer. Moreover, the design of the

Page 24: CIVIL EN INEERING STUDIES - ideals.illinois.edu

15

ilting chamber must consider the- protection of the pumping system from

excessive wear and the total amount of sediment which may reach the chamber.

In some cases, because of flat gradients or other reasons, a single large

structure is not feasible and more than one desilting chamber is necessary.

The Congress Street Expressway represents such a case.

Considering the design of an inlet box-desilting chamber system, all

variables which enter into the operation of the system and all factors,

structural and hydraUlic, which affect the desilting function must be con­

sidered and evaluated. In the following portion of this article (Art. 10),

:",~:howe:ver, only two major hydraulic factors are discussed. These two factors

are the design rate of flow and the design particle size of the silt.

b. Flow Requirements for HydraUlic Design

The design rate of flow devends upon the size of the drainage area and

the magnitude of, the design storm frequency. Figure 4 indicates that the drain­

age area tributary to the topic area of the westbound roadways is apprOXimately

1,320 ft. by 180 ft. Since the desilting structure will serve both the

westbound and the eastbound roadways, the total tributary area at the vertical

sag of the roadway profile is doubJethat of the single roadway or apprOXimately

475,000 sq. ft. or 10.9 acres.

Due to the fact that the flow concentrates near the center of the area,

the time of concentration should be based on one-half the overall ,drainage

area length, or 660 ft. Considering that the total path is composed of about

50 ft. on the turf slope, 300 ft. in the toe-of-slope gutter with longitudinal

slope equal to 1%, and 350 ft. in the collecting sewer on a grade equal to

about 0.75%, the flow path of maximum length is about 700 ft. The overall

average velocity is approximately 0.9 ft. per sec. This is based on assumed

segmental velocities of 5 ft. per min., 3 ft. per sec., and 4 ft. per sec.

Page 25: CIVIL EN INEERING STUDIES - ideals.illinois.edu

16

respectively for the turf slope, the toe-of-slope gutter, and the collecting'

sewer. The length of the path of flow divided by ,the average velocity yields

a time of concentration of about 13 min.

As the stucture under consideration will serve a one quarter mile length

of the entire expressway width rather than one half of a 330 ft. length of a

single directional roadway in the case of catch basin design, frequency of

5 years is assumed for the purpose of the flow determination. From the rain­

fall intensity-duration frequency curves developed for the Chicago area,* the

5-yr. design rainfall intensity for a duration of 13 min. is about 4.2 in. per

Assuming a runoff coefficient of C ;::: 0.80, the discharge may be estimated

by the rational formula as follows~

Q=CIA

0.80 x 4.2 x 10.9

= '36.6 cf's .

This is the design rate of flow for the desilting chamber when the detention

effec.t of the' 'S3ystem is not cone Lder-ed,

c. Particle Size Requirements for Hydraulic Design

Concerning the particle size for the design of the desilting chamber, it

is' logical to assume that the largest particle size which will he allowed to

pass through the structure is the largest 'particle size which will be carried

by the main intercepting sewer at the minimum design velocity. The particle

'size generally accepted by sanitary engineers as the largest which will not

cause trouble with respect to excessive wear on pumping ~quipment or deposition

* "Frequency Analysis of -Hydrologic Data with' Special Application to Rainfall Intensities 11 by Ven Te Chow" University of Illinois Engineering Experimental Station, Bulletin Series No. 414} July 1953, p. 48

Page 26: CIVIL EN INEERING STUDIES - ideals.illinois.edu

17

in prin+a;ry treatment tanks is 0 e .2 mm, According to this criterion, it is

necessary to eliminate all particle.s greater than this a Lze :from the flow

entering the main intercepting sewer. However, it is believed that since no

treatment tanks .are involved, a Lar-ger size can be tolerated.. Such large size

would have no harmf'ul effect upon the storm water pumps. The maximum particle

size vas taken as O.5:mm. This vas determined on the basis of the c.alculated

hydraulic capacity of the intercepting sew-eras shown in Art. 11.

11. Intercepting Sewer

a. General - The profile of the main intercepting sewer is shown on Fig. 5.

Thf.s information was obtained from "Pl.ans for:Main Dr.ain ..,. Section 2425 I-D tl

and Dr.awing No. CP 1208 .of the Department of Subways .and Superhighways of the

City of' Ch Lcago . All pipes with size up to. 60 in. in diameter are standard

reinforced concrete: pipes. For largerstze,e, an egg-:shapesection 8 i s adapt.ed ,

Fig. 5 shows that) at Laramie Stree.t" the se~er cross section changes from the r .:

circular to an egg-ahape section with the maximm:;p. width equal to approxtma'te.Ly

nine'itenths of t-he sewer height. The profile d,raw=!-pgs also indicate that a

minimum slope of 0 ...0005 occurs af the dovns tz-eam end of the interceptor j where

the-sectionis largest. A study of the hydraulic elements, capa.city .and velocity

curves "Which have been pr.epared for·.all sections of the interceptor} confirms

the observation that this section of the sewer on a flat slope with maximum

croaa-s ect.LonaL'area is the critical section so far as the hydraulic transport

capacity is concer-ned', As shown by Fig. 5" the topic area of this s tudy drains

into the critical.section of ·the interceptor . .,

b. HydraUlic, Characteristics- The dimensions of the 8.00 ft. x 7.20 ftc

intercepting sewer aect.Lon of' the maximum cress-aectdons.L ar-ea are given in

Fig. ,6. The hydraulic elements of this aect.f.en are shown on Fig.. 7.. Assuming

.a roughness coef'f'Lc Lerrt of 0.0-13, the· "discharge and velocity curves .of the section

were computed by the Manning f'ormula and are s hewn in Fig. 8.

In large, flat-bottom sewers j relatively high velocitie.s for ,avoiding

Page 27: CIVIL EN INEERING STUDIES - ideals.illinois.edu

18

depds:ition during low flows are usually secured by concentrating,the flow into

a small, longitudinal channel or trough, known asa cunette. Referring to Fig.

6, it is noted that .such provision is not made in the section under consideration.

Hence, it is expected that some deposition of fine particles will take place

during times of low flow. Figure 8 shows that in order to keep an average

velocity of flow higher than 1 ft. per sec., the depth of flow must be main­

tained above 0.4 ft. A depth of 0.5 ft., is required to submerge the sewer invert

as indicated by Fig. 8. The curves in Fig. 8 indicate a velocity of 1.2 ft. per

sec. and a discharge of 340 tfs. at this depth. Obviously, the hydraulic

characteristics of the interceptor at low flow stage could be improved tremendously

by the installation of a low flow v-type cunette.

Fd.gure 8 indicate.s that the 8 ..00 x 7,,20 section with a slope of 0.'1005

can handle a maximum discharge of about 107 cf's . under the condd-t Lcn. of gravity

flow. However, the fact that the flow from the sewer is pumped, to the Chicago

River minimizes the': possibility of the discharge reaching this rate under normal

operating conditions. Considering the section of the interceptor just on the

upstream's.ide of the pumping station wet well, it is apparent that the actual

discharge can never exceed the :sum of the disCharge rate of the .storm water

pumps and the rate of flow contributing to the wet wellst~rage. As the suction­

well storage capacity is negligible, the maximum. rate of discharge through the

critical section of the interceptor will be equal to the total discharge rate

of the storm wat.er pumps" Information available at the time of this study

indicates that the pump capacity~y'be either 50 cfs. or 150 cfs.

For .a particular design storm, the positions of the hydraulic grade line

for hoth pump discharge rates of 50 and 150 cfs. have been calculated by Izzard

as shown in Fig .. 9. If the intercepting sewer is to be kept clean, and the

load entering a grit chamber is fixed by external conditions, the load leaving

the gritchamber must be held to a smaller amount when the interceptor cut.f'Low

is 50 cf's , than when it is 150 cf'a. For this reason" the discharge rate of

50 cfs. is assumed.

Page 28: CIVIL EN INEERING STUDIES - ideals.illinois.edu

19

For an assumed discharge rate of 50 cfs.) the normal depth of flow in the

intercepting sewer is 2.4 ft. Figure 10 gives the curves showing the variation

in discharge and velocity at diff'erentdellths of flow in the sewer. The portions

of the curves for depth less than 2.4 ft. are based on gravity flow conditions.

Portions with depth greater than 2.4 ft. are based on the assumed fixed discharge

of 50, cfs. The velocity curve indicates that maximum velocity through the

section will be obtained at the depth of 2.4 ft. As the stage in the sewer

increases) the velocity will decrease) until the sewer is flowing full, that is)

the hydraulic grade line becomes coincident with the sewer soffit. As the grade

line continues to rise) toward its maximum elevation of about 18 ft. above the

gutter invert, the velocity will remain constant and equal to the rate of dis­/()

charge divided by the area of the flow. F~g. -12- indicates that this velocity

is 1.09 ft. per sec.

The flow condition described above is equally a.PIllicable to other down­

stream sections of the intercepting sewer, provided, allowance for sewer storage

and incremental flow is properly made. Figure 4 indicates that under th~ design conditions the downstream

I

portion of the main intercepting sewer serves

as a storage reservoir} or an extension of the pumping station wet well. The

length of this downstream section is considerably greater than 20)000 ft. The

minimum velocity for a discharge rate of 50 cfs.at full flow is about 1 ft. per

sec. which will induce deposition. Since the velocity is low and the depQsition

will take place, this portion of the intercepting sewer acts like a grit 'chamber

but its capacity will be reduced if it functions as sUch. The principle and

functions of the grit chamber are described in the following article.

c. Intercepting Sewer Particle Size Determined by'Grit Chamber Principle

The grit chamber is a structure commonly used in sanitary engineering.

It is generally designed for two distinct functions. The first is to separate

particles entrained in the inflow by differential or gravity settling. The

Page 29: CIVIL EN INEERING STUDIES - ideals.illinois.edu

20

settling of grit and organics is said to be differential in the sense that

grit settles faster than most of the organic particles. The second is to scour

or sort settled solids on the floor of the chamber. The first function will be

discussed in more detail in Appendix I. The second function is. described here,

because this function and the related concepts are very significant in deter­

mining the maximum particle size which will be carried by the main intercepting

sewer.

The principle of grit chamber design was studied by Camp*. Use was made

of the results of extensive experiments by Shields** and theoretical considera­

of certain velocity characteristics of a flowing stream. Camp's studies

indicate that the so-called "critical velocity", or the velocity required to

start scour of deposited materials, can be estimated by means of the following

formula:

V c =J~ gf (8-1) d (1)

in which V c

= critical velocity in ft. per sec.

d = diameter of particle in ft.

s = specific gravity of particles.

g = gravitational acceleration.

f = !

Darcy-Weisbach friction factor which may be taken as 0.03 for grit chamber design.

B = experimental constant found by Shields to be equal to about o~o4 for unigranular materials. According to Camp, a value of B equal to about 0.06 is a good design value for a sticky material like sewage grit.

From Eq. 1 the particle size may be expressed by

V~ f (2)d = 8Bg(s-1)

Applying this equation to the main intercepting sewer with V = 1 cfs. c

f=O.03, B = 0.04, and S = 2.65, the maximum allowable particle size is

found to be

* "Grit Chamber DeaLgn ", by Thomas R. Camp, Sewage Works -Jour-na.L, March 1942, pp. 368-381.

** "An Analysis of Sediment Transportation in the Light of Fluid Turbu1e~ce,"

Sedimentation Division, U. S. Soil Conservation Service, Technical Pllhl ication 2S. JulY 19~9 9 25 pp.

Page 30: CIVIL EN INEERING STUDIES - ideals.illinois.edu

21

d = 2

( 1,.0) (0.03 ) (8)(0.04)(32.2)(2.65-1)

= 0.00177 ft.

Expressed' in millimeters ,the maximum particle size which should be allowed

to pass the" desilting chamber is 0.54 mm , Baaed on Eq. 1, Fig. 11 was prepared

to show the relationhetween the critical velocity, particle size, and the

constant B.

In assuming a proper design value of the maximum allowable particle size,

two assumpttons are considered as follows:

(1) The material entrained in sewage flow is unigranular in nature; that

is', it does not coalesce or form a flock, but retains, individual granular

characteristics. This assumption requires a value of B= 0.04) and as shown

in Fig. 11, it allows the acceptance of a larger particle size than might be

justified.

(2) The critical velocity used in thecomputa.tion is equal to the velocity

to start. scour of particles after deposition has occured. Obvi?usly this

assumption is conservative because additional tractive force must be available

to move ~he particle which is at rest. The assumed velocity and the resulting

particle size are therefore smaller than might be justified.

Because the assumptions are approximate and they tend to compensate each

other, a design value of 0.50 rom. may be assumed as the maximum allowable

particle size.

d. Intercepting Sewer Particle Size Determined by Sample Ana.IysLa-o-En an

effort to obtain information concerning the kinds] particle sizes and specific

gravtt.ies: of sediments that are likely to beencountere-din storm sewers', four ,<

samples were collected in the Champaign-Urbana area and 'eight samples were

collected along the Calumet Expressway in the City of Chicago.

(1) Champaign-Urbana samples --The four Champaign-Urbana sediment samples

are obtained from highway soil deposits and from storm sewer gutters as described

in Table 1" These samples were first dried in an oven at a temperature of

Page 31: CIVIL EN INEERING STUDIES - ideals.illinois.edu

22

approximately 105°C. and were then placed in the top sieve of a nest of U.S.

Standard sievese The nest, containing sieves numbers 4,16,40,60,80, and 120,

was placed in a Ro-Tap shaker and sieved for 3 minutes. The weight of the

residual sediment retained on each sieve was then determined and the percentage

of sediment passing each sieve- was calculated. 'I'he total amount of material

retained in sieves and in the bottom pan was compared to the total weight of

sample used to serve -as a check on the accuracy of the sieve analysis. Base-d

on the sieve analysi~, the size distribution curves for the Champai~n-Urbana

-sampLes were prepared and are shown in Ff.g . 12. It is noted that over 50%­

sample exceeq.s the allowable design particle size. The percent of

each sample exceeding the design limit of 0 .. 50 rom., or the percent of each

sample which must be removed by desilting chamber, is shown in Table 3.

The specific gravity of each ·of-the Champaign-Urbana sediment samples was

determined in the following manner: A 500-~1.-graduated cylinder was filled

with approximately 250-ml. oftJtwater.. A sample of known weight was poured into

the cylinder anq the latt~r was shaken for 2 min?tes to expel any air trapped

in the solids. Then the sedtment was allowed to settle and the volume of

solids was determined. .by noting .the new water level in the cylinder. The

weight of solids in grams divided by their volume in mI. gave numerically the

specific gravity of the solids. 'All -tif. the Champaign-Urbana sediment samples

had specific gravities ranging very narrowly fr:om 2.64 to 2 .. 65.

(2) Chicago samples -- The eight sediment samples collected at Chicago

were taken from deposits along the Caiumet Expressway, as described in

Table 2. These samp~es were dried for several days in glass beakers in an

o aOven set for a temperature of about 140 - 145 F. A nest of U. S. Standard

sieves 7 Nos. 4, 16, 20, 50, 60, and 80, was used in the sieve analysis. The

Whole sample of sediment was placed in the top sieve of the nest and was

Page 32: CIVIL EN INEERING STUDIES - ideals.illinois.edu

23

TABLE ·1

SEDlMENTSAMPLES FROM CHAMPAIGN."URBANA

Date

1 3/12/52

2

3 3/12/52

4 3/12/52

Place Obtained

North of Route 150 as it turns west off North Prospect Ave~

in Champaign.

On Green St.. in Champaign, one block east of South Neil St. on road leading to BuilderfsSupply Co.

Same location

On Goodwin St. in Urbana, 1/2 block

. north of Green St,;, just east of Goodwin St. and north of Boneyard Creek bridge.

Weight and Type of Sample

3 lb. sediment taken from curve deposit on state highway.

3 lb. sediment taken from deposit below drive on south side of Green St.

3 lb. sediment taken from deposits above drive on SQuth side of Green St.

3 lb. sediment from gutter along Goodwin St •

Page 33: CIVIL EN INEERING STUDIES - ideals.illinois.edu

TABLE 2"

SEDIMENT SAMPLES FROM CHICAGO CALUMET EXPRESSWAY

Place Obta1.ned Weight .and Type of Sample

7/2/52 Calumet Express"Way ,about 600 7.55 lb. west gutter feet ,south.of l30th Stre:et sw'eepings Q

7/2/52 Third inletS'outhof S .8."R.R. 2 ..12 lb. inlet mat.er ta.l on Calumet Expressway. 2 ft. circular .inletwith a-inch discharge pipe norma.1 to center line. 18-inchstr,a,ight s tandar-d, Ve.e;·gutt~rQn 0:0.34%" slope.

7/2/52 Shoulder mte,rial from location 3 ·39 lb. shoulder near .sour-ce 'of Sam,ple No.2 material' ,

7/2/ 52 Inlet :of ~est Bide On approach 5.83 lb. inlet material to C~lumet River Bridge. Same inlet type. as in~am:ple No.2 Uutte,r 'on 2. 7% B lope .

7/2/52 'Shoulder material f'rom .Locat.Lon 6.67 lb. shoulder near' .scurce ,of 'Sample ,No.4 mat.er-La.L

gmft e round ml#t in 18ftO!inch gutter" !lind-curb .~.t M1chi~an Av-e 8

~nd Chie~so Ro~d p ,8s1n~di~c;h§r~~ :pipe. Guttftr on ~r~a.~.of o~ 12 percent o'

SwrJ.;ple from gutter at location .4,.7; 10, .~tt~!!: mtel"i~l of Sam;pl." No.6.

S.~le frO'mentr,anc$ of 8...1nch ettachar~ pipe 1~~;v1ng inlet bas ina! S,s.mple No.6" Pipe ole,an b-elow 'entranc.e.9

Page 34: CIVIL EN INEERING STUDIES - ideals.illinois.edu

25

sieved in- the Ro-Tap shaker for.a period of 20 minutes. The 'Weight and percent

of material passing each sieve were then determined in the usual manner. The

specific gravity of each of the samples was dete~Ir!:ined using the procedure stated

previously for the Champaign~Urbana samples.

The size distribution curves for the sediment samples taken along the

Calumet Expressway in Chicago are shown in :Figs. 13, 14, and 15. Figure 13

shows the curves for the shoulder, gutter and inlet samplede]?ositscollected

south of 130thStreet. Figure 14 shows the distribution curves for shoulder

sample d.eposits collected on the approach to the Calumet Hiver Bridge.

15 shovs the distribution curves for the gutter, inlet and dis charge

deposits collected at Michigan Avenue iand Chicago Road.pipe sampLe

Table 3 contains a description .of the various characteristics of all

deposit samp.Lea, It shovs t.hat , in general, the Champaign-Urbana sediment

samples were composed of much coarser material. than were'the Chicago sediment

samples. The specific gravity of most samples was either 2.64 or 2.65. For

otherv samp.Ies , such as Chicago samples No. 4 and No.6" the sediment contained

a cons LderabLe emount ior cinderJ 'Wood, and other light-weightmaterials and

its specific gravity was less than 2.65. If the light 'Weight material were

separated from the sample, the specific gravity or the remaining material

"Would approach 2.65.

The last column of Table 3 gives the percent by weight of each sample

which exceeds the design particle size of 0.50 ram •.assumed previously. Chicago

sample No~.-8-is ."W'orthy of- particular attention.. As des cr-Lbed in Table 2" this

sample was taken from the inside of an 8-in. pipe which carries flow from an

inlet box .. The deposit "Was located just downstream from the supposed location

of the pipe entrance .area. Figure 15 indicates that 38% of this sample must be

removed by the desilting structure.

Page 35: CIVIL EN INEERING STUDIES - ideals.illinois.edu

26

TABLE 3

CHARACTERISTICS OF SEDIMENT SAMPLES

General Specific Median Particle Size Required . Description Gravity' Particle 10% of sample Removal

Size finer than

mm m.m % No.1 Shoulder Deposit 2.64 2.18 0.210 81

Gutter Deposit 2.65 0.42 0.10 40

Gutter Deposit 2.64 0.82 0.12 59

Gutter Deposit 2.64 2.12 0.306 84

Gutter Deposit 2.64 1.00. 0.16 66

Inlet Deposit 2.65 1.02 0.16 62

No.2

Gb.go .No.3 Shoulder Deposit 2.67 0.34 0.16 40

.No.4 Inlet Deposit 2.57 0.40 0.20 45

Chgo.No.5 Shoulder Deposit 2.67 0.27 0.20 30

Chgo.No.6 Inlet Deposit 2.40 0.60 0.16 58

Chgo.No·7 Gutter Deposit 2.65 0.34 0..14 41

Chgo.No.8 Discharge Pipe 2·57 0·32 0.16 38 Deposit

Page 36: CIVIL EN INEERING STUDIES - ideals.illinois.edu

27

The size distribution curves shown in Fig. 15 indicate the separating

action performed by an inlet box, although the inlet box was not designed as

a separation structure, and as a matter of fact only a small amount of material

was found in the inlet. These curves show that the inlet sample is considerably

sorting nas

samples

does

12.

coarser than the gutter deposits, and in a qualitative manner indicate that

occurred.

A further study of the field sediments indicates that none of the samples

collected exhibited a sticky characteristic. The shoulder and inlet box

were quite compact and dense, but particles showed no tendency to

, except as caused by the natural compaction. The natural compaction

not occur in the case of the entrained particles. This gives a further

evidence that the unigranular assumption described in the previous article

is acceptable.

Sedimentation Chamber

a. General -- The sedimentation chamber is a separation structure. From

previous,discussions it is understood that the separation structure under

consideration should be designed to remove particles with size equal to or

greater than 0.50 rom. and.that the maximum design rate o.f flow, at which the

separation takes place, is 36.6 cfs.

The separation of detritus from storm water flow has long been a problem

of sanitary engineers. In the case of a combined storm-sanitary sewerage

system, the problem becomes complicated by the fact that in addition to the

natural detritus, the entrained sol~~s are augmented by the addition of such

odd materials as egg shells, coffee grounds, fruit seeds, ashes, and almost

any other solid material the house-holder can wash do~n the drain. Theories

and methods have been developed and used for the design of grit removal chamber

in sanitary engineering. The methods by Camp and by Kivell and Lund are found

to be very useful for the purpose of this study and hence are used to determine

the required dimensions of the sedimentation chamber under consideration.

Page 37: CIVIL EN INEERING STUDIES - ideals.illinois.edu

28

b. Design by the Camp Method - Camp*has presented the theory of gravity

separation for the design of settling tanks and developed the method of design,

for practical use. A r~sum~ of the theory and the derivation of the formulas

in his method are given in Appendix I for the convenience of reference.

According to Camp, the smallest particle to be separated from the flow

under ideal settling conditions in a settling tank will have a settling

velocity expressed by

Q QVo = A = WL

in which Q = rate of flow through the tank.

A - surface area of the settling zone of the tank.

W = width of the settling zone.

L - length of the settling zone.

The value computed by this formula is the theoretical settling velocity required ,

for particle separation.

The settling velocity of the critical particle size could . ,

be determined

directly from studies of actual sediment samples. However, such studies were

not conducted because of the time required and the lack of information concern­

ing correlation between these and the design sediments. Based on a survey of

literature, the particle settling velocities in water for several granular

materials of various particle diameters are listed in Table 4. Of the four

materials listed in Table 4, the theoretical settling velocity of spheres,

with specific gravity of 2.65, is the most conservative, because this is the

lowest value,of settling velocity for a particle of a given equivalent diameter.

For the imIrtediate purpose of this study, the design was based on this theo­

retical data. Figure 16 gives the theoretical settling velocity which was

* '¥Bedimentation and the Design of Settling ·Tanks" by Thomas R. Camp, Transactions, American Society of Civil Engineers, Vol. III, 1946, pp. 895-936.

Page 38: CIVIL EN INEERING STUDIES - ideals.illinois.edu

29

TABIE 4

SETTLING VELOCITIES OF GRANULA..R MATERIALS

Theoretical Settling Vel- Settling Vel- Settling Vel-Diameter of Settling Vel- 'oeity of Sand** oeity of Quartz ocity of Sand

Particle ocity'of Spheres* grains*** grains**** T = 500 F T = 64° F T = 680 F T = 680 F Sp. Gr. = 2.65 Sp. Gr. = 2.65 Spa Gr. = 2.65 Sp. Gr. = 2.65

mID/sec ft/sec mm/sec ft/sec mm/sec ft/sec mID/sec ft/sec 100 0.328 118 0·387 98 0·322 119 0·390

92 0·302 110 0·361 93 0·305 liO 0·360

83 0.272 100 0.·328 85 0.279 101 0·329

72 0.236 90 0.295 78 0.256 90 0.295

63 0.207 79 0.269 70 0.230 80 0.263

53 0.174 67 0.220 62 0.203 71 0.230

42 0.138 52 0.171 52 0.171 59·5 0.195

32 0.105 39 _Ck128 39 0.128 49 0.160

21 0.069 23 0 .. 076 23 0.076 34.5 0.113

0.15 15 0.049 15 0.049 15 0.049 25·9 0.085

''7 ~,4 0.0262 7 ·9 0.<)27

'4'.8 .0.0197 5·1 0.017

2~5

l.~l

0.0125

0.0069

--~

.'.".~

"Sewerage and Sewage 'I'reatmerrt ", H.E. Babbitt, Sixth Edition, p . 366.

fTGrit Chamber Des Lgn", Thomas R,. Camp, Sewage Works Journal, March 1942, Fig. I, p. 369.

,1lSettling Velocities of Gravel; Sand and Silt H W"W•Rubey J American Journal of~BefenceJ Vol" 25; 1935) pp. 325-328 .

liThe Transportation of Sand in Pipe Lines It M.P. ,0lBrien and R.G. Folsom, University of California Publication in Engineering" Vol. 3, NO·7· 1937, pp. 343-384.

Page 39: CIVIL EN INEERING STUDIES - ideals.illinois.edu

30

prepared from the spherical particle data in Table 4. The curve in this

figure for particle diameter ranging from 0.2 to 1.0 mID. can be represented

by the following empirical equation:

v = 0.33 d 0·95 (4)o

This is the settling velocity for particle of a given size.

In the chamber design, the chamber velocity required for the separation

of particles of certain given size should be equal to the settling velocity

of particles of the given size; that is, the velocities expressed by Eqs.

(3) and (4) should be equal,

or ~L = 0·33 d 0·95 /

Solving for the width, W,

QW = --~---:"'.....--- (6)

0·95 L0·33 d

Let NL or L = NW, then=W

W -j Q - 0.33 d 0·95 N

This equation is used to determine the width of the separation chamber for

a particle size ~, rate of flow ~, and value of N. The length of the chamber

is equal to NW. Considering a design value of 0.50 mm. for the critical

particle size as determined previously, the width becomes

(8)W = 2.42) ~

This equation was used to construct the family of curves in Fig. 17, which

shows the relations between values of ~j ~, and !.

Considering a design rate of flow of 36.6 cfs. and a value of N = 2,

Fig. 17 gives W = 10.3 ft. and L = 2 x 10.3 =20.6 ft. which are the required

dimensions of an effective chamber to desilt the flow properly. Camp recom­

mended the following" equation for the computation of the maximum

Page 40: CIVIL EN INEERING STUDIES - ideals.illinois.edu

31

were computed and are

c.

velocity of the flow passing through the chamber: (See Art. 110)

V _j8B g (s-l) d (1)c f

2f = 0.03, g = 32.2 ft/sec. , s = 2.65, and d = 0.50 mm. =

0.00164 ft., the maximum allowable velocity through the chamber is

Vc =j~. ~3 0 . 04 :k 3~·2: x (2.65-l) x 0.00l64

= 0.964 ft. pe~ sec.

continuity, the effective depth must be

6d = 36 · . = :3 ~ 69 rt;.,10.3 x 0.964

imilarly, the required dimensions for other values of the length-width ratio

listed in the following table:

TABLE 5

CHAMBER DIMENSIONS DETERMINED BY TEE CAMP METHOD

N W L Vc d

2 10·3 20.6 0.964 3.69

3 8.5 25.4 0.964 4.47

4 7·3 29·3 0.964 5.20

Design by the Kivell and Lund Method - Kivell and Lund* have studied

experimentally the settling rate of sands with specific gravity equal to 2.65.

They observed the paths traced by particles of various sizes while settling

in streams of water flowing at several velocities experienced in grit chamber·

practice. A set of curves was prepared showing these paths and the relation

between the depth of flow, length of flow, and average velocity for a series

of flume tests involving sands of three sizes: Tyler mesh Nos. 100, 65 and 48.

* "Gr I t RemovaL'", by Kivell and Lund, Water Works and Sewerage" Part II, 1941, p. 144.

Page 41: CIVIL EN INEERING STUDIES - ideals.illinois.edu

32

Eq.

These curves may be represented approximately by the equation~

6.66H

in which H = depth of flow in ft.

L = length of flow in ft. (corresponding to the length of settling zon~)

v = velocity of flow in ft. per sec.

K grit size in terms of the Tyler mesh number.

Expressing the grit size in terms of particle diameter d in mm., the above

becomes

H = 0.28 d 0·94 (~) (10)V

By the law of continuity and the substitution of the above equation into

(3), (Art. Ilb),the width of the chamber is

W =: or w Q (11)

0.28 d 0.94 L

LLet N =. Wor L = NW, then

w- Q ( 12) - 0.28 d 0.94 N

Considering a design value of 0.50 rom. for the critical particle size, the

width becomes

w = 2.62 J Q/N

Th~s equation .may be compared with Eg. (8) developed by the Camp method.

It is expressed by a family of curves in Fig. 18 where each curve represents

a specific value of N:

With a design value of Q = 36.6 efs. and V = 0.964 ft. per sec. J the c

Page 42: CIVIL EN INEERING STUDIES - ideals.illinois.edu

33

chamber dimensions for N =2 J . 3 J .and 4 were c.omput.edand are listed in the

follow ing tabLe:

TABLE' 6

CHAMBER DIMENS IONS DETERMINED BY THE KIVELL AND LUND METHOD

N W L Vc d

2 11.2 22.4 0.964 3·39

3 9·2 27·6 0·964 4'.13

4­ 7·9 31 ..6 0·964 4 ..81

Comparing the values in Ta.ble 6 with those in Table 5, it is found that

the re.sults are in fair agreement . Generally speaking) the chamber developed

by the Kivell and Lund method has a larger surface area and a smaller

effective depth than one dev.eloped by the Camp method. The Kivell and Lund

method indicates a volume approximately 9 pm-cent greater than the volum.~

. . obtained by the Camp method. The dimensions determined byeither method

13,atis:fy the hydraulic r-equf.r-emerrta. However j the Kivell and Lund "method

appears to be slightly more .accurate.

The optimum des i.gn of the effective chamber .should be b,asedalso upon

the space allotment J and the costs of excavation.and the .mater:i,.alsof con­

struction. The aepth determined by the hydraulic requirements should be

increased about 2 ft .. to allow for the storage of accumulated sediments.

The optimumde,sign developed :abOve describes the settling zone of the

sediment separation structure. It is assumed in the theory that uniform

velocity would :exist throughout the .settling zone of the chamber. This

assumption requires that entrance and op:tlet zones be provided respectively

at the upstream and downstr.eamen.ds of the effective chamber length. The

function of the upstreamzone·~s to serve as a stabilizing or transition

"l''''''''· -, ••.:, ...•.. ".-,1':"" . ..,....., f1.

region extend.tng from the entranc.e pipe to the grit chamber. In a similar

Page 43: CIVIL EN INEERING STUDIES - ideals.illinois.edu

manner the outlet zone serves' to carry flow from the grit chamber to the

discharge pipe in such fashion that high velocity currents do not form in

the separation area. For the purpose of this example it is assumed that

the entrance zone consists of a transverse rectangular channel discharging

flow to the settling chamber through ports or over a weir extending the full

width of the chamber. If this channel is about 6 ft. deep, a width of about

4 ft. would be required to decrease the maximum velocity to about 1.5 ft.

sec. A similar channel may be assumed at the outlet zone of the separation

structure. Assuming a length-width ratio of N = 2, and a wall thickness of

8 in. the size of the overall structure for the topic area would be approx­

imately 12 ft. 4 in. wide, 32 ft. 8 in. long, and 6 ft. 8 in. deep.

It has been shown in Art. 9 that if the inlet box construction costs

one-half of that of the catch basin and the structure used to deslilt the entire

flow from tohe topic area costs less than thirty times the cost of an individual

catch basin, then the desilting chamber would be economically feasible.

Tentative conclusions, based on the volume of structural mate~ialrequired

.rtf ~ for the two systems, indicate that about ~-per cent less material would be

required for construction of the des ilting chamber. It is probable that the

reduced total excavation costs would also favor the use of a desilting

chamber drainage system.

13. Study of Other Separation Methods

Upon completion of the investigation of the serilimentation chamber for

storm water desilting use, it was apparent that the cost of such a structure

would be quite substantial. Although it was shown that the sedimentation

chamber has considerable economic advantage over the catch basin type system,

it was·still believed that the cost of the desilting chamber system would be higher

than necessary. In an effort to determine some other type of desilting system,

Page 44: CIVIL EN INEERING STUDIES - ideals.illinois.edu

35

a study was made of all known designs. A summary of the results of such

study is given below. It is to be noted that other desilting structures

considered fall in the fields of either sanitary engineering or irrigation

engineering.

A. Desilting Structure'S Developed in Sanitary Engineering

a. Aeration Type ~ Chamber - The principle of the aeration type

grit chamber is a relatively new concept in the design of sewage treatment

The ChicagoPwnp Company has developed a type known as the tlAer­

• A discussion of its various aspects was'presented by Kappe and

in 1951. The principle is to introduce air into the grit chamber

and the resulting actions are:

Increase settling velocity by decreasing the density of the flowing

plants.

Degritter lT

1.

liquid through the introduction of air. (Refer to Eq. A5)

2. Elimination of "short circuiting" by providing a spiral flow path

through the chamber.

3. _Creating sufficient floor velocity to remove organic particles

from the settled material.

Actions 1 and 2 are produced by introducing air weil below the water

surface and one s ide of the chamber only. The pres ence, of.. air reduces the

density of the mixing liquid and the feeding of'air on one side only creates

further the rotational motion of the flow in the tank. The rotational

motion together with the translative longitudinal flow from tank inlet to the

outlet results in the spiral flow condition. An estimate for the type of

grit chamber described by Kappe and Neighbor indicates that for a design rate

of storm water flow of 36.6 cfs. considered in this study, a tank 25 ft. long,

8 ft. wide and 4 ft. deep would be required. According to Kappe and Neighbor,

* "Some New Developments in Aeration--Par.t I, Pre-Aeration and Aerated Grit Chambers," by S. E. Kappe and J. B. Neighbor, Sewage and Industrial Wastes, Vol. 23, No.7, July 1951, pp. 833-838.

Page 45: CIVIL EN INEERING STUDIES - ideals.illinois.edu

air may be supplied at the rate of 3 cfm. per foot of the tank. The volume

of air required in this tank would be about 75 cfm. Comparing the aerated

tank dimensions with the gravity settling chamber developed previously, it is

shown that the major economy effected would be a considerable saving in

the overall volume of the structure. Offsetting the saving in the aerated

chamber construction is the air supply requirement, need for an electric

control device, and increased maintenance. Based on the cursory examination

summarized here, it is concluded that the aeration type grit chamber is not

applicable to the present des ign problem.

b. Micro-Straining -- Another method of particle removal which has been

investigated is the use of a rotating screen constructed in such a manner as

to exclude from flow those particles whose size exceeds the design limit.

Consideration of this method indicated that costs of maintenance and control

system features would render it impractical for use for the purpose under

stUdy. A very recent development in the use of this so-called micro~straining

method has appeared in the literature.* __ The structure reported is designed

for water supply treatment, but in the future some application to desilting

of storm water seems t.o be possible.

B. Desilting structures Developed in Irrigation ;Engineering -- In the .... ~

field of irrigation engineering two developments are worthy of discussion.

These were undertaken at the Bellvue Hydraulic Laboratory at ,Fort Collins,

Colorado in an extensive series of investigations over a number of years.

The purpose "Was to solve the problem of sedimentation,in irrigation canals.

Cooperating in this work have been several Federal agencies and the Experiment

Station of the Colorado Agricultural and Mechanical College. Two structures

have been developed to remove bed load from irrigation canals at or near the

* lIMicro-Straining, n by A. W. Cons oer , Engineering News -Re cor-d . 'vol. 150, No. 15, April 9, 1953, p. 36.

Page 46: CIVIL EN INEERING STUDIES - ideals.illinois.edu

37

canal headworks. The characteristics of both structures were described by

Parshall* and are summarized as follows:

a. Riffle-Vane Deflector -- This structure consists of a series of

curved sheet metal vanes attached to the bottom of an open channel. The vanes,

about 10 in. high and spaced at the same distance apart, are arranged

transversely to the direction of flow in the channel. Flowing over the vanes,

the bed load material is separated from the flow and tends to settle imme­

diately downstream from the riffle. Each vane is formed with an unsymmetrical

curve toward the downstream side at' the top of the' vane, t hus -producing local

cross flow along the downstream side of the transverse riffle. The cross flow

carries the separated bed load laterally across the channel to a point where

it may be ejected, and either wasted, or returned to the stream which supplies

water to the irrigation canal. Parshall described one series of laboratory

tests as follows:

rWhen the riffles were set in line normal to the axis of the canal, the ,bed load was moved laterally at 90o t owa J;,d "411e outlet ~n a well-defined" limited area immediately downstream from the line of riffles. The curvature of the riffle produced the effect which moved the load laterally, and the flow of water over the riffles resulted in a condition that maintained the bed load in a ridge downstream from the riffles. The action of the riffles was apparently independent of the depth of flow. Under maximum conditions of channel velocity (approximately 4 feet per second) the energy developed was sufficient to move large bobblestones, exceeding sizes which wou~d

pass through a 4-inch square opening. lI

Parshall indicated, however, that field tests of this type of structure

have not been-too successful. The vanes are particularly susceptible to

inefficiency caused by the interception of the floating debris in the approach

flow. This tends to clog the structure ,and to interfere with the bed load

* Parshall, Ra1l.ph L., TTModel and Prototype Studies of Sand Traps II J Transactions J

American Society of Civil Engineers, Vol. 117, 1952, p. 204.

Katz Ref~renoe Rac~ UniverSity of Illin n '

~*"'lo' ;L~B106 NOEL

~08 N. Romine St~~~~ Urbana t lllil1tll8

Page 47: CIVIL EN INEERING STUDIES - ideals.illinois.edu

separating function. Another disadvantage, when applying the structure to

the flow of storm water in subsurface conduits, is the problem of the disposal

of the waste water and removed sediments.

b. Vortex-Tube - Ano-ther type of structure tested at the Bellvue

Hydraulic Laboratory is known as the vortex-tube. Parshall described this

structure as follows:

"The main feature of the vortex-tube sand trap, is a tube with an opening along the top side, laid "in the bottom of the channel at an angle of about 450 to the axis of flow. The elevation of the top edge of lip is the same as the bottom or grade of the channel. As the water flows over the opening, a pronounced whirling or spiraled

;'~+"0*"c","'c""",,, ••~~~.~ motion is established within the tube; this motion extends throughout the tube length. This whirling action catches the bed load as it passes over the lip of the opening and carries the sediment to the outlet at the downstream end of the tube, where it is discharged into a suitable sluiceway-for disposal. ll

Results of the tests indicated that the optimum operation of the vortex­

occurs when the velocity of flow over the tube is near the critical

condition..: The tube was found capable of ejecting large size bed load

and in one test a 7.5 pound cobblestone was removed successfully.

Several vortex-tubes have been constructed and operated in the field. Parshall

that the vortex-tube requires that a portion of the channel flow be

in removing the trapped solids. The Bellvue tests indicated that the

of waste flow may vary between 10 to 15% of the total flow, and

a removal of 90% of the bed load may be :expected.

Both the riffle-vane deflector and the vortex-tube structures are best

suited for channels' of moderate width. The optimum velocity for the riffle

'Vane deflect.or is about 2 to 3 ft. per sec. while the vortex-tube requires a

ritical velocity for best operation. Both types of structure exhibit the

ame waste ~ater requirement Df approximately 10 to 15% of the total flow.

arshall stated that the volume of waste water required, h_owever J is dependent

Page 48: CIVIL EN INEERING STUDIES - ideals.illinois.edu

39

more on -the volume-of' material -to beremoyed than-the-totalchannel flow.

The vortex-tube method of sediment removal appears to have some

favorable possibilities. Further details in connection with the application

of this method to the topic area are given in Appendix IlIa

Page 49: CIVIL EN INEERING STUDIES - ideals.illinois.edu

40

APPENDIX I

THEORY OF GRAVITY SEPARATION

FOR GRIT CHAMBER DESIGN

The theory of gravity separation for grit chamber design is briefly

outlined here as a convenient reference. The material presented is based

on two papers py Thomas R. Camp entitleC!-, HGrit Chamber Design", Sewage

Works Journal, March 1942, pp. 368-381 and rlSedimentation and the Design

of Settling Tanks", Transactions, American Society of Civil Engineers,

Vol. 111, 1946, pp. 895-936.

When a particle is released in a still fluid it will move vertically

due to gravity if its density differs from that of the fluid. The particle

will accelerate until the frictional "drag" of the fluid approaches the

value of the impelling force, after which the vertical velocity of the

particle with respect to the fluid at rest will be substantially constant.

The terminal velocity is known as the rlsettling velocityrl of the particle

and it is of great importance in the problem of sedimentation.

The fundamental theory of gravity separation is based on the law of

drag first proposed by Newton,* which is ~ritten:

2 (Al)FD = Crffl ~

in which F = drag forceD

CD drag coefficient

A = projected area of the particle in the direction of motion

fl = mass density of fluid containing the particle

and V = relative velocity between the particle and the fluid.

* "Mathematical Principles of NaturalPhilosophylT, by Sir Isaac Newton, Vol. 2, 1910, Sections 2 and 7.

Page 50: CIVIL EN INEERING STUDIES - ideals.illinois.edu

41

The drag for a small sphere in an incompressible viscous fluid of

infinite extent was first developed by Stokes.* Completely neglecting

the inertia force, the Stokes equation is:

(A2)

in which;t = absolute viscosity of the fluid

d = diameter of the sphere

and V = relative velocity between the particle and the fluid.

Comparison ofEq. A2a,nd Eq , Al reveals that, in the region of viscous

settling, the drag coefficient is

C = 24 D R (A3)

in which R is the Reynold number, Or R =

The settling force for °a sphere due togravi:ty is ° .•. '>(0.' (A4)

F = ~Jt ~l (f~o/fyg.~.,s

in which P = density of the particle.

Equating the settling force from Eg. A4 to the drag force from Eq. Al

and substituting the value of drag coefficient from Eq. A3, the settling

velocity is found to be:

This equation may be used to determine the settling velocity of spherical

particles falling in a given liquid when the absolute viscosity of the

liqUid, the diameter of the sphere and the difference between the densities

of the particle and the liqUid are known. Experiments by numerous investigators

indicate that the data are in good agreement with Stokes l for values of R

• °varyang f rom 10-4 t 0 ba tou a 5..

* "On the Theory of the Internal Friction of Fluids in Motion, and of the Equilibrium and Mption of Elastic Solids", Transactions, Cambridge Philosophical Society, Vol. VIII, 1845, p. 287; and "Mathematical and Physical Papers", by Sir George Gabriel Stokes, Univ. Press, Cambridge, England, Vol. I, 1880, p. 75.

Page 51: CIVIL EN INEERING STUDIES - ideals.illinois.edu

42

In applying the separation theory to settling tank design, an "ideal

"basin Yt has been considered and defined by Camp as a hypothetical settling

tank in which settling takes place in exactly the same manner as in a quiescent

settling container of the same depth. Camp stated that this ideai basin with

a rectangular form and continuous flow for unhindered settling has the

following characteristics:

"l. The direction of flow is horizontal and velocity is the same in all parts of the settling zone (hence, each particle of water is assumed to remain in the settling zone for a time equal to the detention period--namely,the volume of the settling zone divided by the discharge rate);

2. The concentration of suspended particles of each size is the same at all points in the vertical cross section at the inlet end of the settling zone; and

3. A particle is removed from suspension when it reaches the bottom of the settling zone. H

For the purpose of the discussion, a grit chamber or any continuous

flow basin may be considered as composed of four functional zones. These

zones are (1) the inlet zone whose function is to present flow to the

settling zone uniformly with respect to width, depth, .and velocity; (8) the

pettli~g zone whose function is to provide conditions for optimum separation

andsettlingj (3) the storage zone whose function is to store settled

solids, without interference with the settling action, and (4) the outlet

zone whose function is the conveyance of flow to the discharge conduit with­

out undue turbulence or short circuiting in the settling zane. It is

apparent that the fundamental operation of a grit chamber is primarily

dependent upon the settling zone.' The size and construction features of the

other _zoneS2 are dependent upon size of pipe or channel entering the grit

chamber, frequency and method of accumulated grit removal, and type and size

of discharge conduit.

Page 52: CIVIL EN INEERING STUDIES - ideals.illinois.edu

The sketch in Fig. 19 shows an ideal settling zone with length L,

depth H, and width W. From the first of the three characteristics of an ideal

basin mentioned above, it is appaTent that

Vol. LWHT = = --Q-Q

in which T = detention time. (A6)

Q = rate of flow through basin.

Vol. = volume of effective settling zone.

Since the detention time is the time during which the liquid flows

through the settling zone of the grit chamber, it is seen from Fig. 21 that

under conditions of ideal settling the smallest particle which will be

separated from the flow will have a settling velocity

- HV0--T

which velocity is just enough to carry the particle from the tank surface

to the tank bottom.

Referring to Fig. 19, it is seen that the settling path of a particle

with settling velocity Yo is the vectorial sum of the velocity of horizontal

translation and the velocity of settling. If the particle is at the water

surface when entering the tank, the path of settling is A-B. If the

particle is below the water surface, at Al fer instance, the settling path

is Al - Bl, parallel to A-B, since respective values of Yo and Vh are equal

in both cases.

If, however, a particle is at the water surface on entering the tank

and the diameter of the particle is such as to cause the settling velocity

Vs to be less than the critical settling velocity Va' the particle of that

size will not reach the tank bottom in the time T, and as a result, the

particle will not be separated from the flow. This particle will be said

to TlovershootTl the tank as shown by the path A-C.

Page 53: CIVIL EN INEERING STUDIES - ideals.illinois.edu

44

Now,

is

",,,;,'jj'j,;';,,

This

for an optimum condition, the velocity should be such that the

will not overshoot the tank, or time of flow passing through the

just enough for the particle to settle. Then, substituting the

T from Eq. (A6) into Eq. (A7), the settling velocity is

(AS)Vo = -S = ~ LW A

Where A is the horizontal surface area of the tank, or

QA=­Vo

indicates that the horizontal grit chamber area is theoretically

independent of chamber depth,H~ However, the horizontal through velocity

VH is determined as:

v, = SLH WH

which indicates that small values of H will result in high through velocities.,

and conseque~tly scour may take place on the surface of the grit storage zone.

Camp suggested that Eg. 1 in Art. lIb. which is based q? the experimental

work of Shields may be used to determine the maximum allowable through

velocity. Use of Eqs. (1) and (A9), together with an assumed ratio of length

to width will allow the determination of the -dimensions of the settling zone

required to remove particles with diameter d, settling velocity Vo and

specific gravity s .

Page 54: CIVIL EN INEERING STUDIES - ideals.illinois.edu

APPENDIX II

THEORY OF SEDIMENT DISTRIBUTION

The material presented in this section of the report is not to be

considered as a treatment of all phases of -the theory of sediment-distribution.

This section of the report is intended to provide a summary of the background

information -which is available, and to indicate the feasibility of a functional

approach channel design for the combined desilting structure described in

Appendix III.

The material in the literature concerning- sediment transportation has

developed mostly with regard -to flow-- irrpipes, and particularly for flow

in dredge pipes. In most cases the dredge pipe studies attempted to ascertain

the controlling parameters applicable to friction loss or pressure=flow require~

ments. In these studies, the problem of sediment transportation and distribution

which concerns the present investigation is considered only of secondary impor~

tance.

A. Studies at Cornell University - In 1906, NoS. Blatch* described

the results of an experimental investigation made at the Hydraulic Laboratory

of Cornell UniVl;;rsity. This investigation provided information on the -laws

which govern the flow of sand and water in pipes under pressure. The results

were presented as a discussion of a paper by Hazen and -Harky.-)H(- The tests were

conducted to determine the loss of head in I-in. brass galvanized iron pipe

used to carry various degrees of concentration of 20 to 40 mesh and 60 to lOO

TlDiscussion of ~Torks for the Purification of Water at Washington, D~ C., tr* by No S. Blatch, Transactions, American Society of Civil Engineers, Vol~ 57, 1906, p. 403.

TWorks for the Purification of Water at Washington~ D. C. J fT byA~ Hazen

and E. Do. Har-ky, TTansactions" American Society of Civil Engineers, Vol. 57, 1906j} p. 3.07.

Page 55: CIVIL EN INEERING STUDIES - ideals.illinois.edu

46

having specific gravity of 2.64. It was found that two distinctive

conditions of flow occurred; one was obtained at low velocities up to about

ft. per sec., and the other at high velocities between 4 and 10 ft.

per second. Between these two conditions of flow, a transition period occurs.

This period is short if the sand is fine and uniform, and long if there is a

of grades. In direct observation of the nature of flow during these

periods, it was found that for velocities of less than about 3.5 ft. per sec.}

the greater part of the sand was dragged along the bottom of the pipe at a

very low velocity with practically clear water" flowing in the upper part of

cross-section. At a velocity of about 3.5 ft. per sec. large quantities

of sand began to be carried in suspension. It is stated that this velocity

condition marks the point of economical transport for the sand. The change

occurred suddenly for the fine grade of sand, while for the coarse grade, in

which the particles differed more in size; the change became gradual. At

high velocities, all of the sand was in suspension.

It is interesting to note that the three stages described above corre­

spond to the low-velocity flow, the transition period, and the high-velocity

flow. Apparently, the cause of the very high loss of head at low veloc-ities

was due to the dragging of sand along the bottom of the pipe and to the small

cross section available for the flow of the water. The gradual decrease in

the loss of head in the transition period was due to the gradual suspension

of the sand. At high velocities the loss of head due to the presence of sand

was small because all of the sand was in."~.E?uBJ?ension.

Results from tests using I-in. pipe were compar-ed with those obtained

from similar dredge tests using 32 ... in. pipe lines. In the dredge experiments,

when the velocity was allowed to rl-r-op slightlY,below 9 ft. per sec.) the cross­

section became clogged due to the settling out of the sand in the lo-werpart

of the pipe. The -economf.ca.L velocity in the 32-in. pipe was concluded to be

Page 56: CIVIL EN INEERING STUDIES - ideals.illinois.edu

46

mesh sands having specific gravity of 2.64. It was found that two distinctive

conditions of flow occurred; one was obtained at low velocities up to about

2-1/2 to 4 ft. per sec., and the other at high velocities between 4 and 10 ft.

per second. Between these two conditions of flow, a transition period occurs.

This period is short if the sand is fine and uniform, and long if there is a

mixture of grades. In direct observation of the nature of flow during these

periods 7 it was found that for velocities of less than about 3.5 ft. per sec.,

the greater part of the sand was dragged along the bottom of the pipe at a

very low velocity with practically clear water flowing in the upper part of

'~~t1:iec;ross-section. At a velocity of about 3.5 ft. per sec. large quantities

of sand began to be carried in suspension. It is stat:ed that this velocity

condition marks the point of economical transport for the sand. The change

occurred suddenly for the fine grade of sand, while for the coarse grade, 'in

which the particles differed more in size, the change became gradual. At

high velocities, all of the sand was in suspension.

It is interesting to note that the three stages described above corre­

spond to the low-velocity flow, the transition period, and the high-velocity

flow. Apparently, the cause of the very high lOBS of head at low velocities

was due to the dr.agging of sand along the bottom of the pipe and to the small

cross section available for the flow of the water. The gradual decrease in

the loss of head in the transition period was due to the gradual suspension

of the sand. At high velocities the loss of head due to the presence of sand

'was small because all.of the sand was in-::$uapension.

Results from tests using I-in. pipe were compar-ed with those obtained

from similar dredge tests using 32~in. pipe lines. In the dredge experiments,

when the velocity was allowed to drop slightly below 9 ft. per s ec . , the cross­

section became clogged due to the settling out of the sand in the lower part

of the pipe. The -economi.caL veloeity in the 32-in. pipe was concluded to be

Page 57: CIVIL EN INEERING STUDIES - ideals.illinois.edu

Th-e results of t'ests were summarized as follows:

Diameter in 'inche.s'

Velocity in ft/sec at which flow is often blocked.

Minimum velocity for steady flow. or economical velocity, ft/sec.

Velocity at .which·,all sand* is susp.ended ft/sec.

1 1-1/4 3-1 / 2 8 to 9

3 2-1/2 4

32 6 or 7 9 14

20 to 40mesh.s,and

-It was concluded that:

As the size of the pipe inc!~~sed; the velocity required to put

all material in suspension also increased.

(2) The ~elocity of flow required to suspend all 20-40 mesh sand

material in a 32-in .. pipe line was over 9 ft. per sec.

B. Studies at University of California -- In 1937, Of'Brien and Folsom*

published a report of their research at University of California concerning

the transportation of sand in pipes. They included; in .a-ddition toa

dLscus s Lon of the general theory involved, information about friction Loas e.s ,

minimum. permissible velocities; and economic operating conditions for dredge

pipe lines. It was concluded that two minimum velocities were of importance

in the flow of sand-wat.er mi.xtur-es . Thes e are: (1) the "cr f tical1l velocity

at which the head 10s.8 y in feet, for the mixture begins to differappre'ciably

from the head loss for clear water in the same pip.e,and (2) the1(elocity at

which "p.lugg.l.ng" occurs J which is also referred to ,as the velo-city of impending

clogging. The critical velocity is believed to be the velocity below which

* HThe 'Pranapor-ta'tLon of Band in Pipe Lf.nes , tr by M. P. O'Brien and R. G.. Folsom~ University of California" Publication in Engineering, Vol. 3, No·7, 1937, pp. 343-384.

Page 58: CIVIL EN INEERING STUDIES - ideals.illinois.edu

48

a part of the material is transported by rolling along the bottom of the I

pipe. As the velocity is decreased below the critical, more and- more of the

pipe area is obstructed by rolling sand until conditions are reached at which

the pipe clogs. QTBrien and Folsom determined that the velocity of impending

clogging could be expressed as a function of median sand diameter and sand

concentration. However, they indicated that the minimum velocity nece~sary

to keep all of given material in suspension would not produce a uniform

distribution in the pipe. At low velocities, part of the material rolls along

the bottom of the pipe. As the velocity is further decreased, there is a

deposit formed on the bottom, the surface layers of which deposit, however,

are still in motion. They suggested that the deposit reduces the effective

area of the pipe in such a way that the actual velocity probably does not

decrease below a certain minimum value, whereas the apparent velocity based

on the whole pipe area may be greatly decreased.

c. Studies at U. S. Waterways EKperiment Station - 1936, Howard*

made an investigation at the U.S. Waterways Experiment Station in connection­

with a series of tests on 4-in. pipe, transP9rting water mixed with sand and

gravel. In Howard's paper, an attempt was made to prove that the type of

material to be tran_~orted and the experience of the designer should have

more bearing on the solution of a problem than any solid-transportation

formula then extant.

Regarding the method of transporting the sand, Howard stated:

"Thr-ee distinct types of transportation were found for sand and water mixture in pipes. The first of these was at low-veLl.:ocities, where practically all material was on the bottom of the pipe. A layer of sand was built up and the material rolled over this bed in much the same manner as an open flume. The second type of movement was one in which the sand layer that was built up at low velocities would move forward slightly and then halt, while other material would still move freely over the bed. This spasmodic movement can be termed most correctly, T1jerking,1I be.cause the material along the bottom moved freely one instant and was quiet the next. The third type

"I'rarispor-t.at.Lon of Sand and Gravel in a Four-Inch Pipe, II by G. W. Howard, Transactions, American Society of Civil Engineers, Vol. lo4, 1939, pp. 1334­1348

Page 59: CIVIL EN INEERING STUDIES - ideals.illinois.edu

was one in which the material was moving over the entire cross-sectional area, although the greater percentage was concentrated in the lower part of the pipe.1!

For the 4-in. pipe used in the tests, the type of movement in which the

material is on the bottom of the pipe occurred for velocities less than 6.0

ft. per sec. The fTjerking" movement occurred for velocities from 6.0 ft. to

7.5 ft. per sec. The suspended motion occurred for velocities greater than

7.5 ft. per sec. At velocities where the material is settled or concentrated

near the bottom, there isa greater head loss per.foot of pipe than for

slightly higher velocities, because of the constriction of the flow area. The

minimum head loss was obtained in the Yelocity range in which the jerking

motion.occurred ..

In the case of dredge lines, when the velocity drops to about 14 or 15 ft.

per sec. ina 32-in. line, or to 9 or 10 ft. per sec. in a 20-in. line, the

sand will settle on the bottom of the pipe. In the cases of dredge operation,

the largest quantity of material is transported in the lower third,of a pipe

rather than along the bottom. It was concluded that all of Howard IS results

were quantitative for a 4-in. line and were only qualitative for lines of other

sizes. He indicated that the results should not be applied to a line of J..a:cger

diameter "except in a qualitative way. a:

In a dis cuss ion of Howard fa paper, E. ~. Dent* pointed out that in

practical dredging operations the muds and silts are well distributed throughout

the entire cross-section of a pipe line, whereas the sands and gravels cone-en­

trate near the bottom.

In his closing discussion, Howard includes some diagrams shOWing the

distribution of solids in 4-in., 20-in., and 32-in. pipes at various velocities

* "Df.s cuas Lon on Transportation of Sand and Gravel ;" by Elliott J. Dent, Transactions, American Socie~y of Civil Engineers, Vol. 104, 1939, p.1355.

Page 60: CIVIL EN INEERING STUDIES - ideals.illinois.edu

50

of flow. In each case, .even ·though the velocity is sufficiently high so that

all of the material is in suspension, at least 60 and often 70 per cent of the

solids are located in the lower 25% of the pipe.

D. Studies at the University of Iowa - An instance of purely basic research

regarding the problem is the work performed by Craven* at the University of

Iowa. Craven restricted his studies to pipes flOWing full and did not consider

the situation of pipes flowing partly full. The general case of the pipe

. . tlA.UflOWing partiallYl\.was later presented by Ambrose** of the University of

Tennessee. On the basis of ,an analysis of previous investigations and of the

mechanics of movement, he found the theoretical primary parameters which control

the hydraulic gradient and the geometr'yofthedeposited sediments. Craven

attempted to set up an experimental program that would completely determine

the effect ()f'thepa:ra!Il~:~er~>upOIlWPJ>CP.:'Ct:;p.~P:tg.te}:q,icgrad:ient~aspresumed

to depend. The only variables which Gould be independently controlled over a

continuous range of values were: the volume rate of fluid flow Q, the absolute

volume rate of sand flow Qs, and the hydraulic gradient S, therefore, only the

dimensionless parameters Q and S could be varied over a complete range of

values. The experiments on the transportation of sand in pipes indicates that

the transport phenomenon may be divided into three regions: a region in which

the piezometric gradient is governed by the·transport discharge ratio, ~s; a

transition region; and a region in which the piezometric gradient is independent

Of.~s and dependent upon the properties of the flow, the roughness character­

istics of the boundary, and the critical shear of the sand. For all practical

purposes, the first region coincides with the situation in which the sand is

* tlA StUdy of the Transportation of Sand in Pipes") by J. P. Craven, Doctoral Dissertation, University of Iowa, 1951; also liThe Transportation of Sand in Pipes, I.' Full-Pipe Flow tf ,by J. P. Craven, Proceedings of the Fifth Hydraulics Conference, June 9-11, 1952; State University of Iowa, Studies in Engineering, Bulletin 34, No. 426; 1953J pp. 67-76.

** liThe Transportation of Sand in Pipes, II. Free -Surface Flow 11) by H. H. Ambrose, Proceedings of the Fifth Hydraul:i,qsConference, June 9-11,1952, State University of Iowa, Studies in Engineering,Bulletin 34, No. 426, 1953, pp. 77-88.

Page 61: CIVIL EN INEERING STUDIES - ideals.illinois.edu

51

all located on the bottom of the channel and. is carried as bed load. The

third region coincided with the situation in which all of the sand is carried

in suspension and is distributed throughout the channel section, even though

the greater part of it may be in the lower portions of the pipe.

Summarizing the above studies, it can be shown that all investigators

found that the capacity for transportation of sediments can be divided into

three areas. The first is the case of bed movement, which exists at velocities

less than "crLtical rt, (not to be confused with Vc ~ Jgdc)" The second case

of transportation capacity exists when the velocity is sufficiently greater

t.han v'cz-Lt.Lca.L" so that all the solid material is in suspension, and the third.

condition of transportation capacity exists as a transition between the two

foregoing characteristic types of action.

It may be concluded that considering pipes flowing full and with velocities

less than the "crIt.Lca.l tr (about 7 or 8 ft. per sec.), sand and similar detritus

will be located on the bottom or near the bottom of the flow conduit. This

conclusion indicates that there is an excellent possibility that sediment

distribution in the approach channel to the vortex-tube (see Appendix III)

will be conducive to the desilting system operation.

It should be noted that a partial investigation of the various· phases of

the transportation of sediments in open channels was made in connection with

this study. The extensive nature of this problem together with the question­

able applicability to the current study indicates that this material should

not be considered as a main part of this report and hence is supplemented here

as an appendix for the sake of reference. In case the study and design of

the proposed desilting structure requires the consideration of a substantial

bed load formation on the floor of the approach channel owing to the possi­

bility of the existence of such formation, further studies on theories

Page 62: CIVIL EN INEERING STUDIES - ideals.illinois.edu

52

developed by Dobbins, Einstein, Gilbert, Nemenyf, , Rouse and Vanoni* 'Will be

very considerable importance.

llEffect of Turbulence onSedimentation ft , byW.E . Dobbins, Transactions,

American Society of Civil EngineerS 7 Vol. 109,_1944, p. 629.

1tThe Bed-Load Function fo~ Sediment Transportation in Open Channel Flo-w lT

by H. A. Einstein, U. S. Department of Argiculture, Technical Bulletin No. 1026, September 1950.

tlTransportation of Debris by Running Water, It by G.C. Gilbert, U.S. Geological Survey, Professional Paper 86, 1914.

TIThe Different Approaches to the Study of Propuls ion of Granular Materials and the Value of their Coordination", by P. Nemenyi, 'I'ransactdons , American Geophysical-'Union, ~ 1940 j Pt. II, p. 633.

YfModern Conceptions of the Mechanics of Fluid Turbulence", Transactions, American Society of Civil Engineers, by Hunter Rouse, Vo.L; 102, 19377 p. 463·

tiSome Experiments on the Transportation of Suspended Load,H Transactions, American Geophysical Union, 1941, p. 608, and I1Transportation of Suspended Sediment by Water fl, by V.A. Vanont , Transactions, American Society of Civil Engineers, Vol. Ill, 1946, p. 67.

Yetz; Referenoe R'0o-~ University of Il1ino1~

BI06 ~TCEL

~08 N. Romine Street JJrbana l' III i j:J (J:t g

Page 63: CIVIL EN INEERING STUDIES - ideals.illinois.edu

53

APPENDIX III

EVOLUTION OF A POSSIBLE KINETIC-SEDIMENTATION

TYPE DESILTING STRUCTUP~

Considerations presented earlier in this report indicate that the cost

desilt the storm water flow developed from the topic area by sedimentation

chambers is higher than should he expected. Later studies indicate that a

"',',i"'''"'''''''"", vortex-tube method of removing bed load might be an acceptable procedure ~ if

waste water requirement would not exist. ,Further study on this matter

-

has resulted in a possible combined type of structure which takes the

advantage of the desirable features of both·types of structures and eliminates

the undesirable features.

Reference to Fig. 22 shows that the size of the sedimentation chamber,

and hence the cost, is proportional to the rated-f flow through the chamber.

If some method could be .developed for cencentinatdng. the sediments of inflow

in a smaller flow rate, the construction cost of the sedimentation chamber

would be substantially reduced. The study of the vortex.;;tube indicates

the possibIlity of such sediment ccmcentration. It is believed that with

proper irmta.JJ..ation, the vortex-tube1ITBiY be us-ednot only to concentrate

the flow sediments, but also to separate, by kinetic means, that portion of

flow whf.ch requires treatment from the total flow. This concept was applied

to the topic area problem to develop a possible kinetic~sedimentationtype

structure which is descrihed in the following articles.

A. The Proposed System

The tentative design of the kinetic-sedimentation type structure is

shown. by a schematic drawing in Fig. 20, in which the junction chamber is

Page 64: CIVIL EN INEERING STUDIES - ideals.illinois.edu

54

<:~ U§):;i;,," identical in function with the junction chamber shown in Fig. 4. The function

of the different parts of the proposed structure may be studied by tracing

the path of flow through the structure. First the surface runoff from the

topic area is conducted through sewers to the junction box. The junction box

combines the flows from the north and south portions of the roadway and intro­

duces the resulting flow to the approach channel of the desilting structure.

The entrance to the approach channel should include a suitable transition

so as to cause smooth flow conditions to develop in the channel as soon as

possible. The function of the approach channel is to allow sufficient time

,,····,forthe equilibrium condition of sediment dLst r-Lbut.Ion to prevail. This

will cause the major concentration of the entrained sediments to be collected

on or near the bottom of the channel. After the optimum condition of sedi­

ment distribution is established j the flow passes over the vortex-tube. The

action of the vortex-tube is to separate the bed-load, and major portion of

the saltation load, from the total flow. Effluent from the vortex-tube is

passed to the sedimentation chamber, where final separation of the entrained

sediments is accomplished by gravity separation. The effluent fr0m the sedi­

mentation chamber, together with the flow in the approach channel which has

passed over the vortex-tube, is conducted to the main intercepting sewer

through a drop manhole.

B. Critical Design Elements

A study of the various functions of the entire desilting structure

results in the following critical design elements.

a. The Approach Channel -- The major function of this channel is to

allow concentration of sediments nearvthe bottom of the channel. This

action happens most favorably under conditions of low translative'velocities

Page 65: CIVIL EN INEERING STUDIES - ideals.illinois.edu

55

and shallow depths. It is also the function of the approach channel to

supply the flow to the vortex-tube in such manner that the tube may operate

with the maximum efficiency. Parshall has stated that the vortex-tube

operates most satisfactorily under conditions of near critical depth.

However, it is noted that this condition is not advantageous when the sediment

concentration function is considered. Figure 21 shows the design curve for

the various combinations of approach channel dimensions considering the

topic _area flow ra~e and critical depth.

o. The Vortex-Tube -- The action of the vortex-tube in separating

c"~ ··entrained aediraerrt load from the total channel flow can .only be discussed in

a general manner~ because informatlion~inliteratureregarding the precise

action of the tUbe, size of the tube required and exact percentage of the

total flow intercepted by the tube is not available. The head discharge

rela~ionships for vortex-tubes of different sizes under various flow rates

are also unknown. However, Parshall did mention that the vortex-tube

efficiency in moving bed load should be approximately 90%, and that the

use of water by the tube is between 10 and 15% of the total flow. For

tentative consideration) a water use factor of 20% may be assumed. Owing

to the lack of design inf.ormation,e.ven a tentative selection of the tube

size would be very difficult.

c. The Sedimentation Chamber The sedimentation chamber shown as a

part of the proposed scheme in Fig. 20 represents a tentative design which

is based upon data des cribed earlier in this report. Assuming a water use

'factor of 20% for the satisfactory operation of the vortex-tubB, the rate

of flow passing through the sedimentation chamber is found to be 36.6 x

20% = 7.3 cfs. Considering a length-wid.th ratio of N = 2, the design

Page 66: CIVIL EN INEERING STUDIES - ideals.illinois.edu

56

curve in Fig. 18 shows that a theoretical chamber required is about 5 ft~

wide and 10 ft. long. With.a maximum allowable through velocity of 0.964 ft.

per sec., the effective depth of the chamber is about 1.5 ft. Adding 2 ft.

to the depth for sediment storage, the total depth becomes 3.5 ft. Assuming

a length of 2 ft. for the entrance channel and wall thickness of 6 in., the

overall length is 13.5 ft. The overall tentative dimensions of the sedi­

mentation chamber with slab thickness of 6 in. are 6 ft. wide, 13.5 ft. long

and 4.0 ft. deep.

From the preceding discussion it is realized that the practical feasi ....

bilityof the combined system is dependent upon two particular qualifications

as follow:

1) The favorable sediment distribution in the approach channel.

2) The ability of the vortex-tube to intercept all of the sediment

particles witA size equal to or gre~ter than the design minimum value.

A'r,eview of various phases of the sediment distribution problem is given

in Appendix II for further study and reference.

c. Proposed Laboratory Investigation

It is believed that the combination of vortex-tube and sedimentation

chamber isa feasible type of system. Based upon theoretical considerations

and information in literature there appears to be great possibility that a

vortex-tube type structure can be applied satisfactorily to treat storm

sewer flows.

It has been indicated that the successful operation of the vortex-tube

is -primarily dependent upon the di.stributIhon :ofs-ediments in the approach

channel. It follows that laboratory activity should fir.st be directed toward

the compilation and investigation of all existing information and pertinent

data concerning sediment distribution in pipes and channels , where the bed

load 'movement does not occur. The study should be supplemented, if possible,

Page 67: CIVIL EN INEERING STUDIES - ideals.illinois.edu

57

with the determination of sediment distribution and concentration data from

existing Hewers.

As the vortex-tube was d€veloped primarily for the removal of bed load,

it is proposed that laboratory tests of the structure be conducted to

determine the design and efficiency of the tube when operating for the removal

of saltation load, or when, as in the present problem, the ¢ajor portion of

the solid material presented to the structure is in suspension.

In case the laboratory tests indicate that the vortex-tube will operate

properly only for-the-removal of-hed---load, but not satisfactorily for load

suspension, and that the development of a suitable structure for the removal

of both types of load is not probable, it is suggested that further studies

on sediment distribution be made. The purpose of" thes8'- stud-iea should be to

determine whether it is possible or not to Gonvert the load in sl1spension to

the bed load by altering'the hydraulic features of the structure, such as

by varying the' cpt.rmunr slope of' the approach channel, etc.

Upon completion of:v-:arious phases of the study mentioned above, it is

propos-ed that tests of largescale'm:odelofvarious components of the combined

desilting structure be conducted to determine their best designs. This

investigation should result in a series of design criteria and standards

, which -w'ould make possible a rather comprehensive preliminary pr-otot.ype design.

After prototype design criteria and standards are developed, it would

become po-ssible to cooperate with the design engineers of the Illinois

Division of Highways to develop'an inital prototype design for a particular

site. -, Upon compLet Lon of this final design, either a full scale, or a near

full scale, model should be built and tested throughout the design range of

discharge, particle size, and inflow sediment concentration.

Page 68: CIVIL EN INEERING STUDIES - ideals.illinois.edu

58

It would be most desirable, if not essential, to construct in the field,

a prototype structure with proper instrumentation to verify and extend the

model testing data. Such a structure should be placed under continuous

observation in order that long term operating characteristics and. maintenance

costs might be- obtained. Only after the structure has been in operation for

several years may final evaluation of all of the aspects of the structure be

made possible.

Washington, D. C. rr 'I'ranaact.rons , lUllta".LI.,;o,ll UVI..,..t." V,J V.I. v ..... v ...................0 ...." ................. .., Y

Vol. 57, 1906, p. 403.

Thomas R., "Gri.t Chamber Design, II Sewage Works Journal, March 1942, pp. 368-381.

amp} Thomas R., IISedimentation and the Design of Settling Tanks,H Transactions American Society of Civil Engineers, Vol. III, 1946, pp. 895-936.

how, Ven Te, flFrequency Analysis of Hydrologic Data with Special Application to Rainfall Intensities,1l University of Illinois Engineering Experiment Station, Bulletin Series No. 414, July 1953, 80 pp.

oer, A. W., ITMicro-Straining,II Engineering News-Record, Vol. 150, No. 15, 9, 1953, p. 36.

J. P., tlA StUdy of the Transportation of Sand in Pipes, tl Doctoral Dissertation, University of Iowa, 1951.

raven, J. P., ftThe Transportation of Sand in Pipes, I. Full-Pipe Flow,1l Proceedings of the Fifth Hydraulics Conference, June 9-11, 1952, State University of Iowa, Studies in Engineering, Bulletin 34, No. 426, 1953, pp. 67-76.

~nt, Elliott J., HDiscussion on Transportation of Sand and Gravel,!! Transactions, American Society of Civil Engineers, Vol. 104, 1939, p. 1355.

obb Lns , W. E., "Effect of Turbulence on Sedimentation, II Transactions, American Society of Civil Engineers, Vol. 109, 1944, p. 629.

[Lns t e i.n , H. A., tIThe Bed-Load Function for Sediment Transportation in Open Channel Flow,1I U. S. Department of Agriculture, Technical Bulletin No. 1026, September 1950.

~ilbert, G. C., "Transportation of Debris by Running Water, II U. S. Geological Survey, Progressional Paper 86, 1914.

lazen, A. and Harky, E. D., "Works for the P~rification of Water at Washington, D. C. l

lI Transactions, American Society of Civil Engineers, Vol. 57, 1906, p. 307·

Page 69: CIVIL EN INEERING STUDIES - ideals.illinois.edu

60

APPENDIX IV

BIBLIOGRAPHY

Ambrose, H. H., ITThe Transportation of Sand in Pipes, II. Free-Surface Flow,ff Proceedings of the Fifth Hydraulics Conference, June 9-11, 1952, State University of Iowa, Studies in Engineering, Bulletin 34, No. 426, 1953, pp. 77-88.

Babbitt, H. E .. , "Sewerage and Sewage 'I'r'ea'trnerrt j " 6th Ed., p. 366.

Blatch, N.. S., "Discussion of Works for the Purification of Water at Washington, D. C.r! Transactions, American Society of Civil Engineers, Vol. 57, 1906, p. 403.

Camp, Thomas R., r!Grit Chamber Design,ll Sewage Works Journal, March 1942, pp. 368-381.

Camp, Thomas R., "Beddmerrtat.Lon and the Design of Settling Tanks," Transactions American Society of Civil Engineers, Vol. III, 1946,pp. 895-936.

Chow, Ven Te, f1Frequency Analysis of Hydrologic Data with Special Application to Rainfall Intensities,1T University of Illinois Engineering Experiment Station, Bulletin Series No. 414, July 1953, 80 pp.

Consoer, A. W., ITMicro-Straining," Engineering News-Record, Vol. 150, No. 15, April 9, 1953, p. 36.

Craven, J. P., tlA Study of the Transportation of Sand in Pipes, Tl Doctoral Dissertation, University of Iowa, 1951 ..

Craven, J. P.) ITThe Transportation of Sand in Pipes, I. Full-Pipe Flow,1l Proceedings of the Fifth Hydraulics Conference, June 9-11, 1952, State University of Iowa, Studies in Engineering, Bulletin 34, No. 426, 1953, pp .. 67-76.

Dent, Elliott J., "Discussion on Transportation of Sand and Gravel)" Transactions, American Society of Civil Engineers, Vol. 104, 1939, p. 1355.

Dobbins, W. E", "Effect of Turbulence on Sedimentation, IT Transactions, American Society of Civil Engineers, Vol. 109, 1944, p. 629.

Einstein, H. A., tiThe Bed-Load Function for Sediment Transportation in Open Channel FlOW," U. S.. Department of Agriculture, Technical Bulletin No. 1026, September 1950.

Gilbert, G. C., "Transportation of Debris by Running Water,1T U. S. Geological Survey, Progressional Paper 86, 1914.'

Hazen, A. and Harky" E. D., "Works for the Purification of Water at Washington, D. C.,tI Transactions, American Society of Civil Engineers, Vol. 57, 1906, p. 307·

Page 70: CIVIL EN INEERING STUDIES - ideals.illinois.edu

61

Howard" G. W., ftTransport.ation of Sand .and Gravel in a Four-Inch Pipe,tI Transactions" American Society of Civil Engineers, Vol. 104" 1939, pp. 1334­IJ48.

Kappe, S. E. and J. B. Neighbor" IlSome New Developments in Aeration - Part I, Pre-Aeration and Aerated Grit Chambers ll , Sewage and Industrial Wastes~

Vol. 23, No.7, July 1951; pp. 833-838.

Kivell, W. A., and N. B. Lund, IfGrit Removal", Water Works and Sewerage, pt. II, \Tu~·.L'. QQ. 1\T" c::. -Iune 19}'l 1 Jrl.lT\v uu, HU. Vj .u,l..L -r J .1:" .....-r I.

Nemenyi, p., liThe Different Approaches to the StUdy of Propulsion of Granular Materials and the Value of their Coordination, II Transactions, American Geophysical Union, Ft. II, 1940, p. 633.

Newton;- Sir Issac, fTMathematical Principles of Natural Philosophyff, Vol. 2, 1910, Sections 2 and 7.

OVBrien, M" P. and R. G. Folsom, fTThe Transportation of Sand in Pipe Lines,Yl University of Californiaj Publication in Engineering, Vol. 3, No·7, 1937, pp. 343 ....384.

Parshall, Ralph L. ,'IModel and Prototype Studies of Sand Traps) " Transactions, American Society of Civil Engineers) Vol. 117, 1952, p. 204.

Rouse, Hunter, "Modern Conceptions of the Mechanics of Fluid Turbulence,fl Transactions, American Society of' Civil Engineers, Vol. 102, 1937, p. 463.

Rubey, W. W., "Settling Velocities of Gravel, Sand and Silt, H American Journal of' Science, Vol. 25, 1935, pp. 325-328.

Stokes, George Gabriel} HOn the Theory of the Internal.Friction of' Fluids in Motion, and of the EqUilibrium and Motion of'-Elastic Solids, II Transactions, Cambridge Philosophical Society, Vol. VIII, 1845, p. 287.

Stokes, George Gabriel, fTMathematical and Physical Papers,1I University Press, Cambridge, England, Vol. I, 1880, p. 75.

U. So Soil Conservation" Service, Sedimentation Division" "An Analysis of Sediment Transportation in the- Light of Fluid Turbulence;" Technical Publication 25, July 1939)1 35 pp.

Vanoni, V. A., lfSome Experiments on the Transportation of Suspended Load ;." Transactions, American Geophysical Union, 1941, p. 608.

Vanond, V. A." "I'ranspor-tat.Lon of Suspended Sediment by Water" II Transactions} American Society of Civil Engineers, Vol. III; 1946) p. 67.

Page 71: CIVIL EN INEERING STUDIES - ideals.illinois.edu

--

L.VANBUREHS!REET­ t .. CAT'" SASm -- "15TI"G D'!S"," ,.€I 9 TOE-OF-"-""" ~ """ '"!.!T SO, dir~ ~ i FIGURE I - ROADWAY PlAN AND PROFILE OF TOPIC AREA N

. t @ U OPEN DITCH CATCH BAStN- EXISTING DESIGN - DIRECTlON OF SURFACE FLOW ! g~ i BASED ON QR.4WIHG NOS. cPlaoe AM) CP 1"4 OF THE em Dl"Cl11CAGO \

~lZ: -t ill Tot·OF-SLOPE CArCH 9ASIH- REQUIREDD£SlGN - OIRS:T10H OF stB-SURFI\CE FLOW ~ U i DEPARTMENT OF SU8WATS AND SUPERHIGHWAYS

'"'i:... ~ SUB-AREA A @ STANDARD AND DROP MAN HOLts ! !l' I I

660' 660'

If---f-so' I "0' I 13S' --=---t""'1 IS'" I Is"'I~" r

IIi

"s' I IS'" ,l:fI 130' I ISO' I·d -I SUB- fA B C !"~

; SUB-AREAC /' ~Ls-CDLLECTIHG »: ~ l :': ..... .....w

+---1-- - ! - "- - 1: ..".. ---.........----. ------- -~-t----d.!!!<:!!:Q.s•.Q ~---~/ -- ~ -- / - - ,SU8~AREA 0 ~ CHAIN INl'£RCEPTING SEWER II I ~ ~ l - ~

.1 I 7Mk. ~ ~- -- ­r ~ sue-rREA E ¥R0A0S10E c.a. DPEHDITCH ;TCH8ASIHl~..-=-===---=s;;;.=='..=="===='==-~~~~~~~~~EWiR __ ~ -===-.==--=;;;:::-.=:.===­t iI RAIL.ROAO< ! ~~++~~: t + :::::; .... , ..__.... - .- _....

.~ 'CAL!1 '''I-"l0'

I------r ,-GRAOE Of' VAN BUREN ''THEET ~CROg5-OV~R

BRIOG!i-'+10

i 1% GIl")!!''''-G.'''' GRADE OF EXPRESSWAY"") m I fft0 ttl D-U ill l.(j m

CO unL. ttl PROFILE

HOv:rlT~~~~t. ';~~~~ II l~tk);~S!.'O"-10 ~ SOl'"FIT OF YAIN INTERCEPTINg SEWER I

SEWER Sl~E' '.O?O~ ....-. ' ..... .... ....... .' .................. .. , .. "-.,

i

+10

0

-10

- i

Page 72: CIVIL EN INEERING STUDIES - ideals.illinois.edu

~ t OF MEDIAN STRIP

B

I. 601- 0"

SUB- A RE A E

391"911 [

S-9u..4-I~-51 .,,1.I

---

I

241

SUB-AREA 0 24

1 . ± 12

1

SUB-ARE. C ~ISue-AREA SUB-AREA -A

MOUNTABLE PAVEMENT-EDGE GUTTER TO BACK OF

ACCESS ROAD

~~~~~JW

-INTERCEPTING SEWER

DROP MANHOLE '

FIGURE 2 - ELEMENTS OF NORTH HALF TVPICAL ROADWAY CROSS­SECT ION OF THE TOPIC AR E A -

LOOKING WEST

SCALE; I/n6 II ::18

~~~ ..........wema::w e=' W3!R'~"'f!t'!!U!l'~rn:mm?Ti1IMiM'1'P'ffl"S"!'3"7"'W5"G""1?'3:nmr:mn "'55m 'ee:=E '

Page 73: CIVIL EN INEERING STUDIES - ideals.illinois.edu

20 2.5 3.0

SUPPLY::: 7.3 LBS. PER MIN.

0- TEST DATA

0

~ .f')- I """"

0.3 0.4 05 0.6

Q - PROTOTYPE DISCHARGE - CFS

0.5 1,0 15

RATE OF SAND

x 50 u t ­c4: u

40 z

f] 30 z Ci .... ~ 20

o z ~ /0 ~ c

o 0.1 02

Q-MODEL DISCHARGE - CFS

FIGURE 3 -- TRAPPING EFFICIENCY OF CATCH BASIN

Page 74: CIVIL EN INEERING STUDIES - ideals.illinois.edu

- - - - --

- -

-

j~

f~ 'til-AREA A

!H60' I 150'

" - R

{ 'UOo~REA C

T SUe.AreA 0

r I Sua·AREA E

1 1_­

+10

0

-10

I

_. .­- -Le. VAN BUREN STREET

LEGEND I I.~ FlGURE< - APPLICATION OFTHE INLET BOX-OE5ILTING CHAM"" DES.N 1U TI£ TCRC AR8> =cm::c: INlE 'r BOX - EXISTING DESIGN :. ! BASED ON DRAWING HOS. CP race AND r.p 1194 OF THE CITY Of" CHICAGO :=:EEiI::" IHLE:l' BOX - REQUIRED DE:SIGN g i DEPARTMENT OF SUBWAYS AND SUPERHIG" WAYS

_ DIRECTiON Of SVflf'ACE f\.OW

_ DIRECTION OF sue·:SUftFACE FLo« r 660'680'

ISO'180' 15'1 ..~

135'I ISO' 1I -----j t5 r---- !"'r---= I I135' I~O'

."a" " . :1:

(tPR~PO~. ----' II II

------ - ---- . ---- ­(M"JIlI INTERCEPTING SEWER !~L ~ JUHCT~~ , ~;=== ==- -===..~.= ~'= -= ==== -="' = CHAMBER 0 - .. DESILTlttli CHAMBtR.=:=:::~ =-=---===-~-==---=:J

M!!IA~ STRIP

~-c" 0' -- ------- - -

SCALE: 1"'40'

,.IJRAD'£ OF YANBiJREN 9TR£ET

/1M'ViAWlh*MlwW;U::;;:/ I..--CAOSS.. OYER _ BRIOOE

1111 I:RAn£GRAO~ OF EXPRESSWAY71% GRADE

U::'~"""ON CHA..... PROFILE AHO

vtRTl~I"'IO' QE3lLTINOiC"1AldOER

f"lH:~~~:NSE\IIER HooaONTA\.. scM,,£1 1"~4Qt

SEWER SLOPE '''o~ ., . . ... " .. ''', '0 . ..... ..I. ... "" . .. ' . ' " " ,,- .. " .. . . " ' ......, .. ""

N

1 I <0' _!

.----­

-- ----l +10

0

-10

,.~

Page 75: CIVIL EN INEERING STUDIES - ideals.illinois.edu

i'C'"

--,--­~ ~ ~ .; a ~ 0 ~ b ~

"'uu AUSTIN CHICAla CITY OAT"" ~;--

,.~

--_./--- ­ ~~~I~ ei-ee --~--- .... ~ ,~-- -

~ ,~no

11___ -­

~

-T~7#~ ~,_.. ---.­ ----'- I­

~ ee eec --­ ._----­ . f-~ 7 -­ ~ ~

fj~r--q I.n... ~

~.no lll/ilIIIll1l.

I ~ II ~ ---,:11 17. --~-~--

'.O-tOO boWl -~ i ~i 7~

,--:.:.­ ,­

~ / f

~ ~//

I,oo.on ~I ~

J-=nw'­~ '/L~- . t:»

"0"00

~ ~ I,/~ e~ ~ 12D-rOO

~d lll. c

r f l'ii 1)0+00 I

.f.IIl...Y!II.. I ~ I !: I

S 140;. DO "

I ,

"., """"""",,:r "'-YO. I{ ~

I ~1lS0-tOO Olt+'fR

~ U !----­1701'00

Ir~ ---,­ -

j C-­

~

1&0+00

..n;~~· ~ I /I);c ,.1))/, ~.. 'I ,j));I, "-,,

~ i I J ~ !too ..oo If'....

I \ I~

~ I! UI

110 ....00 I

~ I ! I i ;n 0

UOtOO ~

I II ~ \:Hl

~ ~ :i I!lO'tOO mITt

I 'l'- I

~ ~~ ~ ~ I -c Z

t4HOQ l'i£ ~ I:;: "'-Uill!L I I o -l

;;:: ~

2.50;.00 ~ I I ~~

I.llilr.L I /1 :2: z ~ Gl

l eee-ce f:li!l ~ I I a~ ;;

I -.

I.~n ~ I~ I~ ~-

I 0 -l -l

I,,,,.no 0 .... I ~iJi

IJt- I Ii s ~ I I ~ s

1.00 'tOO n £T1~

I 01'"

!>liUl<L ~ en aoc eeo -- II~ ;j

I I

ITt -l

11r~ ,,0

"t;1tI+on ~R -.. _----------

I f I

OJ

j20 .. 00

~

I /II....~

WIflliAlL .I-I

.­ f !!Q!!.!L ( -:T~ ~: j-------­ ---­!----­ -­

"."no H!UlllL f ! ~~I I r,

PlAtP'HG~ nOHATDESPLAlH£5.utD \l;tlf IMJItfN 5 crs .

..n+nn --­~ ~

I i. 0 ;l; + ~ r;; i5 a r;;

Page 76: CIVIL EN INEERING STUDIES - ideals.illinois.edu

FIGURE 6-CROSS SECTION OF THE 8.00' X 7.20' """'"

• l> •

DEPTH::: 6.0·

DEPTH e 5.0'

,p

DEPTH::: 4.0' , .

.... -(

DEPTH::: 3.0·

-0 0 ro I

DEPTH:: 2.0'

'"iI'I Fll 1"\8 t , C.V

I ~

DEPTH:: ----

LOI

t:::> 1 • ". I

BASED ON DRAWING No. 1208

DEPARTMENT OF SUBWAYS AND SUPERHIGHWAYS OITY OF CHICAGO

Page 77: CIVIL EN INEERING STUDIES - ideals.illinois.edu

----+I-~ I I

61--- I I I i

~ 21 RP-Q\\.lS

I I 0.5 I

8·...-­ , · i i

lL o

0: LIJ I- 4 1

« 3t

I

..,: u,

HYDRAULIC RADIUS _ 1.52 _ FT. 2

10AREA _ 3'0 2.5

, _ SQ. FT. I 10 I 25

WETTE[) PERIMETER _I~T. I I TFiGURE 7 -, HYDRAULIC ELEMENlrS OF THE 8.00 Fl: BY 7.20 FT-_.........................................................._..................

....... .......-...il_MAIN INTERCEF-TING SEWER

CONGRESS STREE'f EXPRESSWAY- ---~~~

Page 78: CIVIL EN INEERING STUDIES - ideals.illinois.edu

10

8

~ .&..6

tr.::: i.IJ

~ ~4

I.L o

::t: ~ 0-l.LI

°2

o 2 3 4 5 6 1 8

VELOCITY - FT. PER SEC.

'1\ ') \ /

/

""""

~ ~

J

/-.>

~ ~"...,-

~

~ ~

~ ~

~ ~

py,/'

/~ ..."". .../

»>".,.-

»>: »>

-: ~ ~

~ ~

I , I 1 1;

o

~ iii iii o 20 4'0 6'0 eJo Ido I~O 140 160 U30 200 QUANTITY - CU. FT. PER SEC.

FIGURE 8 -- VELOCITY AND DISCHARGE CURVES FOR T~~E 8.00 FT: BY 1.20 FT

MAIN INTERCEPTING SEWER -- CONGRESS ~5TREET EXPRESSWAY ...

Page 79: CIVIL EN INEERING STUDIES - ideals.illinois.edu

_ _

-- -- --- - - -----

........... ...........

l~ -H~DLuc IGRAD)LI~\~Ls ., ~AC~ FIGURE 9- HYDRAULIC GRADE LINE COMPUTED FOIR THE PROFILE AT 140 MIN.

II~~ 111:::-'I::----L. HYDRAULIC GRADE LINE WITH

INTERCEPTING SEWER, FROM CAMPBELL STREET TO. JUNCTION MANHOLE. OF THE CONGRESS STREET -EXPRESS,WAY.. GHICAGO.

HYDRAULIC GRADE LINE DATA BASED ON "MEMORANDUM REPORT-ILLINOIS

AE-FA 261 (1)- HYDHAULIC STU DY OF WEST ROUTE GRAVITY SEWER.

CHICAGO, ILLINOIS" BY C.F. IZZARD, BUREAU OF PUBLIC ROADS, 1945.

5 ,I +-I I I

II!'" APPROXIMATE HYDRAULIC GRADE

I I r I 10 _ c: ..... HYDRAULIC GRADE LINE (0.8 DEPTH) - GRAVITY

/ ~ - ""­ r--

/ - - -\5 ---­

8.00' X 7.25' -20

18,850 ~25

INTERCEPTING SEWER

..J z 0..J )-, I ­ ,q:01: :zzI ­w~ W cIl[zw....JI ~ aa. t­ :> wz ..J:J

(J) lliC: oct ... ::lie o 0 :r.~ w >­ :J-s, « <.!) 0w « (fJ

()

0<iC <iC00 ..J J: o :B: 0­:.t «

WATER SURFACE PROFILE

z ;(i= (J) ~ :J ~ <t o

AT 1601\41N.

(fJ

i 0 0 ..J

!!! ::lie oct a:: <t ..J

I

L1NE- 50 C. F.S.

FLOW

0 0:: l!J o U

PUMP

~~ CAPACITY ;--=::~

a:: w Z... (fJ

0 ~

0 a:: 0 u, ~ <iC a:: o

I

CAPACITY

a z iLl c( z ..J <:;:x: !J) <iC

0::c(

-Jy.F-

PUMP CAPACITY'" It,-/

r-­

-

_~

(J)

~ <iC ..J a. (fJ

W 0

5

10

15

20

25

~~~ :II:: a:: f <iC

~ :z..J a::<iC W l!Jf:: N ~ ~ ...:z (fJa ;;i

-Ww ::tI:: ~

() o ci3t

APPROXIMATE HYDRAULIC GRADE LINE 150 C.F.S.

~ -

TOPICI~ AREA ~I

PROFILE - VICINITY OF TOPIC AREA

Z <tW <It (!)z iii::a::<:3 00« w:2EI'll: a.

....~PUMPING STATiON AT DES PLAINS AND VAN BUREN STREETS

Z W ILl Ql o ..J

- 0... t; ::r: ..J Z Z (fJ

:;:) <t<Ii: ::It .., ~

-I- -

-",.

Page 80: CIVIL EN INEERING STUDIES - ideals.illinois.edu

8

6

l ­LL

I a: w

~ 4 3: LL o JC I ­o, w o 2

o o 10 20 30 40 50 60 10 80

Btl SED ()f~ WO RST V ~LOCI"r-y CO~ DITIOP S DUF~ING P~MPIN :;

\ \

1\ -, --St- DIS< HARGE -Q

r-, " ~

t'-..... -........ r---..-.. ~A

VERAGI VEUDeiTY -t-V r-..,

r----r---..---- r--- ::::>--.---- ----------~'

------ ------~

----- ---------- --------~ =-----i-: ----- I I

DISCHARGE -CU FT/SEC ----'-------r'----------------r------------- ----,-----Ir--­

o ! VELOCITY ~ FT /SEC

FIGURE 10 --VELOCITY AND DiSCHARGE CURVES FOR THE 8.00 FT BY 7.20 FT ~.II!!a I'a' :m:!:n" 5LLJLLill!i!1I' tC"W3t'"i"""'nn'n·rnmr ~~ :!'fW"""""""'"'"W"

MAIN INTERCEPTING SEWER SECTION ........ CONGRESS STREET EXPRESSWAY , .,...,. 'mT"T:"''l:lIel!' Mre=~

.. ............... llS£'llJi mnm ,

Page 81: CIVIL EN INEERING STUDIES - ideals.illinois.edu

80

• II

1

• o 5 l&.Il 00

........ 4

...= IL

J ...

)0-

o 0 2 ..J I.LB >

(!)

;z

0:: ;:) 1.0

0 .• o en .•

.1 ..J t@1( ••

o ..... ..5

0: U

II­

~

.2 J .2

" ~-~-----_._-"

"

V

V v

»: V V

~ , v/

~~o· ~~

V V

vc =

B::

5:: 2.65

f = 0.03

f- ­

~ V

V ../

v V

~ v v

~

V ./!iii""

~

~ ./

.//

.//'

~ V V~ V

/

V /'

V v~

/ o

~esT g ($ - I) d

B:: 0.06 (for Qrifl

0.04 (for uni~ranulal7' solids)

.3 A .5 ~ .1 .8 .9 1.0 2 3 4 5

PARTICLE SIZE 11 M.M.

!FIGURE II -- CRITICAL SCOURING VELOCITY

6 1 8 9 10

Page 82: CIVIL EN INEERING STUDIES - ideals.illinois.edu

1001 b iii I I

_----T"-'---~SAMPLE NO.2-.-A SAMPLE NO.:3

801 I I

.-....m SAMPLE NO. I

(!)

z (f) 60I I I.U). «­Q..

I ­:z lDJ <.> «0..

CHAMPAIGN- URBANA

SEDIMENTS I20 S P. GR.:: 2.64 - 2.65

o Ie" U I I I , ,

-- I

I • SAMPLE NO.4

I I I I

Ai I ~i I

W 40 t--f

I I 1J'E- I ~ I

o 2 :3 4 5 6 SIZE OF OPENING· (m.mJ

FIGURE 12 --. PARTICLE. SIZE DISTRIBUTION CURVES FOR

CHAMPAIGN-URBANA SAMPLE S

Page 83: CIVIL EN INEERING STUDIES - ideals.illinois.edu

100

80

4$ Z iii 80 tfb1i)

c c..

.... Z IlI.Il

~ r

40

20

~i e SAMPLE NO. 3

~

~. ~ ~SAMPLE NO. I

I~~ I i SAMPLE NO.2

~ I I CALUMET EXPRESSWAY

~ SAMPLE NO.I- SHOULDER MATERIAL 0

S~ GR.:: 2.64

I-­ - SAMPLE NO.2- SHOULDER MATERIALA gP. GR. ::: 2.65

SAMPLE NO.3- SHOULDER MATERIALS I--

SP. GR. :: 2.67

t-­ .

~

°0 2 3 4 5 6

SiZE OF OPENIN G (mm)

FIGURE 13-PARTICLE SIZE DISTRIBUrlON CURVES FOR

CHICAGO SAMPLES, NOSe 1,2, AND 3 ~ C7 tremrm

Page 84: CIVIL EN INEERING STUDIES - ideals.illinois.edu

100 II I---~~

-17f --

~f

-(:"

f--

-4

8S AMPLE NO.5

e SAMPLE NO.4

80

(!)

~ 60 fin en if I ­Z CALUMET EXPRESSW~ kJ

SAMPLE NO.4 - INLET MATERIAL o~ 40 bJ SP. GR.:: 2.51 Q..

SAMPLE NO.5-INLET MATERIAL A

S~ GR. :: 2.61

20

o o 234

SIZE Of' OPENING (m m.)

5 6

FIGURE 14 ......... PARTICLE SIZE DISTRIBUTI N URVES FOR

CHICAGO SAMPLES, NOS. 4 AND 5

Page 85: CIVIL EN INEERING STUDIES - ideals.illinois.edu

I ~

100, iii I i I

_~----ilSAMPLE NO.8

A SAMPLE NO.1

I ; SA-MPLE NO.6

801

t" ~ 601 en (1)

cl Ill..

D-- CALUMET EXPRESSWAYZ W

SAMPLE "10.6- INLET MATERIAL e~ 40 w SP. GR. :: 2.40e,

SAMPLE NO.7-. GUTTER MATERIAL A

SP. GR.:: 2.65

SAMPLE NO.8 - DISCHARGE PI PE 20 MATERIAL (1

SPa GR.:: 2.51

NOTE: INLET SAMPLE CONTAINED CINDER,GLASSlI

STICKS, a FLOATING MATERIAL. Sf? GR. OF SAND=2.65 o· ! I

o 2 :3 4 5 6

SIZE OF OPENING Imm.)

FIGURE 15-PARTICLE SIZE DISTRIBUTION CURVES FOR

CHICAGO SAMPLES NOS. 6 AND a 'S!'l"'i"?"'"' -

Page 86: CIVIL EN INEERING STUDIES - ideals.illinois.edu

I II

I

I

Page 87: CIVIL EN INEERING STUDIES - ideals.illinois.edu

40

30

20

10 9

a-: 8 u,

I 1 Jt 6 I :r: 5I- ~ o :. 4

:2 -30 40 5060 70 80 90 10020'3 4 5 6 78 9 10

DISCHARGE-Q- CFS

FIGURE ~7-DESILTING CHAMBER DESIGN CURVE 8 Y THE CAMP "'4ETHOD

, T I I T r I

PARTICLE SIZE :: 0.50 mm . SPECIFiC GRAVITY :: 2.65

.: k2t\ I"Q L CHAMBER LENGTH W= 2.42~N N=W = CHAMBER WIDTH ~

L4t1.~I I~I 1 I ~ ~ ,ij// +~t:lli b Z~

_ \ I ~_t::: 1/.§£i± ~. q-, ~ .", T 1

7Pf ~~~f-h i -

/" #1 ~; ~ e.tJ ~ ~A--'IJ ~ DESIGN FLOW

:~ I ~. FOR TOPIC AREA ~

ffi= .

--

e, •

G': W

~ 3 « ~

'i nnn .,. ,..,...,....

I~~A ffi'!iii1' ~.,.,."....,. M =:==='W==CZ~=TmD m·nemJmTim?ml~'~Ii'-L'l!.~.:w!'Fi5l ':mm!1C\F«i!!!W1J:>!:"..t'..!f'!'~\S'1'l%Sj2iiJillj ,

Page 88: CIVIL EN INEERING STUDIES - ideals.illinois.edu

30

20

"

10

9 "'=8I.L

I 7

f6 :x: 1-5 Q

it 4

0= W m :E3 <t :I: o

2

PARTICLE SIZE :: 0.50 mm V V

SPECIFIC GRAVITY: 2.65 ~ ),/

J5L L CHAMBER LENGTH I B "til = 2.62 ill N= Vi" = CHAMBER WIDTH »< I I

Jd:/f I I lilt~II~I

/ )::::-/1 . I 71 .»:

)7' prv BYZI" 1 ~ ~

;/' :::2:1 L L /' ~ ~ /.. \ 71 "t> ~- -vlm-:;7

L I "'Zo %' IJ.. ~~~ IY

T~~~ ~~

.- 4 ~+ __DESIGN FLOW FOR TOPIC AREA

./

V

I 00 DiSCHARGE- Q-CFS

FIGURE 18 -- DESILTING CHAMBER DESIGN CURVE BY THE KIVELL

A·NO LUND METHOD

tikte: ",",",,~====r ~~~-a5 mrmes "'9!r !"f!:!J'-~ !)!li~~ rmnv '

Page 89: CIVIL EN INEERING STUDIES - ideals.illinois.edu

~ L ~

,WATER SURFACE A

A'~ ~

~~ 1

I H HI "~ <.V '"

. ~,-..-. j , . - , '. I' ... , -. .. 41, .. ... - •• tI... Q ...

..... ~. :c-'-'.:. : ,'.~,'. '-', 4.- .... : :...." .. .. ... .. .... ...... # -

1 <. .-. <, .~

- .... t ~. '\. ....... '.,:.,

. .' " .. ' , ~'D E'SIG'N' LIM IT . OF -', ". SB.

,­•• ,,, . ' ...... _.

',',': ': .. <'}; GRIT STORAGE AREA" :' ~ • ."....: .. 4 ' .. \'" 11 ... .. .... .. .... 11 to ~ 'to... .. ....

FIGURE 19- SETTLING PRINCIPLE OF IDEAL SETTLING '.

ZO E

Page 90: CIVIL EN INEERING STUDIES - ideals.illinois.edu

---

FLOW FROM NORTH PORTION OF ROADWAY

t" >

VORTE)( TUB E ...................

At\:-:~I -(0 JUNCTION -llO

CHAMBER IIfi

.··._'--·; .. D"--:·.,,:·.··~··.e.·;·".,>··,.· .. · ... 4 ..... :. 1 • . • • J ... :';"':b:J.-Jt:: ...iii ••••

AP~~OACH CHANNEL

PLAN AT SECTION B-B INTERCIEP1lNG SEWER

4'!SO'

FLOW FRORl! VORTEX TU8E IS

. -----.r-

c .... --",. ",.····,···'A· ..... : -.'@t"', A." . · ..·e·· ..

VORTEX TUIE r r ; .. ·I!it'~-· ···A· -; -_-, -:-.dJl@-;--';-U-.~_ • ,r. ' .. -.c' e '-. - ." '.... ' " •. - •.••. ..- ... _'r' ... ··-A·P~~~·.:t· ~L A·'- .-..... • PI

inELEVATION AT SECllON A--A, .,j---,----..-............

DIRECTION QF FLOW If1l~I'~-D ~

. " ' " <, ~~~ .s>'•.•~ .... I ~ •• :,""~ ·a~~.~· ,~'~:_f":>~'': .

~ ".. .." - .... r-_

CROSS SECTION Of TlH!B1E n~STED BY

R. L. PARSHALL

...·.Il

...,.... -, n ----

REMOVABLE fLOOR FOR ct.EAJ\1!ING

OROP MANHOLE TO MAIN

~

'.

DESILTING CHAMM:R

lOll 'Pi~

CamJCTm TO DIESILTING CHJWIllER THROUGH A. PIPE WHICH IS NOT

SH0Wt4.

.... ..,....­ : .. -. '" - ,; 0-. . ". I:J,. ..

';ll d:. . "f= K .~,

-S£.... :·'·4" •. ' .-tl!r-:~

-1­

mo P I\'IANHOLE TO MAIN

e e, ·"··.··: .-' ~~1~I.J_. a l

flGURIE 20 -SCHEMATIC

TYPE

DRAWING

DESILTlNe

OF THE KINETIC-SEDiMENTATION

S1 RUCTURE

REVOLVED SEC.C-C OF MAIN

INTERCEPTING SEWER

APPLIED 1'0 CONGRESS ST~ErlT

/Ilt;ALIE I" " 5' EXPRESSWAY

Page 91: CIVIL EN INEERING STUDIES - ideals.illinois.edu

4 I I I . . . 1--------. I i I I I I

31-1--­

a-: LA..

I

3t o

~ LL ·0

~

D­u, W c

21 I I ~ I I I I I I I I I I I

I I I I I 2 3 4 5 6 7 8 9 10 WIDTH OF APPROACH CHANNEL-FT.

FIGURE 21-DESIGN CHART FOR APPROACH CHANNEL DIMENSIONS