civil engineering - railways

24
U . 'F I i

Upload: wojciech-czerwinski

Post on 28-Mar-2015

735 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: Civil engineering - Railways

U

.

'F I i

Page 2: Civil engineering - Railways

Ra i I ways

9

Page 3: Civil engineering - Railways

Earthworks and drainage 2513

25.1.2.2 Rock cuttings

British Railways has indicated safe slopes for rock cuttings and angles of repose for rock embankments in a chart reproduced as Table 3 in BS 6031. If steep cuttings in rock are essential, then it is necessary to apply engineering geology concepts to assess joint sets in relation to the direction of slope. Rock anchors, rock bolts and sprayed concrete may be used to assure stability before considering the use of mass-retaining walls. Chalk and certain other soft rocks are susceptible to weathering and frost action and may be protected by vegetation cover.

25.1 Earthworks and drainage

The contours of the territory to be crossed by a railway are obviouslv decisive as to its average gradient but they are also the background to fixing the maximum permissible gradient within the limits of tractive and braking adhesion. The lower the difference between average gradient and maximum gradient the greater is the practicable train load and the lesser are the deviations from constant-speed running. The minimum curva- ture to be used also determines the differences between the line speed limit and local speed restrictions. Long curves of small radius on heavy gradients may involve derailment hazards for very long and heavy trains, arising from braking or tractive effort surges along the train. Both maximum gradient and minimum curvature have a large effect on the earthworks cost of constructing a railway and, because of this, the ideal of con- stant-speed running is often subject to heavy qualification. This is particularly the case in mountainous country.

Railway alignment needs to be planned to give a volume balance between excavation in cuttings and tipping in embank- ments, subject to the material excavated being suitable for tipping to form embankments and subject to minimizing the haul of the excavated soil. Recourse to borrow pits for embank- ments and spoil hauls for cuttings should be minimized.

The route may also be affected by other considerations which may be economic, environmental or technical. These would become apparent in a full site investigation, where such matters as previous mining activity, underground services, effect on neighbouring structures, nature of the groundwater table and watercourses would be taken into account. Guidance is avail- able in relevant Codes of Practice, such as BS 6031 and BS 5930. (See also Chapters 9, 1 I and 17.)

25.1.1 Site investigation This will vary according to the extent of the problem. At the outset, a preliminary study may give adequate information to specify the route corridor from geological maps and memoirs, topographical maps and aerial photographs. Earth satellite imagery with interpretation of selective wavebands by special- ists in remote sensing can indicate important features. Water table conditions may vary throughout the year from those obtaining at the time of exploration.

For more localized investigation, the type of equipment (augers, percussion and rotary tools, penetration heads, loading plates, pumps), instruments (piezometers, inclinometer tubes, seismometers, resistivity meters, gravimeters, etc.) must be chosen according to conditions. Relevant disturbed or undis- turbed samples should be procured for testing. According to the type of ground, the construction and the design philosophy applied, it may be necessary to carry out full-scale site testing with long-term monitoring of instruments.

\

25.1.2 General In the past, railways have been maintained over poor ground, with inadequate trackbed materials with a high input of labour time and at slow or moderate train speeds. Although the following concepts may be used in modifying old railways, the basic approach is to obtain a minimum maintenance high-speed railway accepting normal freight traffic on conventional sleepers.

25.1.2.1 Cutting slopes

Slopes in natural ground may be constructed at safe angles according to the properties of the soil.

25.1.2.3 Soil cultings

Where the slopes are in noncohesive sands and gravels, the angle of repose is the limiting gradient (with a maximum value of I : I). Usually, the gradient is shallower than this due to the presence of finer layers in the soil system or a silt or clay matrix around the gravel. The non-cohesive soils tend to be self- draining but erosion can occur when water springs part way up the slope. At such locations a non-woven geotextile filter can be placed and covered with uniform coarse stone (away from the sun’s rays) which will hold the fabric in place.

Drainage measures should take the form of preventing water reaching the slope and of removing it from the slope. Unlined ditches behind the crest of the slope increase the hazard. Drainage trenches, whether behind or below the crest, should be designed to intercept water and have impermeable membranes below them and on the downfill face to prevent water once collected from re-entering the soil. Modem counterfort or buttress drains differ greatly from the original open forms. Like all drains they should be lined with a geotextile layer to prevent erosion behind and fouling within them. The top I or 2m should be composed of impermeable material, either compacted clay fill or a system of stone and plastics membrane to prevent surface water reaching deep into the ground, where it could cause internal pore water pressure at likely slip surfaces.

In some cases, there is a mantle of more permeable silt or sand overlying the older clay and, if possible, a lateral interceptor drain should be placed about 20 m behind the crest to prevent the fast seepage of water. In addition to the above rotational slides, translational slides

can occur, usually as a shallow mass moving on a planar surface. They can take the form of slab or block slides, wedge failures, debris slides and flow slides. These possibilities are assessed in the site investigation. Mires are formed as peat is laid down in a specific sequence with variations in soil content, dimensions of fibre (roots, trees, etc.) and extent of humifica- tion. Peats reduce greatly in volume under the effects of loading and drainage. In making cuttings in a peat system, quite substantial waterflow can occur and a filter is advised to deal with fine particles otherwise carried from the slope. In all cases of cuttings, other engineering works at ground

level should be considered. Urban or industrial construction involves roads which act as catchments to deliver water to local drainage systems and also water services: if these are defective and near the slope, water can flow to increase pore pressure and precipitate a slip. Similarly, surcharging, especially if accompa- nied by dynamic loads from construction plant or the placing of storage containers, can seriously reduce the factor of safety.

Steep rock faces, chalk cliffs, and boulder-strewn hill slopes may present rockfall or chalkfall problems which may need special watchmen, signalling provisions, special fence, apron or tunnel protection.

25.1.2.4 Embankments The nature of the natural soil to receive the embankment must

Page 4: Civil engineering - Railways

. 2514 Railways

be investigated. If it is too weak to receive the embankment loading at the rate of placing likely to be used by the contractor, failure could occur. A total stress analysis is applicable for this. The conventional technique is to place berms as counterweights at the position of heave. A modem alternative is the use of reinforcing geotextiles or meshes (usually of plastics) to resist tensile forces. The fabric is laid directly on the ground and covered with a granular layer at least 200 mm thick; this acts as a filter and permits construction plant to move easily over the site without sinking into the underlying soft soil. Further fabric or mesh is laid at higher levels, the number and spacing of layers depending upon the engineering properties of the specialist type of material chosen.

Slope angles. Embankments may be formed at angles varying from ratios of 1 : 1 horizontal to vertical for crushed rock and gravels to 2.5: 1 or even shallower for clays and silts. The slope angles depend both on the material and rainfall. For modem railways, peat should not be used as fill material.

The surfaces of slopes should be protected from erosion. This may occur naturally as vegetation is established, followed by a protective topsoil. If surface erosion is a problem, various systems are available, such as spraying with a seed mulch, turving, placing filter fabrics held down by gravel layers or using a honeycomb mesh to hold seeded compost in place.

Rockfalls. Vertical or sloping rock faces may erode or topple to cause rocks of various sizes to fall towards the running line. Although vegetation may help by bonding superficially, protec- tion must involve coping with the energy of rockfall and removing the debris regularly. If space is available, one or two berms are constructed between the base of the slope and the railway to collect scree. For some faces, a plastic geomesh is adequate.

Reinforced earth. The dimensions of embankments and of gravity-retaining structures can be reduced by the inclusion of various strengthening meshes, fabrics, strips and rods of metal, glass fibre or plastics. The tensile resistance of these elements is applied to the adjacent granular soil to produce a composite system permitting the construction of vertical faces in the fill. These external faces are protected by facing elements usually of concrete, resulting in a structure which is economic and which can accommodate settlement. The various qualities of creep, longevity of reinforcement, corrosion, etc. are still the subject of study but many such structures exist throughout the world, including railway environments. There are none so far beneath a high-speed running line and, in this particular case, such systems can be installed up to a horizontal distance of 5 m from the running line.

Trackbed designs. The thickness of subsleeper construction (trackbed) is a function of number and size of axle loadings and of the subgrade soil. Modern railways assess the subgrade soil in one of two approaches: ( I ) the classification of the soil accord- ing to its physical properties and taking account of the water table; or (2) correlating some measured strength or modulus of the subgrade with an empirical design chart. The thickness of the trackbed may also depend upon its component layers to protect against frost, water and particle movement. In very frost-prone areas, such as Central Europe, the thickness of ballast for frost protection exceeds that which might be required for prevention of bearing capacity failure.

The thickness of ballast (all dimensions are below bottom of sleeper) is a minimum of 200 mm to permit tamping machines to operate. Although new ballast injection machines would permit this to be reduced, a high-speed or high-axle-load railway would require 300 to 500 mm thickness for minimum maintenance.

Drainage. The control of water in the trackbed is a major factor in designing the construction layers in relation to the type of subgrade soil as discussed above. Soils such as sands and gravels which may be drained fairly easily do not present a great problem unless there is an artesian head in this case, there can be a slow upward migration of fine or medium sand under track vibration combined with water flow, and a geotextile is neces- sary to hold down this sand. Cohesive soils cannot be drained easily and the installation of a channel or pipe will only reduce the pore water pressure to invert level in its immediate vicinity. It is not practical to attempt to remove water from clay in this way as such a large number of drains would be required. If water arrives through precipitation or by flow from adjacent areas, then a relatively small amount is sufficient to produce deleterious changes in pore pressure and so it is practical to provide drains to intercept and remove this free water. Most of the water in cohesive soil is held in capillary suction.

The relationship between the moisture content of cohesive soil and the water table is complex, depending upon the over consolidation ratio (OCR) of the soil. Weathering reduces the OCR effect at the surface.

One object in designing the system of drains and track is to produce a maintenance-free system or one needing minimal attention. Channel drains are readily accessible for cleaning and deal with rainwater, they can be laid at very slight gradients and can deliver at catchpits to deeper pipe camers if necessary. Many pipe drains act both as collectors and carriers, allowing water to enter at open joints or through perforations. The various forms of pipe are glazed earthenware, galvanized corru- gated steel, pitch fibre and, now coming more into use because of ease of handling, plain or perforated PVC pipe. Geotextiles are of great use in static drainage conditions and most railways report satisfactory results using commercially available filtering non-woven fabric. For normal purposes, a fully heat-bonded geotextile with a surface density in the range 100 to 200g/m2 is acceptable; needle-punched geotextiles should be of slightly heavier grade. Fabrics placed in quasi-static conditions near the track should be of heavier grade up to 350g/m*, or more if needle-punched. Such a geotextile would be placed in the sixfoot of a double track line after one track had been cleaned or blanketed. This would prevent slurry from the dirty adjacent track flowing across.

A modern standard design for a side drain is a trench lined with geotextile with a perforated pipe drain running along its base; above and around the pipe is placed uniform stone such as ballast, with the top of the geotextile lapped over the stone about 200 mm below the surface: more stone on the geotextile protects it from disturbance and from the effect of the ultra- violet rays of the sun. As perforated drains can release as well as collect water, possibly at susceptible locations, it is often the practice to place a polyethylene film to line the trench.

25.2 Ballast

Ballast, the material around and below the sleeper, is placed to provide support and lateral resistance to the sleeper. It permits adjustment of level and alignment as required and, if this is done manually, the maximum size of particles should be about 50 mm. Ballast should be free-draining, mainly of single size, of cubical shape but, above all, durable so that there is negligible volume change under track loading. The wet attrition value (WAV) gives the best correlation, with minimum maintenance requirements over the long term and this is determined by the test described in BS 812: 1951. clause 27, which specifies the exact size and type of sample to be used. If particles of different size from the 50 to 37.5 mm required in the test are used, then a different WAV is obtained. The WAV should not exceed 4% for

Page 5: Civil engineering - Railways

Ballast 2515

nominal 20mm size between the ballast bed and the sleeper, which is lifted to insert the stone. There is now a track-levelling machine, electronically controlled, which evaluates cant and level from an advancing inclinometer trolley and places the exact quantity of stone by pneumatic injection to obtain proper level. As stone more than 50 mm below the sleeper is not moved and brought with its dirty matrix up to bottom sleeper level, as with a tamper, the likelihood of pumping track is somewhat lessened; the beneficial effect of high-quality small stone is not reduced by mixing with existing worn stone and there is less attrition of the base of the sleeper.

good ballast and it is possible to obtain stone with a WAV down to 1%. It is rare for synthetic stone, such as slag, to have adequate wet attrition properties and they may generally be grouped with most limestones as being unsuitable to be in contact with the sleeper. Hardness is difficult to define in relation to other tests but, if the ultrasonic pulse velocity of the homogeneous mineral is 6000 m/s or greater, the stone will be suitable. In severe climates, a freezing and thawing test may be applicable.

The dimensions should conform by weight to the values shown in Table 25.1; and the 1.18 mm limit effectively minimizes the amount of dust present.

Table 25.1

Square mesh sieve Yo topass

63 100 50 100-97 28 20-0 14 2 4

1.18 0.3-0

The stone should have a maximum flakiness index of 50%. For elongation qualities, not more than 2% by weight of particles should have a dimension exceeding 75 mm.

The effect of many tamping cycles is to break up ballast particles; stone as hard as possible is required to accommodate this. When a sleeper is tamped, a horizontal load - the major principal stress - is applied to the ballast, causing it to deform vertically and lift the sleeper. The minor principal stress is vertical with the subsequent arrangement of stone particles in the least favourable position to support track loading, even though the rail level is now correct. The maximum rate of rail settlement occurs after tamping, which reduces as the stone packs down under traffic, with the major principal stress becom- ing vertical. The trackbed becomes more stable under vertical loading and the best relevelling procedure is the manual or mechanical placing of measured quantities of small stones of

3307

25.2.1 Track profile Under traffic, rail level, as measured by accurate optical or inclinometer-based machines, shows a profile which is repeated even after many successive tamping and loading cycles. This is related to the care with which the original trackbed layers were installed. When the subgrade is prepared initially, and as subsequent layers of blanket and ballast are placed and com- pacted, it is necessary to provide extra sighting instruments on compaction and grading plant so that there are no short variations in level. This can be successfully done by using a laser system aimed at the surface a fixed distance ahead and which causes the equipment to compensate for deviation from the required level by moving its instrumented blade up or down.

The ends of the sleepers need to be boxed-in with shoulder ballast to a minimum width of I50 mm for any tracks, 200 to 250 mm for running lines carrying moderate-speed, moderate- axle-load traffic, 300mm minimum for welded track on the straight and 350 mm for welded track on curves. Generally, there is little advantage in extending shoulder ballasting beyond 300 to 350 mm. In the last decade or so, the practice of raising the shoulder ballast in a slope from about top of sleeper level at the rail to about top of rail level at the shoulder edge has become common on European railways. This practice not only increases the lateral stability of the track but provides a useful reserve of boxing ballast which can be temporarily utilized to make good the boxing ballast when the track is tamped. The angle of the shoulder should be about 55'.

3307 ~~

- I d

(Min. dimension) (Min. dimension)

Pandrol rail. fastening

915 c

\ 1 000-gauge ' \ polythene sheet

Approved sand I

where required Pipe drain

Figure 25.1 rail (CWR) track (dimensions in millimetres)

Components and formation for continuous welded

Page 6: Civil engineering - Railways

2516 Railways

25.3 Sleepers

25.3.1 Timber sleepers and sleeper spacing The traditional track support since the early days of railways has been the timber sleeper, but now prestressed concrete sleepers are in use in many countries. In some countries the baseplated timber sleeper is already more expensive to install than a baseplateless prestressed concrete sleeper.

In Britain, the sleepers and point and crossing timbers have traditionally been of softwood, chiefly douglas fir from Canada, Maritime pine from southwest France and Corsica, and Baltic redwood from Poland and Russia. Homegrown fir sleepers have been used when they have been available. In continental Eur- ope, beech and oak sleepers have been widely used. All soft- wood sleepers, and most hardwood sleepers that,can be impreg- nated, are pressure creosoted by the Bethell or Ruping processes before being baseplated. The harder softwood sleepers such as douglas fir or scots fir and hardwood sleepers need to be incised prior to creosoting. Four to 14 litres of creosote per sleeper is a normal absorption, according to species. In Canada, the US and South America a mixture of mineral oil and creosote is used.

A timber sleeper may have a first or running line life of between 6 and 50 years with an average of about 20 years according to traffic loading, weather exposure, the nature and incidence of the indigenous vegetative and insect enemies of timber, the presence or absence of baseplates, the nature of the fastenings, the quality of the ballast and its maintenance, the species of timber and, significantly, the rate at which it has grown.

The British softwood timber sleeper is 250 x 125 x 2600 mm with switch and crossing timbers of 300 x I50 mm section. In Europe, hardwood sleepers mainly of oak or beech are used with a depth of 160 mm. Sleeper spacing in Britain is 700 mm with 650mm on curves or on timber sleepered continuous welded rail (CWR). In countries other than Britain, timber sleeper spacings of 600 mm are common with some as close as 550 mm in heavy-axle situations.

The sleeper spacing applied represents a compromise between overall sleeper cost and the lessened frequency of maintenance attention and reduced rail bending stress which results there- from. In addition, a decrease in sleeper spacing may be appro- priate where the formation is weak or where it is not practicable to increase the total track construction depth by increasing the depth of ballast. Since also increasing the density of sleepering increases both the lateral and vertical resistances to buckling movements of the track, it is general practice to reduce sleeper spacing when laying track intended to carry long welded rails. Where the rail formation is regularly subjected to frost heave distortions, there may be a case for deliberately choosing a rather weak rail with complementary close sleeper spacing in order to allow the track to accommodate itself to a frost heave contour without imposing undue bending stresses in the rails.

25.3.2 Steel sleepers Steel sleepers are widely used in India, Africa, South America, Asia and in parts of Europe. Steel shortages during and following the Second World War, and the increased use of concrete, impeded the further development of steel sleepers until about the mid 1970s. Since then, there has been a considerable amount of research done in Australia, Europe, Japan and Britain to evolve improved steel sleeper designs. Computer- based design techniques, e.g. finite element analysis, and modern stress measuring and analysis techniques have been applied to both full-scale laboratory loading and fatigue testing

and to in-track service trials in order to prove the efficacy of new steel sleeper designs.

Many of the older steel sleeper designs gave average service lives of over 50 years before failing through cracking in, or adjacent to, the rail seat area. Generally, these cracks propa- gated from rail fastener holes or slots or from discontinuities in the rail seat area. Abrasive wear and/or corrosion in this area also contributed ultimately to sleeper failure. The steel sleeper design features, and especially those associated with the rail fastener mountings, together with the accumulated gross traffic tonnage carried, are the most important factors determining steel sleeper life. Recently improved steel sleeper designs have given due cognizance to these influences.

I t is commonplace to recondition old steel sleepers which have already given a 30- to 50-year ‘first life’, by welding-on suitably designed reconditioning plates. If required, the recondi- tioning plates used may permit a change in rail fastener type or rail section to be made for the further ‘second life’ of the steel sleeper. When damaged in service, e.g. by derailments, steel sleepers can readily be repaired by pressing and/or welding.

Steel sleepers do not burn or suffer from exposure to dry heat. In tropical climates their immunity to insect or fungoidal damage is extremely beneficial.

Loss of metal section through corrosion is usually surpris- ingly low, but there may be a few very special sites subject to severe corrosion, where the use of steel sleepers would be inadvisable. Under-design of the rail seat, or inadequate sup- port thereof, can greatly increase the localized corrosion and fatigue damage in this generally highly stressed area, and due allowances have been made in modern designs.

Steel sleepers pack neatly into bundles and thus simplify all handling and transport operations and greatly reduce these costs. The relatively low mass and convenient and uniform shape of steel sleepers is of benefit in both mechanical and manual handling.

The use of steel sleepers provides good resistance to lateral and longitudinal movement of the track and gives high consist- ency of gauge,,both at installation and during subsequent service. The achievement of good alignment is necessary when steel sleepers are initially installed and when retamping after a brief ‘running in’ period. The additional care and attention at this early stage generally results in a reduced need for subse- quent maintenance, realignment and retamping. Some of the older steel sleeper designs were difficult to install and adjust, but modern designs are now relatively easy to install and to use for ‘spot replacements’.

The inverted trough shape and its entrapment of tamped-up ballast provides many benefits. The natural resistance of the ballast is more.effectively utilized by steel sleepers, and ballast depth may be decreased by 75 to IOOmm as compared with wood or concrete sleepers. This can be of distinct advantage in tunnels with limited clearances and ballast depth. Where stan- dard ballast depth is retained, the additional load-spreading effect of steel sleepers and their ballast-filled inverted trough, may enable sleeper spacing to be slightly increased. Also, the inverted trough shape has the in-built benefit that any enforced movement of the sleeper increases the entrapped ballast density and its resistance to further sleeper movement, in comparison with the solid shape of wood and concrete sleepers where eventually a ‘break-free’ point is reached.

Steel sleepers are similar to concrete in their tendency to degrade soft ballast more rapidly than wooden sleepers. Hence, the use of a hard stone is preferred for steel sleepers. Neverthe- less, many old steel sleepers have given long and satisfactory service utilizing a gravel-type ballast.

Insulating pads, fastener shoes and/or washers must be incorporated in the steel sleepers designed for lines using track circuit signalling. In most cases the insulating components used

Page 7: Civil engineering - Railways

sleepert an Spacing in British track is usually 700 or 6fioaun, although

600 mm spacing is used in sevcre curves. In the past 15 ycan, collcrctt sleepem have gaimd wider

international aaxptance for several d,

(1) and M e r fteiBht &le loads stronger trrd;.

(2) Hfgh rpbolu intcnsivc track use d t a t e d d frequency of maintenance cycles.

(3) IacrecuKd use of mechanized track-laying and ;renewal equipment has overcqnae the ditxculty of hamuing heavy m s l e e p m .

(4) Softwood sleepm are oftea unable to withstand the stresses in modern main-line track and goodquality hardwood is increasingly expensive and dillidt to obtain.

(5) With modern fastenin@, d y a r c s i i t pad is required between the rail and sleeper thereby elimimting expensive base plates.

aBickmtical to tlpase d with ImRmutC skpxs. Modem p w IfmteIhb hove improd the deariat becuicy of thnn insulating components and the track circuits, but &e high ebctrical conductivity of steel sleepers requires special attention to their design and maintenance.

The mass of individual steel Saecpers is usually mid-way between that of wood and cmwcte, and may be considered a dissdvant.ge with nspact to resietpnCe to the mtical buckling of continuously welded rail track. However. the entram ballast in the inverted trough of steel sleepers and their general shape @articularly the n t w c ~ designs) greatly imxeaseJ the ‘dfective in-track mass’ of s t t e l - q track. Most rail fastener types can be accommodated ia steel sleeper

designs, and thm arc only isolated fastener systems which cannot be economically incorporated in stcd rlspcr dcaips.

253.3 cormeteskepers The first experiments with reinforced concmetc slccpsrs were ma& over 100 yean ago. concrate is attradivlely resistant to decay, insect attack and fire, but it is brittle, and reinforad concrete skcpcrs would not withstand the im- loads in main line track. A solution dtveloped in Frana in the 19-a~ to use pairs of rdnfo rad coMntc blocks connected by stad tie bars. This twin-block sleeptr ooatinucs in use notably in Fr~mcc, Spain and North Africa but is of declining importance world- wide.

Undcr the pr*unues of timber shomges during the Second World War, a satisfactory mnobloaPr congett atceper was M o p e d in Britain in 1943 using the then & techaiqw of pretensiowl, pnsrneecd conmtc. This has led to I major industry in Britain (over 30 million pretensidned coecrcte

slovakia, Iraq, Japm, South Africa, Australin, Canada and the US).

In Britain and most of the other count& pretensionad comrcte skcpcrs arc made by the 1o.g-line method in which the tendons arc fully bonded. This gives good distribution and control of prestress. Post-tmsioned sleepers were developed in West Germany in the 1950s and have found limited favour (in West Germany, Italy, Spain and Mexico).

t British Rail standard sleeper designated F27BS. is lrith*9.3 m q smn-wire strands (Figure 25.2). It is 2.5&4m kmg, 2 0 3 G - h under the rail, 264 mm wide at thc bap and weighs kg. For more arduous conditions, a

Recently the F40. a 2.480 m long sleeper, has keen dev&ped to

British Rail structw gauge. The base width is imxeapad to 285mmtomaintainthebeaMgareaandthedepthis2OOrmn under the rail which mves the same weight as the F27BS.

StmbgqrVQiionm 3 .1psbeenintrodUad,prcrtrrsrcdwith cight strands in thc sarke concrete envelope aS the FzHR(:

fpcilit.te Single-linemchaaizad track renewal withiathe tigat

It is generally predicted tla pstresssd concrete skaprrs will have an average life of 40 to 56 years. Some of the earlier designs of concrete sleepers have been removed from the track due to premature failure of the fastenings *Ugh the canatc re- mains structurally sound. Since 1964, British Rail h.llc uscd the Pandrol fastening in which tbe IeSs m b l e components can be renewed (Figure 25.3). gC high speeds (over 110 kmb) wheel and rail d p a d&ct.tans~~usc hi#t.ftrcsscs in concrete sleepm which, ifallowcd to paoja can causecracking in the rail seat area of sleepers. Rcstrrssed sleepers with such cracks can remain scnkeabk, providing tkc’cause of high stress is

The brit& MtWC Of-COmrcte somlhwa gives cause for concern in derailment dam&&.Jn practics, the enhanced stabi-

mats and their Scvcrity is rd&d by modcrn fastmine whkb

provide protection to the concrete and derpihmnt damage to the track is not a Signiscant probkm with monoblock concrete sleepers. Twinblock sleepers, however, perform badly as the tie bar% relatively easily bent causing severe gauge narrowing.

Whilst concrete is a smhiconductor, adequate insulation for track circuits can be obtained simply and cheaply by incorporat- ing insulating components into thc htcning.

Concrete skcpen can be cast into a concrete slab to provide ballastkss track but it is advisable to use sbcpas with projecting reinforcement to ensure permanent cone@m to the in situ concrete. In dry locations, cspccialk, tumW undu sensitive buildings where structure-borne m t i o v is ob;jectionabk, attenuation can be achiev

mg into the slab.

switch and croadng bearers &we U m d y 197or. UIb was inhibited by the praaia of drilling the coMxctc to locate rail fastenings, but manufactunrs have now dcvctoped methods of cartina fasteninss into the beareW. and incrcaainn use is ~ t i ~ i -

promptly deta3ed a d naiwas lluxsqp

lity of co- tf+JLrsrk*rs UK incideace Qfderail-

hold dl during ikdh~~t~. Well-filled bpllast crib

- -- . (w$hOut p j d u g reinfo

R a e n s i O d concrete bepmsjbve bocn in PIG in &&ill as

Page 8: Civil engineering - Railways

2518 Railways

W12.7 rnrn

1.4 rnrn

rnrn rnrn

Figure 25.3 Types of rail fastening: (a) spring spike, (b) Pandrol fastening, (c) K fastening, (d) square-section cut spikes, (e) FIST fastening

0 U.

Page 9: Civil engineering - Railways

Fastenings 2519

Rail f a s m w Wded into two catcg~&: dimct and indire& :k ak further divided i@ elastic a&i rigid. Direct fastenhpare those which fastea tbe raildircctlyltothe sleeper, and ingimt arc those which f* the rail to 0 chair M bgseplatc. which SS fasted to them^^^^ scpantd$.

Botb types of fastenings may-be either e W or rigid, dcpedhg on whether a spring element is incorpara- and also

-q- * c$ spike was theoriginal f W ursd for flat bohom raB & b e 25.3), but in E& ifis'% longer used except in sidings and light, p$rrow-&augc railways. In North America, however, and on &ne&anlbuilt railways in various parts of the wor~ci, it is still ins&nd on lines carrying axk loads of up to 35 t. Resiliept fonus o w b u t spike have, howcwr, been used extensively outside Qqda and the US, par t idady in Europe. The cut spike has a number of disadvantagcs whiah have lqi

to the dedine in its use by European railways. $be majsr disadvantages are: (1) short sleeper life due to spike I;illing a@ baseplate cutting (2) the need for high slecperins density (ia America timber normal); (3) the with h c a v y - d spike is a simple and robust system'wjiiah hi :ItJclfwcl) to rapid pioneer developments, but it is poorly suited toafgtr welded rail. q m i a l l y in countries where temperatures vary between extremes of heat and cold. It'is alro d lit& use in

on whether they am adjustable or self-ftfdiontng.

used with baseplatts, their performance is improved and this OPD be fmplarcdrfsmth&wim dit&daubmio,sgkkavm .rallolJEc~*~~mtol(h,sl~>Ilris~drrqolt$l psrotiet to ftb8aeplab&aQI&arledr-f-

~ ~ ~ i a g e d ~ ~ w ~ d r ~ ~ p OE-< ' ' I ' ' : ' ' , ;, , I .V I ~ ~ , j . r < ~ , a

8 pOdk1- On ths!dkS# t-w allows the rail to float ' k d : . 3 & t I m & m ~ ~ ~ resisting rail creep and rail expansion due to temperature

*U to w emm&iod'h#JbPll * . M c * f i ~ l r g ~ * * ~ ~ W ' 8 l h b b / ~ ~

tries, e.g. Belgium, only two are u s a t B & c d u n y p ~ g ~ & m O O 1 l l l l P P d l l ) r q d m t ~ . h w r n b r o f s@i l&ip6.Barcnkmbawdogrdwhca~~~iJsk r i l l a r * h ~ I I @ & c ~ , ~ . r - ' 8 ,

timbarsleeper (bottom)

Pandrol fastening, particularly for continuously welded rail. The importance of the fastening in welded-rail track being able to mainwAh GQ%qpu?a.. fuadlmental$hCfhc_St&dl@ 0 t h e h M d h ~ . I U Q L C significance if the ballast condition is below s-. The clamping force generated by the rail M g m w &

able to resist any tmdency for thc rail ta creep throu&,w fasteniw but n&,+ much,gb to all* the rail b push t& slaesgs thmughthe ballast section. A nominalclip pnwsure of betwecn&.4 and 2 $per rail is pncrally &icient ta@eve *. a large d@ection u$y fitted -sition @ order to-ize th effects of inanufaduing t o w on c#p. rail pad, insulatclr, rail clip &xming an&rail foot/ For exam#c. a clip with 6 mm of

I.

It is inprtant tbpt any self.;4maionin@ip is de@ped to

~ ~ ? h a f i t P ~ f Q ~ W i t h 3 I W l l . .

Page 10: Civil engineering - Railways

2511 0 Railways

of wear or tolerances, whereas with 12 mm of deflection, the toe load loss will be only 25%. The ability to ensure positive and accurate track gauge retention is also an important feature of a rail fastening.

Resilient rail fastenings are now used in the harshest of operating conditions, such as heavy haul and high-speed pas- senger services, and particular attention is being devoted to improving the. ability of fastening assemblies to attenuate the transmission of dynamic forces from rail to sleeper. This is proving to be of particular importance in the case of fastenings used with concrete sleepers in high-speed passenger operations. Considerable effort is being focused on improving rail pad characteristics.

A further area of development in rail fastenings is the need for mechanical installation in those areas of the world where track labour costs are relatively high, and machines are now available to drive some of the more widely-used fastening types.

25.5 Rails

The flat bottom, or Vignole, rail is now an almost universal standard so that the obsolescent bull head rail of past British practice need not be developed here.

Generally, rail sections or weights are derived from progres- sive experience, not because of analytical difficulties but because of inadequate quantified knowledge. of what conditions of loading and support actually occur.

A simple rough guide to appropriate rail weight in kilograms per metre is to multiply the axle load in tonnes by 2. However, it is necessary to make allowance for a speed factor and the following formula given by Schramm does this:

10 600 Rail weight in kilograms per metre = 156 - - (Aa + 67) (25.1)

where A =static axle load in tonnes and a = the speed factor. The speed factor is still under critical review but it can be evaluated by three equations which are widely accepted for practical use:

a=I+(V/30000) up to 1 0 km/h (25.2)

a= I +(4.5V/lW)-(I.SV/lO’) up to 140km/h (25.3)

a = I . I8 + (0.706 V/IO’) over 140 km/h (25.4)

From the above expressions, Table 25.2 has been produced. The figures give an indication of appropriate weights within f 15%.

British Standard specifications include rails from 25 to 56.5 kg/m; in Europe rails up to 60 kg/m are used and up to 70 kg/m in the US.

Table 26.2 Approximate rail weights, in kilograms per metre

Static Speed axle (kmfi) weight (1) 50 100 140 160 200

IS 28 34 36 37 39 20 36 42 44 46 49 25 44 50 52 54 58 30 50 56 59 61 65 35 57 61 65 67 10

P

+I I- =

2.75 -1

A1 2.75

49 t 1

Figure 25.6 Sections of British Rail types 110A and 11 3A and fishplate (all dimensions in millimetres)

The present standard in Britain is the 56.5 kg/m (BS I13A) rail, adapted from the earlier British standard 109 Ib/yd rail and its successor BS I IOA section. Until relatively recently in Europe the standard section was the UIC 54 kg/m rail, but currently an increasing proportion of main line track is being constructed using UIC 60 kg/m section. In the USSR main line, heavy duty tracks incorporate 75 kg/m rail sections.

Table 25.2 relates to a representative sleeper spacing of 630mm. If the spacing is wider than this, and until recently British practice utilized a sleeper spacing of 750 mm, the stress due to bending moment may be up to 9% greater, but in any case the occurrence of three loose sleepers can put up rail bending stress by 100% as can a heavy wheel flat at 30 km/h. At rail ends a 12 mm dipped joint can, with an unsprung mass of the order of 20% of the static load at a speed of 160 km/h, create a dynamic increment of load equal to the static load. Since the great majority of rail breaks occur at rail ends it can be stated that the rail weight selected must take into account the unsprung masses on the heavier axles and also the state of maintenance of joints which can be realized.

The weight of rail chosen has an influence on the shear loading of the subsoil. According to Eisenmann increasing the rail weight from 48 to 68 kg/m diminishes shear stress by 20%.

As rail weights increase, the breadth of the rail foot increases so that changing to a heavier-weight rail will generally involve changing the baseplates or, where cast-in inserts are used, respacing the inserts, unless the new rail is limited to new sleepers. Similarly, the administration of permanent way stocks is simplified, and the tied-up capital reduced, if the range of rail sections in use is limited.

The subsurface Hertzian stresses arising from wheel to rail contact must be very carefully considered, in view of their

Page 11: Civil engineering - Railways

Rails 25/11

Table 25.3

Country Max. axle load Rail section Max. speed Rail steel grade used ( 0 (kg/ml Straight track Curves

Britain Europe us

26 22.5 28

56.4 200 Normal 60 200 Wear-resist. 68 120-1 30 Wear-resist.

Wear-resist. Premium Premium

relationship with wheel load, wheel size and tensile strength of the rail steel. The Hertzian contact stresses are directly related to the square root of the wheel load and inversely related to the square root of the wheel radius. The nominal shape of the rail head and wheel tread profiles and the progressive wear of these two profiles in service. also influence the actual wheel-rail contact area and, hence, the Hertzian contact stresses. The maximum level of the Hertzian contact stress normally occurs a few millimetres below the contacting surfaces, and shelling and similar subsurface fatigue failures can develop if the shear stress in this contact zone exceeds about 50% of the ultimate tensile strength of the rail steel. Under conditions of excessive stressing, complete collapse of the rail head can occur.

The principal rail specifications in international use are BSI I of the British Standards Institution, UIC 860-0 of the Union Internationale des Chemins de Fer (UIC) and the Munual of the American Railway Engineering Association (AREA). A norm for railway rails (IS0 5003) has also been published by the International Standards Organization (ISO).

The most commonly used rail steels are defined in the above standard specifications and can be classified as follows:

( I ) Normal grades, typically of 680N/mm2 minimum UTS as per BS 1 I normal grade and UIC 860-0 grade 70.

(2) Wear resisting grades, typically of 880 N/mm2 minimum UTS as per BS 1 I wear resisting grades A and B, UIC 860 grades 90A and 90B, AREA standard carbon grade.

(3) Premium high strength grade, typically of 1080 N/mm2 minimum UTS.

The premium high-strength rail grades are still the subject of much research and development, and are briefly referred to in only one specification - AREA.

These premium grade rails are produced either by the use of alloy steels, generally about I % chromium and in some cases with micro-alloying additions of vanadium, molybdenum or niobium, or by the heat treatment of wear-resisting grade rails, e.g. BS wear resisting grade A. UIC 860 grade 90A, or AREA standard carbon grade. The heat treatment may consist of either full section hardening or localized head hardening only.

The rail steel grade selected for a particular track is dependent on various factors including track design, traffic and operating conditions, standards of maintenance and economic factors, etc.

Table 25.3 illustrates the different optimum strategies selected by different railroads. It is common practice to utilize a higher- strength, more wear-resistant. rail steel grade in tight curves, and a less expensive grade in straight track.

Broad recommendations for the selection of rail steel grade based on track curvature and traffic intensity are outlined in UIC Code 721-R.

A special grade of rail steel utilized throughout the world, albeit in relatively small quantities, is austenitic manganese steel (12-16% Mn) which is usually used in heavily trafficked tur- nouts, switches and crossings. Many crossing vees (frogs) are produced as austenitic manganese castings. Rolled austenitic manganese rails are produced in Britain in relatively small quantities being used in the fabrication of turnouts and S and C work, and occasionally in curved track. Austenitic manganese

steel surface hardens rapidly in service under stress and impact, and develops high wear resistance. However, it is expensive, needs great care in machining to avoid the risk of fatigue crack initiation and can only be welded to similar steel by normal rail welding techniques. Its higher thermal coefficient of linear expansion also produces manufacturing problems and service use limitations, but rolled austenitic manganese rails have been successfully welded and used in the relatively constant tempera- ture conditions of underground railways.

Experimental work continues in the evaluation of more exotic and expensive rail steel chemistries for special applications, e.g. bainitic steels.

Rail joints are either suspended or supported. Joints are also square, i.e. opposite each other, or staggered by up to half the rail length. In some administrations, rail joints are square on the straight and staggered on the curves. Rail and fishplate sections need to be considered together in selecting a rail section, since if the ratio of the f, of the fishplate is much below 25% of the fr., of the rail, broken fishplates and battered rail ends are likely to have a high incidence.

25.5.1 Rail failures It is necessary in any railway system that a record should be kept of all cracked and broken rails removed from the track. In addition, the cause of failure must be noted in order to monitor any specific problems which may be developing. This is camed out with the use of a standard reporting form which gives details of track and conditions as well as the type of defect. This information is fed into a computer and frequent monitoring of the data gives any developing trends.

Whilst this latter information gives details of rails removed, it does not give any indication of those defects remaining in the track under observation. This information comes from the normal regular examination of the track which is carried out by means of an ultrasonic rail flaw detection train and also by hand-held ultrasonic rail flaw detectors used by pedestrian operators.

The ultrasonic test train is normally a self-propelled unit consisting of two vehicles. It operates at speeds up to 30 km/h and uses a series of probes which are applied to the rail head either in the form of sliding probes or wheel probes. The data from these probes are partially reduced by an on-board com- puter and the resulting information is stored on magnetic tape for subsequent off-line analysis. The defects detected by this system are sent to the appropriate maintenance engineers for action depending on the type of defect.

In addition to the train, hand-held ultrasonic units are used to carry out work in areas not covered by the test train and also to examine, in greater detail, defects which have been picked up by the test train but which require more detailed study. In addition, the hand units are also used for monitoring defects which are allowed to remain in track until such time as they can be repaired or removed.

Ultrasonic testing of rails is carried out at a frequency determined by the types and speeds of traffic carried. It ranges

Page 12: Civil engineering - Railways

I 2511 2 Railways

from 6 months to alternate years for some of -the lightly used branch lines.

In addition to this routine testing, other specialized tests are carried out by both the test train and the hand operators which include gauge measurement, crack size estimation in special cases and weld testing.

25.6 Curved track

The main curves of the railway are nominally of constant radius, i.e. circular curves; curves made up of two or more circular curves of different radii curving in the same direction are called compound curves. Straights are generally and desirably con- nected to circular curves by transition curves of progressively vaqing radii; and adjoining circular curves of different radii are commonly joined together in a similar way if the difference of radii exceeds about 10%. Two adjoining circular curves curving in opposite directions comprise a reverse curve, and here, whatever the radius, the presence of connecting transitions is relatively more important than with circular or compound curves.

For practical purposes the cubic parabola y = k x 3 gives a uniform change of curvature between tangent point on the straight and tangent point on the curve, or between the tangent points of two curves, and is the most used form of transition curve. The versines, measured on half-chord overlapping chords along the transition, change with linear uniformity from zero to R although it is usual to smooth out the rate of increase and decrease at the start and end of the transition by putting on about one-sixth of the rate of the first versine at the zero station and reduce the increment at the final transition station to about five-sixths of the half-chord rate of increase. Versines are conveniently measured in millimetres.

The geometrical relation between a circular curve and a transition curve tangenting on to both the straight and the circular curve involves the moving inwards along a diameter normal to the straight of the circular curve by an amount termed the ‘shift’. The transition curve bisects the shift at its midpoint measured along the straight tangent line and the offset from that line to the tangent point of the transition and circular curve is 4 times the shift or 8 times the offset at the mid-transition point. It follows that where no transition exists or where it is insufficient in length the institution or extension of a transition can be done only by sharpening the radius of the circular curve concerned or moving the tangent straight away from the curve, though this may be worthwhile since any transition is better than none.

The length of a transition curve is determined primarily by what is judged to be an acceptable rate of change of cant or cant deficiency. For standard gauge plain track a desirable rate may be 35mm/s, with a maximum of, say, 55mm/s to secure passenger comfort. In switches and crossings a rate as high as 80 mm/s may be applied but a good standard of switch and lead design is desirable for this rate of loss or gain of cant or cant deficiency.

Some limiting cant and cant deficiency values observed in British practice on a 1.432 m gauge are listed at top right.

Wherever space permits, curve design should be based on the desirable rate of change of cant or deficiency of 35 mm/s.

The amount of cant applied to a track depends upon con- sideration of the following factors:

( I ) The line speed limit, i.e. the maximum speed at which traffic is allowed to run on a line or branch or section of a line or branch. This limit is usually fixed with reference to the value and distribution of permanent speed restrictions on the line or branch, or section thereof, involved.

~

Maximum cant: on curved track at station platforms maximum cant gradient deficiency on plain line, CWR deficiency on plain line, jointed track deficiency on switches and crossings welded into CWR on through line on turnout with negative cant on turnout at switch toes

deficiency on switches and crossings in jointed track .

on through line on turnout with negative cant on turnout at switch toes

Maximum rate of change of cant on plain line on switches and crossings

on plain line on switches and crossings

on plain line on switches and crossings (inclined design) on switches and crossings (vertical design)

Maximum rate of change of cant deficiency

Maximum rate of change of cant deficiency

~ _ _

I50 mm I10 mm I in 400 I10 mm 90 mm

I10 mm 90 mm 90 mm 125 mm

90 mm 90 mm 90 mm 125 mm

55 mm/s 55 mm/s

55 mm/s 55 mm/s

55 mm/s 55 mm/s 80 mm/s

(2) The proximity of permanent speed restrictions, junctions, stopping places, etc.

(3) Track gradients which may cause a reduction in the speed of freight or slow-moving passenger trains without having an appreciable effect on the speed of fast trains.

(4) The relative importance of the various types of traffic.

Generally, where fast and slow trains run on the same lines, an intermediate speed is selected to fix the cant. In this situation it may exceptionally be necessary to limit the cant and therefore the maximum speed to prevent surface damage to the low rail by heavy axles on slow-moving freight trains.

Each line of a double line should be separately assessed. In exposed locations subject to high winds it may be desirable to limit cant to below the 150 mm maximum.

Normally, cant or cant deficiency is uniformly gained or lost within the length of a transition curve or, where there is no transition curve, as may occur in switches and crossings, over the length of the virtual transition, which for practical purposes is taken as the shortest distance between the centres of bogies of coaching stock using the line. If the desired cant cannot be put on within this length observing a maximum cant gradient of I in 400, the cant loss or gain is continued on to the circular curve. The 1 in 400 cant gradient mentioned relates to axle twist derailment possibilities, especially where four-wheeled vehicles are concerned.

The maximum permissible speed on circular curves appropri- ate to the determination of permanent speed restrictions may, for standard gauge railways, be obtained from the following expressions:

Equilibrium (or theoretical) cant= E= 11.82(Vef/R) mm Equilibrium speed = Ve=0.29J(RE) km/h

Maximum speed = Vm = 0.29JR (E+ D ) km/h

where R = radius in metres, E=cant, which may be either actual cant or equilibrium cant but in practice the difference is not

Page 13: Civil engineering - Railways

Curved track 25/13

metres. Thus, what is described in American practice as a 10" curve would be described in Europe as a curve of 175 m radius.

Main railway curves are initially set out by theodolite gener- ally on the basis that equal chords are subtended by equal angles but informal setting out by an offset from a tangent followed by the use of overlapping chords of convenient length using the versine appropriate to the radius can give a degree of accuracy sufficient for less important curves. A selection of curve formu- lae covering most calculations for the design or setting out of railway circular curves is set out in Table 25.4.

It is desirable to keep rail joints more or less square, or at a constant stagger where this is preferred, on curves by inserting short rails in the inner rail of curved track. The difference in rail length, D, for standard gauge and for 18.3 m rails is given by D =.(27.45/radius in metres) m. Alternatively, the approximate difference in length can be obtained from the formula D = 3 ver- sine. It is normal to take a standard range of short rails from the makers and for 18.3 m rails, these are 18.25, 18.20 and 18.15 m.

The precise alignment of curves is vital to a smooth ride, stability of the track geometry and minimizing track wear. There are several alternative methods of adjusting railway curves as a maintenance operation but all are based on versine measurements and relate, either to a smoothing or averaging approach, in which the differences between a limited number of adjacent versines are adjusted to give a fairly uniform rate of change in transitions or to a fairly uniform value on circular curves; or to a design lining approach in which the whole of the versines of a curve are adjusted as one revision operation to give a precise rate of increase or decrease in transitions and a strictly uniform value on the circular curve portion, as far as clearances from structures, etc. will permit. It is generally convenient to use smoothing or local adjustment techniques after a curve has been aligned on a design basis. It is also normal practice to set markers or monuments or pegs in or beside the tracks when design lining is carried out.

Curve realignment can be based on manual measurement of versines or with less accuracy on the versine measurements of a track geometry recording car or of a track lining machine.

The side and interbody clearances shown on the diagram contained in the Department's Requirements (see Figure 25.15) relate to straight track and may need to be augmented on curved track for end throw or centre throw of vehicles, which are generally of the same magnitude.

Centre throw= C=Bz/8R End throw=E=(Lz- EZ)/8R

likely to be significant, though the distinction has to be kept in mind in certain circumstances, and D = maximum allowable cant deficiency in millimetres.

Desirable lengths of transition curves can be derived from the greater of the two values obtained from:

Length= L = 0.0075EVm m or L=O.O075DVmm

where E=cant in millimetres, D=deficiency of cant in milli- metres and Vm= maximum permissible speed in kilometres per hour.

If space is limited, the length of the transition may be reduced to two-thirds L subject to a minimum cant or cant deficiency gradient of I in 400. On compound curves to be traversed at a uniform speed, the

desirable length is obtained from the greater of the two follow- ing expressions:

L = 0.0075(E, - EJVm m or L=0.0075(0, - D3Vm m

where E, and D, are the cant and cant deficiency conditions for one curve and E, and D, are the similar values for the other

Similarly, on reverse curves the transition lengths are given curve.

by:

L = 0.0075(EI + E,) Vm m or L=0.0075(D,+DJVmm

It should be noted that in using the above formulae the constants used have reference to a standard gauge, to an assumed height of the centre of gravity of vehicles of about 1.5m and a subjective passenger comfort assessment of the tolerable rate of change of cant or cant deficiency. To this extent the values are arbitrary rather than absolute and refer to standard gauge. Further qualifications are that the springing of vehicles may be such as to produce excessive lean under cant deficiency running to encroach significantly on side clearances or to diminish passenger comfort, whilst if the centre of gravity of a vehicle is higher or lower than that assumed the maximum permissible speed is affected in inverse ratio, so that certain vehicles may be permitted to run at a higher speed than other vehicles.

The versine or middle ordinate of a chord on to a curve is proportional to the curvature and is the basis of all railway curve alignment, checking and adjqstment. Its value as deter- mined from triangular analysis is given b y

2R={(C/2),/V)+ V (25.5)

where R = radius of a curve, C = length of chord on which the versine is measured, and V= the versine, but since the value of V is very small in relation to R in railway situations, the final V of the expression may be disregarded so that for both field measurements and calculation purposes:

V=C/8R (25.6)

In Britain and on the Continent, railway curvature is usually described by the length of the radius measured in metres. The American practice is to describe a curve by the angle subtended at the centre of the curve by a chord of 30.48 m. For railway work it is sufficient in transposing degree units into radius units to divide 1746 by the degree of the curve to give the radius in

where E= wheelbase or bogie centres, L = length of vehicle, and R = radius.

To this increase of effective body width on curved track must be added a further allowance due to the tilting of the vehicle to the low side on canted track. In Britain, the loss of side clearance at the vehicle cornice is about 2.25 times the actual cant.

It is general practice slightly to widen the track on very sharp curves to allow all vehicles, especially locomotives with long rigid wheelbases, to pass round such curves without straining the track. The normal British practice is:

Curves over 200 m radius widened to 1435 gauge 200 10 I10 m radius widened to 1439 gauge I10 to 70 m radius widened to 1451 gauge

Appropriate values of gauge widening for a given track radius depend on free play of wheelsets, .length of half wheel flange below rail level and rigid wheelbase of the critical vehicle.

In 'the UK it is the Department of Transport's enjoined practice to install check rails on curves of 200 m or less radius.

Page 14: Civil engineering - Railways

2511 4 Railways

Table 26.4 Curve formulae

Given Sought Formula Given Sought Formula

E. M C E, R C E, T C E. a C M. T C M. R C M , a C R. T C R. a C T. a C R D a , L D C. M E C. a E M . a E R. C E R, M E R. T E R. a E T. C E T , M E T , a E R. a E a, D L C. E M C. a M E, a M R. C M R. E M R. T M R. a M T, C M T, E M

c=ZMJi (E+ M)/(E- M)} C = 2R J{ E(2R+ E)}/ (R+ E) C=2T(T’- E’)/(T’+ E’) C = 2E {sin (u/2)}/{ex sec (a/2)} O=C- 2TC+4M2C+ 8M’T C=2J{M(2R- M)}

C = 2 TR/J( T‘ + R ’) C = 2R sin (42) C = 2Tcos (a/2) sin ( D / 2 ) = 50/R D= 100a/L approx. E=M(C+4M’)/(C-4Mz) E= C{ex sec (u/2)}/2 sin (a/2) E= M/cos ( 4 2 ) E= R’/J((R+ C/2)(R- C/2)} E= RM/ (R- M) E= J(T’+ R’) - R E= R ex sec (a/2) E= TJ ( (2T- C)/(2T+ C)} O = E’+ E’M- ET’+ MT’

c= 2Mcot (44)

E= Ttan(a/4) E= R( I -cos (a/2)/cos (a/2) L = 100a/D approx.

M= (C/2)tan (a/4) M = E cos (a/2) M= R - J { ( R + C/2)(R - C/2)) M= RE/(R+E) M= R - ( Rz/J( T’ + R’)} M = R vers (a/2) M = ( C / W V T - C)/(2T+ C))

0 = M’ + M’E + ( MC’/4) - (C’E/4)

M=E(T’-E’)/(T’+ E’)

T, a M D R C, E R C. M R C, a R E, a R M. E R M.. a R T , C R T , E R T. M R T, a R C. E T C. M T C. a T E, a T M. E T M . a T R. C T R. E T R. M T R. a T D. L a M . C a M. E a R. C a R. E a R. M a R. T a T , C a T, E a R. a L

M = Tcot (a/2) vers (a/2) R= 50/sin ( 0 / 2 ) O = RI+ R2{(4E?-C) /8E) - (RC/4) - (CE/8) R= {(M + (C/2)’)/2M R= C/2 sin ( 4 2 ) R = E/ex sec (a/2) R= EM/(E- M) R = M/vers ( 4 2 ) R=CT/J{(ZT+ C)(2T- C)} R={(T+ E)(T-E)}/2E O= R’- R’(M2+T’)/2M+ RT’- MT’/2 R= Tcot (a/2) O=2T1- T’C- 2TE’- CE’ T=C(Cz+4M’)/2(C’-4Mz) T= C/( 2 cos(a/2)} T= Ecot(a/4) T=EJi(E+ M)@- M)) T= M( tan (a/2)}/{vers (a/2)} T= CR/2J{(R+ C/2)(R- C/2)} T=J{E(ZR+ E)} T= RJ{M(ZR-M)J/(R-M) T= R tan (a/2) a= DL/l00 approx. tan (a/4) = 2M/C cos (a/2) = M/E sin (a/2)= C/2R ex sec (a/2) = E/R vers (a/2) = M / R tan (a/2) = T / R cos (a/2) = C/2T tan (a/4) = E/T L= 0.01 7 453 292 5Ra

D= k g m O f CUNC

R - Radius T=Tangent i = Ext. angle - antral angle L* Length of C U N ~

M= Mid-ordinate

C= Long chord E= External distance

Check rails_are also sometimes installed in Britain on flatter curves to diminish side cutting of the high rail or as a protection against inadvertance or mishap at the bottom of a gradient. Wide flangeway check rails or guard rails may also be installed to protect bridge supports or girders against being struck by derailed vehicles. In the UK this provision is a Department of Transport Requirement.

25.7 Welded track

About two-thirds of the on-track maintenance work put into jointed permanent way is at or adjoining the rail joints and the great majority of rail failures occur at or near fishplated joints. For these and other reasons the tendency today is to use long welded or continuously welded rails.

This procedure entails the elastic containment of the longitu- dinal expansion and contraction stresses arising in the rails as a consequence of variation in the rail temperature with reference

Nore: ex ICE A== A - I - ( I -cos A)/cos A andvcrs A = I -cos A

to the temperature at which the rails were fastened to the sleepers. If, as is usual, the rails are fastened down on installa- tion within a prescribed narrow temperature range situated at or a little above the mean of the annual rail temperature range in a normal or stress-free condition, then the amount of tension in winter and compression in summer is limited to what is judged to give an optimum compromise between a cold season hazard of broken rails and a hot season hazard of track buckles.

The installation and maintenance of welded rail track need more technical insight and attention than ordinary track. The lateral strength of the track depends upon three main elements: ( I ) the f, of the two rails; (2) the framework stiffness of the assembled rails and sleepers as developed by the fastenings; and (3) the frictional loading of the ballast on the sides, ends and bottoms of the sleepers. The resistance of the track to vertical buckling, which generally occurs in combination with, or as a trigger to, lateral buckling, is determined mainly by the total weight of the track, and in this context concrete through-type sleepers show a considerable advantage. In a fully-ballasted

Page 15: Civil engineering - Railways

pnscribed limits (21 to 2 7 T for the UK). In th& way it is possible to lay welded track all the year round. The pull requirad to &tend a 56kg/m rail is of the order of 1.6tyC. The tensots have a Capacity of about 70 t.

Figun 264 Hydraulic rail sressec This h.. a M t pu(l md 380-rnrn stroke. For pus hi^ action, the rail clamps are turned through 180'. (Courtesy: Pennaquip Co. Ltd)

Welded rails are not normalfy laid in Europe in curves with a lesser radius than 600m. Long wIdcd rails arc made up by ilash butt welding of atandard rail hgths into welded rails of MO to 400m kngthin depot and wcldcdinto continuous wd&d rails by Thermit WeMS, except in t6C USRwherc a mqortabk flash butt welder is appIicd to join raib in the tract.

It is normal practia in Britain and Fmnce to install sliding switches at the ends of long welded rails but in t h m a n y this is not done, reliance being placed on very 1&n fastening of the welded raih wtam they connect with jointed traclr. The advantages of wdded track include an extension of rail

lives by about a ttu.d, a reduction of on-track maintenance by about half, a dramatic reduction of rail b r c a b d L running spccds, less damage to the formation, increased sleeper lives, i m p r 0 w ; d ride comfort, a duction oftnction energy of up to 5%. and a reduction in train noise. IneEect. welded rails.

t8e long-team overall cost of permanent way.

~ W ~ s l a p e r s a n d a d f - t s o p i a n i a e f-arc awnplsmentruy toeach oteer inextkadiog the life and redil&lg

25.8.1 sn#chLs The ha4 of a switch is the point from whi& it is fme to move. Eprly switch dcaigns had a loose heel fenned by a &-tight fishplated joint but this type is now Mdy 4 ortdnidc of sidings. It is now the gmcnd practice for tha-hed dthc switch to be formed by abhckhstwtea s w i t C h d P n d S iswellbddndthe heel. The length of the switch planing* r8t bead of tbc rail variesbetweenabout ldand I I mandnnwt&wayaduhistra- oiom have a range oftwub eight Stsndardpitcbes to meet the requirements of short leads in depots pad various spqeds of -on the runninglines.

o r i g i n a l l y , o r d i n o r y o r s t r a i g h t p ~ ~ s w i t c h ~ w a s universally applied but during the last few duxdescurvcd planing, in which the switch rail is bent strrtially wkiW being planed on ode sidc of= head, has becomr, general. In $his way t h c c u r w ~ g t 4 u o u g h the lead isoa*l iaQtdte~switch tip. A merit practice is to apply a larger radius to t h e m of the switch t&n is applied to the switch beyond tbeslaofthe planingto gin a more robust switch tip a r i t l r ~ h i t c ~ t m g k .

258.2 Crossings are described by the angle at tbe crowing nose. In wntincntd Jkope it is common to state this in &qpew but over the Englisb-#paking world the angle is usually deoaibal as 1 in N. Howerer, the an& of a crowing cxprclcrod &? 1 in N varies slightly d i n g to tbe mepnUing convention adopted. Thus if 1 in 8 is druined by measuring 8 units plogll@cccntr&s for I unit of s;rpaetrical spread normal to t8s ElALtrclina (antreline Illtpsun). &en measuring 8 units along 0110 leg of the we for a spradof 1 unit measured at right angles btbat kg((ri0btangle m a n n c ) ~ give 1 in 7969. whilst if8 unita islacasuad along each leg to@= a spread of 1 unit the croaaingd&wiU be I in 8.016 (isoccelts measure). It is therefore ncccsmy for any railway to have t specific mode of mcaming crossin@ w k h is known to (111 -lying manufacturers of q. or to state tsaangkmdegras.

In the UK l b d diamond crorsiags am limited by Minirtry requiremsslt to be not flatter than 1 in 7.5. In m n h t a l Europe 1 in 10isthepmallimit.Whmalinecraringflattcrtb.nthe allowed limit is F , the points of the diamond crossings arc consteudcd as slachcs and have to beset to suit tha train movematdesired.

There ia no official &nit on the angle of -on croahgs but 1 in 28 is a b thcflattcst an& at which thecrosoingwgthas sufficient robustness. Crossings arc either made up from rails or arc cast in 12 to 14% steel. Butlt-up crossings have the inhmnt limitations of boltcd a s s e m b h and of rcQGllt years it has becomegeneral practicein the UKtondd thevrtrsction and Huck4askn the wings. In general. it is Pefmsd p d to have cast amsings for high-speed or heavily worked l h s rising built-up d g s for kss exacting duty. It is also prcfarcd to usccastcrossingsforanglcstlattcrthanabout 1 in20.InthcW it is common practice for the nose section of the crossing to be. a manganese casting to which ordinary rail section wine are attached to form what is known as a rail bound cast crossing.

Page 16: Civil engineering - Railways
Page 17: Civil engineering - Railways

alignment and * I

*-

Figure 26.11 Sectin of slab track laid in tunnel (to increase haadroom for alactrifiition, and to reduce maintenance costs)

c ,-

provided by the introdudioa or removal of hcight-adjuaing pads located under basepates mounted on the units.

Page 18: Civil engineering - Railways

25/18 Railways

Although these systems place a greater need on period maintenance than do the more cmtia\rour forms of slab track, the d s e and lower cmt of adjwthg the track f&wing major

of the slab mon than aompensafc for thje extm dfort m certain locafisesi Ia streh locations, w h e the stabiiity of slab track& nequiradtdlow Mgh-sped twffk: or themre isf'ieduced d s a m ~ ~ ~ but where id a &tang powitbility of si@&ant movamsd of the back, e.g. as a tosdr df mawWpake, this fonn of dab e& cowtruction 'hgM<rnny advsablgca over 0 t h

Ertirnateo of the limit of speed at which tzaiRs can MI on conventional tracks vary between about 250 and 400 km/& The h i t s tltat u ~ p l e e e d on speeds dftraigs by sleb m c k arelargely teoSe dmcuracyof m c ~ ~ u n m c l l ~ in or&r to detba ratd mrect m i s a l i ~ pt the coastrbchn stpga. K the call for higher speeds continues to be made, it may oaly be pwibie to meet it by *g Ltabtrack.

Similarly, if the need to provide sinuous riailwpy mutes through highly congested areas continues, the use of slab track should allow &is tb Ire b e using the &ea& amount d spacc and w&i~ thebast o~ls&&int on &ain speeds.

25.10 Track maintenance and renewal

Gencdy, the p k r the strength and iahennt stability of the design of tlsb track canstructian and its foundation, the km

demanding is the dntenance task. The stiffness of the rail, the shper spacing end the depth of ballast BW important f&ors af&aling the cost of maintenance. The evolution of the aatomatic levelling lining and tamping

ma&nein t~196os(Fignpc25.12)changadthe~pa~ern of track maintenance. The original manual method of maintan- ance, using beater picks, was to drive individual pieces of ballast under the s l w tb &ain the nquircd rail kvtE aM1 hnness of sapport. A iater &ve?oopnent, pimeemd in France, was to jack the skeper and spread small stone chlppings over the bearing a m . This system wes known as meilwtFcd &owl pucking (Msp) and was efitrtlmly SUOOOSSN in producing gmd track

A ncsnt development has been the laachaeizationhf this process using a machine known as a 'Stoneblower'. This d i n e automrrtically mcamm the voids under the s h p e ~ ~ and, using pophisticatad ekottonic controls, pneumatically in- jects the coned quantity of stone to ptoduce the amect longitadinal. vuticrl track profila, k prototype machine using this process has recently boen can91matd (Figure 2'5.13). Deve- lopment work on this prinapk has shown that track maintained bythissystarn on~de~orcllssac.appto.im~lyonsquaner of the nte of traek maiMeined by eonvmtional mnphg. Very cansidora~ srrviagr am the&- possible in maintenance costs by u s i g this new tececkwque.

otker -inn, llsGd in &tion with tamping end stone- blowing are ballast-regulating machines for positioning ballast

a l k u g b expensive in labour. .

Page 19: Civil engineering - Railways

Track maintenance and mwwd 25kl9

shortw.ve abcNppIlolu * ot;U)to180mfrcqucncywithadeptb

hundred. Recxnt rcsclvch has highlightad tk &&porWn& of maintaining the CO& wheel-rail interaction involving both

- 1

F@uro 28.13 Roeotype ’Stdneblower‘ fa pecking ard a l i i track. (Courreqc Plasser (G6) Ltd)

Page 20: Civil engineering - Railways
Page 21: Civil engineering - Railways

Railway structures 25/21

Overline bridges and elevated roads alongside railways must be provided with parapets complying with Department of Transport Technical Memorandum (Bridges) No. BE 5 . These parapets are intended to protect pedestrians and/or to contain errant vehicles and prevent them from falling on to the railway; they may also be required to be solid, to prevent splash, reduce noise or screen railway electrification equipment.

For bridges carrying roads, such as motorways, from which pedestrians, animals and pedal cycles are excluded by order, the minimum height of parapet above the adjoining paved surface must be 1.250 m. The lower 600 mm of the parapet should have a mesh or solid infill panel, which may be mounted outside any longitudinal members.

For bridges carrying all-purpose roads and footbridges, the parapet is to have a traffic face which is smooth and without hand- or footholds. The minimum height of parapet above the adjoining paved surface must be 1.500m. For bridges used frequently by equestrians, the height must be at least 1.800m.

If a bridge over a railway which is electrified on the overhead system has a parapet with a plinth on its outer face, access must be denied to that plinth. Any parapet more than 100 mm thick is to be surmounted by a ‘steeple-shaped’ coping (i.e. with steep sides meeting at the top at an acute angle).

At locations where the likelihood of vehicle impact with the parapet and consequential damage resulting from its penetra- tion outweigh the hazards resulting from the containment and redirection of errant vehicles within the traffic scheme, ‘high containment’ parapets must be provided.

Pipelines carrying liquids or gases over the railway must be incorporated in a bridge constructed for another purpose or be supported by a purpose-designed beam or service bridge. Such a bridge should preferably span the railway without intermediate supports. Consideration may be given to a free-standing design of pipe crossing only in the case of low-pressure water mains or similar pipes conveying non-hazardous materials.

The design loadings and other criteria for both underline and overline bridges are generally as set out in BS 5400. The major railway undertakings in Britain require underline bridges to be designed and constructed by their own staff or under their direct control.

Where bridges are to be constructed under or over existing railways, special techniques are usually necessary to minimize

Clearance between kinematic envelope and railway operational

Stations should be constructed to be as fire resistant as practicable and extinguishing equipment provided for dealing with fires in station premises.

25.11.3 Bridges and viaducts Bridges and viaducts may be constructed in steel, concrete (reinforced or prestressed), brickwork or masonry. The use of other materials such as light alloys will be considered on their merits, but cast iron must not be used in any portion of the structure of a bridge carrying a railway except when subject to direct compression only. Structural timber is usually restricted to light overline bridges.

New and reconstructed bridges must be built to provide at least the mandatory clearances to the kinematic envelope (des- cribed below) as illustrated in Figure 25.15. For British Rail, this requirement gives a standard structure gauge 4.640 mm high (above rail level) and 2.340mm clear laterally from the centreline of the nearest track (when the latter is straight; additional lateral clearance is necessary alongside curved tracks).

Underline bridges must be provided with robust kerbs as part of the bridge structure and extending to a height of at least 305 mm above rail level to contain the wheels of any derailed vehicle. Such bridges must provide for a safe lineside walkway, with a substantial parapet or railing not less than 1.250m in height above the walkway (unless the main girders themselves provide a sufficient parapet). On bridges and viaducts which are longer than 40 m or where visibility of approaching trains is limited, it may be necessary to incorporate recesses in the parapet design to afford the refuges described below.

Bridges and other structures built over or immediately adjac- ent to railway lines must be protected against the consequences of their supports being struck by railway vehicles in the event of a derailment. Such supports should be located as far from the tracks as practicable. If they can be kept 4.5 m or more clear of the nearest rail, there will normally be no requirement to design for impact forces. Where this clearance cannot be achieved, the supports must be designed with a degree of robustness and continuity to minimize the etTects of contact by a derailed vehicle and to withstand nominal impact forces.

Nearest isolated length but excluding masts carrying overhead line equipment on electrified railways. Nearest face of all other structures including masts carrying overhead line equipment on electrified railways.

J

Standard structure gauge\ 1 I structures above cantrail level.

Normal - 250. Minimum - 1GQ. On railways with existing or

’proposed overhead electrification the requirements for electrical

. clearance, where these are greater, shall apply

Recess for signal wires and cables if required

This space to be kept clear as far -. as possible of permanent obstructions

- Standard dimension between structures for double line standard gauge railway

Figure 25.15 and kinematic load gauge

Department of Transport -standard structure gauge

Page 22: Civil engineering - Railways

25/22 Railways

the interruption to the normal operation of such railways; the requirements of these techniques may significantly influence not only the temporary works but also the design of the permanent works. I t is usually more economic to ensure that work adjacent to running lines, particularly excavation, is located sufficiently far away from them to avoid the necessity for the imposition of speed restrictions on railway traffic. The design and construc- tion of all bridges and viaducts should also be such as to minimize future maintenance on grounds of both economy and avoidance of interference with railway traffic. Provision should be made to ensure that all parts of bridges are accessible for regular inspection and maintenance and that all exposed steel can be painted. Underline bridges should be designed to carry normal ballasted track.

25.1 1.4 Clearances The structural and electrical clearances (to be provided on new lines and on existing railways where new structures are built or existing structures are modified or where clearances are other- wise altered) are specified in the revised part of the above- mentioned Department of Transport Requirements published in 1977.

Structural clearances are related to the ‘kinematic envelope’ of the stock which will use the line and are illustrated in Figure 25.14 in respect of lines carrying trains at speeds up to 200 km/h; that figure is based for the purpose of illustration on the kinematic envelope applicable to British Rail vehicles.

The kinematic envelope is derived from the static load gauge as follows: ( I ) the maximum permitted cross-sectional dimen- sions of vehicles and their loads when at rest and located centrally on straight and level track; (2) the static load gauge must be enlarged to allow for the maximum possible displace- ment of the vehicles when at rest or in motion, with respect to the rails, taking account of their suspension characteristics and making allowance for maximum permitted tolerances in the manufacture and maintenance of the vehicles, including wear; and (3) the resultant kinematic load gauge must then be further enlarged to take account of the maximum permitted tolerances in gauge, alignment, top- and cross-level of track including the effects of wear. The kinematic envelope so derived thus contains the full cross-section of vehicles and their loads under any permissible condition of operation and maintenance of both vehicles and of track. It does not, however, allow for the end- throw and centre-throw of vehicles on curved track, and addi- tional allowance for these must be made as appropriate.

Electrical clearances are dependent upon the nominal voltage of the overhead conductor system and upon whether the cate- gory of clearance is to be normal, reduced or special reduced. They must include provision for tolerances in the installation and maintenance of the overhead equipment and of the track limiting values of the vertical clearance for normal, reduced and special reduced clearance conditions between the underside of a structure and the kinematic load gauge shown diagrammatically in Figure 25.15 (for 25 kV a.c.). Also shown are the corre- sponding clearances between the undersides of structures and the designed rail level, based on the normal British Rail static load gauge. It will be noted that the standard structure gauge on British Rail allows for overhead electrification at voltages up to 25 kV, albeit with ‘close tolerances’; the vertical distance from rail level to the undersides of structures should ideally be increased to 4.780m if this can be achieved with reasonable economy, and further increased where a bridge is adjacent to a level crossing, over which the overhead equipment has to be raised to give 5.600 m clearance over road levels.

25.1 1.5 Refuges Refuges are to be provided in all tunnels and also on long bridges and viaducts and where the railway is enclosed by lineside structures unless lateral clearances over a continuous length of 40 m or more are such that staff can stand in safety during the passage of trains. Similarly, on embankments and in cuttings, wherever lineside clearances over a length of 40 m or more do not give safe standing room, refuge spaces are to be provided. The criteria as to what clearance allows men to stand at the lineside in safety are defined as 830mm from the kinematic envelope at its widest point for train speeds of up to 160km/h and 1.700m for train speeds between 161 and 200 km/h.

Refuges and refuge spaces should be located on both sides of the line at a spacing not exceeding 40 m, staggered to give an effective spacing of 20 m or less. Refuges must be at least 2 m high, 1.400 m wide and 700 mm deep, with their floors substan- tially at the level of the adjacent lineside walkway. Handholds, to assist men in keeping their balance during the passage of a train, are to be provided in refuges and also elsewhere if lateral clearances only marginally exceed the criteria specified in the previous paragraph.

25.12 Inspection and maintenance of structures

In the interests of safety and economy, it is essential to have up to-date and reliable information as to the current condition of all railway structures and to carry out any necessary repairs or renewals in due time.

The key to proper maintenance, therefore, lies in a system of regular routine and methodical examination by suitably trained and experienced staff in order to provide the responsible main- tenance engineer with well-founded records, for each structure, as to: ( I ) its condition; (2) its current fitness for its intended purpose; (3) its rate of deterioration; and (4) the urgency for remedial action.

I t is common practice to legislate for superficial examinations, undertaken at intervals of about I year, and less frequent detailed examinations, in which every element of the structure is carefully and thoroughly inspected at close range and the extent of any deterioration quantified. The frequency of detailed examinations will depend upon the nature, age and condition of the structure, but the interval between such examinations should rarely exceed 6 years unless there are special problems or unjustifiably high costs in providing adequate access; in the latter event, decisions as to the action to be taken following an examination should have particular regard to the length of time likely to elapse before the next one. Additional special examina- tions may be necessary after flooding, damage from impact, fire or vandalism and similar eventualities.

Proper examination depends upon adequate safe access to all parts of a structure. Suitable provision should have been made for this in the initial design by providing removable panels, walkways, fixing points for ladders or safety lines and by avoiding the creation of inaccessible spaces. Where the latter has not been done, some ‘opening-out’ should be undertaken, at least on a sampling basis. Recourse to expensive scaffolding may often be avoided by the use of mobile inspection platforms.

Examiners must compile full written reports of detailed examinations. To facilitate this, most railway undertakings use specially devised forms, which act as a checklist and encourage clear, concise and comprehensive coverage. Sketches or photo- graphs are valuable for illustrating defects. Reports must record defects in quantitative form, e.g. the loss of section (or the

Page 23: Civil engineering - Railways

Bibliography 25/23

these languages are used at UIC and ORE meetings, French being the primary procedural tongue.

Another European body which makes a significant contribu- tion to railway technical literature in its periodical bulletins, is the International Railway Congress Association (IRCA) whose administration is in Brussels.

The principal technical railway co-ordinating organization in the US is the American Railway Engineering Association (AREA) of Chicago which issues a periodical journal covering minutes of meetings, reports of special committees and recom- mendations for specifications and technical procedures. The AREA also sponsors research and development projects which are mainly progressed by the Association of American Rail- roads (AAR) at its Research Centre at Chicago. The Pan American Railway Congress is a similar but less developed organization covering the countries of South America. Much valuable railway research and development work is done in Japan and the English version of the monthly Journal of the Permanent Way Society of Japan, founded in 1958 in Tokyo, provides a comprehensive contemporary reflection of this work.

Important permanent way research centres also exist in Prague, Moscow, Belgrade and Johannesburg but the results of their activities are normally limited to domestic distribution. The chief technical and development railway work carried out in the UK is associated with the Research and Development Centre at Derby which has a considerable international repu- tation. Its reports are generally limited to internal circulation within the British Railways Board but most of its railway research projects are reported through papers and articles for the British engineering institutions, chiefly the Institution of Civil Engineers, the Institution of Electrical Engineers, the Institution of Mechanical Engineers, and the technical press. It also accepts commissions for research from-outside the British Railways Board.

The national railways of the UK, Canada, France, Germany and Japan are also associated with sponsored railway consul- tancy organizations which, whilst primarily concerned with the techniques of railway organization, also offer technical advice to clients.

Contemporary railway civil engineering practice and develop- ments in the UK and elsewhere are more to be found in papers presented to the railway division of the Institution of Civil Engineers and to the Permanent Way Institution, in the bulle- tins and journals of ORE, IRC. and the AREA and in the railway technical press of the UK, France, Germany and America, rather than in the few standard textbooks on railway engineering which are necessarily less up to date.

amount of section remaining), the extent of any displacement, the magnitude of any movement, the width, length and orien- tation of cracks, the extent of hollow-sounding brickwork, the depth of perished mortar or the degree of water percolation. Where appropriate, 'tell tales' and plumbing/levelling points should be established and readings from them recorded. In some cases, more sophisticated techniques of investigation may be called for. The objective should be to ensure that the mainten- ance engineer has readily available data as to the nature, rate and extent of the development of any defect, i.e. the way in which deterioration is occurring over a period of time by comparing a succession of reports. Thus, he is assisted in diagnosing the cause of trouble and guided in his judgement as to the urgency for remedial action.

Financial constraints may well limit the number of structures which can receive maintenance attention in any year, and it is therefore necessary to establish some kind of priority rating system for defects, to ensure that available resources are dir- ected where the need is most urgent. This may well involve some assessment of the residual strength of members. Calculations and possibly instrumental tests may be necessary to determine critical stresses; these should be based on the nature and magnitude of the loads actually having to be sustained and should have regard to the current condition of members, allowing for loss of original section, distortion and similar defects.

The nature, extent and timing of any repair will vary widely depending on the circumstances applicable in individual cases. Decisions hereon must rely heavily on the informed judgement of the experienced maintenance engineer. For repairs to be effective, it is essential that the cause of the defect is correctly diagnosed and that that cause, rather than its results, is properly dealt with. Desirably, this should be done before serious defects develop, by preventive maintenance of a stitch-in-time nature, e.g. painting of metalwork and timber, pointing of brickwork and masonry and sealing points of water percolation.

It is also a matter of professional judgement to determine when repairs are no longer economic and reconstruction is justified.

25.13 Research, development and international collaboration

The principal railway co-ordinating body in Europe is the UIC (Union Internationale des Chemins de Fer) whose headquarters is in Paris. Its primary purpose is the encouragement and development of standard railway policies and practices through- out Europe. It has a permanent secretariat but it works through committees covering the activities of most railway departments. Twenty-six nations are constituent members.

Its technical research co-ordinating arm is ORE (Office for Research and Experiments) which has its office at Utrecht. The UIC issues specifications, standards, and recommendations for railway practice to which railway administrations are expected or encouraged to adhere. The ORE is represented on all technical committees of UIC and issues reports made by work- ing parties or by specially commissioned persons of academic or professional distinction to member administrations of UIC.

The field and laboratory work of ORE is assigned to member administrations or to universities or technical schools; such work is usually progressed by an appropriate working party composed of delegates from member administrations serviced by a technical secretary from ORE. Distinguished men from industry and universities are sometimes co-opted to serve on specific working parties; UIC and ORE reports are normally issued simultaneously in English, French and German, and

Bibliography

Berridge, P. S. A. (1969) The girder bridge. Maxwell. Eisenmann, J . (1969) 'St!ess distribution in the pe'manent way due to

heavy axleloads and high speeds.' American Railway Engineering Association Proceedings.

Fastenrath, F. (1981) Railroad trark - theory and prarrice. New York. Heeler, C. L. (1979) British Railway Track. Permanent Way

Prud'homme and Bentot (1969) 'The stability of tracks laid with long Institution, London.

welded rails', International Railway Congress Association Bullerin (July 1969).

Darmstadt. Schramm, G. (1961) Permanenr way rerhnique and eronomy.

Turton, F. (1972) Railway bridge maintenance. Hutchinson, London. Department of Transport (1983) Bridge inspection guide. HMSO,

London. Department of Transport (1982) 'Design of highway bridge parapets'.

Technical memorandum (bridges) No. BE 5. HMSO, London. Institution of Civil Engineers (1984) Proreedings ofronference on work

rerhnology for the next derade at University of Nottingham.

Page 24: Civil engineering - Railways

25/24 Railways

Permanent Way Institution. Journals and reports of proceedings, list of papers and authors 1884-1976.

Ruild.oy Construction and Operution: Requirements .for Pussenger Lines and Recommendotions.for good.^ Lines (I 963 reprint). HMSO, London.

Ruiluuy construction und operurion: structural ond ekcrricul cleoronces (1977). HMSO, London.

Roiluwy Construction ond Operorion: Level Crossings ( 198 I ). HMSO, London.

Railwuy engineering and moinfenance encyrlopaerlia. Simmons Boardman, US.

Research and Development Division. British Rail and Association of American Railroads ( I 98 I ) Proceedings 0fro~ferennc.e on roil rerlinology at University of Nottingham.

British standards BS I1:1978 (Amended 1984)

BS 47:1959 (Amended 1979)

BS 64:1946 (Amended 1960)

BS 144:1973 (Amended 1974)

BS 500:1956 (Amended 1976)

BS 751:1959 (Amended 1976)

‘Specification for railway rails.’

‘Steel fishplates for bullhead and flat bottom railway rails.’

‘Steel fishbolts and nuts for railway rails.’

‘Coal tar creosote for the preservation of timber.’

‘Steel railway sleepers for flat bottom rails.’

‘Steel bearing plates for Rat bottom railway rails.’

BS 882: I983

BS 913:1973 ‘Specification for aggregates from natural sources for concrete.’

‘Wood preservation by means of pressure creosoting.’

‘Methods of test for soil for civil engineering purposes.’

’Railway track spanners.‘

‘Turnouts using flat bottom rails.’

‘Timber grades for structural use.’

‘Code of practice for the structural use of timber.’

‘Steel. concrete and composite bridges.‘

‘Code of practice for protective coating of iron and steel structures against corrosion.’

‘Code of practice for site investigations’

’Code of practice for earthworks.’

’The structural use of concrete.’

‘Foundations.‘

BS 1377:1975

BS 2589: I955 ( 1984)

BS 4521: Part I 1971: Part I I 1975: Part 111 1974 Part IV 1975

BS 4978:1975 (Amended 1984)

BS 5268: 1984

BS 5400:1978 Parts I to 10

BS 5493:1977 (Amended 1984)

BS 59301981

BS 6031:1981 (Amended 1983)

EIS 81 10:1985: Parts I to Ill

CP 2004:1972 (Amended 1975)