Code of Construction Practice Part B:Site Specifc Requirements
Blackfriars Bridge Foreshore(Track Changes)
December 2013
-
8/13/2019 CoCP Part B Blackfriars Bridge Foreshore Track Changes
2/14
-
8/13/2019 CoCP Part B Blackfriars Bridge Foreshore Track Changes
3/14
Code of Construction Practice Part B ii
Thames Tideway Tunnel
Code of Construction Practice Part B
Blackfriars Bridge Foreshore
List of contents
Page number
1 Introduction ...................................................................................................... 11.1 General .................................................................................................... 1
2 General Requirements ..................................................................................... 23 Communications and community/stakeholder liaison ................................. 24 Site operation ................................................................................................... 25 Public access, highway and river transport .................................................. 4 6 Noise and vibration .......................................................................................... 57 Air quality.......................................................................................................... 68 Water resources ............................................................................................... 69 Land quality ...................................................................................................... 710 Waste management and resource use ........................................................... 711 Ecology (aquatic and terrestrial) .................................................................... 712 Historic environment ....................................................................................... 713 Other ................................................................................................................. 8
Table of figures
Page number
Figure 1.1 Blackfriars Bridge Foreshore: Site context and location plan .................... 2Figure 13.1 Blackfriars Bridge Foreshore: Outline location of Roman boat ................ 9
-
8/13/2019 CoCP Part B Blackfriars Bridge Foreshore Track Changes
4/14
Code of Construction Practice Part B iii
This page intentionally left blank
-
8/13/2019 CoCP Part B Blackfriars Bridge Foreshore Track Changes
5/14
Blackfriars Bridge Foreshore
Code of Construction Practice Part B 1
1 Introduction
1.1 General
1.1.1 All works covered within this document are to be managed and performedto the culture within the Thames Tideway Tunnel vision of Zero Incidents,Zero Harm, Zero Compromise.
1.1.2 The Code of Construction Practice(CoCP) comprises two parts:
a. Part A: General requirements. These measures are applicableproject-wide.
b. Part B: Site-specific requirements. These are site-specific measures,where there are deviations from the general requirements indicated inPart A.
1.1.3 This document comprises the CoCPPart B for the Thames TidewayTunnel project works at Blackfriars Bridge Foreshore site and identifies thedetailed site-specific measures including working hours, site set up andservicing arrangements, taking into account the environmental issues andconsultations with the City of London Corporation and other stakeholders.
1.1.4 For ease of reference the CoCPPart B mirrors the headings in Part A.The CoCPPart B sets out site-specific issues and deviations from Part Aso where there are no site-specific measures reference should be made tothe measures set out in Part A.
1.1.5 A plan showing the location of the site is shown in theFigure 1.1 below.
-
8/13/2019 CoCP Part B Blackfriars Bridge Foreshore Track Changes
6/14
Blackfriars Bridge Foreshore
Code of Construction Practice Part B 2
Figure 1.1 Blackfriars Bridge Foreshore: Site context and locationplan
Note: For detailed Limits of Land to be Acquired or Used, refer to drawings in the Book of Plans.
2 General Requirements
2.1.1 As per text in CoCPPart A.
3 Communications and community/stakeholderliaison
3.1.1 As per text in CoCPPart A.
4 Site operation
Topic Site-specific requirement
Working hours This site willshalladhere to the following workinghours:
a. standard
b. extended standard.
Other working hours are subject to agreement withthe local authority.
-
8/13/2019 CoCP Part B Blackfriars Bridge Foreshore Track Changes
7/14
Blackfriars Bridge Foreshore
Code of Construction Practice Part B 3
Topic Site-specific requirement
The contractor is required to engage with the City ofLondon on the planned works, working hours andpredicted noise levels, as part of the requiredconstruction environmental management plan.
It should be noted that the City of London normallyrestrict noisy work to six hours on weekdays. Theworks are required to schedule noisy workingoperations to hours on weekdays (8am to 10am,12pm to 2pm, 4pm to 6pm), Saturdays 8am to1pm,with no noisy work on Sundays or Bank Holidays.However, the site is a significant distance fromsensitive receptors and standard hours willshallapply.
Other noisy work that may be generated (including
deliveries and maintenance) outside of thesestandard hours need to be the subject of anapplication to, and agreement by, the City ofLondon. (a 'Site Hours Variation Request' -justifying the work and methods). This includeswork categorised in CoCPPart A as extendedworking hours, continuous working, out of hours,possession working, tidal working and short noticeworking.
Site layout The temporary works construction within the river
willshallminimise the works within the navigationalchannel. The detailed methods are to be agreedwith the Port of London Authority, EnvironmentAgency and Marine Management Organisationsubject to required licenses, navigational riskassessments and consents.
Site security / hoardingrequirements
The hoarding is to be as defined in CoCPPart Apara. 4.3.4a and b incorporating suitable art workand viewing windows.
River works As per text in CoCPPart A.
Other items A site-specific lighting plan is required. The lightingwillshalladdress the impact on aquatic ecology andinclude the use of low level directional lightingwhere possible whilst meeting safe workrequirements.
The Citys Code of Deconstruction and ConstructionPractice Edition 7 shall be referenced.
-
8/13/2019 CoCP Part B Blackfriars Bridge Foreshore Track Changes
8/14
Blackfriars Bridge Foreshore
Code of Construction Practice Part B 4
5 Public access, highway and river transport
Topic Site-specific requirement
Site access and gates The site access for construction is to be from thenew entrance from the westbound ramp leadingdown from Blackfriars Bridge apart from the periodwhere the low level no1 interception chamber worksare undertaken.
During this construction phase access willshallbefrom Blackfriars underpass.
Traffic management Lorry arrivals are to be strictly controlled andcoordinated to set times to ensure that no lorriesqueue outside of the site.
The westbound ramp can only take standard HGVsand not abnormal loads.
The area shown for temporary traffic lane closure atthe end of the down ramp is to be used only whenrequired. After use, the area is to be restored tohighway use. Given notice by the City of London/Transport for London for traffic reasons, the areawillshallbe restored to traffic as soon as practicalafter notice.
The minimum width of traffic lanes to be retained onthe westbound ramp willshallbe 3.25m.
Prior to suspending any coach parking spacesalternative parking spaces willshallbe provided.The coach parking willshallbe reinstated oncompletion of the works unless agreed with thehighway authority. It is proposed that subject to therelevant highway consents being obtained thecoach parking spaces would be relocated tosouthbound carriageway of Blackfriars Road (A201)between Webber Street and Westminster BridgeRoad/Borough Road (A3202).
Existing coach parking and loading bay on thewestbound ramp and Victoria Embankment (A3211)willshallbe suspended.
The duration of works effecting traffic lanesincluding the ramp closure are to be minimised.
Event restrictions The London Marathon. Contractor to takeappropriate measures prior to and for the durationof the event, including items such as minimisingextent of works within the highway.
The contractor shall liaise with City of London,
Westminster City Council and TfL Event Planningteams with regard to other major events which may
-
8/13/2019 CoCP Part B Blackfriars Bridge Foreshore Track Changes
9/14
Blackfriars Bridge Foreshore
Code of Construction Practice Part B 5
Topic Site-specific requirement
affect Victoria Embankment.
River transport The new pier is to be in place before the closure ofthe existing pier. Access to the existing and
relocated pier to be maintained for both pedestriansand services. Liaison with London River Services(Transport for London) is required.
A detailed navigational risk assessment is requiredas part of the River Works License to confirm thatthe arrangements for river transport from the worksare safe and acceptable to the Port of LondonAuthority.
Other The diversion of the Thames Path is to be clearlysigned.
Coordination is required with both City of Londonand Transport for London on the requirements ofamended pedestrian routes to the relocatedBlackfriars Pier. This includes notices, pamphlets,guides and signage to the public.
The Contractor shall attend highways liaisonmeetings as required by the City of London. TheCity of London shall provide the contractor with 14days noticeof such meeting.
6 Noise and vibration
Topic Site-specific requirement
General The City of London require the submission of thecontractors site-specific Construction andDemolition Statement for agreementwith the City ofLondon, for works at Blackfriars Bridge Foreshoreincluding the works to relocate the President andthe Millennium Pier.
This supersedes the requirement for a separateSection 61 application as required in Section 6.3 ofPart A. The submission should include details of:
a. noise and vibration assessment andcalculations normally included within a S61application
b. noise and vibration level monitoring details,including real-time monitoring
c. non-compliance procedures for noise andvibration monitoring, including notification
procedured. monitoring required for air quality as detailed
-
8/13/2019 CoCP Part B Blackfriars Bridge Foreshore Track Changes
10/14
Blackfriars Bridge Foreshore
Code of Construction Practice Part B 6
Topic Site-specific requirement
in Part A.
The Contractor should liaise with the City of Londonon these elements in advance of the submission.
The loading and unloading of barges would becarried out during standard hours only.
It should be noted that the Employer retains theright to submit Section 61 applications to the City ofLondon.
The Contractor willshalluse silent pilingtechniques for the eastern end of the MillenniumPier dredged pocket (close to the school premises)and if necessary willshallliaise with the school toagree periods when piling can proceed without
causing adverse noise impacts.Control measures As per text in CoCPPart A.
Other As per text in CoCPPart A.
7 Air quality
Topic Site-specific requirement
Vehicle and plant emissions As per text in CoCPPart A.
Dust emissions/control As per text in CoCPPart A.Odour As per text in CoCPPart A.
Other As per text in CoCPPart A.
8 Water resources
Topic Site-specific requirement
Control of pollution:
surface water / groundwater
Reference should be Section 8.3 of CoCPPart A on
protection of water courses.The contractors environmental management planwillshallinclude specific control and mitigationmeasures for minimising risk of contaminated siterun off directly to the river during the works,particularly during diaphragm wall constructionworks
Control on abstraction As per text in CoCPPart A.
Ground treatment / dredging As per text in CoCPPart A.
OtherAs per text in CoCPPart A.
-
8/13/2019 CoCP Part B Blackfriars Bridge Foreshore Track Changes
11/14
Blackfriars Bridge Foreshore
Code of Construction Practice Part B 7
9 Land quality
Topic Site-specific requirement
Site works As per text in CoCPPart A.
Site-specific issues / mitigation As per text in CoCPPart A.
10 Waste management and resource use
Topic Site-specific requirement
Excavated material As per text in CoCPPart A.
Resource usage As per text in CoCPPart A.
Other As per text in CoCPPart A.
11 Ecology (aquatic and terrestrial)
Topic Site-specific requirement
Protection of habitats Membrane to be installed between river bed andtemporary back fill material to preventcontamination of juvenile fish habitat and benefits inpreserving potential archaeology.
Areas of foreshore used for temporary workswillshallbe restored to similar condition andmaterial as was present prior to the works.
Protection of trees Specification for replacement trees to be agreedwith Transport for London and includes species,size, source, pit design and finish.
Other As per text in CoCPPart A.
12 Historic environment
Topic Site-specific requirement
Other The contractors working methods are to minimiserisk of accidental striking the listed bridge.Protection barriers willshallbe installed as requiredbut not attached to the structure unless otherwiseagreed.
During construction of the new river wall as part ofthe Blackfriars underpass work a Roman boat wasuncovered in the cofferdam (seeFigure 13.1). The
location is between the road and rail bridges. TheContractors method for the river works willshall
-
8/13/2019 CoCP Part B Blackfriars Bridge Foreshore Track Changes
12/14
Blackfriars Bridge Foreshore
Code of Construction Practice Part B 8
Topic Site-specific requirement
minimise the risk of impact on the boat location byselecting suitable river plant and operatingprocedures.
The sturgeon lamp stands willshallbe carefullyremoved, stored and reinstated in their currentpositions as far as it is possible. The existingreplica lamp stands willshallbe replaced withoriginals from elsewhere (by agreement) or newcastings from the original moulds.
Existing granite blocks are to be used to make upthe joint between new and old river wall sections.
13 Other
Topic Site-specific requirement
Other As per text in CoCPPart A.
-
8/13/2019 CoCP Part B Blackfriars Bridge Foreshore Track Changes
13/14
Blackfriars Bridge Foreshore
Code of Construction Practice Part B 9
Figure 13.1 Blackfriars Bridge Foreshore: Outline location of Roman boat
-
8/13/2019 CoCP Part B Blackfriars Bridge Foreshore Track Changes
14/14
100-RU-PNC-BLABF-000002