collaborative planning on 5 london underground projects mr daniel agutter, a2b excellence
TRANSCRIPT
Collaborative Planning on 5 London Underground Projects
Mr Daniel Agutter, A2B Excellence
2
1. Set the Scene
2. Collaborative Planning
3. Summary
4. Questions and Answers
Agenda
3
How often do we complete the things we plan to do?
4
100% of the time?90% of the time?
75% of the time?
50% of the time?
5
In Feb 2013, achieved Authority for:
• £350m
•7 year Programme
•Upgrade 72 Underground stations
•Savings Target of 12% to 20%
1. Set the Scene
So, what did we do?
Developed a new delivery strategy: ‘STAKE’
• Went down supply chain
• Supply chain - Continuity of work
• Capable workforce – Quality & Productivity
• Simplified non-adversarial contracts
8
• 1st time LU to perform Client and Principal Contractor role
• Collaborative working and relationships
• …Collaborative Planning
STAKE Delivery Model
9
2. Collaborative Planning
STAGE 1 - Planning in Design
10
STAGE 1 -
Planning in Design
11
STAGE 1 – Planning in Design
12
STAGE 2 – Production Management
13
STAGE 2 – Production Management
14
STAGE 2 – Production Management
• Daily Pre and Post-Shift Meetings
• Weekly Progress Review
• Periodically Review Stage 1
- Divergence
15
STAGE 3 – Process Improvement
• Unachieved activities
• Issue cards recorded
• Contractor Performance - PPC
• Lessons Learned
16
3. Summary – Costs
• Early Contractor Involvement
• Contractor’s time to complete cards
• Planning cards, boards, frames
• Daily, weekly, periodical meeting attendance
17
3. Summary – Benefits
• One Team Approach
• Early Contractor Involvement
• Standardised site management
• PPC increases from 55-60% to 80-90%
18
3. Summary – Benefits
• Highways England: 10-40% improvements in Time and Cost
• Work-site clashes mitigated & maximise opportunities
• Issues identified early
• Transparency of progress, process and interfaces
19
CPTP & ICE
20
4. Questions and Answers