colorado college barnes science center retro-commissioning ...€¦ · assessment report for this...
TRANSCRIPT
draf
t: w
ork
in p
rogr
ess
Colorado College Barnes Science Center Retro-Commissioning
Preliminary Site Assessment
Submitted to: Colorado College Facilities Services
1125 Glen Avenue
Colorado Springs, CO 80905
draf
t: w
ork
in p
rogr
ess
Barnes Science Center Preliminary Site Assessment RCx Report
Page i
This page left purposely blank for double-sided printing
draf
t: w
ork
in p
rogr
ess
Barnes Science Center Preliminary Site Assessment RCx Report
Page ii
Executive Summary
This Preliminary Site Assessment includes an ASHRAE Level I report, and has identified energy cost
reduction opportunities, repair and maintenance items, and capital improvement projects to be considered for
further evaluation and development with estimation. The BESECx team performed an on-site preliminary
walk-through assessment of this facility noting present operating and maintenance practices, all possible
deficiencies and opportunities for improvements, and then developed a master list of findings compiled in
Appendix C. These deficiencies and opportunities for improvements have been sorted in one of three
categories, ECM’s (Energy Cost Reduction Opportunities), CIP (Capital Improvement Projects), or R&M
(Repair and Maintenance) items.
Even though this building is now 23 years old, with most of the HVAC systems exceeding their median
service life, Barnes Science Center is still a well performing classroom-laboratory building. This is result of
good energy efficiency decisions made during the mid-to-late 80s to incorporate heat recovery systems and
photo-operated lighting controls for lobby and stair towers.
The Energy Use Index (EUI) is an industry standard metric to evaluate the performance of a building,
expressed in the units of kBtu/sf/yr. Thermal data has been harvested from BTU meters installed and
operational during the spring of 2011, and electrical usage and demand data is available from the utility meter
installed in September 2008. Estimating based on normalized weather data for the high-temperature hot and
chilled water usage for the first three months of last year (before thermal meters were installed), the measured
energy consumption was approximately 10.0 MMBtu (10,000,000± kBtu) with an extrapolated EUI of 140
kBtu per square foot per year.
Published data for academic-research laboratory classroom building is sparse, but table below represents a
comparison with data from peer facilities with similar occupancy and operating characteristics.
Energy Performance Rating Comparisons
(EUI in kBtu/sf/yr)
Nat'l or
other Avg Barnes % Diff
CBECS 2003 climate specific average laboratory 255 140 -45%
Research Laboratory (non-higher education, from CBECS) 610 140 -77%
College/University (Campus-level) 283 140 -51%
CC Facilities Management is the on right track with this facility. The original MEP design intent was high-
performing relative to other facilities built in the late 1980s. The two air to air heat recovery systems and the
stair tower – lobby daylighting control system stand out as significant contributors to this building’s energy
performance.
Lord Kelvin once stated "if you cannot measure it, you cannot improve it." CC Facilities Management in
conjunction with the campus Sustainability group has recently begun to incorporate a measurement and
verification program to monitor the energy usage of key campus buildings and the central plant.
The retro-commissioning process includes an ongoing consultation with operational and maintenance
personnel, as well as building occupants. Concurrent with the preliminary site assessment, the Master List of
Deficiencies and Opportunities is developed; this list is one of the most significant deliverables from the
retro-commissioning process and ultimately becomes an important decision making tool. Every finding from
the investigation phase is summarized on the Master List, including those adjustments and repairs made
during the course of the investigation process. This PSA (Preliminary Site Assessment) documents over 25
ECM’s in Appendix C, along with a dozen suggested CIP's (capital improvement projects).
draf
t: w
ork
in p
rogr
ess
Barnes Science Center Preliminary Site Assessment RCx Report
Page iii
TABLE OF CONTENTS
EXECUTIVE SUMMARY.....................................................................................................................................i
OWNER’S PROJECT REQUIREMENTS ...................................................................................................................... 1
RETRO-COMMISSIONING PROCESS OVERVIEW ................................................................................................. 1
OBJECTIVES OF THE RETROCOMMISSIONING PROCESS .......................................................................................................... 1
FACILITY DESCRIPTION .............................................................................................................................................. 4
GENERAL BUILDING ENERGY SYSTEMS DESCRIPTIONS ........................................................................................................ 4
ENERGY COST, USAGE, AND BASELINE METRICS .............................................................................................. 8
ENERGY AUDIT ..................................................................................................................................................................... 8
ELECTRICAL COSTS, USAGE, DEMAND, AND POWER FACTOR ............................................................................................... 8
NATURAL GAS COSTS AND USAGE ...................................................................................................................................... 11
ENERGY METERS ................................................................................................................................................................. 11
BASELINE ENERGY USAGE .................................................................................................................................................. 11
BENCHMARKING .......................................................................................................................................................... 12
EPA ENERGY STAR PORTFOLIO MANAGER ......................................................................................................................... 12
CBECS ............................................................................................................................................................................... 12
ENERGY COST REDUCTION MEASURES (ECM) .................................................................................................. 12
OBJECTIVES ......................................................................................................................................................................... 12
ECM MASTER FINDINGS LIST ............................................................................................................................................. 13
CAPITAL IMPROVEMENT PROJECTS (CIP) .......................................................................................................... 13
OPPORTUNITIES ................................................................................................................................................................... 13
CIP MASTER FINDINGS LIST ............................................................................................................................................... 13
FUME HOOD CONTROLS ...................................................................................................................................................... 13
REPAIR AND MAINTENANCE (R&M) ...................................................................................................................... 13
OBJECTIVES ......................................................................................................................................................................... 13
SYSTEMS AND EQUIPMENT CONDITION ANALYSIS AND ASSESSMENT ................................................................................. 14
HVAC SYSTEMS ................................................................................................................................................................. 14
LIGHTING SYSTEMS ............................................................................................................................................................. 14
BUILDING ENVELOPE .......................................................................................................................................................... 14
NEXT STEPS .................................................................................................................................................................... 15
ASHRAE LEVEL II ENERGY AUDIT .................................................................................................................................... 15
INVESTIGATIVE RETRO-COMMISSIONING PHASE ................................................................................................................. 15
REPORT INTELLIGENCE ............................................................................................................................................ 16
ABBREVIATIONS, ACRONYMS AND UNITS ........................................................................................................................... 16
DISCLAIMER ........................................................................................................................................................................ 16
REVISION HISTORY ............................................................................................................................................................. 16
draf
t: w
ork
in p
rogr
ess
Barnes Science Center Preliminary Site Assessment RCx Report
Page iv
CHARTS
Chart 1: Comparison of Oct 2009 - 2011 Electric Unit Cost per Month ($/kWh) ...............................................9 Chart 2: Electric Usage Profile October 2009 - 2011 ..........................................................................................9 Chart 3: Electrical Demand Profile for October 2009 - 2011 ............................................................................10 Chart 5: Energy Usage Profile Oct 2010 through Sept 2011 .............................................................................11 Chart 6: Energy Usage Comparative to Weather Conditions Oct 2010 through Sept 2011 ..............................12
TABLES
Table 1: Past Year Electrical Costs ....................................................................................................................10
FIGURES
Figure 1: Lab AHU with Heat Wheel Control Diagram ......................................................................................5 Figure 2: Snapshot from BAS Submeter ............................................................................................................11
PHOTOS
Photo 1: Heat Wheel Serving Anatomy/Science Lab and Animal Suite .............................................................5 Photo 2: Anatomy/Science Lab and Animal Suite Pre & Final Filtration Bank ..................................................6 Photo 3: Building AHU Supply Fan ....................................................................................................................6 Photo 4: Atrium Lobby Lighting .........................................................................................................................7 Photo 5: Corridor Lighting ...................................................................................................................................7 Photo 6: Greenhouse Lighting .............................................................................................................................8 Photo 8: Door Leading to South Observatory Deck ..........................................................................................14 Photo 9: Observatory Dome ...............................................................................................................................15
APPENDICES
FACILITY ENERGY ACCOUNTING MATRIX........................................................................................... ................ APPENDIX A
ENERGY STAR STATEMENT OF ENERGY PERFORMANCE….................................................................. ................ APPENDIX B
MASTER FINDINGS LIST ................................................................. ......................................................................APPENDIX C
PHOTO LOG OF IDENTIFIED DEFICIENCIES AND OPPORTUNITIES ……………..................................... ................ APPENDIX D
BUILDING OPERATION SCHEDULE.................................................................................... .................................... APPENDIX E
UTILITY RATE SHEETS................................................................................................. ......................................... APPENDIX F
FACILITY DOCUMENTS CHECKLIST................................................................................................. ..................... APPENDIX G
EQUIPMENT SERVICE LIFE DATA …..……………….......................................................................................... APPENDIX H
INFRARED THERMOGRAPHY…..……………….......................................................................... ........................... APPENDIX I
ECM MANUFACTURER CATALOG DATA...................... .........................................................................................APPENDIX J
RCX TEAM CONTACT INFORMATION................................................................................................. .................. APPENDIX K
draf
t: w
ork
in p
rogr
ess
Barnes Science Center Preliminary Site Assessment RCx Report
Page 1
Owner’s Project Requirements
The Owner’s Project Requirements detail the functional requirements of a project and the expectations of the
Project Owner. These include project goals, measurable performance criteria, cost considerations,
benchmarks, success criteria, and supporting information. The source of some of these requirements is
Colorado College’s goal for achieving carbon neutrality by 2020 as documented in ―A Strategic Vision for
Energy Efficiency at Colorado College‖.
The following summarizes the key Owner’s Project Requirements identified for this retro-commissioning
project:
1) To achieve a 30% reduction in energy use through efficiency upgrades;
2) To identify no or low-cost ECM’s (Energy Cost Reduction Measures) to be possibly implemented
during investigation phase by either CC Facilities Maintenance staff or Long Building Technologies
with minimal capital investment;
3) To identify longer term Energy Cost Reduction Measures for planning purposes to further reduce
energy consumption through replacement or upgrade by attrition;
4) To identify Capital Improvement Projects (CIP), analyze the collected data, and document proposed
system solutions accordingly to justify resource needs to both stakeholders and decision makers;
5) To identify Repair and Maintenance (R&M) deficiencies that affect energy, IAQ, or occupant
comfort;
6) To perform condition assessments of systems and equipment during investigation phase and to
augment current equipment asset inventory of all building energy systems and equipment as required;
7) Summarize identified ECM, R&M, and CIP items for Colorado College Facility Management and
other stakeholders to select items for immediate implementation or to defer for future projects.
Retro-Commissioning Process Overview
Commissioning of existing buildings or ―retro-commissioning,‖ is an event in the life of a building applying a
systematic process for identifying and implementing operational and maintenance improvements and for
ensuring their continued performance over time. The retro-commissioning process most often focuses on
dynamic energy-using systems with the goal of reducing energy waste, obtaining energy cost savings, and
identifying and fixing existing problems. Retro-commissioning assures system functionality. It is an inclusive
and systematic process that intends not only to optimize how equipment and systems operate, but also to
optimize how the systems function together.
Objectives of the Retrocommissioning Process
Although Retrocommissioning may include recommendations for capital improvements, the primary focus is
on using O&M tune-up activities and diagnostic testing to optimize the building systems. Retro-
commissioning is not a substitute for major repair work. Repairing major problems should be performed
before retro-commissioning can be fully completed. The following have been identified by Portland Energy
Conservation, Inc. (PECI) as the typical primary objectives for retro-commissioning a project:
Benchmark current energy usage through energy audits
Improve facility operation and maintenance
Reduce energy and demand costs
Increase equipment life
Improve indoor air quality
Increase occupant satisfaction and reduce complaints
Reduce O&M staff time spent on emergency calls
draf
t: w
ork
in p
rogr
ess
Barnes Science Center Preliminary Site Assessment RCx Report
Page 4
Facility Description
The following summarizes the general description of the building surveyed for the preliminary assessment:
a) Barnes Science Center, dedicated in 1988, and named Barnes Science Center April 23, 1990, in
recognition of the substantial trust fund established by Professor and Mrs. Barnes.
b) Description: 5-story 69,000 ft2 building houses academic and research laboratories, offices, and
classrooms for anthropology, chemistry and physics departments; unique academic features
include astronomical observatory, four greenhouses and a herbarium.
c) Exterior Doors: metal and aluminum storefront
d) Facility Documents available: see Appendix G
General Building Energy Systems Descriptions
BESECx performed a thermal infrared imaging survey during early November. A separate report was issued
to Colorado College Facilities Management which included other east campus buildings including Armstrong
Hall, Olin Hall, and Tutt Library. Preliminary assessment surveys of the facility were conducted during
November 2011 and with follow-ups in December and early January.
HVAC Systems: similar to the majority of buildings at CC campus, HTHW (High Temperature Heating
Water) is supplied from the central plant to a lower temperature secondary or tertiary building hydronic loop
through a heat exchanger located in the basement of Olin Hall (for more detail refer to the preliminary site
assessment report for this project).
Chilled water is provided for both Olin Hall and this facility from the central plant into the Barnes original
chiller room now used for storage as well as water service entrance and the motor control center.
The building chilled water services are separated by a plate and frame heat exchanger; due to the freeze
potential at Olin Hall, a propylene glycol solution is used.
The main building air handler is located in the basement room 113; the 50 hp supply fan is equipped with
adjustable inlet vanes. The DDC controls are programmed with a PID (Proportional + Integral + Derivative)
loop which adjust the speed of the 50 hp supply fan to ensure the farthest VAV terminal unit is supplied a
minimum of 1‖ w.g. static pressure. Correspondingly, to maintain a positive building pressure, the unit relief
fan operates to maintain a positive 0.05‖ w.g. relative to the outdoors. This unit is equipped with optimal start-
stop controls and air side economizer.
The Anatomy/Science Lab and Animal Suite is served by an air handler unit equipped with a 10 hp supply fan
motor is located in the basement. A heat wheel (see photo below) located between the exhaust system and
outside air intake is an effective air-to-air energy recovery technology. By rotating at the most optimum speed,
the wheel transfers heat energy during the winter from the exhausted air and pre-heat the incoming ventilation
makeup air. A desiccant type wheel transfers both sensible (heat) and latent (moisture) energy. At an outside
air temperature of 20°F, a downstream entering temperature of 58°F was observed; this calculates to a heat
transfer effectiveness rate of 78%. This unit is also equipped with an evaporative cooling coil downstream of
the chilled water coil.
The laboratory air handler unit is located in the fifth floor mechanical room, as equipped with a tilting heat
pipe coil located in both intake and exhaust streams. This unit is powered by two 60 hp fans with variable
speed drives optimizing the air flow rate based on lab space requirements. A BAS snapshot is depicted in the
figure below; the calculated temperature transfer efficiency of this heat recovery unit for the conditions of
28.7°F and discharge air temperature of 48.3° F is 46.5%.
draf
t: w
ork
in p
rogr
ess
Barnes Science Center Preliminary Site Assessment RCx Report
Page 5
Figure 1: Lab AHU with Heat Wheel Control Diagram
The building computer center is served by two CRAC units rejecting heat to a recently upgraded dry cooler
located on the roof. This system is equipped with "free cooling" to reject data center heat outdoors through a
pumped glycol solution.
Photo 1: Heat Wheel Serving Anatomy/Science Lab and Animal Suite
draf
t: w
ork
in p
rogr
ess
Barnes Science Center Preliminary Site Assessment RCx Report
Page 6
Photo 2: Anatomy/Science Lab and Animal Suite Pre & Final Filtration Bank
Photo 3: Building AHU Supply Fan
BAS / Temperature Controls: During 2010, upgrades were performed to the Siebe DMS-3500 DDC
building automation system including the new higher end AX interface.
Domestic Water Heating: Domestic hot water is generated by a steam heat exchanger located in the
basement of Olin Hall. The domestic hot water is supplied to fixtures at a setpoint of 125° F.
Interior Lighting: Classroom and office fixtures are primarily 32W T8 fluorescent recessed prismatic 2x4
lay-in troffers.
Formerly pneumatically controlled inlet vanes for 50 hp building AHU; new VFD currently provides variable air
flow volume
draf
t: w
ork
in p
rogr
ess
Barnes Science Center Preliminary Site Assessment RCx Report
Page 7
Photo 4: Atrium Lobby Lighting
Photo 5: Corridor Lighting
Fluorescent Corridor lighting with PL13 lamps to be soon phased out of production
Original incandescent exit signage upgrade to
LED type
draf
t: w
ork
in p
rogr
ess
Barnes Science Center Preliminary Site Assessment RCx Report
Page 8
Photo 6: Greenhouse Lighting
Lighting Controls: the majority of classroom and office spaces deploy dual-level split ballast switching.
Second faculty floor offices sampled during the site survey also had under cabinet lighting separately switched,
and faculty were observed performing computer work without the overhead lights on. Stairwells are equipped
with automatic low-voltage control with a photocell located in the fifth floor of the east stairwell to turn off
lights when the lighting level drop below 5 footcandles. The drawings indicate an astronomical timeclock
located in room 127; during the preliminary site visit, the accuracy of the timeclock was not verified. O
Plumbing Fixtures: fixtures observed appear to be the 1988 originals including water closets at 3.5 gallons
per flush. Facilities Management has confirmed the lavatory faucets were later modified with 1.5 gpm aerator
devices.
Energy Cost, Usage, and Baseline Metrics
Energy Audit
Prior to starting any energy analysis, a preliminary energy use analysis is performed to determine a building's
current energy and cost efficiency relative to other, similar buildings. This is normally done by calculating the
energy use and cost per sf per year, which can indicate the potential value of further levels of analysis.
Electrical Costs, Usage, Demand, and Power Factor
The electrical and natural gas energy usage for this facility has been provided by the local utility engineer and
compiled into an energy accounting matrix included in this report in Appendix A. Colorado Springs Utilities
(CSU) provides electrical power to this facility (see Appendix F for electrical rate schedule). Actual utility
invoices were not provided for review, only a compilation spreadsheet including on/off peak usage, demand,
facility access charges, and cost adjustment charges. It is always recommended to closely review utility bills
for calculation mistakes.
draf
t: w
ork
in p
rogr
ess
Barnes Science Center Preliminary Site Assessment RCx Report
Page 9
Both consumption (in units kilowatt used per hour or kWh) and demand charges (kW) are itemized all monthly
electric bills. The demand charge may be explained as an ―overhead‖ charge to compensate for the capacity of
the electrical infrastructure brought to the facility. Demand in kW is measured as the peak usage at 15 minute
intervals (typical). The electrical unit cost per month is a combined demand (kW) and usage (kWh) as
depicted in the bar chart below.
Chart 1: Comparison of Oct 2009 - 2011 Electric Unit Cost per Month ($/kWh)
December value shall be discarded as it was a partial reading. However, it is noted the unit cost of electricity
in January of 2009 was $0.054; there was a noted increase of over 36% to November of 2011 at $0.074 per
kilowatt hour purchased. Recommend further investigation with Colorado Springs Utilities service
representative to determine the probable cause of this increase.
The chart below indicates the expected decrease in usage during the summer months. During March of 2009,
there may have been above typical activity in research, including heavy environmental chamber use during the
spring break.
Chart 2: Electric Usage Profile October 2009 - 2011
0
0.01
0.02
0.03
0.04
0.05
0.06
0.07
0.08
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Un
it C
ost
($
/kW
H)
2009 2010 2011
70
75
80
85
90
95
100
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
kWH
(Th
ou
san
ds)
2009 2010 2011
draf
t: w
ork
in p
rogr
ess
Barnes Science Center Preliminary Site Assessment RCx Report
Page 10
Over the past year, the electrical demand costs have been exceeding the energy consumption costs by an
average of 19% (see table and figure below).
Month Year Usage ($/mo)
Demand ($/mo)
% Diff
NOV 2011 $2,178.77 $2,774.34 27.3
OCT 2011 $2,189.57 $2,772.63 26.6
SEP 2011 $2,124.23 $2,508.57 18.1
AUG 2011 $2,187.20 $2,349.82 7.4
JUL 2011 $2,370.30 $2,730.17 15.2
JUN 2011 $2,356.06 $2,693.35 14.3
MAY 2011 $2,122.56 $2,505.46 18.0
APR 2011 $2,142.35 $2,606.06 21.6
MAR 2011 $2,001.19 $2,360.48 18.0
FEB 2011 $2,196.48 $2,629.45 19.7
JAN 2011 $2,081.88 $2,500.44 20.1
DEC 2010 $2,176.15 $2,670.68 22.7
Year Totals $26,126.74 $31,101.45 19.0
Table 1: Past Year Electrical Costs
The electrical demand charge includes two components, generation demand and consumer demand, both
charge by kVA (1000 volt-amperes, for reactive loads, the voltage and current are out of phase and the volt-
ampere will be greater than the wattage measurement). The demand charge (also referred to as a ―ratchet‖)
was developed for the local utility to recover costs associated with a given level of electric demand; it is
possible to pay a demand charges even if no consumption is recorded for the month. The demand charge
generally includes all costs associated with operating and maintaining a utility's generation, transmission and
distribution systems.
Chart 3: Electrical Demand Profile for October 2009 - 2011
Over the past year, monthly demand costs have averaged $15.61 / kVA (or kW) and contributed to 54.4% of
2011 average $0.0684 / kWH on a unit cost basis.
120
130
140
150
160
170
180
190
200
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
On
Pe
ak D
em
and
(kW
)
2009 2010 2011
draf
t: w
ork
in p
rogr
ess
Barnes Science Center Preliminary Site Assessment RCx Report
Page 11
Power factor (PF) in simple terms is an efficiency measure of electrical power delivery to the customer. In
technical terms, the power factor is defined as the ratio of ―real power‖ for consumed by electrical loads (kW)
to the apparent power (kVA) in the load circuit. A load with a low PF draws more current than a load with a
high PF for the same amount of useful power transferred, but the utility customer is only billed for the power
used. Since a power factors below 1.0 requires a utility to generate more than the minimum volt-amperes
necessary to supply the real power (kW), this results in increased generation and transmission costs.
Consequently, Colorado Springs Utilities charges additional costs to customers with a lagging power factor
below ninety-five percent (95%) or for a leading PF.
Figure 2: Snapshot from BAS Submeter
Power factor correction devices may be installed at service entrance at for the electrical distribution system or
installed at the equipment or VFD. This will be investigated further during the next phase.
Natural Gas Costs and Usage
Natural gas is supplied from Olin Hall over to the Barnes science center; for measurement verification of
energy usage, it is recommended to consider a pulse-type submeter.
Energy Meters
During the spring of 2011, CC Facilities Management installed Btu meters for building HTHW and CHW in
key campus facilities which measure flow with a non-intrusive ultrasonic flow meter and system supply and
return temperatures utilizing RTD sensors with 0.03 °F accuracy. Data recorded from April of 2011 to last
month is included in the facility energy accounting matrix of Appendix A.
Baseline Energy Usage
Energy use index (EUI) is an industry standard indicator defined as a measurement of the total energy used in a
building (or facility) for a specific period of time stated in terms of one thousand British thermal units (kBtu)
per gross conditioned square foot per year (Btu/sf/yr).
The EUI calculated for the period of April 2011 through November 2011 includes electricity, gas, and central
plant high temperature hot water and chilled water. Information from the missing months extrapolated based
on normalized weather data.
The electrical and natural gas energy usage and energy costs for this facility have been collected for fiscal year
2009 through November 2011, calculated as total energy performance, and are depicted in graphs below.
Chart 4: Energy Usage Profile Oct 2010 through Sept 2011
Snapshot PF = 0.86; a
lagging power factor
below 0.95 is in the
utility penalty zone.
Peak demand value
for recorded by BAS
does not coincide with
utility measured value
Forthcoming
draf
t: w
ork
in p
rogr
ess
Barnes Science Center Preliminary Site Assessment RCx Report
Page 12
Weather impacts the energy performance of a building; the chart below attempts to demonstrate relationship
between the building utility (electricity and gas) consumption and weather (HDD – Heating Degree Days
below 65°F).
HDD (heating degree days for a base temperature of 65°F)
Energy Usage (kBtu)
Chart 5: Energy Usage Comparative to Weather Conditions One Year Starting November 2010
Benchmarking
The value of an energy usage benchmark is to set a baseline for comparison to an implemented ECM. Also,
benchmarks are used to assess this facility with an ―average‖ building of the same type to provide a level to
comparison.
EPA Energy Star Portfolio Manager
At this time, laboratory/classroom buildings are not included in the Energy Star portfolio and cannot be rated
for comparison with peer facilities, the only higher education facilities are dorms / residence halls.
CBECS
The Commercial Buildings Energy Consumption Survey (CBECS) is a national sample survey that collects
information on the stock of thousands of U.S. commercial buildings, their energy-related building
characteristics, and their energy consumption and expenditures. CBECS was first conducted in 1979; the
eighth, and most recent survey, was conducted in 2003. Although CBECS is currently conducted on a
quadrennial basis, the 2007 Commercial Buildings Energy Consumption Survey (CBECS) has not yielded
valid statistical estimates. Unfortunately, similar to Energy Star, CBECS does not collect data for Higher
Education facilities except for specific use such as dormitory-residence halls.
Energy Cost Reduction Measures (ECM)
Objectives
After benchmarking baseline energy use for whole building, the RCx team accomplished the next tasks:
Performed preliminary walk-through survey to provide the information needed to identify low-
cost/no-cost operations, maintenance, and energy cost reduction opportunities relevant to the
specific building or buildings.
Evaluated energy conservation opportunities for expected savings, estimated implementation costs
(including any design work required), risks, and non-energy benefits (e.g., improved system
operation, better indoor comfort).
Recommended a number of energy cost reduction measures for implementation.
Also identified a number issues or deficiencies to be categorized as repair and maintenance items,
and opportunities for capital improvement projects.
Forthcoming
draf
t: w
ork
in p
rogr
ess
Barnes Science Center Preliminary Site Assessment RCx Report
Page 13
ECM Master Findings List
The Master List found in Appendix C includes all ECMs considered during the preliminary assessment
process. The development of the Master List includes a brainstorming effort to catalogue all reasonable energy
reduction opportunities. Based on previous experience, only measures with reasonable paybacks were
included in this list.
Capital Improvement Projects (CIP)
Opportunities
Retro-commissioning a facility methodical may prevent the need for expensive capital improvements;
however, RCx is only the first step in improving the facility’s performance. Potential capital improvements
may be recommended during the RCx process, then deferred with a timetable for planned implementation as
funding is made available.
CIP Master Findings List
Potential capital improvement projects are also included in Appendix C to be discussed with facilities
management prior to proceeding with further evaluation.
Fume Hood Controls
ASHRAE Standard 90.1-2007 prescriptive compliance item 6.5.2.7 requires
buildings with fume hoods having a total exhaust rate greater than 15,000
CFM shall incorporate one of three solutions: (1) VAV hood exhaust and
room supply systems capable of producing exhaust the makeup air by 50% or
less the design values; (2) Direct makeup (auxiliary) air supply equal to at
least 75%of the exhaust rate, heated no warmer than 2°F below room
setpoint, cooled to no cooler than 3°F above room setpoint, no humidification
added, and no simultaneous heating and cooling used for dehumidification
control; or (3) heat recovery systems to precondition makeup air from fume
hood exhaust (similar to the system employed at Barnes Science Center).
Fume hood controls reduce energy use by monitoring sash height and
correspondingly regulating the amount of airflow into the hood at a face
velocity of 100 fpm. As the exhaust air flow reduces, the makeup air system
correspondingly decreases flow to adjust building pressurization to maintain setpoint. Assuming a 5’
operational fume hood exhaust volume averages 1000 cfm at 24‖, lowering the sash height of 25 hoods during
non-use could correspond to a reduction of 22,500 cfm or a corresponding savings of $70,000 a year. The
recommended industry high-performance standard is the Phoenix Valve, which has a retrofit cost of $12,600
per hood plus lab manifold exhaust VFD control, or a 4.5 year simple payback.
Repair and Maintenance (R&M)
Objectives
During the preliminary walk-through survey, existing building energy systems, equipment, or components in
need of repair and maintenance were also identified and documented in the R&M Master Findings List. As the
project progresses through the investigation phase, additional items will most likely be added to the list.
draf
t: w
ork
in p
rogr
ess
Barnes Science Center Preliminary Site Assessment RCx Report
Page 14
Systems and Equipment Condition Analysis and Assessment
An important aspect of operation and maintenance engineering systems is assessing equipment condition. For
complex systems, it may be necessary to monitor several conditions (e.g., temperature, vibration, and load) so
that the overall condition can be assessed.1 The initial assessment steps include:
a) Determine if deficiency is occurring at more than one location;
b) Determine frequency of occurrence;
c) Determine if issue impacts other systems, subsystems, or components.
After the assessment of the deficiency, the problem is analyzed thus:
a) Review all aspects of identified issue;
b) Consider alternate solutions;
c) Recommend appropriate corrective action.
At this preliminary walk-through stage of the retro-commissioning process, observations were recorded in
Appendix D Photo Log of Identified Deficiencies and Opportunities. During the next stage, identified
deficiencies will be further developed with recommendations and estimated costs for ECM improvements or
estimated capital improvement upgrade or replacement costs.
HVAC Systems
HVAC equipment at the facility appears to be adequately maintained. A list of service work orders were not
provided for this facility to review. Reference Appendix D for noted deficiencies and H for tables indicating
service lives for various HVAC equipment.
Lighting Systems
All lighting fixtures typically in need of repair, maintenance, or lamp replacement appear to have previously
identified and reported by staff per proper protocol. Few lamps or ballast were observed to require
replacement, and may have been corrected prior to issuing this report.
Building Envelope
Major building envelope improvements are typically too expensive to implement. Appendix I includes some
thermographic imaging performed in conjunction with Olin Hall. The majority of easily correctable
deficiencies include door realignment in jamb and replacement of worn weather-stripping (photo below is a
sample of observations made).
Photo 7: Door Leading to South Observatory Deck
1 2007 ASHRAE Handbook—HVAC Applications
draf
t: w
ork
in p
rogr
ess
Barnes Science Center Preliminary Site Assessment RCx Report
Page 15
It appears the design intent for the observatory was to isolate its heat loss by installing weather stripping at the
corridor entrance. During the preliminary site assessment, partition wall insulation and additional insulation
separating the space below was not verified, it is recommended to be reviewed during a retro-commissioning
process.
Photo 8: Observatory Dome
Next Steps
ASHRAE Level II Energy Audit
An ASHRAE Level II Energy Audit is not recommended for this facility. It is recommended to proceed
directly to the retro-commissioning process.
Investigative Retro-Commissioning Phase
The calculation of potential savings, payback of appropriate energy conservation measures (ECMs), expected,
and estimated cost to implement will be performed during the investigative phase. Investigative retro-
commissioning phase efforts may take from 2 to 3 days per site. More capital-intensive retrofit opportunities
incidental to the commissioning assessment may be identified. For a more accurate comparison of alternate
ECMs, a more comprehensive economic analysis may be warranted.2
2 2007 ASHRAE Handbook—HVAC Applications 36.10
draf
t: w
ork
in p
rogr
ess
Barnes Science Center Preliminary Site Assessment RCx Report
Page 16
Report Intelligence
Abbreviations, Acronyms and Units
The following are common industry abbreviations, acronyms, and units of measure used in this document: AFUE: Annual Utilization Fuel Efficiency
AHU: Air Handling Unit
ASHRAE: American Society of Heating, Refrigeration
and Air Conditioning Engineers
Btu: British thermal unit
BtuH: British thermal unit per Hour
BAS: Building Automation System
CAV: Constant Air Volume
CBECS: Commercial Building Energy Consumption
Survey
CFL: Compact Fluorescent
CFM or cfm: Cubic Feet per Minute
COP: Coefficient of Performance
DDC: Direct Digital Control
DHW: Domestic Hot Water
DX: Direct Expansion
ECM: Energy Cost Reduction Measure
EMS: Energy Management System
EPDM: Ethylene Propylene Diene Monomer
ERV: Energy Recovery Unit
EUI: Energy Use Index
FC or fc: foot-candle (unit of light intensity)
FY/CY: Fiscal Year/Calendar Year
GPM: Gallons per Minute
Hour: hr
HTHW: High Temperature Hot Water
HEX: Heat Exchanger
HVAC: Heating Ventilation and Air Conditioning
kBtu: One Thousand British Thermal Units
kW: Kilo-Watt
kWh: Kilo-Watt hour
LCCA: Life Cycle Cost Analysis
LED: Light Emitting Diode
LPD: Lighting Power Density
MAU: Makeup Air Unit
MBH: Thousand British Thermal Units per hr
MMBtu: Million British Thermal Units
NPV: Net Present Value
O&M: Operation and Maintenance
PSA: Preliminary Site Assessment
PV: Photovoltaic
RTU: Rooftop Unit
SEER: Seasonal Energy Efficiency Rating
SIR: Savings to Investment Ratio
SOW: Scope of Work
SPP: Simple Payback Period
TAB: Testing Adjusting & Balancing
TOD: Time of Day (scheduling)
Therm: 100,000 BTU+
VAV: Variable Air Volume
VFD: Variable Frequency Drive
W: Watt
Disclaimer
This Preliminary Assessment Report contains proprietary, confidential, and privileged information
specifically intended for our client. The intent of this report is to provide a preliminary evaluation of the
potential energy and demand savings with energy efficiency conservations measures evaluated for this
facility. The conclusions noted in this report are believed to be reasonably accurate relative to the standard of
care for this industry; however, dependent upon implementation, the actual energy savings results may vary.
BESECx will assume no responsibility for any loss, injury, or damage resulting from, or occurring in
connection with, the use of information contained or referred to in this report.
Revision History
A building energy assessment is a snapshot of conditions that exist during the analysis. The table below
documents any revisions that occur during the assessment process.
Vers Date Description milestones
0.1 16 January 2012 peer reviewed by P.E., CEM, CxA, draft
0.2 16 January 2012 provided to CC Facilities Mgmt for preliminary review final draft
1.0 Report Released Client review
draf
t: w
ork
in p
rogr
ess
Barnes Science Center, Colorado College APPENDIX A
Page A-0
ENERGY ACCOUNTING
The overall purpose of the accounting matrix on the following page quantifies all the energy streamsentering the facility from available data over the past 1 to 2 years. The key element to note is the EUI(Energy Use Index or also known as Energy Use Intensity or even Energy Utilization or Usage Index)which quantifies all the energy consumed within a building into a common unit (Btu) divided by its totalsquare feet.
Please refer to spreadsheet next page.
draf
t: w
ork
in p
rogr
ess
EUI Energy Accounting
Utility: Nat Gas Utility: Colorado Springs Utility
Acct No.: Gas Utility Acct No.:
Electric Meter No: Gas Meter No:
71,402 sf Rate Schedule: ETL (EMC) Gas Rate Schedule: G1C
Years: 2009 - 2011 Gas HVAC
Month Year#Days
/bill
Usage
(kWH)
Peak
Demand
On-Peak kW
($/mo)
Off-Peak
($/mo)
kWH Use
($/mo)
ECA+AC
($/mo)3
Billed Cost
($/mo)4
Unit Cost
($/kWH)
Energy
(kBtu)
Load
Factor5
Use
(ccf)
Energy
(kBtu)Cost
HTHW
(kBtu)
CHW
(kBtu)
Energy
(kBtu)
Consumed
(kBtu)Cost of Energy
EUI
(kBtu/sf)
Cost
($/sf)
DEC 2011 - 80,000 170 $2,400.00 $100.00 $2,000.00 $200.00 $4,000.00 $0.0500 272971 1 0.00 $0.00 648353 0 648,353 921,324.2 $9,186.82 12.90 $0.13
NOV 2011 31 85,350 175 $2,591.35 $182.99 $2,178.77 $415.80 $6,290.69 $0.0737 291226 0.654 0.00 588173 0 588,173 879,399.1 $10,996.07 12.32 $0.15
OCT 2011 32 87,150 169 $2,608.30 $164.33 $2,189.57 $425.40 $6,328.82 $0.0726 297368 0.671 0.00 359560 139388 498,948 796,316.1 $9,832.55 11.15 $0.14
SEP 2011 29 80,550 165 $2,474.56 $34.01 $2,124.23 $347.36 $5,850.10 $0.0726 274848 0.702 0.00 256230 404307 660,537 935,384.4 $9,719.32 13.10 $0.14
AUG 2011 30 81,750 149 $2,310.97 $38.85 $2,187.20 $317.25 $5,737.17 $0.0702 278942 0.759 0.00 208160 558442 766,602 1,045,544.4 $9,915.44 14.64 $0.14
JUL 2011 29 87,600 178 $2,730.17 $0.00 $2,370.30 $332.40 $6,378.95 $0.0728 298903 0.707 0.00 222825 548872 771,697 1,070,600.1 $10,631.47 14.99 $0.15
JUN 2011 32 88,800 159 $2,693.35 $0.00 $2,356.06 $343.20 $6,351.65 $0.0715 302998 0.726 0.00 329500 160006 489,506 792,503.6 $9,707.67 11.10 $0.14
MAY 2011 29 79,200 163 $2,505.46 $0.00 $2,122.56 $116.03 $5,599.41 $0.0707 270241 0.696 0.00 424405 59616 484,022 754,263.2 $9,262.93 10.56 $0.13
APR 2011 29 77,850 170 $2,606.06 $0.00 $2,142.35 ($86.10) $5,503.09 $0.0707 265635 0.658 0.00 93988 22489 116,477 382,112.1 $6,356.20 5.35 $0.09
MAR 2011 29 74,700 154 $2,360.48 $0.00 $2,001.19 ($79.80) $5,088.63 $0.0681 254887 0.697 0.00 300000 0 300000 554,886.9 $7,488.63 7.77 $0.10
FEB 2011 32 85,800 160 $2,496.05 $133.40 $2,196.48 ($422.46) $5,469.55 $0.0637 292762 0.700 0.00 500000 0 500000 792,761.6 $9,469.55 11.10 $0.13
JAN 2011 29 81,000 171 $2,288.79 $211.65 $2,081.88 ($473.10) $5,146.02 $0.0635 276383 0.682 0.00 500000 0 500000 776,383.3 $9,146.02 10.87 $0.13
Subtotals 331 989,750 165.3 $30,065.54 $865.23 $25,950.59 $1,435.98 $67,744.08 $0.0684 3,377,166 0.692 0 0.00 $0.00 4,431,194 1,893,120 6,324,314 9,701,479 $111,712.67 135.87 $1.56
DEC 2010 #DIV/0! 0 ###### [8] [8] [8] [8] [8] [8] [8]
NOV 2010 #DIV/0! 0 ###### [8] [8] [8] [8] [8] [8] [8]
OCT 2010 #DIV/0! 0 ###### [8] [8] [8] [8] [8] [8] [8]
SEP 2010 #DIV/0! 0 ###### [8] [8] [8] [8] [8] [8] [8]
AUG 2010 #DIV/0! 0 ###### [8] [8] [8] [8] [8] [8] [8]
JUL 2010 #DIV/0! 0 ###### [8] [8] [8] [8] [8] [8] [8]
JUN 2010 #DIV/0! 0 ###### [8] [8] [8] [8] [8] [8] [8]
MAY 2010 #DIV/0! 0 ###### [8] [8] [8] [8] [8] [8] [8]
APR 2010 #DIV/0! 0 ###### [8] [8] [8] [8] [8] [8] [8]
MAR 2010 #DIV/0! 0 ###### [8] [8] [8] [8] [8] [8] [8]
FEB 2010 #DIV/0! 0 ###### [8] [8] [8] [8] [8] [8] [8]
JAN 2010 #DIV/0! 0 ###### [8] [8] [8] [8] [8] [8] [8]
Subtotals 0 0 #DIV/0! $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! 0 ###### 0 0.00 $0.00 0 0 0
DEC 2009 34 #DIV/0! 0 ###### [8] [8] [8] [8] [8] [8] [8]
NOV 2009 31 #DIV/0! 0 ###### [8] [8] [8] [8] [8] [8] [8]
OCT 2009 32 #DIV/0! 0 ###### [8] [8] [8] [8] [8] [8] [8]
SEP 2009 28 #DIV/0! 0 ###### [8] [8] [8] [8] [8] [8] [8]
AUG 2009 30 #DIV/0! 0 ###### [8] [8] [8] [8] [8] [8] [8]
JUL 2009 29 #DIV/0! 0 ###### [8] [8] [8] [8] [8] [8] [8]
JUN 2009 32 #DIV/0! 0 ###### [8] [8] [8] [8] [8] [8] [8]
MAY 2009 30 #DIV/0! 0 ###### [8] [8] [8] [8] [8] [8] [8]
APR 2009 29 #DIV/0! 0 ###### [8] [8] [8] [8] [8] [8] [8]
MAR 2009 31 #DIV/0! 0 ###### [8] [8] [8] [8] [8] [8] [8]
FEB 2009 29 #DIV/0! 0 ###### [8] [8] [8] [8] [8] [8] [8] JAN 2009 30 #DIV/0! 0 ###### [8] [8] [8] [8] [8] [8] [8]
Subtotals 365 0 ####### $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! 0 ###### 0 0.00 $0 0 0 0
[1] Utility measured kW On-Peak at 15 minute intervals [6] HDD: Fahrenheit-based heating degree days for a base temperature of 65F (est. avg error = 0.8%)
[2] Monthly Power Factor data not availble [7] CDD: Fahrenheit-based cooling degree days for a base temperature of 65F (est. error = 0.4%)
[3] Electric Cost Adjustment plus Access Facility Daily Charge [8] Electrical meter installed in June of 2009; Btu Meters installed winter of 2011
[4] Billed cost is monthly service charge, not sum of usage, demand, and ECA charges. [9] Quantifying accurate central plant Btu costs in progress; assumed HTHW @ $8.00 /MMBTU & CHW @ $4.50 /MMBTU
Energy Use Index
Facility:
Address:
City|ST|Zip:
Gross Area:
Barnes Science Center, Colorado College
1040 N Nevada Ave
Colorado Springs, CO 80903
Colorado Springs Utility
9604956600
544004
None – verify
Electricity Totals
Work in Progress Page A-1 of 1
draf
t: w
ork
in p
rogr
ess
Barnes Science Center, Colorado College APPENDIX B
Page B-0
ENERGY STAR RATING
Fiscal year 2009 utility data was entered into the EPA Energy Star Portfolio Manager database resultingin the report include on the pages to follow.
One purpose of the Energy Star “STATEMENT OF ENERGY PERFORMANCE” is to compare to othersimilar buildings using the Environmental Protection Agency’s (EPA’s) Energy Performance Scale of 1–100, with 1 being the least energy efficient and 100 the most energy efficient. However, at this time,higher education facilities except for dorms / residence halls are not rated.
draf
t: w
ork
in p
rogr
ess
Barnes Science Center, Colorado College APPENDIX C
Page C-0
MASTER FINDINGS LIST
The overall purpose of the Master List of Findings is to identify improvement measures including ECM’s,R&M’s, and CIP’s that upon implementation will improve building and system performance to meet theOwner’s project requirements of energy and O&M cost reduction, and/or improve the indoorenvironmental quality.
Please refer to spreadsheet next page.
draf
t: w
ork
in p
rogr
essRCx Master Findings List
ECM Description Issue / Deficiency / Opportunity Recommended ImprovementEstimated Cost
Range [1]
1
Fume Hood Face
Velocity Exhaust Control
Fume hoods are notorious energy consumers in all
academic and research laboratories.
Approximately 8 existing fume hoods have been successfully
retrofitted with Siemens Fume Hood Controllers interlocked with a
variable volume exhaust damper. Recommend retrofitting remaining
27 fume hoods.
$7500 to $11,500
per fume hood
2
PF (Power Factor)
Correction
CSU penalizes customers for lagging PF as described in
the Electrical Costs, Usage, Demand, and Power Factor
section of the Preliminary Site Assessment, this facility
has recorded a lagging PF below 0.95 (refer to report
and Appendix A Energy Accounting Matrix).
Investigate power factor correction devices including an automatic
device (capacitors switched by contactors) at service entrance and at
motors to decrease the magnitude of reactive power.~$10,000
(Berwick Electric
currently
estimating)
3
Retro-commissioning
with focus on Control
Sequence Tune-up and
Optimization
Observed existing control strategies that may not be
providing optimum control for thermal comfort and
energy savings, such as adjusting setpoints, increase
deadband, economizer control, optimum start/stop,
staging, hot/cold deck reset, etc. Heating setpoint
dropped to 68°F on 7 November 2011 with significant
results; refer to ECM section of Preliminary Site
Assessment report for detail.
Perform DDC control optimization by point-to-point commissioning to
ensure correct operation for each HVAC system. Review all
sequences for occupied, unoccupied, warm-up, and cool-down
modes of operation for AHU’s. Studies conducted by LBNL
(Lawrence Berkeley National Laboratory) and PECI (Portland Energy
Conservation, Inc.) indicate retro-commissioning services result in
energy cost savings ranging from 5% to 30%.
$9,500 to $18,000
depending on the
depth & rigor of
RCx scope
4
Owner Training for
Systems
Recommissioning
O&M staff may not have readily available resources to
judge if existing building energy systems are operating
per design intent or at optimized and tuned steady-state.
Provided tuned system parameter benchmarking to maintenance
personnel after retro-Cx. Provide additional training to maintenance
personnel on tuned systems to ensure optimal system operation.
$9,500 to $18,000
depending on the
depth & rigor of
RCx scope
5
TAB Services & Building
Pressure Static Control
Tune-up
During the post-construction test, adjusting, and
balancing of the system, the TAB contractor provides the
temperature controls contractor a static pressure value
required to ensure the farthest VAV terminal unit is
supplied adequate pressure to operate at the design
airflow.
For this project, a 1.0 inch w.g is utilized as the target static pressure
according to the documented sequences of operation. Recommend
validation during retro-commissioning process through system air re-
balancing, measurement, and validating if this static pressure
setpoint values could be reduced.
Certified TAB
contractor up to
$20,000
depending on the
depth & rigor of
TAB scope
6
Premium Efficiency
Motors
Based on accelerated testing of motor insulating
materials, life expectancy of electric motors averages 15
to 17 years. AHU-D motor and a couple others have
already been upgraded by attrition.
Recommend replacement of 5 hp+ with NEMA Premium efficiency
motors; smaller motors by attrition. Cost avoidance (an action taken
in the present designed to decrease costs in the future) may be
considered in energy cost reduction calculations.
Installed cost of
(1) premium 10 hp
motor estimated at
$2400
7
Sensor Location
Optimization
Wall sensors in some classrooms are across room from
RA grille and may not be measuring representative
space temperature.
Review feasibility of relocating sensors to optimum location or return
air openings to augment light fixture slots. Include in retro-
commissioning
scope
RCx Preliminary Assessment Phase Issues Log Project: Barnes Science Center
APPENDIX C
draf
t: w
ork
in p
rogr
essAPPENDIX C
RCx Preliminary Assessment Phase Issues Log Project: Barnes Science Center
8
Reduce HVAC operating
time / Optimize TOD
(Time of Day) Schedules
Observed several unoccupied spaces in the occupied
mode for relatively long durations.
Recommend review of BAS TOD schedule operating parameters for
occupied periods including coordination with the weekly published
"Colorado College Room Usage and Equipment Requirements".
Also recommend space overrides and possibly multiple unoccupied
setpoints.
Include in retro-
commissioning
scope
9
HWP Differential
Pressure Setpoint
Optimization
Often VFD setpoint values for differential pressure
setpoints are set arbitrarily during construction.
Recommend measurement and validation of optimum pressure drop
across furthest or worst case heating coil, and tune the sequence of
operation.
Include in retro-
commissioning
scope
10
Reduce HVAC operating
time / Optimize TOD
(Time of Day) Schedules
Observed several unoccupied spaces in the occupied
mode for relatively long durations; observed AHU A-I
occupied schedule programmed for Sunday through
Saturday, 7:00 a.m. to 6 p.m.
Recommend review of BAS TOD schedule operating parameters for
occupied periods including coordination with the weekly published
"Colorado College Room Usage and Equipment Requirements".
Also recommend space overrides and possibly multiple unoccupied
setpoints.
Include in retro-
commissioning
scope
11
Optimum Start-Stop
Control Strategy
Optimal start-stop is a control strategy that compares the
occupied-period setpoints with the actual space
temperature and determines how long it will take to
recover to setpoint; this algorithm reduces fan system
operation by about 5-10% while ensuring that space
temperatures are at setpoint prior to occupancy.
Optimize HVAC system start /stop time through a PID algorithm to
bring building within specified comfort parameters by scheduled
occupied time and "coast" system to unoccupied period. Note
ASHRAE Standard 90.1 mandates optimal start-stop control of all fan
systems over 10,000 CFM in capacity to eliminate unnecessary
heating.
Include in retro-
commissioning
scope
12
Outdoor Air Delivery
Monitoring with Air Flow
Measuring Stations
"To measure is to know" (Lord Kelvin). Air handlers may
be over-ventilating both unoccupied and occupied
spaces.
Air flow stations shall utilize thermal based air measurement. The
sensor accuracy shall read airflow rates within ±2% of reading with
±2% repeatability
and temperature within ±0.15 deg F.
Estimate available
upon request
13
HW Coil PD (pressure
drop) reduction
Fouled AHU HW and CHW coils increase airflow
resistance and fan energy up to 20%.
Recommend measuring pressure differential across coil and
chemical or steam clean coils per industry standard to reduce fan
energy.
Estimate available
upon request
14
Greenhouse
Environmental Control
Systems Optimization
Observed during operation, a small "dead band"
between heating and evaporative cooling/fan operation.
Recommend system tune-up to match the academic and research
temperature and humidity requirements of each greenhouse. Estimate available
upon request
15
Reduce Duct Leakage On average, almost 15% of cooling energy is wasted
due to HVAC system air leakage; some studies have
quantified energy costs due to duct leakage as high as
$5 cfm per year.
Seal existing duct, accessories, and equipment to reduce leakage.
Consider new technology of injecting a fog of aerosolized sealant
particles into a pressurized duct system.Estimate available
upon request
16
Infiltration Reduction Observed gaps at door head, sill, and at jambs. Some
doors appear to be out of plumb requiring adjustments,
new gaskets or resetting (reference APPENDIX D:
Photo Log of Identified Deficiencies and Appendix I
Infrared Thermography).
Replace all head and jamb seals, and sill sweeps (Refer also to R&M
(Repair and Maintenance) section regarding door alignment). Caulk
all exterior and interior wall penetrations. Cost estimation to be
performed during RCx Investigation Phase.
Estimate available
upon request
Work in Progress Page C-2 Level I
draf
t: w
ork
in p
rogr
essAPPENDIX C
RCx Preliminary Assessment Phase Issues Log Project: Barnes Science Center
17
Lighting Retrofit /
Upgrades
Observed incandescent & original building T-12
fluorescent fixtures in mechanical spaces.
Upgrade all remaining fluorescent fixtures with T-12 lamps and
magnetic ballasts with T-8 25W lamps and electronic ballasts. Estimate available
upon request
18
Lighting Optimization &
Capacity Reduction |
Corridors, Toilets &
Stairwells
Lighting fixtures have been upgraded to indirect T-8
fixtures (reference APPENDIX D: Photo Log of
Identified Deficiencies).
IESNA (Illuminating Engineering Society of North America)
recommends 10-15-20 fc for areas of egress. Safety issues trump
energy cost reduction, however, de-lamping existing fixtures should
be reviewed. Recommend measuring illumination levels throughout
building to identify spaces above IESNA Lighting Handbook levels
and ANSI / ASHRAE / IESNA Standard 90.1-2004 densities. Review
opportunity to add split ballast switching, occupancy sensors, de-
lamping, etc. to reduce the lighting runtime based on need.
Estimate available
upon request
19
Light reduction controls
per IECC 505.2.2.1
For areas not controlled by an occupant-sensing device,
it is required to have a manual control to also allow
occupants to reduce the connected lighting load in a
reasonably uniform illumination pattern by at least 50
percent.
Per IECC 2006, 505.2.2.1 Lighting reduction may be achieved by
dual switching of alternate rows of luminaires, alternate luminaires or
alternate lamps; switching the middle lamp luminaires independently
of the outer lamps; switching each luminaire or each lamp; or other
methods.
Estimate available
upon request
20
Lighting Controls |
Classrooms, Restrooms,
Storage, Offices
Utilize dual technology type occupancy sensors to reduce lighting
runtimes based on need. Also consider lighting occupancy controls
for some spaces to combine daylight-harvesting control to turn lights
off or to dim when enough ambient daylight is available while room is
occupied.
Estimate available
upon request
21
Pneumatic Compressed
Air System leakage
reduction
Air leakage in pneumatic control system results in lower
end-of-line pressures and loss of control.
Recommend isolating and repairing leak, and verifying proper
operation. A single 1/32" diameter hole leaking 1 scfm at $0.06 kWh
costs expends over $100 per year of electrical costs. Estimate available
upon request
22
Lab Exhaust
Optimization
The number of air changes in the original design may
not correspond with actual use of laboratories and
classrooms.
Recommend studying design intent and verifying actual design
implementation or if adjustments have been made during
recommended retro-commissioning process
Recommend
including in RCx
scope
23Cogged Belts Observed fan motor belts are standard V-type. Cog type belts fit in standard sheaves and can reduce up to 2%
power consumption. Recommend switching on an attrition basis. Estimate available
upon request
24
Replace OA Fan & Zone
Exhaust with Heat
(energy) Recovery
system
Make-up air ventilation systems require large amounts of
energy during heating season to temper air for space
comfort levels.
Review countercurrent heat exchange solutions that recover energy
between the inbound and outbound air flow. Estimate available
upon request
Work in Progress Page C-3 Level I
draf
t: w
ork
in p
rogr
essAPPENDIX C
RCx Preliminary Assessment Phase Issues Log Project: Barnes Science Center
25
Measurement &
Verification Through
Submetering
To reiterate, "To measure is to know" (Lord Kelvin).
Currently unable to quantify building process loads from
HVAC fans and pumps and lighting.
Recommend monitoring device (Lon compatible if possible to match
CC standards) to measure true RMS Power in Watts, power factor,
and energy in Watt-hours plus peak demand in ratchet periods.
Accumulation of energy data for analysis is important for ECM cost
allocation.
Recommend
including detailed
M&V plan in RCx
scope
26
Owner Training for
systems
Recommissioning
O&M staff may not have readily available resources to
judge if existing building energy systems are operating
per design intent or at optimized and tuned steady-state.
Provided tuned system parameter benchmarking to maintenance
personnel after retro-Cx. Provide additional training to maintenance
personnel on tuned systems to ensure optimal system operation.
Recommend
including in RCx
scope
27
Lighting Optimization &
Capacity Reduction
New IESNA data indicates spaces occupied by
populations under 25 years old may be over illuminated.
Consider de-lamping spaces over lit by IENSA standards accordingly
to space needs.Recommend
review by CC FM;
perform in-house
28
HW Demand Reduction Domestic hot water is furnished via HTHW heat
exchanger in basement delivered at setpoint 125°F;
recirculation pump control not apparent and recommend
further investigation.
Facilities Management reports installation 1.5 GPM aerators on
lavatories. Recommend review of all low flow aerators on non-critical
lavatory faucets. Tune operation of recirculation pump. Check for
leakage.
Estimate available
upon request
29
Air Filtration Upgrade Large quantity of air (as-built documents lack detailed
mechanical equipment schedules) is filtered during peak
occupancy.
Review opportunity to reduce energy through use of long life lower
pressure drop air filters with equal or better efficiencies than currently
used.
Estimate available
upon request
30
Transformer Upgrade Older dry-type, three phase ventilated transformers
perform at lower efficiencies and have greater heat
losses than current equipment.
Replace original 480 volt to 208/120V electric transformers with new
dry type energy efficient transformers meeting the NEMA TP-1
energy efficiency levels.
Estimate available
upon request
31
Exterior Door Infiltration Of exterior 3-0x7-0 doors sampled, some were out of
alignment with air gaps at jambs and worn weather-
strips around door (refer also to appendix C).
Realign doors then replace all weather strip and threshold sweeps.
Remove existing caulk, clean prep and re-caulk at jamb.No to low cost if
performed by FM
CC
32
Vending Machine
Economizers
Campus building occupancy rates average 33%
annually; vending machine lights and compressors
typically operate 8760 hrs / yr. A typical vending
machine costs $300 of electricity per year to operate.
Recommend Vending Miser or equal device to power down a
vending machine during unoccupied periods and automatically
repowers the vending machine when the area is reoccupied. An
intelligent controller uses fuzzy logic to learn from the habits of the
building occupants, and modifies the time-out period accordingly.
$250; typ.
payback < 2 years
33
Plug Load Reduction Observed lab equipment, laptops, PC monitors, etc. on
during unoccupied evening hours. On an individual
basis, power consumption is minimal, however, an
accumulated wattage from dozens of pieces of
equipment left on when not in use is significant.
Recommend utilizing a student team to survey facility for PC's, lab
equipment, monitors, copiers, printers, speakers, etc. operating
unnecessarily in the standby mode, after hours or weekends. Also,
recommend cataloging by spreadsheet devices consuming standby
power in "sleep" mode.
No cost if
managed
internally
Work in Progress Page C-4 Level I
draf
t: w
ork
in p
rogr
essAPPENDIX C
RCx Preliminary Assessment Phase Issues Log Project: Barnes Science Center
34
Behavioral Modification Operational changes such as turning off lights when
daylight is adequate or turning off lights during
unoccupied periods may result in significant energy
reduction.
Implement reward program to reduce energy consumption via
behavioral modification of facility occupants, i.e. turning off lights,
equipment, PCs when not in use.
No cost if
managed
internally
NOTES
[1]
[2]
ECM's are not necessarily interactive.
ECM cost estimation source is RS Means.
Work in Progress Page C-5 Level I
draf
t: w
ork
in p
rogr
essRCx Master Findings List
CIP Description Issue / Deficiency / Opportunity Recommended ImprovementEstimated Cost
Range [1]
1
BAS Upgrade from DDC-
Pneumatic hybrid
Current energy management control system is a Siebe
Environmental Control DMS-3500 DDC-Pneumatic
hybrid; DMS system is several DDC generations old,
and manufacturer is no longer producing replacement
parts or directly supporting equipment.
DDC systems solid-state sensors and controllers offer considerable
energy-efficiency advantages over conventional pneumatic systems.
Substantial savings are realized in calibration and maintenance, but
the critical value lies in the accuracy and reliability of the DDC
systems. These features can yield operational energy savings of 15%
Long Technology
2
Demand Control
Ventilation (DCV)
Observed several classrooms, faculty offices,
observatory, work areas, etc. not occupied during
scheduled BAS occupancy times. Monitoring occupant
emitted carbon dioxide to quantify occupancy and
accordingly modulate outdoor air dampers to adjust
ventilation rate appropriate to the condition.
Investigate feasibility of CO2 sensors to monitor the average level in
relation to the outdoor level in assembly and other key spaces at the
breathing level of 48" to 60" above finish floor for input to modulate
OA dampers to maintain CO2 setpoint per ASHRAE 62.1.(Waiting on cost
estimate from
Aircuity rep)
3
Building & Lab Air
Handling Units
Existing air handler unit age approaching 24 years;
median service life of an AHU is 20 years.
Recommend complete refurbishment of AHU.
Estimate pending
4
Anatomy/Science Lab
And Animal Suite
Existing system age including heat wheel approaching
24 years; one disadvantage to heat wheels is the
potential for cross contamination due to leakage or
wheel surface carryover.
Consider heat recovery system utilizing pumped coils.
(Waiting on cost
estimate from
Konvecta rep)
5
Scientific Equipment
Upgrades: Ultra-low
refrigeration equipment
Some refrigeration equipment observed to be passed
expected service life.
Consider upgrades to higher efficiency equipment. Also refer to
manufactured data included in appendix J.Request faculty
support for cost
estimation
6
Scientific Equipment
Upgrades: environmental
chambers
Laboratory environmental chamber equipment observed
to be passed expected service life. Please reference
appendix C photo log of deficiencies and opportunities.
Consider upgrades to higher efficiency equipment. Also refer to
manufactured data included in appendix J. Request faculty
support for cost
estimation
7
Scientific Equipment
Upgrades: Biological
Incubator
Laboratory incubator equipment observed to be passed
expected service life.
Consider upgrades to higher efficiency equipment.Request faculty
support for cost
estimation
8
Low Flow Fume Hoods Exhaust systems in academic and research laboratories
combined with the conditioned air required to replenish
and pressurize the buildingis a source of great energy
consumption.
Constant volume low flow fume hood manufacturers include
LabCrafters Inc. & Berkeley Hood. Request faculty
support for cost
estimation
Project: Barnes Science Center RCx Preliminary Assessment Phase Issues Log
APPENDIX C
draf
t: w
ork
in p
rogr
essAPPENDIX C
Project: Barnes Science Center RCx Preliminary Assessment Phase Issues Log
9
Roof Insulation Upgrade Roof replacement project possibly budgeted for future
capital project (current roof estimated at 8 to 10 years
old) [verify]; replacement projects are an excellent
opportunity to add insulation cost effectively.
Provide additional layer of rigid roof insulation as part of a re-roofing
capital project. Further investigation into campus master plan
required during next phase prior to cost estimation and
recommending improvement.
May include spray
foam on the
underside of the
top floor deck
10
Unoccupied/Occupied
Air Change Rates for
Labs
Forthcoming Forthcoming
Forthcoming
11
Reduce HVAC operating
time / occupancy
sensors
Observed several unoccupied spaces in the occupied
mode for relatively long durations.
Recommend incorporating classroom & lab occupancy sensors to
both reduce or turn off lighting and adjust space setpoint to
unoccupied accordingly.
Recommend
including in BAS
upgrade scope
12
Greenhouse Window
Replacement
The existing greenhouse window systems appear to be
single glazed [CC FM Gary Griffin to verify]
The costs of new replacement windows for any facility may be
difficult to justify for a capital improvement project. After verification,
cost estimation
during offered
during next phase
NOTES
[1] CIP ROI calcs and labor/material cost estimation provided in next phase Level II Energy Audit or RCx.
Work in Progress Page C-2 Level I
draf
t: w
ork
in p
rogr
ess
Barnes Science Center, Colorado College APPENDIX D
D-1 of 18
PHOTO LOG OF IDENTIFIED DEFICIENCIES AND OPPORTUNITIES
Following photos depict finding, issue, deficiency, or opportunity for either an ECM (energy cost
reduction measures) or a R&M item as keyed to Master Finding List.
R&M: Pressure differential gauge not connected, therefore not functional (at least one other gauge observed in this condition).
One of the existing fume hoods have been successfully retrofitted with Siemens Fume Hood Controllers interlocked with a variable volume exhaust damper. Only 8 of the 35 existing fume hoods have been retrofitted to limit face velocity to 100 fpm when not in
use.
Plate and frame heat exchanger located in basement of Barnes required to separate 20% glycol-water chilled water solution due to potential freezing in the semi – insulated perimeter chases of Olin Hall.
15 hp chilled water pump serving Olin Hall observed operating at 50° F outside ambient temperature circulating approximately 70°F water.
draf
t: w
ork
in p
rogr
ess
Barnes Science Center, Colorado College APPENDIX D
D-2 of 18
New data center dry cooler with economizer; BAS observations indicating operating correctly
Lab exhaust air handler systems exhibit good maintenance practices
Cogged type belts increase efficiencies per manufacturer’s ratings by 2 to 5%
Equipment and piping are well labeled with directional flow arrows
draf
t: w
ork
in p
rogr
ess
Barnes Science Center, Colorado College APPENDIX D
D-3 of 18
Water damaged fiberglass insulation may reduce
insulating value up to 80%
Building relief fans
draf
t: w
ork
in p
rogr
ess
Barnes Science Center, Colorado College APPENDIX D
D-4 of 18
Recommend weatherstripping upgrade for mechanical room
door
See photo door below from interior; lab AHU exhaust stack seen from the top of roof
Observed damaged fiberglass piping insulation in several locations; recommend outsourcing a repair program & spreading cost several
facilities
draf
t: w
ork
in p
rogr
ess
Barnes Science Center, Colorado College APPENDIX D
D-5 of 18
Noted static pressure value below expected clean filter value as documented on
sheet metal
Hot water pump disconnect in off position; advised CC Facilities Maintenance
Probable water leak and building envelope breach
requiring further review
draf
t: w
ork
in p
rogr
ess
Barnes Science Center, Colorado College APPENDIX D
D-6 of 18
Magnehelic differential pressure gauge not connected
per design intent
Recommend upgrade by attrition all original T12
equipped light fixtures
Observed signs of corrosion at the bottom of unit required attention before unit is breached.
draf
t: w
ork
in p
rogr
ess
Barnes Science Center, Colorado College APPENDIX D
D-7 of 18
Chilled water system drain down observed during site
visit
Observed several Victaulic fittings lacking insulation; refer to previous comment regarding insulation repair &
upgrade program
The larger lamp manufacturers (Sylvania, GE) are phasing out the type PL 13 fluorescent lamp. Lamp on right has
failed.
draf
t: w
ork
in p
rogr
ess
Barnes Science Center, Colorado College APPENDIX D
D-8 of 18
Recommend upgrade by attrition all original T12 equipped light fixtures in Greenhouses
Observed stainless steel thermostat covers absorbing and possibly re-radiating to temperature sensor giving false elevated readings; recommend verification on BAS prior to correcting
See comment above
draf
t: w
ork
in p
rogr
ess
Barnes Science Center, Colorado College APPENDIX D
D-9 of 18
Algae most likely expected in this environment; recommend cleaning heat transfer coil surfaces more often in these spaces.
Ditto, above.
Faculty provided greenhouse climate environment
parameters.
draf
t: w
ork
in p
rogr
ess
Barnes Science Center, Colorado College APPENDIX D
D-10 of 18
Individual greenhouse environmental control system
independent of the BAS
Sampled accuracy of temperature sensor determined acceptable
Safety issue: Recommend staff electrician to review the missing circuit breaker cover
for subpanel ‘SDP’
draf
t: w
ork
in p
rogr
ess
Barnes Science Center, Colorado College APPENDIX D
D-11 of 18
Approximately 4 ultra-low temperature -80°C (-112 ºF) scientific application storage freezers located in Barnes
Science Center
Replacement fluorescent lamps currently stored in the
fifth floor closet
Ditto note above
draf
t: w
ork
in p
rogr
ess
Barnes Science Center, Colorado College APPENDIX D
D-12 of 18
Environmental growth chamber / biological incubator; current equipment used may not be as efficient
as newer models.
Recommend functional testing of lab freezer during retro-
commissioning process
Several pieces of critical lab equipment are on emergency
power
draf
t: w
ork
in p
rogr
ess
Barnes Science Center, Colorado College APPENDIX D
D-13 of 18
Pair of doors exiting to South deck from the observatory area; recommend door alignment with weather-
stripping retrofit.
Recommend phase out of pneumatic actuators on dampers and coils with low voltage replacement systems
Flexible duct observed decomposing possibly due to misapplication for heat removal from environmental growth chambers; recommend insulated hard galvanized sheet-metal duct.
draf
t: w
ork
in p
rogr
ess
Barnes Science Center, Colorado College APPENDIX D
D-14 of 18
Prefilter and filter
assembly examined
Recommend labeling light switch or replacing with pilot light to prevent accidental turning off of critical equipment by switching disconnect label
Recommend verification of heat recovery cleaning procedure is followed to maintain heat transfer
effectiveness
draf
t: w
ork
in p
rogr
ess
Barnes Science Center, Colorado College APPENDIX D
D-15 of 18
Recommend low – leakage damper upgrades as budget allows
Missing section of insulation
post pipe repair
Observed duct liner failure in the air filter assembly
enclosure
draf
t: w
ork
in p
rogr
ess
Barnes Science Center, Colorado College APPENDIX D
D-16 of 18
Pneumatically controlled inlet vanes for 50 hp building AHU removed and replaced with VFD; actuator abandoned in place
More than adequate space to store empty polypropylene glycol containers in the former chiller mechanical room; note expense of glycol purchased by the drum in order to maintain facility temperature during winter due to poor performing building envelope
Periodic cleaning of air intake systems recommended; Facilities Management may consider tasking to supervised
janitorial staff
draf
t: w
ork
in p
rogr
ess
Barnes Science Center, Colorado College APPENDIX D
D-17 of 18
15 hp chilled water pump
serving Olin Hall
Another non-insulated pipe
fitting
Recommend airflow monitoring stations CIP with TAB verification and RCx validation of outdoor ventilation and makeup air rates
draf
t: w
ork
in p
rogr
ess
Barnes Science Center, Colorado College APPENDIX D
D-18 of 18
Stored spare equipment blocking access to water
service entrance
Circuit breaker Lockout for abandoned chiller pump and
the motor control center
Hydronic piping installed above electrical service and
violation of NFPA 70 / NEC
draf
t: w
ork
in p
rogr
ess
Barnes Science Center APPENDIX E
Page E-0
BUILDING OPERATION SCHEDULE
The intent of the attached schedule as part of a Facilities Operation Plan is to meet the objective ofoperating a healthy, comfortable, and energy efficient building.
Please refer to next page.
draf
t: w
ork
in p
rogr
ess
Science Building Heating and Cooling Schedules (Barnes, Olin, Russell T. Tutt Science Center)
Science Buildings / Areas
Heating Season Days per week Cooling Season Days per week Cooling Season Days per week
Barnes Science Laboratory Classrooms (Note 1,2,3,9 ) 24 hrs per day 7 24 hrs per day 7 N/A N/A
Barnes General Classrooms / Offices 6:00 am - 8:00 pm 7 6:00 am - 8:00 pm 7 Evening & night hours 7
Barnes Anatomy / Science Lab (Note 3,4 ) 24 hrs per day 7 24 hrs per day 7 N/A N/A
Olin Laboratory Classrooms (Note 1,5,6 ) 24 hrs per day 7 7:00 am - 6:30 pm 7 Evening & night hours 7
Olin General Classrooms / Offices (Note 6 ) 24 hrs per day 7 7:00 am - 6:30 pm 7 Evening & night hours 7
Olin Fish Bowl (Note 6) 7:00 am - 6:30 pm 7 7:00 am - 6:30 pm 7 Evening & night hours 7
Olin Laboratory Classroom no. 482 (Note 6) 7:30 am - 6:30 pm 7 7:30 am - 6:30 pm 7 Evening & night hours 7
Tutt Science Center (TSC) Lab Classrooms & Animal Lab (Note 7) 24 hrs per day 7 24 hrs per day 7 N/A 7
TSC North Quadrant (All Floors) Classrooms & Offices (Note 6) 7:00 am - 11:00 pm 6 - (Off on Sunday) 7:00 am - 11:00 pm 6 - (Off on Sunday) Evening & night hours 6 - (Off on Sunday)TSC South Quadrant (All Floors) Classrooms, Labs & Offices (Note 8) 24 hrs per day 7 24 hrs per day 7 N/A 7
General Notes:A. Most building space temperatures are continuously monitored and maintained ranging from 70F - 74F depending upon user requirements and surrounding conditions as indicated by schedule.
C. The chiller plant operates only during warm, summer-like months and is normally turned off each day when the outside air temperature drops below 65-68F. Exception: (Note 3,7,8)
E. Building temperatures may not be uniform as "hot" or "cold" spots may exist.
G. This schedule is provided for information only and may be modified by contacting Facilities Services (X6568 or X6017). Schedule is not intended to include every possibility.
Detailed Notes:
2. Barnes Science Laboratory Classroom nos: Basement: 100, 102,104,106,108,110,116,120,128,130.
Third Floor: 305,303,307,323,325,327. Fourth Floor: 411,413,419,421,423,427,432,430,428,426,424,422,420,418,402. Fifth floor: 511,519,525,527,529,516
3. Barnes Science Laboratory Classrooms and Barnes Anatomy / Science and Animal Labs remain air conditioned spaces throughout the year, 24/7 unless scheduled 'OFF' by user.
5. Olin Laboratory Classrooms are not equipped for A/C throughout the year. Olin Lab space temperatures may vary outside the range between 70-74 degrees F. during the summer.
7. TSC Chemical Labs with Fume & Canopy Hoods and Animal Lab area remain air conditioned spaces throughout the year, 24/7 unless scheduled 'OFF' by user.
8. All spaces on all floors south of the Main Lobby in TSC are served by equipment that serve chemical labs 24/7, year round in addition to the animal lab located north of the lobby.
9. Barnes Science Laboratory Classroom space temperatures are not remotely monitored. Exception: Rooms 423 & 427.
Heating and Ventilation Air Conditioning & Ventilation Ventilation Only
Winter Summer
6. Late evening and/or night hours of operation imply that each space may be cooled by typically 'cool' nighttime outside air as conditions may allow.
B. The heating plant operates 'year round' 24 hrs per day. When requested or scheduled, any building space requiring 'heating' may be accommodated by the building mechanical system.
D. Cool outside air normally provides sufficient cooling for most spaces with the exception of large populated spaces such as lecture halls and theatres. Events in these large spaces should be scheduled with Facilities
Services for mechanical cooling.
4. Barnes Basement Anatomy / Science and Animal Lab Room nos. 109, 121,117,119,121,123,125,127,131,129,115,113. Most rooms have occupancy sensors which save energy by turning off the air supply to the room when
unoccupied. The Anatomy/ Science Lab can also be scheduled "off" by the user when it's not in use or when it's not required.
1. During summer-like conditions, lab experiments requiring 24/7 indoor environmental control are best accommodated in Barnes Science Lab Classrooms and should be coordinated with Facilities Services.
F. Building energy use is minimized by turning systems 'off' or 'setting back space temperatures' in buildings when not in use or when partially occupied. For example: weekdays during evening and/or night time hours of
operation including weekends, block breaks, Christmas break and holidays. This means that the heating/cooling will be scaled back when the building is, for the most part, unoccupied; temperatures may fall or rise
accordingly.
2/6/20128:52 PM SciencesBldgSchedRev6
draf
t: w
ork
in p
rogr
essArmstrong Hall APPENDIX E
Page E-1
APPENDIX E – Equipment and Systems Asset InventoryThe following matrix indicates the specific systems to target for energy assessment, primarily all HVAC, domestic water heating, and lighting systems:
SystemEquipTag
Data Collection
Manufacturer Model No. Serial No Capacity Notes
HVAC Systems
Building Automation BAS
HW Pumps HWP-1:2
Air Handler Unit AHU-A Trane Climate Changer
Air Handler Unit AHU-B Trane Climate Changer
Air Handler Unit AHU-C Trane Climate Changer
Air Handler Unit AHU-D Trane Climate Changer
Air Handler Unit AHU-E Trane Climate Changer
Air Handler Unit AHU-F Trane Climate Changer
Air Handler Unit AHU-G Trane Climate Changer
Air Handler Unit AHU-H Trane Climate Changer
Air Handler Unit AHU-I Trane Climate Changer
Air Handler Unit AHU-J Trane Climate Changer
Air Handler Unit AHU-K Trane Climate Changer
Air Control System AS-1, ET-1
Exhaust Fans EF1
Exhaust Fans EF2
Exhaust Fans EF3
Exhaust Fans EF4
Air Compressor
draf
t: w
ork
in p
rogr
essArmstrong Hall APPENDIX E
Page E-2
Plumbing Systems
Domestic WaterHeating
DWH-1
Storage Tank ST-1
HW RecirculationPump
HWRP-1
Notes:(1) missing info to be populated during next RCx phase
draf
t: w
ork
in p
rogr
ess
Barnes Science Center APPENDIX F
Page F-0
Utility Rate Schedules
The table below is a snapshot of the Colorado Springs Utilities electrical rate schedule:
Rate Description$2.40 Access/Facilities charge per day$0.0489 Electric supply on-peak, per kWh$0.0203 Electric supply off-peak, per kWh($0.0020) ECA (Electric Cost Adjustment) per kWh$0.5286 On-peak demand, per kW per day$0.3436 Off-peak demand, per kW per day$0.0108 ECC (Electric Capacity Charge) per kWhNotes:On-peak periods Oct. - March: 4 to 10 p.m. Monday through FridayOn-peak periods April - Sept.: 11 a.m. to 6 p.m. Monday through FridayOff-peak periods: all other hours plus legally-observed holidaysSales tax is assessed unless tax exempt status is filed on record with CSU
Colorado Springs Utilities Natural Gas rate schedule snapshot:
Std Rate Seasonal Description$0.6037 $0.6251 Access charge per day$0.1276 $0.1073 Access charge per CCF$0.6034 - Natural gas cost per CCF
- $0.6597 Natural gas cost Nov. - Apr. per CCF- $0.5225 Natural gas cost May - Oct. per CCF
($0.0550) ($0.0550) Gas Cost Adjustment (GCA), per CCFnote 3 State sales taxnote 3 City sales taxnote 3 County sales tax
Notes:1) 12.01 PSIA pressure base2) Sales tax is assessed unless tax exempt status is filed on record with CSU3) recommend verification through utility billing access
Please refer to next pages for rate schedules.
draf
t: w
ork
in p
rogr
ess
Armstrong Hall, Colorado College APPENDIX G
G-1 of 1
Facility Documentation ChecklistProject: ASHRAE Level I & II analysis
Building: Armstrong Hall
Location: 14 E. Cache La Poudre, Colorado Springs, CO 80903
Updated: 31 October 2011
Building DocumentationDescription Notes
Available
Record Drawings (as-builts) 1966 HVAC only; data center mods 1
Record Dwgs of minor alterations Data Center only
Utility Usage (past 3 years minimum) spreadsheet furnished
Utility bills (copies of recent) 8 samples
Utility provider data
Utility rep contact data
Utility rate schedules CSU ETL
Original project specifications
TAB Report available?
Pump curves
Fan curves
Operation and Maintenance Manuals access to review?
Original submittals
Installation manuals
Equipment manufacturer’s literature
System or Equipment warranties none / verify replacement equipment
Control Dwgs / BAS
Points list though online access
Sequences Of Operation though online access
Hard copy of the program
Lighting control dwgs & submittals
Time of day schedules though online access
Setpoint schedules by zone though online access
Maintenance logs Work Orders?
Current service contracts
Current O&M practices
Building Operation Plan
Previous Energy Audit report not applicable?
Previous commissioning report n/a not applicable
Office equipment info
List of items facility staff considers to bemost significant problems
available through staff interviews
Other: VPN access from Worner Cx project
Notes:1) Requested lighting, wall sections, elevations (bldg envelope), roof plan, RCP, etc.2)
draf
t: w
ork
in p
rogr
ess
BLDG DOCUMENTATION CHECKLIST
BuildingEnergySystemsEngineering&Commissioning
www.besecx.com | [email protected]
Project: ASHRAE Level I & II analysis
Date: 30 August 2011
Building: Barnes Science Center, Colorado College
Location: 1040 North Nevada Avenue, Colorado Springs, CO 80903
Contact: Emily Wright, Colorado College Sustainability Coordinator
Building DocumentationEquipment or System
Energy Mech Lighting Envlpe Special other
Record Drawings (as-builts) includingrenovations, alterations, etc.
Utility bills (past 3 years minimum)
Utility provider contact data
Utility rate schedules
All Operation and Maintenance Manuals
TAB Report
Fan & Pump curves
Original submittals
Installation manuals
Original project specifications
Equipment manufacturer’s literature
Control dwgs / sequences of operation
Current service contracts
Time of day schedules
Maintenance logs
Current O&M practices
List of items facility staff considers to bemost significant problems
Building Operation Plan
Previous Energy Audit report
Previous commissioning report
Kitchen Appliance info
Office equipment info
Other: VPN & BAS access
Other:
Other:
draf
t: w
ork
in p
rogr
ess
Armstrong Hall, Colorado College APPENDIX H
H-1 of 2
HVAC Equipment and Components Service Life EstimatesThe following Table from 2008 ASHRAE Handbook HVAC Applications offers median service lives forvarious HVAC equipment and components:
From Commercial Energy Auditing Reference Handbook, 2008, Steve Doty, P.E., CEM:
draf
t: w
ork
in p
rogr
ess
Armstrong Hall, Colorado College APPENDIX H
H-2 of 2
draf
t: w
ork
in p
rogr
ess
Barnes Science Center APPENDIX I
Barnes Science Center I-1 of 2
Infrared Thermography Survey
The intent of this infrared thermography survey was to identify excess energy loss through the building openings. The
main objectives were to identify missing thermal insulation, thermal bridges, and air leakage. Also, since water is an
excellent conductor of heat, latent moisture behind a building element may be detected behind cool surfaces appearing
colder or detected behind warm surfaces as warmer.
For this project, the IR camera was utilized as a tool to capture the infrared light spectrum of heat energy flow in or out
of the building envelope. Typically, a bright white color represents the higher temperature, and the darker purplish
colors indicate colder surfaces or moisture. In some cases, this may reverse later in the day or evening, due to higher
thermal capacitance of wet objects as the building cools in the evening, as the moisture in materials retains heat. This
evaluation is based on quantitative measurements, with the emissivity set to most common existing materials (typically
brick veneer). For further discussion, please refer to the summary of methodology in the main body of the report.
ASNT-ASTM IR BUILDING SPECIFIC DATA
DATE 4 November 2011
O.A.T Range: 31F to 34F
I.A.T Range: 69.0F to 72.0F (source: BAS)
T F Range: 38F to 43F
Outside – Rh | Inside Rh 43% | 40.2%
WIND SPEED 3.8 mph to 4.2 mph
BLDG VINTAGE | AREA 23 Yrs | 69,000 gross ft2
FLOORS Basement, 1st through 3
rd
WEATHER CONDITIONS Clear | Slight Breeze
PRIOR WEATHER <2” snow in previous 48 hours
Photo 1: South Façade of Barnes Science Center
draf
t: w
ork
in p
rogr
ess
Barnes Science Center APPENDIX I
Barnes Science Center I-2 of 2
Location: West Entrance
Photo 2: White-yellow heat signature denotes higher surface temperature readings
Location: West Entrance Ramp
Photo 3: Note bright white high temperature anomalies at basement level; recommend further investigation
Location: South Lobby
Photo 4: Cabinet unit heater in west lobby; spot temperature at cabinet register measured at expected 141°F
draf
t: w
ork
in p
rogr
ess
Barnes Science Center APPENDIX J
Page J-0
ECM and CIP MANUFACTURER CATALOG DATA
Following sheets include data from manufacturers to consider for increasing energy efficiency.
Figure 1: the Phoenix Valve for fume hood applications
draf
t: w
ork
in p
rogr
ess
Barnes Science Center APPENDIX J
Page J-1
Percival Scientific, Inc. Biological Incubators and Environmental Growth Chambers http://www.percival-scientific.com/
draf
t: w
ork
in p
rogr
ess
This Quotation Subject To Your Written Acceptance Within Thirty Days
1. Orders based on this quotation are subject to Air Purification Co.’s terms and conditions of sale and are subject to approval and acceptance by the Air
Purification Company. No Tax is included in the above quoted material. 2. These prices apply only to the specific materials and electrical characteristics listed in the above quotation. 3. All orders with the Air Purification Company are contingent upon strikes, accidents, government demands, inability to obtain materials, or other delays beyond
the companies control. 4. Unless noted above, only standard one-year manufacturer’s warranty is included. 5. All Prices are F.O.B. factory, full freight allowed, unless otherwise stated above.
QUOTATION
Air Purification Company 1861 W. 64th Lane • Denver, CO 80221-2347
(303) 428-2800 • (303) 428-2700 • CO/WY (800) 668-4966
Project: Colorado College -Barnes Bldg Date: 1/17/2011
Phoenix Controls Budget Location: Colorado Springs, CO
To: Colorado College Engineer: N/A
Addenda: N/A
Listed below are general guidelines for budgeting only. The complete work scope should be thoroughly developed on a full set of
bid documents by a professional engineer. The below information was taken from as-built drawings. They have NOT been field verified. The below budget is for parts and startup of the phoenix control system. There’s no other labor for removing existing equipment
and there’s no labor for installing new equipment. There are several contractors and subcontractors that may have to be involved to accomplish the installation.
You may have a General Contractor, Mechanical Contractor, Electrical Contractor, Temperature Control Contractor, or other contractors involved to perform the installations.
Air Purification Company isn’t an Engineer or Contractor.
Base Budget: 32 Phoenix – Low pressure VAV hood exhaust valves w/phenolic coating and high-speed actuators
26 Phoenix – Low pressure VAV general exhaust valves w/high-speed actuators 24 Phoenix – Low pressure VAV supply valves w/high-speed actuators 1 Phoenix – Macroserver point server for BacNet integration
5 Phoenix – 4 point routers 17 Phoenix – Room temperature sensors w/LCD display, slider setpoint and occupancy button
17 Phoenix – Duct temperature sensors 32 Phoenix – Fume hood monitors
32 Phoenix – Vertical sash sensors 24 RIB – Transformers 24 American Coil – Hot water coils
Start-up Total: $311,000
Alternate Budget 32 Zone Presence Sensors Total: $30,464
*All notes and exclusions apply to the base budget and all alternates *Excludes installation, wiring, valve transitions and transitions between valve and coil, control valves for
hot water coils, access doors for coils, hot water piping and fittings, sound attenuators, quick ship fees, *Please note, there are no plans and specifications for this project. The budget was based on discussions with
Colorado College personnel and copies of as-built drawings. The above quotation for the base budget and all of the following alternate pricing is based on past Phoenix Controls projects and standard Phoenix Controls
equipment. Pricing is subject to change as the specification is written and the plans are created. Room Breakout (FOR ACCOUNTING PURPOSES ONLY, the first room(s) will cost way more because of the integration
into the BAS AND we would have to purchase a macroserver, transformer(s), and router(s) even if only one room is done. )
105, 149, 313, 314, 326, 408, 440, 439, 438, 435, 418? $11,378 each room (X 11) 421 and 425 $22,756 each room (X 2)
315, 324 and 520 $15,171 each room (X 3) 325 $94,817
By: Tony Anderson Air Purification Company
draf
t: w
ork
in p
rogr
ess
GOLD SERIES GP1 DUCT AND PLENUM SENSORS
, Inc. 1663 Hwy. 701 S., Loris SC 29569 Toll Free: 800.2 (232.8766) Fax: 843.756.1838 Internet: .com12
TM_G
P1
_R1
H
ing devices will indicate 0 fpm (0 m/s) when thereis no airflow across the sensors. Adding a filter ormoisture eliminator upstream of the airflow meas-uring device may dampen the wind effect on someinstallations.
2. Locate the application diagram in Figure 9 that bestfits your application. Verify that minimum placementdistances can be achieved to ensure proper perform-ance. Minimum distance requirements may necessi-tate relocating dampers or adding an extension�sleeve�. A standoff mounting option is available forapplications where ductwork is unavailable. Followthe placement procedure described in LOCATINGPROBES when the distance exceeds minimumrequirements.
3. The diagrams were developed to achieve an installedaccuracy of 3% of reading (�C� density probes) at lessthan or equal to the louver manufacturer�s maximumfree area velocity (i.e. the louver is applied properly).
4. Select a mounting style, insertion, internal or stand-off, that best suits the installation requirements ofthe application. Mounting styles do not need to bespecified until the product is ordered.
5. The best results can be achieved using one ofEBTRON�s sequencing control strategies which aredescribed in the APPLICATIONS section of theEBTRON�S Engineer�s Catalog for AirflowMeasurement Devices.
OUTSIDE AIR (OA) INTAKE APPLI-CATIONSEBTRON thermal dispersion devices are well suited foroutside air intakes that generally have flow rates lessthan 500 fpm (2.54 m/s). Unlike other technologies,EBTRON sensors do not require a developed velocity pro-file to accurately measure airflow rates and are not sub-ject to fouling in most outside air environments. Eachsensor is independent and can accurately average a vari-able velocity profile without the addition of straight ductor flow straighteners.
OA Intake Probe Placement Procedure
EBTRON offers free software, EBTRON Auto-SelectTool, to assist in optimizing the placement of EBTRONairflow measuring probes in ducts or plenums. Theselection tool uses a Microsoft® Excel® spreadsheetto create a schedule for printing or e-mailing toEBTRON. The latest version of the software can bedownloaded at www.ebtron.com/autoselecttool.
To manually perform the calculations for sensor loca-tion and placement manually, please use the followingprocedure:
1. Locate the airflow measuring device upstream of theoutside air damper (between the louver and thedamper). Determine minimum airflow rate, fpmmin at
the desired location that you wish to place the airflowmeasuring device as follows:
fpmmin=cfmmin/Cross Sectional Area (sq ft).
If the airflow measuring device is located within 10 ftof the intake louver or hood and the airflow rate is lessthan 200 fpm (1.02 m/s) consider relocating the air-flow measuring device, resizing the opening or addinga separate damper for the minimum outside air intake.Installations that do not meet this guideline have beensuccessfully installed and operated. However,EBTRON cannot recommend or approve installationsnot meeting this guideline. This guideline is basedupon the following laboratory and field experience:
a. Systems designed with outside air dampers sized for200 fpm (1.02 m/s) or less may not provide ade-quate control to maintain the desired minimum air-flow setpoint.
b. Transient wind gusts can result in airflow indicationsof 100 fpm (0.51 m/s) or more on outside airintakes, even when the intake damper is closed. A�low-limit� cutoff has been implemented on allGTx116 transmitters (beginning with firmware ver-sion 4.0), to force the output below a specified air-flow value to 0. �False� readings are strictly a result ofair movement induced by winds near the airflow sta-tion on outside air intakes. DO NOT ENABLE ANDADJUST THE OUTPUT SIGNAL OFFSET TO COMPEN-SATE FOR THIS EFFECT. All EBTRON airflow measur-
NOTE
Outside Air intake standoff mounting may result ingreater measurement uncertainty since the effec-tive area may be larger than the area used to deter-mine the volumetric flow rate. Therefore, the use ofthe Field Adjustable Gain and Offset feature may berequired for acceptable accuracy performance.
Figure 8. Typical OA Damper Installation
draf
t: w
ork
in p
rogr
ess
draf
t: w
ork
in p
rogr
essBarnes Science Center APPENDIX K
Page K-0
Building Floor Plans from BAS
Basement Floor Plan
draf
t: w
ork
in p
rogr
essBarnes Science Center APPENDIX K
Page K-1
Ground Floor Plan
draf
t: w
ork
in p
rogr
essBarnes Science Center APPENDIX K
Page K-2
Second Floor Plan
draf
t: w
ork
in p
rogr
essBarnes Science Center APPENDIX K
Page K-3
Third Floor Plan
draf
t: w
ork
in p
rogr
essBarnes Science Center APPENDIX K
Page K-4
Fourth Floor Plan
draf
t: w
ork
in p
rogr
essBarnes Science Center APPENDIX K
Page K-5
Fifth Floor Plan