com .& start-up strategy 120926

Upload: rodinsendiong

Post on 04-Apr-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 Com .& Start-Up Strategy 120926

    1/24

  • 7/31/2019 Com .& Start-Up Strategy 120926

    2/24

    TABLE OF CONTENTS

    1

    1. Objective

    2. Scope of Work

    3. Process Configuration

    4. Priming Fluids5. Commissioning & Start-up Sequence

    6. Schedule

    7. Work Definitions & Flow

    8. Organization & RR Involvement

    9. Areas of Concern

  • 7/31/2019 Com .& Start-Up Strategy 120926

    3/24

    - Implementation of HSE Plan& Procedures

    - Safety Audit- Pre-Startup Safety Review- Safety Training & Emergency Drill- TRA & Risk Assessment

    - Qualified & ExperiencedCommissioning Work Force

    - Develop Detailed Procedures- Implementation of Training- Faultless Execution ofPre-commissioning /Commissioning Activities

    Safe Completion

    Good Performance

    - Well Planned Preparation- Implementation of CMS- Tight Control of Commissioning

    & Start-up Activities/Schedule- Interface Management- Harmonized Communication& Coordination

    Schedule On-Time

    Safety

    QualitySchedule

    1. Objective

    2

    Turnover

  • 7/31/2019 Com .& Start-Up Strategy 120926

    4/24

    Construction

    By UnitBy Subsystem

    50 M

    Punch A Clear

    Commissioning

    Start-up &Stabilization

    Test Run

    2. Scope of work

    3

    Pre-commissioning

    35 M

    By Unit /Discipline

    48 M

    By Subsystem/System

    41 M 44 M

    Punch B Clear Punch C Clear

    Commercial

    Production

    Pre-Commissioning Team

    Construction Team

    Commissioning & Start-up Team

    COMPANY Operation / Maintenance Team

    CONTRACTORs Care, Custody & Control CONTRACTORs Care, Custody & ControlCOMPANYs Assistance

    MC Certificate&

    Ready ForCommissioning

    CommercialProduction

    Certificate &Ready For

    Test Run Certificate

    ProvisionalAcceptanceCertificate &Hand-Over

    Nov.2012 May.2013 Aug.2013 Dec.2013 Feb.2014

    CommissioningCompletion

  • 7/31/2019 Com .& Start-Up Strategy 120926

    5/244

    3.

    Process Units - EPC #1

    Unit No. Unit Name Capacity Licensor / (FEED)

    1 1100 Crude Distillation 417.1 KBPSD (Bechtel)

    2 1110 Sat. Gas Plant 142.4 KBPSD -

    3 1120 Sat. LPG Treating 22.2 KBPSD UOP

    4 1130 Sat. LPG Splitter 23.7 KBPSD (Bechtel)

    5 1210 SR Heavy Naphtha Hydrotreating 68.9 KBPSD UOP

    6 1300 H2 Manufacturing 151.2 kNm3/h Haldor Topsoe (SSW)

    7 1400 Kerosene Hydrotreating 107.8 KBPSD UOP

    8 1510 LGO Hydrotreating 74.8 KBPSD UOP

    9 1520 HGO/LCO Mild Hydrocracking 57.4 KBSPD UOP

    10 1530 MHC H2 Recovery 2 t/h (Bechtel)

    11 1690 Benzene Reduction 26.9 KBPSD UOP

    12 1700 Sour Water Stripping 120 m3/h (Bechtel)

    13 1800 MDEA Regeneration 440 m3/h (Bechtel)

    14 1810 DEA Regeneration TBA (Bechtel)

    15 1900 SRU & TGTU 400 TPSD CB&I

    16 1036 Spent Caustic - (Bechtel)

    17 1045 Acid Gas Flare - -

  • 7/31/2019 Com .& Start-Up Strategy 120926

    6/24

    1100CDU

    1110SGP

    1120/1130LPG Treating

    / Splitter

    1210H/N HDT

    1400Kero HDT

    1510LGOHDT

    1520MHC

    1300HMU

    1690BRU

    CrudeOil

    AR

    LCO/LLCO

    Natural Gas

    H2

    SR Kero

    SR LGO

    SR HGO

    LPG

    HDT H/N, S

  • 7/31/2019 Com .& Start-Up Strategy 120926

    7/24

    1700Sour WaterStripping

    Phenolic SW (RFCC)Non-Phenolic SW

    (Process Units)

    Brine (CDU)

    1800MDEA

    Regeneration

    1810DEA

    Regeneration

    Rich MDEAUnit 1110/1520/1530

    Rich DEAUnit 1600/1220

    1900

    SRU & TGTU

    1045

    Acid Gas Flare

    Stripped Water to WWTUPhenolic Stripped Water to RFCC

    Lean MDEAUnit 1110/1520

    1530

    Lean DEAUnit 1600/1220

    Molten Sulfurto Granulation Plant

    1036

    Spent CausticTreatment

    Acid

    Gas

    Acid

    Gas

    Spent CausticUnit 1120

    Unit 1610/1620

    Oxidized Causticto WWTU

    3.

    6

  • 7/31/2019 Com .& Start-Up Strategy 120926

    8/24

    7

    UnitPriming

    Fluid

    Approx. Required Amount (BBls)Expected

    DateRequired

    Reasons forRequirementTotal EPC1

    EPC 3Intercon.

    Piping

    EPC 4Intercon.

    Piping/Tank

    11001110

    HeavyNaphtha

    6,000 6,000 Same line with Unit 1210Heavy Naphtha feed line

    26 Jun 2013 - Inventorying for facilitates of Initial S/U- Removing remaining water in LPG serviceline to avoid icing during Initial S/U.

    1100LGO

    - Flushing Oil26,600 26,600

    Same line with Unit 1520LGO line

    21 Jun 2013

    - Allows flushing of System & checking outof Rotating Machinery.

    - For cleaning of filters & strainers duringflushing rather than using Crude Oil.

    1110

    1120

    1130

    LPG 1,586 1,500 86 - 25 Jun 2013

    - Allows earlier S/U of Unit 1110, 1120 &1130 before feed off-gas introduction fromUnit 1100

    - Earlier introduction of main feedstock fromexisting Ruwais Refinery

    1210HydrotreatedNaphtha orSR Naphtha

    68,219 46,700 134Line: 925Tank: 20,465

    15 Jul 2013- Allows the pre-sulfiding of catalystper Licensors requirement.

    1400SR Kerosene

    - S/U Oil100,400 79,600 327

    Line: 308Tank: 20,165

    04 Jul 2013- Allows the pre-sulfiding of catalystPer Licensors requirement.

    1510LGO

    - S/U Oil70,963 50,400 134

    Line: 264Tank: 20,165

    06 Jul 2013- Allows the pre-sulfiding of catalyst per

    Licensors requirement.

    1520LGO

    - S/U Oil59,195 58,600 86 Line: 509 06 Jul 2013

    - Allows the pre-sulfiding of catalyst perLicensors requirement.

    - From Unit 1510 LGO Feed Tank

    1900Granular

    Sulfur6 tons 6 tons - - 12 Jul 2013

    - Allows fill-in of Seal Leg & Sultrap to avoidtoxic H2S gas release from SulfurCondenser to Sulfur Degassing Pit

    1300 Methanol 14 tons 14 tons - - 24 May 2013- Allows production of recycle H2 for InitialS/U before feed Natural Gas in.

    - No need if H2 is available from OSBL

  • 7/31/2019 Com .& Start-Up Strategy 120926

    9/24

    8* Tank Volume is based on Min. Operating Volume

  • 7/31/2019 Com .& Start-Up Strategy 120926

    10/24

    UNITS / UTILITY SYSTEM REQUIRED FOR STARTUP BY OTHER EPCS

    EPC #1 UNITS Start-up

    EPC #2

    EPC #3

    EPC #4

    UNIT 1300

    UNIT 1100 UNIT 1110 UNIT 1120 UNIT 1130

    UNIT 1530

    UNIT 1690

    UNIT 1400

    UNIT 1045 UNIT 1900

    UNIT 1510

    UNIT 1520

    UNIT 1036

    UNIT 1210

    UNIT 1800

    UNIT 1810

    UNIT 1700

    UNIT 1600

    Utilities Flare FG

    CrudeStorageTanks

    IntermediateProduct Tanks

    Balance &Product Tanks

    NG

    High Level Unit Interface For Start-up

    9

    ReformateTanks

  • 7/31/2019 Com .& Start-Up Strategy 120926

    11/24

    10

  • 7/31/2019 Com .& Start-Up Strategy 120926

    12/24

    Overall

    11

  • 7/31/2019 Com .& Start-Up Strategy 120926

    13/24

    12

    Unit - Typical

    7 Work Definitions & Flow

  • 7/31/2019 Com .& Start-Up Strategy 120926

    14/24

    13

    7.Work Definitions & Flow

    The System is defined as a major subdivision of an installation, being either

    process or non-process, which performs a major operational function of theunit.

    Each System is further broken down into a Sub-System, which performs agiven operational function, with no or little interference from other Sub-Systems for the Commissioning execution.

    The most efficient way for achieving plant completion in a limited period oftime will be to carry out Pre-commissioning and Commissioning activities bySystems and/or Subsystems according to the predetermined MechanicalCompletion and Commissioning priorities.

    The Pre-commissioning & Commissioning Schedules are prepared based on

    Sub-Systems.

    Each Sub-System will be tied to a database containing all elements of each

    Sub-System for tracking & recording the status of Sub-System MechanicalCompletion and Commissioning.

    System Approach

    7 Work Definitions & Flow (continued )

  • 7/31/2019 Com .& Start-Up Strategy 120926

    15/24

    14

    The System / Subsystem has been erected in accordance with approved drawings,

    specifications and applicable codes.

    Activities include non-operating checks, inspections, testing, adjusting andcold alignment, etc. of equipment, piping, instrumentation, electrical to bringthe System / Subsystem to MC and Ready for Commissioning.

    - Piping Cleaning : Flushing / Air Blowing / Steam Blowing / Chemical Cleaning- Reinstatement & Box-up- Energize Electrical Network- Rotating direction, Driver Solo-run, Alignment- Instrument & Electrical System / Equipment SIT- Loop Test & Functional Checks- Operational Tightness Test- Purging & Inerting (O2 Free)

    Punch List A Clear

    Utilities in service

    7.Work Definitions & Flow (continued..)

    Mechanical Completion incorporating Pre-commissioning

    7 Work Definitions & Flow (continued )

  • 7/31/2019 Com .& Start-Up Strategy 120926

    16/24

    15

    Work Flow for Pre-Commissioning & Mechanical Completion

    7.Work Definitions & Flow (continued..)

    7 Work Definitions & Flow (continued )

  • 7/31/2019 Com .& Start-Up Strategy 120926

    17/24

    7.Work Definitions & Flow (continued..)

    Work Volume _ No. of Components

    16

    7 Work Definitions & Flow (continued )

  • 7/31/2019 Com .& Start-Up Strategy 120926

    18/24

    17

    All works, activities and tests associated with preparing the Plant for theintroduction of feedstock for the purpose of starting initial productionof the end products prior to commencement of Test Runs.

    - Introduce Fuel Gas- Flares / Hydrocarbon Drains activation- Heater Firing & Drying out / Boil out- Catalyst Loading- Initial filling of Chemicals

    - Operational Test

    Priming Fluids Introduction

    Pre-Sulfiding & Cold Circulation

    Punch List B Clear

    Company assist with experienced refinery plant operation supervisoryand shift operating personnel to supplement Contractor Commissioning Team.

    7.Work Definitions & Flow (continued..)

    Commissioning

    7 Work Definitions & Flow (continued )

  • 7/31/2019 Com .& Start-Up Strategy 120926

    19/24

    18

    Work Flow for Commissioning Completion

    7.Work Definitions & Flow (continued..)

    7. Work Definitions & Flow (continued..)

  • 7/31/2019 Com .& Start-Up Strategy 120926

    20/24

    Start-up & Commercial Production Operation

    19

    Feedstock-in

    Initial Start-up & Stabilization

    The plant will achieve stable, safe, continuous operation

    at no less than 80% of guaranteed capacity for a continuous period of 15 daysat guaranteed product quality conditions.

    To demonstrate to Company that Units can be operated safely under alloperating conditions in accordance with Contract

    - At Design Capacity for 72 hrs

    - At Turndown Capacity for 72hrs

    Performance Test Run

    7.Work Definitions & Flow (continued..)

  • 7/31/2019 Com .& Start-Up Strategy 120926

    21/24

    Commissioning & Start-Up Organization Chart

    20

  • 7/31/2019 Com .& Start-Up Strategy 120926

    22/24

  • 7/31/2019 Com .& Start-Up Strategy 120926

    23/24

    22

    1) Early Involvement of Companys Personnel for Integrated One-Team

    - Familiarization with Facilities

    - Witness & Supervision- Training

    2) Interface between with other Contractors

    - On-Time Power Energizing & Introduction of Utilities

    3) PSSR (Pre-Startup Safety Review)- Timing of Implementation

  • 7/31/2019 Com .& Start-Up Strategy 120926

    24/24

    - END -