commissioning status 10022015
DESCRIPTION
Commissioning statusTRANSCRIPT
![Page 1: Commissioning Status 10022015](https://reader035.vdocument.in/reader035/viewer/2022081821/55cf8f0b550346703b985bf9/html5/thumbnails/1.jpg)
PSSR
DAILY COMMISSIONING REPORTFORMAT NO:QMS/SR/12-
F24/01
Site: Kalpakkam Date:10.02.15Unit No: 1x500 MWe PFBR Project Report No:73
PROGRESS: on 09/02/2015TURBINE:
Control Fluid System:
Regeneration Pump is in continuous operation.
Control oil flushing is started on 12.01.15.
Control fluid flushing all the loops charged.
Coolers normalizing under progress.
TDBFP-B:
1. Drive Turbine of TDBFP-B was put in mechanical barring gear on 10.12.14. Max. Speed reach is 384 rpm.
C&I cable not ready from DCS (Customer scope).Cabling works is under progress (Customer scope).
TDBFP-A:
TDBFP-A oil flushing Completed on 25.12.14.
JOP motor trail run completed. (31/01/2015).
Jacking oil lines hydro test completed 120KSC on 06/02/2015.
Barring gear and governing lines hydro test completed on 05/02/2015.
Oil transfer pump motor trail run completed on 06/02/2015.
Oil draining from Lube oil tank completed on 09/02/2015.
Lube oil tank cleaning under progress.
VACCUM PUMP:
Vacuum pump motors 2 nos. trail run completed on 20.11.14.
POWER CYCLE PIPING & PIPING:
1. Main stream line (MS) from SG Nozzle to ESV East side and west side
Steam blowing completed
![Page 2: Commissioning Status 10022015](https://reader035.vdocument.in/reader035/viewer/2022081821/55cf8f0b550346703b985bf9/html5/thumbnails/2.jpg)
2.Feed water line East side steam blowing completed on and West side steam
blowing is to be completed after getting LDO (Customer scope).
OGDHR:
OGDHR motor two numbers electrical testing was completed.
OGDHR motor was run decoupled condition. BOTH the motors
De bearing temperature is reached 85’C. Bearings to be
inspected.
C& I SYSTEM
HMI Engineer from BHEL/EDN for the backup node splitting in
Metso-DNA and for other HMI pending issues.
ERV’s cable checking under progress. 1/7 valves completed.
Logic linking from DCS to BCP(back up control panel) under progress.
Auxiliary Boiler:
Pending points attending are under progress.
PROGRAMME/plan
1. Starting of Control oil flushing after normalizing coolers.
ABNORMALITIES
Distribution1. Head/TSX 2. Site-Planning 3. UCM