PSSR DAILY COMMISSIONING REPORT FORMAT NO: QMS/SR/12-F24/01 Site: Kalpakkam Date:10.02.15 Unit No: 1x500 MWe PFBR Project Report No:73 PROGRESS : on 09/02/2015 TURBINE: Control Fluid System: Regeneration Pump is in continuous operation. Control oil flushing is started on 12.01.15. Control fluid flushing all the loops charged. Coolers normalizing under progress. TDBFP-B: 1. Drive Turbine of TDBFP-B was put in mechanical barring gear on 10.12.14. Max. Speed reach is 384 rpm. C&I cable not ready from DCS (Customer scope).Cabling works is under progress (Customer scope). TDBFP-A: TDBFP-A oil flushing Completed on 25.12.14. JOP motor trail run completed. (31/01/2015). Jacking oil lines hydro test completed 120KSC on 06/02/2015. Barring gear and governing lines hydro test completed on 05/02/2015. Oil transfer pump motor trail run completed on 06/02/2015. Oil draining from Lube oil tank completed on 09/02/2015. Lube oil tank cleaning under progress.

Upload: bidyut100

Post on 20-Dec-2015

3 views

Category:

Documents


0 download

DESCRIPTION

Commissioning status

TRANSCRIPT

Page 1: Commissioning Status 10022015

PSSR

DAILY COMMISSIONING REPORTFORMAT NO:QMS/SR/12-

F24/01

Site: Kalpakkam Date:10.02.15Unit No: 1x500 MWe PFBR Project Report No:73

PROGRESS: on 09/02/2015TURBINE:

Control Fluid System:

Regeneration Pump is in continuous operation.

Control oil flushing is started on 12.01.15.

Control fluid flushing all the loops charged.

Coolers normalizing under progress.

TDBFP-B:

1. Drive Turbine of TDBFP-B was put in mechanical barring gear on 10.12.14. Max. Speed reach is 384 rpm.

C&I cable not ready from DCS (Customer scope).Cabling works is under progress (Customer scope).

TDBFP-A:

TDBFP-A oil flushing Completed on 25.12.14.

JOP motor trail run completed. (31/01/2015).

Jacking oil lines hydro test completed 120KSC on 06/02/2015.

Barring gear and governing lines hydro test completed on 05/02/2015.

Oil transfer pump motor trail run completed on 06/02/2015.

Oil draining from Lube oil tank completed on 09/02/2015.

Lube oil tank cleaning under progress.

VACCUM PUMP:

Vacuum pump motors 2 nos. trail run completed on 20.11.14.

POWER CYCLE PIPING & PIPING:

1. Main stream line (MS) from SG Nozzle to ESV East side and west side

Steam blowing completed

Page 2: Commissioning Status 10022015

2.Feed water line East side steam blowing completed on and West side steam

blowing is to be completed after getting LDO (Customer scope).

OGDHR:

OGDHR motor two numbers electrical testing was completed.

OGDHR motor was run decoupled condition. BOTH the motors

De bearing temperature is reached 85’C. Bearings to be

inspected.

C& I SYSTEM

HMI Engineer from BHEL/EDN for the backup node splitting in

Metso-DNA and for other HMI pending issues.

ERV’s cable checking under progress. 1/7 valves completed.

Logic linking from DCS to BCP(back up control panel) under progress.

Auxiliary Boiler:

Pending points attending are under progress.

PROGRAMME/plan

1. Starting of Control oil flushing after normalizing coolers.

ABNORMALITIES

Distribution1. Head/TSX 2. Site-Planning 3. UCM