commitments and major issues for lhc applications eugenia hatziangeli on behalf of co, op & lsa...

28
Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

Upload: conrad-rodgers

Post on 19-Jan-2016

213 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

Commitments and Major Issues for LHC Applications

Eugenia Hatziangelion behalf of

CO, OP & LSA application providers

Page 2: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

24 Jan 2006 Chamonix XV: Commitments and Major Issues on LHC Applications

Eugenia Hatziangeli AB/CO 2

Goal of the presentation Clarify the responsibilities Present the LHC Beam operation software architecture

Draw the list of the applications for stage I & II

Expose the major issues

?? 75ns ops75ns ops

43 bunch operatio

n

43 bunch operatio

n

Beam commissioning

Beam commissioning

Stage IStage I IIII

BeamBeam BeamBeam

Page 3: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

24 Jan 2006 Chamonix XV: Commitments and Major Issues on LHC Applications

Eugenia Hatziangeli AB/CO 3

Goal of the presentation Clarify the responsibilities Present the LHC Beam operation software architecture

Draw the list of the applications for stage I & II

Expose the major issues

?? 75ns ops75ns ops

43 bunch operatio

n

43 bunch operatio

n

Beam commissioning

Beam commissioning

Stage IStage I IIII

BeamBeam BeamBeam

Page 4: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

24 Jan 2006 Chamonix XV: Commitments and Major Issues on LHC Applications

Eugenia Hatziangeli AB/CO 4

Responsibility Limits - Inside 1/2The Controls group

provides core control functionality & applications (HWC sequencer, equip state, equip monitoring, SDDS,…) in collaboration with AB/OP

produces and maintains standard facilities (Logging, FDs, LASER, JAPC, SIS, BIC, OASIS, CCM, …)

develops, maintains and supports UNICOS based applications (Cryo, QPS, PIC, WIC,..) for industrial control system

provides support for modeling of the Controls database (SPS, HWC, LEIR, LHC) and for the logging and measurement services (Timber, Meter)

Page 5: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

24 Jan 2006 Chamonix XV: Commitments and Major Issues on LHC Applications

Eugenia Hatziangeli AB/CO 5

Responsibility Limits - Inside 2/2 AB/CO is also providing development environment, tools and graphical components to be used by application developers, equipment and MD specialists

FESA editor Java dataviewer General purpose graphical beans Java GUI frame LabVIEW development environment UNICOS frame Working sets & Knobs Jython Build and release tools Software support to developers

µCR

Page 6: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

24 Jan 2006 Chamonix XV: Commitments and Major Issues on LHC Applications

Eugenia Hatziangeli AB/CO 6

Responsibility Limits - Outside

AB/CO is NOT responsible for

equipment expert GUI applications (except QPS, CRYO)

MD software GUI applications

Page 7: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

24 Jan 2006 Chamonix XV: Commitments and Major Issues on LHC Applications

Eugenia Hatziangeli AB/CO 7

Goal of the presentation Clarify the responsibilities Present the LHC Beam operation software architecture

Draw the list of the applications for stage I & II

Expose the major issues

?? 75ns ops75ns ops

43 bunch operatio

n

43 bunch operatio

n

Beam commissioning

Beam commissioning

Stage IStage I IIII

BeamBeam BeamBeam

Page 8: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

24 Jan 2006 Chamonix XV: Commitments and Major Issues on LHC Applications

Eugenia Hatziangeli AB/CO 8

Frameworks for LHC ApplicationsThree approaches in place to build applications

Beam based control applications Majority of applications Java infrastructure

Industrial control PLC/SCADA based applications UNICOS frame based on PVSS

Post Mortem data analysis Based on LabVIEW

Page 9: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

24 Jan 2006 Chamonix XV: Commitments and Major Issues on LHC Applications

Eugenia Hatziangeli AB/CO 9

Our Approach to Java Applications Development

A considerable amount of applications for stage I & II is requested

This will be achieved since we have put in place a common architecture based on a solid core functionality a standard equipment access reusable software components standard facilities

upon which the LHC applications are being built

This requires high competence in software engineering for core development BUT it pays back Complex self contained applications are replaced by

light weight GUI applications which are easier to develop

GUI applications based on the core are less error prone

Page 10: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

LHC Java Applications and Core

LSA Controls System

Core

FESAEquipment

s

Controls Middleware

Monitoring &

Concentration

LSATrim

BeamSteering

SettingsGenerati

on

BDIApplic

FixedDisplay

s

Controls Settings

LSA API

FESAEquipment

s

FESAEquipment

s

Standard Equipment Access (JAPC)

Core applications

Equipment and instrumentation applications

Standard Equipment Access

High-Level Services

LSA Core

Page 11: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

24 Jan 2006 Chamonix XV: Commitments and Major Issues on LHC Applications

Eugenia Hatziangeli AB/CO 11

LHC Java Applications - Organization The work is done in a close collaboration with the OP group - we work in a team

One single project in place (LSA *) providing the common architecture

Aim to use for several accelerators TT40, TI8, HWC, LEIR, SPS, sector test and LHC

Test using every possible controls or operational milestone and several dry runs

* In 2006: 4 CO FTE and ~5 OP FTE

Page 12: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

24 Jan 2006 Chamonix XV: Commitments and Major Issues on LHC Applications

Eugenia Hatziangeli AB/CO 12

Goal of the presentation

Clarify the responsibilities Present the LHC Beam operation software architecture

Draw the list of the applications for stage I & II

Expose the major issues

?? 75ns ops75ns ops

43 bunch operatio

n

43 bunch operatio

n

Beam commissioning

Beam commissioning

Stage IStage I IIII

BeamBeam BeamBeam

Page 13: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

24 Jan 2006 Chamonix XV: Commitments and Major Issues on LHC Applications

Eugenia Hatziangeli AB/CO 13

High Level Requirements - extract from Mike’s talk

Core Functionality Equipment Instrumentation Exploitation Standard facilities

Page 14: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

High Level Application for Stage 0

Priority When Responsible

Vacuum 1 Start-up I. Laugier

AT/VAC

PostMortem Analysis

1 Start-up(QPS, PIC, PC)

R. Lauckner/coordinationRijllart/AnalysisG. Kruk, N. Trofimov/Core

CRYO 1 Start-up P. Gayet/SupervisionAT/ACR/System

QPS 1 Start-up H. Milcent/SupervisionAT/MEL/System

PIC 1 Start-up F. Bernard/SupervisionM. Zerlauth/System

WIC 1 Start-up F. Bernard/SupervisionP. Dahlen/System

Common core functionality Unstaffed activity Temporary or departing staff

PM already connected to PC and QPS

BIC already tested in TI8

PIC soon to be tested (HWC)

All systems will be ready for startup

1 temp staff for the applications of PIC & WIC

1 retiring staff for the coordination of PM project

Page 15: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

Core Functionality for Stage I & IIFunctionality Priorit

yWork Test Responsible

Settings Generation 1 < 3months LEIR, SPS, sector test

L.Normann D.JacquetM.Lamont

Archive/Reload/Rollback/Copy

1 1 month LEIR, SPS, sector test

L.Mestre/G. Kruk

Trim 1 Core functionalityin place - extensions for autotrim

LEIR, SPS, sector test

L.Mestre/G. KrukM.AlbertM.Lamont

State 1 V1 in place LEIR, SPS, sector test

F.Chevrier D.Jacquet

Equipment Access 1 V1 in place LEIR, SPS, sector test

L.Mestre/R.Gorbonosov

Optics 1 V1 in place sector test M.Lamont

Mode/Run Configuration 1 sector test NN

Database Configuration 1 V5 in place sector test M.Lamont D.Jacquet

Expert Settings 1 Under discussion with FESA

sector test NN

Equipment Monitoring 1 V1 in place SPS, sector test N.Hoibian

Common core functionality Unstaffed activity Temporary or departing staff

Already in a very advanced stage of development

Provides common functionality for high level applications

Data model definition completed - same for TLs, SPS, LEIR, LHC

Main architect/core developer leaves in May

2 temp staff for core activities

Page 16: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

EquipmentPriority

Work When Responsible

Collimators & Absorbers

1 2 months/year available effort Start-up S. Redaelli[dev, support]

Beam Dump 1 Control/State/SettingsXPOC

Start-up LSAJ.Axensalva

Power converters 1 Core functionalityin place for HWC (sequencer)

Acquisition: debugging, tracking studies TBD

Start-up LSAF.Chevrier D.JacquetNN

Radio Frequency 1 Mountain RangeSetting Unit Control

Start-up NN

LSA

Longitudinal Feedback

1 State/SettingsResponse - 1 month

Start-up LSA NN

Transverse Feedback 1 State/SettingsResponse - 1 monthXPOC 2 months

LSANN

Injection Kickers 1 XPOC - prototype for beam dump - 3 months for V1 with basic functionality

Q2 2006 J.Axensalva

Magnets 1 Implement FiDel Model of decay, Unit control, SettingsInput: Bottura, Sammut

V1 Q2 2006 LSA/M.Lamont

Common core functionality Unstaffed activity Temporary or departing staff

• Collimation project already discussed extensively• Settings/control/state in place for all equipment applications by LSA core• Majority of application are assigned including XPOC• A few unmanned activities to be taken up in the course of 2006

Page 17: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

Equipment under CO responsibility

Priority Work When Responsible

BIC 1 Hardware developmentGUI Application

Start-up B.ToddK.Sigerud/ V. Tsaplin

SLP Safe LHC Parameters

1

2

Hardware/Timing development

High Level Application

Start-up B.PuccioJ.SerranoNN

FMCMFast Magnet Current change Monitor

2 Equipment hw developmentProto application

Stage II M.ZerlauthNN

Common core functionality Unstaffed activity Temporary or departing staff

Activities OK for stage I

BIC with 2 temp staff for hardware and GUI development

Page 18: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

Instrumentation - Stage IPriority

Work When Responsible

Beam Loss Monitors 1 Concentration, publication - 1 monthAcquisition, data structs. - 2 monthsDisplay extensions - 2 weeksGUI - 1 month

Q1 2006 G.KrukG.KrukN.Hoibian

BPM: Orbit, trajectory 1 Concentration, publication - 1 month

Trajectory, Orbit - 1 weekFixed Display - use standard utilitiesGUI - 1 month

Q1 2006Q1 2006Q3 2006

G.KrukG.KrukJ.Wozniak J.Wenninger

Bunch Current Transformers 1 Acquisition [DC, bunch/bunch)& Lifetime]Display - 2 weeks

Q1 2006 M.AlbertM.Albert

Screens (matching monitors) 1 Acquisition - extension of existing

Screen control - extension of existingGUI - extension of existing

N.Hoibian M.LamontG.Crockford F.Follin

Tune - BBQ 1 Acquisition, control, display, analysis, dedicated application - 3 months

NN

Tune - PLL 1 plus Q’, CTA - 3 months NN

Luminosity Monitors 1 NN

Common core functionality Unstaffed activity Temporary or departing staff

• Critical instrument (BLM, BPM, BCT, BTV) applications applications are assigned

• BLM and BPM concentrators are taken care by LSA core

• Within the following 3 months the application responsible with the equipment specialists will define the operational APIs of critical instrument and a test plan (when we need what)

This should result in simulation equipment servers in place by the eq. specialists

• Resources for tune and luminosity will be found in the 2nd half of 2006

Page 19: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

Instrumentation - Stage II & III

Priority

Work When Responsible

Wall Current Monitors 2 NN

Wire Scanner BWS 2 Interlocks, movement control, acquisition

NN

BPM: multi-turn analysis 2 Application for the SPS (LHC like BPM) will be provided

Summer 2006

V. Kain

Chromaticity – head-tail 2 NN

Abort gap monitor 2 NN

Synchrotron Monitors 2 NN

Schottky 2 2 BQS (H & V) per beam in RA47 Not essential for 1st commissioning phase

Q1 2007 S.GysinFNAL

Rest Gas Ionisation Monitor(BIPM)

3 B-field control plus compensation interlocks

NN

Common core functionality Unstaffed activity Temporary or departing staff

Most activities for stage II & III remain unmanned - revisited in the course of 2006

Schottky development covered by LARP collaboration

Page 20: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

Measure/Adjust

Priority

Work When Responsible

Orbit 1Ongoing - Good basis in place

2006J.Wenninger

LSA

Collimation Optimisation

1SPS MD/ Sector test prototype

2006S.Redaelli

[dev, support]

Luminosity scans 12007 – first

physicsNN

Beta-beating 1 Big Effort 2007 NN

Common core functionality Unstaffed activity Temporary or departing staff

Orbit in good shape

Rest of the work is staged and will be manned in the course of 2006

Page 21: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

Exploitation

Priority

Work When Responsible

Sequencer 1 Big effort - 6 months for final version

Q2 - Q3 2006

GH.Hemelsoet J.Axensalva M.Lamont

Injection Sequencer 1 3 months for final version

V1 Q2 - Q3 2006 for commissioning

M.Gruwe [dev, support]

Magnet Model 1 FiDel ImplementationBottura & Sammut

M. Lamont

On-line Model 2 NN

Shot Data Analysis 2 Define necessary acquisitions and storage medium

FNAL

Common core functionality Unstaffed activity Temporary or departing staff

Both sequencers are important tools for operation and they are covered in terms of development and support.

Page 22: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

Major Standard FacilitiesPriority Work Who

OASIS 1

Application: main requirements covered. Remote trigger scheme & timing integration not before 2007. Oscilloscope: 8 bits, 1 GSa/s supported, 10 bits @ 2-8 GSa/s under dev., Slower models & ADCs not before 2007.

S.Deghaye

SDDS 1 V3 Core and browser: tested TI8/TT40/ SPS, sector tests G.Kruk

Software InterlocksSystem

1

Large system. V1 min functionality Q2 2006: Tested at CNGS startupTested partially before Beam commissioningOperational version for startup

J.Wenninger J.WozniakV.Baggiolini

LASER 1

Minimum functionality operational version available: HWC, LEIR, SPS, sector tests - Core supportDB archive and alarm sourcesAlarm ConsoleOP request: Support 365/24 - Present support coverage: CO experts

K.Sigerud N.StapleyM.MisiowiecNN

Fixed Displays

1 Several fixed displays (~24 configurations) are requested (cf. Mike table)

J.Wozniak/coreOP configuration

CCM 1Operational version available: Tested HWC, LEIR, SPS, sector tests V.Paris

K.Porowski

Common core functionality Unstaffed activity Temporary or departing staff

• SIS system with several complicated client inputs for LHC

• Requirements documented/published

• Proof of concept delivered in Jan 2006

• Laser

• min. solution for 2006 - exercise for SPS & sector tests and improve functionality for startup

• Support by CO experts - 365/24 not guaranteed

• 3 temp and 1 departing staff for these facilities

Page 23: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

24 Jan 2006 Chamonix XV: Commitments and Major Issues on LHC Applications

Eugenia Hatziangeli AB/CO 23

Goal of the presentation Clarify the responsibilities Present the LHC Beam operation software architecture

Draw the list of the applications for stage I & II

Expose the major issues

?? 75ns ops75ns ops

43 bunch operatio

n

43 bunch operatio

n

Beam commissioning

Beam commissioning

Stage IStage I IIII

BeamBeam BeamBeam

Page 24: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

24 Jan 2006 Chamonix XV: Commitments and Major Issues on LHC Applications

Eugenia Hatziangeli AB/CO 24

Issues - Resources The system architect & core developer leaves CERN

in May

Major core activities are staffed by temp or departing staff

The same application developers are working for HWC, LEIR, CNGS, PS and SPS startup and ….. what is left of them … for LHC Beam Operations…

LHC applications list not fully staffed clearly showing lack of resources

We need experienced Java software developers

Page 25: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

24 Jan 2006 Chamonix XV: Commitments and Major Issues on LHC Applications

Eugenia Hatziangeli AB/CO 25

Issues -Time allocated for Testing

While TT40/TI8, HWC, LEIR, and SPS ring will be used to test the LSA core and applications extensively, …

the tests foreseen in 2006 CNGS TI8/TT40 sector testwill be the only validation of the LHC software, so …

we need well coordinated dry runs beforehand

We request time allocated during LHC commissioning for the final tests of the deployed software

Page 26: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

24 Jan 2006 Chamonix XV: Commitments and Major Issues on LHC Applications

Eugenia Hatziangeli AB/CO 26

Issues - Remote Access and Security

Experts and piquet require access to LHC controls from outside the CCC

Who has the right to modify LHC parameters? Control of certain devices (Schottky) from other institutes is already requested (US-LARP collaboration)

We need remote access and role based access policy and manpower to implement it CNIC is not the answer

Page 27: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

24 Jan 2006 Chamonix XV: Commitments and Major Issues on LHC Applications

Eugenia Hatziangeli AB/CO 27

Conclusions Solid architecture on which to base the LHC

applications exists with main core services and several GUI applications already deployed

Tested and validated with TT40/TI8, HWC, LEIR, SPS, CNGS and sector test

We have a complete list of the LHC applications/developers

http://cern.ch/ab-lsa/planning/commissioning.htm

but with some holes …

There are issues on resources, time for testing, remote access and security

We have the right tools for the job and we will be able to do it, provided effort is not diverted into lower priority work

Page 28: Commitments and Major Issues for LHC Applications Eugenia Hatziangeli on behalf of CO, OP & LSA application providers

24 Jan 2006 Chamonix XV: Commitments and Major Issues on LHC Applications

Eugenia Hatziangeli AB/CO 28

Thank you

Acknowledgement for discussions/contributions L. Mestre,G. Kruk, V. Baggiolini, N. Stapley, S. Deghaye, J. Wozniak, M. Albert, M. Lamont, R. Billen, I. Laugier, R. Schmidt,

P. Charrue, A. Rijllart, J. Wenninger, B. Frammery, R, Lauckner,