San Mateo County CCE Formation Timeline Peninsula Clean Energy proposes an August 2016 Launch Phase 1 Phase 2 Phase 3 January -September 2015 Oct 2015 – February 2016 March – August 2016 Pre-Planning & Due Diligence Community Outreach; PCE Planning & Development Preparing for Launch Internal planning team Initial outreach to cities and key stakeholders Workshops & education Formation of CCE advisory committee CCE technical study complete (go/no-go) PCE Program & JPA design City outreach/Passage of local ordinances Impl. Plan Prepared RFP for Energy Services Plan for JPA staffing/working capital Community outreach First JPA Board meeting Energy supply and other service contracts Utility Service Agmt. Regulatory Registrations Marketing Campaign Call Center & Customer Enrollment

TRANSCRIPT

Page 1: Community Choice Energy (CCE) In San Mateo County

Community Choice Energy (CCE)In San Mateo County

2016 Program Implementation Plan

Page 2: Community Choice Energy (CCE) In San Mateo County

San Mateo County CCE Formation Timeline

Peninsula Clean Energy proposes an August 2016 Launch

Phase 1 Phase 2

January -September 2015 Oct 2015 – February 2016 March – August 2016

Pre-Planning & Due Diligence

Community Outreach; PCE Planning & Development

Preparing for Launch

• Internal planning team• Initial outreach to cities

and key stakeholders• Workshops & education• Formation of CCE

advisory committee• CCE technical study

complete (go/no-go)

• PCE Program & JPA design• City outreach/Passage of

local ordinances• Impl. Plan Prepared • RFP for Energy Services • Plan for JPA

staffing/working capital• Community outreach

• First JPA Board meeting• Energy supply and other

service contracts • Utility Service Agmt. • Regulatory Registrations• Marketing Campaign• Call Center & Customer

Enrollment

Phase 3

Page 3: Community Choice Energy (CCE) In San Mateo County

November - February

City Ordinances/JPA Resolutions Community Engagement -- ongoing• New RFP for public campaign in 2016

JPA Prep: Draft bylaws, filing with the state, prep for initial board meeting (current SMC team to serve as interim staff support)

Finalize PCE power offerings and customer phasing planBegin credit discussions/banker outreachDraft energy services RFP and Implementation PlanDraft data management RFP

Page 4: Community Choice Energy (CCE) In San Mateo County

March – May 2016

JPA Board seated in March or April 2016 Begin steps to administrative independence – staffing,

office, credit, insurance, et al Finalize Implementation Plan, submit to CPUC (90 days)

Issue RFPs and negotiate energy services and data mgmt. contracts

Public marketing campaign underway

Page 5: Community Choice Energy (CCE) In San Mateo County

June – August 2016

Finalize banking relationship and credit terms:• JPA working capital • Loan for first energy contract (will require guarantee)• Establish lockbox for payments, et al

Finalize JPA staff and key vendor relationships Utility Matters: Utility service agreement, post bond and PGE

deposit, Complete Regulatory registrations ~ Mid June -- customer notifications begin (60 days prior) September – First revenues; ongoing enrollment