conceptual design - simcoe county treatment... · 2017. 6. 22. · conceptual design of the -septic...
TRANSCRIPT
SARJEANT LANDS Hillsdale, ON
Sewage Treatment and Disposal System Conceptual Design
prepared by: prepared for
C.C. Tatham & Associates Ltd. 115 Sandford Fleming Drive, Suite 200 Collingwood, ON L9Y 5A6 Tel: (705) 444-2565 Fax: (705) 444-2327 [email protected]
Golder Associates Ltd.
March 9, 2017
CCTA File 116147
TABLE OF CONTENTS
1 Introduction 1
2 Design Flows and Sewage Characteristics 2
2.1 Design Flows 2
2.2 Sewage Characteristics 2
3 Conceptual Design 3
3.1 Overall Concept 3
3.2 Sewage Collection System 6
3.3 Sewage Pumping Station 6
3.3.1 Sewage Pumps 6
3.3.2 Emergency Storage Tank 6
3.4 Primary Treatment (Septic Tanks) 7
3.5 Effluent Pumping Station 7
3.5.1 Effluent Flow Balancing Tank 7
3.6 Enviro-Septic Systems 8
3.6.1 Hydrogeology 9
3.6.2 Contact Area 9
3.6.3 Vertical Profile 9
3.6.4 Number of Enviro-Septic Pipes 9
3.6.5 Low Pressure Distribution Systems 10
3.7 Control Building 10
3.8 Standby Generator 10
3.9 Phasing 10
LIST OF FIGURES Figure 1: Heritage Village Sewage Works – Overall Site Plan 4
Figure 2: Sarjeant Lands Sewage Works – Overall Site Plan 5
Figure 3: Sewage Treatment and Disposal System – Control Building Plan 11
APPENDICES Appendix A: Conceptual Design Calculations
Appendix B: Enviro-Septic System
Appendix C: Waste Water Disposal Design, Golder Associates Ltd.
Sarjeant Lands Sewage Treatment and Disposal System
Page 1 March 9, 2017
1 Introduction
C.C. Tatham & Associates Ltd. (CCTA) has been retained by Golder Associates Ltd. (Golder) to complete the conceptual design of an on-site sewage treatment and disposal system in support of a Functional Servicing Report for the Sarjeant Lands in Hillsdale, ON.
The Sarjeant Lands are located on Part N1/2, Lot 57, Concession 1, Oro-Medonte as in RO102551, except Part 1, 2 and 5, Springwater as in RO51R27010.
Ultimately, the sewage works will service the residential lots in the Sarjeant Lands, as well as the residential lots in Heritage Village and the existing public school in Hillsdale. The public school will be expanded to accommodate students from the proposed developments.
Sewage from the Sarjeant Lands will be collected by gravity and conveyed to the Heritage Village sewage block for treatment. A portion of the treated effluent will be pumped back to the Sarjeant Lands sewage block for subsurface disposal in proprietary Enviro-Septic systems.
This report presents the design basis and a functional description of the sewage treatment and disposal system.
Sarjeant Lands Sewage Treatment and Disposal System
Page 2 March 9, 2017
2 Design Flows and Sewage Characteristics
2.1 Design Flows
Ultimately, the sewage works will service a total equivalent population of 1,155 consisting of:
a residential population of 342 in the Sarjeant Lands, consisting of 114 units with a population density of 3;
a residential population of 696 in Heritage Village, consisting of 232 units with a population density of 3; and,
an equivalent population of 120 to account for the expanded public school.
The design flows for the development are based on MOE 2008 Design Guidelines for Sewage Works (MOECC Design Guidelines). Detailed calculations are included in Appendix A. The design flows use a domestic flow rate of 360 L/cap/day, plus an allowance of 90 L/cap/day for inflow and infiltration, for a total of 450 L/cap/day:
The ultimate design flow is 1,155 cap x 450 L/cap/day = 521,000 L/day plus an allowance of 5% for a total of 550,000 L/day. Of this design flow, the Sarjeant Lands account for 339 cap x 450 L/cap/day = 150,000 L/day. The total design peak flow is 22.3 L/s, calculated by applying the Harmon Factor to the domestic flow and adding an allowance of 227 L/cap/day for peak inflow and infiltration.
2.2 Sewage Characteristics
It is expected the sewage characteristics will be typical of municipal strength wastewater with TSS and BOD5 in the range of 200 to 250 mg/L. The sewage will be suitable for primary treatment in conventional septic tanks, as discussed in the following sections.
Sarjeant Lands Sewage Treatment and Disposal System
Page 3 March 9, 2017
3 Conceptual Design
3.1 Overall Concept
The conceptual design for the sewage treatment and disposal system is summarized below:
Sewage will flow by gravity from Heritage Village and the Sarjeant Lands to a sewage pumping station in the Heritage Village sewage block (SPS) consisting of a wet well, trash basket or screen, submersible sewage pumps, and emergency storage tank.
The SPS will pump the sewage evenly to six septic tanks with effluent filters, via a discharge manifold equipped with electrically-actuated pinch valves.
Effluent from the septic tanks will be collected in an effluent pumping station (EPS) consisting of a wet well and submersible effluent pumps.
The EPS will pump the effluent via transport forcemains and low pressure distribution systems evenly to eight Enviro-Septic systems in the Heritage Village sewage block and three Enviro-Septic systems in the Sarjeant Lands sewage block. Similar to the SPS, the effluent will be divided among the Enviro-Septic systems via a discharge manifold equipped with electrically-actuated valves.
The Enviro-Septic system is a proprietary sub-surface treatment and disposal system that incorporates attached growth aerobic treatment within the distribution piping of the subsurface disposal bed.
A central control building in the Heritage Village sewage block will house the sewage and effluent discharge manifolds, flow meters, as well as a motor control centre (MCC) with programmable logic controller (PLC) and human-machine interface (HMI).
Standby power will be provided by an exterior generator set housed in a sound-proof enclosure.
The sewage works areas will be fenced with a single gated access road.
Sewage from the Sarjeant Lands will be collected by gravity and conveyed to the Heritage Village sewage block for treatment in the septic tanks. A portion of the septic tank effluent will be pumped back to the Sarjeant Lands via three transport forcemains for subsurface disposal in the three Enviro-Septic systems. Thus, the Sarjeant Lands sewage block will consist of three Enviro-Septic systems.
Overall site plans of the conceptual design for the Heritage Village and Sarjeant Lands sewage works are shown on Figure 1 (Drawing SP-1) and Figure 2 (Drawing SP-2) overleaf.
Sarjeant Lands Sewage Treatment and Disposal System
Page 6 March 9, 2017
3.2 Sewage Collection System
A network of gravity sewers, designed and detailed by others, will collect sewage from the development and ultimately discharge to a manhole upstream of the proposed SPS in the Heritage Village sewage block.
3.3 Sewage Pumping Station
The SPS will consist of a wet well equipped with a trash basket or screen, three submersible sewage pumps, and an overflow to an emergency storage tank. The exact dimensions and configuration of the wet well will be determined during detailed design when details of the sewer inlet size and invert are available.
3.3.1 Sewage Pumps
The pumps will be equipped with variable frequency drives (VFD) and will operate in a lead/lag/standby configuration. When operating together, the pumps will be capable of pumping up to the ultimate peak design flow of 22.3 L/s.
The sewage flow will be divided among the six septic tanks via a discharge header equipped with a magmeter and a manifold with six discharge pipes equipped with electrically-actuated pinch valves. The PLC will open the valves sequentially such that only one septic tank is being dosed at any time. Since only one valve will be open at a time, the PLC can measure and control the dose to each septic tank.
Primary treatment efficiency will be improved by dosing the septic tanks with small volumes of sewage. Thus, each septic tank will be dosed up to 20 times per day with a volume of 5,000 L per dosing cycle up to the design flow of 550,000 L/day.
In order to minimize pump starts, the pumps will be controlled by the PLC such that a pre-set liquid level is maintained in the wet well. The level will be measured by an ultrasonic sensor or pressure transducer with backup float switches. Further, the next valve in sequence will open while the currently open valve is closing, so that the sewage pump can remain on when switching from dosing one septic tank to another.
3.3.2 Emergency Storage Tank
In an emergency, the wet well will overflow to a 100,000 L precast concrete tank. In the event of a catastrophic pump failure or stand-by generator failure, the holding tank will provide approximately 4 hours of storage at the design flow.
Sarjeant Lands Sewage Treatment and Disposal System
Page 7 March 9, 2017
3.4 Primary Treatment (Septic Tanks)
The proposed Enviro-Septic system requires primary treatment in the form of septic tanks providing a total of 24-hours of retention time (assuming the septic tank is 50% full of sludge and scum) at the design flow of 550,000 L/day, or two times the design flow.
Primary treatment will be provided by six cast-in-place concrete septic tanks, each with a capacity of 200,000 L.
In order to minimize turbulence in the septic tanks, sewage from the SPS will be pumped to a 1.2 m diameter manhole upstream of each septic tank from where it will flow by gravity to the septic tank.
Each septic tank will be equipped with up to three effluent filters to prevent solids carryover.
The septic tank outlets will be plumbed to a common pipe that will discharge by gravity to the EPS.
3.5 Effluent Pumping Station
The EPS will consist of a wet well equipped with two submersible effluent pumps. The exact dimensions and configuration of the wet well will be determined during detailed design.
The effluent pumps will be equipped with VFDs and operate in a duty/standby configuration. The pumps will be controlled such that a minimum flow rate of approximately 8 L/s is maintained to ensure the low pressure distribution systems for each Enviro-Septic system are adequately pressurized and dosed.
Based on the supplier’s recommendation, each Enviro-Septic system will be dosed up to 20 times per day with a volume of 2,500 L per dosing cycle. The Enviro-Septic systems will be dosed sequentially via the discharge manifold in a manner similar to the septic tanks described above.
3.5.1 Effluent Flow Balancing Tank
The wet well will overflow to a 100,000 L precast concrete flow balancing tank sized to store up to two hours of peak flow in excess of the minimum flow rate for dosing the Enviro-Septic systems at the design flow.
In the unlikely event the EPS and flow balancing tank reach high level, in order to prevent a spill, the PLC will start the standby pump and open two valves to simultaneously dose two Enviro-Septic systems.
Sarjeant Lands Sewage Treatment and Disposal System
Page 8 March 9, 2017
3.6 Enviro-Septic Systems
Following primary treatment, septic tank effluent will be further treated and disposed in eleven Enviro-Septic systems: eight systems in the Heritage Village sewage block; and three systems in the Sarjeant Lands sewage block. Each Enviro-Septic system will have a capacity of 50,000 L/day. Thus, the three Enviro-Septic systems in the Sarjeant Lands will have sufficient capacity for the Sarjeant Lands portion (150,000 L/day) of the ultimate combined design flow (550,000 L/day).
The Enviro-Septic system is a proprietary treatment and disposal system approved for use under the OBC by Building Materials Evaluation Commission (BMEC) Authorization No. 13-03-365. The conceptual design of the Enviro-Septic systems for Heritage Village is based on the BMEC authorization with due consideration to the MOECC Design Guidelines for large subsurface disposal systems.
The Enviro-Septic system essentially combines attached growth aerobic treatment with a subsurface treatment and disposal system. The system uses a network of perforated Enviro-Septic pipes made out of corrugated high-density polyethylene. Each pipe is approximately 300 mm in diameter and 3 m long. Up to 10 Enviro-Septic pipes can be coupled together with special adaptors to form a run of up to 30 m. A non-braided polypropylene fiber membrane covers the inside of the pipe, providing a matrix to support biomass, while a non-woven polypropylene geotextile canvas, sewn around the fibrous membrane, keeps soil from migrating into the pipes. Multiple vents at both ends of the pipe runs provide ventilation and maintain aerobic treatment throughout.
The network of Enviro-Septic pipes lies in a 700 mm layer of system sand meeting the specifications listed in Section 4.6.2. of the BMEC. The system sand forms an integral part of the treatment system, providing additional treatment, effluent polishing and pathogen removal. A sampling device that collects effluent from under the system sand will be installed to permit sampling and monitoring of the final effluent. The Enviro-Septic system does not require a mantle. Details of the Enviro-Septic system are included in Appendix B.
Rigorous testing of the Enviro-Septic system has shown it is capable of treating septic tank effluent to the tertiary standards specified in Table 8.6.2.2.A. of the OBC, or maximum concentrations based on 30-day averages of 15 mg/L BOD5 and 10 mg/L SS.
The principal design parameters for the Enviro-Septic system include the contact area between the system sand and underlying soil, and the vertical separation distance between the system sand and high water table, bedrock, or soil with a percolation time greater than 50 min/cm, and the number of Enviro-Septic pipes.
Sarjeant Lands Sewage Treatment and Disposal System
Page 9 March 9, 2017
3.6.1 Hydrogeology
Golder excavated six test pits within the vicinity of the proposed Enviro-Septic systems in the Heritage Village sewage block. Generally, the uppermost receiving strata of soil consists of granular silt loam with weak-moderate structure, including layered silts and compact sand with a T-time of 12-20 min/cm. Based on Table 22-1 of the MOE Design Guidelines and the layered silts and compact sand, Golder recommends a loading rate of 20 L/m2/day for effluent treated to CBOD5 of 30 mg/L or less.
Golder also excavated two test pits within the vicinity of the proposed Enviro-Septic systems in the Sarjeant Lands sewage block. Generally, the uppermost receiving strata of soil consists of fine sandy loam and silt loam soils of granular, weak-moderate structure with a T-time of 8-10 min/cm. Golder recommends a loading rate of 20 L/m2/day.
The high water table was encountered at a depth of 1.5 to 2.5 m.
A copy of Golder’s report, Waste Water Disposal Design, is included in Appendix C.
3.6.2 Contact Area
At a capacity of 50,000 L/day for each Enviro-Septic system and at the recommended loading rate of 20 L/m2/day, the required contact area between the system sand and underlying soil is 2,500 m2. The dimensions of the contact area for each Enviro-Septic system are 73 m x 34.2 m to provide the necessary contact area.
3.6.3 Vertical Profile
The Enviro-Septic systems will be constructed at the current grade by stripping the topsoil and placing the system sand directly on top. The Enviro-Septic systems will be tiered to accommodate the grade drop across the sewage block.
A high groundwater table of 1.5 m below finished grade is assumed from Golder’s report. The mounding on the high groundwater table is estimated at 0.7 m. Thus, there will be 0.8 m vertical separation between the bottom of the sand layer and the mounded high groundwater table. This is greater than the 0.45 m vertical separation required by the BMEC.
The finished grade will be 0.9 m above the existing grade, including 0.7 m for the system sand layer and 0.2 m for cover and topsoil.
3.6.4 Number of Enviro-Septic Pipes
The required number of Enviro-Septic pipes is calculated according to Section 5.2.1. of the BMEC, or NESP = Q ÷ 90:
NESP = 50,000 L/day ÷ 90 pipes/L/day = 556 pipes
Sarjeant Lands Sewage Treatment and Disposal System
Page 10 March 9, 2017
Each Enviro-Septic system will be divided into two zones, with four cells per zone, and 15-15 m runs per cell. The runs will be spaced approximately 1.4 m apart to provide the necessary number of pipes and contact area.
3.6.5 Low Pressure Distribution Systems
Each Enviro-Septic system will be dosed by a low pressure distribution system consisting of a transport forcemain with laterals to each cell. As discussed above, the effluent pumps and VFDs will be controlled by the PLC to maintain a minimum flow rate suitable for pressurizing the distribution systems. The design and sizing of the low pressure distribution systems depends on the configuration of the Enviro-Septic system and will be determined during detailed design.
3.7 Control Building
A control building adjacent to the SPS and EPS will house the sewage and effluent discharge headers and valves, the MCC, and the PLC/HMI. A conceptual layout of the control building including the discharge header, piping and valves is shown on Figure 3 (Drawing SP-3) overleaf. The conceptual layout suggests a footprint of approximately 6 m by 17 m. The control building will be complete with electrical, HVAC and plumbing systems.
3.8 Standby Generator
Standby power will be provided by an exterior generator housed in a sound-proof enclosure and an automatic transfer switch in the control building. The generator will provide all power necessary to operate the sewage pumps, effluent pumps, building utilities and electrically-actuated valves. The generator will be sized during the detailed design phase. The generator may be fuelled with diesel or by natural gas if it is available at the site.
3.9 Phasing
The multiple septic tanks and Enviro-Septic systems provide a great deal of flexibility in phasing the construction of the sewage treatment and disposal system. Generally, each septic tank and two Enviro-Septic systems have capacity for an equivalent population of 220. The SPS, EPS and control building must be built, and the generator installed, in the first phase.
Sarjeant Lands Sewage Treatment and Disposal System
Page 12 March 9, 2017
Authored by:
Keith Shular, B.Sc., B.E.Sc., P.Eng. Project Manager
Reviewed by:
Suzanne Troxler, B.Eng., M.Sc., P.Eng. Director, Manager – Environmental Engineering
© C.C. Tatham & Associates Ltd The information contained in this document is solely for the use of the Client identified on the cover sheet for the purpose for which it has been prepared and C.C. Tatham & Associates Ltd. undertakes no duty to or accepts any responsibility to any third party who may rely upon this document. This document may not be used for any purpose other than that provided in the contract between the Owner/Client and the Engineer nor may any section or element of this document be removed, reproduced, electronically stored or transmitted in any form without the express written consent of C.C. Tatham & Associates Ltd.
APPENDIX A: CONCEPTUAL DESIGN CALCULATIONS
1 of 5
DESIGN SEWAGE FLOWS
The sewage works will service the following total equivalent units:
Residential units x cap/unit = Heritage Village
Public School
Residential units x cap/unit = Sarjeant Lands
The design flow criteria are based on MOE Design Guidelines:
Per capita flow L/cap/day
Average I/I L/cap/day
Peaking factor Harmon Equation , where p = population in thousands
Peak I/I L/cap/day
Heritage Village
Public School
Sarjeant Lands
with ~5% allowance
114 3 342
Revision: Revised with extra units for Sarjeant Lands
1,222 440,000 110,000 550,000 3.74 19.1 3.2
816
Sarjeant LandsHillsdale, ONProject:
116147
Sewage Treatment and Disposal System Conceptual Design
File No.:
Subject:
696 251,000 63,000 314,000
232 3 696
Nov 18, 2016
KES
ST
Date:
Designed:
Checked:
Development Peaking Factor
PF(L/s)
Peak I/I(L/s)
Design I/I
(L/day)
Total Design Flow
(L/day)
Design Flow
(L/day)
EquivPopn
Revision: Revised as per SCS and client comments. KES/ST
360
90
227
Total PF(L/s)
120 Includes allowance for existing public school in Hillsdale and expansion for students from Heritage Village.
1158
KES/ST
22.3
120 43,000 11,000 54,000
342 123,000 31,000 154,000
1,158 417,000 105,000 522,000
𝑃𝑃 = 1 + 14
4 + 𝑝0.5
2 of 5
Sarjeant LandsHillsdale, ONProject:
116147
Sewage Treatment and Disposal System Conceptual Design
File No.:
Subject:
Nov 18, 2016
KES
ST
Date:
Designed:
Checked:
CONCEPTUAL DESIGN
The conceptual design is as follows:
Sewage will flow by gravity from Sarjeant Lands and Heritage Vilalge to a Sewage Pumping Station (SPS).
The SPS will divide the sewage evenly among septic tanks via a discharge header equipped with electrically actuated pinch valves.
Sewage from the septic tanks will be collected in an Effluent Pumping Station (EPS).
The EPS will divide the effluent evenly among
SEWAGE PUMPING STATION
holding tank with a capacity of L will provide emergency storage:
L / L/day = days = hours of emergency storage at the design flow.
PRIMARY TREATMENT (SEPTIC TANKS)
The septic tank in each treatment train will be sized to provide 24 hours retention time when the septic tank is 50% full of sludge and scum.
septic tanks will be provided, each with a capacity of:
L/day x / tanks = L SAY L
Each septic tank will be dosed up to times per day:
L/day / / cycles = L/dosing cycle SAY L/dosing cycle
EFFLUENT PUMPING STATION (EPS)
As discussed below, each of the Enviro-Septic systems will have a capacity of:
L/day / = L/day
Based on the supplier's recommendation for the Enviro-Septic system, each system can be dosed up to times per day:
L/day / = L/dose20 2,500
20
4,583550,000
200,000
5,0006 20
20
11
550,000 11 50,000
50,000
550,000 2
100,000 550,000 0.18
1 100,000
183,3336
6
4
Enviro-Septic systems via an effluent discharge header equipped with electrically actuated pinch valves. Eight Envio-Septic systems will be located in the Heritage Village sewage block and three Enviro-Septic systems will be located in the Sarjeant
6
11
3 of 5
Sarjeant LandsHillsdale, ONProject:
116147
Sewage Treatment and Disposal System Conceptual Design
File No.:
Subject:
Nov 18, 2016
KES
ST
Date:
Designed:
Checked:
A typical flow rate for dosing an Enviro-Septic system of the size calculated below is approximately L/s.
Thus, the effluent flow balancing tank will be sized to provide hours of storage for flows in excess of L/s up to the peak hourly flow of
L/s:
( - L/s ) x hrs = L
ENVIRO-SEPTIC SYSTEM
Each of the Enviro-Septic systems will have a capacity of:
L/day / = L/day
All of the Enviro-Septic systems will have the same configuration.
Soil Characteristics
Based on the Wastewater Disposal Design soils report issued by Golder Associates, June 2016:
Native soils:
T-time: min/cm
Recommended loading rate: L/m2/day FROM TABLE 22-1 WITH TREATMENT TO CBOD5 < 30 mg/L
High groundwater table: Groundwater was encountered at depths of to m.
Due to the low groundwater table, sandy soils, and moderate loading rate, mounding is not expected to be significant.
Vertical Separation
If the T-time is greater than 6 min/cm and less than 50 min/cm, the required vertical separation distance m.
The required vertifcal separation distance can be maintained with the EnviroSeptic system constructed at the existing grade level.
20
From the BMEC, the vertical separation distance from the bottom of the system sand layer to the high groundwater table, perched groundwater table, rock, or soil with a T-time > 50 min/cm is determined by the T-time of the underlying native soil:
8
22.3
22.3
8 to 20
0.450
1.5 2.5
Silt loam of granular weak-moderate structure and fine sandy loam/silt loam soils of granular weak-moderate structure
2
8
8.0 2 103,000
11
550,000 11 50,000
4 of 5
Sarjeant LandsHillsdale, ONProject:
116147
Sewage Treatment and Disposal System Conceptual Design
File No.:
Subject:
Nov 18, 2016
KES
ST
Date:
Designed:
Checked:
Loading Area
The required loading area is calculated from the design flow and recommended loading rate:
L/day / L/m2/day = m2
The EnviroSeptic system does not require a mantle.
Design and Sizing
ALL DIMENSIONS ARE IN METRES
3.6 3.6
3.6 4 : 1 SIDE SLOPES
3.6 3.6
ENVIROSEPTIC PIPES 34 41
AND SYSTEM SAND GRADE
MOUNDING
HIGH WATER TABLE
3.6
Number of EnviroSeptic pipes required: L/day / L/day = pipes SAY FROM SECTION 5.2.1 OF BMEC
Each EnviroSeptic system will be divided into zones.
Each zone will be divided into cells.
Each cell will have runs of EnviroSeptic piping.
Thus, each zone will consist of runs.
Each run of EnviroSeptic piping will consist of EnviroSeptic pipes.
Thus, each EnviroSeptic system will have runs.
The runs will be spaced at approximately m / = m.
The total length of EnviroSeptic pipe is * = m.
50,000 90 556 600
82
20 2,500
NATIVE SOIL
0.700
0.800
PIPES AND SYSTEM SAND
COVER
0.700
0.200
74
600 3.05 1,830
50,000
2
4
82 60 1.4
600
15
5
60
5 of 5
Sarjeant LandsHillsdale, ONProject:
116147
Sewage Treatment and Disposal System Conceptual Design
File No.:
Subject:
Nov 18, 2016
KES
ST
Date:
Designed:
Checked:
The volume of system sand required is:
m x m x m = m3
Less the volume of EnviroSeptic pipe / 4 x ( m) ^ 2 x m = m3
m3
Density:
tonne4,000
2.2
130
1,630
0.300
74 34 0.700 1,760
1,8303.14
6 of 6
MOUNDING CALCULATIONS (Finnemore and Hantsche, 1983)
The Finnemore and Hatsche method is used to calculate mounding on an underlying water table:
Iterate this value until equal to Zm below.232
m
FROM MOECC WELL RECORDSm Initial guess of Zmm
m3/day Average flow (mounding calculations are based on long-term average daiy sewage flow)
m Length of disposal fieldm Width of disposal fieldm2 Area of disposal field
Length:width ratioInterpolated from Table 1Interpolated from Table 1
m/day Permeability of soil (see below)days Time since beginning of wastewater application% Specific yield, from Table
m Maximum rise of the groundwater mound
cm/sec FROM GOLDER REPORTm/secm/day
1 3.4179 1.7193
8 0.5922 1.7793
2 2.0748 1.75524 1.1348 1.7716
0.00100.00000.8640
TABLE 1L/W C n
Sy 21
Zm 0.67
PERMEABILITY
n 1.760K 0.864t 365
A 2,516L/W 2.2C 1.844
Q 50
L 74W 34
Zm 0.67hbar 40.3 Distance from boundary to mid-point of the long
term mound
Subject: Enviro-Septic SystemMounding Calculations Checked: ST
ho 40 Height of stable groundwater table above impermeable boundary (e.g., bedrock)
Project: Heritage VillageHillsdale, ON Date: Jul 22, 2016
File No.: 116147 Designed: KES
2
_m
oZ
hh +=
n
y
nn
m St
KhL
ACQZ
5.015.014
−
=
APPENDIX B: ENVIRO-SEPTIC SYSTEM
APPENDIX C: WASTE WATER DISPOSAL DESIGN, GOLDER ASSOCIATES LTD.
March 9, 2017
WASTE WATER DISPOSAL DESIGN
Waste Water Disposal Design
REPO
RT
Report Number: 07-1170-0010
Distribution: 1 copy - C.C. Tatham & Associates Ltd. 1 copy - Golder Associates Ltd.
Submitted to: C.C. Tatham & Associates Ltd. Attention: Keith Shular 115 Sandford Fleming Drive Suite 200 Collingwood, ON L9Y 5A6
WASTE WATER DISPOSAL DESIGN
Table of Contents
1.0 INTRODUCTION .................................................................................................................................................... 1
2.0 SITE ....................................................................................................................................................................... 1
2.1 Heritage Village ........................................................................................................................................ 1
2.2 Sarjeant Lands.......................................................................................................................................... 2
FIGURES
Figure 1 Proposed Effluent Bed – Test Pit and Borehole Locations
Figure S-1 Gradation Curves for Test Pits 1 through 4
Figure S-2 Gradation Curves for Test Pits 5 and 6
Figure S-3 Gradation Curves for Test Pits 7 and 8
TABLES
Table 1 Summary of Soil Classifications for Test Pits 1 through 6
Table 2 Summary of Soil Classifications for Test Pits 7 and 8
APPENDICES APPENDIX A Borehole Logs
APPENDIX B Test Pit Logs
March 9, 2017 Report No. 07-1170-0010 i
WASTE WATER DISPOSAL DESIGN
1.0 INTRODUCTION Hillsdale Land Corporation (HLC) owns lands designated for residential development in the Hillsdale Settlement Area “Heritage Village Development” (Heritage Village). The Heritage Village adjoins the proposed “Sarjeant Lands Development” (Sarjeant Lands), both located off Highway 93 north of Albert Street in the Community of Hillsdale. The Heritage Village Lands have an area of approximately 53 ha, and are proposed to be serviced with on-site sub-surface communal septic bed(s). The Sarjeant Lands have an area of approximately 30 ha, of which 14.5 are proposed for development.
HLC has requested Golder provide content for the Functional Servicing Report being prepared by SCS Consulting Group Ltd. (SCS) of Markham. The content is to include a conceptual design for the waste disposal system and design and construction costs for each of the subject lands.
Field investigations include:
1) Borehole drilling for geotechnical purposes and information from the drilling adjacent the septic beds were reviewed and included in this assessment (logs appended).
2) Test pitting was conducted on June 15, 2016 to provide detailed information for siting and design of the proposed sub-surface communal septic beds (logs appended).
3) Gradation analyses were completed on 13 grab samples from 8 test pits. The results are shown on Figures S-1, S-2 (Heritage Village) and S-3 (Sarjeant Lands).
2.0 SITE The bed siting was co-ordinated with the SCS plan of April 2016, downgradient east of proposed residential areas. Private locates were completed ahead of eight test pits excavated in the proposed bed area(s). Borehole drilling was conducted under the inspection of Golder staff. Inspection of the test pit soils intersected were logged by Golder staff, and observed by staff of C.C. Tatham & Associates Ltd. (Tatham). Gradation analyses were conducted at the Golder laboratory in Barrie.
2.1 Heritage Village The soils intersected were compact sand / sand silt mixtures to depth ranging nominally 1.2 to 1.5 m depth, underlain by loose uniform sands and gravels to depths of excavation up to 2.7 m. At locations on the Heritage Village, the sands and silts are rhythmically bedded and layered.
The water table was intersected in the Heritage Village bed area ranging 1.5 to 2.5 m depth. The distribution curves describe soils as Type ML, Type SM, and Type SP. A summary of the sample soil types are attached in Table 1.
The area for septic bed construction at Heritage Village is currently cropped farmland, of moderate slope west to east. The area for septic bed construction on the Sarjeant Lands is level mixed meadow and afforested, gently sloping northwest to southeast.
Based on Table 22-1 of the Ministry of Environment and Climate Change (MOECC) 2008 Design Guidelines for Sewage Works, suggested hydraulic and organic loading rate range 8 to 32 L/m2/day for silt loam soils of granular, weak-moderate structure, and treatment of CBOD5 to 30 mg/L or less. Due to the layered silts and compact sand in the upper sub-soils, it is suggested loading over the extent of the leach field contact should be at the middle of the range or approximately 20 L/m2/day.
March 9, 2017 Report No. 07-1170-0010 1
WASTE WATER DISPOSAL DESIGN
It was previously reported for the Heritage Village lands in Golder geotechnical reports that the eastern parts of the area selected for sub-surface disposal contain compressible soils. Where the thickness of imported soil is greater than the volume of stripped soil, an assessment for construction practices and design on these soils is recommended.
2.2 Sarjeant Lands Two test pits were dug on the Sarjeant Lands to depths of 2.4 and 2.7 m. The subsoils were sandy and uniformly graded. The surficial sand in TP7 appeared to be windblown loess, which rested upon 1.2 m of clayey silt to silt. Below the fine grained materials wet sand was encountered. In TP8 materials intersected were sand grading downward to sand and gravel. The depth to water table in the Sarjeant Lands bed area was 2.3 m or deeper; the deepest dry pit excavated to a depth of 2.7 m. A summary of the grain size sample soil types are attached (Table 2).
Borehole drilling indicates the fine sand (Type SP) found below 2.13 m below ground level (mbgl) at TP7 extends to a depth of 4.6 mbgl at TB-2 and the sand intersected at the ground surface in TP8 extends to approximately 3 mbgl at TB-1.
Based on Table 22-1 of the MOECC 2008 Design Guidelines for Sewage Works, suggested hydraulic and organic loading rate range 20 to 32 L/m2/day for Fine Sandy Loam and Silt Loam soils of granular, weak-moderate structure, and treatment of CBOD5 to 30 mg/L or less. Due to the layered silts intersected at TP7 and TB-2 it is suggested loading over the extent of leach field contact should be at the lower of the range or approximately 20 L/m2/day.
March 9, 2017 Report No. 07-1170-0010 2
WASTE WATER DISPOSAL DESIGN
Report Signature Page
GOLDER ASSOCIATES LTD.
Jim Regier, C.E.T. John Easton, M.Sc., P.Geo. Project Manager Senior Hydrogeologist, Associate
JR/JAE/plc
Golder, Golder Associates and the GA globe design are trademarks of Golder Associates Corporation.
n:\active\2007\07-1170-0010_hillsdale_geranium_ws\2016\septic bed design report\sarjeant update\07-1170-0010 septic design criteria report mar 2017v2.docx
March 9, 2017 Report No. 07-1170-0010
WASTE WATER DISPOSAL DESIGN
FIGURES
March 9, 2017 Report No. 07-1170-0010
241.00
244.00
242.
00
242.00
243.00244.00245.00246.00247.0
0
248.00
242.00
243.00243.00
258.00
257.00
254.00254.00255.00256.00
257.00
251.00252.00
253.0
0
251.00252.00253.00
254.00
256.00
257.00
256.00
255.
0025
4.00
255.
0025
5.00
256.0
0
257.00
256.
00
255.00
255.0
0
255.00
256.00
255.
00
255.00
254.0
0
254.00
255.00
255.0
0
254.00
254.00
255.
0025
6.00
254.0
025
4.00
255.
00
253.
0025
2.00
251.
00
254.00
255.00
255.0
0
252.0
025
3.00
250.0
025
1.00
252.
0025
3.00
247.00
246.0
0
245.00
244.
00
242.0
0
243.0
0
241.0
0
240.00
240.
00 239.00 238.00
237.00
237.00
235.00
236.00
237.0
0
234.00
235.00
236.0
0
237.0
0
238.00
238.00
238.00239
.00
240.00
240.00
240.00
241.00241.00
241.00
241.00
241.00
241.00241.0
0
242.0
0241.0
0241.00241.00
242.
00
242.00242.0
0
243.00
243.00
242.00
242.00
243.00
243.0
0
244.0
0
245.0
0
246.00
247.00
248.00
249.
00
250.00251.00
251.00
252.00
253.0
0
255.
00
254.
0025
3.00
252.0
025
1.00
250.0
024
9.00
248.0
0
246.00
247.00
248.
00
253.00
252.00 251.0
0 250.00
249.00
245.
00
244.00
243.0
0
242.0
0
241.
00
240.0
0 239.00
238.00
239.00
238.0
0
239.
00
240.00
241.0024
1.00
242.0
0
243.00
236.0
0
237.0
0
238.
00
184.00
N O R T H H A L F O F L O T 5 7WET AREA
NO FENCE
DITCH
DITC
H
CHAINLINK FENC
E
CHAINLINK
FENCE
BOARD FE
NCE
BOARD FENCE
REMAINS OF POST AN
D WIRE FENCE
DITC
H
DITCH
14117
14118
WL-2
237.9714119
WL-3
14120
WL-4
14121
WL-5
14122
WL-6
14123
WL-7
14124
WL-8
14125
WL-9
14126
WL-10
14127
14128
WL-12
14129
WL-13
14130
WL-14
14131
WL-15
14132
WL-16
14133
WL-17
14134
WL-18
238.08 14135
WL-19
14136
WL-20
14137
WL-22
14138
WL-23
14139
WL-24
14140
WL-25WL-
26
14142
WL-27
14143
WL-28
14144
WL-29
14145
WL-30
14146
WL-31
14147
WL-32
14148
WL-33
14149
WL-34
14150
WL-35
235.72 14151
WL-36
14152
WL-37
14153
WL-38
235.40 141
54WL-
39
14155
WL-40
14156
WL-41
235.05 14157
WL-42
14159
BH #1BOREHOLE
14160
BH #2BOREHOLE
14161
BH #3BOREHOLE
14162
BH #4BOREHOLE
14163
BH #5BOREHOLE141
64BH
#6
BOREHOLE
14165
BH #7BOREHOLE
14166
BH #8BOREHOLE
14167
BH #9BOREHOLE 141
68
BH #10BOREHOLEBELLPED
BELLPED
BELLPED
BELLPED
CBCB
CBCB
16540
MON WELL16542
MON WELL
254.61 16560
MON WELL
16572
MON WELL
16580
MON WELLCB
16591
16592
MON WELLCB
16704
MON WELL
CB
20056
239.67 20057
EW
20058
EW20059EW 2006
0
20061
20062
EW
20063
20064
EW20065EW
20066
EW 20067
EW20068239.64 20069
EW
20070
EW
20071
20076
EW20077EW20078
20079
EW
20082
20083
20084
20090
EW
20119
240.31 201
20
EW
20121
EW
20122
EW
20123
0.27 SOUTHWEST
END OF FENCE0.15 NORTHWEST
PL5&MEASMEASX X X X X X X X X X X X X X X
PL3285.83PL5
X X X X XPL5&MEAS
X X X X X X X X X X X X X X X X X X X184.00 MEAS 110.56 MEAS
MEAS
PL3294.58
P A R T 1 , P L A N 5 1 R - 1 9 4 2 4
(NOT TO SCAL
E)980
.76N62%%
d36'50"W
728.4
4N2
9%%
d05'2
5"W
(NOT
TO SC
ALE)
X X X X X X X X X X X X X
END OF FENCE
ON LINE
MEAS MEAS
290.37 PL3,PL5
PL3,PL5&MEAS
PL3
MEASMEAS
257.83 PL3,PL5
PL5,P
L6&M
EAS
57.4
0PL
6&M
EAS
298.
97PL
6&M
EAS
PART 4, PLAN 51R-27010
PART 3, PLAN 51R-27010PL3
PL5PL5N58%%d 18' 50"E
PL3
N58%%d 05' 40"E PL5
PL5
,PL6
MEAS
P A R T 1 , P L A N
5 1 R - 3 2 9 3 2
PL5,PL6&MEAS
MEAS
N57%%d43'25"E PL5,PL6
MEAS
MEAS
N57%%d43'20"E PL5
45.72 D2,PL5
PL1&SET
MEAS
N32%%d20'25"W PL5
55.01 D2,PL5
FENCE
1.55 SOUTHWEST
FENCE0.68 SOUTHWEST
48.6
6M
EAS
48.9
1PL
56.2
1M
EAS
6.1
0P
L1,P
L5,P
L8
PART 3, PLAN 51R-28303PART 1, PLAN 51R-5148
PART 2
PART 1, PLAN 51R-32932
PAR
T 4,
PLA
N 5
1R-2
8303
PL8&SETMEAS
N57%%d22'00"E PL8N57%%d47'30"E PL5 PL583.88
L O T 6 B L O C K B
MEAS
N57%%d44'35"E PL8
90.97N58%%d08'00"E PL190.93N58%%d24'45"E PL5
6.10PL8&MEAS
MEAS84.73
MEASXX X XXXXX
103.59N58%%d30'30"E PL1,PL5PL1
N58%%d14'00"E PL5
N57%%d42'30"E 88.61 PL5
LOT
10LOT 11
N57%%d59'00"E 80.99
20.7660.24
B L O C K C
XXXXXXXXXXXXX
PART 2PART 1PLAN 51R-18869
MEAS
31.46 PL5,PL931.49 MEAS
31.46 PL5,PL929.87
PL5,PL10&MEAS
PART 17PART 16PART 15PART 14PART 13
29.6
8
29. 87PL10& MEAS
29.84 PL5 24.23PL5,PL10&MEAS
29.87PL5,PL10&MEAS
5.6
4 P
L10&
ME
AS
5.6
1 P
L5
MEASNO FENCE
FENC
EC
HA
IN L
INK
FENC
E0.1
6 S
OU
TH
EA
ST
P L A N 5 1 R - 1 6 8 3 2
FEN
CE
0.1
5 S
OU
TH
EA
ST
PL5
,PL1
0&M
EA
S
FENC
E0
.50
NO
RT
HW
ES
T
FENC
E0.5
0 N
OR
TH
WE
ST
FEN
CE
CH
AIN
LIN
K
X XX
X
XXX N58%%d 26' 00"E PL5,PL9,PL10
PART F
R E G I S T E R E D P L A N 4 5 1 LOT 25
PART E
LOT 24
PART D
LOT 23
X XX
PART C
LOT 22
PART B
LOT 21
PART A
LOT 20LOT 19LOT 18P L A N 5 1 R - 4 0 7 6
R E G I S T E R E D P L A N 2 0 3
MEA
SP
L5&
ME
AS
N32%
%d11
'30"W
PL2
,PL5
129.5
4PL
2
POST
AN
D W
IRE
FEN
CE
X
X
X
X
X
X
X
X
X XX XX
X
PART 2 , PLAN 51R - 3398
LOT 17LOT 16LOT 15L OT 14LOT 13LOT 12LOT 11LOT 10LOT 9
FENCEON LINE
P A R T 1 , P L A N 5 1 R - 3 3 9 8
MEAS
256.79 PL2
257.00 PL5
X X X X X X X X X X X X X X X X X X
MEA
S129.5
4N3
2%%d
11'30
"WP
L2129.4
1N3
2%%d
15'30
"WP
L5
POST
AN
D W
IRE
FEN
CE
0.30 NORTHEAST
FENCE0.06 SOUTHEAST
PL2,PL5&SET256.79N56%%d 50' 00"E MEASN57%%d 43' 30"E PL2,PL5
X
X
X
X
X
X
X
X
LOT 8LOT 7LOT 6
LOT 5
XX
X
X
X
X
N56%%d 35' 35"E 152.52 MEAS
D1,PL5&SETMEAS
N57%%d27'40"E PL5
X
PL5,P
L11&M
EAS
MEA
S
N40%
%d18'0
0"WPL
5,PL1
1
MEA
S11
9.00
3.0
7PL
12&M
EAS
PART 1PLAN 51R-32018
KNO
WN
ASPEN
ETANG
UISH
ENE R
OAD
(THE KIN
G'S H
IGH
WAY N
o. 93)
MEA
S
PL5,PL11,P
L12&MEA
S
6.98PL1
2&MEAS
84.57
PL12&M
EAS
N43%%
d10'00"
WPL
5,PL1
1
158.8
7
N48%%
d02'00"W
PL5,P
L11
N O R T H H A L F O F L O T 5 6
A P P R O X I M A T E L I M I T B E T W E E N L O T S 5 6 A N D 5 7 , C O N C E S S I O N 1
C O N C E S S I O N
1
PLAN 51R-28303
113.
47PL
11
PL11
158.
85
N45%%
d51'30"W
PL12
N40%
%d08'5
0"WPL1
2
N58%%d 06' 30"E PL5
N3
1%
%d
3
4'
50
"W
N58%%d10'55"E287.81 PL6
PL1
211
9.04
PL1
212
2.11
N43%%d56'30"WD1,PL5&MEAS38.40
MEASN43%%d10'00"W D1N43%%d07'35"W PL5
XX
X X XMEAS PL10&MEAS
N57%%d47'30"E PL5,10 83.75 PL5 128.30 PL5, PL10
NO FENCEPL5
REMAINS OF POST AND WIRE FENCE
MEAS
N57%%d 59' 00"E 169.62 PL1
N57%%d58'15"E PL7
88.58 PL7&MEAS
PART 1 PART 2 PART 3PLAN 51R - 27092
SE
T O
UT
IN IN
ST.
RO
1429
615
SU
BJE
CT
TO A
N E
AS
EM
EN
T A
S
NO FENCEX
X
XPOST ANDWIRE FENCE
X
X
POST AND WIRE FENCEEND OF REMAINS OF
AS SET OUT IN INST. RO1429616SUBJECT TO AN EASEMENT
REMAINS OF POST AND WIRE FENCE
X
PL884.76
PART 1 PLAN 51R-21494
PAR
T 3
SE
T O
UT
IN IN
ST.
LT1
1907
6SU
BJEC
T TO
AN
EAS
EMEN
T AS
(BY REGISTERED PLAN 203)ANN STREET
PL5&MEAS
N43%%d07'35"W PL5
MEAS
N43%%d10'30"W PL11
GRAVEL DRIVEWAY
30.78PL14& MEAS PART G
PL5&
MEAS
MEA
S
NO FENCE
NO
FEN
CE
PART
KNOWN AS ALBERT STREET
18026
BH#11BOREHOLE
\A1;20.00\A1;20.00
\A1;20.00 \A1;20.00
PARKETTE0.53 ha
MTO
BUFFER
MTO
BUFFERC
HAN
NEL BLO
CK
MTO STORM FLOWS CHANNEL BLOCK
SWM Pond2.73 ha
Septic Area3.80 ha
Park12.9 ha
CommunalApproximate
Open Space7.4 ha
RO
AD
FUTU
RE
RO
AD
FUTU
RE
L O
T
1
1
REGISTERED PLAN 451
N
REMAINS OF POST AND WIRE FENCE
P L
A N
5
1 R
-
2 1
4 9
4
X
PART
1, P
LAN
51R-
6619
P A
R T
4
PA
RT
2P
A R
T
1
L O
T
1
0
P A
R T
1
,
P L
A N
5 1
R
-
2 7
0 9
2
B L
O
C
K
B
BLOCK C
PART
3PL
AN 5
1R-2
7092
X X X X XXX
XX
XXBOARD FENCE
POST
AND W
IRE FE
NCE
XXBOARD FENCE
X
X
X
X
X
X
X
X
X
X
X
FRAMESHED
SHED
SHED
FRAMESHED
XX
X
X
X X
LINK FENCE
BOAR
D FE
NCE
LOT 9
KNOWN AS MILL STREET(ROAD ALLOWANCE BETWEEN LOTS 55 AND 56, CONCESSIONS 1)
LIMIT OF ORIGINAL ROAD ALLOWANCE
XX X
XBOARD
CHAI
N LI
NK F
ENCE
SHED
NO F
ENCE
X
FRAMESHED
PAR
T 3
PART 4PLAN 51R-3355
SHED
NORTHEAST ANGLEOF LOT 10REGISTERED PLAN 451
\A1;45.00
SETTLEMEN
T BOU
ND
ARY
MTO STORM FLOWS CHANNEL BLOCK
Tree
Storm Swale
MTO
STOR
M FLO
WS
NO
ISE BLOC
K
NO
ISE BLOC
K
BUFFER BLOCK
Storm Swale & Access Road
Road Setback
AREA 1
AREA 2
AREA 3
CT
CT
CT
07-20
07-21
07-23
2-081-08
3-08
4-08
10-08
11-08
12-0813-088-08 10-08
6-085-08
9-08
OW2
OW1
OW3
OW4
OW6
OW5
OW12
OW8
OW9
OW7
TP21TP22 TP23
TP24
TP1
TP2
TP3
TP4TP5
TP6
TP7
TP8 TP9
TP10
TP11
TP12
TP14
TP15
TP19
TILE07-1
07-16 07-15
07-2
07-3
07-14
07-13
07-4
07-5
07-12
07-7
07-6
07-8
07-11
07-9
07-10
CT1 2
6
5
8
4
3
BH-1
BH-2 BH-3
BH-4BH-5
TB-1
SWM-1TB-2
TP1 TP2
TP3
TP4
TP5
TP6
TP7
TP8
Compressible Soils
SARJEANT LANDSSARJEANT LANDSSARJEANT LANDSSARJEANT LANDSSARJEANT LANDSSARJEANT LANDSSARJEANT LANDSSARJEANT LANDSSARJEANT LANDSSARJEANT LANDSSARJEANT LANDSSARJEANT LANDSSARJEANT LANDSSARJEANT LANDSSARJEANT LANDSSARJEANT LANDSSARJEANT LANDS
HERITAGE LANDSHERITAGE LANDSHERITAGE LANDSHERITAGE LANDSHERITAGE LANDSHERITAGE LANDSHERITAGE LANDSHERITAGE LANDSHERITAGE LANDSHERITAGE LANDSHERITAGE LANDSHERITAGE LANDSHERITAGE LANDSHERITAGE LANDSHERITAGE LANDSHERITAGE LANDSHERITAGE LANDS
ALBERT STREETALBERT STREETALBERT STREETALBERT STREETALBERT STREETALBERT STREETALBERT STREETALBERT STREETALBERT STREETALBERT STREETALBERT STREETALBERT STREETALBERT STREETALBERT STREETALBERT STREETALBERT STREETALBERT STREET
HIG
HW
AY 93H
IGH
WAY 93
HIG
HW
AY 93H
IGH
WAY 93
HIG
HW
AY 93H
IGH
WAY 93
HIG
HW
AY 93H
IGH
WAY 93
HIG
HW
AY 93H
IGH
WAY 93
HIG
HW
AY 93H
IGH
WAY 93
HIG
HW
AY 93H
IGH
WAY 93
HIG
HW
AY 93H
IGH
WAY 93
HIG
HW
AY 93
HILLSDALE LAND CORPORATIONHERITAGE VILLAGE 1
PROPOSED EFFLUENT BEDTEST PIT INVESTIGATIONS
Barrie, Ontario, Canada
TITLE
PROJECT No.
FILE No.
REV.
SCALE
CAD
DESIGN
REVIEW
CHECK
DATE
FIGURE0711700010GASITE.dwg
07-1170-0010 E
AS SHOWN
2016-03-15
JPR
DPD
Development Property Line
N
0 25 50 100 250
SCALE 1:4000 metresPlotted Tabloid 11x17
300
m O
ffset
from
Wat
er C
ours
esSept
ic T
anka
ge
Septic Design Borehole (Sarjeant Lands)
(Pro
pose
d)
2016 Test Pit for Septic Design
Geotechnical and Other Historical Investigations
Hillsdale Community Limit
Heritage Village Layout, Malone Given Parsons 07 Dec 2016Subject to Revision
Sarjeant Lands Layout, Malone Given Parsons 07 Dec 2016Subject to Revision
0.1
5
0.65
6.5
0.450.55
5.5
4.5
0.35
0.250.22
2.2
3.5
1.75
1.25
0.75
0.25
0.0
0.5
1.0
1.5
2.0
cm/m
in
0.2
0.3
0.4
0.50.60.70.80.9
1
4
2
1.5
3
8
56
910
2.5
MASCH & DENNY
d50 (phi units)1.03.04.0 2.0 0.0
0.0020.001
10
0.050.010.005 0.02
20
30
UNIFIED SOIL CLASSIFICATION SYSTEMCLAY DENOTED FROM MIT SOIL CLASSIFICATION
0.50.2 1.00.1
Grain Size (mm)20105.02.0 7050
100
90
80
70
50
% S
ize
Pas
sing
40
60
70
80
CLAY AND SILT (fines)
90
100
CLAY*
SIEVES
SILT
270
30
20
Coarse
200 140 100 60
Fine
304050 20 16
Medium
10 4
Coarse
3 1"
Fine
SAND GRAVEL
10
02"8"
LEGEND
/ 1 2"/ 3 4"/*
TP1 - 75 cmTP1 - 137 cmTP2 - 75 cmTP2 - 127 cm
TP3 - 100 cm
ML
SM
ML
TP4 - 71 cmTP4 - 178 cm CONSULTANT
DESIGN
PREPARED
REVIEW
APPROVED
YYYY-MM-DD TITLE
PROJECT No. Rev.
PROJECTCLIENT
Path: ################################################ | File Name: 1649706-0002-CW-SVE1.dwg
025
mm
IF T
HIS
ME
AS
UR
EM
EN
T D
OE
S N
OT
MA
TCH
WH
AT
IS S
HO
WN
, TH
E S
HE
ET
SIZ
E H
AS
BE
EN
MO
DIF
IED
FR
OM
: AN
SI A
1649706Phase-
Figure
S-102
2016-06-20
JPR
HERITAGE VILLAGEHILLSDALE, TOWNSHIP OF SPRINGWATER
HILLSDALE LAND CORPORATION
GRAIN SIZE ANALYSESTEST PITS 1, 2, 3, 4
SM
0.1
5
0.65
6.5
0.450.55
5.5
4.5
0.35
0.250.22
2.2
3.5
1.75
1.25
0.75
0.25
0.0
0.5
1.0
1.5
2.0
cm/m
in
0.2
0.3
0.4
0.50.60.70.80.9
1
4
2
1.5
3
8
5
6
910
2.5
MASCH & DENNY
d50 (phi units)1.03.04.0 2.0 0.0
0.0020.001
10
0.050.010.005 0.02
20
30
UNIFIED SOIL CLASSIFICATION SYSTEMCLAY DENOTED FROM MIT SOIL CLASSIFICATION
0.50.2 1.00.1
Grain Size (mm)20105.02.0 7050
100
90
80
70
50
% S
ize
Pas
sing
40
60
70
80
CLAY AND SILT (fines)
90
100
CLAY*
SIEVES
SILT
270
30
20
Coarse
200 140 100 60
Fine
304050 20 16
Medium
10 4
Coarse
3 1"
Fine
SAND GRAVEL
10
02"8"
LEGEND
/ 1 2"/ 3 4"/*
TP5 - 140 cmTP5 - 85 cm
TP6 - 45 cmTP6 - 75 cm
SP
SP
CONSULTANT
DESIGN
PREPARED
REVIEW
APPROVED
YYYY-MM-DD TITLE
PROJECT No. Rev.
PROJECTCLIENT
Path: ################################################ | File Name: 1649706-0002-CW-SVE2.dwg
025
mm
IF T
HIS
ME
AS
UR
EM
EN
T D
OE
S N
OT
MA
TCH
WH
AT
IS S
HO
WN
, TH
E S
HE
ET
SIZ
E H
AS
BE
EN
MO
DIF
IED
FR
OM
: AN
SI A
1649706Phase-
Figure
S-202
2016-06-20
JPR
HERITAGE VILLAGEHILLSDALE, TOWNSHIP OF SPRINGWATER
HILLSDALE LAND CORPORATION
GRAIN SIZE ANALYSESTEST PITS TP5, TP6
0.1
5
0.65
6.5
0.450.55
5.5
4.5
0.35
0.250.22
2.2
3.5
1.75
1.25
0.75
0.25
0.0
0.5
1.0
1.5
2.0
cm/m
in
0.2
0.3
0.4
0.50.60.70.80.9
1
4
2
1.5
3
8
56
910
2.5
MASCH & DENNY
d50 (phi units)1.03.04.0 2.0 0.0
0.0020.001
10
0.050.010.005 0.02
20
30
UNIFIED SOIL CLASSIFICATION SYSTEMCLAY DENOTED FROM MIT SOIL CLASSIFICATION
0.50.2 1.00.1
Grain Size (mm)20105.02.0 7050
100
90
80
70
50
% S
ize
Pas
sing
40
60
70
80
CLAY AND SILT (fines)
90
100
CLAY*
SIEVES
SILT
270
30
20
Coarse
200 140 100 60
Fine
304050 20 16
Medium
10 4
Coarse
3 1"
Fine
SAND GRAVEL
10
02"8"
LEGEND
/ 1 2"/ 3 4"/*
TP7 - 75 cmTP8 - 100 cm
SP
TB-1 - 150 cmTB-2 - 150 cm
SP
CONSULTANT
DESIGN
PREPARED
REVIEW
APPROVED
YYYY-MM-DD TITLE
PROJECT No. Rev.
PROJECTCLIENT
Path: \golder.gds\gal\barrie\CAD rojects\2007\07-1170-0010 (Hillsdale, ESA)\-GA-2016\ | File Name: 0711700010SVE3.dwg
025
mm
IF T
HIS
ME
AS
UR
EM
EN
T D
OE
S N
OT
MA
TCH
WH
AT
IS S
HO
WN
, TH
E S
HE
ET
SIZ
E H
AS
BE
EN
MO
DIF
IED
FR
OM
: AN
SI A
1649706Phase-
Figure
S-302
2016-06-20
JPR
HERITAGE VILLAGEHILLSDALE, TOWNSHIP OF SPRINGWATER
HILLSDALE LAND CORPORATION
GRAIN SIZE ANALYSESTEST PITS TP7 TP8; BOREHOLES TB-1 TB-2
WASTE WATER DISPOSAL DESIGN
TABLES
March 9, 2017 Report No. 07-1170-0010
Soils AnalysesTABLE 1 HERITAGE VILLAGE
Testpit Depth (cm) Silt(%) Type k TTP1 60 - 90 30 SM 10-4 12TP1 140-170 34 SM 10-5 20TP2 60 - 90 34 SM 10-4 12TP2 150-180 76 ML 10-6 40TP3 70-100 69 ML 10-6 40TP4 60 - 90 30 SM 10-5 20TP4 140-170 52 SM - ML 10-6 30TP5 90-120 28 SM 10-5 20TP5 130-160 6 SP 10-2 6TP6 30-60 9 SP 10-2 8TP6 60-90 50 ML-SP 10-6 40
TABLE 2 SARJEANT LANDSTestpit Depth (cm) Silt(%) Type k TTP7 60-90 13 SP 10-3 10TP8 100-130 7 SP 10-2 8
SP Poorly Graded Sands, Gravelly Sand, k 10-1 to 10-3
SM Silty Sands, Sand Silt Mixtures, k 10-3 to 10-5
ML Inorgranic Silts and vf Sands, Low Plasticity, k 10-3 to 10-5
WASTE WATER DISPOSAL DESIGN
APPENDIX A Borehole Logs
March 9, 2017 Report No. 07-1170-0010
Bug
gy M
ount
Pow
er A
uger
DO
DO
DO
DO
DO
DO
DO
1
2
3
4
5
6
7
2
16
25
20
19
27
11
Hol
low
Ste
m A
uger
(SP) SAND, trace silt, with topsoil; darkbrown to brown; non-cohesive, moist,very loose
(SG) gravelly SAND; brown;non-cohesive, moist, compact
(SM) SILTY SAND, trace clay, trace tosome gravel; grey, (TILL); non-cohesive,moist to wet, compact
End of Borehole
NOTE:
1.52
3.05
9.60
Casing
Hole Plug
Silica Sand
10 Slot PVC Screen
TY
PE
BORING DATE: April 22, 2016
NU
MB
ER
Wl
PIEZOMETEROR
STANDPIPEINSTALLATION
HYDRAULIC CONDUCTIVITY, k, cm/s
Wp W
WATER CONTENT PERCENT
BO
RIN
G M
ET
HO
D
ELEV.
AD
DIT
ION
AL
LAB
. TE
ST
ING
SOIL PROFILE
ST
RA
TA
PLO
T
BLO
WS
/0.3
m 10-6 10-5 10-4 10-3
10 20 30 40
SHEET 1 OF 2
SPT/DCPT HAMMER: MASS, 64kg; DROP, 760mm
RECORD OF BOREHOLE: TB-1
SAMPLES
DEPTH(m)
DESCRIPTION
GROUND SURFACE
CONTINUED NEXT PAGE
LOGGED:
CHECKED:
DATUM: Geodetic
PROJECT: 1654967-BG-0001
LOCATION: N ; E
DD
0.00
DEPTH SCALE
1 : 50
DE
PT
H S
CA
LEM
ET
RE
S
0
1
2
3
4
5
6
7
8
9
10
NL
GT
A-B
HS
001
S
:\CLI
EN
TS
\GE
RA
NIU
M\H
ILLS
DA
LE\0
2_D
AT
A\G
INT
\165
496
7-B
G-0
001.
GP
J G
AL-
MIS
.GD
T 4
-28
-16
ST
B
DYNAMIC PENETRATIONRESISTANCE, BLOWS/0.3m
20 40 60 80
SHEAR STRENGTHCu, kPa
20 40 60 80
Q -U -
nat V.rem V.
1. Borehole dry upon completion ofdrilling on April 22, 2016.
TY
PE
BORING DATE: April 22, 2016
NU
MB
ER
Wl
PIEZOMETEROR
STANDPIPEINSTALLATION
HYDRAULIC CONDUCTIVITY, k, cm/s
Wp W
WATER CONTENT PERCENT
BO
RIN
G M
ET
HO
D
ELEV.
AD
DIT
ION
AL
LAB
. TE
ST
ING
SOIL PROFILE
ST
RA
TA
PLO
T
BLO
WS
/0.3
m 10-6 10-5 10-4 10-3
10 20 30 40
SHEET 2 OF 2
SPT/DCPT HAMMER: MASS, 64kg; DROP, 760mm
RECORD OF BOREHOLE: TB-1
SAMPLES
DEPTH(m)
DESCRIPTION
LOGGED:
CHECKED:
--- CONTINUED FROM PREVIOUS PAGE ---
DATUM: Geodetic
PROJECT: 1654967-BG-0001
LOCATION: N ; E
DDDEPTH SCALE
1 : 50
DE
PT
H S
CA
LEM
ET
RE
S
10
11
12
13
14
15
16
17
18
19
20
NL
GT
A-B
HS
001
S
:\CLI
EN
TS
\GE
RA
NIU
M\H
ILLS
DA
LE\0
2_D
AT
A\G
INT
\165
496
7-B
G-0
001.
GP
J G
AL-
MIS
.GD
T 4
-28
-16
ST
B
DYNAMIC PENETRATIONRESISTANCE, BLOWS/0.3m
20 40 60 80
SHEAR STRENGTHCu, kPa
20 40 60 80
Q -U -
nat V.rem V.
Bug
gy M
ount
Pow
er A
uger
DO
DO
DO
DO
DO
DO
DO
1
2
3
4
5
6
7
3
6
18
50
52
42
55
Hol
low
Ste
m A
uger
(SM) SILTY SAND, with topsoil; darkbrown to brown; non-cohesive, moist,very loose
(SP) SAND, trace silt; brown;non-cohesive, moist to wet, compact
(SM) SILTY SAND, trace clay, trace tosome gravel; grey, (TILL); non-cohesive,moist, very dense to dense
(SG) gravelly SAND, trace silt; grey;non-cohesive, moist, very dense
End of Borehole
NOTE:
1.52
4.57
8.61
9.60
TY
PE
BORING DATE: April 22, 2016
NU
MB
ER
Wl
PIEZOMETEROR
STANDPIPEINSTALLATION
HYDRAULIC CONDUCTIVITY, k, cm/s
Wp W
WATER CONTENT PERCENT
BO
RIN
G M
ET
HO
D
ELEV.
AD
DIT
ION
AL
LAB
. TE
ST
ING
SOIL PROFILE
ST
RA
TA
PLO
T
BLO
WS
/0.3
m 10-6 10-5 10-4 10-3
10 20 30 40
SHEET 1 OF 2
SPT/DCPT HAMMER: MASS, 64kg; DROP, 760mm
RECORD OF BOREHOLE: TB-2
SAMPLES
DEPTH(m)
DESCRIPTION
GROUND SURFACE
CONTINUED NEXT PAGE
LOGGED:
CHECKED:
DATUM: Geodetic
PROJECT: 1654967-BG-0001
LOCATION: N ; E
DD
0.00
DEPTH SCALE
1 : 50
DE
PT
H S
CA
LEM
ET
RE
S
0
1
2
3
4
5
6
7
8
9
10
NL
GT
A-B
HS
001
S
:\CLI
EN
TS
\GE
RA
NIU
M\H
ILLS
DA
LE\0
2_D
AT
A\G
INT
\165
496
7-B
G-0
001.
GP
J G
AL-
MIS
.GD
T 4
-28
-16
ST
B
DYNAMIC PENETRATIONRESISTANCE, BLOWS/0.3m
20 40 60 80
SHEAR STRENGTHCu, kPa
20 40 60 80
Q -U -
nat V.rem V.
1. Groundwater measured at a depth of3.1 m in open borehole upon completionof drilling on April 22, 2016.
TY
PE
BORING DATE: April 22, 2016
NU
MB
ER
Wl
PIEZOMETEROR
STANDPIPEINSTALLATION
HYDRAULIC CONDUCTIVITY, k, cm/s
Wp W
WATER CONTENT PERCENT
BO
RIN
G M
ET
HO
D
ELEV.
AD
DIT
ION
AL
LAB
. TE
ST
ING
SOIL PROFILE
ST
RA
TA
PLO
T
BLO
WS
/0.3
m 10-6 10-5 10-4 10-3
10 20 30 40
SHEET 2 OF 2
SPT/DCPT HAMMER: MASS, 64kg; DROP, 760mm
RECORD OF BOREHOLE: TB-2
SAMPLES
DEPTH(m)
DESCRIPTION
LOGGED:
CHECKED:
--- CONTINUED FROM PREVIOUS PAGE ---
DATUM: Geodetic
PROJECT: 1654967-BG-0001
LOCATION: N ; E
DDDEPTH SCALE
1 : 50
DE
PT
H S
CA
LEM
ET
RE
S
10
11
12
13
14
15
16
17
18
19
20
NL
GT
A-B
HS
001
S
:\CLI
EN
TS
\GE
RA
NIU
M\H
ILLS
DA
LE\0
2_D
AT
A\G
INT
\165
496
7-B
G-0
001.
GP
J G
AL-
MIS
.GD
T 4
-28
-16
ST
B
DYNAMIC PENETRATIONRESISTANCE, BLOWS/0.3m
20 40 60 80
SHEAR STRENGTHCu, kPa
20 40 60 80
Q -U -
nat V.rem V.
WASTE WATER DISPOSAL DESIGN
APPENDIX B Test Pit Logs
March 9, 2017 Report No. 07-1170-0010
GOLDER ASSOCIATESTEST PIT INVENTORY
CLIENT: Hillsdale - Heritage Village LandsJOB NO: 1649706 DATE : 15-Jun-2016
BY: JPRSTREET 911 Property # LOT NO. Logged:Access off Highway 93 JPRFrom To Colour Density Description TEST PIT # 1
0 10 Brown Compact Sandy LOAM10 137 Red Compact Silty SAND, grading Silt with f-m Sand Layers, Seeps @ 1 m
137 244 Grey Compact Layered f-m SAND, Silt Banding; Wet
Design or Comments: Standing Water below 1.5 m depth, Formation CavesBackfilled and Excavator Compacted
From To Colour Density Description TEST PIT # 2
0 15 Black Compact Sand / Silt LOAM15 56 Red Compact Silty f-m SAND56 152 Brown Compact f-m SAND, Layered Sand Silt Rhythmites 2 to 10 cm's thick
152 183 Grey Hard SILT/ vf Sandy Silt183 244 Grey Loose m SAND, Silt Layered, Wet
Design or Comments: Standing water below 1.8 m depth, Formation CavesBackfilled and Excavator Compacted
GOLDER ASSOCIATESTEST PIT INVENTORY
CLIENT: Hillsdale - Heritage Village LandsJOB NO: 1649706 DATE : 15-Jun-2016
BY: JPRSTREET 911 Property # LOT NO. Logged:Access off Highway 93 JPRFrom To Colour Density Description TEST PIT # 3
0 10 Brown Compact Sandy LOAM10 30 Red Compact f SAND, with f-m Silty Sand Layers30 107 Brown Compact Layered f SAND & Sand Silt Rhythmites 10 to 15 cm's thick
107 147 Grey Loose m SAND, Seeps147 213 Grey Loose Stoney SAND, Sand & Gravel / Silt Layered, Sorted213 244 Grey Compact vf Sandy SILT
Design or Comments: Standing Water below 1.8 m depth, Formation CavesBackfilled and Excavator Compacted
From To Colour Density Description TEST PIT # 4
0 30 Black Compact Silt LOAM30 51 Red Compact f-m SAND, with Silt51 91 Br-Grey Compact vf-f SAND, Layered Sand Silt Rhythmites 10 to 15 cm's thick91 183 Grey Compact m SAND & Sand Silt Rhythmites, Banding 2 - 3 mm thick
183 244 Grey Loose m SAND, Layered with Silt / vf Sand 2 - 3 cm's thick
Design or Comments: Standing water 1.5 m depth, Formation caves below 1.2 mBackfilled and Excavator Compacted
GOLDER ASSOCIATESTEST PIT INVENTORY
CLIENT: Hillsdale - Heritage Village LandsJOB NO: 1649706 DATE : 15-Jun-2016
BY: JPRSTREET 911 Property # LOT NO. Logged:Access off Highway 93 JPRFrom To Colour Density Description TEST PIT # 5
0 38 Brown Compact Sandy Silty LOAM38 64 Red Compact Silty SAND64 86 Yellow Compact f SAND, Black Silty Lens Banding / Sand Silt Layered86 127 Brown Soft Silty f SAND, Seep at depth
127 213 Grey Compact Grading to c Sand, into well sorted SAND & GRAVEL, rounded
Design or Comments: Standing Water below 1.8 m depthBackfilled and Excavator Compacted
From To Colour Density Description TEST PIT # 6
0 30 Black Compact Silt LOAM30 66 Red Compact f-m SAND, Trace to Some Silt66 127 Yellow Compact f Sand, Silt Lensed SAND & SILT; grading f-m Sand at depth
127 183 Brown Compact f-m SAND, Lensed f-vf Sands & Silt mixtures, Seeps @ depth183 213 Grey Soft vf SAND / Silty Sand213 274 Grey Loose m SAND274 Into f SAND, Layered m Sand with vf Sand & Slit, Wet
Design or Comments: Standing water 2 m depth, Formations caves below 1.5 mBackfilled and Excavator Compacted
GOLDER ASSOCIATESTEST PIT INVENTORY
CLIENT: Hillsdale - Sarjeant LandsJOB NO: 1649706 DATE : 15-Jun-2016
BY: JPRSTREET 911 Property # LOT NO. Logged:Access off Highway 93 JPRFrom To Colour Density Description TEST PIT # 7
0 25 Brown Loose Sandy Topsoil25 89 Red v Loose vf SAND, (Loess)89 213 Br-Grey Soft Clayey Silt, grading to SILT
213 244 Brown Loose m SAND, Uniform; formation Caves
Design or Comments: Seepage / Wet at 2.3 mBackfilled and Excavator Compacted
From To Colour Density Description TEST PIT # 8
0 25 Black Sandy Topsoil25 76 Red-Ylw Loose SAND, with Granular76 183 Brown Loose m SAND, uniform (sorted)
183 244 Grey Loose SAND / f Gravel244 274 Grey Loose SAND & GRAVEL
Design or Comments: Dry to depth, Formation Caves below 1.5 mBackfilled and Excavator Compacted
Golder Associates Ltd. 121 Commerce Park Drive, Unit L Barrie, Ontario, L4N 8X1 Canada T: +1 (705) 722 4492