conference report and recommenndations...conference report cost opmised construcon of tunnel in...
TRANSCRIPT
![Page 1: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/1.jpg)
Conference Report and Recommenndations
![Page 2: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/2.jpg)
![Page 3: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/3.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 2016 1 PageI
CONFERENCE REPORT
ACKNOWLEDGEMENTS
ASSOCHAM expresses sincere thanks to Chair and Co-Chair Naonal Council on
Power for their guidance and support extended to the Conference.
Chairman
Shri Shrirang KarandikarCEO, India Power Corporaon Ltd.
Co-Chairmen
Shri M.M.Madan
CEO (Hydro & Renewable Energy)
Jindal Power Ltd.
Shri Kapil Mantri
Head Corporate Strategy
Jindal Steel and Power Ltd.
Shri Sash Jindal
CEO and Director
JSW PTC Ltd.
ASSOCHAM is indebted to Knowledge partners for their intellectual contribuon
towards the Conference.
Yogesh DarukaPartner
Energy, Ulies & Mining, PwC [email protected]
Subhrajit Daa Ray
Soham Biswas
Suddhasaa Kundu
![Page 4: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/4.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 20162 PageI
CONFERENCE REPORT
CONTENTS
Conference Programme
Conference ProceedingsInaugural Session
Session 1 – Delusions and Advanced TechnologySession 2 – Policy, Governance Framework and Risk Migaon
Highlights of the Knowledge Paper
Importance of Hydropower Development
Conference Recommendaons
List of Parcipants
![Page 5: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/5.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 2016 3 PageI
CONFERENCE REPORT
PROGRAMME
9.30 am Registraon and Tea
10.00 am – 11.45 am Inaugural Session
10.00 am Lighng the Inaugural Lamp
10.03 am Opening Remarks Shri D.S.Rawat, Secretary General, ASSOCHAM
10.05 am Welcome Address Shri Sandeep Jajodia, Sr Vice President ASSOCHAM CMD, Monnet Ispat and Energy Ltd.
10.10 am Address Shri Sujit Ghosh, Partner & Naonal Head Taxaon, Advaita Legal 10.20 am Special Address Shri Naveen Jindal, CMD Jindal Steel & Power Ltd.
10.30 am Mr. Sigvald T. Hauge, Charge d' Affaires a.i.,/Deputy Chief of Mission Embassy of Norway in India 10.40 am Shri K.M. Singh, CMD, NHPC
10.50 am Smt Shakuntala D. Gamlin IAS, Chief Secretary to the Govt of Arunachal Pradesh
11.00 am Addresses by the Shri B.P. Pandey IAS, Addional Secretary to the Guests of Honour Govt of India, Ministry of Power (Hydro) 11.15 am Inaugural Address Shri Kalikho Pul by the Chief Guest Hon'ble Chief Minister, Govt of Arunachal Pradesh 11.40 am Vote of Thanks Mr. Shrirang Karandikar Chairman Naonal Council on Power and CEO India Power Corporaon Ltd.
11.45 am – 12.15 noonTea / Coffee
12.15 noon – 2.00 pm Session 1: Hydropower Development – Delusions and Advanced Technologies
Chairman Shri A.B. Pandya, Former Chairman CWC
Co-Chair and Session Co-ordinator Shri Sash Kumar Sharma, V. P. Eng. Management , HCC Ltd.
Environmental inc. Seismic and Safety issues Shri D.P. Bhargava, Former Dir - Tech NHPC Ltd. of downstream people on Hydro Power Shri P.K. Gupta General Manager (Geo-Tech), NHPC Longitudinal Flow in High Dams; is it possible? Shri D. P. Goyal, Director Jaiprakash Power Ventures
Hydro Technology – Exploing the potenal Shri Rohit Uberoi, Vice President and Head of Design and Engg, Voith Hydro Pvt Ltd.
![Page 6: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/6.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 20164 PageI
CONFERENCE REPORT
Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd.
High impact velocity hydro abrasive erosions Dr. D.A. Karandikar Head - Coang Plant, Andritz Hydro Pvt Ltd.
Hydropower: Balancing of Renewable Shri K.K. Singh, Reg. Exe. Director (Hydro), NTPC Ltd.
Hydropower: The Innovave Way Shri Maninder Singh, Director, Internaonal Coil Ltd.
Queson / Answers
2.00 pm – 3.00 pm Lunch
3.00 pm – 5:30 pm Session 2: Sustainable Development, Policy and Government Framework, and Risk Migaon
Chairman and Shri Shyam D. Dubey, Member (Hydro), Session Co-ordinator Central Electricity Authority Co-Chairman Shri M.M. Madan, CEO (Hydro & Renewables) Jindal Power
Co- chairman Shri A.B.Giri, Member Board Internaonal Hydropower Associaon
Necessity for Hydropower Development Shri Anand Behari Agrawal Execuve Director (HR), NHPC and Former Chairman Bhakra Beas Management Board
Why change in Hydro Power Policy is required Shri Asim Thakurta, Chief, Corporate Projects, Tata Power and Chairman, Dugar Hydropower Ltd.
Sustainable Development of Hydropower Shri Gyanbhadra Kumar, Head Hydro, JSW Energy
Policy Imperaves Shri Kapil Mantri, Head, Corporate Strategy and Bus. Development, Jindal Steel & Power Limited
Risk Migaon Shri Rahul Varshney, Director, Buss Dev. Statkra Ltd.
Sharing of risks through Contract Document Shri Vibhash Pathania (On Behalf of ) Mr. Rajeev Vishnoi, General Manager, THDC
Financing Risks in Hydropower Development - Mr. Kaushlendra Tripathi Director, Energy advisory, Key Migaon Measures PWC
Address Shri K.C.Dhimole, Tech Advisor to CM Arunachal
Concluding Address Shri M.M. Madan, Chairman Hydro Group, ASSOCHAM
Queson / Answers
5.30 pm. High Tea (Close)
![Page 7: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/7.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 2016 5 PageI
CONFERENCE REPORT
HYDRO POWER@CROSSROADS - Tapping The Untapped
ASSOCHAM had organised the Conference on
Hydropower@Crossroads on May 3, 2016 at Hotel
Lalit, New Delhi. Shri Kalikho Pul, Hon'ble Chief
Minister of Arunachal Pradesh was the Chief Guest at
the Occasion. Shri T.N. Thongdok, Hon'ble Minister of
Power and Non-Convenonal Energy, Govt of
Arunachal Pradesh, Shri B.P. Pandey IAS, Addional
Secretary to the Government of India, Ministry of
Power, Mrs. Shakuntala D. Gamlin, Chief Secretary to
the Government of Arunachal and Shri Sigvald Hauge
Deputy Chief of Mission, Embassy of Norway and Shri
K.M. Singh CMD Naonal Hydropower Corporaon
were the Guests of Honour at the event. Mr. Naveen
Jindal, Chairman Jindal Steel and Power Ltd, the Steel
and Power Industry's legend was also present at the
event.
India is endowed with rich hydropower potenal to the
tune of 148 GW, which would be able to meet a
demand of 84 GW at 60% load factor. Various factors
have contributed to the slow pace of hydropower
development, resulng in the declining share of
hydropower in India's energy mix since 1966. These
have been compounded as hydropower development
has largely remained under the ambit of state
governments with varying policies since water is state
specific subject. The objecve of Conference was to
flag collecvely the concerns of industry and issues
that have led to the decline of the Hydroelectric Power
development - the most important constuent of the
green power, which is also extremely important for
balancing the renewable.
Inaugural Session
The Chief Guest Shri Kalikho Pul, Hon'ble Chief
Minister of Arunachal in his Inaugural Address said
that hydropower is indeed at crossroads as the sector is
not receiving the sort of aenon it deserves. Power is
the basis robust economy. With India aspiring for a
double digit economic growth, reliable, affordable and
sustainable power supply will be a key determinant to
achieve this objecve. It has been a maer of serious
concern that most of the hydropower projects are held
up because of issues like long construcon periods,
lack of transport infrastructure, environmental
concerns and geological risks. Environmental and
other clearances have slowed hydropower projects.
Out of a total 1.5 lakh MW hydro power potenal in the
country, around one-third has been harnessed to date.
One-half of the untapped potenal of 1.0 lakh MW in
the country is found in Arunachal Pradesh and
regreably, less than 1.0 per cent of the state's
potenal of 58,000 MW has been harnessed so far.
Thus, it will be Arunachal Government's priority to
ensure that this potenal is harnessed in an opmal
manner in which the environmental impact and human
displacement is reduced to the absolute minimal and
posive outcomes are achieved in the shortest
possible me. Worldwide, the total hydropower
installed capacity is 936 GW and leading generang
countries are China, Canada, Brazil, USA, Norway and
India.
Chief Minister informed that the State Government
had so far alloed 145 projects with a total installed
capacity of 46,432 MW. Of these, 10 projects with an
installed capacity of 11,675 MW have been alloed to
Chief Guest Shri kalikho Pul Honble Chief Minister of Arunachal lighng the Inaugural Lamp.
![Page 8: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/8.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 20166 PageI
CONFERENCE REPORT
Central Public Sector Undertakings. The remaining 135
projects with installed capacity of 34,757 MW have
been alloed to Independent Power Producers.
Currently, 3 out of 10 projects alloed to CPSUs are
under different stages of implementaon. By next
year, there will be a capacity addion of 710 MW from
2 of these 3 projects. Another project with Private
Sector - the Gongri HEP (144 MW) is also under
implementaon. Besides these projects, techno-
economic clearances for 31 projects (18368.19 MW)
have been accorded and Detailed Project Reports in
respect of 27 projects (4649.4 MW) are under
preparaon/ examinaon. The remaining projects are
in the Survey & Invesgaon stage. When the alloed
projects come up, the State would receive free power
more than 5600 MW installed generaon capacity in
terms of the agreements entered into with the
developers as against the state's current requirement,
which would not be more than one-tenth of that. The
surplus power will be available for development of
agricultural, mining, industrial and infrastructural
sectors. He assured developers that Arunachal
Government will provide support to developers for
installing & commissioning of hydropower plants
with facilies of single window clearance. All
requirements of local coordinaon will be fast tracked
with no barriers for investments. The State
government is also examining various opons available
to the state of Arunachal Pradesh for funding the
equity parcipaon of the state including the opon to
exit from the same. We invite power developers to
invest in the sector on an as-is-where-is basis and the
State government would only need for the 12% free
power to be assigned to it. Arunachal Government
stands commied to extension of necessary
cooperaon and assistance that is required to reduce
risks in the sector and ensure that hydropower projects
are commissioned without me and cost overruns.
Shri B.P. Pandey, Addional Secretary to the Govt of
India, Ministry of Power in his keynote address
presented status of Hydro Power Development in India
– A concept note prepared by the Ministry of Power
likely to be placed before the cabinet commiee for
approval. Shri Pandey highlighted sector-wise
installed capacity & energy mix, state-wise demand
and supply of power, analysis of reasons for declining
share of hydropower, relevance and cricality for
Hydropower Development in the country parcularly
in context of water management, water security, grid
stability, peaking power requirement. He also
presented comparave analysis of Hydropower
vis-à-vis other sources of Power – Thermal/ Nuclear/
Solar/ Wind in terms of project life, cost of generaon,
operaon and maintenance cost, land area
requirement, environmental costs, its impact on social
economic and infrastructure development. Shri
Pandey shared State-wise and basin-wise status
and the Projected Gap in Hydropower by 2030,
comparave analysis of policies of various State
Governments. He highlighted regional issues and
techno economic issues including increasing tariff, cost
over-runs, lack of long term low interest bearing
financing instruments, contractual and geological
surprises. Shri Pandey shared his insights about
exisng Policy Provisions - Naonal Electricity Policy,
2005, Hydropower Policy, 2008, Tariff Policy, 2016 and
Right to Fair Compensaon and Transparency in Land
Acquision and Rehabilitaon, 2013.
Shri Pandey informed that the Government of India is
working on several proposals to address industry
needs e.g fair and transparent policy for allocaon of
projects with local communies having higher share
(L-R : Shri K.M. Singh CMD NHPC Ltd. Shri B.P. Pandey IAS, Addl Secretary to Govt of India Ministry of Power and Shri naveen Jindal CMD JSPL
![Page 9: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/9.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 2016 7 PageI
CONFERENCE REPORT
out of the free power given to the states, viability gap
funding for hydropower projects, guidelines for
handling geological surprises and natural calamies
and risk-sharing mechanism and preferenal
treatment for environment and forest clearances
for hydropower projects and beer contract
management pracces.
Smt Shakuntala D. Gamlin IAS Chief Secretary to the
Govt of Arunachal in her address said that India has
limited fossil fuel reserves. With volale internaonal
energy prices and heightened concerns over carbon
emissions there is an increasing focus on developing a
cleaner and greener energy basket. In a naon
endowed with huge natural resources for hydropower
generaon, development of Hydroelectric power is a
natural choice. The world is coping with the problems
caused by a hydrocarbon-fuelled economic growth.
Hydropower remains one prime source of generang
carbon-free electricity. While sharing Arunachal's
percentage share in energy mix share, Smt Gamlin said
that out of a total 1.5 lakh MW hydro power potenal in
the country, half of the two-third untapped potenal
(i.e 1.0 lakh MW) in the country, lies in the state of
Arunachal Pradesh. There have been delays in
obtaining statutory clearances - environmental and
forest in the case of hydroelectric projects, especially in
the case of those that are envisaged with a reservoir for
water storage. These clearances are ed to the
Cumulave Impact and Carrying Capacity Studies for
the enre river basin (prescribed by the Union Ministry
of Environment & Forests). Apart from the above,
MOAs, DPRs and spulaons of a higher environment-
flow, which is a minimum of 20 per cent, and for
maintenance of a free flow to keep a distance of 1 km
between two projects, have rendered many projects
commercially unviable. This is because expected tariff
in many of these project tends to be not more than
Rs.5/- per unit (kWh). Consequently investors have
been unable to sign long term PPAs and obtain financial
closures for their projects.
Smt Gamlin said that the logical chain of events must be
corrected through a mid-course correcon. We also
need to look at spulaons in a more realisc and
pragmac manner. We have been taking up these
issues with the concerned Union Ministry and are
hopeful that genuine issues will be addressed in a
me-bound manner. With Chief Minister who is a
visionary and pragmac personality with progressive
outlook and proacve approach, Arunachal
Government is commied towards addressing
industry concerns and providing faci l itang
env i ronment for speedy deve lopment and
commissioning of Hydroprojects in the State. The
Hydropower tariff is though slightly on higher side viz a
viz other renewable, but, hydropower's inherent
advantages, of peeking load factor of 50% as against
16%-20% for wind and solar, its much longer project
life, water sustainability and security and praccally
carbon free power generaon capacity for
environmental conservaon, need to be recognised.
The purchaser of power should take into account that
the PPA signed now, will be applicable for purchase of
power aer 10 years, and the current tariff by then,
may be the most compeve price then. There is a
great need to view hydropower in a correct
perspecve and its importance in comparison to any
other power source needs to be appreciated. Local
agitaon is jusfied but there is need to create an
awareness about the benefits that locals would derive
from development of hydropower projects viz safety
from flash floods, water security which is the basis of
humanity and life, provision of infrastructure like
roads, housing, medical and educaonal facilies and
an addional revenue stream arising from businesses
like fisheries, tourism etc. Globally, it is seen that
hydroelectric power is the basis of the energy security
in developed countries like US, Canada and Norway.
Shri K M Singh ,CMD, NHPC in his address said that it
is necessary to spread awareness about the need to
develop the hydro potenal of our country in a
sustainable manner from the viewpoint of three
important pillars namely economic, social and
environmental. India is the world's third largest
![Page 10: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/10.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 20168 PageI
CONFERENCE REPORT
economy as well as the third largest energy consumer.
Considering the pace of development and rising
populaon, energy consumpon will further increase
over the next coming years. Needless to say that there
is an immediate need to give aenon to Energy
Security of the country. Presently Indian power sector
is dominated by thermal plants, which contribute
about 70% of the capacity, followed by 15 % from
hydro, about 13 % from other renewable sources and
2% from nuclear power. Thus the share of hydro has
fallen drascally from the level of 40% during late
sevenes to that of 15% today. It is also a known fact
that, India had been relying on fossil fuel for adding to
generang capacity. However, with the fast
diminishing coal deposits and the concerns of climate
change due to global warming, there is an urgent need
to look for other renewable sources. There has been a
recent thrust in renewables like Solar and Wind, but
hydro seems to require more aenon of our planners
and developers. This is probably due to the fact that
Wind and solar can be commissioned faster whereas
hydro, as you all know takes much longer me.
Shri Singh asserted that Hydropower clearly has an
edge over other sources of power generaon. It is
environmentally benign and non-pollung source of
power and has negligible greenhouse gas emission
compared to other convenonal modes of power
generaon. Thermal (on Coal) has 957 GHG emission
per kWh in Gram Equivalent CO2, Thermal (on Gas) has
this figure 422 whereas GHG emission by Hydro
(RoR) comes out to 4, significantly smaller than
corresponding emission factors from thermal power
plants alternaves. Further, Hydro projects have
relavely longer useful plant life, help in providing
inexpensive power in long term and is ideal for meeng
peaking load and as a spinning reserve. Besides this, it
also helps in remote area development, flood
moderaon, irrigaon, navigaon and drinking water
requirement and increasing agriculture producvity
besides creang other streams of revenue including
tourism. Mulpurpose storage projects can address
the concern of water security also. India has a
substanal hydropower potenal of about 1,48,000
MW. Of this, only about 26% has been harnessed so far.
Thus there is a considerable scope for development of
hydro power in our country. Of late, the concern
expressed by civil society about the adverse impacts of
Dams, has opened the doors for civil agitaons and
ligaons, opposing construcon of dams/ hydro
projects
NHPC is contribung about 15% of the total
hydropower developed in India. Though absolute
figure of installed capacity which aggregates 6587 MW
including NHPCs JV capacity, may not be impressive,
but it is true indicave of the fact that hydro projects
are not easy to implement. Even with such long
experience and technical knowledge in Hydro power,
NHPC is sll facing problems/constraints in developing
hydro power projects. Pre-construcon clearances
take abnormally long me which adds significantly to
the project cost. During project implementaon the
major problems which come up are geological
surprises during construcon intermient stoppage of
works by local public/PAFs and consequenal
contractual issues. NHPC has tried to migate the
contractual issues by expedious decision making to
resolve issues relang to changes, cash flow, delay
impacts etc. Technical challenges are being overcome
by adopon of latest technologies from world over. To
address the concerns of loss of livelihood of project
affected families, NHPC has taken iniaves like
providing employment to the extent possible and
monthly subsistence allowance for periods varying up
to 35 years to provide connual income. Private sector
has approx. 37% share of installed capacity in thermal
while in Hydro only 7% of the installed capacity. Shri
Singh said that the development of hydro power
projects in India needs to be encouraged.
Mr. Naveen Jindal CMD JSPL Group in his address said
that the conference is the right plaorm for re-vising
the drawbacks in the growth of hydro power and take
correcve measures to develop the vast potenal of
hydropower available in the country. Every second
![Page 11: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/11.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 2016 9 PageI
CONFERENCE REPORT
millions of cubic meters of water is wastefully flowing
down into the sea. Considering the GDP growth of India
as 7-8% in coming years, it is essenal to have
sustainable power development which will also cater
to the need of water in the drought prone areas of
India.
He said Countries like Norway, Paraguay, Brazil, Canada
produce 90% of electricity by Hydropower. The share of
Hydropower and Pumped storage around the world is
led by China (320 GW), USA (102 GW), Brazil (91 GW),
Canada (78 GW), Russia & India stands with 43 GW
each. Per capita consumpon of electricity in Canada is
15,687 kWh and USA is 12,947 kWh. However, in India,
per capita consumpon of electricity is 1010 kWh,
which is much lower compared to other naons. The
installed capacity of Hydropower in India as on 31st
March' 2016 is 42,783 MW, which indicates that 70% of
hydro potenal is sll unulized. India is having about
1,00,000 MW of untapped hydropower potenal,
which is technically feasible, economically viable,
socially equitable & environmentally sustainable.
Majority of this unulized potenal is in the State of
Arunachal Pradesh and for its development; the
support of the Government is urgently and essenally
required. Thousands of household in our villages in
India are sll un-electrified or parally electrified.
Promoon and development of hydropower is the
need of the hour to curb carbon emissions as envisaged
in the recently concluded COP21, Paris. Almost 90% of
the Hydro Power Potenal is already alloed to various
developers. Developers have also invested huge
amount of money for the invesgaon and clearances
for these projects. It normally takes 3-4 years to
prepare a detailed project report (DPR) for Hydro
project and stascs show 25,678 MW of potenal is
already concurred by CEA which is yet to be taken up
for construcon. This amounts to 17.67% of total
installed capacity. Reluctance of DISCOMS to sign PPAs,
Delay in Environmental & Forest Clearances, Lack of
Infrastructure, Policy issues has slowed down the pace
of hydropower projects.
Shri Jindal said that there is a serious need to address
the issues in the Hydropower sector and some
conceptual changes are urgently needed in the
Hydropower Policy. He highlighted key issues and
suggested some policy changes for expedious hydro
power development in the country.
Govt. of India should play a pivotal role to stress
upon the DISCOMs for signing PPAs with Hydro
Power Developers. Addionally for North East
states, beneficiary quota of power from each
Hydro project should be fixed so that PPA can be
signed with NE states on CERC norms.
The financing policies for hydro projects need to
be revised with a view to provide longer tenure
debt to hydro sector (say 25-30 years).
The Banks should be advised to earmark at least
40% of the total lending to power sector dedicated
only for hydropower projects.
The condional concurrence (for E Flows) of
Environment & Forest Ministry may be granted so
that developer should carry on further acvies of
the project without waing for Basin studies final
recommendaons.
GoI in consultaon with State Govt.(s) should
formulate a me bound process of land
acquision which should be monitored regularly
on target vs achievement basis.
Law & order i ssues should be handled
expediously at each project.
The Government should declare all Hydropower
Projects, regardless of the capacity, under
“Renewables” category.
There should be separate Hydropower Purchase
Obligaon (HPO).
Agencies implemenng the road sector projects
need to be provided adequate support to
complete the projects expediously.
Naonal Clean Energy Fund (NCEF) (Coal cess)
should be used for development of hydro projects.
State Govt. / Central Govt. should organize Public
Awareness Programs emphasizing Hydro Power as
safe and sustainable for green development, so
that people become aware of seismic & safety
aspects which are taken care during the design of
the Dam and how it safe guards the people of the
Downstream.
![Page 12: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/12.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 201610 PageI
CONFERENCE REPORT
Shri Sujit Ghosh, Partner and Legal Head Advaita Legal
said that Hydropower Projects are highly capital
intensive on account of civil works and cost of electro-
mechanical equipments like turbines and generators.
Taxes on equipment and input services used for seng
up projects, building and other construcon workers
cess (BoCW), water royalty payable to State
government and levy of excise duty further, adds to
project cost. Several tax exempons accorded in the
past have been withdrawn recently. These include
Customs and Excise duty exempon for non listed and
future hydro projects, deemed exports for mega hydro
projects, blanket non-levy of service tax on
construcon of dams, bridges and tunnels. The 80IA
benefit is also limited unl 2017. Mr. Ghosh
recommended tax exempon on capital goods used for
seng up and operaon of hydropower projects be
granted. Service tax exempon should be used for and
in relaon to Hydro Power Projects, Exempon from
VAT, Entry Tax and Electricity Duty by the State
Government for goods used in Hydro Power Projects
should be granted. Government may consider zero
rang for electricity under the GST regime .
Shri Sandeep Jajodia Sr Vice President ASSOCHAM
and CMD Monnet Ispat & Energy Ltd. presided over
the Inaugural Session. In his welcome address he
highlighted several challenged that need to be
addressed namely inter-state disputes that hinder
integrated river basin development for hydroprojects.
Land availability and acquision cause delays in
construcon and rehabilitaon of project affected
people. Delays and non-clearance on environmental
and forest aspects result in cost over-runs.
Hydropower development needs long tenure debt
availability for say 20 or even more, which is limited in
the Indian markets. Techno economic viability of
hydroelectr ic projects depends on geology,
topography, hydrology and accessibility to project
area. Most of the hydropower projects are located in
remote sites and require development of enabling
infrastructure for power evacuaon. The plant load
factor for Hydropower projects is typically less than
50% and as a result significant transmission capacity is
underulized.
S h r i J a j o d i a h i g h l i g hte d s o m e o f t h e key
recommendaons. He suggested that for effecve
planning of river basin development, Govt of India
needs to ensure that inter-state agreements for water,
are in place. Benefit–sharing is a commitment by the
government and the developer to share monetary and
non-monetary returns with stakeholders. Appropriate
benefit-sharing mechanism can ensure social stability.
Involvement of project affected persons in joint
consultaon between developer, government could
help smoothen out differences and get legal and social
consent. Opmal balance should be sought in respect
of revenue sharing, local development funds,
ownership structure, taxaon levels and preferenal
electricity rates. The Land acquision procedure for
Hydro projects should be in line with the one
applicable for road projects of Naonal importance as
per NHAI Act. Present Act 2013 is too, cumbersome
and the me schedule makes the projects tariff
unviable. Specific melines toward all statutory and
non-statutory clearances to a project, at both center
and state level, need to be fixed. Building pooling sub-
staons in locaons having large concentraon of
hydro resources is an efficient opon which help
developers reduce the project cost on account of last
mile connecvity. Establishment of Green energy
corridors for evacuaon of renewable energy projects
to be given priority. We also need to look at technical
Mr. Sujit Ghosh, Partner and Naonal Taxaon Head, Advaita Legal addressing tax perspecve at the Inaugural Session
![Page 13: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/13.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 2016 11 PageI
CONFERENCE REPORT
capacity development. An upstream storage facility in
each river basin can, by regulang overall flow, will
reduce silt loads downstream as well as lead to greater
energy output.
Unl 2011, Hydropower industry enjoyed favourable
tax regime. Thereaer, some benefits like duty
drawback were withdrawn. Service tax was imposed in
addion to water, power and green energy cess
rendering it unviable. Favourable tax treatment,
especially at early stages of projects, reduces project
costs and helps them to secure cheaper financing.
Cascading taxes lead to higher tariffs Government may
offer tax credits (as in the US) or tax holidays (as in Laos)
to facilitate investment. Government may consider
innovave financial products like tax –exempt bonds
focused on hydropower sector, channelize long term
funding (from pension funds, banks) to this sector.
Government may create special hydropower financing
schemes eg. accelerated generaon and supply
programme to state ulies, providing loans to power
ulies at a reduced rate of interests. The Government
needs to consider making it mandatory for power
distribuon ulies to purchase a fixed amount of
hydropower. Tariff comparison should be based on the
quality of energy supplied, reflected by the posion
hydropower occupies in load duraon curve. Time of
the day tariff concept should be introduced to
purchase peak power from hydro projects at higher
rates than base load power. Provision for Viability Gap
funding could be a soluon to hydro power
development. For new projects, Government may
consider floang tenders for say 1000 MW Case 2
Hydro projects and allot project to developer with
lowest VGF proposal. Government can also idenfy
sites and ask developers to bid for lowest Viability Gap
Funding. Government may ulize the Clean Energy
Fund for the purpose. State Government is to be
provided 12% of free power as royalty from any Hydro
Power Project to be developed in the State. This
allocaon to State increases to 15%, 18% and even 30%
over the life of the Project. Recently for a large Hydro
Power Project (1000 MW) in a Northern State, 12%
free power was been waived off by the State
Government apart from providing exempon from
WCT/ Entry Tax. This model could be replicated by
other state Governments as well.
He voiced industry's earnest request to consider all
hydro projects regardless of capacity be treated as
'renewables' and extended all benefits as applicable
for renewable projects. The Government has though
emphasized upon 5 mes installed solar capacity, it is
not sustainable proposion without being balanced by
hydropower. Hydro consideraon should be integral
part of solar and wind energy development. Hydro's
crical role in energy security for the country is based
on the elements of sustainability, availability and
affordability.
Shri Shrirang Karandikar, Chairman ASSOCHAM's
Naonal Council on Power and CEO India Power
Corporaon Ltd. proposed the Vote of Thanks to
conclude Inaugural Session of the Conference.
Shri Sandeep Jajodia Sr. Vice President ASSOCHAM and Shri D.S.Rawat Secretary General ASSOCHAM felicitang Shri T. N. Thongdok, Hon’ble Miniser for Power and Non-Convenonal energy, Government of Arunachal with a memento
![Page 14: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/14.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 201612 PageI
CONFERENCE REPORT
Session 1
Hydropower Development Delusions and Advanced Technologies
(Shri A.B. Pandya, Former Chairman Central Water Commission and Session Chairman addressing Delusions and Advanced Technology for Hydropower Development
The Session was chaired by Shri A.B. Pandya, Former
Chairman Central Water Commissions and Shri Sash
Sharma V.P. Engg Management HCC Ltd.
Shri D.P. Bhargava, Former Director Tech NHPC while
addressing Environment Safety and Siesmic Issues of
Downstream People in A.H.E. Projects recommended
that if projects are built and operated by different
agencies, River Basin Reservoir Regulaon Authority
should be established for co-ordinated operaons. He
also recommended that some poron of free power
royalty should be given to immediate Downstream
State, if no other tangible benefits like irrigaon are
happening to it. He suggested that 2% of project cost
should be provisioned for hydropower development.
Shri P.K. Gupta General Manager (Geo-Tech NHPC
Ltd.) while sharing his perspecve on the subject said
downstream people are disillusioned on various
aspects. Their belief is that hydropower project
development leads to drying of rivers, consequent loss
of biodiversity and sedimentaon and prospects of
flash floods. On the contrary, hydropower projects lead
to sustained adequate supply of water flow in river
L to Right.Shri Maninder Singh, Director ICL. Shri K. K. Sigh, Reg Exec ve Director NTPC Ltd.Shri Rohit Uberoi, VP and Head of Design and Engg Voith. Shri P. K. Gupta, General manager NHPC Ltd.Shri A.B. Pandya, Session Chairman and Former Chairman CWC. Shri S sh Sharma, VP Engg HindustanConstru on Company Ltd. Shi Milon Mukhopadhyaya, Managing Director Normet India Ltd.Shri D. P. Bhargava, Former Director Technical, NHPC Ltd. Shri D. A. Karandikar, Head Co ng Plant AndritzIndia Pvt Ltd. and Shri D. P. Goyal, Director Jayprakash Power ventures
![Page 15: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/15.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 2016 13 PageI
CONFERENCE REPORT
streams even in lean periods. It provides water security
in the downstream area. It helps preservaon of
biodiversity and other sources of livelihood for the
local community through co-operaves e.g. Bhakra/
Indra Sagar/ Omkareshwar Dams. It helps provide
conducive habitat for aracng migratory birds in the
area creang addional tourism potenal. It also
preserve soil ferlity as sediments are flushed out for
opmal generaon power. Dams in upstream (like
Arunachal) also reduce fury of floods in downstream
areas of Assam. Tehri Dam was a boon for Rishikesh
and Haridwar region during Alakhnanda floods. Till
date no damage has occurred in any of the mega
Hydropower Project Dam structures due to floods or
earthquakes. The Dams are designed to absorb Siesmic
forces under extreme condions. The Hydropower
Projects cause posive social-environmental benefits
in the downstream. Bhakra is a classical example for
posive revoluon in the downstream in terms of
irrigaon, quality power supply and sustained water
security, flood migaon and business opportunies.
The downstream people are the actual beneficiaries
from Hydro Projects. He recommended that instead of
several Run on River projects, large storage projects
are the need of the country to foster water security,
flood control, added benefits of fisheries and tourism
e.g. Tehri, Hirakund, Sardar Sarovar, Nagarjuna Sagar.
Shri D.P. Goyal Director Jaypee Power Ventures Ltd. in
his address on Longitudinal flow in High dams said that
Flow of water, sediments and other natural Resources
should be connuous and adequate over enre length
of river throughout the year for sustenance of rare and
endangered species in water. Reducon in natural flow
can affect anthropocentric value of a river including its
social, economic, cultural, aesthec and recreaonal
values. ROR projects lead to fragmentaon of river
length affecng riverine biota and diversity. Release of
EF from a dam/barrage with power house located at a
distance will result in loss of power generaon.
Shri Rohit Uberoi VP and Head of Design and Engg,
Voith Hydro Pvt Ltd. in his address said that
Hydropower Energy is clean renewable Source of
Energy which is sustainable, Renewable, Clean,
Reliable and Efficient. There is need to look beyond
convenonal potenal through distributed generaon
closer to consumers. This model has inherent
advantages of direct supply to local consumers/
connecon to local grid. It provides impetus to rural
electrificaon in hilly regions and access to electricity
where grid is not extended, reducon of transmission
costs and intangible benefits of inclusive growth. He
suggested integraon of new technology with
irrigaon schemes, industries and convenonal fossil
fired powerhouses.
Mr. Milon Mukhopadhyay, Managing Director,
Normet India Pvt Ltd. addressed issues of cost
opmised construcon of tunnels in Hydro Power. He
said that hydropower tunnels are built in Himalayas
with a designed service life of over 50 years. Himalayan
Geology is very young and many terrains have weak
rock mass, clay, water bearing strata which creates
major challenges during excavaon in Tunnel. It
demands use of advance technology, to ensure safe &
cost opmised construcon. It involves preliminary
support installaon by WET shotcreng, rock bolng ,
groung etc. Rock support by quality sprayed concrete
in Tunnel construcon is most important as it ensures
preliminary support to overburden mass along with
Rock bolt and ensure safety for the workmen, helps
further progress of excavaon. Sprayed concrete was
invented in 1907, and is widely used ll today for rock
support world wide, both in mining and tunneling. Use
of such spraying equipment along with Alakali Free
accelerator, HRWRA, Hydraon Control agent etc. ,
construcon chemicals (as per EFNARC Standard) has
now made possible to produce and sprayed a durable
shotcrete in Tunnel which ensures early strength
development @1Mpa at one hour which is the basic
aim for preliminary support to overburden .
Mr. Mukhopadhyay said that errors in tunnelling come
from people. The main causes aributed to lack of
knowledge & preparedness for the geological
![Page 16: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/16.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 201614 PageI
CONFERENCE REPORT
Mr. K.K. Singh Regional ED Hydro NTPC Ltd. said that
less share of hydro in the Indian energy basket not only
adversely affects the efficiency of the power system
and plant life but also necessitate burning of huge
amount of valuable natural resources. With
commitment of 24x7 power to all by 2019, it becomes
essenal to ensure quality power with proper grid
management. Although Renewable energy is demand
of the me but have certain limitaons about reliability
of supply, low CUF/PLF, unscheduled power cuts, grid
stability, energy storage. To migate this aspect, hydro
power plants have advantages of flexible operaon,
built in energy storage, low stress on the plant with
short run up me, capable to handle part loading &
voltage fluctuaon, are ideally suitable for balancing of
renewables. Besides these, if water is regulated
through storage and pumped storage hydropower
schemes, it can assist in migang climate change,
providing freshwater for irrigaon, domesc/
industrial water supply, drought management and
flood protecon soluons, ground water recharge, etc.
If not controlled or regulated, clean/potable water
will end up into Ocean/Sea without fruiul use.
For BALANCING OF RENEWABLES, we have to re-
emphasise on development of HYDRO POWER.
Shri Maninder Singh, Director Internaonal Coil Ltd.
addressed innovave Technology for Hydropower
Development.
![Page 17: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/17.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 2016 15 PageI
CONFERENCE REPORT
Session 2 :
Policy and Governance Framework and Risk Migaon
The Session was chaired by Shri S.D. Dubey Chairman
CEA, and Co-Chaired by Shri M.M. Madan CEO (Hydro
and Renewables) Jindal Power along with Shri A.B.
Giri Member Board Internaonal Hydropower
Associaon.
Shri Asim Thakurta, Chief Corporate Projects, Tata
Power and Chairman Dugar Hydropower Ltd.
addressed Policy change related to role of State in land
acquision, infra development and clearances. He said
that land acquision and R&R of Project Affected
People (PAP) remains one of the most crical aspect for
large storage hydro projects. To address opposion to
these projects, the opon of equity in exchange of land
(with a cap of say 2% of total equity); can be promoted
which guarantees long lasng returns (in the form of
dividends) and aligns interests of communies
towards success of the project. Cost of infrastructure
like roads and bridges for the enre valley shall not be
loaded to the first project; rather State Govt. should
first bear the expenditure, and then share it with all the
projects ulizing the facility. The state should pursue a
mechanism to securize/ offset and pool the free
Le - Right Shri Vibhash Pathania, THDC, Shri Rahul Varshney, Director, Buss Dev. Statkra Ltd. Shri Gyan Bhadra, Head Hydro JSW Energy, Shri K. C. Dhimole, Tech Advisor to CM Arunachal, Shri A.B. Giri, Member Board Internaonal Hydropower Associaon. Shri Anand Behari Agrawal, Execuve Director (HR), NHPC and Former Chairman Bhakra Beas Management Board, Shri Kapil Mantri, Hear Corporate Strategy, JSPL, Shri Asim Thakurta, Chief , Corporate Projects, Tata Power and Chairman, Dugar Hydropower Ltd. and Shi Kaushlendra Tripathi ,Director, Energy advisory, PWC
(Shri S.D. Dubey Chairman Central Electricity Authority addressing the parcipants Policyand Governance Framework for Hydropower Development.)
![Page 18: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/18.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 201616 PageI
CONFERENCE REPORT
power revenues from mulple projects (which will
only begin once the project is developed) for
investment in the inial infrastructure. Absence of
transmission facilies creates uncertaines, delaying
the financial closure. PGCIL should proacvely
undertake corridor planning and implementaon. In
order to opmize clearances and sancons, a Hydro
Power Commission at the naonal level could be
considered as a Nodal Agency to cover issues required
for various clearances. Central Electricity Authority,
Central Water Commission, Environment Ministry,
State Government, Ministry of Power, Ministry of
Water Resources, could be nominated on this
Commission. Financial Structuring to reduce the
weighted average cost of capital for compeve tariff,
it is suggested that Debt: Equity be kept flexible say at
80:20 with mandatory incurrence of equity poron
minimum of 50% before any disbursement. Also the
repayment can be structured in a way to spread the
repayment period over a longer duraon as the life of a
hydro project is much more than that of a convenonal
generaon project. Government needs to consider
making available funds for longer tenor and lower
interest rates such as Pension Funds, Tax Free Bonds
etc. with adequate safeguards. Supply of free power
can be deferred as in the inial years the project faces
maximum repayment strains and should be rather
aer the loan has been disbursed. Numerous
“advalorem” charges (like LADF, CAT, Entry Tax, Labour
Cess etc.) shall be reviewed to lower the project cost.
Typically taxes make up to 11-12% of the total project
cost ignoring the compounded IDC. There is a need to
relook at these charges. Secon 80I (A) of the Income
Tax Act, 1956 provides for Tax Holiday on the income
generated from Power Projects. However, such holiday
is available only if the project gets commissioned in the
specified period. Tax Holiday under Secon 80I(A) of
the Income Tax Act, 1956, should be made applicable
for 10 years for all Hydropower Projects including
under implementaon projects. Granng Mega status
to all HEPs over 300 MW capacity having water storage
of above 6 hours of operaon and considering Excise
Duty exempon on Steel and Cement. Regulaon of
tariff under the Secon 62 of the Electricity Act 2003,
(which has now been extended ll Mar 2022 as per
recently released Naonal Tariff Policy) would help
breathe fresh life into hydro projects, provided State
Discoms have obligaon to buy some quantum
specified as percentage of Hydro Power. Defining a
Hydro Purchase Obligaon similar to Renewable
Purchase Obligaon (RPO) will ensure states plan
procurement of Hydro power also giving certainty of
revenues to projects thereby helping reduce risk
premiums on loans. Determining an appropriate
Return on Equity - higher than current levels of 15.5%-
17% commensurate with the risks is necessary to
aract quality developers. It has been established that
while the average gestaon period for a typical
thermal power project is about 36 to 40 months, the
same for hydro projects varies between 60 to 80
months. For hydro projects, there is a strong case that
return on equity should be suitably enhanced to
capture the relavely longer gestaon periods for
compleon of projects and also adequately reward
developers for early compleon. Infrastructure, access
to schools and hospitals, prevenon of damage due to
flood. Idenficaon of project affected communies
and they should be adequately compensated to make
up for the loss of livelihood, land and houses and
inclusion of affected people in project life. Provision of
free electricity, water and health services to the
affected people could help in sustainable development
of hydropower plants across the naon.
Shri Kapil Mantri Head – Corporate Strategy and
Business Development Jindal Steel and power Ltd.
addressed the policy imperaves. He said that country
needs peaking power. The issues that need to be
addressed include high cost and development period,
geological risks, infrastructure and connecvity
concerns in remote locaons and difficult terrains,
land acquision problems, environment & forest
clearance, power evacuaon challenges, opposion by
NGOs and difficulty in achieving financial closure. He
said introducon and reorientaon of certain
policies is a must to ensure revival of hydropower
![Page 19: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/19.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 2016 17 PageI
CONFERENCE REPORT
development. He recommended ten point agenda :
• Power Off Take & Hydropower Purchase
Obligaons: DISCOMS are reluctant to enter into
PPA because of higher tariff in inial years as
compared to other power sources like thermal.
Financial Instuons not willing to finance the
hydropower projects. HPO is the only soluon to
this issue.
• Hydropower is Renewable. Hydropower Projects
irrespecve of the capacity – parcularly all Run of
the River Projects should be declared as
Renewable to bring the projects under the net of
Government subsidy and other Tax benefits
• Taxaon at par with Solar – Mega Power Benefits
should be extended to construcon materials like
Cement, Steel and E&M equipment, as they are
major contributors to the project cost of Hydro
Projects. It is recommended to waive off / reduce
Advalorem Charges/Tax (LADF, Entry Tax, Labour
Cess etc). Secon 80I (A) of the Income Tax Act,
1956, provide Tax holiday on the income
generated from Power Projects . Tax Holiday
should be made applicable for 15 years for all
H yd ro Po we r P ro j e c t s i n c l u d i n g u n d e r
implementaon projects.
• Higher Risk, Longer Gestaon period deserves
higher Return on Equity. Longer gestaon hydro
projects suffer from a lower return since no return
on equity is allowed during construcon period
compared to relavely shorter gestaon thermal
projects. Need to evaluate construcon period
linked returns to bring all projects at par for
ret u r n s . To co m m e n s u rate t h e r i s ks &
uncertaines, current level of RoE 16.50% needs
to be made higher.
• Financial Support. Loan repayment period should
be spread over a longer duraon s ince
hydropower projects have longer life than other
type of power projects. Exempon of Tax for
interest income of FIs should be granted. Benefits
u/s 10(23)g of IT Act, 1961 to Hydro Power
Projects, which allowed for the exempon of tax
on the interest income earned by the FIs from
Infrastructure projects, were withdrawn and is not
available now with respect to infrastructure
projects. Restoraon of such benefits to Hydro
Power Projects would enable Indian FIs to provide
funds to Hydro Projects at lower interest rate,
leading to lower cost of generaon.
• Environment Flow requirement should be
determined based on project specific study and
should not be imposed arbitrarily. Dra River
Basin Study reports which are underway in various
basins should be shared with concerned project
developers before finalizaon. In case, change is
required in project features due to the
recommendaon of river basin study, CEA/CWC
should review only relevant chapters of the DPR &
accord concurrence expediously. Further,
MoEF&CC on its part may be advised to issue
corrigendum to already granted clearance
specifying the revised parameters (as they tend to
reduce the impact on environment) and not direct
developer to revise the EIA/EMP report etc and file
applicaon for re-consideraon of Expert
Appraisal Commiee (EAC) of MoEF & CC.
Compensaon of Flood Moderaon Cost Some
hydropower projects having provision of flood
moderaon have been alloed to private sector.
As per CERC regulaons, the cost of flood
moderaon component cannot be passed
through the tariff. As such, either the enre cost of
flood moderaon component should be
reimbursed to the private developer by Govt. or
the project should be re-alloed to PSUs and the
expenditure incurred by the private developer
should be reimbursed if the developer opts to exit
the project
• Equity funding by State Govt in JV Projects. Many
hydropower projects are under development in JV
between Private Sector & State Sector. However, in
many cases, private partner needs to contribute
100% towards project expenses since State Govt
does not contribute its equity funding. Many JV
projects are delayed due to inability of State Govt
![Page 20: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/20.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 201618 PageI
CONFERENCE REPORT
in contribung equity funding required for
development of the project. In such projects, State
Govt. should forego its equity and exit JV
partnership.
• Naonal Clean Energy Fund (NCEF) (Coal cess) can
be used for development of Roads / Infrastructure
common for many hydro projects.
• Time of Day Meetering : Hydroelectric power is a
very important source for peaking power . ToD
should be implemented as proposed in Tariff
Policy 2016.
Mr.Rahul Varshney, Director Business Dev Statkra
India Pvt Ltd. said most common cause for projects
being stalled is difficult geological condions
combined with lack of experse. These may be on
account of Polical and Country Risks eg Increase of
Environment flow from 15% of lean season to 30% of
peak season flow, Introducon of 5% entry tax in
Himachal, dividend distribuon tax increased by 5%,
2.5% mandatory for CAT Plan, introducon of 1%
labour cess; 1.5% LADA, Indus water treaty – Pakistan
holds construcon of Baghliar Dam, significant
increase of cost of funding–RBI increased int. rate
4.25% to 8.5% (2010-12), average Inflaon rate from
2008 to 2013 around 10%, changes in land acquision
policy, policy changes like promong Solar & Wind
thereby discouraging other forms of generaon,
moving towards totally regulated market from
deregulaon or macro-economic parameters like GDP
projecons (CAGR), Fiscal deficit etc. Risk Migaon
would involve leadership and communicaon,
integraon of an-corrupon in the project cycle,
systemac approach to integrity due diligence of
partners, code of conduct & dilemma trainings, record
keeping and documentaon.
Mr. Vibhash Pathania, THDC while sharing his insignts
of Sharing Risks through Contract Document said that
But risk can be managed, minimized, shared,
transferred, or simply accepted. While in structural
engineering the properes of the construcon
materials such as steel and concrete are well known,
situaon is different in case of underground
construcon . The ground properes can vary in a large
range within same project and even within short
distances. Even with the best test methods the ground
properes will never been known at the same level as
the properes of concrete and steel. Therefore risks
are higher. During the inial phase i.e. the conceptual
stage or early design stage risk assessment is carried
out by the owner only. During tender and contract
negoaon owner sll have the primary responsible
party but he may have some inputs to the tender from
the contractors. The construcon risk policy may
indicate that emphasis should be placed on minimising
overall risk by reducing the likelihood of occurrence of
events with large consequences, e.g., with several
fatalies or of significant polical concern. This
requires communicaon of informaon about
idenfied hazards (nature & significance) to all pares
by some form of comprehensive risk register and
connuous monitoring, audit and review procedures.
Risk Management during Tendering and Contract
Negoaon include the specificaon of technical and
other requirements in the tender documents such that
the risks are managed in accordance with the risk
policy. Risks should be allocated to the party who has
the best means for controlling them. The qualitave
risk assessment carried out in the early design stages
should be reviewed and accordingly modificaons of
the tender documents be made. Definion of the
informaon requested from the tenderers in order to
Evaluate the tenderer's ability to manage risk and of
the differences in risk between the proposals made by
the different tenderers. Specificaon of requirements
in the tender document concerning the contractors
risk management acvies during execuon of the
contract. For Risk management during Construcon
The owner must connue to perform risk assessment
for risks that are the owners responsibility and are not
covered by the contractor. This could be contractual
risks, including contractual aspects of technical risks
idenfied by the contractor. Of primary concern are
risks related to economic loss to the owner, or delay.
Migaon acons should be idenfied and
![Page 21: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/21.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 2016 19 PageI
CONFERENCE REPORT
implemented by the owner, but some migaon
measures may be handed over to the contractor for
implementaon. The owner should encourage and
monitor the contractors risk management. The
owner, or the joint risk management team, is advised
to look out for pracces on site that are at variance
with the risk migaon measures that have been
agreed upon. Mr. Pathania recommended that Risk
register has to be specific to the project standard lists
and can be helpful as a checklist. Choose simple risk
classificaon methods. Risk management is a maer
of thinking. Risk management is a connuous process
(CRM) that starts at the earliest possible beginning of
the project. Contractors, designs engineers, site
supervision and experts shall (according to the project
phase) be involved in the CRM-Process.
Mr. Kaushlendra Tripathy, Director Energy Advisory,
PWC while addressing Financial Risks in Hydropower
Development and Key Migaon Measures suggested
that in India hydropower potenal of 148 GW, able to
meet demand of 85 GW at 60% load factor however,
only accounts for 15% share in India's energy mix
owing to Higher dependency on thermal generaon.
Only 41 GW of hydropower capacity has been
installed, which is only 28% of the total potenal.
Canada and Brazil had harnessed around 69% and 48%
of the economically feasible potenal back in 2009.
Hydropower can play a crucial role in India's
sustainable development and energy security. He
recommended key enablers for facilitate Investments
and financing:
Encourage Tax Free bonds & Pension Funds for
financing of hydropower projects with long tenure
and relavely low coupon rates.
Creaon of dedicated Hydro Fund / special
hydropower financing scheme.
Explore mul-lateral and green funds.
Streamlining clearances and land acquision.
Investment board/nodal agency to facilitate
private sector parcipaon in hydropower.
Fiscal Incenves: Extension of tax holiday and
exempon of import tariffs for projects with
higher capacity.
Provide Enabling Infrastructure: Devising proper
and coherent framework between central and
state agencies to sort out the impediments.
Ulizing finance from alternave sources - local
development fund, upfront premium , state
budget to the extent possible
Ownership structure: Project development model
considering who is best placed to develop –
government, private, joint
Standardised fiscal & revenue sharing policies for
selecon of technically and financially qualified
private developers
HPO: Enhance project viability by promong off-
take of electricity; enabler for higher revenue
Differenate tariffs for peak and off peak –
reimburse hydropower for contribuon to quality
of energy supplied, peak demand and grid
reliability
Develop market for Ancillary Services: Robust
commercial & regulatory mechanism to
incenvise hydro support for naonal grid (black
start, start up, reserve capacity etc.).
Power Purchase Agreement : Key features
During dry season the power will be supplied
during peak hours while throughout the day
supply during wet season
NEA obligated to purchase and off-take 100%
of the declared available energy within the
limits of agreed Contracted Energy Table
Purchase tariff to be determined through a
cost plus approach also allowing THL to earn a
reasonable return by efficiently operang the
project
Excess generaon declared over and above
the level of agreed Contracted Energy Table as
well as within the licensed and installed
capacity, to be sold at 50% of the applicable
tariff
![Page 22: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/22.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 201620 PageI
CONFERENCE REPORT
Knowledge Paper - Highlights
Hydropower can play a crucial role in India's
sustainable development and energy security given
that it meets the criteria of sustainability, availability,
reliability and affordability.
Regional Assessment of Hydropower development
shows that almost 75% of the total potenal for
hydropower development is concentrated in north
eastern region. However, only 34% of the total
potenal in the north eastern region has been
developed as on date. Exploitaon of the large hydro
potenal in the north-east region would contribute
significantly in meeng the country's peaking needs in
the future. The region would also benefit from the
development of associated infrastructure such as
roads, schools and electricity supply to remote areas,
which would further improve the quality of life.
Crical success factors would be:
Integrated River Basin Development and Project
Allocaon Procedure
The central government can constute an
authoritave body to improve river management,
address interstate water-sharing disputes and
conduct integrated river basin development. A
proper planning forum must be in place to bring all
the stakeholders together to reach a consensus on
the way forward.
A basin-wide study needs to be conducted under
the guidance of the Central Electricity Authority
(CEA)/Central Water Commission (CWC) to
understand the effect of one project on another
and to ensure efficient project allocaon in a river
basin. Moreover, the Ministry of Environment and
Forest (MoEF) is expected to conduct a basin-wise,
cumulave impact assessment study and idenfy
clear go/no-go areas to eliminate uncertainty.
The allocaon of hydropower sites must be done
keeping in mind the financial and technical
capacity and credibility of developers. Also, cost-
benefit analysis should be carried out with
different project allocaon models.
Power Evacuaon and Associated infrastructure
The Ministry of Power and the Ministry of Finance,
Highlights of the Knowledge Paper
![Page 23: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/23.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 2016 21 PageI
CONFERENCE REPORT
Government of India, may allocate funds for the
construcon of a dedicated transmission corridor
for hydropower (e.g. Green Energy Corridor) to
evacuate the hydropower generated from remote
areas.
The state governments should make provisions for
building pooling substaons in locaons having a
large concentraon of hydro resources to help
developers reduce the project cost on account of
last mile connecvity.
Other associated infrastructure needs to be
developed to facilitate project implementaon in
a cost-effecve manner. The development of such
associated infrastructure has spurred economic
acvies, and the state government must parally
bear the costs of development. The state
governments must effecvely channelise local
development funds, upfront premium, etc.,
received from developers to invest in such
associated infrastructure.
The integrated river basin plan, along with a
transmission system master plan, can help in the
opmum ulisaon of transmission infrastructure
and prohibit delays in commissioning of plants.
Fiscal Incenves
Adequate fiscal incenves in terms of Tax Holiday,
Value Added Tax (VAT) exempon, and exempon
of custom duty should be allowed by the
government to help in reducing the project cost
and securing a cheaper source of finance.
The lender consorum may also provide interest
rebates on long-term loans dur ing the
construcon and early years of operaon to help
developers in generang sufficient revenue for
meeng their repayment obligaons. Similarly, a
provision of higher depreciaon in the early years
of operaon can also be allowed for hydro
developers to serve their requirement of higher
upfront cost efficiently.
New Financing Avenues
Capital markets need to be deepened to help
provide long-term debt financing given the
capital-intensive nature and high gestaon
periods of hydropower projects. Iniaves such as
the seng up of the India Infrastructure Finance
Company Limited (IIFCL) for infrastructure lending
have been taken. The government of India also
needs to encourage suitable innovave products
(e .g . tax-exempt bonds focused on the
hydropower sector).
Viability Gap Funding (VGF) can also be a viable
proposal to make hydropower projects price
compeve. For new projects, the government
may consider floang tenders and allocang
projects to developers with the lowest VGF
proposal.
Considering the importance of hydropower in the
country's energy basket and its capital intensive
nature, hydropower projects need specialised and
dedicated funds to secure their long-term
financing. The Government of India may create a
special hydropower development fund or can use
the clean energy fund to provide loans to hydro
projects at a lower rate of interest.
Hydropower developers can also opt for
mullateral funding and financing from green
funds provided there is a viable business case and
an appropriate risk migaon plan.
Streamlining of land acquision process and other
approvals
The state government, in consultaon with the
central government, may develop appropriate
procedures to expedite various clearances, such
as those for the environment, forest and land. It
can also form a specialized instuon for
facilitang large infrastructure projects in terms of
clearances and approvals, thereby minimising the
me taken for these processes. In addion,
specific melines for all statutory and non-
statutory clearances for a project at both the
central and state levels need to be fixed, along
with accountability for delays.
The government on the other hand can also
complete all predevelopment acvies (e.g. land
![Page 24: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/24.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 201622 PageI
CONFERENCE REPORT
acquision) and statutory clearances (e.g.
environment and forest) for idenfied priority
projects which are in line with the procedure for
Ultra Mega Power Projects (UMPP) developed
through the Power Finance Corporaon (PFC)
before allocang them to developers.
The government should also provide all available
data for the land records in advance, which will
help the developer with project preparaon and
also facilitate the project financing process. In
addion, the government can form a lender
consorum to validate the available data of
different hydropower sites and review the
financial viability of a project at the detailed
project report (DPR) preparaon stage. This will
assist in beer preparaon of bankable DPRs to be
shared with financial instuons, as, once
prepared, it is very me-consuming to collect and
present raw data again to sasfy the financier.
Market Instruments:
With its strong regulatory oversight, CERC should
faci l itate market-based instruments l ike
hydropower purchase obligaons (HPOs), which
have an underlying principle of mandatory
purchase of hydropower by distribuon ulies.
Such HPOs provide assurance to developers by
guaranteeing the purchase of electricity and make
projects much more financially viable.
Tariff comparison needs to be done on the basis of
the quality of the energy supplied, reflected by the
posion hydropower occupies in the load
duraon curve. CERC needs to come up with a
differenated peak and off-peak tariff to
incenvize hydropower, given its potenal to
meet peak demand.
Hydropower plants are generally beer placed to
provide ancillary services to the grid and offer
beer system reliability. The implementaon of
the ancillary service market must be guided by an
efficient commercial mechanism based on an
enabling regulatory framework to encourage the
generaon of plants for maintaining grid
reliability. It will also help hydropower plants to
monese their capabilies to provide reacve
power compensaon, voltage stabilisaon, etc.,
given a plant's ability to ramp-up and ramp-down
in a very short me.
Benefit sharing framework
Hydropower dams oen help regulate river flows and
operate by storing volumes of floodwater and
controlling the ming of discharge. However, there is a
need to set storage rule curves to balance the
drawdown levels prior to the flood season, prevent or
minimise spill and maintain maximum hydraulic head
for hydro generaon for more effecve use of dams for
flood control. Other uses of hydropower dams, which
provides social and environmental benefits, include
Recreaon, Navigaon and Fish Breeding, Irrigaon,
Water Supply, Hydropower and Flood control.
The benefits of a hydropower development project
come at the cost of negave impacts on natural
resource developments. Hence, benefit-sharing
mechanisms and migaon measures play a key role in
addressing the social and environmental risks
associated with hydropower development. An
appropriate benefit sharing mechanism leads to social
stability and helps a country's naonal strategy to
meet various local needs.
Social and environmental impact assessments
need to be given due importance instead of
treang them as mere legal formalies.
Involvement of project affected persons (PAPs)
and joint consultaon processes between the
developer, government and PAPs need to be
carried out to eradicate differences and get legal
and social consent. Such involvement and joint
consultaon processes are necessary to address
immediate problems and legimise decisions.
As a part of economic and social development of
the area, developers need to be mandated to
open technical training centres, clinics and health
centres, schools, etc., in the project affected area.
This will help developers gain public acceptance
![Page 25: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/25.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 2016 23 PageI
CONFERENCE REPORT
and get skilled labour, while local residents get
employment opportunies.
A structured mechanism needs to be developed
for balancing benefits from hydropower projects
and transferring economic rents from projects to
the government, which should ulmately be
passed on to affected stakeholders.
Case Studies
1. Critical Role of Hydro energy in restoring system after power failure
Poland : The Polish Zarnowiec hydropower plant's contribution to system stabilityThe exible units of Zarnowiec, Poland's largest hydropower plant with 716 MW capacity, play an important role in ensuring stability in the national electricity system
· Flexibility to cope with the fast activation and disconnection of units, and covering a sudden power drop or increase in
the system· Control of reactive power ow in the system (voltage regulation and reactive power control)· Establishment of rotating reserve by means of second power controlling (primary control) and minute power controlling
(secondary control)
Zarnowiec therefore, played an important role in managing the European blackout of 4 November 2006. Activating pumps
helped to stabilise the frequency and voltage and restore the system after power failure.
2. Investment Facilitation: Fiscal Incentives
Brazil : Change of policy to facilitate private investment In the 1990s, Brazil moved to a free-market model by awarding
hydropower generation concessions on a highest rent basis. However, to encourage improved security of supply and attract
more private investment from 2004, hydro concessions began to be awarded based on the lowest tariff offered. Brazil has used this system even for some very large (>3,000 MW) sites. The Brazilian authority emphasised limiting risks substantially for developers in order to make this model attractive to them. Some of the key initiatives towards achieving this objective included pre-specifying projects in great detail, providing payment surety for developers and arranging finance from the
Brazilian Development Bank.
Philippines: The 345-MW San Roque Multipurpose Project in the Philippines was to be financed by public funds. However, it was eventually developed through the public private partnership (PPP) route with the 'split ownership model'. The dam was built at a cost of 610 million USD and was financed by the Government of Philippines using a bilateral soft loan and domestic
funds. On the other side, the power complex costing 580 million USD was financed on a 75:25 debt-equity ratio, with 52% of
the total cost derived from export credits and the rest of the debt as loans from the Japanese government and commercial
banks. The utility payment obligations were backed by sovereign guarantees. The construction was the responsibility of the private partner to mitigate conicts during the development stage. This model allowed burden sharing between the private and public sectors, and also allowed the Government of Philippines to operate the dam according to its irrigation
requirements.
3. Technical Capacity Augmentation
Democratic Republic of Congo: The Nseke Hydroelectric Power Plant, the Democratic Republic of the Congo, was
commissioned in the 1950s and has been operating at reduced capacities. The utility decided to rehabilitate four 65-MW
Francis turbines with challenges associated with its control system. A new control system, a supervisory control and data
acquisition (SCADA) product with a modern automation level, replaced the old system based on the electromechanical relays logic with control panels, thus improving plant control and performance monitoring with more real-time decision-making enablers.
Georgia: Flexibility, technical knowledge and expertise proved crucial in the successful implementation of the 53-MW
Mtkvari hydropower project in Georgia. Initially, the developers decided to adopt the conventional method and a 400-m tunnel was excavated. However, the low efficiency of the method prompted the decision makers to engage a 6-m diameter tunnel boring machine (TBM), which can excavate at a rate of 400 m/month.
![Page 26: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/26.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 201624 PageI
CONFERENCE REPORT
IMPORTANCE OF HYDROPOWER DEVELOPMENT
Need to Create Awareness amongst Masses to get Social Acceptance
Hydropower can play a crucial role in India's sustainable development and energy security given that it meets the
criteria of sustainability, availability, reliability and affordability. Hydropower has clear edge over other sources of
power generaon. If not controlled or regulated, clean/potable water will end up into Ocean/Sea without fruiul use.
Cleanest Source of Energy: It is environmentally benign and non-pollung source of power and has negligible
greenhouse gas emission compared to other convenonal modes of power generaon. Hydropower projects emit
169 gCO2 equivalent compared to the 2,010 gCO2 equivalent and 443 gCO2 equivalent released by coal-based and
gas based power plants respecvely.
Drought Management and Irrigaon: Hydropower projects preserve soil ferlity as sediment flow is regulated,
helps increase agricultural producvity and replenish ground water discharge.
Safety and Flood Control: Dams are designed to absorb seismic forces under extreme condion and are therefore
safe. It helps regulate river flows and operate by storing volumes of floodwater. Dams in upstream reduce fury of
floods in downstream areas e.g. importance of Tehri Hydro Power Plant that saved Haridwar and Rishikesh regions
post Alkhananda floods
Water Security: Hydropower projects maintain sustained adequate supply of water flow in river streams even in
lean periods for use by locals and for irrigaon purposes.
Black Start Capability: Hydropower plants have the ability to run at a zero load, which means it does not need any
outside source of power to start. This allows system operators to provide auxiliary power to other generaon
sources (e.g. Thermal) that could take hours or even days to start.
Quick-start capability, taking just a few minutes— compared to 30 minutes for other turbines, and hours for steam
generaon. Savings in start-up and shutdown costs of thermal plants and steadier operaons
Peak Saver Asset: The ability of hydropower plants to quickly change their output helps them to serve peak
demand. Hydropower peak load factor is @ 50% as against 16-20% in solar and wind energy.
Low Operang Costs: Hydropower plants have a low operang cost—almost half that of thermal power plants.
Long Economic Life: The plant life of hydropower projects is normally in the range of 40–50 years. In fact, their
operang life can be increased to 100 years through mely renovaon, which also helps in higher revenue
generaon for investors.
Reliable Grid Support: Given its large inera, hydropower provides transient stability to the grid. Ensures quality
Power Supply.
Voltage Support - ability to control reacve power, thereby ensuring that power will flow from generaon to load
Support for variable generaon of renewable energy (RE sources): The storage capabilies of many hydropower
plants make them a perfect instrument for opmising the use of variable RE sources over both shorter and longer
periods. Hydro power plants are ideally suitable for balancing of renewables.
Spinning Reserves: It helps preservaon of biodiversity and other sources of livelihood for the local community. It
helps provide conducive habitat for aracng migratory birds and fish breeding in the area, creang addional
tourism potenal.
![Page 27: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/27.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 2016 25 PageI
CONFERENCE REPORT
CONFERENCE RECOMEMNDATIONS
1. In order to aract Private Sector parcipaon in Creaon of an enabling Infrastructure Government should
consider Infrastructure Development Compensatory Allowance
The Government of India/ State Governments has limited resources to develop infrastructure. Since the
provision of an enabling infrastructure is imperave to achieve the plan growth target, private sector parcipaon
by way of investments could be invited for the development of infrastructure in economically viable projects.
Compensaon can be made to private sector or through tax breaks to the extent of investments/ financial outlay of
the projects or through tax exempon from future income streams emanang from the infrastructural projects
financed by them. Investments in such projects could be deemed as ‘Advance Payment of Taxes’ (implying a
deferred payment on part of the Government to Private investor).
This would encourage private sector to provide linkages from producon centers to ports, airports, highways,
irrigaon dams etc. through development of physical infrastructure. The facilies could be shared by other
companies as well, on payment of ulity charges. (e.g Commercial exploitaon of land adjacent to highways).
2. Land Acquision - People-Public-Private Partnership Model for investments
Infrastructure is one of the determining force behind the sustainability of India’s growth and compeveness – and
more important is the meliness of the infrastructure assets. The long gestaon periods add to high costs of creang
the infrastructure and reduce the overall socio-economic paybacks.
The Public-Private People Partnership model provides a symbioc mechanism for “Land Acquision” for infrastructure
development.
A ‘Company’ should be formed and registered priori for building and operang the said infrastructure.
The primary role of the government should be to acquire land at market prices for use by the company and
provide environmental clearance.
The ‘Company’ should pay for this land. However, to prevent any misuse, the ownership and control of this
land should vest with the Government.
In return of these services, the Government would be aided in terms of shares of the company. This would be
the public-sector holding in the company. Although a part of the ownership of the company rests with the
Government, the operaons should be professionalised.
In addion to the cost of the land acquired, the original land-owners should also be compensated in terms of
shares of the company. Will ensure jusfying long lasng returns to project affected people.
As is the pracce in any company, the share holders (both original land owner and the Government) should be
paid dividends.
There should be a me-bound land acquision system and an appellate authority should be created to ensure
just and effecve implementaon of land acquision within a spulated me-frame which will be legally
binding.
This mechanism would not only ensure fairness, but also gain for the project the acceptance of the local people and
local governing bodies, thus movang them to parcipate in the process of infrastructure projects and hydropower
projects. This strategy ensures two-fold source of revenue to the Government - direct tax (income and corporate)
received from the company and dividend on the shares.
Other provisions to address Local agitaon:
Create awareness amongst locals about derived benefits they would accrue from the development of
hydropower projects namely, safety from flash floods, water security, provision of infrastructure like roads,
housing, medical and educaonal facilies and an addional revenue stream arising from businesses like
fisheries, tourism etc.
![Page 28: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/28.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 201626 PageI
CONFERENCE REPORT
To address the concerns of loss of livelihood of project affected families, concrete steps need to be taken e.g.
Providing employment to the extent possible and monthly subsistence allowance for periods varying up to 35
years to provide connual income.
Opons of equity holding in exchange of land (with a cap of say 2% of total equity); can be promoted which
guarantees long lasng returns (in the form of dividends) and aligns interests of communies towards success
of the project.
Benefit–sharing is a commitment by the government and the developer to share monetary and non-monetary
returns with stakeholders. Appropriate benefit-sharing mechanism can ensure social stability. Involvement of
project affected persons in joint consultaon between developer, government could help smoothen out
differences and get legal and social consent. Opmal balance should be sought in respect of revenue sharing,
local development funds, ownership structure, taxaon levels and preferenal electricity rates.
3. Hydro projects regardless of capacity should be treated as ‘Renewables’ and extended all benefits as applicable for
renewable projects.
4. Foster Larger Storage Projects instead of several Run on River projects to ensure water security in the country.
Policy guidelines, for development of Pumped Storage Schemes need to be framed to integrate large scale renewable
capacity addion proposed from Wind and Solar.
5. Tariff comparison needs to be done on the basis of quality of the energy supplied, reflected by the posion
hydropower occupies in the load duraon curve. CERC needs to come up with a differenated peak and off-peak tariff
to incenvize hydropower, given its potenal to meet peak demand.
6. Taxaon: Cascading taxes constute 15-25% of overall project cost. Government may consider offering:
Restoraon of exempon of tax for interest income of FIs. Benefits u/s 10(23)g of IT Act, 1961 to Hydro Power
Projects allowed exempon of tax on the interest income earned by FIs from Infrastructure projects, were
withdrawn. Restoraon of such benefits would enable FIs to finance Hydro Projects at lower interest rate.
Secon 80I (A) of the Income Tax Act, 1956, provided tax holiday on the income generated from Power
Projects. This is limited unl 2017. Instead, this should be made applicable for 15 years for all Hydro Power
projects including under implementaon Projects too. Tax credits in the US and tax holidays in Laos, have
helped streamline flow of investments.
Government withdrew benefits associated with Mega Power status in 2012. These included VAT and custom
duty exempon on import of capital equipment; deemed export benefits accorded as per the EXIM Policy and
exempon of sales tax and other local levies on supplies to Mega power Plants by the State Governments.
Industry requests re-introducon of Mega Power Benefits for Hydro Projects.
Waiver/ reducon in Advalorem Charges/Tax (LADF, Entry Tax, Labour Cess, Excise Duty, Work Charge Tax, CST,
etc.) in respect of project equipment (construcon, E&M, HM), steel, cement, etc. required for development
of Hydropower projects.
Service tax exempon to services used in relaon to Hydro Power Projects shall significantly reduce project
cost and consequent reducon in tariff to compeve levels.
Government may consider zero rang for electricity under the GST regime.
7. Financing
State Government is to be provided 12% of free power as royalty from any hydropower Project to be
developed in the State. The State Governments may however, consider deferment of free power share for at
least inial years of repayment of loan period since project developers face maximum repayment strains in the
inial years of loan sancon. As such State Governments would benefit through infrastructure development,
in addion to assured 12% free power, though at a deferred date. Developers will be able to receive cheaper
finance.
![Page 29: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/29.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 2016 27 PageI
CONFERENCE REPORT
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 2016 27 PageI
CONFERENCE REPORT
Addionally for North East states, beneficiary quota of power from each Hydro project should be fixed so that
PPA can be signed with NE states on CERC norms.
Although, Opon of geng the tariff determined by the appropriate commission on the basis of performance
based cost of service regulaons has been extended up to December 31, 2022, However Private players are in
distress due to disparity of the State Discoms. While DISCOMS have an obligaon to sign PPA with PSUs, they
are reluctant to sign PPAs with Private Players. Level playing field should be provided to all hydro power
generators irrespecve whether the generator is PSU or Private.
Review and revise financing policies for hydro projects to provide a longer tenure debt to hydro period (25 -30
years). Financial Structuring to reduce the weighted average cost of capital for compeve tariff, it is
suggested that Debt: Equity (80:20) with mandatory incurrence of equity poron minimum of 50% before any
disbursement.
Provision of higher depreciaon in the early years of operaon, to enable hydropower developers meet their
repayment obligaons.
Majority of risks e.g. geological surprises, construcon risk, extreme terrain, hydrological risks are migated
aer Commissioning of Dam (CoD), therefore, financial instuons along with consorum lenders should
extend interest rebate on long-term loans.
Creaon of sub sectoral limit for lending to hydropower projects on priority basis by banks. The Banks should
be advised to earmark at least 40% of the total lending to power sector dedicated only for hydropower
projects.
Need to evaluate construcon period linked returns to bring all projects at par for returns. To commensurate
the riconcentraon of hydro resources to help developers reduce project cost on last mile connecvity.
sks & uncertaines, current level of RoE 16.50% needs to be made higher, to aract quality developers.
Soer interest rates should be extended to large Hydro Plants : IREDA NCEF launched a refinancing scheme for
revival of operaonal Small hydro Projects (SHP) and Biomass Project which have been affected by low tariff,
low PLF levels or force majure condions. To make these projects viable & bankable, IREDA shall extend loans
(funds sourced from NCEF), to extent of INR 150 MM for each project or 30% of loans of the project to Banks
(exisng lenders of these projects) at interest rate @ 2% p.a which these banks shall on lend to such power
projects @ 2% p.a. Such schemes should also cover projects under implementaon with larger funding
amounts so as to reduce the IDC thereby making the tariffs of HEPs more compeve.
9. New Financing Avenues
Viability Gap Funding is a viable proposal to make hydropower projects price compeve. For new projects,
the government may consider floang tenders and allocang projects to developers with the lowest VGF
proposal.
Innovave financial products: Encourage Tax-Free Bonds, Pension Funds to channelize long-term funding for
hydro sector. Mul-lateral and green funding for hydro projects can also be explored.
Time of Day Meetering: Hydroelectric power is a very important source for peaking power. Time of the day
tariff concept should be introduced to purchase peak power from hydro projects at higher rates than base load
power. ToD should be implemented as proposed in Tariff Policy 2016.
Hydropower Purchase Obligaons (HPOs): There should be separate HPO, an underlying principle of
mandatory purchase of hydropower by distribuon ulies. On the lines of renewable energy wherein 5 – 8 %
power needs to be met from renewable sources, minimum 10 – 15% of power may be sourced from large
Hydro Power Plants. Key features to include:
Dry season - power to be supplied during peak hours while through the day in the wet season
NEA obligated to purchase and off-take 100% of the declared available energy within the limits of agreed
Contracted Energy Table. Purchase tariff to be determined through a cost plus approach
Excess generaon declared over and above the level of agreed Contracted Energy Table, to be sold at 50%
of the applicable tariff.
![Page 30: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/30.jpg)
The purchaser of power should take into account that the PPA signed now, will be applicable for purchase of power aer
10 years hence, and the current tariff may be the most compeve price, then.
Investment board/nodal agency to facilitate private sector parcipaon in hydropower. Hydropower
Commission as a Nodal Agency could be established to opmize clearances and sancons to hydro projects
and facilitate private sector parcipaon in hydropower. Central Electricity Authority, Central Water
Commission, Environment Ministry, State Government, Ministry of Power, Ministry of Water Resources, could
be nominated on this Commission.
Government may create special hydropower financing schemes eg. accelerated generaon and supply
programme to state ulies, providing loans to power ulies at a reduced rate of interests.
Free Power to Downstream State: Some poron of free power royalty should be given to immediate
Downstream State, if no other tangible benefits like irrigaon are happening to it.
10. Streamlining of land acquision process: The Land acquision procedure for Hydro projects should be in line with
the one applicable for road projects of Naonal importance as per NHAI Act.
The government should complete pre-development acvies (e.g. land acquision) and statutory clearances
(e.g. environment and forest) for idenfied priority projects which are in line with the procedure for Ultra
Mega Power Projects (UMPP) before allocang them to developers.
The government should provide land record data and form a lender consorum to validate the available data
of different hydropower sites, review financial viability of a project, at Detailed Project Report (DPR)
preparaon stage. This will assist in preparaon of bankable DPRs to be shared with financial instuons
11. Environment and Forest Clearances
Revision in project parameters like E-Flows, project levels, based on Basin Study reports, aer the projects are
cleared by CEA & accorded Environment Clearance by MoEF & CC, makes the project unviable. Revisions
necessitate DPR revision & re-appraisal by CEA. E-Flows should be firmed up on the basis of scienfic studies
and should not be imposed at random. The dra of basin study report should be shared with concerned
project developers before finalizaon.
12. Integrated River Basin Development and Project Allocaon Procedure
The Central government can constute an authoritave body, River Basin Reservoir Regulatory Authority, to
address interstate water-sharing disputes and conduct integrated river basin development and prohibit delays
in commissioning of plants.
13. Power Evacuaon and Associated infrastructure
The Ministry of Power and the Ministry of Finance, Government of India, may allocate funds for the
construcon of a dedicated transmission corridor for hydropower (Green Energy Corridor) to evacuate the
hydropower generated from remote areas.
The state governments should make provision for building pooling substaons in locaons having a large
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 201628 PageI
CONFERENCE REPORT
![Page 31: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/31.jpg)
Shri Shyam D. Dubey Member (Hydro) CEA 8527243555 / [email protected]
08527243445
Shri M.M. Madan CEO – Hydro Jindal Power 9971814445 [email protected]
Shri A.B. Giri Member Board International Hydropower 9910460505 [email protected]
Association
Shri K.C. Dhimole Tech Advisor to CM Govt of Arunachal 9971071335 [email protected]
Shri Anand Behari Agarwal ED(HR) NHPC 9717766381 [email protected]
Shri Asim Thakurta Chief – Corporate Projects Tata Power 9711207681 [email protected]
Shri Gyanbhadra Kumar Head – Hydro JSW Energy 8894055500 [email protected]
Shri Kapil Mantri Head (Corp.Strat. & BD) JSPL 9871719255 [email protected]
Shri Rahul Varshney Director – BD Straftkraft Ltd. 9958691225 [email protected]
Shri Vibhash Pathania Representing THDC 9719653930 [email protected]
Shri Rajeev Vishnoi GM
Shri Kaushlendra Tripathi Director – Energy Advisory PWC 9560885956 [email protected]
Shri A.B. Pandya Former Chairman Central Water Commission 9910264141 [email protected]
Shri Satish Kumar Sharma VP Engg HCC 9820425386 [email protected]
Shri D.P. Bhargava Former Director (Tech) Retd. NHPC 9958833995 [email protected]
Shri P. K. Gupta GM (Geo-Tech) NHPC 9958010624
Shri D.P. Goyal Director Jaiprakash Power Ventures 9910067370 / [email protected]
0120-4972324
Shri Rohit Uberoi VP & Head of Design & Engg. Voith Hydro Pvt. Ltd. 9910039610 [email protected]
Shri Milon Mukhopadhyay MD Normet India Pvt. Ltd. 8130197200 [email protected]
Dr. D A. Karandikar Head – Coating Plant Andritz 9873903669 [email protected]
Shri K.K. Singh Reg. Exe Director (Hydro) NTPC Ltd. 9650998871 [email protected]
Shri Maninder Singh Director International Coil Ltd. [email protected]
Name Designation Organization Contact Email
Shri Sandeep Jajodia Sr Vice President ASSOCHAM [email protected]
Shri Sujit Ghosh Partner & National Head Advaita Legal [email protected]
Shri Naveen Jindal CMD JSPL [email protected]
Shri K.M. Singh CMD NHPC [email protected]
Shri Sigvald T. Hauge Charge-d’ Affaires Embassy of Norway [email protected]
Sr. MC Member
Smt Shakuntala D.Gamlin,IAS Chief Secretary Govt of Arunachal [email protected]
Shri B P Pandey Addl Secretary Min. of Power [email protected]
Shri Kalikho Pul Hon. CM Govt. of Arunachal Pradesh [email protected]
Shri Shrirang Karandikar Chairman ASSOCHAM National [email protected]
Council on Power
![Page 32: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/32.jpg)
Name Desig Company Contact Email
Mr. Dhiraj Kumar Fanish Manager ABB India Limited 9971508282 [email protected]
Mr. Manish Gupta Manager ABB India Limited 9971450003 [email protected]
Mr. Sai Krishna Seela Managing Director AF Consult India Pvt. Ltd. 9810126730 [email protected]
Mr. Hari S. Saxena Vice President AF Consult India Pvt. Ltd. 9582174680 [email protected]
Mr. Nikesh Ranjan Principle Engineer AF Consult India Pvt. Ltd. 9971965874 [email protected]
Ms. Preeti Malhotra Senior Specialist- ALSTOM India Limited 9717776629 [email protected]
Government Relations
Mr. O.P. Ajmera CEO Bhilwara Energy Ltd 9717766756 [email protected]
Mr. Jainender Kardam DGM Bhilwara Energy Ltd 9810599955 [email protected]
Mr. M.S. Gusain CESC Projects Ltd. 9810197358 [email protected]
(RP Sanjiv Goenka Group)
Mr. N.D. Arora CESC Projects Ltd. 9810319977 [email protected]
(RP Sanjiv Goenka Group)
Mr. R.K. Khanna Former Chief Engineer Central Water Commission 9811757497 [email protected]
(Environ. Mgnt.)
Mr. Arun Bhalla Executive Director - CPP Dalmia Bharat Cement 9910171715 [email protected]
Mr. Anjani Mallik Chief Engineer - Hydel Damodar Valley Corporation
Mr. S.K. Gupta Dy. Chief Engineer - Hydel Damodar Valley Corporation 9431319459 [email protected]
Mr. S.B. Pandey Dy. Chief Engineer - Hydel Damodar Valley Corporation
Mr. S.K. Majhi SE (Civil) Damodar Valley Corporation
Mr. R.K. Chaubey Chief safety Officer Damodar Valley Corporation 943354693 [email protected]
Mr. Subhash Chander Mittal Managing Director DMR Hydro Engg. &
Infrastructures (P) Ltd.
Mr. Jaikumar Dakhane Manager DMR Hydro Engg. &
Infrastructures (P) Ltd.
Mr. Surendra Sharma Dy. GM, Construction Elkem South Asia Pvt. Ltd. 9867736845 [email protected]
Mr. Saurabh Aggarwal Key Project Manager Elkem South Asia Pvt. Ltd. 9466510484 [email protected]
(Construction)
Mr. Alexander Karyukin Counsellor Finance Embassy of Russia 9650944256 [email protected]
Mr. Kshitij Mathur Sr. Engineer (Sales & Mktg.) Flovel Energy Pvt. Ltd. 9873558029 [email protected]
Mr. Ranjan Chauhan Sr. Global & Key GE India Indl. Pvt. Ltd. 9811210954 [email protected]
Accounts Manager [email protected]
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 201630 PageI
CONFERENCE REPORT
PARTICIPANTS
![Page 33: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/33.jpg)
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 2016 31 PageI
CONFERENCE REPORT
Name Desig Company Contact Email
Mr. Y. Mara Chief Engineer & Govt. of Arunachal Pradesh
Member Secretary
Mr. Manoj Kumar Verma Associate Manager GMR Energy Limited 8527700227 [email protected].
Mr. Rajesh Mediratta India Energy Exchange
Mr. A.K. Nanda Country Head – BD Innogeo 9717936346 [email protected]
Mr. Manjeet Pugalia Sr. Business Analyst International Coil Limited [email protected]
Mr. Angad Arora BD Manager International Coil Limited [email protected]
Mr. Maninder Singh Nayyar Director - Sales International Coil Limited
Mr. Paramjeet Singh Director - Technical International Coil Limited
Mr. R P Sharma
Mr. Anil Dhar AVP Jindal Power Ltd 9958111258 [email protected]
Mr. Dheeraj Marwaha DGM Jindal Power Ltd 8800690206 [email protected]
Mr. Souvik Khamrui AGM Jindal Power Ltd 9971003474 [email protected]
Mr. Chatar Singh Dy. Manager Jindal Power Ltd 9899153081 [email protected]
Mr. Pawan Kumar Kohli Director JMD Power Solutions 9810008537 [email protected]
Mr. P.V.Prasad Babu Executive Director Lanco Mandakini 9650012994 [email protected]
Hydro Energy Pvt. Ltd.
Mr. Dominic Fernandes L&T Ltd. 9818370645
Mr. P.S. Dutta Gupta Director Madhya Bharat Power
Corpn. Ltd.
Mr. Manish Verma AGM- North, Central Metropolis [email protected]
& East India
Ms. Ruchi Handa Metropolis
Mr. D. N. Dhawan Technical Director Ministry of Communications 9810220878 [email protected]
& IT
Mr. Nishant Verma AM-BD Miyar Hydro Electric
Power Co. Ltd.
Mr. R.P. Sharma Ex, Director (Tech.) NEEPCO 9810139025 RP Sharma [email protected]
Mr. P. S. Khurana COO (Hydro) Naying DSC Power Ltd
Shri Rajeev Sachdeva Chief Enginee NHPC 9958930077 [email protected]
CMD Secretariat
Mr. Vijoy Krishna NHPC
Mr. Rajeev Kumar NHPC
PARTICIPANTS
![Page 34: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/34.jpg)
Name Desig Company Contact Email
Mr. Prashant Jaiswal NHPC 99911540574 [email protected]
Mr. Rakesh Kumar NHPC
Mr. Prashar Rai NHPC
Mr. V.K. Gupta Principal Director NPTI [email protected]
Mr. M V Pande Director NPTI
Mr. Nitish Kumar Singh PGDC NPTI
Mr. Aman Singh PGDC NPTI
Mr. Surojit Banerjee PGDC NPTI
Mr. Prashant Gaurav PGDC NPTI
Mr. Vivek Singh PGDC NPTI
Mr. Dinesh Kumar PGDC NPTI
Mr. Rohit Kumar PGDC NPTI
Mr. Uma Shankar PGDC NPTI
Mr. Subimal Sengupta GM-Sales & Mktg. Normet India Pvt Ltd. 9560599978 [email protected]
(Constn. Chemicals)
Ms. Neha Burman Manager - HR Normet India Pvt Ltd. 8130197209 [email protected]
Mr. Puneet Narula General Manager- Normet India Pvt Ltd. 8130662830 [email protected]
Equipment Sales & LTC
Ms. Rohini Jindal Dy Manager (Technical) Normet India Pvt Ltd. 9560966464 [email protected]
Mr Anil Agrawal (MD)Managing Director Omega Ice Hill Private Ltd.
Mr D K Singh ( V P Works) Omega Ice Hill Private Ltd. 09917933111 [email protected]
Mr. Mohit Jindal (Agm marketing) Omega Ice Hill Private Ltd. 9990435111 [email protected]
Mr. Praveen C. Baroooah Managing Director Premier Intercontinental (I) Ltd.
Mr. Padam Prakash Associate Director PricewaterhouseCoopers [email protected]
Pvt Ltd
Mr. Kunal Singhal Associate Director PricewaterhouseCoopers [email protected]
Pvt Ltd
Mr. Sourish Dasgupta Manager PricewaterhouseCoopers [email protected]
Pvt Ltd
Mr. Soham Biswas Manager PricewaterhouseCoopers 9433394054 [email protected]
Pvt Ltd
Mr. Sanchit Makhija Manager PricewaterhouseCoopers [email protected]
Pvt Ltd
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 201632 PageI
CONFERENCE REPORT
PARTICIPANTS
![Page 35: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/35.jpg)
Name Desig Company Contact Email
Mr. Biswadeep Parida Senior Consultant PricewaterhouseCoopers [email protected]
Pvt Ltd
Mr. Dhirendra Goyal Senior Consultant PricewaterhouseCoopers [email protected]
Pvt Ltd
Ms. Kritika Nimesh Consultant PricewaterhouseCoopers [email protected]
Pvt Ltd
Mr. Sanjay Kumar Goyal Quantum Meruit Consultants 987152-23451 [email protected]
Mr. N.K. Gupta Rep. Raj Geotech Engg. Pvt. Ltd. 9871890032 [email protected]
Ms. Komal Luthra Manager Reliance Power Ltd 9310709087 [email protected]
Mr. Ajit Singh Associate VP-Hydro Seli Hydro Electric 844774 9868 [email protected]
Business Energy Power Co. Ltd.
Mr. P.C. Sharma President Shiga Energy Pvt. Ltd. 9810096455 [email protected]
Mr. Nukala Kishore Manager Shiga Energy Pvt. Ltd. 9873574939 [email protected]
Mr. U. Bora V P Soma Sissiri Hydro Power Ltd [email protected]
Mr. Afroz Alam Product Manager(North India) Sunil Chemical Industries 9934320355 [email protected]
Mr. S. Ramesh Brand Director Sunma Power Pvt. Ltd. 984116470
Mr. M. Viswanathan GM Projects Sunma Power Pvt. Ltd. 9944988442
Mr. K. Prabhakar Executive Director Sunma Power Pvt. Ltd. 9840392421
Mr. Vipin MitalE V P Uex Ltd. 9810357087 [email protected]
Mr. Kanwal Monga Chairman Virgo Consultants & 43588335337 [email protected],
Mr. Chandan Gupta Manager Voith Hydro Private Limited 8588823606 [email protected]
Mr. Amarjit Singh Makhija Manager Voith Hydro Private Limited 7827332462 [email protected]
Mr. Rajnish Nath Manager Voith Hydro Private Limited 9953488167 [email protected]
Ms. Sonia Koul Sr. Manager Voith Hydro Private Limited 9958599667 [email protected]
Mr. Shiv Kumar Manager Voith Hydro Private Limited 9650175332 [email protected]
Mr. Rajat Narang Yes Bank
Mr. L.V. Kumar Consulting Engineer Restructuring and Dev. of 9810429041 [email protected]
Water and Power Utilities
Mrs Reena Malhotra Director NT Dept of Telecom & IT GoI 9868132627 [email protected]
ASSOCHAM CONFERENCE : HYDROPOWER@CROSSROADS, May 3, 2016 33 PageI
CONFERENCE REPORT
PARTICIPANTS
![Page 36: Conference Report and Recommenndations...CONFERENCE REPORT Cost opmised Construcon of Tunnel in Hydro Power Shri Milon Mukhopadhyay, MD, Normet India P. Ltd. High impact velocity hydro](https://reader033.vdocument.in/reader033/viewer/2022041614/5e3a40f9cb46eb0b890e3cc1/html5/thumbnails/36.jpg)
THE ASSOCIATED CHAMERS OF COMMERCE AND INDUSTRY5 Sardar Patel Marg,
Chanakyapuri New Delhi 110021Tel: 011- 46550555 Fax: 011-23017008/9
Email: [email protected], [email protected]
Organising Team:Shri M.M.Madan, CEO (Hydro and Renewables) Jindal Power and Chairman Hydro Group, ASSOCHAM’s Naonal Council on PowerKavita Sharma, Joint Director, ASSOCHAM and Shri Kalyan Mukherjee, Sr. Director, ASSOCHAM
About ASSOCHAM
ASSOCHAM, since its incepon in 1920, has a glorious history of achievements that have led the
country in recent mes on a high growth path. The Chamber has established a strong legacy and an
impeccable lineage over the years. The Chamber has not only passed the test of longevity since its
establishment in 1920, but also has proacvely evolved with the changing mes and responded to
the needs of its members to be a beacon of connuing compeveness in a professional and
dispassionate manner. The Chamber has been very closely connected with the mulfarious
developmental acvies in the country and has been the incubator of ideas. The Chamber is well
respected for its balanced and studied approach to maers pertaining to development of trade and
industry and creang facilitang environment of the idenfied sectors.