Congestion Management Settlement Credits. December, 2002. Market Design Principles. The price of energy at each time and place should reflect the marginal cost of producing or not consuming one more unit of energy (at that time and place) - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/1.jpg)
Congestion Management Settlement Credits
December, 2002
![Page 2: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/2.jpg)
22
Market Design Principles
• The price of energy at each time and place should reflect the marginal cost of producing or not consuming one more unit of energy (at that time and place)
• Dispatchable market participants should be compensated for the effects of constraints
![Page 3: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/3.jpg)
33
Congestion
Occurs when physical capability of the transmission system cannot meet market
requirements
![Page 4: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/4.jpg)
Operating Profit
![Page 5: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/5.jpg)
55
Operating Profit
• Operating Profit is the difference between operating cost and revenue
• Market Rules written assuming participants bid and offer based on marginal benefit/cost
• Marginal Cost - Cost of producing next MW• Marginal Benefit - Benefit of consuming next
MW
![Page 6: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/6.jpg)
66
OP = Revenue - Cost
Quantity (MW)Quantity (MW)
MCP = 20MCP = 20
Price ($/MWh)Price ($/MWh)
MQSI=60MQSI=60100100
1515
1010
55
2525
3030
808060604040202000
OP+OP+OP+OP+
OP+OP+
![Page 7: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/7.jpg)
77
Skill Check
![Page 8: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/8.jpg)
88
Skill Check• Generator A offer:
• 0-20 MW $15• 21-30 MW $25• 31 - 40 MW $100
Dispatched to 30 MW
• Load B bid:• 0-10 MW $1,000• 11-20 MW $500• 21-30 MW $20
Dispatched to 20 MW
If MCP is $30, what is the OP for A and B?
![Page 9: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/9.jpg)
Congestion Management Settlement Credits
![Page 10: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/10.jpg)
1010
Congestion Management Settlement Credit
• CMSC payments are based on the difference between the Operating Profit that would result from the Market Schedule and Operating Profit resulting from the Dispatch Instruction
OP (MQSI) - OP (DQSI)Where MQSI = Market Quantity Scheduled for Injection
DQSI = Dispatch Quantity Scheduled for Injection
![Page 11: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/11.jpg)
1111
Market Schedule
Requirement is Requirement is 190 MW190 MW• Gen 1: 100 MWGen 1: 100 MW• Gen 2: 90 MWGen 2: 90 MW• MCP $20MCP $20• GEN 3: does not runGEN 3: does not run
Region 2Region 2Region 1Region 1
nonotransmissiontransmission
line limitline limit
Generator 3Generator 3
100 MW100 MW$25$25
LoadLoad
190 MW190 MW
Generator 1Generator 1
100 MW100 MW$15$15
Generator 2Generator 2
100 MW100 MW$20$20
![Page 12: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/12.jpg)
1212
Transmission Congestion
Requirement is Requirement is 190 MW190 MW• Gen 1: 100 MWGen 1: 100 MW• Gen 2: 50 MWGen 2: 50 MW• Gen 3: 40 MWGen 3: 40 MW• MCP $20MCP $20
Generator 1Generator 1
100 MW100 MW$15$15
Generator 2Generator 2
100 MW100 MW$20$20
Generator 3Generator 3
100 MW100 MW$25$25
LoadLoad
190 MW190 MW
Region 2Region 2Region 1Region 1
150 MW150 MWtransmissiontransmission
line limitline limit
![Page 13: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/13.jpg)
1313
CMSCFor Generator 2 in this case:MQSI = 90 Offer = $20DQSI = 50 MCP = $20
CMSC = OP(MQSI) - OP(DQSI) = (MCP-Offer) x MQSI - (MCP-Offer) x DQSI
= (20-20) x90 - (20-20) x 50= 0 - 0= $0
![Page 14: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/14.jpg)
1414
CMSCFor Generator 3 in this case:MQSI = 0 Offer = $25DQSI = 40 MCP = $20
CMSC = OP(MQSI) - OP(DQSI) = (MCP-Offer) x MQSI - (MCP-Offer) x DQSI
= (20-25) x 0 - (20-25) x 40= 0 - (-$200)= $200
![Page 15: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/15.jpg)
1515
Gen 1- Constrained Off
Requirement is Requirement is 190 MW190 MW• Gen 1: 95 MWGen 1: 95 MW• Gen 2: 55 MWGen 2: 55 MW• Gen 3: 40 MWGen 3: 40 MW• MCP $20MCP $20
Generator 3Generator 3
100 MW100 MW$25$25
LoadLoad
190 MW190 MW
Region 2Region 2Region 1Region 1
150 MW150 MWtransmissiontransmission
line limitline limit
95 MW limit95 MW limitGenerator 1Generator 1
100 MW100 MW$15$15
Generator 2Generator 2
100 MW100 MW$20$20
![Page 16: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/16.jpg)
1616
Constrained Off PaymentGenerator 1
• Market Schedule: 100 MW• Dispatch : 95 MW• Offer: $15 /MWh• MCP: $20 /MWh
CMSC= OP(MQSI) - OP(DQSI) = (MCP-Offer) x MQSI - (MCP-Offer) x DQSI = (20-15) x 100 - (20-15) x 95 = $25
![Page 17: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/17.jpg)
1717
Gen 2 - Constrained Off
Requirement is Requirement is 190 MW190 MW• Gen 1: 95 MWGen 1: 95 MW• Gen 2: 55 MWGen 2: 55 MW• Gen 3: 40 MWGen 3: 40 MW• MCP $20MCP $20
Generator 3Generator 3
100 MW100 MW$25$25
LoadLoad
190 MW190 MW
Region 2Region 2Region 1Region 1
150 MW150 MWtransmissiontransmission
line limitline limit
9595MWMW
100100MWMW
Generator 1Generator 1
100 MW100 MW$15$15
Generator 2Generator 2
100 MW100 MW$20$20
![Page 18: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/18.jpg)
1818
Constrained Off PaymentGenerator 2
• Market Schedule: 90 MW• Dispatch : 55 MW• Offer: $20 /MWh• MCP: $20 /MWh
CMSC= OP(MQSI) - OP(DQSI) = (MCP-Offer) x MQSI - (MCP-Offer) x DQSI
= (20-20) x 90 - (20-20) x 55 = $0
![Page 19: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/19.jpg)
1919
Constrained On PaymentGenerator 3
• Market Schedule: 0• Dispatch : 40 MW• Offer: $25• MCP: $20 /MWh
CMSC= OP(MQSI) - OP(DQSI) = (MCP-Offer) x MQSI - (MCP-Offer) x DQSI
= ($20-$25) x 0 - ($20-$25) x 40 MW = $200
![Page 20: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/20.jpg)
Constraint Payments
When Actual Quantity Different than Dispatch Quantity
![Page 21: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/21.jpg)
2121
Gen 1- Constrained Off
Requirement is Requirement is 190 MW190 MW• Gen 1: 95 MWGen 1: 95 MW• Gen 2: 55 MWGen 2: 55 MW• Gen 3: 40 MWGen 3: 40 MW• MCP $20MCP $20
Generator 3Generator 3
100 MW100 MW$25$25
LoadLoad
190 MW190 MW
Region 2Region 2Region 1Region 1
150 MW150 MWtransmissiontransmission
line limitline limit
95 MW limit95 MW limitGenerator 1Generator 1
100 MW100 MW$15$15
Generator 2Generator 2
100 MW100 MW$20$20
Actually produces 50 MW
![Page 22: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/22.jpg)
2222
Constraint Payments
MQSI = 0 MW, DQSI=40 MW, AQEI =50MWMCP = $20 Offer = $25
CMSC = OP (MQSI) - MAX [OP (DQSI), OP (AQEI)]= (20-25) x 0 - MAX [(20-25) x 40, (20-25) x 50]= $0 - MAX [$-200, $-250]= $-(-200)= $200
![Page 23: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/23.jpg)
2323
CMSC for a Dispatchable Load
• Load may be dispatched off or on• Any time constrained and unconstrained are
different, possibility exists for CMSC
![Page 24: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/24.jpg)
2424
CMSC for a Dispatchable LoadE.G.• Load A bids for 100 MW at $2,000• Market Clearing Price = $100• Load A is dispatched to only 75 MW• At a bid price of $2,000 Load A will be scheduled by the unconstrained algorithm for all 100
MW
![Page 25: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/25.jpg)
2525
CMSC for a Dispatchable Load• Bid = $2,000 MCP = $100• MQSI = 100 MW, DQSI = 75 MW• CMSC = OP(MQSI) - OP(DQSI)
= ($2,000 - $100) x 100 - ($2,000 - $100) x 75)
= $1900 x 100 - $1900 x 75 = $47,500
• The lost Operating Profit is $47,500
![Page 26: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/26.jpg)
2626
Negative CMSC
• CMSC payments bring the participant back to the market schedule operating profit
• Generally CMSC payments will be a top-up to restore operating profit
• Sometimes the schedule would lead to lower profit than dispatch instructions
![Page 27: Congestion Management Settlement Credits](https://reader035.vdocument.in/reader035/viewer/2022062814/5681679e550346895ddce5af/html5/thumbnails/27.jpg)
2727
CMSC
• CMSC payments bring the participant back to the market schedule operating profit
• While CMSC can be negative, it is more often a payment to participants
• The cost of CMSC is recovered from loads based on their activity in the market