consideration of comments 2016epr02 enhanced... · consideration of comments | project...

160
Consideration of Comments Project Name: 2016EPR02 Enhanced Periodic Review of VAR Standards | Template for VAR0014.1 Comment Period Start Date: 2/28/2017 Comment Period End Date: 4/13/2017 There were 30 sets of responses, including comments from approximately 94 different people from approximately 77 companies representing the 10 Industry Segments as shown in the table on the following pages. All comments submitted can be reviewed in their original format on the project page. If you feel that your comment has been overlooked, please let us know immediately. Our goal is to give every comment serious consideration in this process. If you feel there has been an error or omission, you can contact the Director of Standards Development, Steve Noess (via email) or at (404) 4469691. Executive Summary The periodic review team completed a comprehensive review of VAR0024 – Generator Operation for Maintaining Network Voltage Schedules. The team found the standard is sufficient to protect reliability and meet the reliability objective of the standard; however, there may be future opportunity to improve a nonsubstantive or insignificant quality and content issue. Industry comments also affirmed that the standard: 1) is sufficient to protect reliability, 2) meets the reliability objective of the standard, and 3) no immediate revision is necessary. The following are the observations and recommendations of the periodic review team.

Upload: others

Post on 25-Aug-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

      

                

      Consideration of Comments 

     

               Project Name:  2016‐EPR‐02 Enhanced Periodic Review of VAR Standards | Template for VAR‐001‐4.1 

Comment Period Start Date:  2/28/2017 Comment Period End Date:  4/13/2017 

 

 

  There were 30 sets of responses, including comments from approximately 94 different people from approximately 77 companies representing the 10 Industry Segments as shown in the table on the following pages. 

 

 

  

 All comments submitted can be reviewed in their original format on the project page.  If you feel that your comment has been overlooked, please let us know immediately. Our goal is to give every comment serious consideration in this process. If you feel there has been an error or omission, you can contact the Director of Standards Development, Steve Noess (via email) or at (404) 446‐9691.

 Executive Summary The periodic review team completed a comprehensive review of VAR‐002‐4 – Generator Operation for Maintaining Network Voltage Schedules. The team found the standard is sufficient to protect reliability and meet the reliability objective of the standard; however, there may be future opportunity to improve a non‐substantive or insignificant quality and content issue. Industry comments also affirmed that the standard: 1) is sufficient to protect reliability, 2) meets the reliability objective of the standard, and 3) no immediate revision is necessary. The following are the observations and recommendations of the periodic review team.   

 

   

Page 2: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    2 

Questions

1. VAR‐001‐4.1 Requirement R4, regarding exemptions and exempted units, does not require periodic reviews or reviews triggered by changes; such as, technology, system conditions or other factors. Does this create an impact to reliability? If yes, please explain. 

2. If the voltage schedule issued by the TOP to the GOP (Requirement R5) results in a generating unit routinely running at maximum limits, does a lack of dynamic reactive reserve have a reliability impact? 

3. As of April 1, 2017, there will no longer be any explicit requirements for monitoring or ensuring adequate reactive reserves. Absent of any explicit requirements to monitor or ensure adequate reactive reserves within the IRO, TOP, or VAR standards, is there an impact to reliability? If yes, please explain. 

4. As VAR‐001‐4.1 Requirement R5, Part 5.2 is silent with regards to a time duration that a generator can be outside of voltage schedule before notification is required. If the TOP is not required to specify the timing portion of the notification requirements while maintaining the necessary flexibility, is there an impact to reliability? If yes, please explain. 

5. VAR‐001‐4.1 Requirement R5 does not include the RC as a recipient of voltage or Reactive Power schedules issued to generators. Is there an impact to reliability? If yes, please explain. 

6. VAR‐001‐4.1 Requirement R5 dictates the status of an AVR. Does the lack of a similar requirement to identify the initial state of the PSS impact reliability? If yes, please explain. 

7. The continent‐wide VAR standards do not address external control loops to the AVR that may impact the reactive response of a generator. Some external control loops do not have the purpose of automatic voltage control, therefore, is there a need to coordinate external loops to prevent an impact to reliability?[1] If yes, please explain. 

Page 3: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    3 

[1] See also: Lesson Learned, Generator Distributed Control System Impact on Automatic Voltage Regulators, June 9, 2015, (http://www.nerc.com/pa/rrm/ea/Lessons Learned Document Library/LL20150602_Generator_Distributed_Control_System_ Impact_on_Automatic_Voltage_Regulators.pdf)  

8. There are a number of errata (i.e., administrative) type observations listed in Attachment 4 of the VAR‐001‐4.1 template. If you disagree with any of the observations, please list the reference number when providing comment. 

9. There are a number of other observations in Attachment 5 of the VAR‐001‐4.1 template that could enhance the standard, but would require a drafting team to develop for industry feedback. If you have any comments about these, please list the reference number when providing comment. 

10. The team did not identify a concern related to cost effectiveness as drafted.  Do you agree?  If not, please provide additional detail.

11. Given the items identified by the periodic review team in the VAR‐001‐4.1 template, do you agree that the Reliability Standard is sufficient to protect reliability and meet the reliability objective of the standard and does not need immediate modification through standards development; however, there may be a future opportunity to improve any non‐substantive or insignificant quality and content issues? If you have any other comments on this review that you haven’t already mentioned above, please provide them here. 

  

Page 4: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    4 

The Industry Segments are:

  1 — Transmission Owners   2 — RTOs, ISOs   3 — Load‐serving Entities   4 — Transmission‐dependent Utilities   5 — Electric Generators   6 — Electricity Brokers, Aggregators, and Marketers   7 — Large Electricity End Users   8 — Small Electricity End Users     9 — Federal, State, Provincial Regulatory or other Government Entities   10 — Regional Reliability Organizations, Regional Entities    

Page 5: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    5 

Organization Name  Name  Segment(s)  Region  Group Name Group Member 

Name 

Group Member 

Organization

Group Member 

Segment(s)

Group Member Region 

ACES Power Marketing 

Brian Van Gheem 

6  NA ‐ Not Applicable 

ACES Standards Collaborators

Shari Heino  Brazos Electric Power Cooperative, Inc. 

1,5  Texas RE 

Tara Lightner  Sunflower Electric Power Corporation 

1  SPP RE 

Greg Froehling  Rayburn Country Electric Cooperative, Inc. 

3  SPP RE 

Bob Solomon  Hoosier Energy Rural Electric Cooperative, Inc. 

1  RF 

Mark Ringhausen 

Mark Ringhausen 

3,4  SERC 

John Shaver  Arizona Electric Power Cooperative, Inc. 

1  WECC 

Page 6: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    6 

Organization Name  Name  Segment(s)  Region  Group Name Group Member 

Name 

Group Member 

Organization

Group Member 

Segment(s)

Group Member Region 

Bill Hutchison  Southern Illinois Power Cooperative 

1  SERC 

Michael Brytowski 

Great River Energy 

1,3,5,6  MRO 

Ginger Mercier  Prairie Power, Inc. 

1,3  SERC 

Duke Energy   Colby Bellville 1,3,5,6  FRCC,RF,SERC Duke Energy   Doug Hils   Duke Energy   1  RF 

Lee Schuster   Duke Energy   3  FRCC 

Dale Goodwine  Duke Energy   5  SERC 

Greg Cecil  Duke Energy   6  RF 

New York Independent System Operator 

Gregory Campoli 

2    ISO/RTO Standards Review Committee 

Gregory Campoli 

NYISO  2  NPCC 

Ben Li  IESO  2  NPCC 

Kathleen Goodman 

ISONO  2  NPCC 

Mark Holman  PJM  2  NPCC 

Charles Yeung  SPP  2  SPP RE 

Terry Bilke  MISO  2  MRO 

Nathan Bigbee  ERCOT  2  Texas RE 

Ali Miremadi  CAISO  2  WECC 

Page 7: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    7 

Organization Name  Name  Segment(s)  Region  Group Name Group Member 

Name 

Group Member 

Organization

Group Member 

Segment(s)

Group Member Region 

Entergy  Julie Hall  6    Entergy/NERC Compliance 

Oliver Burke  Entergy ‐ Entergy Services, Inc. 

1  SERC 

Jaclyn Massey  Entergy ‐ Entergy Services, Inc. 

5  SERC 

DTE Energy ‐ Detroit Edison Company 

Karie Barczak  3,4,5    DTE Energy ‐ DTE Electric 

Jeffrey Depriest  DTE Energy ‐ DTE Electric 

5  RF 

Daniel Herring  DTE Energy ‐ DTE Electric 

4  RF 

Karie Barczak  DTE Energy ‐ DTE Electric 

3  RF 

Southern Company ‐ Southern Company Services, Inc. 

Pamela Hunter 

1,3,5,6  SERC  Southern Company 

Katherine Prewitt 

Southern Company Services, Inc. 

1  SERC 

R. Scott Moore  Alabama Power Company 

3  SERC 

William D. Shultz 

Southern Company Generation 

5  SERC 

Jennifer G. Sykes 

Southern Company Generation 

6  SERC 

Page 8: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    8 

Organization Name  Name  Segment(s)  Region  Group Name Group Member 

Name 

Group Member 

Organization

Group Member 

Segment(s)

Group Member Region 

and Energy Marketing 

Northeast Power Coordinating Council 

Ruida Shu  1,2,3,4,5,6,7,8,9,10 NPCC  RSC no ISO‐NE 

Paul Malozewski Hydro One.  1  NPCC 

Guy Zito  Northeast Power Coordinating Council 

NA ‐ Not Applicable 

NPCC 

Randy MacDonald 

New Brunswick Power 

2  NPCC 

Wayne Sipperly  New York Power Authority 

4  NPCC 

Glen Smith  Entergy Services 

4  NPCC 

Brian Robinson  Utility Services 5  NPCC 

Bruce Metruck  New York Power Authority 

6  NPCC 

Alan Adamson  New York State Reliability Council 

7  NPCC 

Page 9: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    9 

Organization Name  Name  Segment(s)  Region  Group Name Group Member 

Name 

Group Member 

Organization

Group Member 

Segment(s)

Group Member Region 

Edward Bedder  Orange & Rockland Utilities 

1  NPCC 

David Burke  Orange & Rockland Utilities 

3  NPCC 

Michele Tondalo UI  1  NPCC 

Sylvain Clermont 

Hydro Québec 1  NPCC 

Si Truc Phan  Hydro Québec 2  NPCC 

Helen Lainis  IESO  2  NPCC 

Laura Mcleod  NB Power  1  NPCC 

MIchael Forte  Con Edison  1  NPCC 

Kelly Silver  Con Edison  3  NPCC 

Peter Yost  Con Edison  4  NPCC 

Brian O'Boyle  Con Edison  5  NPCC 

Greg Campoli  NY‐ISO  2  NPCC 

Michael Schiavone 

National Grid  1  NPCC 

Michael Jones  National Grid  3  NPCC 

Page 10: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    10 

Organization Name  Name  Segment(s)  Region  Group Name Group Member 

Name 

Group Member 

Organization

Group Member 

Segment(s)

Group Member Region 

David Ramkalawan 

Ontario Power Generation Inc. 

5  NPCC 

Quintin Lee  Eversource Energy 

1  NPCC 

Silvia Mitchell  NextEra Energy ‐ Florida Power and Light Co. 

6  NPCC 

Sean Bodkin  Dominion Resources Services, Inc. 

4  NPCC 

Southwest Power Pool, Inc. (RTO) 

Shannon Mickens 

2  SPP RE  SPP Standards Review Group 

Shannon Mickens 

Southwest Power Pool Inc. 

2  SPP RE 

Jim Nail  City of Independence, Power and Light Department 

5  SPP RE 

John Allen  City Utilities of Springfield, Missouri 

4  SPP RE 

Kevin Giles  Westar Energy 1  SPP RE 

Page 11: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    11 

Organization Name  Name  Segment(s)  Region  Group Name Group Member 

Name 

Group Member 

Organization

Group Member 

Segment(s)

Group Member Region 

mike kidwell  Empire District Electric Company 

1,3,5  SPP RE 

Tara Lightner  Sunflower Electric Power Corporation 

1  SPP RE 

Don Schmit  Nebraska Public Power District 

5  SPP RE 

J.Scott Williams  City Utilities of Springfleld 

1,4  SPP RE 

Page 12: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    12 

1. VAR‐001‐4.1 Requirement R4, regarding exemptions and exempted units, does not require periodic reviews or reviews triggered by changes; such as, technology, system conditions or other factors. Does this create an impact to reliability? If yes, please explain. 

Aaron Cavanaugh ‐ Bonneville Power Administration ‐ 1,3,5,6 ‐ WECC 

Answer  No 

Document Name   

Comment 

BPA does not exempt any qualified units. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. 

Pamela Hunter ‐ Southern Company ‐ Southern Company Services, Inc. ‐ 1,3,5,6 ‐ SERC, Group Name Southern Company 

Answer  No 

Document Name   

Comment 

Not necessarily.  Generally speaking, IAs and Operating Agreements usually contain language that requires notifications between the GO and TO/TSP/TOP and vice‐versa when there are changes.  That would serve as the prompt to re‐evaluate. Even absent the aforementioned prompt to re‐evaluate, nothing precludes the TOP from re‐evaluating exemptions. 

Likes     0   

Dislikes     0   

Page 13: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    13 

Response 

Thank you for your comment. 

Stephanie Burns ‐ International Transmission Company Holdings Corporation ‐ 2 ‐ MRO,SPP RE,RF 

Answer  No 

Document Name   

Comment 

This sounds like an improvement in theory but it would manifest as a documentation requirement and add little value. A requirement would likely be met by showing an annual review of a procedure containing the exemption criteria. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. 

Chris Scanlon ‐ Exelon ‐ 1,3,5,6 

Answer  No 

Document Name   

Comment 

There is no need for an administrative requirement to conduct a periodic review. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. 

Page 14: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    14 

Ruida Shu ‐ Northeast Power Coordinating Council ‐ 1,2,3,4,5,6,7,8,9,10 ‐ NPCC, Group Name RSC no ISO‐NE 

Answer  No 

Document Name   

Comment 

The exemption should be based on the system need. Operating experience will bring to light when an exeption needs to be reconsidered. There is no need to create a requirement to perform a review. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) concluded based on industry comment that the current TOP/IRO standards provide for an Operational Planning Analysis (OPA) and Real‐time Assessment (RTA) that will identify any reliability issues; therefore, no immediate revision to the standard is warranted. Based on minority response, the PRT affirms that there may be future opportunities to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Russel Mountjoy ‐ Midwest Reliability Organization ‐ 10 

Answer  No 

Document Name   

Comment 

There are 30 minute system evaluations, next day analysis and other operation studies being run that would highlight if this were an issue.  See Reliability Standards – TOP‐001‐3 & TOP‐002‐4. 

Likes     0   

Dislikes     0   

Response 

Page 15: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    15 

Thank you for your comment. The periodic review team (PRT) concluded based on industry comment that the current TOP/IRO standards provide for an Operational Planning Analysis (OPA) and Real‐time Assessment (RTA) that will identify any reliability issues; therefore, no immediate revision to the standard is warranted. Based on minority response, the PRT affirms that there may be future opportunities to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Colby Bellville ‐ Duke Energy ‐ 1,3,5,6 ‐ FRCC,SERC,RF, Group Name Duke Energy  

Answer  No 

Document Name   

Comment 

Duke Energy does not believe a periodic review or a review triggered by the specified changes is necessary, and does not believe that the lack of a requirement impacts reliability. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. 

Brian Van Gheem ‐ ACES Power Marketing ‐ 6 ‐ NA ‐ Not Applicable, Group Name ACES Standards Collaborators 

Answer  No 

Document Name   

Comment 

TOPs already assess operations that would impact reliability through various Real Time Assessments and Operational Planning Analyses, as required in NERC Reliability Standards TOP‐001‐3 and TOP‐002‐4.  We feel introducing a requirement for a periodic review of these exemptions would only cause confusion. 

Likes     0   

Page 16: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    16 

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) concluded based on industry comment that the current TOP/IRO standards provide for an Operational Planning Analysis (OPA) and Real‐time Assessment (RTA) that will identify any reliability issues; therefore, no immediate revision to the standard is warranted. Based on minority response, the PRT affirms that there may be future opportunities to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Elizabeth Axson ‐ Electric Reliability Council of Texas, Inc. ‐ 2 

Answer  No 

Document Name   

Comment 

ERCOT agrees that TOPs should periodically review any exemptions provided along with the criteria for granting such exemptions, but it is not necessary to require that through a standard. If a unit’s exemption is causing reliability issues, the symptoms will more likely be observed in Planning Assessments, Operational Planning Analysis, and Real Time Assessments.  This will prompt either Corrective Actions Plans or Operating Plans to be developed to address. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) concluded based on industry comment that the current TOP/IRO standards provide for an Operational Planning Analysis (OPA) and Real‐time Assessment (RTA) that will identify any reliability issues; therefore, no immediate revision to the standard is warranted. Based on minority response, the PRT affirms that there may be future opportunities to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Glen Farmer ‐ Avista ‐ Avista Corporation ‐ 1,3,5 

Answer  No 

Document Name   

Page 17: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    17 

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Dennis Chastain ‐ Tennessee Valley Authority ‐ 1,3,5,6 ‐ SERC 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Preston Walker ‐ PJM Interconnection, L.L.C. ‐ 2 ‐ RF 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

Page 18: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    18 

 

Michelle Amarantos ‐ APS ‐ Arizona Public Service Co. ‐ 1,3,5,6 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Sean Bodkin ‐ Dominion ‐ Dominion Resources, Inc. ‐ 3,5,6 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Karie Barczak ‐ DTE Energy ‐ Detroit Edison Company ‐ 3,4,5, Group Name DTE Energy ‐ DTE Electric 

Answer  No 

Document Name   

Comment 

Page 19: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    19 

 

Likes     0   

Dislikes     0   

Response 

 

Jesus Sammy Alcaraz ‐ Imperial Irrigation District ‐ 1 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

David Jendras ‐ Ameren ‐ Ameren Services ‐ 1,3,6 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Page 20: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    20 

Laura Nelson ‐ IDACORP ‐ Idaho Power Company ‐ 1 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Sandra Shaffer ‐ Berkshire Hathaway ‐ PacifiCorp ‐ 6 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Michael Cruz‐Montes ‐ CenterPoint Energy Houston Electric, LLC ‐ 1 ‐ Texas RE 

Answer  No 

Document Name   

Comment 

 

Page 21: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    21 

Likes     0   

Dislikes     0   

Response 

 

Shannon Mickens ‐ Southwest Power Pool, Inc. (RTO) ‐ 2 ‐ SPP RE, Group Name SPP Standards Review Group 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Gregory Campoli ‐ New York Independent System Operator ‐ 2, Group Name ISO/RTO Standards Review Committee 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Hien Ho ‐ Tacoma Public Utilities (Tacoma, WA) ‐ 1,3,4,5,6 

Page 22: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    22 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Thomas Foltz ‐ AEP ‐ 3,5 

Answer  Yes 

Document Name   

Comment 

There should be a requirement to conduct a periodic review to the units that are exempt, at a minimum of every three years of the exemption criteria. In addition, the specified voltage schedule supplied to the unit should be reviewed as well. For example, the initial stages of a wind farm project may not require a specific voltage schedule (i.e. exempt), but as the project progresses, changes (perhaps driven by a proposed increase in the size of the wind farm), a voltage schedule may need to be developed.  

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) concluded based on industry comment that the current TOP/IRO standards provide for an Operational Planning Analysis (OPA) and Real‐time Assessment (RTA) that will identify any reliability issues; therefore, no immediate revision to the standard is warranted. Based on minority response, the PRT affirms that there may be future opportunities to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Page 23: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    23 

Julie Hall ‐ Entergy ‐ 6, Group Name Entergy/NERC Compliance 

Answer  Yes 

Document Name   

Comment 

Agree that there is a gap there. The review could be periodic or trigger based such as an equipment modification or any change that could impact the exempted status. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. 

Aubrey Short ‐ FirstEnergy ‐ FirstEnergy Corporation ‐ 1,3,4 

Answer  Yes 

Document Name   

Comment 

Exemptions and exemption units should be required to ensure statuses have been updated to and from TOP and GOP on a predetermined periodic schedule. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. 

Rachel Coyne ‐ Texas Reliability Entity, Inc. ‐ 10 

Page 24: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    24 

Answer  Yes 

Document Name   

Comment 

Texas RE recommends periodic reviews of exemptions.   In order to determine the best actions to support the reliability of the grid, TOPs need to understand the status or capability of available resources.  When a generating unit becomes exempt, the TOP loses visibility to that generator.  

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) concluded based on industry comment that the current TOP/IRO standards provide for an Operational Planning Analysis (OPA) and Real‐time Assessment (RTA) that will identify any reliability issues; therefore, no immediate revision to the standard is warranted. Based on minority response, the PRT affirms that there may be future opportunities to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Richard Jackson ‐ U.S. Bureau of Reclamation ‐ 1,5 

Answer  Yes 

Document Name   

Comment 

Reclamation asserts it is prudent to apply a time period for the TOP to review their specific criteria for generator exemptions. Reclamation asserts that the logical time period would coincide with the time period specified in the NERC system modeling (MOD) standards.  Reclamation suggests Requirement R4 should specify that at least once every 10 years the Transmission Operator shall review and evaluate its exemption criteria for generators and notify pertinent Generator Operators of any changes to the previous criteria. 

Likes     0   

Dislikes     0   

Page 25: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    25 

Response 

Thank you for your comment. The periodic review team (PRT) concluded based on industry comment that the current TOP/IRO standards provide for an Operational Planning Analysis (OPA) and Real‐time Assessment (RTA) that will identify any reliability issues; therefore, no immediate revision to the standard is warranted. Based on minority response, the PRT affirms that there may be future opportunities to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

John Seelke ‐ LS Power Transmission, LLC ‐ 1 

Answer   

Document Name  LS Power Transmission Comments Project 2016‐EPR 04.13,17.docx 

Comment 

LS Power Transmission's comments address a problem wth both and are therefore separately attached.. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) addresses the redundancy issue in the Periodic Review Recommendations: VAR‐001‐4.1 – Voltage and Reactive Control document, Attachment 5: Other Miscellaneous Corrections/Revisions, Item 1.1. 

Page 26: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    26 

2. If the voltage schedule issued by the TOP to the GOP (Requirement R5) results in a generating unit routinely running at maximum limits, does a lack of dynamic reactive reserve have a reliability impact? 

Elizabeth Axson ‐ Electric Reliability Council of Texas, Inc. ‐ 2 

Answer  No 

Document Name   

Comment 

A lack of dynamic reactive reserves on only a single unit will not typically have a reliability impact.  However, multiple generating units in the same reactive zone all running at Qmax or Qmin limits while using their dynamic reactive capability to provide that response could have a reliability impact.   If seen ahead of time, or if monitored in real time with voltage stability applications, voltage stability System Operating Limits can be established to monitor when it would become a reliability impact.  Voltage Schedules should be optimized to use static reactive devices first in order to maximize availability of generating unit dynamic reactive capability.  While this is best practice, ERCOT does not necessarily agree that this should be captured in a standard 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) notes that industry submitted comments that the lack of reserves on a single unit would not pose a reliability issue regarding the need for a periodic review. Any issues involving multiple generating units would be identified as part of an Operational Planning Analysis (OPA) or Real‐Time Assessment (RTA). The PRT affirms that there may be future opportunity to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Michael Godbout ‐ Hydro‐Québec TransÉnergie ‐ 1 ‐ NPCC 

Answer  No 

Document Name   

Comment 

Page 27: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    27 

Not necessarily. A specific unit running at maximum doesn not mean there is a lack of dynamic reactive reserve. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) notes that industry submitted comments that the lack of reserves on a single unit would not pose a reliability issue regarding the need for a periodic review. Any issues involving multiple generating units would be identified as part of an Operational Planning Analysis (OPA) or Real‐Time Assessment (RTA). The PRT affirms that there may be future opportunity to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Shannon Mickens ‐ Southwest Power Pool, Inc. (RTO) ‐ 2 ‐ SPP RE, Group Name SPP Standards Review Group 

Answer  No 

Document Name   

Comment 

The SPP Review Group has the perspective that a single generating unit is not a concern, because voltage control is a wider area issue involving multiple generator resources. However, if the drafting team feels that the focus of this project extends beyond the single generator, we recommend the drafting team revise the project language to reflect those concerns. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) notes that industry submitted comments that the lack of reserves on a single unit would not pose a reliability issue regarding the need for a periodic review. Any issues involving multiple generating units would be identified as part of an Operational Planning Analysis (OPA) or Real‐Time Assessment (RTA). The PRT affirms that there may be future opportunity to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Russel Mountjoy ‐ Midwest Reliability Organization ‐ 10 

Page 28: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    28 

Answer  No 

Document Name   

Comment 

TOP’s have the responsibility to ensure adequate dynamic reactive response. From the TOP perspective, reliability impact depends on available resources for the area and dynamic response available for the TOP footprint. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) notes that industry submitted comments that the lack of reserves on a single unit would not pose a reliability issue regarding the need for a periodic review. Any issues involving multiple generating units would be identified as part of an Operational Planning Analysis (OPA) or Real‐Time Assessment (RTA). The PRT affirms that there may be future opportunity to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Ruida Shu ‐ Northeast Power Coordinating Council ‐ 1,2,3,4,5,6,7,8,9,10 ‐ NPCC, Group Name RSC no ISO‐NE 

Answer  No 

Document Name   

Comment 

Not necessarily. This would have to be studied to determine whether there is a reliability impact. Planning studies should identify areas that lack sufficient reactive capability. If there are, system modifications should be proposed. 

Likes     0   

Dislikes     0   

Response 

Page 29: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    29 

Thank you for your comment. The periodic review team (PRT) notes that industry submitted comments that the lack of reserves on a single unit would not pose a reliability issue regarding the need for a periodic review. Any issues involving multiple generating units would be identified as part of an Operational Planning Analysis (OPA) or Real‐Time Assessment (RTA). The PRT affirms that there may be future opportunity to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Sandra Shaffer ‐ Berkshire Hathaway ‐ PacifiCorp ‐ 6 

Answer  No 

Document Name   

Comment 

This question is not clear. 

Likes     0   

Dislikes     0   

Response 

 

Pamela Hunter ‐ Southern Company ‐ Southern Company Services, Inc. ‐ 1,3,5,6 ‐ SERC, Group Name Southern Company 

Answer  No 

Document Name   

Comment 

Not necessarily ‐ this cannot be generally answered. A single unit in an entire interconnect running at it maximum limits should not have an adverse reliability impact. If something like this occurs routinely, it could indicate the need for an overall review of reactive planning in the area. However, the described behavior of the generating unit could be in line with the overall reactive plan for that area. 

Likes     0   

Dislikes     0   

Page 30: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    30 

Response 

Thank you for your comment. The periodic review team (PRT) notes that industry submitted comments that the lack of reserves on a single unit would not pose a reliability issue regarding the need for a periodic review. Any issues involving multiple generating units would be identified as part of an Operational Planning Analysis (OPA) or Real‐Time Assessment (RTA). The PRT affirms that there may be future opportunity to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Sean Bodkin ‐ Dominion ‐ Dominion Resources, Inc. ‐ 3,5,6 

Answer  No 

Document Name   

Comment 

Any impact on the system would be highly dependent on the specific system characteristics as well as the specific unit characteristics. A large unit near a critical interface has more impact than a small unit attached to a very strong network. This issue should not be addressed in a continent wide reliability standard. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) notes that industry submitted comments that the lack of reserves on a single unit would not pose a reliability issue regarding the need for a periodic review. Any issues involving multiple generating units would be identified as part of an Operational Planning Analysis (OPA) or Real‐Time Assessment (RTA). The PRT affirms that there may be future opportunity to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Preston Walker ‐ PJM Interconnection, L.L.C. ‐ 2 ‐ RF 

Answer  No 

Document Name   

Comment 

Page 31: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    31 

Any impact on the system would be highly dependent on the specific system characteristics as well as the specific unit characteristics. A large unit near a critical interface has more impact than a small unit attached to a very strong network. This issue should not be addressed in a continent wide reliability standard. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) notes that industry submitted comments that the lack of reserves on a single unit would not pose a reliability issue regarding the need for a periodic review. Any issues involving multiple generating units would be identified as part of an Operational Planning Analysis (OPA) or Real‐Time Assessment (RTA). The PRT affirms that there may be future opportunity to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Colby Bellville ‐ Duke Energy ‐ 1,3,5,6 ‐ FRCC,SERC,RF, Group Name Duke Energy  

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Michael Cruz‐Montes ‐ CenterPoint Energy Houston Electric, LLC ‐ 1 ‐ Texas RE 

Answer  No 

Document Name   

Comment 

Page 32: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    32 

 

Likes     0   

Dislikes     0   

Response 

 

David Jendras ‐ Ameren ‐ Ameren Services ‐ 1,3,6 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Jesus Sammy Alcaraz ‐ Imperial Irrigation District ‐ 1 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Page 33: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    33 

Dennis Chastain ‐ Tennessee Valley Authority ‐ 1,3,5,6 ‐ SERC 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Glen Farmer ‐ Avista ‐ Avista Corporation ‐ 1,3,5 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Richard Jackson ‐ U.S. Bureau of Reclamation ‐ 1,5 

Answer  Yes 

Document Name   

Comment 

Page 34: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    34 

Reclamation asserts there are serveral variables to consider. Reclamation considers routinely operating all generating units at the maximum limits to be an undesirable practice because it removes available reactive margin to respond to a grid event. The TOP, as the entity with the area‐wide purview, should be aware of other available equipment (for adequate reactive reserves), and would need the flexibility to develop voltage schedules accordingly. If System design limits dictate the need for a voltage schedule which requires routinely running the generating units at maximum limits, the design should be modified to allow units to have more reactive reserve capability. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) notes that industry submitted comments that the lack of reserves on a single unit would not pose a reliability issue regarding the need for a periodic review. Any issues involving multiple generating units would be identified as part of an Operational Planning Analysis (OPA) or Real‐Time Assessment (RTA). The PRT affirms that there may be future opportunity to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Brian Van Gheem ‐ ACES Power Marketing ‐ 6 ‐ NA ‐ Not Applicable, Group Name ACES Standards Collaborators 

Answer  Yes 

Document Name   

Comment 

The question is ambiguous and does not provide sufficient background regarding the system’s current conditions and configurations for proper context. Furthermore, the question assumes that the generator is the sole source for reactive reserves in the local region. However, we believe TOP‐required Real Time Assessments and Operational Planning Analyses, as well as annual TP‐required Planning Assessments, would already identify areas where additional infrastructure would be necessary to address potential voltage and reactive reserves issues. 

Likes     0   

Dislikes     0   

Page 35: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    35 

Response 

Thank you for your comment. The periodic review team (PRT) notes that industry submitted comments that the lack of reserves on a single unit would not pose a reliability issue regarding the need for a periodic review. Any issues involving multiple generating units would be identified as part of an Operational Planning Analysis (OPA) or Real‐Time Assessment (RTA). The PRT affirms that there may be future opportunity to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Rachel Coyne ‐ Texas Reliability Entity, Inc. ‐ 10 

Answer  Yes 

Document Name   

Comment 

Generation routinely running at maximum reactive output is an indicator of insufficient reactive infrastructure support in the surrounding system. Voltage collapse or voltage degradation can result in load loss or equipment damage. Planning studies should encompass periodic corrections for inductive load growth. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) notes that industry submitted comments that the lack of reserves on a single unit would not pose a reliability issue regarding the need for a periodic review. Any issues involving multiple generating units would be identified as part of an Operational Planning Analysis (OPA) or Real‐Time Assessment (RTA). The PRT affirms that there may be future opportunity to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Aubrey Short ‐ FirstEnergy ‐ FirstEnergy Corporation ‐ 1,3,4 

Answer  Yes 

Document Name   

Comment 

Page 36: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    36 

In a circumstance where numerous generators (not specified within the question) were operating at their VAR limits there would be potential for some impact on the reliability of the system. The systems, capability to react to an event would render the local area with the highest risk. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) notes that industry submitted comments that the lack of reserves on a single unit would not pose a reliability issue regarding the need for a periodic review. Any issues involving multiple generating units would be identified as part of an Operational Planning Analysis (OPA) or Real‐Time Assessment (RTA). The PRT affirms that there may be future opportunity to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Laura Nelson ‐ IDACORP ‐ Idaho Power Company ‐ 1 

Answer  Yes 

Document Name   

Comment 

This would impact reliability, which is why we do not operate this way. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. 

Aaron Cavanaugh ‐ Bonneville Power Administration ‐ 1,3,5,6 ‐ WECC 

Answer  Yes 

Document Name   

Page 37: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    37 

Comment 

BPA believes it depends on whether the voltage schedule would place the whole plant or multiple plants under stress. The wide area risk would not be significant for a single unit operating at reactive limits. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) notes that industry submitted comments that the lack of reserves on a single unit would not pose a reliability issue regarding the need for a periodic review. Any issues involving multiple generating units would be identified as part of an Operational Planning Analysis (OPA) or Real‐Time Assessment (RTA). The PRT affirms that there may be future opportunity to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Julie Hall ‐ Entergy ‐ 6, Group Name Entergy/NERC Compliance 

Answer  Yes 

Document Name   

Comment 

Entergy expressed concerns that there is not a feedback loop between the TOP and GOP to raise concerns for issues with the voltage schedule – this should be allowed by the standard. If a generating unit is struggling ot meet its voltage schedule, it would also not have margin left for dynamic reserves. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) notes that industry submitted comments that the lack of reserves on a single unit would not pose a reliability issue regarding the need for a periodic review. Any issues involving multiple generating units would 

Page 38: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    38 

be identified as part of an Operational Planning Analysis (OPA) or Real‐Time Assessment (RTA). The PRT affirms that there may be future opportunity to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Karie Barczak ‐ DTE Energy ‐ Detroit Edison Company ‐ 3,4,5, Group Name DTE Energy ‐ DTE Electric 

Answer  Yes 

Document Name   

Comment 

If additional reactive is needed for BES operation, the generator will not be able to assist in suppling additional reactive. If the generator is routinely running at maximum limits, system upgrades need to be performed such as installation of additional capacitiors. This should be addressed with the TOP yearly review of the Voltage Schedules. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) notes that industry submitted comments that the lack of reserves on a single unit would not pose a reliability issue regarding the need for a periodic review. Any issues involving multiple generating units would be identified as part of an Operational Planning Analysis (OPA) or Real‐Time Assessment (RTA). The PRT affirms that there may be future opportunity to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Michelle Amarantos ‐ APS ‐ Arizona Public Service Co. ‐ 1,3,5,6 

Answer  Yes 

Document Name   

Comment 

A lack of dynamic reactive reserves could have a reliability impact if the TOP system is depending upon the generator to provide VAR support during transients to maintain reliability. However, the TOPs study work should identify this condition in advance. 

Likes     0   

Page 39: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    39 

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) notes that industry submitted comments that the lack of reserves on a single unit would not pose a reliability issue regarding the need for a periodic review. Any issues involving multiple generating units would be identified as part of an Operational Planning Analysis (OPA) or Real‐Time Assessment (RTA). The PRT affirms that there may be future opportunity to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Thomas Foltz ‐ AEP ‐ 3,5 

Answer  Yes 

Document Name   

Comment 

While a potential lack of dynamic reserves for a single unit may not have far‐reaching impacts, a wide‐scale lack of dynamic reserves could very well have an impact on reliability. Voltage schedules should be developed to allow a unit to have dynamic reserves available under normal conditions to respond to contingencies or disturbances. If a unit is hitting limits on reactive capability, the GOP and TOP should work together to resolve the issue (for example, voltage schedule change, exemptions, GSU tap changes, auxiliary transformer tap changes, etc.). 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) notes that industry submitted comments that the lack of reserves on a single unit would not pose a reliability issue regarding the need for a periodic review. Any issues involving multiple generating units would be identified as part of an Operational Planning Analysis (OPA) or Real‐Time Assessment (RTA). The PRT affirms that there may be future opportunity to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Hien Ho ‐ Tacoma Public Utilities (Tacoma, WA) ‐ 1,3,4,5,6 

Answer  Yes 

Page 40: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    40 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Gregory Campoli ‐ New York Independent System Operator ‐ 2, Group Name ISO/RTO Standards Review Committee 

Answer   

Document Name   

Comment 

We do not fully understand the question since the term “lack of dynamic reactive reserve” needs to be clarified wrt whether it means:

a.      Lack of dynamic reactive reserve capability? 

b.     Lack of dynamic reactive reserve requirements? 

c.      Both 

Not knowing the exact meaning of the term, we are unable to provide relevant comment wrt whether or not the lack of any of the above can have a reliability impact.  

In general, we hold the view that if there are dynamic reactive reserve requirements, then they need to be met by having sufficient dynamic reactive reserve capability. Hence, the lack of dynamic reactive requirements does not have any reliability impact. On the other hand, the lack of dynamic reactive reserve capability may have a reliability impact; it depends on whether or not there are any dynamic reactive reserve requirements. 

Page 41: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    41 

             Footnote: ERCOT does not support the joint response provided.

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) notes that industry submitted comments that the lack of reserves on a single unit would not pose a reliability issue regarding the need for a periodic review. Any issues involving multiple generating units would be identified as part of an Operational Planning Analysis (OPA) or Real‐Time Assessment (RTA). The PRT affirms that there may be future opportunity to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Chris Scanlon ‐ Exelon ‐ 1,3,5,6 

Answer   

Document Name   

Comment 

Difficult to answer at the unit level. A reasonable presumption is that if a unit is always at the max point then the unit is not able to supply dynamic support but the TOP is in a position to know if that is a concern.  

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) notes that industry submitted comments that the lack of reserves on a single unit would not pose a reliability issue regarding the need for a periodic review. Any issues involving multiple generating units would be identified as part of an Operational Planning Analysis (OPA) or Real‐Time Assessment (RTA). The PRT affirms that there may be future opportunity to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Stephanie Burns ‐ International Transmission Company Holdings Corporation ‐ 2 ‐ MRO,SPP RE,RF 

Answer   

Page 42: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    42 

Document Name   

Comment 

Maybe, this is very situational. The TOP would need the discretion to decide what is best for the system for each situation. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) notes that industry submitted comments that the lack of reserves on a single unit would not pose a reliability issue regarding the need for a periodic review. Any issues involving multiple generating units would be identified as part of an Operational Planning Analysis (OPA) or Real‐Time Assessment (RTA). The PRT affirms that there may be future opportunity to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

Page 43: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    43 

3. As of April 1, 2017, there will no longer be any explicit requirements for monitoring or ensuring adequate reactive reserves. Absent of any explicit requirements to monitor or ensure adequate reactive reserves within the IRO, TOP, or VAR standards, is there an impact to reliability? If yes, please explain. 

Preston Walker ‐ PJM Interconnection, L.L.C. ‐ 2 ‐ RF 

Answer  No 

Document Name   

Comment 

The absence of an explicit requirement to monitor reactive reserves does not create a reliability gap. 

The IRO suite of standards requires the RC to perform Operational Analyses and Real‐time Assessments to prevent instability, uncontrolled separation, or Cascading and to ensure prompt action to prevent or mitigate instances of exceeding Interconnection Reliability Operating Limits (IROLs). 

The TOP suite of standards requires the TOP to perform Operational Analyses and Real‐time Assessments to prevent instability, uncontrolled separation, or Cascading and to ensure prompt action to prevent or mitigate instances of exceeding System Operating limits SOLs). 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that recently approved TOP/IRO standards address the issue and that no reliability gap exists. The PRT retained a general recommendation that a future Standards Authorization (SAR) or technical guideline outside of a NERC Reliability Standard could address monitoring reactive reserves as a minority of commenters noted reactive reserves should be monitored. 

Sean Bodkin ‐ Dominion ‐ Dominion Resources, Inc. ‐ 3,5,6 

Page 44: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    44 

Answer  No 

Document Name   

Comment 

The absence of an explicit requirement to monitor reactive reserves does not create a reliability gap. 

The IRO suite of standards requires the RC to perform Operational Analyses and Real‐time Assessments to prevent instability, uncontrolled separation, or Cascading and to ensure prompt action to prevent or mitigate instances of exceeding Interconnection Reliability Operating Limits (IROLs). 

The TOP suite of standards requires the TOP to perform Operational Analyses and Real‐time Assessments to prevent instability, uncontrolled separation, or Cascading and to ensure prompt action to prevent or mitigate instances of exceeding System Operating limits SOLs). 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that recently approved TOP/IRO standards address the issue and that no reliability gap exists. The PRT retained a general recommendation that a future Standards Authorization (SAR) or technical guideline outside of a NERC Reliability Standard could address monitoring reactive reserves as a minority of commenters noted reactive reserves should be monitored. 

Pamela Hunter ‐ Southern Company ‐ Southern Company Services, Inc. ‐ 1,3,5,6 ‐ SERC, Group Name Southern Company 

Answer  No 

Document Name   

Comment 

Page 45: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    45 

No, TPL‐001‐4 covers this. In addition, reactive reserve requirements are generally specific to each region or locale, and each TOP is best‐qualified to determine those requirements within their respective transmission systems. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that recently approved TOP/IRO standards address the issue and that no reliability gap exists. While the PRT agrees that TPL‐001‐4 will identify any stability issues that may manifest as a result of reactive reserve deficiencies, VAR‐001‐4.1 focuses on the operations time horizon. The PRT retained a general recommendation that a future Standards Authorization (SAR) or technical guideline outside of a NERC Reliability Standard could address monitoring reactive reserves as a minority of commenters noted reactive reserves should be monitored. Any future effort will have the flexibility to identify the appropriate entity (e.g., TOP). 

Chris Scanlon ‐ Exelon ‐ 1,3,5,6 

Answer  No 

Document Name   

Comment 

IRO and TOP standards are sufficient to address this. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that recently approved TOP/IRO standards address the issue and that no reliability gap exists. The PRT retained a 

Page 46: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    46 

general recommendation that a future Standards Authorization (SAR) or technical guideline outside of a NERC Reliability Standard could address monitoring reactive reserves as a minority of commenters noted reactive reserves should be monitored.

Sandra Shaffer ‐ Berkshire Hathaway ‐ PacifiCorp ‐ 6 

Answer  No 

Document Name   

Comment 

Monitoring and operations are covered by other NERC Reliaiblity standaads such as TOPs. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that recently approved TOP/IRO standards address the issue and that no reliability gap exists. The PRT retained a general recommendation that a future Standards Authorization (SAR) or technical guideline outside of a NERC Reliability Standard could address monitoring reactive reserves as a minority of commenters noted reactive reserves should be monitored.

Ruida Shu ‐ Northeast Power Coordinating Council ‐ 1,2,3,4,5,6,7,8,9,10 ‐ NPCC, Group Name RSC no ISO‐NE 

Answer  No 

Document Name   

Comment 

There are requirements to remain within limits post contingency. Operators would be aware of reactive reserve deficiencies if a plan cannot be developed to maintain the system within voltage limits post contingency. See TOP‐002‐4 R2, TOP‐004‐2 R1 and TOP‐006‐2 R3. 

Page 47: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    47 

Therefore monitoring is being done. Additionaly it may be impossible to “ensure” adequate reactive reserves if the planning process did not provide adequate reserves. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that recently approved TOP/IRO standards address the issue and that no reliability gap exists. The PRT retained a general recommendation that a future Standards Authorization (SAR) or technical guideline outside of a NERC Reliability Standard could address monitoring reactive reserves as a minority of commenters noted reactive reserves should be monitored. 

Russel Mountjoy ‐ Midwest Reliability Organization ‐ 10 

Answer  No 

Document Name   

Comment 

Reactive reserves adequacy is addressed in the Real‐time and next day Operating studies. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that recently approved TOP/IRO standards (Operational Planning Analysis) and Real‐time Assessments (RTA) address the issue and that no reliability gap exists. The PRT retained a general recommendation that a future Standards Authorization (SAR) or technical guideline outside of a NERC Reliability Standard could address monitoring reactive reserves as a minority of commenters noted reactive reserves should be monitored. 

Colby Bellville ‐ Duke Energy ‐ 1,3,5,6 ‐ FRCC,SERC,RF, Group Name Duke Energy  

Page 48: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    48 

Answer  No 

Document Name   

Comment 

Duke Energy does not believe that the lack of requirments for monitoring of reactive resources impacts reliability. An effective operator will already be aware of reactive reserves, and adequacy of reactive reserves is covered by Real‐time assessments already. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that recently approved TOP/IRO standards address the issue and that no reliability gap exists. The PRT retained a general recommendation that a future Standards Authorization (SAR) or technical guideline outside of a NERC Reliability Standard could address monitoring reactive reserves as a minority of commenters noted reactive reserves should be monitored. 

Shannon Mickens ‐ Southwest Power Pool, Inc. (RTO) ‐ 2 ‐ SPP RE, Group Name SPP Standards Review Group 

Answer  No 

Document Name   

Comment 

The SPP Review Group agrees with the TOP/IRO mapping document that provides supportive details addressing monitoring adequate reactive reserves in the VAR Standards. However, we recommend that the drafting team include the mapping document in future resource materials to provide clarity on these type of discussions. 

Likes     0   

Dislikes     0   

Response 

Page 49: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    49 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that recently approved TOP/IRO standards address the issue and that no reliability gap exists. The PRT retained a general recommendation that a future Standards Authorization (SAR) or technical guideline outside of a NERC Reliability Standard could address monitoring reactive reserves as a minority of commenters noted reactive reserves should be monitored. 

Brian Van Gheem ‐ ACES Power Marketing ‐ 6 ‐ NA ‐ Not Applicable, Group Name ACES Standards Collaborators 

Answer  No 

Document Name   

Comment 

We believe other reliability requirements in place to conduct Real Time Assessments and Operational Planning Analyses already address these concerns. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that recently approved TOP/IRO standards address the issue and that no reliability gap exists. The PRT retained a general recommendation that a future Standards Authorization (SAR) or technical guideline outside of a NERC Reliability Standard could address monitoring reactive reserves as a minority of commenters noted reactive reserves should be monitored. 

Richard Jackson ‐ U.S. Bureau of Reclamation ‐ 1,5 

Answer  No 

Document Name   

Comment 

Reclamation supports that the absence of explicit requirements for monitoring or ensuring adequate reactive reserves does not in itself impact reliability; however, the absence of adequate reactive reserves would impact reliability. Reclamation contends that ensuring 

Page 50: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    50 

sufficient var capacity is quite difficult outside of requiring AVRs and sufficient amounts of spinning reserve. In order to ensure adequate reactive reserves, Reclamation suggests that an explicit requirement be retained. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that recently approved TOP/IRO standards address the issue and that no reliability gap exists. The PRT retained a general recommendation that a future Standards Authorization (SAR) or technical guideline outside of a NERC Reliability Standard could address monitoring reactive reserves as a minority of commenters noted reactive reserves should be monitored. 

Glen Farmer ‐ Avista ‐ Avista Corporation ‐ 1,3,5 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Dennis Chastain ‐ Tennessee Valley Authority ‐ 1,3,5,6 ‐ SERC 

Answer  No 

Document Name   

Comment 

 

Page 51: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    51 

Likes     0   

Dislikes     0   

Response 

 

Michelle Amarantos ‐ APS ‐ Arizona Public Service Co. ‐ 1,3,5,6 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Jesus Sammy Alcaraz ‐ Imperial Irrigation District ‐ 1 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Michael Cruz‐Montes ‐ CenterPoint Energy Houston Electric, LLC ‐ 1 ‐ Texas RE 

Page 52: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    52 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Gregory Campoli ‐ New York Independent System Operator ‐ 2, Group Name ISO/RTO Standards Review Committee 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Hien Ho ‐ Tacoma Public Utilities (Tacoma, WA) ‐ 1,3,4,5,6 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Page 53: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    53 

Dislikes     0   

Response 

 

Thomas Foltz ‐ AEP ‐ 3,5 

Answer  Yes 

Document Name   

Comment 

From an overall situational awareness point of view, there should be a mechanism to monitor reactive reserve capabilities. While we agree there needs to be an awareness, it is unclear what “adequate” reactive reserves mean. If voltage contingencies in your Real Time Assessment are being monitored, operating plans should be developed for any potential SOL’s. While we believe that there should be a requirement for monitoring reactive reserves, the diversity in the renewable generation mix makes modeling of the reserve units more complex. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that recently approved TOP/IRO standards address the issue and that no reliability gap exists. The PRT retained a general recommendation that a future Standards Authorization (SAR) or technical guideline outside of a NERC Reliability Standard could address monitoring reactive reserves as a minority of commenters noted reactive reserves should be monitored. 

Karie Barczak ‐ DTE Energy ‐ Detroit Edison Company ‐ 3,4,5, Group Name DTE Energy ‐ DTE Electric 

Answer  Yes 

Document Name   

Comment 

Page 54: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    54 

Reactive reserves must be available to support the reliable operation of the BES. The TOP must be required to know the status of reactive reserves at all times. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that recently approved TOP/IRO standards address the issue and that no reliability gap exists. The PRT retained a general recommendation that a future Standards Authorization (SAR) or technical guideline outside of a NERC Reliability Standard could address monitoring reactive reserves as a minority of commenters noted reactive reserves should be monitored. 

Julie Hall ‐ Entergy ‐ 6, Group Name Entergy/NERC Compliance 

Answer  Yes 

Document Name   

Comment 

Entergy agrees, monitoring reactive reserves is part of the purpose of this standard but is not addressed by any requirements. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that recently approved TOP/IRO standards address the issue and that no reliability gap exists. The PRT retained a general recommendation that a future Standards Authorization (SAR) or technical guideline outside of a NERC Reliability Standard could address monitoring reactive reserves as a minority of commenters noted reactive reserves should be monitored. 

Aaron Cavanaugh ‐ Bonneville Power Administration ‐ 1,3,5,6 ‐ WECC 

Answer  Yes 

Page 55: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    55 

Document Name   

Comment 

In lieu of RTCA voltage stablility analysis, BPA believes an explicit requirement for monitoring is necessary. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that recently approved TOP/IRO standards address the issue and that no reliability gap exists. The PRT retained a general recommendation that a future Standards Authorization (SAR) or technical guideline outside of a NERC Reliability Standard could address monitoring reactive reserves as a minority of commenters noted reactive reserves should be monitored. 

Stephanie Burns ‐ International Transmission Company Holdings Corporation ‐ 2 ‐ MRO,SPP RE,RF 

Answer  Yes 

Document Name   

Comment 

One could argue that VAR‐001‐4.1 R2, the RTA, and the OPA work to ensure adequate reactive reserves. However, there are no requirements for monitoring reactive reserves. For many TOPs, there are not frequent reactive reserve issues. Therefore, it is often not given adequate attention. A lack of frequent reactive reserve issues may lead some to discount their importance. Lack of awareness of reactive reserves is a common factor during voltage collapse events. 

Not requiring that any party monitor reactive reserves (in real‐time) impacts relaibilty. Furthermore, the TOP is the appropriate party to monitor reactive reserves. A requirement to monitor reactive reserves would fit well within the VAR‐001 standard. 

Likes     0   

Dislikes     0   

Page 56: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    56 

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that recently approved TOP/IRO standards address the issue and that no reliability gap exists. The PRT retained a general recommendation that a future Standards Authorization (SAR) or technical guideline outside of a NERC Reliability Standard could address monitoring reactive reserves as a minority of commenters noted reactive reserves should be monitored. Any future effort will have the flexibility to identify the appropriate entity (e.g., TOP). 

David Jendras ‐ Ameren ‐ Ameren Services ‐ 1,3,6 

Answer  Yes 

Document Name   

Comment 

With no requirements to monitor or ensure adequate reactive reserves within the IRO, TOP, or VAR standards, there is a risk of falling below adequate resources and not being aware. Were this to occur and an initiating even occurred, it could be too late to acquire such resources. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that recently approved TOP/IRO standards address the issue and that no reliability gap exists. The PRT retained a general recommendation that a future Standards Authorization (SAR) or technical guideline outside of a NERC Reliability Standard could address monitoring reactive reserves as a minority of commenters noted reactive reserves should be monitored. 

Aubrey Short ‐ FirstEnergy ‐ FirstEnergy Corporation ‐ 1,3,4 

Answer  Yes 

Document Name   

Page 57: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    57 

Comment 

Primary reliance on TO’s to accurately report VAR reserves absent a specific requirement could negatively impact accurate knowledge of VAR reserves available on the system and create the potential to impact reliability. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that recently approved TOP/IRO standards address the issue and that no reliability gap exists. The PRT retained a general recommendation that a future Standards Authorization (SAR) or technical guideline outside of a NERC Reliability Standard could address monitoring reactive reserves as a minority of commenters noted reactive reserves should be monitored. 

Elizabeth Axson ‐ Electric Reliability Council of Texas, Inc. ‐ 2 

Answer  Yes 

Document Name   

Comment 

MVAR or Reactive reserves should be monitored to ensure pre and post contingency voltage stability. With many entities having real time / online voltage stability monitoring tools, MVAR reserves can be monitored in terms of MW flows along an interface. So, if all reactive zones are either monitored via real time / next day voltage stability limit calculating tools (i.e. an SOL exists for each zone) OR thermal constraints (Facility Ratings) are always more limiting than Voltage stability limits, then it would not impact reliability. OPA and RTA is predicated on evaluation for SOL exceedances, so if there is not an SOL that represents a reactive zone/area, then there is potential for voltage stability issues if MVAR reserves is not monitored in its stead. Voltage instability and reactive reserve deficiencies were contributing causes to the 2003 Northeast Blackout. 

Likes     0   

Dislikes     0   

Page 58: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    58 

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that recently approved TOP/IRO standards address the issue and that no reliability gap exists. The PRT retained a general recommendation that a future Standards Authorization (SAR) or technical guideline outside of a NERC Reliability Standard could address monitoring reactive reserves as a minority of commenters noted reactive reserves should be monitored. 

Laura Nelson ‐ IDACORP ‐ Idaho Power Company ‐ 1 

Answer   

Document Name   

Comment 

N/A 

Likes     0   

Dislikes     0   

Response 

 

Rachel Coyne ‐ Texas Reliability Entity, Inc. ‐ 10 

Answer   

Document Name   

Comment 

Texas RE is concerned the entity will have too much leeway in determining its reactive reserves. TOPs need to understand its voltage levels. The TOPs need to have the ability to accurately assess current voltage control capability in order to take proper action during abnormal voltage conditions. 

Likes     0   

Page 59: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    59 

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that recently approved TOP/IRO standards address the issue and that no reliability gap exists. The PRT retained a general recommendation that a future Standards Authorization (SAR) or technical guideline outside of a NERC Reliability Standard could address monitoring reactive reserves as a minority of commenters noted reactive reserves should be monitored.    

Page 60: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    60 

4. As VAR‐001‐4.1 Requirement R5, Part 5.2 is silent with regards to a time duration that a generator can be outside of voltage schedule before notification is required. If the TOP is not required to specify the timing portion of the notification requirements while maintaining the necessary flexibility, is there an impact to reliability? If yes, please explain. 

Elizabeth Axson ‐ Electric Reliability Council of Texas, Inc. ‐ 2 

Answer  No 

Document Name   

Comment 

TOP‐003 already provides a mechanism for TOPs to notify GOPs of duration requirements. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Template document to capture comments that VAR‐001 Requirement 5.2 allows the flexibility to specify a time duration, requiring a time duration would be prescriptive, and that there may be future opportunity to provide technical guidance outside of a Reliability Standard. 

Richard Jackson ‐ U.S. Bureau of Reclamation ‐ 1,5 

Answer  No 

Document Name   

Comment 

Reclamation asserts it is appropriate to allow the TOP to determine whether to specify a timing portion of the notification requirement. 

Likes     0   

Dislikes     0   

Page 61: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    61 

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Template document to capture comments that VAR‐001 Requirement 5.2 allows the flexibility to specify a time duration, requiring a time duration would be prescriptive, and that there may be future opportunity to provide technical guidance outside of a Reliability Standard. 

Brian Van Gheem ‐ ACES Power Marketing ‐ 6 ‐ NA ‐ Not Applicable, Group Name ACES Standards Collaborators 

Answer  No 

Document Name   

Comment 

The question is ambiguous. The TOP is already required to specify a duration when a GOP deviates outside the required range or tolerance band. We assume the question asks how soon after the initial deviation occurs that the GOP must notify the TOP. If so, we believe System Operators who monitor the BES will likely be notified by EMS alarms first for significant deviations causing a reliability impact. For other deviations, the TOP has followed best practices and established a notification requirement for the GOP, as part of the timing duration requirement. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Template document to capture comments that VAR‐001 Requirement 5.2 allows the flexibility to specify a time duration, requiring a time duration would be prescriptive, and that there may be future opportunity to provide technical guidance outside of a Reliability Standard.  VAR‐001 R5.2 does not require a time duration for which it is acceptable for the GOP to be outside of the schedule, then return to within the schedule, but not be required to notify the TOP. 

Shannon Mickens ‐ Southwest Power Pool, Inc. (RTO) ‐ 2 ‐ SPP RE, Group Name SPP Standards Review Group 

Answer  No 

Document Name   

Page 62: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    62 

Comment 

We have no concerns that the TOP notification to the GOP doesn’t contain a timing limit for the generator in Part 5.2 of the standard. The TOP’s responsibility to provide the GOP with notification requirements would reasonably include the timing of such notifications. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Template document to capture comments that VAR‐001 Requirement 5.2 allows the flexibility to specify a time duration, requiring a time duration would be prescriptive, and that there may be future opportunity to provide technical guidance outside of a Reliability Standard. 

Colby Bellville ‐ Duke Energy ‐ 1,3,5,6 ‐ FRCC,SERC,RF, Group Name Duke Energy  

Answer  No 

Document Name   

Comment 

Duke Energy does not believe that the absence of a requirement outlining a time duration that a generator can be outside of the voltage schedule before notification is required presents a clear impact to reliability. From a reliability standpoint, there are already standards that require the TOP to monitor SOL limits. In doing so, a TOP would be notified based on monitoring of SOL(s) whether a GOP sent notification or not. We believe this mitigates any potential issue pertaining to reliability of the system. We do feel that additional guidance around this topic may be useful to industry stakeholders in the form of a guidelines and technical basis section. 

Likes     0   

Dislikes     0   

Response 

Page 63: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    63 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Template document to capture comments that VAR‐001 Requirement 5.2 allows the flexibility to specify a time duration, requiring a time duration would be prescriptive, and that there may be future opportunity to provide technical guidance outside of a Reliability Standard. 

Russel Mountjoy ‐ Midwest Reliability Organization ‐ 10 

Answer  No 

Document Name   

Comment 

Requirement 5.2 states that the TOP provides the GOP with the notification requirements for deviations from the voltage schedule. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Template document to capture comments that VAR‐001 Requirement 5.2 allows the flexibility to specify a time duration, requiring a time duration would be prescriptive, and that there may be future opportunity to provide technical guidance outside of a Reliability Standard. 

Ruida Shu ‐ Northeast Power Coordinating Council ‐ 1,2,3,4,5,6,7,8,9,10 ‐ NPCC, Group Name RSC no ISO‐NE 

Answer  No 

Document Name   

Comment 

No, the TOP is aware of real time and post contingency voltages and whether the system is or will be within limits. If the system is not or will not be within limits the TOP can call the generator to inquire the status of the AVR or their ability to control to the reactive schedule. 

Likes     0   

Dislikes     0   

Page 64: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    64 

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Template document to capture comments that VAR‐001 Requirement 5.2 allows the flexibility to specify a time duration, requiring a time duration would be prescriptive, and that there may be future opportunity to provide technical guidance outside of a Reliability Standard.   The PRT agrees that if a generator was outside of a voltage schedule, reliability issues would be identified by the TOP by its RTA. If these issues persisted, the TOP has the ability to modify it notification requirements, as needed. 

Aubrey Short ‐ FirstEnergy ‐ FirstEnergy Corporation ‐ 1,3,4 

Answer  No 

Document Name   

Comment 

While the requirement does not specify a timing requirement it is likely implemented in practice. For FirstEnergy, PJM manuals document the notification requirement for when a generator is outside of its voltage schedule and a timing aspect is included. The standard should not mandate a specific time, however, it could generally indicate that the notification must specify an expected timing for the notification. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Template document to capture comments that VAR‐001 Requirement 5.2 allows the flexibility to specify a time duration, requiring a time duration would be prescriptive, and that there may be future opportunity to provide technical guidance outside of a Reliability Standard. 

Chris Scanlon ‐ Exelon ‐ 1,3,5,6 

Answer  No 

Document Name   

Page 65: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    65 

Comment 

We don't believe this has a significant reliability impact, This should be left to the discretion of the TOP and can be detailed in the voltage schedule issued to the GOP if the TOP requires it. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Template document to capture comments that VAR‐001 Requirement 5.2 allows the flexibility to specify a time duration, requiring a time duration would be prescriptive, and that there may be future opportunity to provide technical guidance outside of a Reliability Standard. 

Stephanie Burns ‐ International Transmission Company Holdings Corporation ‐ 2 ‐ MRO,SPP RE,RF 

Answer  No 

Document Name   

Comment 

Relibility may not be affected, but a timing duration that a generator can be outside of a schedule before notification is required can significantly reduce compliance risk for the GOP. This compliance risk does not align with an improvement to reliability. It would be reasonable for NERC to require the TOP specify a time duration before a notification is required by the GOP. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Template document to capture comments that VAR‐001 Requirement 5.2 allows the flexibility to specify a time duration, requiring a time duration would be prescriptive, and that there may be future opportunity to provide technical guidance outside of a Reliability Standard. 

Pamela Hunter ‐ Southern Company ‐ Southern Company Services, Inc. ‐ 1,3,5,6 ‐ SERC, Group Name Southern Company 

Page 66: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    66 

Answer  No 

Document Name   

Comment 

Not necessarily ‐ the TOP has the flexiblity to specify the time frame for any required notification where they determine that timing is critical. R5.2 of VAR‐001‐4.1 is sufficient as it is. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Template document to capture comments that VAR‐001 Requirement 5.2 allows the flexibility to specify a time duration, requiring a time duration would be prescriptive, and that there may be future opportunity to provide technical guidance outside of a Reliability Standard. 

Aaron Cavanaugh ‐ Bonneville Power Administration ‐ 1,3,5,6 ‐ WECC 

Answer  No 

Document Name   

Comment 

If BPA dispatch specified a deviation from the voltage or reactive schedule, it would include a projected time frame.  This is considered an Operating Instruction in accordance with COM‐002‐4. 

Likes     0   

Dislikes     0   

Response 

Page 67: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    67 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Template document to capture comments that VAR‐001 Requirement 5.2 allows the flexibility to specify a time duration, requiring a time duration would be prescriptive, and that there may be future opportunity to provide technical guidance outside of a Reliability Standard. 

Karie Barczak ‐ DTE Energy ‐ Detroit Edison Company ‐ 3,4,5, Group Name DTE Energy ‐ DTE Electric 

Answer  No 

Document Name   

Comment 

There is not an impact to reliability but this issue needs to be addressed for compliance monitoring. The GOP must know how long the voltage can be outside the generator bus schedule. This will assist the auditor when reviewing compliance and assist the GOP in knowing when a self report is required. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Template document to capture comments that VAR‐001 Requirement 5.2 allows the flexibility to specify a time duration, requiring a time duration would be prescriptive, and that there may be future opportunity to provide technical guidance outside of a Reliability Standard. 

Thomas Foltz ‐ AEP ‐ 3,5 

Answer  No 

Document Name   

Comment 

While there may be no significant impact to reliability, not specifying the duration that a unit can be outside the specified band could result in communication issues. For example, this could potentially result in excessive phone calls which could be distracting to both the 

Page 68: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    68 

GOP and TOP. Perhaps the language in the requirement could be changed to suggest examples of what can be included in the notification requirement from the TOP to the GOP.  

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Template document to capture comments that VAR‐001 Requirement 5.2 allows the flexibility to specify a time duration, requiring a time duration would be prescriptive, and that there may be future opportunity to provide technical guidance outside of a Reliability Standard. 

Hien Ho ‐ Tacoma Public Utilities (Tacoma, WA) ‐ 1,3,4,5,6 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Gregory Campoli ‐ New York Independent System Operator ‐ 2, Group Name ISO/RTO Standards Review Committee 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Page 69: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    69 

Dislikes     0   

Response 

 

Michael Cruz‐Montes ‐ CenterPoint Energy Houston Electric, LLC ‐ 1 ‐ Texas RE 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Sandra Shaffer ‐ Berkshire Hathaway ‐ PacifiCorp ‐ 6 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Laura Nelson ‐ IDACORP ‐ Idaho Power Company ‐ 1 

Answer  No 

Page 70: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    70 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Jesus Sammy Alcaraz ‐ Imperial Irrigation District ‐ 1 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Sean Bodkin ‐ Dominion ‐ Dominion Resources, Inc. ‐ 3,5,6 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Page 71: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    71 

Response 

 

Michelle Amarantos ‐ APS ‐ Arizona Public Service Co. ‐ 1,3,5,6 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Preston Walker ‐ PJM Interconnection, L.L.C. ‐ 2 ‐ RF 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Dennis Chastain ‐ Tennessee Valley Authority ‐ 1,3,5,6 ‐ SERC 

Answer  No 

Document Name   

Page 72: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    72 

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Glen Farmer ‐ Avista ‐ Avista Corporation ‐ 1,3,5 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

David Jendras ‐ Ameren ‐ Ameren Services ‐ 1,3,6 

Answer  Yes 

Document Name   

Comment 

If the TOP is not required to specify the timing portion of notifying them of a generator being outside of the voltage schedule and VAR‐002 does not specify such timing for notification, a generator could be outside of the TOP's provided voltage schedule an indefinite amount of time.  We believe that it is obvious that this could have an impact to reliability. 

Page 73: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    73 

Currently the voltage schedule is an hourly average, however, this has nothing to do with notification.  Currently the schedule that we send only indicates, "All such notices to the TOS shall be without intentional delay." If there is no stipulation in 5.2, we envision some GOPs will insist that they have no requirement for notification. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Template document to capture comments that VAR‐001 Requirement 5.2 allows the flexibility to specify a time duration, requiring a time duration would be prescriptive, and that there may be future opportunity to provide technical guidance outside of a Reliability Standard.   The PRT contends that if a generator was outside of a voltage schedule, reliability issues would be identified by the TOP by its RTA. If these issues persisted, the TOP has the ability to modify it notification requirements, as needed. 

Julie Hall ‐ Entergy ‐ 6, Group Name Entergy/NERC Compliance 

Answer  Yes 

Document Name   

Comment 

Agree that the timing portion should be required to be specified by the TOP. Do not agree that this parameter should be prescriptively defined by NERC. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Template document to capture comments that VAR‐001 Requirement 5.2 allows the flexibility to specify a time duration, requiring a time duration would be prescriptive, and that there may be future opportunity to provide technical guidance outside of a Reliability Standard. 

Page 74: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    74 

Rachel Coyne ‐ Texas Reliability Entity, Inc. ‐ 10 

Answer   

Document Name   

Comment 

: Texas is concerned that if there is no timing requirement, there is no control in place to ensure the generator’s reactive schedule is reset back to normal, which could mean an entity could be out of its voltage schedule indefinitely.   Texas RE frequently recommends entities provide timing in notifications so expectations are set.  

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Template document to capture comments that VAR‐001 Requirement 5.2 allows the flexibility to specify a time duration, requiring a time duration would be prescriptive, and that there may be future opportunity to provide technical guidance outside of a Reliability Standard.   The PRT contends that if a generator was outside of a voltage schedule, reliability issues would be identified by the TOP by its RTA. If these issues persisted, the TOP has the ability to modify it notification requirements, as needed.   

5. VAR‐001‐4.1 Requirement R5 does not include the RC as a recipient of voltage or Reactive Power schedules issued to generators. Is there an impact to reliability? If yes, please explain. 

Dennis Chastain ‐ Tennessee Valley Authority ‐ 1,3,5,6 ‐ SERC 

Answer  No 

Document Name   

Page 75: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    75 

Comment 

Provided within a timeframe specified by the RC upon request would be adequate. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that IRO‐010‐2 addresses the issue by allowing the Reliability Coordinator to identify and request such information. Therefore, no reliability gap exists. 

Karie Barczak ‐ DTE Energy ‐ Detroit Edison Company ‐ 3,4,5, Group Name DTE Energy ‐ DTE Electric 

Answer  No 

Document Name   

Comment 

Voltage control is a local issue. The TOP, GOP and DP must be aware and concerned with voltage control. The RC is looking a higher level and at a much larger area where local voltage control should not be a concern. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that IRO‐010‐2 addresses the issue by allowing the Reliability Coordinator to identify and request such information. Therefore, no reliability gap exists. 

Julie Hall ‐ Entergy ‐ 6, Group Name Entergy/NERC Compliance 

Answer  No 

Page 76: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    76 

Document Name   

Comment 

This is already addressed in IRO‐010 and VAR‐001 is not the appropriate place to address this. Entergy disagrees with adding this requirement to VAR‐001. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that IRO‐010‐2 addresses the issue by allowing the Reliability Coordinator to identify and request such information. Therefore, no reliability gap exists. 

Aaron Cavanaugh ‐ Bonneville Power Administration ‐ 1,3,5,6 ‐ WECC 

Answer  No 

Document Name   

Comment 

BPA believes VAR‐001‐4.1, R1.1 ensures that the RC and adjacent TOP’s receive the system voltage schedule on request. BPA believes the IRO‐010 data request would be available for the RC to receive the voltage or Reactive Power schedules. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that IRO‐010‐2 addresses the issue by allowing the Reliability Coordinator to identify and request such information. Therefore, no reliability gap exists. 

Page 77: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    77 

Pamela Hunter ‐ Southern Company ‐ Southern Company Services, Inc. ‐ 1,3,5,6 ‐ SERC, Group Name Southern Company 

Answer  No 

Document Name   

Comment 

 R1.1 of VAR‐001‐4.1 gives the RC the ability to request this information if needed. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that IRO‐010‐2 addresses the issue by allowing the Reliability Coordinator to identify and request such information, even if beyond or different than VAR‐001‐4.1, Requirement R1, Part 1.1. Therefore, no reliability gap exists. 

Stephanie Burns ‐ International Transmission Company Holdings Corporation ‐ 2 ‐ MRO,SPP RE,RF 

Answer  No 

Document Name   

Comment 

The RC can specify this as required data in their documented specification for data from IRO‐010‐2. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that IRO‐010‐2 addresses the issue by allowing the Reliability Coordinator to identify and request such information. Therefore, no reliability gap exists. 

Page 78: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    78 

Chris Scanlon ‐ Exelon ‐ 1,3,5,6 

Answer  No 

Document Name   

Comment 

The RC has other ways of getting this information. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that IRO‐010‐2 addresses the issue by allowing the Reliability Coordinator to identify and request such information. Therefore, no reliability gap exists. 

Sandra Shaffer ‐ Berkshire Hathaway ‐ PacifiCorp ‐ 6 

Answer  No 

Document Name   

Comment 

RC is informed as part of IRO‐010. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that IRO‐010‐2 addresses the issue by allowing the Reliability Coordinator to identify and request such information. Therefore, no reliability gap exists. 

Page 79: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    79 

Ruida Shu ‐ Northeast Power Coordinating Council ‐ 1,2,3,4,5,6,7,8,9,10 ‐ NPCC, Group Name RSC no ISO‐NE 

Answer  No 

Document Name   

Comment 

Per R1.1 the RC can obain a copy of the voltage schedule. Therefore the schedules are available to the RC. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that IRO‐010‐2 addresses the issue by allowing the Reliability Coordinator to identify and request such information, even if beyond or different than VAR‐001‐4.1, Requirement R1, Part 1.1. Therefore, no reliability gap exists. 

Russel Mountjoy ‐ Midwest Reliability Organization ‐ 10 

Answer  No 

Document Name   

Comment 

The TOP is responsible for system operations and reliability. The RC can specify their data needs per IRO‐010‐2. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that IRO‐010‐2 addresses the issue by allowing the Reliability Coordinator to identify and request such information. Therefore, no reliability gap exists. 

Page 80: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    80 

Colby Bellville ‐ Duke Energy ‐ 1,3,5,6 ‐ FRCC,SERC,RF, Group Name Duke Energy  

Answer  No 

Document Name   

Comment 

An RC may already be receiving this information via established agreements with member entities, and can request this information at any time. While having this information may be helpful for the RC, we do not see a real impact to reliability with there not being a requirement to provide the RC with these scehdules. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that IRO‐010‐2 addresses the issue by allowing the Reliability Coordinator to identify and request such information. Therefore, no reliability gap exists. 

Shannon Mickens ‐ Southwest Power Pool, Inc. (RTO) ‐ 2 ‐ SPP RE, Group Name SPP Standards Review Group 

Answer  No 

Document Name   

Comment 

The review group does not find any reliability impact with the RC not receiving the voltage and Reactive Power schedules from the TOP. However as registered RC, SPP finds the data in the schedules to be very valuable to other processes associated with the RC function. For example, this particular data can help increase the accuracy of the network applications as well as the Real‐time Assessment. In our review and interpretation of the IRO Standards, it is our understanding that the IRO‐010‐2 Standard addresses the RC receiving this type of data and eliminating any concerns for reliability issues. 

Likes     0   

Page 81: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    81 

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that IRO‐010‐2 addresses the issue by allowing the Reliability Coordinator to identify and request such information. Therefore, no reliability gap exists. 

Brian Van Gheem ‐ ACES Power Marketing ‐ 6 ‐ NA ‐ Not Applicable, Group Name ACES Standards Collaborators 

Answer  No 

Document Name   

Comment 

By its definition, a TOP is the entity responsible for the reliability of its “local” transmission system.  The issuance of voltage or Reactive Power schedules to generators should be identified as a “local” reliability concern.  We feel the inclusion of the RC as a recipient would be burdensome, particularly when monitoring and assessing the Wide Area view of the BES. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that IRO‐010‐2 addresses the issue by allowing the Reliability Coordinator to identify and request such information. Therefore, no reliability gap exists. 

Gregory Campoli ‐ New York Independent System Operator ‐ 2, Group Name ISO/RTO Standards Review Committee 

Answer  No 

Document Name   

Comment 

Page 82: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    82 

NERC currently has IRO Standards that require RC’s to obtain this information. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that IRO‐010‐2 addresses the issue by allowing the Reliability Coordinator to identify and request such information. Therefore, no reliability gap exists. 

Richard Jackson ‐ U.S. Bureau of Reclamation ‐ 1,5 

Answer  No 

Document Name   

Comment 

Reclamation proposes the TOP should provide the RC with copies of the voltage or Reactive Power schedules issued to generators so that the RC has the appropriate information for analysis and operations. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that IRO‐010‐2 addresses the issue by allowing the Reliability Coordinator to identify and request such information. Therefore, no reliability gap exists. 

Michael Godbout ‐ Hydro‐Québec TransÉnergie ‐ 1 ‐ NPCC 

Answer  No 

Document Name   

Page 83: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    83 

Comment 

We support NPCC's comments. That is, requirement 1.1 provides for an mandatory communication of the schedules to the RC upon the RC's request. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that IRO‐010‐2 addresses the issue by allowing the Reliability Coordinator to identify and request such information, even if beyond or different than VAR‐001‐4.1, Requirement R1, Part 1.1. Therefore, no reliability gap exists. 

Elizabeth Axson ‐ Electric Reliability Council of Texas, Inc. ‐ 2 

Answer  No 

Document Name   

Comment 

IRO‐010 provides the RC the means to get the desired information, if necessary.  

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that IRO‐010‐2 addresses the issue by allowing the Reliability Coordinator to identify and request such information. Therefore, no reliability gap exists. 

Glen Farmer ‐ Avista ‐ Avista Corporation ‐ 1,3,5 

Answer  No 

Page 84: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    84 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Preston Walker ‐ PJM Interconnection, L.L.C. ‐ 2 ‐ RF 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Michelle Amarantos ‐ APS ‐ Arizona Public Service Co. ‐ 1,3,5,6 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Page 85: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    85 

Response 

 

Sean Bodkin ‐ Dominion ‐ Dominion Resources, Inc. ‐ 3,5,6 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Jesus Sammy Alcaraz ‐ Imperial Irrigation District ‐ 1 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Laura Nelson ‐ IDACORP ‐ Idaho Power Company ‐ 1 

Answer  No 

Document Name   

Page 86: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    86 

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Aubrey Short ‐ FirstEnergy ‐ FirstEnergy Corporation ‐ 1,3,4 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Michael Cruz‐Montes ‐ CenterPoint Energy Houston Electric, LLC ‐ 1 ‐ Texas RE 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

Page 87: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    87 

 

Hien Ho ‐ Tacoma Public Utilities (Tacoma, WA) ‐ 1,3,4,5,6 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Thomas Foltz ‐ AEP ‐ 3,5 

Answer  Yes 

Document Name   

Comment 

The RC is required to monitor SOL’s and IROL’s. The information in the voltage/reactive power schedules could, at a minimum, be used to improve the RC’s awareness. While this could potentially have a positive reliability impact, we do not believe VAR‐001 is the proper standard for such an obligation. Rather, we believe IRO‐010‐2 would be more appropriate.  

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that IRO‐010‐2 addresses the issue by allowing the Reliability Coordinator to identify and request such information. Therefore, no reliability gap exists. 

Page 88: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    88 

David Jendras ‐ Ameren ‐ Ameren Services ‐ 1,3,6 

Answer  Yes 

Document Name   

Comment 

In many cases the RC is the Planning Authority for the TOP.  If the RC is not aware of the voltage schedule provided to the generators, this cannot be taken into account for system planning. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that IRO‐010‐2 addresses the issue by allowing the Reliability Coordinator to identify and request such information. Therefore, no reliability gap exists. 

Rachel Coyne ‐ Texas Reliability Entity, Inc. ‐ 10 

Answer   

Document Name   

Comment 

Texas RE suggests it would be prudent for the RC to understand its entities’ voltage and Reactive Power schedules.  Understanding these schedules allow for better planning of reactive resources and, system awareness.  Since the RC has the authority to direct dispatch of generation outside of its voltage or reactive power schedule due to real time concerns or contingencies, it should know it is doing so. Knowledge of normal reactive schedules is a primary means by which an RC can realize the extent of reactively deficient areas. 

Likes     0   

Dislikes     0   

Page 89: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    89 

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that IRO‐010‐2 addresses the issue by allowing the Reliability Coordinator to identify and request such information. Therefore, no reliability gap exists.     

Page 90: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    90 

6. VAR‐001‐4.1 Requirement R5 dictates the status of an AVR. Does the lack of a similar requirement to identify the initial state of the PSS impact reliability? If yes, please explain. 

Brian Van Gheem ‐ ACES Power Marketing ‐ 6 ‐ NA ‐ Not Applicable, Group Name ACES Standards Collaborators 

Answer  No 

Document Name   

Comment 

The question assumes that all generators have a PSS.  This is simply not true.  For those that do, the GOP is already required to notify the TOP of a PSS status change in Requirement R3 of NERC Standard VAR‐002‐4.  This notification is used to identify what is outside normal operation and could affect a generator’s availability. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) appended the recommendation to note that industry comments affirm that it is not necessary to require notification of the initial state of the PSS. Regional practices, interconnection agreements, and data specifications can address the initial state of the PSS; therefore, revising the continent‐wide VAR‐001‐4.1 standard is not necessary. 

Shannon Mickens ‐ Southwest Power Pool, Inc. (RTO) ‐ 2 ‐ SPP RE, Group Name SPP Standards Review Group 

Answer  No 

Document Name   

Comment 

Page 91: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    91 

The SPP Review Group has no concerns with the power system stabilizer (PSS) initial state not being mentioned in this particular requirement. After reviewing VAR‐001 and VAR‐002 Standards, the review group believes that the PSS status change concerns are addressed in VAR‐002‐4 under Requirement R3 and there are no concerns in reference to reliability issues. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) appended the recommendation to note that industry comments affirm that it is not necessary to require notification of the initial state of the PSS. Regional practices, interconnection agreements, and data specifications can address the initial state of the PSS; therefore, revising the continent‐wide VAR‐001‐4.1 standard is not necessary. 

Russel Mountjoy ‐ Midwest Reliability Organization ‐ 10 

Answer  No 

Document Name   

Comment 

The NSRF acknowledges a potential impact on reliability, but only when there is an identified reliability need per the TPL‐001‐4 stability analysis. We agree there is a need to know the initial state.  However, VAR‐002‐4 R3 already requires the GOP to notify the TOP of PSS change.  The TOP can pursue other avenues via a data specification request (TOP‐003‐3 and IRO‐010‐2). 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) appended the recommendation to note that industry comments affirm that it is not necessary to require notification of the initial state of the PSS. Regional practices, interconnection agreements, and data specifications can address the initial state of the PSS; therefore, revising the continent‐wide VAR‐001‐4.1 standard is not necessary. 

Ruida Shu ‐ Northeast Power Coordinating Council ‐ 1,2,3,4,5,6,7,8,9,10 ‐ NPCC, Group Name RSC no ISO‐NE 

Page 92: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    92 

Answer  No 

Document Name   

Comment 

A PSS would only be installed if there was a reliability reason. Presumably when the generator and PSS were commissioned the TOP knew the status. Therefore only notifications of chages to the status are necessary. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) appended the recommendation to note that industry comments affirm that it is not necessary to require notification of the initial state of the PSS. Regional practices, interconnection agreements, and data specifications can address the initial state of the PSS; therefore, revising the continent‐wide VAR‐001‐4.1 standard is not necessary. 

Chris Scanlon ‐ Exelon ‐ 1,3,5,6 

Answer  No 

Document Name   

Comment 

A PSS does not function like an AVR, a PSS is typically not enabled automatically until a certain MWe when ramping a unit up in power and subsequently disabled at a certain MWe on ramping a unit down in power.  Specifying an initial state may not be meaningful. 

Likes     0   

Dislikes     0   

Response 

Page 93: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    93 

Thank you for your comment. The periodic review team (PRT) appended the recommendation to note that industry comments affirm that it is not necessary to require notification of the initial state of the PSS. Regional practices, interconnection agreements, and data specifications can address the initial state of the PSS; therefore, revising the continent‐wide VAR‐001‐4.1 standard is not necessary. 

Stephanie Burns ‐ International Transmission Company Holdings Corporation ‐ 2 ‐ MRO,SPP RE,RF 

Answer  No 

Document Name   

Comment 

It may not be wise for the TOP to dictate the PSS status as part of a NERC standard. However, the TOP should be aware of the PSS status. Perhaps, the GOP should be required to tell the TOP the actual and normal PSS status on an annual basis, in additional to real‐time notification of status changes. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) appended the recommendation to note that industry comments affirm that it is not necessary to require notification of the initial state of the PSS. Regional practices, interconnection agreements, and data specifications can address the initial state of the PSS; therefore, revising the continent‐wide VAR‐001‐4.1 standard is not necessary. 

Pamela Hunter ‐ Southern Company ‐ Southern Company Services, Inc. ‐ 1,3,5,6 ‐ SERC, Group Name Southern Company 

Answer  No 

Document Name   

Comment 

PSS requirements are often already detailed in the interconnection requirements or existing regional requirements.  A PSS is typically set up in such a way it would be automatically turned on/off at pre‐determined MW setpoints when the AVR is in service.  So, with languge on AVR, it will typically also cover the PSS. 

Page 94: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    94 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) appended the recommendation to note that industry comments affirm that it is not necessary to require notification of the initial state of the PSS. Regional practices, interconnection agreements, and data specifications can address the initial state of the PSS; therefore, revising the continent‐wide VAR‐001‐4.1 standard is not necessary. 

Aaron Cavanaugh ‐ Bonneville Power Administration ‐ 1,3,5,6 ‐ WECC 

Answer  No 

Document Name   

Comment 

As BPA is a part of the WECC region, there is already standard VAR‐501‐WECC‐2 with a requirement for PSS to be kept in service. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) appended the recommendation to note that industry comments affirm that it is not necessary to require notification of the initial state of the PSS. Regional practices, interconnection agreements, and data specifications can address the initial state of the PSS; therefore, revising the continent‐wide VAR‐001‐4.1 standard is not necessary. 

Karie Barczak ‐ DTE Energy ‐ Detroit Edison Company ‐ 3,4,5, Group Name DTE Energy ‐ DTE Electric 

Answer  No 

Document Name   

Comment 

Page 95: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    95 

The PSS on many units do not come into service until the unit is on line and loaded to some point. The initial state of the PSS should be considered out of service until documentation provided by the GOP states when the PSS comes into service. Once that point is obtained, the PSS should be considered in service unless notied other wise by the GOP.  

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) appended the recommendation to note that industry comments affirm that it is not necessary to require notification of the initial state of the PSS. Regional practices, interconnection agreements, and data specifications can address the initial state of the PSS; therefore, revising the continent‐wide VAR‐001‐4.1 standard is not necessary. 

Michelle Amarantos ‐ APS ‐ Arizona Public Service Co. ‐ 1,3,5,6 

Answer  No 

Document Name   

Comment 

The PSS status information does not meaningfully impact the TOP.  

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) appended the recommendation to note that industry comments affirm that it is not necessary to require notification of the initial state of the PSS. Regional practices, interconnection agreements, and data specifications can address the initial state of the PSS; therefore, revising the continent‐wide VAR‐001‐4.1 standard is not necessary. 

Hien Ho ‐ Tacoma Public Utilities (Tacoma, WA) ‐ 1,3,4,5,6 

Answer  No 

Page 96: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    96 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Colby Bellville ‐ Duke Energy ‐ 1,3,5,6 ‐ FRCC,SERC,RF, Group Name Duke Energy  

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Michael Cruz‐Montes ‐ CenterPoint Energy Houston Electric, LLC ‐ 1 ‐ Texas RE 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Page 97: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    97 

Response 

 

Aubrey Short ‐ FirstEnergy ‐ FirstEnergy Corporation ‐ 1,3,4 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Sandra Shaffer ‐ Berkshire Hathaway ‐ PacifiCorp ‐ 6 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Laura Nelson ‐ IDACORP ‐ Idaho Power Company ‐ 1 

Answer  No 

Document Name   

Page 98: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    98 

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Jesus Sammy Alcaraz ‐ Imperial Irrigation District ‐ 1 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Sean Bodkin ‐ Dominion ‐ Dominion Resources, Inc. ‐ 3,5,6 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

Page 99: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    99 

 

Preston Walker ‐ PJM Interconnection, L.L.C. ‐ 2 ‐ RF 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Dennis Chastain ‐ Tennessee Valley Authority ‐ 1,3,5,6 ‐ SERC 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Glen Farmer ‐ Avista ‐ Avista Corporation ‐ 1,3,5 

Answer  No 

Document Name   

Comment 

Page 100: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    100 

 

Likes     0   

Dislikes     0   

Response 

 

Elizabeth Axson ‐ Electric Reliability Council of Texas, Inc. ‐ 2 

Answer  Yes 

Document Name   

Comment 

There are instances where the PSS will have an impact on IROL Limits.  PSS desired states should be determined for each generator.  ERCOT has Protocols that identify the necessary coordination.  While this is a best practice, ERCOT sees no need to codify this in a standard.   

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) appended the recommendation to note that industry comments affirm that it is not necessary to require notification of the initial state of the PSS. Regional practices, interconnection agreements, and data specifications can address the initial state of the PSS; therefore, revising the continent‐wide VAR‐001‐4.1 standard is not necessary. 

Richard Jackson ‐ U.S. Bureau of Reclamation ‐ 1,5 

Answer  Yes 

Document Name   

Comment 

Page 101: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    101 

Reclamation contends both AVR and PSS should be addressed in both VAR‐001‐4.1 and VAR‐002‐4. The lack of including PSS creates the need to address PSS in regional variances to ensure grid stability. Reclamation asserts that it is important for PSSs to be required as applicable. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) appended the recommendation to note that industry comments affirm that it is not necessary to require notification of the initial state of the PSS. Regional practices, interconnection agreements, and data specifications can address the initial state of the PSS; therefore, revising the continent‐wide VAR‐001‐4.1 standard is not necessary. 

Gregory Campoli ‐ New York Independent System Operator ‐ 2, Group Name ISO/RTO Standards Review Committee 

Answer  Yes 

Document Name   

Comment 

Impacts on the system would be highly dependent on the specific system characteristics as well as the specific unit characteristics, however There can be instances where the PSS will have an impact on IROL Limits. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) appended the recommendation to note that industry comments affirm that it is not necessary to require notification of the initial state of the PSS. Regional practices, interconnection agreements, and data specifications can address the initial state of the PSS; therefore, revising the continent‐wide VAR‐001‐4.1 standard is not necessary. 

Rachel Coyne ‐ Texas Reliability Entity, Inc. ‐ 10 

Answer  Yes 

Page 102: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    102 

Document Name   

Comment 

Texas RE recommends a similar requirement for the PSS.  Understanding the PSS availability gives a broader view of the system and its ability to damp out instability.  While the PSS is not a reactive resource (it is a real power resource), studies should provide input on which assumptions concerning PSS were used, and whether there should be PSS in‐service requirements for regional generation. If determined dynamically necessary, enough PSSs must be in service regionally to provide the necessary oscillatory damping.  

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) appended the recommendation to note that industry comments affirm that it is not necessary to require notification of the initial state of the PSS. Regional practices, interconnection agreements, and data specifications can address the initial state of the PSS; therefore, revising the continent‐wide VAR‐001‐4.1 standard is not necessary. 

David Jendras ‐ Ameren ‐ Ameren Services ‐ 1,3,6 

Answer  Yes 

Document Name   

Comment 

In many cases system stability is greatly altered with a PSS out of service.  Therefore the initial state of the PSS is very important and should be stipulated. PSS is normally fixed in the firmware of the generator and cannot be changed or altered. 

If a unit is designed such that the initial state of the PSS will be “on” when the unit is first synchronized, that this information can be shared with the TOP in a ONE TIME notification which will inform the TOP that the PSS is always on, unless notified. It is essential that the TOP know the state of the PSS but if the design “forces” the PSS to be on unless otherwise “switched” off and the “switch off” entails notice, then the TOP would know the status. 

Likes     0   

Page 103: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    103 

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) appended the recommendation to note that industry comments affirm that it is not necessary to require notification of the initial state of the PSS. Regional practices, interconnection agreements, and data specifications can address the initial state of the PSS; therefore, revising the continent‐wide VAR‐001‐4.1 standard is not necessary. 

Julie Hall ‐ Entergy ‐ 6, Group Name Entergy/NERC Compliance 

Answer  Yes 

Document Name   

Comment 

Agree that clarity is needed, but this should appear in VAR‐002 R1, not related to VAR‐001 R5. Disagree with putting this content in VAR‐001. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) appended the recommendation to note that industry comments affirm that it is not necessary to require notification of the initial state of the PSS. Regional practices, interconnection agreements, and data specifications can address the initial state of the PSS; therefore, revising the continent‐wide VAR‐001‐4.1 standard is not necessary. 

Thomas Foltz ‐ AEP ‐ 3,5 

Answer  Yes 

Document Name   

Comment 

While Power System Stabilizers are not used on all generating units, a requirement to inform the TOP of the initial state of the PSS may be beneficial for those instances where they are used. That being said, since a Power System Stabilizer does not regulate voltage or reactive 

Page 104: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    104 

power, and, instead, is used to dampen electro‐mechanical oscillations, references to Power System Stabilizers should not be added to VAR‐001. In addition, consideration might also be given to removing PSS references from VAR‐002 as well. It may be worth considering that requirements relating to PSS operation and status be placed in a different standard or technical guide; otherwise, the scope of these standards should be expanded to encompass PSS operation and status.  

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) appended the recommendation to note that industry comments affirm that it is not necessary to require notification of the initial state of the PSS. Regional practices, interconnection agreements, and data specifications can address the initial state of the PSS; therefore, revising the continent‐wide VAR‐001‐4.1 standard is not necessary.      

Page 105: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    105 

7. The continent‐wide VAR standards do not address external control loops to the AVR that may impact the reactive response of a generator. Some external control loops do not have the purpose of automatic voltage control, therefore, is there a need to coordinate external loops to prevent an impact to reliability?[1] If yes, please explain. 

[1] See also: Lesson Learned, Generator Distributed Control System Impact on Automatic Voltage Regulators, June 9, 2015, (http://www.nerc.com/pa/rrm/ea/Lessons Learned Document Library/LL20150602_Generator_Distributed_Control_System_ Impact_on_Automatic_Voltage_Regulators.pdf)  

Karie Barczak ‐ DTE Energy ‐ Detroit Edison Company ‐ 3,4,5, Group Name DTE Energy ‐ DTE Electric 

Answer  No 

Document Name   

Comment 

No comments 

Likes     0   

Dislikes     0   

Response 

 

Julie Hall ‐ Entergy ‐ 6, Group Name Entergy/NERC Compliance 

Answer  No 

Document Name   

Comment 

The "how" of meeting the specifications of the TOP is not the TOP's job to define. This may be a lessons learned to consider these factors in your "net" response. This should be results based and not method determinate. 

Page 106: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    106 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified the Enhanced Periodic Review document to reflect that industry comments did not reveal any reliability related need to address external control loops within the continent‐wide Reliability Standard. 

Pamela Hunter ‐ Southern Company ‐ Southern Company Services, Inc. ‐ 1,3,5,6 ‐ SERC, Group Name Southern Company 

Answer  No 

Document Name   

Comment 

Not necessarily ‐ it depends ‐ at the high speed response level (the inverter) most DGR sites do not employ voltage control ‐ most run in reactive control or PF control.  They respond to commands from the outer loop plant voltage control. The external (plant wide) control loops are slower in response time to what is traditionally considered to be used for system transient voltage conditions.  The external loops can assist with ensuring that the voltage schedule is followed.     

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified the Enhanced Periodic Review document to reflect that industry comments did not reveal any reliability related need to address external control loops within the continent‐wide Reliability Standard. 

Colby Bellville ‐ Duke Energy ‐ 1,3,5,6 ‐ FRCC,SERC,RF, Group Name Duke Energy  

Answer  No 

Document Name   

Comment 

Page 107: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    107 

While external control loops can provide an unintended impact to reliability we do not believe that VAR‐001 is the correct standard to address identifying and correcting these deficiencies. We believe MOD‐025 or MOD‐026 would be a more appropriate standard to identify the need to document and communicate the impact of external control loop actions on the AVR to the TOP. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified the Enhanced Periodic Review document to reflect that industry comments did not reveal any reliability related need to address external control loops within the continent‐wide Reliability Standard. 

Shannon Mickens ‐ Southwest Power Pool, Inc. (RTO) ‐ 2 ‐ SPP RE, Group Name SPP Standards Review Group 

Answer  No 

Document Name   

Comment 

The SPP Review Group has no concerns with control loops not being mentioned in this particular requirement as well as seeing no reliability issues. The status change of the alternative voltage controlling device (control loops) has been addressed in the VAR‐002‐4 Standard under Requirement R3.  

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified the Enhanced Periodic Review document to reflect that industry comments did not reveal any reliability related need to address external control loops within the continent‐wide Reliability Standard. 

Brian Van Gheem ‐ ACES Power Marketing ‐ 6 ‐ NA ‐ Not Applicable, Group Name ACES Standards Collaborators 

Page 108: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    108 

Answer  No 

Document Name   

Comment 

We do not believe there is a need to require coordination of external loops.  Though we thank the Periodic Review Team for reaffirming the importance of this documented NERC lesson learned, we disagree that the occurrence of this singularity necessitates a NERC enforceable requirement.  This would set a precedence for all future NERC Lesson Learned and undermine the intent of that program. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified the Enhanced Periodic Review document to reflect that industry comments did not reveal any reliability related need to address external control loops within the continent‐wide Reliability Standard. 

Richard Jackson ‐ U.S. Bureau of Reclamation ‐ 1,5 

Answer  No 

Document Name   

Comment 

Reclamation contends that VAR‐001‐4.1 should require external control loops to be coordinated. 

Likes     0   

Dislikes     0   

Response 

Page 109: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    109 

Thank you for your comment. The periodic review team (PRT) has modified the Enhanced Periodic Review document to reflect that industry comments did not reveal any reliability related need to address external control loops within the continent‐wide Reliability Standard.  Some commenters identified, and the PRT agrees, that TOP involvement in detailed AVR external controller loop design is outside the scope of VAR‐001. 

Glen Farmer ‐ Avista ‐ Avista Corporation ‐ 1,3,5 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Dennis Chastain ‐ Tennessee Valley Authority ‐ 1,3,5,6 ‐ SERC 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Page 110: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    110 

Preston Walker ‐ PJM Interconnection, L.L.C. ‐ 2 ‐ RF 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Michelle Amarantos ‐ APS ‐ Arizona Public Service Co. ‐ 1,3,5,6 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Sean Bodkin ‐ Dominion ‐ Dominion Resources, Inc. ‐ 3,5,6 

Answer  No 

Document Name   

Comment 

 

Page 111: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    111 

Likes     0   

Dislikes     0   

Response 

 

Jesus Sammy Alcaraz ‐ Imperial Irrigation District ‐ 1 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Aubrey Short ‐ FirstEnergy ‐ FirstEnergy Corporation ‐ 1,3,4 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Michael Cruz‐Montes ‐ CenterPoint Energy Houston Electric, LLC ‐ 1 ‐ Texas RE 

Page 112: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    112 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Russel Mountjoy ‐ Midwest Reliability Organization ‐ 10 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Aaron Cavanaugh ‐ Bonneville Power Administration ‐ 1,3,5,6 ‐ WECC 

Answer  Yes 

Document Name   

Comment 

There are external control loops, like VAR regulators and power factor controllers, that can over‐ride action of generator’s Automatic Voltage Regulator. The action of such controls is one of the contributing factors to the August 10, 1996 Western Interconnection power 

Page 113: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    113 

outage. BPA believes if language were to be included in a Standard revision, it would need to be carefully drafted as it may become too prescriptive, requiring expensive equipment replacements. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified the Enhanced Periodic Review document to reflect that industry comments did not reveal any reliability related need to address external control loops within the continent‐wide Reliability Standard. 

Stephanie Burns ‐ International Transmission Company Holdings Corporation ‐ 2 ‐ MRO,SPP RE,RF 

Answer  Yes 

Document Name   

Comment 

Both GOP and TOP need to understand how a generator is going to control voltage. Requiring that the GOP understand and document any external control schemes lends itself to improving reliability. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified the Enhanced Periodic Review document to reflect that industry comments did not reveal any reliability related need to address external control loops within the continent‐wide Reliability Standard. 

David Jendras ‐ Ameren ‐ Ameren Services ‐ 1,3,6 

Answer  Yes 

Document Name   

Page 114: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    114 

Comment 

If the AVR response is altered due to external control loops, this needs to be taken into account.  The purpose of VAR‐001 in its entirety is for the TOP to understand the VAR resources available from each generator.  If the resource availability is altered due to something other than automatic voltage control, the TOP needs to be aware of it and also have the latitude to request removal of the loop if it is not for the protection of the unit, transmission system or equipment on which either is dependent. 

AVR is required to operate in auto if not a notification is required per VAR‐002.  

We are concerned that even though the AVR could stay in auto, an external control loop might impact the reactive response of the generator.  We believe that this could, in effect, defeat the purpose of the AVR to control the voltage as mandated.  

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified the Enhanced Periodic Review document to reflect that industry comments did not reveal any reliability related need to address external control loops within the continent‐wide Reliability Standard.  Some commenters identified, and the PRT agrees, that TOP involvement in detailed AVR external controller loop design is outside the scope of VAR‐001. 

Gregory Campoli ‐ New York Independent System Operator ‐ 2, Group Name ISO/RTO Standards Review Committee 

Answer  Yes 

Document Name   

Comment 

Page 115: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    115 

If there are external controls loops that could override the AVR and limit the reactive output, some level of coordination or notification should be required. Plant owners need to be diligent that external control loops do not counteract the primary function of excitation or governor control. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) has modified the Enhanced Periodic Review document to reflect that industry comments did not reveal any reliability related need to address external control loops within the continent‐wide Reliability Standard.  Some commenters identified, and the PRT agrees, that TOP involvement in detailed AVR external controller loop design is outside the scope of VAR‐001. 

Elizabeth Axson ‐ Electric Reliability Council of Texas, Inc. ‐ 2 

Answer  Yes 

Document Name   

Comment 

If there are external controls loops that could override the AVR and limit the reactive output, some level of coordination or notification is appropriate.  However, this does not necessarily require modification to a standard. 

Likes     0   

Dislikes     0   

Response 

Page 116: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    116 

Thank you for your comment. The periodic review team (PRT) has modified the Enhanced Periodic Review document to reflect that industry comments did not reveal any reliability related need to address external control loops within the continent‐wide Reliability Standard. 

Laura Nelson ‐ IDACORP ‐ Idaho Power Company ‐ 1 

Answer   

Document Name   

Comment 

N/A 

Likes     0   

Dislikes     0   

Response 

 

Rachel Coyne ‐ Texas Reliability Entity, Inc. ‐ 10 

Answer   

Document Name   

Comment 

Texas RE recommends external control loops (for example, PSS) that have an affect on AVR operations should be considered in planning studies to alleviate impacts to reliability.  

Likes     0   

Dislikes     0   

Response 

Page 117: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    117 

Thank you for your comment. The periodic review team (PRT) has modified the Enhanced Periodic Review document to reflect that industry comments did not reveal any reliability related need to address external control loops within the continent‐wide Reliability Standard.  Some commenters identified, and the PRT agrees, that TOP involvement in detailed AVR external controller loop design is outside the scope of VAR‐001.     

Page 118: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    118 

8. There are a number of errata (i.e., administrative) type observations listed in Attachment 4 of the VAR‐001‐4.1 template. If you disagree with any of the observations, please list the reference number when providing comment. 

Brian Van Gheem ‐ ACES Power Marketing ‐ 6 ‐ NA ‐ Not Applicable, Group Name ACES Standards Collaborators 

Answer   

Document Name   

Comment 

We agree with the errata list and thank the Periodic Review Team for identifying these administrative type observations. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. 

Richard Jackson ‐ U.S. Bureau of Reclamation ‐ 1,5 

Answer   

Document Name   

Comment 

Reclamation agrees with the proposed errata. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. 

Page 119: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    119 

Russel Mountjoy ‐ Midwest Reliability Organization ‐ 10 

Answer   

Document Name   

Comment 

The NSRF agrees with the review team. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. 

Rachel Coyne ‐ Texas Reliability Entity, Inc. ‐ 10 

Answer   

Document Name   

Comment 

Texas RE recommends using the latest Results Based Standards template for VAR‐001.  Texas RE noticed R4 starts with “The Transmission Operator…” but the R4 Measure says “Each Transmission Operator…” 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) added the additional errata to the Periodic Review Recommendations: VAR‐001‐4.1 – Voltage and Reactive Control document. 

Sandra Shaffer ‐ Berkshire Hathaway ‐ PacifiCorp ‐ 6 

Page 120: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    120 

Answer   

Document Name   

Comment 

No comment. 

Likes     0   

Dislikes     0   

Response 

 

Aaron Cavanaugh ‐ Bonneville Power Administration ‐ 1,3,5,6 ‐ WECC 

Answer   

Document Name   

Comment 

No comments 

Likes     0   

Dislikes     0   

Response 

 

Karie Barczak ‐ DTE Energy ‐ Detroit Edison Company ‐ 3,4,5, Group Name DTE Energy ‐ DTE Electric 

Answer   

Document Name   

Comment 

Page 121: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    121 

No comments 

Likes     0   

Dislikes     0   

Response 

 

Julie Hall ‐ Entergy ‐ 6, Group Name Entergy/NERC Compliance 

Answer   

Document Name   

Comment 

2.4 Reactive Power Schedule should be defined and included the “which could include” statement one time and not repeated throughout the document. It impairs readability. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The periodic review team (PRT) retained this recommendation in Attachment 5 of the Periodic Review Recommendations: VAR‐001‐4.1 – Voltage and Reactive Control document, Item 3.1.     

Page 122: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    122 

9. There are a number of other observations in Attachment 5 of the VAR‐001‐4.1 template that could enhance the standard, but would require a drafting team to develop for industry feedback. If you have any comments about these, please list the reference number when providing comment. 

Julie Hall ‐ Entergy ‐ 6, Group Name Entergy/NERC Compliance 

Answer   

Document Name   

Comment 

1.1 Disagree, these are separate actions by separate functional entities and need to be required independently. Could reword to say “…in automatic control mode as specified by the TOP”. 

2.1 Entergy does not find this unclear – is this a frequently violated or misunderstood requirement in the industry? 

2.2 Disagree ‐ don't see this as an action that will improve reliability. This seems like an administrative or business practice that is out of scope of the standard. 

2.3 agree 

2.4 disagree. the transmission operators are already tasked with maintaining the reliability of the BES in their interconnection by detailed means. 

2.5 Recommend solving this issue with a glossary term, as commented above. Avoid excess noisy verbiage in the requirements that might cause confusion and impair readability. 

3.1 Agree, see comments above. 

4.1 and 4.2 ‐ Disagree, would like to see "assess and schedule" added to R2 to make the wording more robust. 

4.3 Agree ‐ ‐ term “instruct” should be used consistently throughout the standards (it is an Operating Instruction). 

Page 123: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    123 

4.5 Agree, change to "all applicable" or "all non‐exempt" also applies to part 1 of R5 severe VSL

4.6 Agree, Severe is for missing all of the applicable GOPs, High would be for missing 1 or more of non‐exempt GOPs. 

4.7 and 4.8 Agree 

4.9 We agree that this information is important and needs to be considered, but feel that dynamic voltage schedules need to be developed into a new/separate requirement (new R6) and make the original R6 into R7. 

5.1 agree 

5.2 agree, recommend to go with "instruct" consistently in this and other standards. (see reasoning above) 

5.3 Agree ‐ TOP should coordinate with the "GSU Owner" rather than trying to specify any Functional Entity. 

9.1 Not necessary for clarity ‐ is this a highly violated and misunderstood requirement in industry? 

Likes     0   

Dislikes     0   

Response 

Thank you for your comments. 

1.1 The periodic review team (PRT) retained this item (R5, Part 5.1 redundancy clause) based upon the majority of comments received from industry. 

2.1 There is no current indication that these more recent versions of the VAR standards are frequently violated. 

2.2 The PRT retained this item as many of the stakeholder responses indicate that clarity could be improved. 

2.3 Thank you for your comments. 

Page 124: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    124 

2.4 The PRT retained this item as many of the stakeholder responses indicate that clarity could be improved. Clarity could be addressed in the Guidelines and Technical Basis section. 

2.5 Thank you for your comments. 

3.1 Thank you for your comments. 

4.1‐4.2 The PRT retained this item as many of the stakeholder responses indicate that clarity could be improved in the Measure. 

4.3‐5.3 Thank you for your comments. 

9.1 The PRT retained this item as many of the stakeholder responses indicate that clarity could be improved. There is no current indication that these more recent versions of the VAR standards are frequently violated. 

Karie Barczak ‐ DTE Energy ‐ Detroit Edison Company ‐ 3,4,5, Group Name DTE Energy ‐ DTE Electric 

Answer   

Document Name   

Comment 

No comments 

Likes     0   

Dislikes     0   

Response 

 

Pamela Hunter ‐ Southern Company ‐ Southern Company Services, Inc. ‐ 1,3,5,6 ‐ SERC, Group Name Southern Company 

Answer   

Document Name   

Page 125: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    125 

Comment 

Item 1.1:  R5.1 of VAR‐001‐4.1 is not a GOP requirement, so there is no redundancy with R1 of VAR‐002‐4.    

Item 2.2:  No additional clarity is needed for R2.2 of VAR‐001‐4.1 for how a TP determines the exemption criteria needs to be individually decided and not dictated.    

Item 3.1:   It is not necessary to define the terms listed in the article ‐ generator owners and operators are already fully aware of the meaning of the terms.  

Item 2.4:  No additional clarity is needed around coordination of implementing voltage schedules at the same point in time.  Transmission Operators are well aware of the system response to changes in voltage schedule and already take that into consideration. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comments. 

1.2 The periodic review team (PRT) retained this item (R5, Part 5.1 redundancy clause) based upon the majority of comments received from industry. 

2.2 The PRT retained this item as many of the stakeholder responses indicate that clarity could be improved. 

3.1 The PRT retained this item as many of the stakeholder responses indicate that clarity could be improved. 

2.4 The PRT retained this item as many of the stakeholder responses indicate that clarity could be improved. Clarity could be addressed in the Guidelines and Technical Basis section. 

Aaron Cavanaugh ‐ Bonneville Power Administration ‐ 1,3,5,6 ‐ WECC 

Answer   

Page 126: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    126 

Document Name   

Comment 

No comments 

Likes     0   

Dislikes     0   

Response 

 

Sandra Shaffer ‐ Berkshire Hathaway ‐ PacifiCorp ‐ 6 

Answer   

Document Name   

Comment 

No comment. 

Likes     0   

Dislikes     0   

Response 

 

David Jendras ‐ Ameren ‐ Ameren Services ‐ 1,3,6 

Answer   

Document Name   

Comment 

Page 127: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    127 

For #1 in Attachment 5, VAR‐002‐4 Requirement R1 is not redundant with VAR‐001‐4.1 Requirement R5 in that it does not specify the location of the monitoring or control.  VAR‐002‐4 Requirement R2, Part 2.3 does stipulate that the GOP must inform the TOP if the location is not the location the TOP required when they provided the voltage schedule.  However, it does not allow for approval by the TOP of the methodology for conversion of the schedule.  Therefore, the requirement in VAR‐001‐4.1 Requirement 5 should not be retired.

Likes     0   

Dislikes     0   

Response 

Thank you for your comments. 

1.1 The periodic review team (PRT) retained this item based upon the majority of comments received from industry. 

Rachel Coyne ‐ Texas Reliability Entity, Inc. ‐ 10 

Answer   

Document Name   

Comment 

Texas RE does not have comments on this question. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. 

Russel Mountjoy ‐ Midwest Reliability Organization ‐ 10 

Answer   

Document Name   

Page 128: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    128 

Comment 

The review team has highlighted a number of issues that would help with clarification of requirements, however the review team has also indicated that this is not a highly violated standard, is practically implemented and addresses a reliability need. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. 

Richard Jackson ‐ U.S. Bureau of Reclamation ‐ 1,5 

Answer   

Document Name   

Comment 

Reclamation agrees with the proposed observations. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. 

Brian Van Gheem ‐ ACES Power Marketing ‐ 6 ‐ NA ‐ Not Applicable, Group Name ACES Standards Collaborators 

Answer   

Document Name   

Comment 

Page 129: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    129 

We thank the Periodic Review Team for identifying Paragraph 81 requirements within this standard.  However, the team also identified the need for additional requirements.  We believe this is a step in the wrong direction for a standard that is not often violated. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. 

Elizabeth Axson ‐ Electric Reliability Council of Texas, Inc. ‐ 2 

Answer   

Document Name   

Comment 

It may be helpful to define the terms “voltage schedules” and “Automatic Voltage Regulators” for the sake of clarity.  There has been confusion around the terms “voltage schedules,” “reactive power schedules,” and “voltage limits.”  The recent Reactive Power Planning Realibility Guideline has added some clarity to what is a “voltage schedule,” and it seems clear that this is not synonomous with “voltage limits,” but the definition could be clearer than the parentheticals in the requirements R1 and R5 today.  Additionally there has been confusion between the voltage schedules in R1 and those mentioned in R5 if they are one and the same or different.  

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. 

Michael Godbout ‐ Hydro‐Québec TransÉnergie ‐ 1 ‐ NPCC 

Answer   

Document Name   

Page 130: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    130 

Comment 

Attachment 5, point 5.3. 

In the Québec interconnection, a number of step‐up transformers are owned by TOs. Standards like FAC‐008‐3 and PRC‐025‐1 allow for this reality. This standard does not (R6). We believe that when this standard is revised, this change should be made in order to make the standard consistently applicable. 

This same requirement (R6) (and the matching requirements in VAR‐002‐4) do not seem to be RBS. In particular, they do not specify a performance to be achieved, only a means ‐ tap changes ‐ by which an unspecified goal must be attained. In the Enhanced Periodic Review, some parties stated that such a requirement regarding tap changes was necessary in some regions. Nevertheless, such a requirement currently calls out a single manner of achieving an unnamed goal. Currently, the requirement, as written, causes us no problems. However, when the standard is revised, it should be rewritten to reflect a performance‐based approach. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment.     

Page 131: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    131 

10. The team did not identify a concern related to cost effectiveness as drafted.  Do you agree?  If not, please provide additional detail.

Aaron Cavanaugh ‐ Bonneville Power Administration ‐ 1,3,5,6 ‐ WECC 

Answer  No 

Document Name   

Comment 

Per Question 7 – BPA believes any new requirement would need to be drafted in such a way that the needed functionality can be achieved without requiring the potential for replacing a bevy of equipment. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. 

Sean Bodkin ‐ Dominion ‐ Dominion Resources, Inc. ‐ 3,5,6 

Answer  No 

Document Name   

Comment 

Without additional information and studies it is difficult to determine cost impacts relative to the reliability benefits provided by the standard. 

Likes     0   

Dislikes     0   

Response 

Page 132: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    132 

Thank you for your comment. 

Shannon Mickens ‐ Southwest Power Pool, Inc. (RTO) ‐ 2 ‐ SPP RE, Group Name SPP Standards Review Group 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Aubrey Short ‐ FirstEnergy ‐ FirstEnergy Corporation ‐ 1,3,4 

Answer  No 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Richard Jackson ‐ U.S. Bureau of Reclamation ‐ 1,5 

Answer  Yes 

Document Name   

Comment 

Page 133: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    133 

Reclamation does not have any concerns related to the cost effectiveness of VAR‐001‐4.1, but asserts that the standard would be more cost‐effective after incorporating the above suggestions. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. 

Sandra Shaffer ‐ Berkshire Hathaway ‐ PacifiCorp ‐ 6 

Answer  Yes 

Document Name   

Comment 

Cost effectiveness is always a concern but should not take precedence over reliability issues.  

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. 

Karie Barczak ‐ DTE Energy ‐ Detroit Edison Company ‐ 3,4,5, Group Name DTE Energy ‐ DTE Electric 

Answer  Yes 

Document Name   

Comment 

No comments 

Page 134: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    134 

Likes     0   

Dislikes     0   

Response 

 

Hien Ho ‐ Tacoma Public Utilities (Tacoma, WA) ‐ 1,3,4,5,6 

Answer  Yes 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Rachel Coyne ‐ Texas Reliability Entity, Inc. ‐ 10 

Answer  Yes 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Brian Van Gheem ‐ ACES Power Marketing ‐ 6 ‐ NA ‐ Not Applicable, Group Name ACES Standards Collaborators 

Page 135: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    135 

Answer  Yes 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Russel Mountjoy ‐ Midwest Reliability Organization ‐ 10 

Answer  Yes 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Laura Nelson ‐ IDACORP ‐ Idaho Power Company ‐ 1 

Answer  Yes 

Document Name   

Comment 

 

Likes     0   

Page 136: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    136 

Dislikes     0   

Response 

 

Chris Scanlon ‐ Exelon ‐ 1,3,5,6 

Answer  Yes 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

David Jendras ‐ Ameren ‐ Ameren Services ‐ 1,3,6 

Answer  Yes 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Stephanie Burns ‐ International Transmission Company Holdings Corporation ‐ 2 ‐ MRO,SPP RE,RF 

Answer  Yes 

Page 137: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    137 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Julie Hall ‐ Entergy ‐ 6, Group Name Entergy/NERC Compliance 

Answer  Yes 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Jesus Sammy Alcaraz ‐ Imperial Irrigation District ‐ 1 

Answer  Yes 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Page 138: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    138 

Response 

 

Michelle Amarantos ‐ APS ‐ Arizona Public Service Co. ‐ 1,3,5,6 

Answer  Yes 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Preston Walker ‐ PJM Interconnection, L.L.C. ‐ 2 ‐ RF 

Answer  Yes 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Dennis Chastain ‐ Tennessee Valley Authority ‐ 1,3,5,6 ‐ SERC 

Answer  Yes 

Document Name   

Page 139: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    139 

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Glen Farmer ‐ Avista ‐ Avista Corporation ‐ 1,3,5 

Answer  Yes 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

     

Page 140: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    140 

11. Given the items identified by the periodic review team in the VAR‐001‐4.1 template, do you agree that the Reliability Standard is sufficient to protect reliability and meet the reliability objective of the standard and does not need immediate modification through standards development; however, there may be a future opportunity to improve any non‐substantive or insignificant quality and content issues? If you have any other comments on this review that you haven’t already mentioned above, please provide them here. 

Stephanie Burns ‐ International Transmission Company Holdings Corporation ‐ 2 ‐ MRO,SPP RE,RF 

Answer  No 

Document Name   

Comment 

Due to the lack of a requirement across all the NERC standards for any party to monitor reactive reserves, the VAR‐001 standard should be revised to include such a requirement on the TOP. This standard review should be graded as REVISE – RED. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The consensus of the industry is the standard is sufficient to protect reliability and meet the reliability objective of the standard. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that recently approved TOP/IRO standards address the issue and that no reliability gap exists. The PRT retained a general recommendation that a future Standards Authorization (SAR) or technical guideline outside of a NERC Reliability Standard could address monitoring reactive reserves as a minority of commenters noted reactive reserves should be monitored. 

Elizabeth Axson ‐ Electric Reliability Council of Texas, Inc. ‐ 2 

Answer  No 

Document Name   

Comment 

Page 141: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    141 

ERCOT does believe the Reliability Standard is sufficient to protect reliability and meet the reliability objective of the standard and does not need immediate modification through standards development.   

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The consensus of the industry is the standard is sufficient to protect reliability and meet the reliability objective of the standard.  

Karie Barczak ‐ DTE Energy ‐ Detroit Edison Company ‐ 3,4,5, Group Name DTE Energy ‐ DTE Electric 

Answer  Yes 

Document Name   

Comment 

No comments 

Likes     0   

Dislikes     0   

Response 

 

Michelle Amarantos ‐ APS ‐ Arizona Public Service Co. ‐ 1,3,5,6 

Answer  Yes 

Document Name   

Comment 

Page 142: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    142 

AZPS recommends a change the Purpose to remove “monitoring” since there are no monitoring requirements.  

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. Monitoring of voltage is implicit in VAR‐001‐4.1 in the performance of the standard; therefore, the periodic review team (PRT) contends that the term “monitoring” should remain in the Purpose statement. 

Aaron Cavanaugh ‐ Bonneville Power Administration ‐ 1,3,5,6 ‐ WECC 

Answer  Yes 

Document Name   

Comment 

No comments 

Likes     0   

Dislikes     0   

Response 

 

Pamela Hunter ‐ Southern Company ‐ Southern Company Services, Inc. ‐ 1,3,5,6 ‐ SERC, Group Name Southern Company 

Answer  Yes 

Document Name   

Comment 

 All suggested changes found in Attachment 4 of the periodic review are acceptable.   The other changes suggested are not needed.     

Page 143: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    143 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The consensus of the industry is the standard is sufficient to protect reliability and meet the reliability objective of the standard. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to reflect the majority of industry comment. 

Aubrey Short ‐ FirstEnergy ‐ FirstEnergy Corporation ‐ 1,3,4 

Answer  Yes 

Document Name   

Comment 

While our responses to Q1, Q2 and Q3 suggestion some improvements in the standard may be warranted based on the questions asked, we believe that overall the standard is sufficient.  However, if the majority of industry also believes there may be some reliability impact to the items raised in Q1, Q2 and Q3 then NERC may need to further investigate those items through a standards development project. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The consensus of the industry is the standard is sufficient to protect reliability and meet the reliability objective of the standard. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to reflect the majority of industry comment. 

Michael Cruz‐Montes ‐ CenterPoint Energy Houston Electric, LLC ‐ 1 ‐ Texas RE 

Answer  Yes 

Document Name   

Comment 

Page 144: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    144 

CenterPoint Energy believes that the VAR‐001‐4.1 Standard is sufficient to protect reliability and meet the reliability objective of the standard and does not need immediate modification through standards development. We appreciate the efforts of the review team in identifying potential areas for future improvement to low priority issues. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The consensus of the industry is the standard is sufficient to protect reliability and meet the reliability objective of the standard. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to reflect the majority of industry comment. 

Brian Van Gheem ‐ ACES Power Marketing ‐ 6 ‐ NA ‐ Not Applicable, Group Name ACES Standards Collaborators 

Answer  Yes 

Document Name   

Comment 

We thank you for this opportunity to provide these comments. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. 

Richard Jackson ‐ U.S. Bureau of Reclamation ‐ 1,5 

Answer  Yes 

Document Name   

Comment 

Page 145: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    145 

Reclamation asserts that VAR‐001‐4.1 should be modified to include the proposed requirements, errata, and observations. Reclamation supports periodic reviews of standards like these as essential, and appreciates the work of the Periodic Review Team. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The consensus of the industry is the standard is sufficient to protect reliability and meet the reliability objective of the standard. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to reflect the majority of industry comment. 

Michael Godbout ‐ Hydro‐Québec TransÉnergie ‐ 1 ‐ NPCC 

Answer  Yes 

Document Name   

Comment 

The PRT has identified a number of issues. However, most issues identified so far seem relatively minor. We do not see a pressing need to revise the standard at this time. At some point though, the standard will have to be revised and cleaned up though. 

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The consensus of the industry is the standard is sufficient to protect reliability and meet the reliability objective of the standard. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to reflect the majority of industry comments. 

Glen Farmer ‐ Avista ‐ Avista Corporation ‐ 1,3,5 

Answer  Yes 

Page 146: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    146 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Dennis Chastain ‐ Tennessee Valley Authority ‐ 1,3,5,6 ‐ SERC 

Answer  Yes 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Preston Walker ‐ PJM Interconnection, L.L.C. ‐ 2 ‐ RF 

Answer  Yes 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Page 147: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    147 

Response 

 

Sean Bodkin ‐ Dominion ‐ Dominion Resources, Inc. ‐ 3,5,6 

Answer  Yes 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Jesus Sammy Alcaraz ‐ Imperial Irrigation District ‐ 1 

Answer  Yes 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Julie Hall ‐ Entergy ‐ 6, Group Name Entergy/NERC Compliance 

Answer  Yes 

Document Name   

Page 148: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    148 

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

David Jendras ‐ Ameren ‐ Ameren Services ‐ 1,3,6 

Answer  Yes 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Ruida Shu ‐ Northeast Power Coordinating Council ‐ 1,2,3,4,5,6,7,8,9,10 ‐ NPCC, Group Name RSC no ISO‐NE 

Answer  Yes 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

Page 149: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    149 

 

Chris Scanlon ‐ Exelon ‐ 1,3,5,6 

Answer  Yes 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Laura Nelson ‐ IDACORP ‐ Idaho Power Company ‐ 1 

Answer  Yes 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Sandra Shaffer ‐ Berkshire Hathaway ‐ PacifiCorp ‐ 6 

Answer  Yes 

Document Name   

Comment 

Page 150: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    150 

 

Likes     0   

Dislikes     0   

Response 

 

Shannon Mickens ‐ Southwest Power Pool, Inc. (RTO) ‐ 2 ‐ SPP RE, Group Name SPP Standards Review Group 

Answer  Yes 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Russel Mountjoy ‐ Midwest Reliability Organization ‐ 10 

Answer  Yes 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Page 151: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    151 

Gregory Campoli ‐ New York Independent System Operator ‐ 2, Group Name ISO/RTO Standards Review Committee 

Answer  Yes 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Hien Ho ‐ Tacoma Public Utilities (Tacoma, WA) ‐ 1,3,4,5,6 

Answer  Yes 

Document Name   

Comment 

 

Likes     0   

Dislikes     0   

Response 

 

Rachel Coyne ‐ Texas Reliability Entity, Inc. ‐ 10 

Answer   

Document Name   

Comment 

Page 152: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    152 

Texas RE frequently encounters wind farms that do not recognize that the technology to maintain voltage is an AVR.  Wind Farm Management Systems (under a variety of names) clearly demonstrate the capability to control volatage and are used daily but, because it is not specifically called an “AVR”, entities often miss responsibilities.  With the penetration of wind, it is imperative that this get corrected globally, rather than one‐off awareness (via an compliance discovery method) or workshops that are not necessarily attended by all parties.  Texas RE has done outreach and will continue to do so but would encourage a project to clarify the VAR standards.   

Likes     0   

Dislikes     0   

Response 

Thank you for your comment. The consensus of the industry is the standard is sufficient to protect reliability and meet the reliability objective of the standard. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to reflect the majority of industry comments. The PRT agrees that an Automatic Voltage Regulator (AVR) definition added in a future revision could provide additional clarity as identified in the VAR‐001‐4.1 Enhanced Periodic Review Recommendation document, Attachment 5: Other Miscellaneous Corrections/Revisions, Item 3.1.  Comments received from Leonard Kula of IESO 

 

Questions

1. VAR‐001‐4.1 Requirement R4, regarding exemptions and exempted units, does not require periodic reviews or reviews triggered by changes; such as, technology, system conditions or other factors. Does this create an impact to reliability? If yes, please explain. 

 Yes  No 

Comments:  The exemption criteria may change due to changes in technology or system conditions, hence if not reviewed, may 

deem the previously established criteria invalid. A periodic review is necessary to ensure there are no reliability gaps. 

Page 153: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    153 

Response 

Thank you for your comment. The periodic review team (PRT) concluded based on industry comment that the current TOP/IRO standards provide for an Operational Planning Analysis (OPA) and Real‐time Assessment (RTA) that will identify any reliability issues; therefore, no immediate revision to the standard is warranted. Based on minority response, the PRT affirms that there may be future opportunities to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

 

2. If the voltage schedule issued by the TOP to the GOP (Requirement R5) results in a generating unit routinely running at maximum limits, does a lack of dynamic reactive reserve have a reliability impact? 

 Yes  No 

Comments:  

We do not fully understand the question since the term “lack of dynamic reactive reserve” needs to be clarified wrt whether it means: 

a. Lack of dynamic reactive reserve capability? 

b. Lack of dynamic reactive reserve requirements? 

c. Both 

Not knowing the exact meaning of the term, we are unable to provide relevant comment wrt whether or not the lack of any of the above can have a reliability impact.  

In general, we hold the view that if there are dynamic reactive reserve requirements, then they need to be met by having sufficient dynamic reactive reserve capability. Hence, the lack of dynamic reactive requirements does not have any reliability impact. On the other hand, the lack of dynamic reactive reserve capability may or may not have any reliability impact; it depends on whether or not there are any dynamic reactive reserve requirements. 

Response 

Thank you for your comment. The periodic review team (PRT) notes that industry submitted comments that the lack of reserves on a single unit would not pose a reliability issue regarding the need for a periodic review. Any issues involving multiple generating units would 

Page 154: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    154 

be identified as part of an Operational Planning Analysis (OPA) or Real‐Time Assessment (RTA). The PRT affirms that there may be future opportunity to revise the standard or provide technical guidance (e.g., guideline) outside of a Reliability Standard. 

 

3. As of April 1, 2017, there will no longer be any explicit requirements for monitoring or ensuring adequate reactive reserves. Absent of any explicit requirements to monitor or ensure adequate reactive reserves within the IRO, TOP, or VAR standards, is there an impact to reliability? If yes, please explain. 

 Yes  No 

Comments:  

We do not believe that explicit requirements to monitor or ensure adequate reactive reserves are needed. Reactive reserves are needed to support voltage schedule (R2), which in turn supports SOLs and IROLs (R1). The need to monitor and ensure sufficiency of reactive reserve is implicit in meeting Requirements R1 and R2 of VAR‐001‐4.1.  

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that recently approved TOP/IRO standards address the issue and that no reliability gap exists. The PRT retained a general recommendation that a future Standards Authorization (SAR) or technical guideline outside of a NERC Reliability Standard could address monitoring reactive reserves as a minority of commenters noted reactive reserves should be monitored. 

 

4. As VAR‐001‐4.1 Requirement R5, Part 5.2 is silent with regards to a time duration that a generator can be outside of voltage schedule before notification is required. If the TOP is not required to specify the timing portion of the notification requirements while maintaining the necessary flexibility, is there an impact to reliability? If yes, please explain. 

 Yes  No 

Comments:  

Page 155: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    155 

We assume that the TOP will include in its notification requirement, the time duration that a generator can be outside of voltage schedule before notification is required. Hence we don’t believe there is any reliability impact for not having such explicit wording. However, we are indifferent as to whether or not such wording should be added to Part 5.2. 

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Template document to capture comments that VAR‐001 Requirement 5.2 allows the flexibility to specify a time duration, requiring a time duration would be prescriptive, and that there may be future opportunity to provide technical guidance outside of a Reliability Standard. 

 

5. VAR‐001‐4.1 Requirement R5 does not include the RC as a recipient of voltage or Reactive Power schedules issued to generators. Is there an impact to reliability? If yes, please explain. 

 Yes  No 

Comments:  

The RC may have a reliability need to be notified the of voltage or Reactive Power schedules issued to generators. The requirement in Part 1.1 only addresses the situation when a request is made by the RC; it not address the situations when the TOP itself develops and conveys the schedule to the GOP. Not having the latter information can have a reliability impact if the RC needs to monitor and ensure adherence to the schedule. 

Response 

Thank you for your comment. The periodic review team (PRT) has modified its Enhanced Periodic Review Recommendation document to capture the comments that IRO‐010‐2 addresses the issue by allowing the Reliability Coordinator to identify and request such information. Therefore, no reliability gap exists. 

 

Page 156: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    156 

6. VAR‐001‐4.1 Requirement R5 dictates the status of an AVR. Does the lack of a similar requirement to identify the initial state of the PSS impact reliability? If yes, please explain. 

 Yes  No 

Comments:  

We believe that the default assumption is that the PSS is initially in service. A change to this initial status is required in VAR‐002 (R3). This should suffice to ensure reliability. That said, we do not oppose strongly to adding an explicit requirement under VAR‐001, R5. 

Response 

Thank you for your comment. The periodic review team (PRT) appended the recommendation to note that industry comments affirm that it is not necessary to require notification of the initial state of the PSS. Regional practices, interconnection agreements, and data specifications can address the initial state of the PSS; therefore, revising the continent‐wide VAR‐001‐4.1 standard is not necessary. 

7. The continent‐wide VAR standards do not address external control loops to the AVR that may impact the reactive response of a generator. Some external control loops do not have the purpose of automative voltage control, therefore, is there a need to coordinate external loops to prevent an impact to reliability?1 If yes, please explain. 

 Yes  No 

Comments:  

Notes to IESO SME: please assess if we have similar set up in Ontario, and provide draft comment accordingly. Please see excerpt from NERC’s assessment of the current VAR‐001‐4.1 (the VAR‐001‐4.1 template): 

1 See also: Lesson Learned, Generator Distributed Control System Impact on Automatic Voltage Regulators, June 9, 2015, (http://www.nerc.com/pa/rrm/ea/Lessons Learned Document Library/LL20150602_Generator_Distributed_Control_System_ Impact_on_Automatic_Voltage_Regulators.pdf)  

Page 157: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    157 

“The WECC variance E.A.18 is specific to external control loops to the manufacturer’s AVR control loop. Due to the system configuration of the WECC, it was one of the earlier adopters of AVR and PSS controls. Due to the age of the controls or difficulty with setting reactive droop compensation on some older style controls, external loop controls were implemented from the plant control system. This can be done via DCS or SCADA. Variance E.A.18 requires that if external controls are used, that they do not affect the AVR’s transient response during fault conditions. There is a need to determine if this type of control is used outside of the WECC. Adding this variance to the continent wide NERC standard might be justified if other utilities practice this method of voltage control and there have been documented cases that the external control hindered the AVR from responding properly during a fault event.” 

Response 

Thank you for your comment. The periodic review team (PRT) has modified the Enhanced Periodic Review document to reflect that industry comments did not reveal any reliability related need to address external control loops within the continent‐wide Reliability Standard. 

 

8. There are a number of errata (i.e., administrative) type observations listed in Attachment 4 of the VAR‐001‐4.1 template. If you disagree with any of the observations, please list the reference number when providing comment. 

Comments:  

No comment. 

9. There are a number of other observations in Attachment 5 of the VAR‐001‐4.1 template that could enhance the standard, but would require a drafting team to develop for industry feedback. If you have any comments about these, please list the reference number when providing comment. 

Comments:  

We generally agree with the proposed enhancements presented in Attachment 5, but do support developing the definitions for those terms listed under Section 3.1. The VAR‐001 standard has been in place for almost 10 years and there have not been many issues with the lack of clarity associated with the terms “generator voltage schedule”, “generator Reactive Power schedule, “system voltage schedule,” and “automatic voltage regulator (AVR). We not believe that defining them will improve the understanding of the VAR‐001 standard. Rather, adding these definitions to the NERC Glossary may 

Page 158: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    158 

prolong the development and approval of the next VAR‐001 version, and add unnecessary chore to maintaining the glossary down the road.  

Response 

Thank you for your comment. The periodic review team (PRT) retained this recommendation in Attachment 5 of the Periodic Review Recommendations: VAR‐001‐4.1 – Voltage and Reactive Control document, Item 3.1. 

 

10. The team did not identify a concern related to cost effectiveness as drafted.  Do you agree?  If not, please provide additional detail. 

 Yes  No 

Comments:            

11. Given the items identified by the periodic review team in the VAR‐001‐4.1 template, do you agree that the Reliability Standard is sufficient to protect reliability and meet the reliability objective of the standard and does not need immediate modification through standards development; however, there may be a future opportunity to improve any non‐substantive or insignificant quality and content issues? If you have any other comments on this review that you haven’t already mentioned above, please provide them here. 

 Yes  No 

Comments:             

 Additional comments received from John Seelke of LS Power Transmission, LLC 

VAR Standards Enhanced Periodic Review (EPR) Comments of Behalf of LS Power Transmission, LLC (LSPT)

Page 159: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    159 

The comments below address an issue with both VAR standards – VAR-001-4.1 and VAR-002-4. While the review team reviewed each standard individually, they did not identify the reliability issue discussed below. Because comments were requested separately for each standard, LSPT’s comments do not fit within either standard.

The issue is contradictory language regarding a Transmission Operator’s (TOP’s) obligations regarding the automatic voltage regulator obligations of its Generator Operators (GOPs). This issue can easily be addressed by the review team. VAR-001-4.1, in part, is listed below:

The highlighted text in 5.1 requires the TOP to “direct the Generator Operator to comply with the schedule in automatic voltage control mode (the AVR in service and controlling voltage).” This language should be deleted because an AVR’s operation is more completely addressed in VAR-002-4, R1.

Page 160: Consideration of Comments 2016EPR02 Enhanced... · Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017 2 Questions

Consideration of Comments | Project 2016‐EPR‐02 Enhanced Periodic Review of VAR Standards VAR‐001‐4.1 | May 25, 2017    160 

While the first phrase in R1 requires the GOP to “operator each generator…in the automatic voltage control mode (with its automatic voltage regulator (AVR) in service and controlling voltage,” the remaining language in R1 describes exceptions to this rule. These exceptions require either the TOP’s approval or the TOP’s notification by its GOP. VAR-002-4, R1 contradicts VAR-001-4.1, part 5.1, because no TOP directive to its GOPS is required regarding AVR operation. Furthermore, part 5.1 does not permit the exceptions described in R1. Would a TOP that did not direct its GOPs on its AVR operation as required by part 5.1 be non-compliant with part 5.1? That question is moot if the highlighted language in VAR-001-4, part 5.1 were deleted.

Therefore, the language in R1 should be the only requirement addressing normal AVR operation. The confusion created highlighted language in VAR-001-4.1, part 5.1 can only have a negative impact on reliability.

  End of Report