BUSINESS DECISION BUSINESS DECISION ANALYSISANALYSIS
Constructing a Network Diagram
Click function key F5 to run this lecture as a Slide Show
![Page 2: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/2.jpg)
Are there any pre-requisites for this topic?
NO. You may have come across
terms like “critical path”
but no knowledge is
pre-supposed.
![Page 3: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/3.jpg)
Project management is also referred to as:
network analysis
critical path analysis
PERT - program evaluation & review technique
![Page 4: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/4.jpg)
OK, so what’s a project?
Well any managerial
activity can be represented as
a project.
For example:
• developing a new product or service
• marketing a new product or service
• breaking into a new market
• building a new plant
• installing a new computer system
• planning a training programme
• re-locating head office.
![Page 5: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/5.jpg)
What do your example
projects have in common?
Each can be decomposed into its
constituent parts, called ACTIVITIES.
We can then define a project as a collection
of related activities.
Three things are important:
• each activity takes time
• each activity uses up resources
• activities are structured.
![Page 6: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/6.jpg)
What gives activities
structure?
Precedence:
some activities have to be completed before others
can be started.
But that’s too vague. A roof cannot be erected unless the foundations have been dug. Obviously
true! So digging foundations must precede erecting the roof! But what about the walls?
So we refer to the immediately preceding activities.
![Page 7: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/7.jpg)
The first step for any project is to:
• list the constituent activities
• arrange them into a Precedence Table.
Activity Description Preceding TimeActivity (weeks)
A Survey site - 6
BDevelop initial proposal
- 8
CObtain approval of governors
A,B 12
D Choose architect C 4E Work out budget C 6F Finalise design D,E 15G Agree financing E 12H Hire contractor F,G 8
The project is to build an extension to the Recreation Centre. The table lists the activities
and their immediate
predecessors – up to the point of starting
construction.
![Page 8: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/8.jpg)
And here’s another project …………. “purchase of a new car”.
Activity DescriptionPreceding Activity
Duration (days)
A Decide feasibility of purchase - 3B Find buyer for existing car A 14C Decide on possible models A 1D Investigate models decided upon C 3E Discuss with knowledgeable friends C 1F Get information from dealers C 2G Put all information together D,E,F 1H Narrow down to three options G 1I Test drive all three H 3J Get warranty & finance information H 2K Choose one car 1,J 2L Compare dealers & choose one K 2M Decide upon colour etc L 4N Test drive chosen model L 1O Buy new car B,M,N 3
![Page 9: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/9.jpg)
Is activity B a pre-condition for starting activity I?
NO
Activity DescriptionPreceding Activity
Duration (days)
A Decide feasibility of purchase - 3B Find buyer for existing car A 14C Decide on possible models A 1D Investigate models decided upon C 3E Discuss with knowledgeable friends C 1F Get information from dealers C 2G Put all information together D,E,F 1H Narrow down to three options G 1I Test drive all three H 3J Get warranty & finance information H 2K Choose one car 1,J 2L Compare dealers & choose one K 2M Decide upon colour etc L 4N Test drive chosen model L 1O Buy new car B,M,N 3
![Page 10: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/10.jpg)
Is activity A a pre-condition for starting activity K?
YES
Activity DescriptionPreceding Activity
Duration (days)
A Decide feasibility of purchase - 3B Find buyer for existing car A 14C Decide on possible models A 1D Investigate models decided upon C 3E Discuss with knowledgeable friends C 1F Get information from dealers C 2G Put all information together D,E,F 1H Narrow down to three options G 1I Test drive all three H 3J Get warranty & finance information H 2K Choose one car 1,J 2L Compare dealers & choose one K 2M Decide upon colour etc L 4N Test drive chosen model L 1O Buy new car B,M,N 3
![Page 11: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/11.jpg)
Can activities E and F take place at the same time?
YES
Activity DescriptionPreceding Activity
Duration (days)
A Decide feasibility of purchase - 3B Find buyer for existing car A 14C Decide on possible models A 1D Investigate models decided upon C 3E Discuss with knowledgeable friends C 1F Get information from dealers C 2G Put all information together D,E,F 1H Narrow down to three options G 1I Test drive all three H 3J Get warranty & finance information H 2K Choose one car 1,J 2L Compare dealers & choose one K 2M Decide upon colour etc L 4N Test drive chosen model L 1O Buy new car B,M,N 3
![Page 12: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/12.jpg)
Precedence tables aren’t that easy to use. Is there
some other way of representing a project?
Y E S
A useful visual representation of a project is obtained by
drawing a network diagram.
![Page 13: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/13.jpg)
This is how we represent an activity.
activityevent of starting
an activityevent of ending
an activity
get out of bed
So somewhere in the project “Get to University Monday Morning” will be:
![Page 14: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/14.jpg)
Err .. but we’ll need to link activities together,
won’t we. That’s correct.
Sometimes we might want to show:
ActivityPreceding Activity
A -B AC B
A B C
![Page 15: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/15.jpg)
Err .. but we’ll need to link activities together,
won’t we. That’s correct.
Sometimes we might want to show:
ActivityPreceding Activity
M K,L
MK
L
![Page 16: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/16.jpg)
ActivityPreceding Activity
B AC A
Err .. but we’ll need to link activities together,
won’t we. That’s correct.
Sometimes we might want to show:
AB
C
![Page 17: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/17.jpg)
Are there any rules to follow when drawing network diagrams? YES
1. Must be drawn from left to right.
2. Must have a single starting point.
3. Also a single ending point.
4. One arrow (only) per activity.
5. Must correctly reflect the precedence table.
![Page 18: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/18.jpg)
There is one complication that we need to allow for.
OK, tell me the worst!!
Sometimes we have to use Dummy activities.
We use a dashed arrow to record these.
A dummy activity may be needed:
• to prevent 2 or more activities sharing the same starting and ending events.
• to maintain network logic – i.e. to ensure that the network abides by the precedence table.
![Page 19: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/19.jpg)
DETAILS
OK. Let’s have a go at drawing a network.
We’ll draw the one for the extension to
the recreation centre.
![Page 20: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/20.jpg)
DETAILS
Where do I
start?
Well, a network must have a single starting point – a circle or node.
Once the project has started which activities can be begun?
A Survey site
B Develop initial proposal
![Page 21: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/21.jpg)
DETAILS
A
B
So we draw arrows for activities A & B running from the starting event. Make sure that you label
the activities as you include them in the network.
What comes next?
Activity Preceding Activity
C A,B
![Page 22: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/22.jpg)
DETAILS
Well is this correct. Does it abide by the rules for drawing network diagrams?
That’s no problem. Just do
this.
Activity Preceding Activity
C A,B
A
BC
RULES
NO Two or more activities may not share the same starting and ending event.
![Page 23: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/23.jpg)
DETAILS
Use a dummy activity. Here’s one way in which it can be done. It prevents A & B from sharing the same starting and ending event.
So how do I remedy
this error?
RULES
A
B
C
![Page 24: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/24.jpg)
DETAILSRULES
A
B
C
Activities D & E can start when C is finished.
E
D So we’ll add these to the network.
![Page 25: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/25.jpg)
DETAILSRULES
The table says that F can start when D & E are
completed.
So can we do this?
A
B
CE
D
F
![Page 26: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/26.jpg)
DETAILSRULES
No. We’ve broken the rules again.
A
B
CE
D
F
So another dummy activity
is needed.
![Page 27: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/27.jpg)
DETAILSRULES
This will
work.
A
B
C
E
D
F
![Page 28: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/28.jpg)
RULES
Now we can add
activity G.
A
B
C
E
D
F
DETAILS
G
G can be started once E is
completed.
![Page 29: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/29.jpg)
RULES
That leaves
activity H.
A
B
C
E
D
F
DETAILS
G
The start of H requires the
completion of F and G.
![Page 30: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/30.jpg)
RULES DETAILS
A
B
C
E
D
F
G
H
So we bring the arrows for F & G into the starting event for activity H.
And this is the finished
network.
![Page 31: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/31.jpg)
RULES DETAILS
A
B
C
E
D
F
G
H
Always check the network against the
precedence table before continuing.
![Page 32: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/32.jpg)
RULES DETAILS
Right, now we’ll draw the network for the project of
buying a new car.
For this project there’s only one starting activity,
namely A
![Page 33: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/33.jpg)
RULES DETAILS
A
Activities B & C can be started
once A is completed.
B
C
![Page 34: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/34.jpg)
RULES DETAILS
A
And D, E & F can be started
when C is completed.
B
C
D
E
F
![Page 35: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/35.jpg)
RULES DETAILS
Activity G requires
completion of D, E & F.
So two dummy activities are needed to prevent D, E & F having the same
starting and ending events.
A B
C
D
E
F
G
![Page 36: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/36.jpg)
RULES DETAILS
Activity H can now be added to the
network.
A B
C
D
E
F
GH
![Page 37: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/37.jpg)
RULES DETAILS
I & J can now
start.
A B
C
D
E
F
GH
IJ
![Page 38: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/38.jpg)
RULES DETAILS
Since the start of K needs completion of I & J we need another dummy
activity.
A B
C
D
E
F
GH
IJ
K
![Page 39: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/39.jpg)
RULES DETAILS
Now we add
activity L
A B
C
D
E
F
GH
IJ
K
L
![Page 40: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/40.jpg)
RULES DETAILS
A B
C
D
E
F
GH
IJ
K
L
M
N
Activities M & N can now be
started.
![Page 41: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/41.jpg)
RULES DETAILS
A B
C
D
E
F
GH
IJ
K
L
M
N
That leaves
activity O.
It can be started when activities B, M & N are completed.
![Page 42: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/42.jpg)
RULES DETAILS
A B
C
D
E
F
GH
IJ
K
L
M
N
That leaves
activity O.
A dummy activity will be needed to separate activities M and N.
![Page 43: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/43.jpg)
RULES DETAILS
A
C
D
E
F
GH
IJ
K
L
M
N
The network is
now completed.
OB
But remember to
check it against the precedence
table.
![Page 44: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/44.jpg)
What should I now be able to do?
Given the precedence table for a project, you should be able to draw
its network diagram.
![Page 45: Constructing a network diagram](https://reader033.vdocument.in/reader033/viewer/2022061118/5469a412af795925028b49bc/html5/thumbnails/45.jpg)
That’s the end of this lecture. You should now explore the problems, on drawing networks, that
are available within Blackboard.