the project's network diagram

12
Ricardo Viana Vargas, MSc, IPMA- B, PMP [email protected] © BY RICARDO VIANA VARGAS. TODOS OS DIREITOS RESERVADOS The Project’s Network Diagram

Upload: ricardo-viana-vargas

Post on 09-May-2015

12.419 views

Category:

Career


0 download

DESCRIPTION

In this presentation, the Ricardo explains the two types of network diagram - activity on arrow and activity in node, and makes some considerations on the network diagram.

TRANSCRIPT

Page 1: The Project's Network Diagram

Ricardo Viana Vargas, MSc, IPMA-B, [email protected]

© BY RICARDO VIANA VARGAS. TODOS OS DIREITOS RESERVADOS

The Project’s Network Diagram

Page 2: The Project's Network Diagram

Ricardo Viana Vargas, MSc, IPMA-B, PMP

2

Ricardo Viana Vargas is a project, portfolio and risk management specialist. During the past 15 years, he has been responsible for over 80 major projects in various countries in the areas of petroleum, energy, infrastructure, telecommunications, information technology and finances, comprising an investment portfolio of over 18 billion dollars.

He was the first Latin American volunteer to be elected Chairman of the Board for the Project Management Institute (PMI), the largest project management organization in the world with close to 500,000 members and certified professionals in 175 countries.

Ricardo Vargas has written ten books on project management, published in Portuguese and English, which have sold over 200,000 copies throughout the world. In 2005 he received the PMI Distinguished Award for his contribution to the development of project management and the PMI Professional Development Product of the Year award for the PMDome® workshop, considered the best project management training solution in the world.

He is a project management professor for various MBA courses, and actively participates on editorial boards for specialized journals in Brazil and the United States. Vargas is a recognized reviewer of the PMBOK Guide, the most important reference in the world for project management, and also chaired the official translation of PMBOK into Portuguese.

He is a chemical engineer and holds a master’s degree in Industrial Engineering from UFMG (Federal University of Minas Gerais). Ricardo Vargas also holds a Master Certificate in Project Management from George Washington University and is certified both as a Project Management Professional (PMP) by PMI and as IPMA-B by the International Project Management Association. He attended the Program on Negotiation for Executives at Harvard Law School.

Over an eleven year timeframe, which began in 1995, Ricardo, in conjunction with two partners, established one of the most solid Brazilian businesses in the area of technology, project management and outsourcing, which had a staff of 4,000 collaborators and an annual income of 50 million dollars in 2006, when Ricardo Vargas sold his share of the company to dedicate himself on a fulltime basis to the internationalization of his project management activities.

He is a member of the Association for Advancement of Cost Engineering (AACE), the American Management Association (AMA), the International Project Management Association (IPMA), the Institute for Global Ethics and the Professional Risk Management International Association (PRMIA).

© BY MACROSOLUTIONS SA. TODOS OS DIREITOS RESERVADOS

Page 3: The Project's Network Diagram

© BY RICARDO VIANA VARGAS. TODOS OS DIREITOS RESERVADOS

Network Diagram

Any schematic display of the logical

relationships between the project’s activities.

It is always depicted from left to right to show the chronological sequence

of project execution.

Vulgarly known as PERT

network.

The diagram shows the interrelationships between all activities

in a project.

Page 4: The Project's Network Diagram

© BY RICARDO VIANA VARGAS. TODOS OS DIREITOS RESERVADOS

Network Diagram

Atividade

T=dias

ES EF

LS LF

Atividade

T=dias

ES EF

LS LF

Atividade

T=dias

ES EF

LS LF

Atividade

T=dias

ES EF

LS LF

Task

T=dias

ES EF

LS LF

Atividade

T=dias

ES EF

LS LF

Atividade

T=dias

ES EF

LS LF

Page 5: The Project's Network Diagram

© BY RICARDO VIANA VARGAS. TODOS OS DIREITOS RESERVADOS

The Origin of the Network Diagram

Developed in 1957 by the US Navy during the construction of the Polaris submarines.

It was a joint effort between the Navy and Lockheed, a traditional aviation and military company with links to NASA and Booz, Allen & Hamilton.

By using this new tool, it was possible to reduce the development time of the Polaris Project in 45%.

Page 6: The Project's Network Diagram

© BY RICARDO VIANA VARGAS. TODOS OS DIREITOS RESERVADOS

Type of Network Diagram

AOA – Activity on Arrow

AON – Activity On Node

Page 7: The Project's Network Diagram

© BY RICARDO VIANA VARGAS. TODOS OS DIREITOS RESERVADOS

AOA – Activity On Arrow

Shows the diagram with the activities being represented by arrows that connect to an initial and a final state.

Mainly used when managing projects without a computer.

Also known as ADM (Arrow Diagramming Method).

Page 8: The Project's Network Diagram

© BY RICARDO VIANA VARGAS. TODOS OS DIREITOS RESERVADOS

Network Diagram - AOA

1

2 3

5 4

6

7

118

9

10

a

b

c

d

e f

g i

h

j

k

l

m

n

Page 9: The Project's Network Diagram

© BY RICARDO VIANA VARGAS. TODOS OS DIREITOS RESERVADOS

AON – Activity On Node

Shows the activities on nodes between the arrows.

Currently the most used visualization tool because it is automatically generated by most of the project management software tools.

Page 10: The Project's Network Diagram

© BY RICARDO VIANA VARGAS. TODOS OS DIREITOS RESERVADOS

Network Diagram - AON

Atividade

T=dias

ES EF

LS LF

Atividade

T=dias

ES EF

LS LF

Atividade

T=dias

ES EF

LS LF

Atividade

T=dias

ES EF

LS LF

Task

T=dias

ES EF

LS LF

Atividade

T=dias

ES EF

LS LF

Atividade

T=dias

ES EF

LS LF

Page 11: The Project's Network Diagram

© BY RICARDO VIANA VARGAS. TODOS OS DIREITOS RESERVADOS

Some Observations

There is a starting point.

There is an end point.

All activities have

predecessors.

All activities have

successors.

The network must be kept

up-to-date

There are no loops.

Page 12: The Project's Network Diagram

© BY MACROSOLUTIONS SA

Visitewww.ricardo-vargas.com

Para acessar outras apresentações, podcasts, videos e conteúdo técnico sobre gerenciamento de

projetos, riscos e portfólio.