construction activities and process

44
BUILDING CONSTRUCTION 1 Project 2: Construction Activities and Process Ibrahim Adhnan 0314694

Upload: ibrahim-adhnan

Post on 19-Dec-2014

273 views

Category:

Education


1 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Construction activities and Process

         BUILDING  CONSTRUCTION  1  Project  2:  Construction  Activities  and  Process                                                                          Ibrahim  Adhnan  0314694      

Page 2: Construction activities and Process

2   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

 WEEK  1            

                   

       

             

 Construction  Activity1:  Site  Setting  and  Site  Clearance  Duration:  5  days  Materials:  Steel  Fencing  Equipment:    Excavator,  Bump  Truck,  Dozer,  Chain  Saw,  Survey  Equipment  Skilled  Worker:  5  General  Workers,  2  Truck/Dozer  Operators  Technical  Information:    

• Prior  to  the  commencement  of  the  site  clearing  Contractor  shall  establish  the  site  boundary  

• Contractor  shall  erect  sufficient  safety  sign  to  notify  public  on  the  construction  activities  shall  any  need  arise.  

• Contractor  shall  also  submit  their  proposed  dumping  site  for  approval  prior  to  site  clearing  to  the  superintending  officer    

     

Page 3: Construction activities and Process

3   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

 WEEK  2                                                                                                        

 Construction  Activity  2:  Excavation  and  Earth  Works  Duration:  5  days  Materials:  Natural  Soil  Equipment:  Excavator,  Pay  loader,  Six  Wheel  Truck,  Bob  Cat,  Shovel,  Meter  Tape  Skilled  Worker:  5  General  Workers,  Truck  Driver,  Excavator  Operator  Technical  Information:    

• The  area  to  be  excavated  shall  be  properly  mark  and  clear  before  starting  the  works  • The  depth  of  excavation  shall  be  periodically  checked  by  a  surveyor  to  avoid  over  

excavation      

Page 4: Construction activities and Process

4   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

 WEEK  3                                                                

             

 Construction  Activity:    Pile  boring  and  reinforcement  installation  (Grid  a-­‐c)                                                                                                                                                                          Duration:    6  days  Materials:  Steel  Bore,  Reinforcement  bar,  bar  bender                                                                                                                                                                                                                                                                        Equipment:  Rebar  Bending  machine,  Boring  Machine  Skilled  Worker:  5  General  Workers,  Boring  Machine  Operator,  Bar  Bending  Machine  Technical  Information:  

• Survey  and  record  the  existing  ground  level  at  each  pile  location.    • Refer  to  the  reference  points  in  drawings  

           

Page 5: Construction activities and Process

5   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

 WEEK  4                                                                  

           

 Construction  Activity  1:    Pile  boring  and  reinforcement  installation  (Grid  e-­‐j)                                                                                                                                                                          Duration:    6  days  Materials:  Steel  Bore,  Reinforcement  bar,  bar  bender                                                                                                                                                                                                                                                                        Equipment:  Rebar  Bending  machine,  Boring  Machine  Skilled  Worker:  5  General  Workers,  Boring  Machine  Operator,  Bar  Bending  Machine  Technical  Information:  

• Survey  and  record  the  existing  ground  level  at  each  pile  location.    • Refer  to  the  reference  points  in  drawings  • The  reinforcement  cage  will  be  fabricated  in  lay-­‐down  sections  • type  and  size  of  the  steel  cage  will  be  according  to  drawings  

           

Page 6: Construction activities and Process

6   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

 WEEK  5                                                                    

         

 Construction  Activity  :    Pile  Filling    Duration:    6  days  Materials:  Concrete  Equipment:  Concrete  mixer,  Concrete  dispenser,  Concrete  vibrator                                                                                                                                                                                                                                                                                    Skilled  Worker:  5  General  Workers  Technical  Information:  

• The  self-­‐compacting  mixed  concrete  will  be  discharged  through  a  tremie  pipe,  which  is  lowered  centrally  to  the  bottom  of  the  bored  hole  prior  to  filling  it  with  concrete.  

• All  completed  piles  shall  be  temporarily  barricaded  and  to  be  backfilled  to  ground  level  with  a  suitable  material  the  next  day.  

           

Page 7: Construction activities and Process

7   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

 WEEK  6                                                                      

       

 Construction  Activity  1:  Pile  Cap  construction  (Grid  a-­‐g)  Duration:    5  days  Materials:  Concrete,  Reinforcement,  Timber  formwork  Equipment:  Bar  Bending  Machine,  Saw,  Vibrating  Machine,  Concrete  Mixer  Skilled  Worker:  3  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  

• Formwork  is  erected  according  to  the  design  • Fix  pile  cap  reinforcement  in  the  framework  • Apply  sufficient  vibration    • Pile  caps  distributes  the  load  from  the  above  structure  evenly  through  to  the  piles  

below.        

Page 8: Construction activities and Process

8   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

 WEEK  7          

                       

             

     

 Construction  Activity  2:  Stump  on  Pile  Cap  Duration:    5  days  Materials:  Concrete,  Reinforcement,  Timber  formwork  Equipment:  Bar  Bending  Machine,  Saw,  Vibrating  Machine  Skilled  Worker:  3  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  

• To  realign  the  level  of  the  substructure  to  ensure  the  ground  floor  and    corresponding  floors  are  level  

   

 Construction  Activity  1:  Pile  Cap  construction  (grid  h)  Duration:    5  days  Materials:  Concrete,  Reinforcement,  Timber  formwork  Equipment:  Bar  Bending  Machine,  Saw,  Vibrating  Machine,  Concrete  Mixer  Skilled  Worker:  3  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  

• Formwork  is  erected  according  to  the  design  • Fix  pile  cap  reinforcement  in  the  framework  • Apply  sufficient  vibration    • Pile  caps  distributes  the  load  from  the  above  structure  evenly  through  to  the  piles  

below.        

Page 9: Construction activities and Process

9   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

 WEEK  8                                                      

   

 Construction  Activity  1:  Ground  Beam  Construction  (Grid  a-­‐c)  Duration:    5  days  Materials:  Concrete,  reinforcements,  timber  formworks  Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  3  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:          Construction  Activity  2:  Stump  on  Pile  Cap  (Grid  d-­‐i)  Duration:    5  days  Materials:  Concrete,  Reinforcement,  Timber  formwork  Equipment:  Bar  Bending  Machine,  Saw,  Vibrating  Machine  Skilled  Worker:  3  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  

• To  realign  the  level  of  the  substructure  to  ensure  the  ground  floor  and    corresponding  floors  are  level  

   

Page 10: Construction activities and Process

10   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

 WEEK  9                            

                                       

         

 Construction  Activity:  Ground  Beam  Construction  (Grid  c-­‐h)  Duration:    5  days  Materials:  Concrete,  reinforcements,  timber  formworks  Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  3  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  Ground  beams  resist  applied  loads  with  a  rebar  spanning  above  stumps  and  connect  piles  caps  together  into  a  web  network,  concrete  is  then  cast-­‐in-­‐situ        

Page 11: Construction activities and Process

11   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

 WEEK  10                                                          

 Construction  Activity:  Ground  Floor  Slab  Construction  (grid  a-­‐e)  Duration:    5  days  Materials:  Concrete,  reinforcement  bars,  timber  formworks,  Damp  Proof  Membrane  (DPM),  Rigid  Floor  Insulation                                                                                                                                                                                              Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  :  Structural  engineers  typically  call  for  slabs  to  be  casted  between  4  and  20  inches  (100  and  500  millimeters)  thick,  thinner  slabs  are  also  used  for  exterior  paving.  Slabs  are  supported  on  the  foundation  or  directly  on  the  subsoil,  it  will  be  the  eventual  the  ground  floor  of  a  building.  The  slab  is  made  uniformly  thick,  reinforced  in  one  or  more  directions  and  casted  intergrally  with  the  parallel  ground  beams.          

Page 12: Construction activities and Process

12   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  11                                                                      

         

 Construction  Activity:  Ground  Floor  Slab  Construction  (grid  e-­‐k)    Duration:    5  day  Materials:  Concrete,  reinforcement  bars,  timber  formworks,  Damp  Proof  Membrane  (DPM),  Rigid  Floor  Insulation                                                                                                                                                                                              Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  Structural  engineers  typically  call  for  slabs  to  be  casted  between  4  and  20  inches  (100  and  500  millimeters)  thick,  thinner  slabs  are  also  used  for  exterior  paving.  Slabs  are  supported  on  the  foundation  or  directly  on  the  subsoil,  it  will  be  the  eventual  the  ground  floor  of  a  building.  The  slab  is  made  uniformly  thick,  reinforced  in  one  or  more  directions  and  casted  intergrally  with  the  parallel  ground  beams.          

Page 13: Construction activities and Process

13   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  12                      

 Construction  Activity:  Ground  Floor  Columns  (grid  a-­‐c)  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  Structural  columns  are  built  to  bear  the  load  from  super  structure  above  and    transfer  it  downwards  into  foundation.  The  timber  formwork  is  built  around  the  starter  bars  protruding  from  the  ground  floor  slab.  A  cage  is  bent  and  placed  inside  before  concrete  is  vibrated  into  the  mould.  The  12”  (305cm)  column  can  support  up  to  2000  square  ft  of  floor  area.        

Page 14: Construction activities and Process

14   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  13                                                                

               

 Construction  Activity:  Ground  Floor  Columns  (grid  e-­‐k)  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  Structural  columns  are  built  to  bear  the  load  from  super  structure  above  and    transfer  it  downwards  into  foundation.  The  timber  formwork  is  built  around  the  starter  bars  protruding  from  the  ground  floor  slab.  A  cage  is  bent  and  placed  inside  before  concrete  is  vibrated  into  the  mould.  The  12”  (305cm)  column  can  support  up  to  2000  square  ft  of  floor  area.          

Page 15: Construction activities and Process

15   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  14      

   

           

 Construction  Activity:  First  Floor  Beam  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  Super  structure  columns  are  connect  together  via  beams,  they  resist  applied  loads     with  a  rebar  from  the  columns.            

Page 16: Construction activities and Process

16   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  15                                                                

   

 Construction  Activity:  First  Floor  Beam  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  :  Super  structure  columns  are  connect  together  via  beams,  they  resist  applied  loads     with  a  rebar  from  the  columns.                

Page 17: Construction activities and Process

17   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  16                                    

 Construction  Activity:  First  Floor  Slab  (Grid  a-­‐g)  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork,  DPM                                                                                                                                                                                          Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  The  slab  is  cast  intergally  with  the  beams  which  provide  support  in  two  direction        

Page 18: Construction activities and Process

18   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  17              

Construction  Activity  1:  First  Floor  Slab  (Grid  g-­‐k)  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork,  DPM                                                                                                                                                                                        Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  The  slab  is  cast  intergally  with  the  beams  which  provide  support  in  two  direction            Construction  Activity  2:  Ground  Floor  Wall  (Grid  a-­‐e)  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  Walls  seperate  exterior  and  interior  as  well  as  rooms.  Bricks  are  laid  with  a  50/50  overlap  running  bond.        

Page 19: Construction activities and Process

19   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  18              

 Construction  Activity  1:  Ground  Floor  Wall  (Grid  c-­‐j)  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  Walls  seperate  exterior  and  interior  as  well  as  rooms.  Bricks  are  laid  with  a  50/50  overlap  running  bond.        Construction  Activity  2:  Ground  Floor  Stairs  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  :  Stairs  connect  individual  floors  together  by  means  of  a  series  of  incremental  steps  that  allow  a  human  to  gradually  climb.  The  stairs  is  built  from  a  starter  box,  which  is  a  series  of  starter  bars  protruding  from  the  ground  floor  slab.  Then  timber  form  work  is  make  at  the  desired  pitch.  The  tread(depth)  and  riser(height)  is  carefully  made  to  a  uniform  specifications.  The  half  turn  stairs  turns  180  degrees  through      two  right  angles  at  an  intervening  landing.  This  space  floor  space  on  the  revelant  floor  plans.            

Page 20: Construction activities and Process

20   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  19                                                            

                     

 Construction  Activity:  First    Floor  Columns  (grid  a-­‐c)  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  Structural  columns  are  built  to  bear  the  load  from  super  structure  above  and      transfer  it  downwards  into  foundation        

Page 21: Construction activities and Process

21   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  20        

 Construction  Activity:  First    Floor  Columns  (grid  e-­‐j)  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  Structural  columns  are  built  to  bear  the  load  from  super  structure  above  and      transfer  it  downwards  into  foundation            

Page 22: Construction activities and Process

22   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  21          

 Construction  Activity:  Second  Floor  Beam  (Grid  a-­‐e)  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  Super  structure  columns  are  connect  together  via  beams,  they  resist  applied  loads     with  a  rebar  from  the  columns.                

Page 23: Construction activities and Process

23   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  22      

 Construction  Activity:  Second  Floor  Beam  (Grid  c-­‐h)  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  Super  structure  columns  are  connect  together  via  beams,  they  resist  applied  loads     with  a  rebar  from  the  columns.                

Page 24: Construction activities and Process

24   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  23                                                                

                   

 Construction  Activity:  Second  Floor  Slab  (Grid  a-­‐g)  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork  ,  DPM                                                                                                                                                                                      Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  The  slab  is  cast  intergally  with  the  beams  which  provide  support  in  two  direction            

Page 25: Construction activities and Process

25   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  24      

     

Construction  Activity:  First  Floor  Wall  (Grid  a-­‐c)  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  Walls  seperate  exterior  and  interior  as  well  as  rooms.  Bricks  are  laid  with  a  50/50  overlap  running  bond.            

 Construction  Activity:  Second  Floor  Slab  (Grid  g-­‐j)  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork,  DPM                                                                                                                                                                                          Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  The  slab  is  cast  intergally  with  the  beams  which  provide  support  in  two  direction            

Page 26: Construction activities and Process

26   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  25        

Construction  Activity  2:  First  Floor  Wall  (Grid  d-­‐j)  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  Walls  seperate  exterior  and  interior  as  well  as  rooms.  Bricks  are  laid  with  a  50/50  overlap  running  bond.            

 Construction  Activity  1:  First  Floor  Stairs  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:        

Page 27: Construction activities and Process

27   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  26    

     

 Construction  Activity:  Second    Floor  Columns  (grid  a-­‐c)  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  Structural  columns  are  built  to  bear  the  load  from  super  structure  above  and      transfer  it  downwards  into  foundation            

Page 28: Construction activities and Process

28   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  27    

                                                 

                         

 Construction  Activity:  Second    Floor  Columns  (grid  e-­‐j)  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  Structural  columns  are  built  to  bear  the  load  from  super  structure  above  and      transfer  it  downwards  into  foundation            

Page 29: Construction activities and Process

29   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  28              

   Construction  Activity:  Roof  Beam  (Grid  a-­‐c)  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  Super  structure  columns  are  connect  together  via  beams,  they  resist  applied  loads     with  a  rebar  from  the  columns.                

Page 30: Construction activities and Process

30   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  29        

 Construction  Activity:  Third    Floor  Columns  (grid  c-­‐j))  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  Super  structure  columns  are  connect  together  via  beams,  they  resist  applied  loads     with  a  rebar  from  the  columns.                

Page 31: Construction activities and Process

31   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  30        

 Construction  Activity:  Roof  Truss  (Grid  a-­‐c)  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  Trusses  are  built  as  a  support  frame  work  for  the  pitched  roof        

Page 32: Construction activities and Process

32   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  31                                                                              

 

 Construction  Activity:  Roof  Truss  (Grid  a-­‐c)  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  Trusses  are  built  as  a  support  frame  work  for  the  pitched  roof          

Page 33: Construction activities and Process

33   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  32                                                                    

               

 Construction  Activity:  Roof  Construction  (Phase  1)  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  Roofs  are  the  protective  cover  of  a  building  against  rain,  snow  and  wind        

Page 34: Construction activities and Process

34   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

   WEEK  33                

 Construction  Activity:  Roof  Construction  (Phase  2)  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  Roofs  are  the  protective  cover  of  a  building  against  rain,  snow  and  wind            

Page 35: Construction activities and Process

35   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  34    

 Construction  Activity:  Second  Floor  Walls  Duration:    5  days  Materials:  Concrete,  reinforcement,  timber  formwork                                                                                                                                                                                          Equipment:  Concrete  Vibrator,  Rebar  bending  machine,  table  saw,  concrete  mixer                                                                                                                                                                                                                                                                                                      Skilled  Worker:  5  General  Workers,  3  Bar  benders,  2  carpenters  Technical  Information:  :  Walls  seperate  exterior  and  interior  as  well  as  rooms.  Bricks  are  laid  with  a  50/50  overlap  running  bond        

Page 36: Construction activities and Process

36   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  35                                    

 Construction  Activity  1:  Curtain  Walls  Installation    Duration:    5  days  Materials:  Glass,  Steel,  Screws  Equipment:  Wrench,  Level,  Screw  Driver  Skilled  Worker:  2  General  Workers,  1  Special  Worker  Technical  Information:  walls  are  to  be  connected  to  the  ground  floor  and  beam  on  the  upper  floor          Construction  Activity  2:  Railing    Installation    Duration:    3  days  Materials:  Aluminium  handrail  (staircase),  Aluminium  guardrail  (balcony)  Equipment:  Wrench,  Level,  Screw  Driver  Skilled  Worker:  2  General  Workers,  1  Special  Worker  Technical  Information:  :  Railing  provide  a  sturdy  barrier  when  walking  around  unenclosed  area.  The  handrail  is  installed  by  bolting  multiple  segments  of  the  rail  system  to  the  tread.  Similarly,  guardrails  are  also  bolted  to  the  ground  but  typically  at  the  edge  of  a     balcony.          

Page 37: Construction activities and Process

37   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  36              

 Construction  Activity  1:  Ground  Floor  door  framing  and  installation    Duration:    2  days  Materials:  Hollow  single  rabbet  metal  frame        Equipment:  Wrench,  Level,  Screw  Driver,  measuring  tape,  marker                                                                                                                                                                                                                                                                                    Skilled  Worker:  2  General  Workers,  1  Special  Worker  Technical  Information:  :  Doors  are  openings  between  exterior  and  interior,  and  between  rooms.  They  are  carefully  positioned  between  columns  where  the  wall  will  eventually  be  made.  Doors  are  correctly  oriented  as  to  whether  they  open  in  or  out  and  stood  up  right  with  wood  temporarily  nailed  to  columns  and  beams.            Construction  Activity  2:  Ground  Floor  window  framing  and  installation    Duration:    3  days  Materials:  Aluminium  casement  frame,  glass  window,  screws                                                                                                                                                                                                                                        Equipment:  Wrench,  Level,  Screw  Driver,  measuring  tape,  marker                                                                                                                                                                                                                                                                                    Skilled  Worker:  2  General  Workers,  1  Special  Worker  Technical  Information:  :  :  Windows  provide  ventilation  for  a  building,  a  casement  window  provides  100%  ventilation.  A  window  frame  is  first  installed,  followed  by  the  two  smaller  windows  and  their  pivot  brackets,  the  unit  is  topped  off  with  trimming  for  aesthetics.              

Page 38: Construction activities and Process

38   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  37          

 Construction  Activity  1:  First  Floor  door  framing  and  installation    Duration:    2  days  Materials:  Hollow  single  rabbet  metal  frame        Equipment:  Wrench,  Level,  Screw  Driver,  measuring  tape,  marker                                                                                                                                                                                                                                                                                    Skilled  Worker:  2  General  Workers,  1  Special  Worker  Technical  Information:  :  Doors  are  openings  between  exterior  and  interior,  and  between  rooms.  They  are  carefully  positioned  between  columns  where  the  wall  will  eventually  be  made.  Doors  are  correctly  oriented  as  to  whether  they  open  in  or  out  and  stood  up  right  with  wood  temporarily  nailed  to  columns  and  beams.          

 Construction  Activity  2:  First  Floor  window  framing  and  installation    Duration:    3  days  Materials:  Aluminium  casement  frame,  glass  window,  screws                                                                                                                                                                                                                                        Equipment:  Wrench,  Level,  Screw  Driver,  measuring  tape,  marker                                                                                                                                                                                                                                                                                    Skilled  Worker:  2  General  Workers,  1  Special  Worker  Technical  Information:  :  :  Windows  provide  ventilation  for  a  building,  a  casement  window  provides  100%  ventilation.  A  window  frame  is  first  installed,  followed  by  the  two  smaller  windows  and  their  pivot  brackets,  the  unit  is  topped  off  with  trimming  for  aesthetics.              

Page 39: Construction activities and Process

39   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

   WEEK  38          

 Construction  Activity  1:  second    Floor  door  framing  and  installation    Duration:    2  days  Materials:  Hollow  single  rabbet  metal  frame        Equipment:  Wrench,  Level,  Screw  Driver,  measuring  tape,  marker                                                                                                                                                                                                                                                                                    Skilled  Worker:  2  General  Workers,  1  Special  Worker  Technical  Information:  :  Doors  are  openings  between  exterior  and  interior,  and  between  rooms.  They  are  carefully  positioned  between  columns  where  the  wall  will  eventually  be  made.  Doors  are  correctly  oriented  as  to  whether  they  open  in  or  out  and  stood  up  right  with  wood  temporarily  nailed  to  columns  and  beams.          

 Construction  Activity  2:  second    Floor  window  framing  and  installation    Duration:    3  days  Materials:  Aluminium  casement  frame,  glass  window,  screws                                                                                                                                                                                                                                        Equipment:  Wrench,  Level,  Screw  Driver,  measuring  tape,  marker                                                                                                                                                                                                                                                                                    Skilled  Worker:  2  General  Workers,  1  Special  Worker  Technical  Information:  :  :  Windows  provide  ventilation  for  a  building,  a  casement  window  provides  100%  ventilation.  A  window  frame  is  first  installed,  followed  by  the  two  smaller  windows  and  their  pivot  brackets,  the  unit  is  topped  off  with  trimming  for  aesthetics.              

Page 40: Construction activities and Process

40   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

   WEEK  39      

   WEEK  40      

 WEEK  41        

Construction  Activity:  Electrical  Wiring    Duration:    7  days  Materials:  insulated  cooper  wires,  electrical  tape,  connector                                                                                                                                                                                                                                          Equipment:  Test  pen,  voltage  meter                                                                                                                                                                                                                                                                                    Skilled  Worker:  2  electricians  Technical  Information:  Electrical  cables  are  pulled  through  PVC  pipe  ambedded  in  the  concrete  walls  or  along  the  wall  surface.        

Construction  Activity:  Plumbing    Duration:    7  days  Materials:  assorted  dimensions  of  PVC  pipe,  connectors,  PVC  glue                                                                                                                                                                                                                                        Equipment:  Saw,  measuring  tape                                                                                                                                                                                                                                                                                    Skilled  Worker:  Plumber    Technical  Information:  Plumbing  is  essential  for  bringing  in  clean  water  into  a  building  and  taking  waste  products  away.  PVC  pipes  are  pieced  together,  in  order  to  connect  various  systems  together.        

Construction  Activity:  Sanitary  Fittings  Duration:    5  days  Materials:  Ceramics  Equipment:  Saw,  Measuring  tape,  drill                                                                                                                                                                                                                                                                                    Skilled  Worker:  Special  Worker,  2  General  Workers  Technical  Information:  Sanitary  fittings  such  as  sick,  water  closet  and  shower  are  usually  bought  as  modular  units  and  are  easily  installed.  Just  connect  the  plumbing  to  the  inlet  and     outlet,  and  ensure  the  fastening  is  secure.        

Page 41: Construction activities and Process

41   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  42      

   WEEK  43    

     WEEK  44        

Construction  Activity      :  Tiling    (Second    Floor)  Duration:    5  days  Materials:  Mortar,  Grout,  homogenenous  ceramic  tiles                                                                                                                                                                                                                                            Equipment:  Putty  knife,  spacers,  level                                                                                                                                                                                                                                                                                      Skilled  Worker:  2  Tilers  Technical  Information:  Tiles  are  a  durable,  easy  to  clean  modular  finish  that  requires  careful  installation  in  order  to  last  a  long  time.  A  tiling  pattern  is  first  determined  and  the  tiler  spread  mortar  on  the  floor  surface.  The  tiles  are  uniformly  spaced  and  align  with  the  aid  of  spacers.  The  gaps  are  made  to  allow  for  expansion  and  are  filled  with  grout.    .        

Construction  Activity  :  Tiling    (Ground  Floor)  Duration:    5  days  Materials:  Mortar,  Grout,  homogenenous  ceramic  tiles                                                                                                                                                                                                                                            Equipment:  Putty  knife,  spacers,  level                                                                                                                                                                                                                                                                                      Skilled  Worker:  2  Tilers  Technical  Information:  Tiles  are  a  durable,  easy  to  clean  modular  finish  that  requires  careful  installation  in  order  to  last  a  long  time.  A  tiling  pattern  is  first  determined  and  the  tiler  spread  mortar  on  the  floor  surface.  The  tiles  are  uniformly  spaced  and  align  with  the  aid  of  spacers.  The  gaps  are  made  to  allow  for  expansion  and  are  filled  with  grout.    .        

Construction  Activity      :  Tiling    (Second    Floor)  Duration:    5  days  Materials:  Mortar,  Grout,  homogenenous  ceramic  tiles                                                                                                                                                                                                                                            Equipment:  Putty  knife,  spacers,  level                                                                                                                                                                                                                                                                                      Skilled  Worker:  2  Tilers  Technical  Information:  Tiles  are  a  durable,  easy  to  clean  modular  finish  that  requires  careful  installation  in  order  to  last  a  long  time.  A  tiling  pattern  is  first  determined  and  the  tiler  spread  mortar  on  the  floor  surface.  The  tiles  are  uniformly  spaced  and  align  with  the  aid  of  spacers.  The  gaps  are  made  to  allow  for  expansion  and  are  filled  with  grout.    .        

Page 42: Construction activities and Process

42   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  45      

 WEEK  46        

 WEEK  47        

Construction  Activity    :  Plastering  (Ground  Floor)  Duration:    5  days  Materials:  Plaster  Board    Equipment:  Ramset  concrete  nailer,  Makita  concrete  driller,  Laser  Level  machine,    Plumbs,  Basic  hand  tools,  Makita  steel  bench  cutters,  Ceiling  gun,  Ladder,  Steel  square  ruler,  Drilling  Machine  Skilled  Worker:  3  General  Workers  Technical  Information:  All  leveling  set  out  coordinates  shall  be  based  on  the  setting  out  levels  provided  on  design.      

Construction  Activity    :  Plastering  (first  Floor)  Duration:    5  days  Materials:  Plaster  Board    Equipment:  Ramset  concrete  nailer,  Makita  concrete  driller,  Laser  Level  machine,    Plumbs,  Basic  hand  tools,  Makita  steel  bench  cutters,  Ceiling  gun,  Ladder,  Steel  square  ruler,  Drilling  Machine  Skilled  Worker:  3  General  Workers  Technical  Information:  All  leveling  set  out  coordinates  shall  be  based  on  the  setting  out  levels  provided  on  design.      

Construction  Activity    :  Plastering  (first  Floor)  Duration:    5  days  Materials:  Plaster  Board    Equipment:  Ramset  concrete  nailer,  Makita  concrete  driller,  Laser  Level  machine,    Plumbs,  Basic  hand  tools,  Makita  steel  bench  cutters,  Ceiling  gun,  Ladder,  Steel  square  ruler,  Drilling  Machine  Skilled  Worker:  3  General  Workers  Technical  Information:  All  leveling  set  out  coordinates  shall  be  based  on  the  setting  out  levels  provided  on  design.      

Page 43: Construction activities and Process

43   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  48      

 WEEK  49      

     WEEK  50    

Construction  Activity      :  Hardware  Installation  Duration:    5  days  Materials:  Stove  ventilation  hood,  kitchen  cabinets,  etc    Equipment:  Measuring  tape,  level,  screwdriver                                                                                                                                                                                                                                                                                    Skilled  Worker:  3  General  Workers  Technical  Information:  :  After  wall  and  floor  finishs  are  completed,  fixed  furniture  and  appliances  can  be  installed.  

Construction  Activity      :  Painting  (Ground  Floor  and  Part  of  First  Floor)  Duration:    5  days  Materials  roller  brush.  Brush  extention  pole,  Masking  tape                                                                                                                                                                                                                                                                                  Equipment:  large  bucket,  wheelbarrow,  trowel,  garden  hose    Skilled  Worker:  3  General  Workers  Technical  Information:  Paint  provides  an  added  layer  of  protection  to  the  applied  surface.  There  3  components  to  paint;  primer  (improves  the  adhension  of  subsequent  coats),  base  (pigmentation  give  colour)  and  sealer  (reduces  absorption  of  moisture)    

Construction  Activity      :  Painting  (First  Floor  and  second    Floor)  Duration:    5  days  Materials  roller  brush.  Brush  extention  pole,  Masking  tape                                                                                                                                                                                                                                                                                  Equipment:  large  bucket,  wheelbarrow,  trowel,  garden  hose    Skilled  Worker:  3  General  Workers  Technical  Information:  Paint  provides  an  added  layer  of  protection  to  the  applied  surface.  There  3  components  to  paint;  primer  (improves  the  adhension  of  subsequent  coats),  base  (pigmentation  give  colour)  and  sealer  (reduces  absorption  of  moisture)    

Page 44: Construction activities and Process

44   Project  2:  Construction  Activities  and  Process  |  Ibrahim  Adhnan  0314694    

WEEK  51      

     WEEK  52      

Construction  Activity      :  Exterior  Finishes  Duration:    5  days  Materials:  lime  ,sand  ,water  Equipment:  large  bucket,  wheelbarrow,  trowel,  garden  hose    Skilled  Worker:  3  General  Workers  Technical  Information:  :  Apply  the  render  to  the  wall  as  forcefully  as  possible  to  ensure  that  it  keys  into  the  wall  well.  Once  the  first  coat  of  render  is  applied  but  not  yet  set,  scratch  the  surface  throughout  the  wall  to  provide  a  key  for  the  next  layer  to  adhere  to.  Best  done  on  cool  and  cloudy  day.    

Construction  Activity      :  Cleaning  Duration:    5  days  Materials:    Equipment:  Mop,  cloth,  vacumn                                                                                                                                                                                                                                                                                    Skilled  Worker:  3  General  Workers  Technical  Information:  To  remove    all  the  dirt  before    Handing  over.