construction innovation: the millau viaduct deck launch paul eliasson brian follweiler
TRANSCRIPT
![Page 1: Construction Innovation: The Millau Viaduct Deck Launch Paul Eliasson Brian Follweiler](https://reader036.vdocument.in/reader036/viewer/2022083004/56649d9c5503460f94a84bf7/html5/thumbnails/1.jpg)
![Page 2: Construction Innovation: The Millau Viaduct Deck Launch Paul Eliasson Brian Follweiler](https://reader036.vdocument.in/reader036/viewer/2022083004/56649d9c5503460f94a84bf7/html5/thumbnails/2.jpg)
Construction Innovation:The Millau Viaduct Deck
Launch
Paul Eliasson
Brian Follweiler
![Page 3: Construction Innovation: The Millau Viaduct Deck Launch Paul Eliasson Brian Follweiler](https://reader036.vdocument.in/reader036/viewer/2022083004/56649d9c5503460f94a84bf7/html5/thumbnails/3.jpg)
The Millau Viaduct
• Recently completed Cable-Stayed bridge in Southern France.
• Built to span the plateaus of the Tarn Valley.
• Boasts the highest bridge pylons in the world. The deck rises 1,125 ft above the ground.
![Page 4: Construction Innovation: The Millau Viaduct Deck Launch Paul Eliasson Brian Follweiler](https://reader036.vdocument.in/reader036/viewer/2022083004/56649d9c5503460f94a84bf7/html5/thumbnails/4.jpg)
![Page 5: Construction Innovation: The Millau Viaduct Deck Launch Paul Eliasson Brian Follweiler](https://reader036.vdocument.in/reader036/viewer/2022083004/56649d9c5503460f94a84bf7/html5/thumbnails/5.jpg)
Construction Overview
• Temporary piers used to help launch and support the deck as the the pylons were constructed.
• The 2460m deck was launched in two pieces.
• Pylons and cables were added on top of the piers.
![Page 6: Construction Innovation: The Millau Viaduct Deck Launch Paul Eliasson Brian Follweiler](https://reader036.vdocument.in/reader036/viewer/2022083004/56649d9c5503460f94a84bf7/html5/thumbnails/6.jpg)
Deck Launching
• 7 temporary piers help support the weight of the deck.
• 2 deck segments are launched from the each end of the bridge.
![Page 7: Construction Innovation: The Millau Viaduct Deck Launch Paul Eliasson Brian Follweiler](https://reader036.vdocument.in/reader036/viewer/2022083004/56649d9c5503460f94a84bf7/html5/thumbnails/7.jpg)
Hydraulic Launchers
• Computerized launchers push the pre-fabricated deck segments onto the piers.
• Each cycle moves the deck 600mm. Total of 5000 cycles required.
![Page 8: Construction Innovation: The Millau Viaduct Deck Launch Paul Eliasson Brian Follweiler](https://reader036.vdocument.in/reader036/viewer/2022083004/56649d9c5503460f94a84bf7/html5/thumbnails/8.jpg)
Nose Recovery
• Weight of steel box-girder deck sags as span is completed.
• Nose recovery system attached to raise the deck to the level of the next pier.
![Page 9: Construction Innovation: The Millau Viaduct Deck Launch Paul Eliasson Brian Follweiler](https://reader036.vdocument.in/reader036/viewer/2022083004/56649d9c5503460f94a84bf7/html5/thumbnails/9.jpg)
Completion
• Two deck segments joined in May of 2004.
• Opened to traffic on December 16, 2004. This new route shaves 60km off the Paris-Barcelona route.
![Page 10: Construction Innovation: The Millau Viaduct Deck Launch Paul Eliasson Brian Follweiler](https://reader036.vdocument.in/reader036/viewer/2022083004/56649d9c5503460f94a84bf7/html5/thumbnails/10.jpg)
![Page 11: Construction Innovation: The Millau Viaduct Deck Launch Paul Eliasson Brian Follweiler](https://reader036.vdocument.in/reader036/viewer/2022083004/56649d9c5503460f94a84bf7/html5/thumbnails/11.jpg)