construction of quarry house - nao
TRANSCRIPT
NATIONAL AUDIT OFFICE
REPORT BY THE
COMPTROLLER AND
AUDITOR GENERAL
Construction of Quarry House
ORDERED BYTHE HOUSE OF COMMONSTO BE PRINTED29 MARCH 1996
LONDON: HMSO
HC 333 Session 1995-96Published 19 April 1996 f9.15
CONSTRUCTION OF QUARRY HOUSE
This report has been prepared under Section 6 of the National Audit Act, 1983
for presentation to the House of Commons in accordance with Section 9 of tbe
Act.
John Bourn
ComptroUer and Auditor General
National Audit Office
28 March 1996
The ComptroUer and Auditor General is the head of the National Audit Office
employing some 750 staff. He, and the NAO, are tota~y independent of
Government. He certifies the accounts of all Government departments and a
wide range of other pubtic sector bodies; and he has statutory authori~ to
report to Parliament on the economy, efficiency and effectiveness with which
departments and other bodies have used their resources.
CONSTRUCTION OF OUMRY HOUSE
Contents
Summary and conclusions
Part 1: Introduction
Part 2: Wig of the project
Part 3: Cost of the project
Part 4: QuaSity of the bdtig
Appendices
1: Chronology of key events
2: Organisation of the Department of Health and
Department of Social Security
3: Management responsfifities for the Quarry House project
4: Budgets and costs for the Quarry House project
5: Examples of ener~ efficiency measures tith a pay-back
period greater than three years
Page
1
7
11
19
30
42
44
45
46
47
Qu,,rry HuusI!: East E,ltrarlc(! S~)urc(!: I)t)rcl][:sl[!r- 1.tdt)(!ttl:r I’llf)togr;il]t)(rs
West Entrance (;owyard atrium (paragraph 4.26)
CONSTRUCTION OF QUARRY HOUSE
Summary and conclusions
1 In November 1989, Ministers announced that a substantial amount of the
headquarters work of the Departments of Health and Social Security wodd
relocate to Leeds. The main aims of the relocation were to improve efficiency
through lower accommodation and salary costs and easier recruitment and
retention of high quatity staff.
2 Under a contract with NorWest Hoist, Quarry House, Leeds, was accordingly
constructed to accommodate about 2,100 staff of the Benefits Agency’s Central
Sefices, the Central Adjudication Service and the NHS Executive, The National
Audit Office examined the management of this project and its outcome.
Was the building completed on time?
3 Meeting planned occupation dates was a crucial part of the project. The
Departments succeeded in occupying the final phase of Quarry House by the
planned date of February 1993. They addressed au fire, health and safety issues
before occupation, but some building work remained outstanding
(paragraphs 2,7 to 2.10),
Was the building completed tithin budget?
4 At a total cost of E79,7 mi~on the Departments constructed and fitted out
Quarry House tithin the budget of S85.2 mi~on. The National Audit OfOce
calctiated a cost per s~are metre of S1 ,095 which compares favorably with
similar headquarters buildings (Figure 7, paragraphs 3.3 and 3.10),
Did the btiding meet the Departments’accommodation needs?
5 The office areas of the buildlng have been btit and fitted out to a standard
comparable with private sector head office accommodation (paragraph 4.30)
6 The building provided about 1,850 square metres (nine per cent) of office space
less than the Departments had specified. This was because the design made
instilcient a~owance for circdation space and for plant and machinery. These
shortcomings were identified by the Departments when they began detailed
space planning, by which time it was too late for designs to be changed. To
compensate for this shortfaU the Departments accepted the contractor’s offer to
convefi roof space, intended for futue expansion, into offices at no cost to the
Departments (paragraphs 4.22 and 4,23).
1
CONSTRUCTION OF QUARRY HOUSE
7 The Departments did not carry out any financial appraisal of this work, but
recognised that it allowed them to meet their timetable for occupation of the
building and avoid the possibility of lengthy and cosdy litigation. But there sti~
remained a shortfall of 460 square metres (two per cent) and this, along tith an
increase in the size of the Benefits Agency and an increased re@rement for
cellular office space by the NHS Executive, led each of the Depar~ents to rent
separately space in another building in Leeds at an aggregate annual rent of
S705,600 (paragraphs 3.8 and 4.23).
Did the Departments achieve plannedaccommodation savings?
8 The Departments estimated that the relocation would achieve savings in
accommodation and staff costs of 821.6 milhon a year. The Departments now
expect that such savings will be about El 5.6 million a year at 1993-94 prices,
El 3.3 miMon of which relates to the release of vacated space to Prope~
Holdings. But reahsing these savings to the Exchequer depends on the abihty of
Property Holdings to dispose of surplus accommodation in the prevaihng
market or to find an alternative use for it (paragraph 3.17).
9 The relocation coincided witi a major rationahsation of the Departments’
London estates. By the end of 1993, the Departments had vacated about
82,000 square metres in 22 buildings. The Department of Health calctiated
savings on the basis of the average per capita cost of accommodating staff in
London after rationalisation. The Department of Social Security based their
savings on the cost of accommodation occupied at the time of the relocation.
These were reasonable methods of assessment, given that it was not possible to
determine precisely the savings which would arise from relocation and those
from rationahsation (para~aph 3.17 and Figure 10).
10 Property Holdings found it difficult to dispose of or find tenants for au of the
space surrendered and in February 1996 continued to pay rent on vacant space
in one office building previously occupied by the Department of Health, Because
of the concurrent rationa~sation it is not possible to qnanti~ to what extent the
savingsattributedbythe Departmentto relocationmighthavebeen affected.However, it is unlikely that the financial case supporting the move wotid have
been affected materially (para~aph 3.17).
my did the Departments place the contract withNorwest Hoist?
11 The Departments awarded the contract to NorWest Hoist because their design
was strongly favoured by au the major parties concerned with the project. They
also considered that it would provide a building with a better environment for
staff and folly justified an additional cost of S2.67 milhon over the lowest bid
which was from BaEour Beatty (paragraphs 4.15 and 4.16).
2
CONSTRUCTION OF OUMRY HOUSE
12
13
It is clear from the papers that the Departments made a detailed analysis,
involving both qualitative and quantitative factors, in reaching their decision to
award the contract to NorWest Hoist on value for money grounds. However, as a
subsidiary point of good contracting practice, the National Audit Office found no
evidence that the Contract Award Panel saw a report by ~EC who, as the
Departments’ project manager, provided an evaluation of the bids and who
argued in favour of BaKour Beatty. The Department used WEC’S report to
make a detailed comparison of the bids on a hke for hke basis. However, in the
opinion of the National Audit Office there would have been advantage to the
Panel in seeing the ~EC document itself (paragraph 4.18).
Lessons learned
The Departments foUowed good practice in a number of instances, but there are
a number of lessons relevant to future relocation projects.
Examples of good practice adopted by theDepartments:
a) The Project Team had no previous experience of construction work but
arranged relevant training. They also employed a technical adviser who was
recommended by the Treasury Central Unit on Procurement
(paragraph 1.12),
Codssiontig departments shodd develop an hteffigesst cfient role by
acqniriig expertise in managing btitig projects
b) At the outset the Departments set a timetable for occupation of the new
building, prepared a detailed specification which defined their requirements
and agreed cost estimates. These factors determined the Departments’
contract strategy (para~aphs 2.13 and 2.14).
Departments shoufd set quant~led and prioritised objectives in terms of
time, cost and qutity before selectiug the contract strategy
c) The Departments chose a design, develop and construct contract as the most
appropriate method for achieving fast dehvery and price certain@. This
strategy placed the balance of risk for time and cost overruns with the
contractor, but Emited the scope for the Departments’ control of design
changes. In the event design shortcomings led to a shortfa~ in office space
(paragraphs 2.14 and 4.21 to 4.23).
Departments shoufd choose the contract strategy most appropriate to
their needs. A design develop and constrnct contract, for example, may
not be snitable where a department wishes to retati fnff control over the
design
CONSTRUCTIONOF QUMRY HOUSE
d) The Project Team were closely involved in the management of the
construction. They were successful in hmiting the number of variations to
tbe contract, thereby avoiding any significant time and cost overruns.
Variations were kept to about three per cent of the contract price. Only one
change, to the specification for information tecbnolo~, delayed the early
phases of occupation. But it did not affect completion of the final phase
(paragraphs 2.15 to 2.17).
Departments shotid be fwm in keeping projects tithm their timetables
and shotid, wherever possible, avoid contract variations which might
cause signiRcant time and cost overrnns
e) Nthough clearance of some defects is taking a long time to resolve, the
Project Team monitored defects and discussed these at re~ar internals with
the project manager and contractor (paragraphs 2,8 to 2,12).
Procedures shmdd he estah~shed so that defects are corrected as soon
as possible
0 Close involvement with the progress of construction was effective in
minimizing legal claims with consultants and contractors. Potential claims
were dealt with as they arose through meetings with the project manager
and contractor instigated specifically for this purpose. This enabled the
project team to agree provisional the final account for the bnildlng contract
when building work, excluding defects work, was completed
(para~aph 3.22).
Departments shotid address claims by contractors as they atie and
agree a provisional fmd amount on completion of construction
g) The Project Team recognised the importance of developing a good ~aEty
design for the exterior of the building. They began discussions tith Leeds
City Council some five months prior to the apphcation for outhne planning
permission and sought the views of the Royal Fine&t Commission at an
early stage. This prompt action helped the design for Quarry House to gain
planning approval without compromising the Departments’ tight timetable
[paragraphs 4.8 to 4.1OJ.
Departments can minknise the time taken to secure plantig approval
hy early crmstitation at the concept design stage
Other lessons from the Departments’ experience
h) The initial timetable for constructing Quarry House was unreahstic. The
revised final completion date was feasible but tight and did not include any
contingency for deahng with problems. This created difflcdties for the
Project Team because the size and structure of the occupying organisations
4
CONSTRUCTION OF QUMRY HOUSE
were ucertain and continued to change throughout the project. The
Departments did provide a contingency for possible cost increases
(paragraphs 2.5 and 3.4).
Departments shoufd consider inclntig time and cost contingencies
tithm budgets for deahg with unforeseen problems, such as the size
md strnctnre of the occupying organisations
i) The Departments opted for phased occupation because it slowed the earhest
relocation of staff into the building. However at each phase there was
outstanding building work which caused some disruption to staff while it
was completed. The presence of staff in torn added to the time taken to
complete this work (paragraphs 2.4, 2.9 and 2.12).
Departments should consider the disruption to staff and contractorsbefore adoptimg a phased handover of a btitig, particularly where
there is tilted site space
j) The Departments drew up separate business cases for Quarry House which
showed a strong financial justification for the project. The revised and
outturn cases continued to suppofi the project but they contained some
omissions and inconsistencies, the effect of which was to over-state the
financial case for the relocation (para~aphs 3,13 to 3,17).
Were joint projects are involved Departments should co-ordinate
business cases so as to avoid inconsistency of treatment
k) The Depa~ents developed procedwes for regnfar monitoring and
discussion of design issues. Despite these measmes it was not mtil
construction was well advanced that they identified a shortfaU in available
office space. Neither ~EC nor Nomest Hoist were aware of the shofifa~
(paragraphs 4.22 and 4.23).
Depwtments shoufd protide sufficient time for design development and
monitor design work closely
1) The National Audit Office’s consultants put a value of E300,000 on items in
the Departments’ spectilcation, such as floor loadings and electricity
capacity, which they considered were in excess of indust~ good practice,
They accept that these specifications had been prepared in accordance with
Property Services Agency guidance at that time and on the basis of advice
from MEC. The National Audit Office recognise that a reduced specification
might not have produced a lower tender price (paragraphs 4.30 to 4.32).
The National Audit Office’s consultants also considered that there were some
omissions, for example single-glazing of the atfia which had been
recommended by the Depatiments’ adtisers. The National Audit Office’s
constitants considered that double-glazing might have increased costs by up
to E250,000, but would have improved the working environment where
there have been continuing problems since the building was completed, A
5
CONSTRUCTIONOF QUAORYHOUSE
technical audit undertaken by constants in September 1994 drew attention
to problems of temperature control related to the single glazing of the atria
waUs. The Departments told the National Audit Office that they fo~owed the
guidance provided by their consultants at the time and that in their tiew
groups of experts will take different views on these matters
(paragraphs 4.33 to 4.36).
Departments shodd assess the cost consequences of setttig
requirements in excess of industry good practice. Departments shmdd
make nse of value en~eering techniques, in order to test resumptionsand ebtiate unnecessary costs
m) The design specification for Quarry House required long Me and low
maintenance costs for the building’s finishes. The Departments reheal on
their project managers to ensure that this requirement was met and did not
set specific quantitative targets, making it difficult to measure whether the
building is as e~cient as intended (paragraphs 4.38 and 4.39).
Departments shodd requhe long Me and low mbtenance costs for a
btiding’s Mlshes and shodd express ttis in quantitative rather than
just qnahtative terms
n) Energy efficiency measures in Quar~ House were hmited because, on the
advice of the Departments’ energy advisers, such measwes had to pay for
themselves within three years. The National Audit OffIce’s advisers
considered that a period of five to seven years may have been more
aPPrOprlate (parawaphs 4.4o and 4.41).
SpecW1cations shmdd hclude Me cycle costs and an appropriatepay-back period for energy efficiency measures
The National Audit OffIce consider that these are important lessons for
departments in view of their increasing responsibihties for works projects.
6
CONSTRUCTION OF QUARRY HOUSE
Part 1: Introduction
1.1 Quarry House, Leeds protides 33,900 square metres of office and support
space. It was constructed between December 1990 and June 1993 to
accommodate about 2,100 staff of the Benefits Agency headquarters, the
Central Adjudication Semite and the NHS Executive.
Reasons for the relocation
1.2 Since 1988, the Government have required departments to consider whether
relocating their offices might secure cost savings and improvements in staff
recruitment and retention and in service dehvery.
1.3 During 1989, in response to this requirement and to rising accommodation
costs and shortages of ski~ed staff in London and the South East, the
Departments of Health and Social Security examined the scope for relocating
their headquarters functions. Their reasons for relocating away from London
and the South East included:
. the cost of renting and maintaining old, outdated and inefficient buildings;
. persistent problems of recruiting and retaining quatiled staff;
. the dlficufties in the epread of work across 19 different sites in London; and
. the expense and dificufty of attracting staff to move to London from the
provinces, even on promotion.
1.4 The relocation was planned at a time of rapid change in the Departments
(Append& 1). In January 1989 the Department of Health announced their
intention to create the NHS Executive and in May 1989 the Depa~ent of Social
Security announced their intention to create the Benefits Agency.
1.5 The relocation review identified financial and operational benefits from
relocating the new organisations, together with the Adjudication Service
(Appendix 2), However, at this stage, the Departments had not determined the
functions, structures and staffing of the Benefits Agency and NHS Executive.
Site selection
1.6 In January 1989, the Departments commissioned property professional, Jones
Lang Wootton, to undertake a location analysis. This identified Leeds and
Manchester as locations which met the Departments’ criteria. These covered a
number of factors relating to the Departments’ operational needs and the hving
environment for staff, such as an area’s accessibihty and educational facihties.
7
CONSTRUCTIONOF QUMRY HOUSE
Jones Lang Wootton concluded that there were a nmber of suitable sites in
both cities. The Deparwents selected Leeds because they considered it wodd
offer advantages in the Hving environment for staff such as easier commuting
and a buoyant local economy and housing market. A GaUup survey of staff
showed a preference for Leeds rather than Manchester.
1.7 In October 1989, the Departments commissioned the former Proper@ Setices
Agency to evaluate four development sites in Leeds. The Agency’s evaluation
and the Departments’ inveshent appraisal in January 1990 both identified
Quarry HiU as the most suitable site. The Depar@ents estimated that the cost of
constructing Quarry House would be fl 2.5 miMon less than the cheapest
single-site option offered by a developer. The Departments prefemed co-location
because it would provide economies of scale, flexibihty and a viable career
structure for their staff.
1.8 In November 1989, the Secretaries of State for Health and of Social Secmi@
announced the relocation of a substantial number of head office posts to Leeds.
The moves were due to start in late 1991.
Organisational changes
1.9 The relocation was hnked to two exercises to rationahse the Departments’
Central London estates. In 1990 the Departments occupied 23 btidings in
London, but this fell to 13 buildings by the end of 1993. Of the 2,070 posts
which relocated to Leeds, some 1,630 came from London and 440 came from
nine other locations including Southampton, Lytham St Anne’s and Preston.
1.10 The structures and staffing of the NHS Executive and Benefits Agency have
continued to change during the construction of Quarry House, and since its
completion. This has required the relocated organisations to occupy space in
other buildings; in 1995 the Depar~ent of Social Secmity occupied Quarry
House and ftve other buildings in Leeds and the Depaaent of Health occupied
one other building. The Department of Social Securi@ akeady had a presence in
fonr of these buildings before the relocation; the Department of Health had no
buildings in Leeds prior to relocation. TrevelyanSquareis the onlynewlyleasedaccommodation. In November 1994 the NHS Executive annonnced plans to
reduce their staffing levels in Quarry House by about 20 per cent (200 posts) by
31 March 1997.
Roles and responsibilities
1.11 Quarry House was one of tbe first major buildings on the Government’s civil
estate to be constructed following the untying of depa~ents from the former
Property Services Agency. Each Department established a project team to
manage the relocation and a steering group to monitor progress. The
Department of Health led tbe management of personnel matters. while the
Department of Social Securi@ led the management of the construction project.
The two project teams worked together closely.
8
CONSTRUCTION OF QUMRY HOUSE
1.12 The Department of Social Security’s project team (the Project Team) consisted of
17 staff who dealt with buildlng, planning and control, personnel and contract
matters. The Project Team had no previous experience of construction work, but
arranged some relevant training. The Departments recognised their shortage of
relevant expertise and employed a technical adviser, Martin Drake, who was
recommended by the Treasury Central Unit on Procurement. He worked with
the Project Team to advise them on building and contractual matters
(Figure 1 and Appendix 3).
—
ProjectTeam MartinDrake
A group of 17 Depatimental staffTechnicalAdviser
responsible for overseeing allResponsible for providing advice
building and contract issuesto the Project Team on building
and contract issues
AMECProjecl ManagementTemrr
Responsible for managing thedesign and construction of
the building
Norwest HolslMain Contractor
Responsible for the design andconstruction of the building,including the management of
sub-contractors
Source: National Audit Office ana&sis of Oepaflment of Social Security records
Note: A more detailed description of management responsibilities for the Quarry House projectcan be found at Appendix 3,
1.13 After competitive tendering, the Departments commissioned MEC to produce a
concept design and specification and to manage the detailed design and
construction; and appointed NorWest Hoist, a firm of building contractors, to
produce the detailed design and construct the building (Figure 1 and
Appendix 3),
9
CONSTRUCTION OF QUMRY HOUSE
Scope of the examination
1.14 The National Audit Office study examined:
. how the timetable was set for the project and the reasons for the timescale
achieved;
. how the financial targets were set for the project and how far these were
met and
. how the quahty of the building was spectied and to what extent the project
achieved the required quatity.
1.15 The examination did not address the human resources aspects of the relocation
or the extent to which the move has affected operational efficiency.
1.16 The National Audit Office’s analysis is based on a review of depar~ental
papers and discussions with staff. It also draws on intetiews with Martin
Drake (the Departments’ technical adviser), AMEC, Nomest Hokt, Leeds City
Council Planning Department, the Royal Fine Art Commission, Property
Holdings and the Treasu~.
1.17 The National Audit Office employed Ove Arup and Partners as advisers on
aspects of the examination, They also constited Professor Brian Atkin BSC
MPhil PhD FCIOB and Graham Robinson BSc(Hons) MCIM of the Centre for
Strategic Studies in Construction at the University of Reading.
10
CONSTRUCTION OF QUMRY HOUSE
Part 2: Timing of the project
2,1 This part examines the Departments’ achievement in dehveriug Quarry House
to timetable. It considers:
. how the Departments set the original and revised timetables;
● whether construction was completed within the revised timetable; and
. the steps taken to achieve occupation by the target dates.
2.2 The National Audit Office found that
. the Departments extended their tentative target date for completing the
relocation from January 1992 to December 1992 on the advice of the
Treasury and MEC. They adopted phased construction and occupation to
a~ow for the earhest relocation of staff. They revised the timetable as the
project progressed and circumstances changed (paragraphs 2.4 and 2.5);
. the revised target date for completing the building was tight, because it did
not include any contingency for deahng with problems (Figure 2 overleaf and
paragraph 2.5);
. the Project Team were closely involved in the management of the
construction, including contract variations. Their action was effective in
minimizing delays. Only one variation had imphcations for timing, where a
change in information technology re@rements delayed the f~st two phases
by up to eight weeks, but did not affect completion of the final phase
(paragraphs 2.15 to 2.17);
. the Departments occupied the final phase of the building in February 1993.
To achieve this timetable, it was necessary for phased occupation to take
place before au outstanding buildlng work was completed. The Departments
told the National Audit Office that this did not disrupt the flow of business
intolerably. They ensured that health and safety issues were addressed
before each phase was occupied and that commissioning programmed for
mechanical and electrical services were sufficiently well advanced.
The National Audit Office noted, however, that the practical completion
certificates were not issued until several months after occupation
(paragraphs 2.7 to 2.10); and
. phased handover caused some disruption to staff who were occupyiog
Quarry House while building work was sti~ being undertaken. The presence
of staff added to the time taken to complete the work. Clearance of
outstanding defecte has been protracted and was stiU ongoing in
October 1995 (paragraphs 2.9, 2.11 and 2.12).
11
CONSTRUCTION OF OUARRY HOUSE
~~”z:p~~]~ctid and actual cimple~on dates for the construction Of’QUarry House
Projection as aNovember 198!(Announcement
of relocation
Projection aa aMay 199(
(Concept deaig!stage
Projection as aNovember 199(
(Leting of buildin!contract
Projection as aJuly 199
(Change of 1“specification
Actuaoccupation
date
Iaaue opractical complefio)
certificate
May 1990 October 1991 Januaw 1992
,k
Key to phaaea:
k, ,&1: East Wing
Stati 12 Z Notih and South Wnga3 West Wng4 Expansion space
October 1990 27 March 1992 26 June1992 leOecember1992
h kii
Stati 12 3
Oecember 1990 7Mayi992 3August 19925 February 1993
k kid
Stafl 12 3
Oecember 1990
h
6July1992 31Au ust1992 5February1993
\2 d
Start 12 3
Oecember 1990
\ 6JU’Y’99Y, ‘~t ’992 ,/:::uaw1gg3
Stafl 12 34
December 1990 160ecember 1992 15 January 1993 12 July 1993
k, A,,& ,&
Stat 21 3 and 4
Source: National Audit Office analysis of depatimental papers
Note: Eachsing/e numberbelowa keydatedenotes thecompletion of therespectivephase of the building. Jhefinalcomp/etioncertificate for the building has not yet been issued. Phase 4 was added in November 1991 with the same completion date asPhase 3.
12
CONSTRUCTION OF QUMRY HOUSE
How the Departments set the ori~nal and retisedtimetables
Ori@nal timetable
2.3 In the early stages of planning the relocation, the Department of Social Secmity
intended that the new headwaiters wotid be ready for occupation when the
Benefits Agency was estabhshed in April 1991. However, it @ckly became
clear that this timetable was not feasible. Later timetables were developed with
the aim of aUowing relocation to take place as soon as possible after this date.
The Department of Health did not want to start relocating before tbe bti of
planning the National Health Service reforms was completed.
2,4 In November 1989, the Project Team prepared an outhne timetable which
would allow occupation of the first phase of the btilding in October 1991 and
project completion in January 1992 (Figure 2). The timetable reflected the
Departments’ desire to minimise the period of uncertainty for staff, and tbe
disruption caused to people working away from home while the relocation was
completed. The Departments opted for phased completion because it slowed
for the earhest relocation of staff.
Retised timetable
2.5 In November 1989, the Treasury Central Unit on Procurement advised the
Departments that their tentative initial timetable was Unreahstic. In May 1990,
AMEC drew up a revised timetable, which planned for completion and
occupation of the bnildlng in three phases - by March 1992, June 1992 and
December 1992. This timetable did not include any contingency for deafing with
problems. It was further revised during the project (Figure 2):
. in November 1990, because of delays in obtaining planning consent and
awarding the construction contract
. in Jdy 1991, because of the need to revise the Information Technology (1~
specification; and
. in November 1991 through the addition of a fourth phase, with the same
completion date as Phase 3. This was for fitting out space in the roof area,
which had been intended for expansion at a later date, to compensate for a
shortfaU in office space.
~ether construction was completed within theretised timetable
2.6 Staff occupied Quarry House as soon as the Project Team’s constants advised
them that the building was safe to occupy and mechanical and electrical
systems were operational. Certificates of practical completion were issued by
the Departments on AMEC’S advice when aU building works had been
13
CONSTRUCTION OF OUARRY HOUSE
2.7
2.8
2.9
2.10
completed, but the twelve month period during which the contractor was
required to correct any defects and carry out snagging work started with the
commencement of partial possession of each phase. These partial possessions
took place in advance of the practical completion certificates. Snagging refers to
minor works and adjustments which are often carried out before handover.
Occupation
The Departments’ planned occupation dates drove the construction process.
Occupation began with Phase 1 in Jdy 1992. The Departments occupied
Phase 2 in September 1992 and Phases 3 and 4 in February 1993 (Figure 2)
Practical completion certificates
Mthough there were a number of areas still to be addressed by NorWest Hoist at
Phase 1 handover, such as hfts and air conditioning, the Project Team decided,
on the advice of ~EC and fire and safety building control constants, that the
building met health and safety standards and that it was possible to start
occupying it. Newest Holstmdertook todealquickly with ou@tandingworks
and defects.
As part of their monitoring role ~EC reported in Jtiy 1992 that incomplete
work and defects were causing disruption to staff and directed NorWest Hoist to
take appropriate action. MEC did not recommend issue of the practical
completion certificate for Phase 1 until over sixmonths after tbe Departments
had accepted it for occupation and one month after they had granted the
certihcate for Phase2 (Figure 2). Ove Arupadvised the National Audit Ofice
that, although the final completion date for the building set out in the
Departments’ November 1990 timetable was feasible, the target date for the
completion of Phase 1 works wasnotrealistic. The Departments told the
National Audit Office that all companies tendering for the project management
role, andallcompanies tendering forthemain contract, hadtioughtthe date
achievable. They hadachieved tieirtarget date ofopening Phase 1 of theofflce
in Jtiy 1992 andconsidered that incomplete work onoccupation did not
seriously disrupt the handhng of business.
As the Phase 3 occupation date approached, ~EC reported that progress was
behind schedule. The Depa~ents agreed to defer certain elements of the
project because their later completion would not have affected the staff or
business activities in Quarry House. This action helped the Departments to
occupy the building hy the planned dates. The deferred work included:
partitioning to create ceUular offices not required until the end of the occupation
programme; some work to the courtyards and to the leisure block; and the
fitting out of basements. The Departments dld not grant practical completion
cetilficates for Phases 3and4until July 1993, Overfour months after
occupation (Figure 2).
14
CONSTRUCTION OF QUARRY HOUSE
Snag@g and defects
2.11 The Project Team considered it essential to ensure occupation of the building by
the planned dates. However, while the building was ftiy occupied by
April 1993, snagging and defect rectification work remained outstanding. By
October 1995 this work sti~ had not been completed. Ove Arup advised the
National Audit Office tiat this timescale for remedying defects was longer than
they would have expected for a building of this size and complexity.
2,12 The main causes of the slow progress were:
. some building work was outstanding at the time of occupation (Figure 2).
N parties gave this work a higher priori~ than snagging work. Defects
were, however, discussed regularly with the project manager and the
contractor.
. the volume of work re~red. For example, a routine defects examination
revealed that some fire dampers in the building had been insta~ed
incorrectly. There were several hundred dampers to examine, some of which
were difficult to access;
. the retirement to rectify defects outside office hours so as to avoid
disturbance for staff working in the building; and
. a technical audit commissioned by the building management team in
Jtiy 1994 (Appendix 3). This resulted in a new defects fist. Some of tbe
defects re-opened issues which had previously been addressed to the
satisfaction of the Project Team.
Steps taken to achieve occupation by the targetdates
2.13 The National Audit Office examined the steps taken by the Depatients to
select an appropriate contract strategy which wmdd meet their timetable. The
National Audit Office also examined how the Departments monitored the
construction and managed contract variations.
Contract strate~
2,14 There are a number of contiact strategies which may be adopted in construction
projects (Figure 3 overle~. The Depaments decided to adopt the desi~, develop
ad construct strategy because it offered the potential for fast dehvery, as
development of the design overlaps with construction. It abo enabled a fied price
to be esttihshed ewly in the design process and placed responsibfity for tie and
cost overruns with the contractor, unless proven to be the resub of chent
intervention. N prospective project managers recommended this contract strategy.
In the economic recession of the early 1990s, the Departments were able to
15
A contract strategy sets out the respective roles of the chent, architect, contractor and project manager, and
helps to apportion the potential risks between thsse paties.
StrategyTraditional
Construction
management
Management
contract
Design and manage
Design and build
Design, develop and
construct
Definition
Architects first draw up a detailed design for the building. Contractors then tender
for, and carry out, construction of the building.
The petiod of design by the clen?a consultants and the construction period
overlap. A fee earning construction manager defines and manages the work
packages. All contracts are between the chent and the trade contractors. The final
cost can only be accurately forecast when the last work package has been let.
The period of design by the client’s consultants and the construction peflod
overlap. A management contractor is appointed early in the process to let elements
of work. The contracts are between the management contractor and the trade
contractors. The final cost can only be accurately forecast when the last work
package has been let
Similar to the management contract, with the contractor also responsible either for
producing the detailed design m managing the detailed design process.
A single contractor accepts responsi~tify for design and construction in return for a
lump sum price.
As with design and build, except that a concept design is developed before the
contractor is appointed. This strategy places the risk of responsibility with the
contractor.
Source: National Audit Ofice and tieasuy Central Unit on Procurement guidance.
Note: The design, develop and construct strategy selected by the Depaflments had the advantage of
determining a contract price earti in the construction process. This meant that many of the
problems encountered during the project were resolved at no additional cost to the Depaflmenfs.
transfer these risks to the contractor at httle or no cost, but this may not always
be the case. The Departments appointed Newest Hoist in November 1990 to
design and construct the building.
Monitoring arrangements
2,15
2.16
The timetable for occupation was tight and close monitoring of the bnildlng
work was essential if target dates were to be met. At the outset, the Project
Team drew up a detailed action plan showing the milestones to he achieved.
The Project Management Board met every fortnight and progress against the
action plan was discussed each month by the relocation steering groups
(Appendix 3).
As project managers, AMEC monitored pro~ess on the building contract and
the Departments exerted control through detailed monthly reports and monthly
meetings with AMEC and Nomest Hoist. Throughout the project, NorWest Hoist
had difflcdties in keeping to the programme. Figure 4 shows the roles of the
various parties on a typical design, develop and construct contract and the
additional input made by the Project Team and technical adviser on this project.
16
CONSTRUCTION OF QUMRY HOUSE
ClientDeDatiments
Select and appointcontractor L
‘ey: ~ Main action
O Input
Source: National Audit Office
Depatimentai ProjectTeam and
technical adviser
zSelect contractstrategy
Select and appointproject manager
AMECPrOiect manager
(Concept designer)
*
mIssuecompletioncertificates I
Norwest HoistContractor
(Design, developand construct)
T
A COmulete 1
This figure shows typical management responsibilities for design, develop and construct building projects. The numberedcircles represent additional management input required in the construction of Quarry House.
Key to numbered circles1. The Project Team leader and technical adviser became involved in the management of the project during construction to overcome a
potential breakdown in communications between the project manager and the contractor.2. The Project Team leader maintained direct contact at senior level with the contractor’s organisation to ensure that deadlines would
be met.3. The project manager became directly involved in meetings with sub-contractors as deadlines approached.4. The length of the defect rectification period means that responsibility for completion of defects work has passed to the Benefits
Agency’s building management team.5. The Project Team’s involvement continued for two years after occupation because of diticulties in cleating snagging and defects.
17
CONSTRUCTION OF QUAORYHOUSE
2.17
They found that informal direct contact with the contractor produced better
results than the more confrontational document-based approach adopted by
~EC in the early stages of the project. They sometimes withheld M payment
to encourage NorWest Hoist to recover shppage. Their action was successfti in
minimizing delays. To maintain target dates, the Project Team a~owed some
relaxations of the specification, such as rescheduhng the installation and testing
of semices.
Contract variations
The Departments’ Project Management Board had authori@ to alter the
specification, but only did so after first estabtishlng the Ml time and cost
imphcations of proposed contract variations (AppendM 3). In total there were
141 variations. Only the change to the IT cabfing extended the timetable - for
Phase 1 by eight weeks and Phase 2 by four weeks (paragraphs 2.5 and 3.20
and Figure 2). Ove Arup told the National Audit Office that this reflected weU on
the Team’s efforts (paragraph 3.20).
18
CONSTRUCTION OF QUMRY HOUSE
Part 3: Cost of the project
3.1 This part considers how the Depatients set financial targets for the
Quarry House project and whether these targets were met. It considers:
. the cost of Quarry House compared tith the budget
. the preparation of the budgets and business cases; and
. how project costs were contro~ed and monitored and the action taken to
minimise outstanding financial commitments.
3.2 The National Audit Office found that
. the total cost of the building project was S79. 7 mi~on which included
S55.4 mi~on (at 1993-94 prices) for constructing Quarry House.
This compared with the Departments’ revised budget of E85,2 miMon
(1993-94 prices). The Departments are also paying rent of S705,600 a year
for extra accommodation in Leeds, This arose from an increase in the
number of Benefits Agency posts relocated to Leeds, a greater than expected
requirement for ceUular office space for the NHS Executive and loss of office
space in Quarry House as the building design was developed (paragraphs 3.3
and 3.5 to 3.8);
. detailed budgets were prepared and revised as the project progressed. The
Departments monitored and controled costs closely (paragraphs 3.12, 3.19
and 3.20):
. the cost of building Quarry House was at the lower end of the range of
construction costs for similar headquarters buildings (paragraph 3.10);
. the initial business cases showed that relocation would save the Departments
S21.6 mi~ion a year in running costs (1993-94 prices), with a break even
point for the project at year 14 (paragraph 3.15 and Figure 8);
. the final business cases show that the net annual savings are expected to be
El 5.6 milfion at 1993-94 prices; as a result, the break even point wi~ take up
to five years longer to achieve than expected. The cases rely heavily on
notional savings mainly from vacated office accommodation in London,
which are reahsed when Property Holdings manage to dispose of the
accommodation. In February 1996 Prope@ Holdings continued to pay rent
on vacant space in one office building preciously occupied by the Department
of Health; it is uuhkely that the financial case supporting the move would
have been materia~y affected by delays in disposing of property (Figures 8
and 9 and paragraph 3.17);
19
CONSTRUCTION OFOU~RY HOUSE
3.3
3.4
. the National Audit Office noted some omissions and inconsistencies in the
business cases, mostly in the revised and outturn cases; but because of the
notional nature of some elements they were unable to Wanti& their impact
(paragraph 3.17 and Figure 10); and
● the Project Team agreed provisionally the final account for the bnildlng
contract promptly on completion of building work. They successftiy avoided
any financial disputes. In April 1995 the Departments retained S280,000
pending completion of outstanding defects work (paragraphs 3.22 and 3.23).
The cost of Quarry House compared tith budget
The Departments succeeded in dehvering Quarry House within the total project
budget of S85.0 miMon set in February 1990, which was revised in Jtiy 1991 to
E85. 2 million (at 1993-94 prices). The total cost of the project was S79. 7 mi~mr
at 1993-94 prices [Figure 5 and Appendix 4).
Initial budget Revised budget Actual
February1990 July 1991 expendituref million f million f million
Builr6ng contract with 48.7 56.8 55.4
Norwest Hoist
Other capital coats, eg 31.5 22.4 18.7
land
Non-recurring running 4.8 6.0 5.6
costs
Total project costs 85.0 85.2 79.7
Source: Arationa/Audit OMce ana~sis of depatimerrtalpapers
Notes: 1. A more detailed comparison of budgets against actual expenditure can be found atAppendix4,
2. All figures except those for the building contract with fdorwest Ho/stare expressed in
1993-94 prices.
Hgure 5 ahowa that total Depatimental expenditure relating to the building project was lower than both the
budget set at the stat of the project and the revised budget set in July 1991. The cost of the buildng
contract with Norwest Hoist was higher than the initial budget but lower than the revised budget.
Major project costs
Mter competitive tendering, the Departments contracted NorWest Hrdst to
construct Quarry House. Following the award of the contract the Departments
set a construction budget of f57.7 milhon. This was based on the contract price
of S53. 7 mi~ion and S4 milhon for contingencies (Figure 6 opposite).
20
CONSTRUCTION OF OU~RY HOUSE
3.5
3.6
3.7
, ~~.. .... ,.- :..,,s ~~.’~,., .. ... .~,, : < ,, ~’~‘~ :-:.. .; , ?!.-!,~.,,,?r..,, . ,~! ,.. ?.?.>.:... . “:,,W9ure6:Bud9el:estl,rnaiesforthe;tiulldin9:conlractwl!tiNor.Yg:tHpJ:!... .,....,:.:,,:..,.,....4--.,=,; :?,..,.:.,:....... ,..::.:,,,,;',,..,:.-,~:...,...,...,,.,,>*:,.:..?2,.. ....... ,,..... : . . .:. ., ,’.::.’. <....,- ‘.. -.,,
Date Budget Budgeted cost
f million
Febmaw 1990 Initial budget, excluting contingency 4B,7
March 1990 Revised budgetBuilding work f60,0 millioni
Contingency f 0.5 milfionz 60.5
December 1990 Revised budget following contract
award
COntrati sum f53.7 milfionl
Contingency 23.2 milhonz
York stone f 0.2 milhon3
Further contingency f 0.6 mi160n4
July 1991 Estimated outturn
March 1993 Actual outturn
57.7
56.6
55.4
Source: NatiorralAudit Office ana~sia of departmental tiies
Notes: 1. Includes a provision for inflation.
2. The contingency was increased to 6percent of the contract sum to reflect ~easu~guidance.
3. Additional York stone was required to that included in the contract sum.
4. The furfhercorrtingency covered poterrfiaiadditional costs relating to furniture and fitting out
for the restaunnt, leisure facilities and public areas.
The final cost of the building, excluding land, was f55.4 mi~on (Figure 5 and
Appendix 4). The additional fl.7 million of expenditure over the contract price
(but within the budget for contingencies) arose from changes re@red by the
Departments. These included a revised IT specification, increased partitioning
and enhancement of the West Entrance (paragraph 3.20).
The f55.4 milhon cost of the building included the leisure facihties. In addition,
the Departments contributed to the Government’s “Percent for ~ initiative,
mder which those responsible for major building projects are asked to use a
proportion of the capital budget to commission works of afi or crafts. The
Project Team decided that the work undetiaken within the huildlng contract to
construct and landscape the courtyards, valued at S543,000, could be attributed
to the scheme. Further commissions brought the total expendltore under
“Percent for M to f706,600.
The cost of land, at S8 mi~on, was in fine with the District Valuer’s valuation.
The Property Semites Agency conducted, on the Depatiments’ behaff, early
negotiations for a site at Quarry HiU. However, in December 1989, the Project
Team considered that the fou acre plot was too small for the Departments’
needs and was poorly situated. They re-opened negotiations and secured a
more prominent site of 5.7 acres at Qua~ Hill for no extra cost.
21
CONSTRUCTION OF QUARRY HOUSE
3.8
3.9
3.10
3.11
3.12
Other project-related costs
Other costs, excluding land, associated with the project (E16.4 milhon) iucluded
the contract with ~EC, furniture, telecommunications and the Departments’project teams (Appendix 4). The Department of Health spent an additional
S8.4 miUion on advancing the development of a new office information system
to coincide with the relocation. The Benefits Agency and the NHS Estates
Agency also took out separate 25 year leases on additional space
(3,880 square metres) at 1 Trevelyan Square, Leeds at an aggregate annual rent
of S705 ,600. The additional accommodation was needed because of an increase
in the number of Benefits Agency posts located in Leeds, a Weater than
expected requirement for cellular office space for the NHS Executive and
because of the loss of office space in Quarry House as the bnildlng desi~ was
developed.
The total shotifall of office space was some 1,850 square meties; even after
fitting out the expansion space there remained a net loss of 460 square metres.
There will be an oppotiunity cost to the project as the expansion space wi~ not,
as intended, be available for futme development. However, tils cost is dlfflctit
to quantify, partly because the cost of fitting out the expansion space is not
known. The Departments told the National Audit Office that had additional
office space been needed, it wodd probably have proved cheaper to lease other
accommodation than to undertake this conversion.
Comparison of building costs tith other projects
In order to assess the reasonableness of the construction costs for Quar~
House, the National Audit Office’s consultants compared them with five
buildings constructed between 1987 and 1992. The comparable btidings were
constructed to a head office standard for reasonably sized, weU estabhshed
companies and offer similar office accommodation to Quarry House. The
analysis showed that the cost of Quar~ House compared favorably with the
costs for constructing these buildings (Figme 7 opposite),
Quar~ House includes leisure facihties: two squash COWS, a bar, fitness room,
spotis hall and swimming pool. The costs of these facihties were not separately
identified.Staffpay to use thesefacihties,whichare alsousedbygroupsin tielocal community,
The preparation of budgets and business cases
The Depatients’ main financial controls were the monitoring of outtin<.
\
against budgets and the business cases for the relocation, The National Audit
Office found that the budgets had been well prepared and included au relevant
costs. The initial business cases fully supported the Departments’ decision to
proceed with the relocation.
22
CONSTRUCTION OF OUMRY HOUSE
3.13
3.14
3.15
3.16
Quarw House
Building 1
1,095
947
Buildng 2 1,055
Buildng 3 1,293
Building 4
Building 5
1,294
1,631
Source: Natimar/Audit Ofticeb cmrmdtrmts
Notes: 1. Costs sre based on the total floor area within the inside face of the buildirrgk walls.
2. Actual costs pmsquare metre for buildings 1 to 5 have been aflusted to match the
specification for Quarv House, excluding the swimmhrg pool. For the purposes of this
exercise, the cost of the swimming pool was estimated by Ove Amp as the actual
construction cost was not separately identified,
figure 7 shows that the cost of constructing Quarv House is towards the lower end of the range of costs
of constructing five similar buildings. The comparable buildngs provide head office standard ofOce
accommodation for reasonably sized well eatabflshed companies.
Business cases
The Treasury require depatiments to assess the financial viabih~ of proposed
projects by carrying out investment appraisals which discoont costs and savings
to a base year. The difference beween discounted costs and savings is the net
present value of the investment proposal. To be cost-effective, projects should
produce a positive net present value over the expected project fife. Investment
appraisalsshodd be updated regularly to ensure that a project continues to be
cost-effective.
The Departments prepared separate business cases for approval by their
respective Treasury Expenditure Ditisions. In October 1989, Treasury approved
the general decision to relocate to Leeds on the basis of the outline appraisak.
Project finding was aUocated on the basis of the first fu~ business cases which
the Departments produced in February 1990; these indicated a combined
positive net present value of S165.1 milhon (at 1993-94 prices) over 60 years,
with the project breaking even by year 14 (Figure 8 overleaO
At that time, this conclusion assumed that relocation wodd secure the
Departments accommodation and staff satigs of E21.6 miltion a year at
1993-94 prices (Figure 9). The Department of Health did not subject their full
business case to sensitivity analysis for changes in circumstances, for example
the changes in staffing levels, the effect of time or cost overruns. Neither
Department assessed the effect on the cases of changes in the rents of vacated
accommodation.
The Departments retised the business cases during the project to reflect
changes in phasing dates and as firmer information on costs and benefits
emerged. Outturn cases were based on actual costs as far as possible. However,
23
CONSTRUCTION OF QUARRY HOUSE
October 1989February 1990
July 1991
July/August 1991FebruaW1993July 1993
October 1993July 1994
July 1995
Department ofSocial Security
f million
46.0
74.9
25.0
44.8
Net present value
Department of Project total Department of
Heallb Social Security
f million f million
55.8 101.8 Year 6
90.2 165.1 Year 13
Year 23
92.1
108.374.9
Year 17
53.2
72.0
Department of CombinedHealth
Year 5 Year 5
Year 15 Year 14
Year 15
Year 15Year 16
Year 21
Year 19
Source: National Audit Office anavsis of business cases
Notes: 1.
2.
3.
4.
5.
6.
All monetary values are expressed at 1993-94 prices.
Project totalarrd combined break-even dates are given where the Depatimentsprepared business cases at a common date,
The 1989 cases were prepared to obtain outline approval from Treasurya#er the Departments had decided to relocate to Leeds
but before they decided to construct a new building at Quar~ Hill.
The first full busbreaa cases were drawn up in Februa~ f990.
The casea drawn up in October 1993 and Ju~ t994 were outturn cases.
The Depaflment of Health published the final evaluation of their business case in Ju~ f995, The National Audit Ofice noted
that this did not take account ofa reduction of200posts in the NHS &ecutive being phased in over2years from 1995-96,
Figure 8 shows that the flrat full business cases for the project had a combined net present value of 2165.1 milhon at 1993-94 prices over 60 yearn,
with the project breakng even in Year 14, Later appraisals were constructed at different times by the two Departments, and included different cost
assumofiona
the revised casea were produced nearly WO years apart (Figure 8). There were
also other significant variations between the ho (Figure 10). These factors
prevented the National Audit Office from assessing accurately tbe financial case
for the project as a whole.
3.17 In examining the business cases the National Audit Office noted:
. the revised appraisals continued to show positive returns, although with later
break-even dates than at the start of the project (Figure 8);
. in Jdy 1995 the Department of Health completed a retiew of their Jtiy 1994
outturn business case. The revised outturn was a net present value of
S72 million with break-even in year 19. The National Audit Office noted that
this final adjustment of the business case did not reflect the planned
reduction of some 200 posts in the NHS Executive headquarters in Leeds;
24
CONSTRUCTION OF QUARRY HOUSE
. the cases were calctiated over 60 years, the expected physical fife of the new
building, on advice of the Departments’ economic advisers and in the fight of
Treasury guidance. No a~owance was made for any refurbishment costs
during that period; normaly a major refurbishment would be required after
25 years and current Treasury guidance, issued in 1993, requires business
cases to be assessed over this period. The National Audit Office consider that,
because of the uncertainties of assessing these and other costs and savings so
far into the future, appraisals shotid have been based on the expected
economic Efe of the internal services and fit out of the building, which is
genera~y betieen 15 years and 25 years;
. the appraisals reheal heavily on the Departments’ notional assessment of
savings attributable to vacated accommodation in London. These were set at
S12. 5 mi~on a year in the final business cases (Figure 9), The Departments
have not been able to assess the actual savings because their accommodation
was affected by an exercise to rationafise au of their London estates, The
method used by each Department to calcdate the notional savings is
described in Figure 10 overleaf;
Hrstfull business cases Outturn business cases1993-94 prices 1993-94 prices
fmiltion fmillion
Accommodation savings
. London 17.0 12.5
. Other locations 0.2 0.8
Staff savingaz 6.4 5.7
Other aavingas 0.2 0.4
Total annual savinga 23.8 19.4
Total annual costs 2.2 3.8
Net annual savings 21.6 15.6
Source: Natiorra/Audit Office anafysis of the business cases
Notes: f. Th/a figure is baaed on annual kteadysfate’ costs andsavingspredicted for the petiod
year22 toyear 59.
2. Staff savings include savinga for: London weighting and otherlocalpay additions; increased
e~cierrcy from working an efira hours week than in London; London staff receiving higher
salaries; and additional housing cost allowance.
3. Other savings include savings for: cleaning, new /Tand telecommunications.
Hgure 9 shows that the notional savings for vacated accommodation in London accounted for over 70 per cent
of totil annual savings in the initial business casea and nearly 65 per cent in the ouftum business cases.
Department of Sociaf Security
Cases produced:
Octobar 1989 Initial case seekng mrttine Treasuy approval for
relocation to Leeds
February 1990 First full business caae submitted to Traasuy
July 1991: Revised case submitted to Treasuy
October 1993 Outfurn case submitted to Treasuw
1 Trevefyan Square, Leeds
Cases exclude coats and savings for 132 posts relocated to 1 Trevelyan
Square. 30 of the posts moved from London and 102 from Preston. The
Oepaflment planned to accommodate some of them at Quarv House.
No sepamte business case was prepared for this move.
Accommodaffmr savings
Notional savings for space vacated in London are calculated on the cost
of accommodation whch posts moved out of at the time of the
relocation. TNs gives an annual saving of f6,815 per post.
Accommodation savings are claimed from the date at which peats
moved to Leeds.
Maintenance coats and savingx
Maintenance =vings for vacated accommodation are included in revised
and outturn caaes,wtile equivalent costs for Quarv House are not.
Tefecommunicafimrs and office machfrray
Revised and outturn cases exclude any impact of the relocation on
running costs relating to telecommunications and office machines.
Post-project evaluation:
The post-project evaluation does not compare the outturn business
case with the case prepared at the stafl of the QuarW House project or
include sensitivity analysis of the outturn case.
Source: National Audit Ofice anawsis of the business cases
Depatiment of Hesfth
Cases produced
October 1989: Initial case seeting outtine Treasury approval for
relocation to Leeds
Februay 1990 First full business case submitted to Treasuy
July 1993: Case revised for Health Select Commiftee heating
July 1994 Compaflaon of outturn with initial case submitted to Treasury
July 1995 Case revised to correct wrong assumptions
t Travelyan Squara, Leeds
Cases include costs and savings for 134 poata relocated to 1 Trevelyan
Square. All posts moved from London. The Depaflment planned to
accommodate them at Quary House.
Accommodation savings
Notional savings for space vacated in London are calculated using the
per capita cost of accommodating staff in London aftar the ralocatimr.
This gives an annual saving of f8,236 per post.
Accommodation savings are phased in over three yearn in order to
allow for the possibihfy of space remaining vacant on the government
estate until an alternative use is found.
Maintenance CONSand savings
Maintenance savings have been included for all postc but continuing
costs have only been included for QuarW House, not 1 Trevelyan Square.
Telecommunications and offfca macbfrreW
Revised and outturn cases include an increase in telecommunications
costs duting the project, followed by a fall as fewer buildings are
occupied. They also include hire and maintenance of etira office
machines naeded because of the move.
Post-project evacuation:
The post-project evaluation compares the outturn business case with
the case prepared at the atafl of the Quar~ House project and includes
sensitivity analysis of the outturn caae.
Figure 10 shows that there were a number of differences between the revised and outturn business cases prepared by the Oepatiments. These
relate to the timing of revisions, the costs and savings included and the methods used to calculate them. This made it difficult to assess the
fbrancial case for the whole relocation both duting the project and affewards.
26
CONSTRUCTION OF QUMRY HOUSE
. actual savings accrue to the Exchequer when Proper@ Holdings are able to
dispose of the property or re-let it to another Government department. In
calcdating their business case the Department of Health assumed that an
alternative use wodd not immediately be found for vacant space. They
therefore phased accommodation savings over three years. The National
Audit Office noted that, between 1990 and 1993, the Departments had
surrendered about 82,000 square metres of space in 22 properties to
Prope@ Holdings. Two of these properties vacated by the Department of
Health were still who~y or partly vacant in October 1995, although one
property has subsequently been handed back to the lessor. Because of the
complexity of the concurrent rationahsation programme it was not possible
to quantify to what extent the satings attributed by the Department to
relocation might have been affected. However, having regard to other costs
and benefits, the continuing cost of the vacant space will not materially affect
the financial case for the move to Leeds;
. the business cases were not always updated to reflect changes in
circumstances. UnEkethe Department of Health’s outturn case, the
Department of Social Security’s case does not a~ow for the costs and savings
relating to staff relocated to Trevelyan Square, Leeds. These are relevant
figures because the Department origina~y planned to accommodate some of
these staff in Quarry House. Nthough the Depatient viewed the move to
Trevelyan Square as a separate project, neither the Benefits Agency nor the
Department produced a business case setting out the costs and benefits
attaching to the additional posts relocated. The National Audit Office consider
that the Department shotid either have included the posts in the business
case for the main relocation or prepared a separate appraisal;
. maintenance costs have not been treated consistently in the appraisals. The
Department of Social Securi@’s revised cases included maintenance savings
for vacated accommodation, but excluded the equivalent costs for
Quarry House, Correcting for this wodd reduce the outturn positive net
present value from S44.8 mi~on to S37. 7 miWon (at 1993-94 prices) and
extend the break-even date to year 18 (Figure 8). The Department of Health’s
outturn case included maintenance savings based on all posts relocated to
Leeds while on-going maintenance costs were included for Quarry House but
not Trevelyan Square. Such appraisals should include aU maintenance costs
and savings; and
. the business cases excluded fuel andutifities costs ontheassmption that
these wotid have been incurred irrespective of the decision to relocate. The
National Audit Office consider that fuel and utihties costs shotid have been
excluded only if reEable estimates showed that the costs were the same for
both the new property and that vacated.
3.18 Most of these omissions anddeficiencies relate totherevised and final versions
of the business cases. mile the final appraisals continued to support the
financial case for the project, they were not as strong as Figure 8 suggests. This
is because, although thevalue of theomissions anddeficiencies in the final
27
CONSTRUCTIONOF OUARRYHOUSE
3.19
3.20
3.21
3.22
cases cannot be quantified, it is Ekely that they woufd reduce the estimated
financial benefit of the relocation and extend the break even date indicated in
the outturn appraisals.
Cost control and monitoring
In April 1993, the Department of Social Security’s interual audit team reviewed
the procedures for monitoring and controlhg relocation expenditure. They
concluded that the Department had estabhsbed sound controls. These controh
included monthly monitoring by the Project Team of expenditure against
budget. AMEC and the Project Team checked monthly reports from Newest
Hoist against physical progress, which included a forecast of the final account
sum, before authorizing payment. The monthly forecast of the final account sum
was produced at the Project Team’s request, and was an important financial
control over the project.
To minimise the risk of variations to the building contract, au changes in users’
requirements were passed through MEC and the Project Team to the
Departmental Project Management Board (Appendix 3). No such variations
were actioned without assessing the imphcations for the project budget and
timetable. There were 141 contract variations which increased costs by
El.7 milhon. Ove Arup told the National Audit OffIce that the number of
variations reflects well on the Team’s efforts in setting up and operating the
design, develop and construct contract, the success of which depends upon
minimizing variations,
The action taken to minimise outstandingcommitments
Outstanding financial commitments can arise from claims made by constants
and contractors and from the retention of funds pending completion of
outstanding work. A tight timetable and a competitive contract price meant
there was a significant risk of claims by the contractor.
The Project Team dealt with potential claims as they arose. They maintained a
record of all actual and potential financial issues which arose. They resolved
them at regular monthly meetings with Nomest Hoist and ~EC which the
Project Team instigated specifically for this purpose. This ensured that the Ekely
total cost of the building contract was kept in tiew and enabled the Project
Team to agree provisionally the final account when bnildlng work, excludlng
snagging and defects work, was completed. It also helped to ensure that the
Departments were not involved in any subsequent financial disputes be~een
contractors employed on the project.
2s
CONSTRUCTION OF OUARRY HOUSE
3.23 Under the contract with NorWest Hoist the Departments retained three per cent
of the value of works (El. 7 mi~on) which was released as follows:
. hay of the retention was paid when the relevant phase of the building was
handed over for occupation; and
. the other hat was to have been paid once the defects habihty period
(12 months) had expired, However, because some defects work remained
outstanding beyond this period, the Departments were still retaining
S280,000 in October 1995.
29
CONSTRI lr.TmN OF m IhRRV unl ISE
4.1
4.2
4.3
Part 4: Quality of the building
This part examines how the Departments specified the quahty of Qna~ House
and how the building was constructed to meet these requirements. It considers
how well the Depaflments:
. achieved the required Wahty standards for the external design of the
building;
. achieved the required quahty standards for the internal desi~ of the
building; and
. ensured that the quality of the building will be maintained in the fuwe.
For the purposes of their examination, the National Audit Office interpreted
quality as covering
. the external appearance of the building being sufficient to enable the
Departments to secure planning consent from Leeds City Comcil. This
included the size, height, materials, detai~ng and visual impact; and
● the abiEty of the building to meet the requirements of its users, both now and
for the rest of its design life.
The National Audit Office found that
. the desigu for Quarry House gained the approval of Leeds City Comcil
without compromising the Departments’ tight timetable (paragraph 4.12);
. the Departments awarded the contract to Newest Hoist mainly because of
the quality of their desiW. They considered that it would protide a better
environment for staff and folly justified an additional S2 ,67 milhmr over the
lowerbid fromBalfourBeat@(paragraph4.16);
. AMEC considered that Balfour Beatty’s bid comphed more ftiy with the
Departments’ specification. They expressed concern about NorWest Hoist’s
technical proposals and ability to co-ordinate desigu work between
contractors for mechanical and electrical services. The Departments enswed
that both bids were comparable and were satisfied that they comphed
snfOciently with the specification to enable them to award a contract. They
were confident that AMEC’S concerns codd be addressed through contract
management (paraWaphs 4.13, 4.14, 4.17 and 4.18);
. design shortcomings led to the building having approximately 460 square
metres less office space than specified, even after future expansion space of
1,390 square metres was brought into use prematurely. The Departments
1
30
CONSTRUCTION OF QUMRY HOUSE
4,4
.
.
.
.
.
.
.
regarded this as the only option which wodd allow them to meet their
timetable for occupation of the building and avoid the possibiE@ of costly
Etigation (paragraphs 4.21 to 4.23);
the external structure shotid meet the design fife stipulated by tbe
Departments of 60 years. The office areas of the building have been built and
fitted out to a standard comparable with private sector head office
accommodation (paragraphs 4.19 and 4.30);
some building defects are stiU being corrected (paragraph 4.26);
a major change to the IT specification cost E683,000. This was required to
protect the flexibility of the building for future use (paragraph 4.28);
some items in the Departments’ specification, although proposed in
accordance with guidance from the Property Semites Agency and AMEC,
were in excess of industry good practice at the time and might have
increased construction costs by up to S300,000. The National Audit Office
recognise, however, that a lower price might not have been obtained from a
different specification (paragraphs 4.30 to 4.32);
the National Audit Office’s consultants, Ove Arup, also advised that there
were some omissions, for example the provision of double glazing in the
atria, which might have increased costs by up to S250,000. The Departments
told the National Audit Office that they had acted on the basis of expert
adtice available to them at the time. In their view the project architects BDP
were recognised authorities on atria design. The National Audit Office
consider that value engineering, which challenges assumptions and identifies
unnecessa~ costs, might have identified these items at the concept stage
(paragraphs 4.30 to 4.36);
the Departments’ specification required long fife and low maintenance costs
for the building’s finishes, fixtures and semices. The Departments reheal on
their project managers to ensure that this requirement was met and did not
set specific quantitative targets (paragraph 4.39); and
after consdting their Departmental energy experts, the Departments decided
to hmit the inclusion of energy efficiency measures to those which would pay
for themselves within three years. This hmited the scope to include such
measures (para~aph 4.41 and Appendix 5).
The specification of the btilting
The Departments prepared a brief for AMEC which defined in broad terms their
requirements for the building. This was used by MEC as the basis for
developing the technical specification, which was a detailed description of how
the Departments’ requirements would be met in the building’s construction.
The specification met government standards developed by the former Property
31
CONSTR1 ICTION OF nl lARRVHO1lSR
Services Agency. These standards had previously been mandatory for au new
government buildings but were only advisory once departments had untied
from the Agency.
4.5 AMEC were responsible for ensuring that the finished buildlng met the quahty
standards set out in the specification. Figure 11 opposite sets out the
Departments’ initial requirements and how these were interpreted in the
specihcation and reflected in the finished building.
4.6 During the project, Norwest Hrdst applied for215 relaxations of the
specification on grounds of impracticality or expense. Ml such requests were
considered by AMEC, the Project Team and their technical adviser. No detailed
records have been kept of how many of these relaxations were accepted. There
were three occasions when the Project Team asked their technical adviser to
negotiate agreements with NorWest Hoist, under which a number of relaxations
were granted in return for the clearance of otier outstanding financial issues or
the provision of enhancements at no cost. On one occasion AMEC did not
support the granting of the relations.
External quality of the btiding
4.7 The brief required that the building shmdd be an architectural status symbol
and that its fabric should have a design Me of 60 years. The Departments were
aware that it was important to obtain Leeds City Council’s approval for the
exterior design if the project was to proceed to timetable.
Planning approval
4.8 Afthough government btildings are exempt from the Town and Country
Planning Acts, departments observe au stages of the planning process. The
Quarry House design was required to meet the design constraints which Leeds
City Council had determined for their masterplan for the whole Quarry HiU site.
4.9 In February 1990, the Project Team began discussions with Leeds City Cmmcfl
and their masterplanner. This was some five months prior to the apphcation for
outiine planning permission. The Council told the National Audit Office that tils
action had helped to progress the Departments’ application quickly.
4.10 The Council found the original concept design unacceptable in terms of the
proposed building’s size and height and, in May 1990, sought the views of the
Royal Fine Art Commission, who can enquire into any btiding design which
may affect amenities of a pubhc or national character. The Commission strongly
objected to the concept design and to the Departments’ intended design,
develop and construct strategy. The Departments and AMEC accepted
amendments from the Counci~s masterplanner which altered the exterior of the
proposed building and brought it into tine with the masterplan.
32
CONSTRUCTION OF QUMRY HOUSE
ClientBrief
Architecture to reflect status of building
Occupation dates for the building:
Phase 1 November 1991
Phase 2 Januaw 1992
Phase 3-
Phase 4-
Space for 2,022 staff
Office space requirement
1B,601 square metres
Total usable space requirement
30,430 squars metres (excluding circulation
space)
Low energy usage
Natural ventilation wherever possible
FlexiMli~ for future use
Expansion space for up to 120 eflra staff
Cellular offices for Grade 7 and above only
Modest provision of recreation space
Restaurant, creche, videoconferencing
Source: AratiorralAudit Ofice analysis of Department of Social Securi@ records
Specification
At this stage Leeds Gfy Council altered the
concept design significantly
Occupation dates for the building:
Phase 1 May 1992
Phase 2 August 1992
Phase 3 FebruaW 1993
Phase 4-
Space for 2,076 staff
Office space requirement
19,983 square metres
Tots usable space requirement
30,140 square metres (excluding circulation
space)
No energy consumption targets set. Advice of
Departmental Energy Managers incorporated
Air conditioned
Concept design provided for segregation of
cellular offices and open plan areas. The IT
specification required Depaflments to occupy
separate halves of the building
Expansion space equivalent to five percent of
office area
Occupants of cellular offices specified for
Grade 7 and above
Swimming pool, sports hall, fitness room,
squash coutis and bar
Restaurant, creche, videoconferencing
As Built
Leeds Qty Council and Departmental senior
management approved the final design
Occupation dates for the building:
Phase 1 July 1992
Phase 2 August 1992
Phase 3 February 1993
Phase 4 February 1993
Workplaces provided for 1,9B2 staff
Office space provided
19,526 square metres
Tots usable space provided:
33,910 square metres ~ncluding circulation
space)
Continued teetting problems with the
computerised buildng management system. The
system ia not operating at otimum ticienv.
Ar conditioned
Full flexitili~ of movement within the building,
but difficulties in mixing of open plan and
cellular space
Planned expansion space (1,400 square metres)
utifised to compensate for space shotiall - no
hnfher expansion space available
Cellular otices only provided below Grade 7
level if justified on grounds of work
confidentiality
Swimming pool, spmfa hall, fitness room
squash coufis and bar
Restaurant, creche, videoconferencing
33
CONSTRUCTIONOF QU~RY HOUSE
4.11
4.12
4.13
4.14
4.15
4.16
Selection of a contractor
The Departments issued an invitation to tender, setting out their requirements
in a detailed tender enquiry specification. Four tenders were returned on
3 August 1990, none of which met fully the requirements of the specification.
The Departments’ Project Team, assisted by MEC, spent two months on a
detailed tender evaluation process which examined tbc four bidding companies’
commercial, architectural, technical and operational proposals. During the
course of the evaluation the two most expensive bids were dropped. The bids
made by the other two companies, Balfour Beat~ and NorWest Hoist, were
clarified and developed through a series of meetings with the firms. The
Departments referred the designs of these companies to Leeds City Councfi and
to the Royal Fine Art Commission.
The Commission rejected the Balfour Beatty design and were very critical of the
NorWest Hoist proposal. The Council strongly preferred the NorWest Hrdst
design. However, in October 1990, they granted full planning permission for
both designs, but with a hst of reserved matters. The Departments made it a
condition of the building contract that all the reserved matters were resolved to
the satisfaction of the Council.
The Project Team priced the additional work retired to make the contractors’
bids comply with the tender enquiry specification and to ensure that they were
comparable. After this revision the Balfour Betty tender was E49.5 miwon and
NorWest Hoist’s tenderf153 million.
rhe Departments told the National Audit Office that, by tie end of
September 1990, the two bids met their requirements sticientiy to proceed
with the award of the contract.
[n their report of 2 October 1990 to the Contract Award Panel, which consisted
of senior representatives of both Departments, the Project Team concluded that
their tender evaluations did not point to a clear winner. They considered that
there was nothing to chose between BaErmr Beatty and NorWest Hoist on the
technical and operational aspects. At the same time the Project Team noted that
the NorWest Hoist design was strongly preferred by au major parties to the
project. Mthough Balfour Beatty had provided the cheapest and most compfiant
tender, the Project Team strongly recommended that weight be given to the
superiority in design terms of the NorWest Hoist scheme. The Project Team also
noted that the Balfour Beatty design was acceptable to Leeds City Couucil but
not to the Departments’ senior officers or to the Royal Fine Art Commission.
The Project Team considered that the extra S3.5 milfion (6.4 per cent of the
contract value) would be an acceptable price to pay for a design which had
earned the strong support of all the major participants in the project. They
therefore recommended that the contract be awarded to NorWest Hoist.
The Contract Award Panel, which met on 3 October 1990, questioned the
Project Team closely on the price difference between the two bids and were told
that the Team had re-evaluated the bids and that the difference had faUen to
S2.67 million. The Panel decided that the general quahty of the NorWest Hoist
I
34
CONSTRUCTION OF OUMRY HOUSE
4.17
4.18
4.19
btiding wodd be superior and that it wotid provide a better environment for
staff. They regarded neither scheme as ideal but endorsed the Project Team’s
recommendation to award the contract to NorWest Hoist. In reaching this view
they weighed the clearly stated preferences of senior officers and the
importance they thought shmdd attach to the views of potential users.
~EC’s tender evaluation report of 2 October 1990 concluded that, hating
regard to price and the technical and operational aspects of the building, their
recommendation was for the acceptance of the BaEonr Beatty tender. Their
report was accompanied by an analysis of the main aspects of each of the four
bids. This analysis noted, in relation to the NorWest Hoist bid, their concerns
about the co-ordination of the building design with the design for mechanical
and electrical semices; and about the co-ordination of work between the
sub-contractors. They also stated that the bid did not fdy comply tith the
Departments’ re@rements for mechanical and electrical services. MEC
concluded that the support for the designs proposed by NorWest Hoist and
BaMour Beatty was evenly balanced and offered no opinions on which scheme
they preferred aesthetica~y,
The National Audit Office noted that the Contract Award Panel had seen WEC’S
analysis of the tenders, but codd find no etidence that the Panel had been
informed of ~EC’s conclusions and recommendations. The Departments told
the National Audit Office that the ~EC report had been used as the basis for
retising the bids to ensure comparabihty and that ~EC’s concerns had been
brought out ftiy in the Pane~s discussion. The Departments considered, with
~EC’s agreement, that the concerns about NorWest Hoist’s technical proposals
cotid be addressed through the management of the contract. The Departments’
position was protected since their contract with NorWest Hoist rewired the
company to construct a building which met the Departments’ re~irements,
rather than on the basis of the contractor’s proposals. They considered that
these provisions wmdd ensure that they got the ~ahty prescribed in the
specification. In the event design shortcomings contributed to a shortfa~ in
ofDce space (paragraph 4.22).
Achieting the design Efe
The spectilcation re@red high ~afity materials for the exterior of the buildlng.
The Departments’ intention was that the structure wodd remain sound for60 years, with a period of at least 25 years to first major maintenance - as
opposed to routine operating needs. Ove Arup advised the National Audit Office
that, from their tisit to the btiding, the structure and finishes appear to meet
those design fife re~irements.
35
CONSTRUCTION OF OUMRY HOUSE
Internal quality of the buflfing
4.20
4.21
4.22
4.23
4.24
4.25
In meeting users’ needs, an office building shmdd provide good quahty
workspace to facihtate efficient operational use. This includes sufficient, usable
space; a comfortable working environment; flexibili~ to meet changing
requirements; and satisfactory staff facihties. The building shotid also meet
normal building industry standards, except where the users have special needs.
Protision of office space
Figure 12 opposite shows the Departments’ staff accommodation requirements
set out in the brief and specification and bow these compare tith actual
provision. The building was intended to provide space for 2,076 staff, In the
event workplaces were provided for about 1,982 staff - a shortfa~ of 94
(five per cent).
In June 1991 the Department of Health identified a shortfaU of office space, This
arose from the underprovision of space for circulation within and between office
areas, space for plant and machinery and because of the poor co-ordination of
design information between sub-contractors. The total shortfall in office space
was about 1,850 square metres (nine per cent). Neither ~EC or NorWest Hoist
were aware of the shortfall,
The design of the building provided for about 1,390 square metres in the roof
area for future expansion. As a resdt of pressure from the Departments for
compensation for the loss of space, NorWest Hoist offered to convert the
expansion space to offices at their own expense. After consulting their legal
advisers, the Departments accepted this proposal as the only option which
would allow them to meet their timetable for occupation and avoid long and
costiy litigation. There remained, however, a net loss of about 460 square
metres (two per cent),
Use of office space
The concept design provided for the open-plan space and ceUdar offices to be
in separate wings ofthe btilding. In the event,operationalneedsre~red a mkof both types of accommodation. This proved difficult to achieve in some parts
of the building because:
.
.
the positioning of cellular offices within some open plan areas has obstructed
the flow of natural light to other occupiers; and
open plan areas inserted into cellular wings are sma~ and therefore Emit
flexibility.
The occupancy densi~ of Quarry House, expressed as the total usable space
(office space and support areas such as conference and training rooms, Ebraries
and computer suites) divided by the number of people, is 17.7 square metres
per person. This compares with an average occupancy densi~ in Government
offices of 19.2 square metres per person, as reported by the Treasury Central
36
CONSTRUCTION OF OUMRY HOUSE
4.26
Client brief Specification Variance Capacity Variancefrom brief in April1995 from(per cent) (estimated) specification
(per cenf)
Beneflta Agency and 804 819 2 890 9
Central Amudication
Service
NHS Executive 1,218 1,257 3 1,064 (15)
SuppOrf Staff 1 28
Total 2,022 2,076 3 1,982
Source: Depaflment of Social Security records and Benefits Agerrcybuilding management team
Note 1: Contracted out oflce aewices functions shared by both Depaflments.
(5)
figure 12 shows that the estimated capacity of the building is some five percent Ieaa than specified. The
8enefOa Agency and Central A~uticafion SeNice have accommodated nine per cent more staff than
planned. 8ut the NHS Executive have accommodated 15 per cent fewer than expected.
Unit on Procurement in their 1994 annual report. Since occupation, Benefits
Agency space requirements have increased while those of the NHS Executive
have fallen.
Work environment
The worting environment is regtiated by a computerised building management
system. Since occupation, a series of defects have led staff to complain about
environmental conditions in many areas of the building
. the single rather than double glazing specified for the courtyard atria has
caused cold airflow affecting staff iu surrounding areas. The problem arose
because the tender specification protided only for internal atila. However,
Newest Hoist’s desi~ included external atila. Solutions to the problem were
stifl being considered in October 1995;
. faulty insta~ation; for example, temperature sensors were wrongly installed,
leading to incorrect temperatures in the work areas; and
. a technical audit carried out on behaK of the Benefits Agency in August 1994
recommended that au air systems shodd be re-commissioned. The
Departments have yet to accept some equipment which, although in use, has
not been operating to an acceptable standard. In October 1995 discussions
with Nomest Hoist about remedial measures were continuing.
37
CONSTRUCTIONOF QU~RY HOUSE
Fletibfilty of use
4.27 As there was uncertainty about tbe size and structure of the occupying
organisations, the Departments’ brief emphasised that the buildlng shotid
permit flexible use, Staff wodd require access to their own IT system wherever
they were based in the building. The Departments instaUed separate IT systems
because they were tied to different supphers before the building contract was
placed, although they agreed a single cable specification (Figure 11).
4.28 The Departments’ IT divisions designed the cable layout assuming that tbe
building wodd be divided between the Departments on a north-south basis,
Mthough this plan changed during the concept design period, the IT design
continued on the original assumption. The Departments identified this mistake
in February 1991, In April 1991 the IT divisions produced an amended
specification, including a requirement for an additional 8,000 metres of cable,
at an extra cost of S683,000. The Project Team concluded that the problem had
been caused by the spht of responsibihties and their own lack of IT expertise.
N parts of the building are now suitable for use by both Departments, thereby
meeting tbe flexibility of use requirement,
Staff facilities
4.29 The Departments’ brief required a staff restaurant and nursery, and a modest
provision of leisure facilities. The concept design and specification (Figure 11)
included a swimming pool, sports ball, fitness room, two s~ash courts and a
bar. This was accepted by the Treasury. The Departments justified these
facihties as a way of encouraging staff to relocate and of giving practical support
to the Health at Work initiative. Staff pay to use these facihties, which are also
used by groups in the local community. The cost of constructing these factities
was not separately identified.
Btiding standards
4.30 Ove Arup told the National Audit Office that the office areas of the bnildmg had
been built and fitted out to a standard comparable with reasonable, but not
lavish, private sector owner-occupied o~ces, The Departments’ specification
was prepared in accordancewithProper&ServicesAgency@dance butincluded items in excess of normal industry standards. These included:
. high floor loadings for the building (Figure 13 opposite);
. electrical capacity considerably in excess of potential demand; and
. a high amount of heat gain from electronic equipment which the cookg
system would be required to cope with,
38
CONSTRUCTION OF OUARRYHOUSE
4.31
4.32
4.33
4,34
Silorrewlonsper square metrez
Quarw House (PSA afandard apecificafion) 6Pmpe@ Hokfinga 1993 5
Government ofice guidance
Btifiah Standard Code of Practice 3.5
Source: Department of Socia/Securi@papers, Prope~Ho/dhrgs and fhe British Counci/for Ofices
Note: f Loads borne by the finished floors
Note: 2 Includes 1 kilonewon for partitioning
Hgure 13 shows that floor loadings for Quarw House were in hne with previous standards for Government
buildings laid down by the former PropeW Services Agency, but were overspecified compared with
industv atandarda.
On the question of electrical capacity, the Department told the National Audit
Office that the power loading was within the guidehnes pubfished for highly
computerised buildings with high occupation densities. A further aUowance had
been included for future trends such as larger computer screens, more intensive
usage and more fax machines.
Ove Arup estimated the over-specification might have increased construction
costs by about S300,000. However, the National Audit Office accept the view of
the Departments that, in the circumstances of a single tender for the whole
project, it is not certain that a lower price wmdd have been obtained with a
stightly different specification.
Ove Arup also identified some areas where tie mechanical and electrical
semices are below industry good practice, for example:
.
.
.
a lack of provision of standby generation of electrical powe~
Emited flexibihty for using spare electrical capacity in other parts of the
system if needed; and
poor control over entionmental conditions in the atria. Inadequate glazing
of the atria is causing discomfort to staff in adjoining areas.
Ove Arup estimated that incorporating these facilities at the design stage wotid
have increased costs by about E300,000. Providing them after the building had
been constructed wotid cost considerably more as indicated by the technical
audit undertaken by the Benefits Agency’s constitants. The Departments told
the National Audit Office that the decision not to incorporate a standby
generator was made after an assessment of the costs and risks involved. The
building is fed by WO separate high voltage supphes, the simultaneous failure of
which would only be likely in a period of industrial action by power workers. In
such circumstances the Department wmdd expect to obtain mobile standby
39
CONSTRUCTIONOF QUARRYHOUSE
generation facihties from the Ministry of Defence or a private sector suppher.
They therefore decided that buying permanent facihties, which wmrfd probably
never be used, would not be an effective use of Government fuuds.
4.35 The Depatients told the National Audit Office that AMEC had advised that the
provision of low voltage finks between the electrical switchboards, which wotid
provide greater flexibility in using spare electrical capaci~ in other parts of the
building, was not a standard procedure for an office building.
4.36 Value engineering is a formal review of detailed design solutions in order to
estabhsh whether or not what is being proposed can be achieved in a more
cost-effective manner. It cha~enges assumptions and can identify unnecessa~
cost. The greatest return from such an exercise is during the early design stage
of a project, Had the Project Team carried out a value engineering exercise
during the development of the project brief and concept design then the issues
identified at paragraphs 4.30 to 4.35 might have hccn highhghtcd.
Maintaining quahty during the btiding’s Hfe
4.37 Many of the issues raised in the earher sections of the report, such as the
durability of materials and the building’s flexibih~ in use, also apply to the
future (paragraphs 4,19, 4,27 and 4,28). However, there are other factors to be
considered, such as Efe cycle costing energy efficiency; the rehabih~ of plant
and equipment; and the building’s suitabihty for alternative use,
Ufe cycle costing
4.38 Ufe cycle costing involves examining all the major elements and systems of a
proposed building to assess both the initial capital costs and the running costs
over the estimated hfe of the building,
4.39 The specification for Quarry House stated that internal finishes, fitures and au
aspects of the services shotid provide long life and low maintenance. It did not
set quantitative targets for maintenance costs and energy use. The contract,
however, required NorWest Hoist to indicate the Efe expectancy and
maintenance requirements of interual finishes, fixtures and services.
The Project Team required AMEC to ensure that the specification met the
requirements for long hfe and low maintenance. AMEC prepared Ests of
approved supphers whom they considered could meet this requirement.
Energy efficiency
4.40 The Departments specified that Quarry House should include a btiding
management system which wodd ensure that energy was used eficientiy
(paragraph 4.26). The brief also specified that the building sbotid have natural
ventilation wherever possible. But, during discussions shout the concept design.
the Departments decided to change to full air conditioning (Figure 11). They
decided the building wodd be physicaly unsuited to natural ventilation and,
40
CONSTRUCTIONOF QUARRYHOUSE
being bounded by busy roads on three sides, there wodd be too much
disruption through traffic noise if the main means of ventilation was through
open windows. No detailed analysis of options was undertaken.
4,41 The building specification required that the mechanical engineering service
insta~ation shodd be economical to run and, on the advice of tbe Department’s
energy experts, that any energy conservation measures had to pay back their
initial cost within three years (Figure 11). In September 1994, a technical audit
undertaken by consultants for the Benefits Agency concluded that the three year
payback period had restricted the adoption of energy conservation measures,
except in relation to the swimming pool. Ove Arup advised the National Audit
Office that a payback period of five to seven years may have been more
appropriate.
Efficient operation of plant and equipment
4.42 For plant and equipment to function effectively, ite operators shodd be ftily
acquainted with the insta~ed equipment. The contract required NorWest Hoist
to provide the Benefits Agency with operation and maintenance manuals and
plans of the services immediately following the issue of practical completion
certificate. However, in April 1995, the manuals and plans were still being
amended hy the contractors. The facihties managers told tbe National Audit
Office that this had hindered the operation and maintenance of the equipment.
NorWest Hoist told the National Audit Office that they were unaware of any
problems after January 1995.
Suitabfity for re-use
4.43 As custodians of the Government’s Common User Estate of office buildings,
Property Holdings were involved in design haison meetings with the Project
Team and Leeds City Council during the development of the early concept
design. This design was not adopted and Prope~ Holdlngs had no involvement
in the subsequent design work. Proper~ Holdlngs were provided with copies of
WO subsequent concept designs and confirmed that either would provide
accommodation suitable for re-use by other Government departments if the
occasion arose.
41
CONSTRUCTIONOF QUMRY HOUSE
Appendix 1
Chronolo~ of key events
The Paymaster General announced that departments should
review the location of their work.
June 1988
January 1989
Apri 1989
May 1989
October 1989
November 1989
Oecember 1989
February 1990
April 1990
May 1990
July 1990
August 1990
October 1990
November 1990
Oecember 1990
April 1991
The Department of Health and Social Securny examined the
case for relocating their headquarters office functions out of
London.The Department of Health and Social Securiw announced
their intention to create the NHS Executive.
The Department of Health and Social Security spht into the
Department of Health and the Oepaflment of Social Security.
Creation of the NHS Executive.Creation of the Reaeftlement Agency within the Oepafiment
of Social Security.
The Department of Social Securi~ announced their intention
to create the Benefits Agency.
The Oepartmenta of Health and Social SecuflV produced a
feasibnity study, “Moving to the Future”.
The Department of Social Secufity appointed a Project Team
leader.
Ministers announced that 1200 Department of Health posts
and 800 Oepatiment of Social Secuflv posts would relocate
to Leeds.
Project Finance and Planning Manager appointed by the
Department of Social Secud~.
Technical Adviser appointed by the Department of Social
Security.
AMEC appointed as Project Managers.
The Treasuv approved the purchaae of land at Quarv Hill
and gave in principle approval for the whole project,
TheDepaflmentsannouncedthatQuarWNllwastheoreferred site.
The information Technology Sewices Agency was created
within the Department of Social SecufiOy.
AMEC produced the concept design.
The Departments applied to Leeds Sity Council for outline
planning permiaaion.
Return of tenders for the construction contract.
Leeds Sity Council granted planning permission. Full
Treasury approval to proceed with the construction contract
The main construction contract waa awarded to Nomest
Hoist.
Building work began,
The Benefits Agency waa created.
42
CONSTRUCTION OF QUMRY HOUSE
Aptil 1991
Apri 1991
July 1991
Janua~ 1992
April 1992
July 1992
August 1992
September 1992
December 1992
Janua~ 1993
February 1993
April 1993
June 1993
July 1993
August 1993
October 1993
December 1993
July 1994
October 1994
November 1994
July 1995
NHS Estates was created as an agency within the
Oepatiment of Health.
The second wave of NHS Trusts was estabhshed,
The Department of Social Security submitted a revised
business case to the Treasury.
The Benefits Agency published their Customer Charter,
The Department of Health published the Patients’ Charter,The second wave of NHS Trusts was established.
The Depatimerds occupied Phase 1 (East Wng),
The Depatiments occupied Phase 2 (Noflh and
South Wings).
Ovwspill space was occupied in 1 Trevelyan Square, Leeds.
The Depaflmenta issued a practical completion certificate for
Phase 2.
The Departments issued a practical completion certificate for
Phase 1.
The Departments occupied Phases 3 and 4 (West Wing and
expanaion space).
Benefits Agency building management team assumed
responsi~lify for the building.Instigation of weekly completion meetings attended by all
parties for managing outstanding work.
The Oeparfments issued practical completion ce~ficates for
Phases 3 and 4.
Mnisters commissioned a manpower review of the NHS,
The Child Suppofi Agency was estabflshed.
The third wave of NHS Trusts was established.
Conclusion of NHS manpower review.
The Department of Social Secuflty sent their outturn
business case to the Treasury.
The Department of Health established an NHS Information
Technology strategy,
The Depatiment of Health sent their outturn business case to
the Treasury.
The Benefits Agency assumed responsibility for managing
outstanding work from the Depaflment of Social Securi~.The Department of Health announced a 20 per cent
reduction in staffing of the NHS Executive in Quarry House,
The Depatiment of Health announced the results of a revised
outturn business case.
43
CONSTRUCTIONOF QUARRY HOUSE
Appendix 2
eDepartmental Reaourcea & Services
&7 INHS Executive Chief MedicalHeadqustiers Officer
Department of Social Security
Secretary of State
Agencie;: Im Permanent Secretary
● Headquarters Pohcy Group
. Contributions Agency ● Resource Management andPlannino GrouD
o CNldSuppofiAgency● Soticito~s Group
\r● Information Technology Services Agency Independent Statutory Bodres
● Central Adjudication Group● War Pensions Agency
● Occupational Pensions Board● ResettlementAgency
Key
Accountabiliu to Permanent Secretary as Head of Department
Managerial accountabihfy
m Relocated to Quarry House andotherbuildings in Leeds
● Independent Review Service for the Social Fund
● Independent Tribunal Service
● Office of the Pension Ombudsman
44
Before occupation:
Department of Health
MRelocation Steering Group
ProjectTeam:Responsible for personnel issues
wAffer occupation:
NHS Executive
DepatimentalManagement Soard
Relocation Steering Group:Responsible for monitoringprogress on the relocation Imanagement of the project
mResponsible for building Issues
mCentral Adjudication Service
Genefits Agency
Suilding Management Team:’Responsible for managing the
building after handover
Consultants and contractorsto Department of Social Security
EMatin Drake’
Technical AdvisecResponsible for providing
advice to the ProjectTeam on building
and contract issues
1AMEC, Pmiect Management Team:Responsible for managing
the buildino contract
Newest Holsl, Main Contracto~’Responsible for constructing
the building, including themanagement of sub-contractors
Conardtants and contractorsto the Senefilc Agency
TFM GranadaFacilities Manager:
Responsible for day-to-dayrunning of the building
after handover
I DEGWEmployed to carry out a use
of space audit ISummers Project Management
Employed to carry out atechnical audit
Source: National Audit Office analysia of depaflmental papers
Notes: l, The Project Team leaderawere both members of both Deoatiments` Relocation Steeflno Grouosand of theProject Management Board,
2. The Technical Adviser and, from September 1991, the Quarry House Building Manager, were alao members of theProject Management Board.
3. NoWest Hoist were appointed on the recommendation of a Contract Award Panel consisting of representatives ofboth Depafiments.
45
CONSTRUCTIONOF QUMRY HOUSE
Appendix 4
Budgets and costs for the Quarry House project
fooo
8,116
(38)
23
(1,326)
(559)
(8)(7,832)
111
463
(1,040)
(160)
394469
67401
1,191
(151)
Capital costs
No~est Hoist
AMECTechnical Adviser
(Mr Drake)
Land
Telecommunications
FurnitureFitting out
Project Team
Miscellaneous
Sub total
Non-recurringrunning costs
Proiect Teams
Tempma~
accommodation
ConsultanciesFaciflties
managementTelecommunications
0f6ce machines
SubIotal
Total
48,728
1,400
153
9,694
5,768
4,9479,320
27
S0,237
4,782
4,782
85,019
56,844
1,362
176
8,568
5,209
4,9391,486
138
463
79,197
4,622
394469
87401
5,973
S5,170
17
(3)
15
(13)
(lo)
o
(64)
411
nla
(1)
(3)
nlanla
nlanla
23
0
55,361
1,411
227
7,977
3,364
3,6511,218
153
733
74.lla
499271
102
318
519
5,577
79,692
(1 ,483)
49
51
(591)
(1,825)
(1,288)(270)
15270
(5,082)
(754)
105
(196)
(;3;
519
(396)
(5,478)
(3)
4
29
(7)
(35)
(26)
(18)
11
58
(6)
(16)
27
(42)
(;1;nla
(7)
(6)
Source: Arationa/ Audit Oflce anaksis of depaflmentalpapera.
Notes: 1. In addition to the above costs, the Depaflment of Health aperrt an estimated f8.37million on introducing a new otice information
system, the development of which was brought forward by relocation. Both Depaflments also leased additional accommodation
in Leeds.
2. All figures are expressed in 1993-94 prices except those for Norwest Hoist.
AppenrOx 4 shows that Departmental expenditure relating to the building project was lower than both the budget aet at the stat of the project and
the revised budget aet in July 1991.
46
CONSTRUCTION OF OUMRY HOUSE
Appendix 5
(1) Heat recovery on fresh air systems
(2) Heat recovery on recirculation air handling systems
(3) Upgrade temperature controls in air conditioning
(4) Sequence control of ctiller plant
(5) Reduced air change rate in car park
(6) Solar control to efiernal fighting
(7) Control of car park hghfing
(8) Indvidual cassette air conditioning units to shops, bars etc.
Source: Summers & Partnera techrdcaiaudit, September 1994
Esllmaled cow
fooo100
400
50
15
30
10
5
2.5
Note: Ove Amp advised the Natimra/Audit Office that the pay-backperiod for these items would be in the three to seven year range.
47