construction schedule for sewege treatment plant
DESCRIPTION
here is a detail schedule for the construction of sewage treatment plant. abstract of a part of a project executed in pakistan.TRANSCRIPT
SEWERAGE SCHEME OF RAHIM YAR KHAN CITY WITH TREATMENT PLANTZONE I
Targets of Balance Work
Description / Scope Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11 Remarks
A STP,Pattan Minara
1 Brick Lining 200 Sq.m/ day
i) Arrangement of Material / Labour
ii)
2 Interconnection of Ponds 01 Structure / day 36 Nos.
i) Arrangement of Material / Labour
ii)
21" i/d 63 Nos. 15 pipes/day
18" i/d 36 Nos. 15 pipes/day
iii) Excavation / Lean Concrete 2 Structures/day
iv) Steel Fabrication of Inlet / outlet slides 1 Structure/day
v) Concrete laying of inlet / outlet slides 2 Structures/day
vi) Laying of pipes and concrete pouring 2 Structures/day
3 Soling / Brick Pavement ( 8433 m) 100 m / day
i) Arrangement of Material / Labour
ii) Levelling / Dressing / Compaction of bed 150 m / day
iii) 423 sq.m
4 Barbed Wire Fencing 2539 m
i)
ii) Casting of Concrete Poles (1036/15 = 70 days)
iii)
iv) Installation of Concrete Poles 1036 /20 = 52 days 20 Poles / day
v) Installation of Barbed Wire (2539 / 30 = 85 days) 30 m / day
5 Distribution Chamber 1 Job
i) Arrangement of material
ii) Excavation / Lean concrete
iii) Steel Fabrication for Base Slab
iv) Concrete Laying in Base Slab
Sr No.
677 m3
Lining (daily consumption of Bricks(322807/30=10760 Nos /day)
Supply of R.C.C pipes 21"i/d = 63 Nos,18" i/d = 36 Nos.
4035 m3
Pavement (Cosumption of bricks 1923968/90 = 21377 / day)
Arrangement of Material / Labour / Moulds for casting of R.C.C Posts
Moulds 5 Nos.Base Plate 15 Nos.
Arangement of barbed wire (13 gauge) and eye bolts (10 mm)
Description / Scope Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11 RemarksSr No.
v) Steel Fabrication of Walls
vi) Concrete pouring in walls
6 Inlet Channel 15 m / day 535 m
i) Arrangement of material and labour (535/15 = 53 days)
ii) Excavation / Lean concrete
iii) Steel Fabrication in Base Slab
iv) Concrete laying in base Slab
v) Steel Fabrication for walls
vi) Concrete pouring in walls
7 Outlet channel 15 m / day 610 m
i) Arrangement of material and labour (610/15 = 40 days)
ii) Excavation / Lean concrete
iii) Steel Fabrication in Base Slab
iv) Concrete laying in base Slab
v) Steel Fabrication for walls
vi) Concrete pouring in walls
8 Area Lighting 1 pole/ 3 days 1 Job
i) Arrangement of poles
ii)
9 Plantation 3421 Nos.
i) Laying of Sweet soil
ii) Arrangement of plants
iii) Plantation 3421/60 = 57 /day
B Pattan Minara Disposal
1 Generator Room 1 Job
i) Arrangement of material and labour
ii) Excavation and Lean Concrete
iii) Steel Fabrication for Columns and Beams
iv) Concrete Pouring in columns and Beams
v) Brick Work / Foundation / Cable Trench / Flooring
vi) Fabrication for Roof slab
vii) Concrete laying in Roof slab
viii) Fixing of Windows / Ventilators / Door Shutter
Installation of poles with laying of wires (8 nos. x 3 days = 24 days)
Description / Scope Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11 RemarksSr No.
ix) Plaster
x) Electrification
2 Staff Quarter 1 Job
i) Arrangement of material and labour
ii) Excavation and Lean Concrete
iii) Brick Work / Flooring / Plaster
iv) Fixing of Door / Window / Ventilators
v) Electrification
vi) Sanitary Works
3 Pluging 4 Jobs
i) Arrangement of material /labour / machinery
ii) First layer
iii) Second layer
iv) Third layer
v) Final Layer / Finishing
4 Dry Well 1 Job
i) Civil Work
ii) Intermediate Slab
iii) Stairs / Railing
iv) Brick Work
v) Fixing of Girder / Chain Pully
v) Roof Slab
5 Electrical works 1 Job
i) Manual Change Over
ii) Control pannel
iii) Motor control centre
6 Installation of Machinary & Yard Piping 1 Job
i) Construction of Foundation for Pumps
ii) M.S Sheet Installation under pumps
ii) Fixing of Machinery
iii) Yard Piping (suction, delivery with specials)
Description / Scope Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11 RemarksSr No.
7 Boundary wall (182 / 40 = 05 m/ day) 5 m / day 182 m
i) North Side
ii) East Side
iii) West Side
iv) South Side
C Lift station Sadiq Branch
1 Generator Room 1 Job
i) Arrangement of material and labour
ii) Excavation and Lean Concrete
iii) Steel Fabrication for Columns and Beams
iv) Concrete Pouring in columns and Beams
v) Brick Work / Foundation / Cable Trench / Flooring
vi) Fabrication for Roof slab
vii) Concrete laying in Roof slab
viii) Fixing of Windows / Ventilators / Door Shutter
ix) Plaster
x) Electrification
2 Staff Quarter 1 Job
i) Arrangement of material and labour
ii) Excavation and Lean Concrete
iii) Brick Work / Flooring / Plaster
iv) Fixing of Door / Window / Ventilators
v) Electrification
vi) Sanitary Works
3 Sinking 4 Jobs
i) Arangement of machinery
ii) Dewatering set etc.
iii) Excavation under SSWL
Description / Scope Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11 RemarksSr No.
4 Pluging 4 Jobs
i) Arrangement of material /labour / machinery
ii) First layer
iii) Second layer
iv) Third layer
v) Finishing
5 Dry Well 1 Job
i) Civil Work
ii) Intermediate Slab
iii) Stairs / Railing
iv) Brick Work
v) Fixing of Girder / Chain Pully
v) Roof Slab
6 Electrical works 1 Job
i) Manual Change Over
ii) Control pannel
iii) Motor control centre
7 Installation of Machinery 1 Job
i) Construction of Foundatio for Pumps
ii) M.S Sheet Installation under pumps
ii) Fixing of Machinery
iii) Yard Piping (suction, delivery with specials)
8 Screening Chamber 1 Job
i) Arrangement of Material (Screen / Pen Stock, etc)
ii)
iii) Fixing of Screen
iv) Fixing of Pen Stock
9 Boundary wall (182 / 40 = 05 m/ day) 5 m / day 180 m
i) North Side
ii) South Side
iii) East Side
Intermediate Slab (Shttering / Steel Fabrication / Concrete Pouring
Description / Scope Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11 RemarksSr No.
iv) West Side
D Sewer Lines
1 Manufacturing of Pipe 72" dia 390 m / 160 Nos.
2 Laying of Pipe Line V - X 72" dia 1072 m
3 Manufacturing of Pipe 66" dia 512 m
4 Laying of Pipe Line R - V 66" dia 543 m
5 30 m
E Other works
1 Ittefaq colony disposal
2 Missing link to old disposal Line S -T 27" dia
i) Manufacturing of pipe 317 m / 130 Nos.
ii) Laying of pipe 318 m / 130 Nos.
3 G - I sewer line 48" dia
i) Manufacturing of pipe 543 m/ 223 Nos.
ii) Laying of pipe 543 m/ 223 Nos.
4 Line N-H City chowk crossing 21" dia 192 m / 79 Nos.
5 L-AW - 6a Abdu Zahbi road 21" dia
i) Manufacturing of pipe 287 m / 118 Nos.
ii) Laying of pipe 287 m / 118 Nos.
6 L-AW-6a Nazim Line 12", 15", 18" dia
i) Manufacturing of pipe 1636 m/ 670 Nos.
ii) Laying of pipe 1636 m / 670 Nos.
7 U1-V1 Niazi colony missing link, 24" dia
i) Manufacturing of pipe 390 m/ 160 Nos.
ii) Laying of pipe 390 m/ 160 Nos.
8 L-AW-2a Rescue/Hospital Road 21"dia
i) Manufacturing of pipe 852 m/ 350 Nos.
ii) Laying of pipe 852 m/ 350 Nos.
Laying of Pipe Line B - R 27" dia / M.H
Assumption-Stay order vacated in
January,11
Description / Scope Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11 RemarksSr No.
9 A1-C Shahi road 12", 15" dia
i) Manufacturing of pipe 649 m/ 266 Nos.
ii) Laying of pipe 649 m/ 266 Nos.
10 A2-C-B Shahi road 15",18" dia
i) Manufacturing of pipe 791 m/ 324 Nos.
ii) Laying of pipe 791 m/ 324 Nos.
11 Collection Chamber Dari sangi "Q" Point 1 Job
12 Q-J Crossing of Fauji Chowk 24" dia 35 m
13 Collection Cahmber Ittefaq Town "U" Point 1 Job
14 Q-J Zarai College (additional) 18" dia
i) Manufacturing of pipe 65 m / 27 Nos.
ii) Laying of pipe 65 m / 27 Nos.
15 Syphon Line Y-Z 72" dia 1 Job
i) Arrangement of material / Labour
ii) Diversion of seepage drain
iii) Excavation / Lean Concrete
iv) Steel Fabrication for Base Slab
v) Concrete Laying in Base Slab
vi) Steel Fabrication / Shuttering of Walls
vii) Concrete Pouring
viii) Construction of Manholes
ix) Laying of pipe 72"i/d
x) Steel Fabrication & Shuttering for R.C.C Conduit
xi) Concrete Pouring
xii) Backfill / Dressing / Stone Pitching / Finishing
16 Ventilating Shaft 35 Nos.
i) Arrangement of material (Poles, etc) / labour
Description / Scope Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11 RemarksSr No.
ii) Fixing of Poles
Description / Scope Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11 RemarksSr No.
17 U-V Missing Link 33" dia 10 m
i) Manufacturing of pipe
ii) Laying of pipe
18 U-V Crossing 18" dia
i) Manufacturing of pipe
ii) Laying of pipe
19 D-E-F-H Missing link/M.H 21", 24" dia 44 m
20 Line I-R Missing Manhole 54" dia 1 No.
21 A.C Force main Dari Sangi 4" dia
i) Arrangement of A.C pipe 715 m
ii) Laying of pipe 715 m
iii) Testing of Pipe
22 Fixing of machinery Lift Station Dari Sangi 1 Job
23 Fixing of machinery Lift Station chak 111/P Gharbi. 1 Job
F G.R.P PIPE (Forcemain)
1 176 m
2 285 m
3 560 m
4 253 m
5 120 m
24 m / 9 Nos.
24 m / 9 Nos.
Ittefaq colony Arrangement of pipe 20" Ф
Laying of pipe 20" Ø
Basti Amanat Ali Arrangement of pipe 20" Ф
Laying of pipe 20" Ø
Basti Kahur Arrangement of pipe 36" Ф
Laying of pipe 36" Ø
Chak 111/East/West Arrangement of pipe 36" Ф
Laying of pipe 36" Ø
Pattan Minara Arrangement of pipe 36" Ф
Laying of pipe 36" Ø
SEWERAGE SCHEME OF RAHIM YAR KHAN CITY WITH TREATMENT PLANTZONE II
Targets of Balance Work
Description Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11
A Lift station Moye Mubark P.IV1 Sinking of well 4 Jobs
i) Arangement of machinery
ii) Dewatering set etc.
iii) Excavation under SSWL
2 Pluging 4 Jobs
i) Arrangement of material / labour / machinery
ii) First layer
iii) Second layer
iv) Third layer
v) Finishing
3 Dry well 1 Job
i) Civil Work
ii) Intermediate Slab
iii) Stairs / Railing
iv) Brick work
v) Fixing of Girder/ Chain Pully
vi) Roof Slab
4 Generator room 1 Job
i) Arrangement of material / labour / machinery
ii) Excavation and lean concrete
iii) Steel fabrication for columns and beams
iv) Concrete pouring in columns and beams
v) Brick work / Foundation / cable trench / flooring
vi) Fabricatio for Roof Slab
vii) Concrete laying in Roof Slab
viii) Fixing of Windows/ Ventilators/ Door Shutters
ix) Plaster
x) Electrification
5 Installation of Machinery & Yard Piping 1 Job
i) Constructio of foundations for pumps
ii) M.S Sheet Installation under pumps
Sr. No.
Description Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11Sr. No.
iii) Fixing of machinery
iv) Yard piping (suction / delivery with specials)
6 Screening Chamber 1 Job
i) Arrangement of material (Screen/Penstock.etc)
ii)
iii) Fixing of Screen
iv) Fixing of Pen Stock
7 Boundary wall 3 m / day 200 m
i) North Side
ii) East Side
iii) West Side
iv) South
8 GRP Pipe 40" dia 290 m
i) Arrangement of GRP Pipe
ii) Laying of Pipe
iii) Testing of pipe
9 Electrical works 1 Job
i) Manual Change Over
ii) Control Panel
iii) Motor control Centre
10 Ventilating Shaft 4 Nos
i) Arrangement of material (Poles, etc)
ii) Fixing of Poles
B Package III,V1 LAW6-b 18" i/d
i) Manufacturing of pipes
ii) Laying of pipes 219 m / 90 Nos.
2 Under water sewer(KLM 30") 15 m/ (4 MH)
i) Arrangement of material / labour / machinery
ii) Laying of pipe
3 L4a 21" i/d 2 MH
i) Arrangement of material / labour / machinery
Intermediate Slab (Shuttering/Steel Fabrication/Concrete Pouring)
Description Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11Sr. No.
ii) Laying of pipe
4 LAW1-b 15" i/d 112 Mtr
i) Arrangement of material / labour / machinery
ii) Laying of pipe
5 Under water sewer(KLM 36") 18 Mtr (1 MH)
i) Shifting of Poles
ii) Arrangement of material / labour / machinery
iii) Laying of pipe
6 L5a 12" i/di) Manufacturing of pipe 677 Mtr 279 Nos.
ii) Laying of pipe 677 Mtr 279 Nos.
7 LAW3-b 15" i/di) Manufacturing of pipe 60 Mtr/ 25 Nos
ii) Laying of pipe 60 Mtr 3 M.H
8 Forcemain 12" dia Basti Shahidan 901 Mtr
i) Arrangement of GRP Pipe
ii) Laying of pipe
iii) Testing of Pipe
9 L4b 12" i/d 115 Mtr
i) Arrangement of material / labour / machinery
ii) Laying of pipe
10 Remaining connections in Package III,V 50 Mtr
i) Arrangement of material/ labour/ machinery
ii) Laying of pipe
C Package IX Part I
Lift station Chak 111/P
1 Generator Room 1 Job
i) Arrangement of material/ labour/ machinery
ii) Excavation and lean concrete
iii) Steel Fabrication for columns and beams
iv) Concrete pouring in columns and beams
Description Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11Sr. No.
v) Brick work/ Foundation/ Cable Trench/ Flooring
vi) Fabrication for Roof slab
vii) Concrete laying in Roof slab
viii) Fixing of Windows/ Ventilators/ Door Shutter
ix) Plaster / Finishing
x) Electrification
2 Dry well 1 Job
i) Civil Work
ii) Intermediate Slab
iii) Stairs / Railing
iv) Brick work
v) Fixing of girder / Chain pully
vi) Roof slab
3 Installation of Machinery 1 Job
i) Construction of foundation for pumps
ii) M.S Sheet Installation under pumps
iii) Fixing of machinery
iv) Yar piping (Suction / Delivery with specials)
4 Electrical works 1 Job
i) Manual Change Over
ii) Control pannel
iii) Motor control centre
Lift station Nore wali/ Kacha sadiq abad road
1 Electrical works 1 Job
i) Manual Change Over
ii) Control pannel
iii) Motor control centre
2 yard piping (Suction / Delivery with specials) 15 Mtr
D Package IX Part II
Description Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11Sr. No.
Lift station J1 Point Water works
1 yard piping (Suction / Delivery with specials) 1 Job
2 Boundary wall 63 Mtr
i) North Side
ii) East Side
iii) West Side
iv) South Side
Lift station Basti Nayian
1 Forcemain(C.I) 32 Mtr
i) Arrangement of Pipe / Labour / machinery
ii) Laying of pipe
E STP,Moye Mubarak P.VIII
1 Earth Work 157805 Cum
i) Excavation / Filling for Ponds 1520 cu.m/day
2 Lining of Anaerobic ponds 220 Sq.m / Day 3521 Cum.
i) Arrangement of material / labour
ii)
3 Lining of Facultative Ponds 172 Sq.m / Day 3972 Cum
i) Arrangement of material / labour
ii)
4 Lining of Maturation ponds 61 Sq.m / Day 1361 Cum
i) Arrangement of material / labour
ii)
5 Distribution Chamber 1 Job
i) Arrangement of material
ii) Excavation / Lean concrete
iii) Steel Fabrication for Base Slab
iv) Concrete Laying in Base Slab
Lining (daily consumption of bricks 2537159 / 215 = 11800 Nos/ day)
Lining (daily consumption of bricks 1893929 / 205 = 9240 Nos/ day)
Lining (daily consumption of bricks 648952 / 200 = 3245 Nos/ day)
Description Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11Sr. No.
v) Steel Fabrication of Walls
vi) Concrete pouring in walls
6 Inlet Channel 7 m/ day 497 Mtr
i) Arrangement of material and labour
ii) Excavation / Lean concrete
iii) Steel Fabrication in Base Slab
iv) Concrete laying in base Slab
v) Steel Fabrication for walls
vi) Concrete pouring in walls
7 Interconnection 1 Job
i) Arrangement of Material / Labour
ii)
iii) Excavation / Lean Concrete 1 Structures/day
iv) Steel Fabrication of Inlet / outlet slides 1 Structure/day
v) Concrete laying of inlet / outlet slides 1 Structures/day
vi) Laying of pipes and concrete pouring 1 Structures/day
8 Outlet Channel 8 m / day 549 Mtr
i) Arrangement of material and labour
ii) Excavation / Lean concrete
iii) Steel Fabrication in Base Slab
iv) Concrete laying in base Slab
v) Steel Fabrication for walls
vi) Concrete pouring in walls
9 Soling / Brick Pavement ( 1204 m) 16 m / day 5098.67 Cu.m
i) Arrangement of Material / Labour
ii) Levelling / Dressing / Compaction of bed 50 m / day
iii)
10 Area Lighting 1 pole/ 3 days 1 Job
i) Arrangement of poles
ii)
11 Plantation 3090 Nos
i) Laying of Sweet soil
Casting of R.C.C pipes 21"i/d = 56 Nos,18" i/d = 32 Nos.
10 pipes/day10 pipes/day
Pavement (Cosumption of bricks 2431148/75 = 32415 Nos./ day)
Installation of poles with laying of wires (8 nos. x 3 days = 24 days)
Description Balance Qty. Nov,10 Dec,10 Jan,11 Feb,11 Mar,11 Apr,11 May,11 Jun,11Sr. No.
ii) Arrangement of plants
iii) Plantation 3090/30 = 103 Plants /day
12 Barbed Wire Fence 2575 Mtr
i)
ii)
iii)
iv)20 Poles / day
v)150 m / day
Arrangement of Material / Labour / Moulds for casting of R.C.C Posts
Moulds 5 Nos.Base Plate 15 Nos.
Casting of Concrete Poles (1051/15 = 70 days)
Arangement of barbed wire (13 gauge) and eye bolts (10 mm)
Installation of Concrete Poles 1051 /20 = 53 days
Installation of Barbed Wire (2575 / 150 = 18 days)
SEWERAGE SCHEME OF RAHIM YAR KHAN CITY WITH TREATMENT PLANTZONE II
Targets of Balance Work
Remarks
M/S Friends Engineering Co.
Remarks
work is in progress
M/S Nisar Ahmed & Company
work is in progress
Further time extention may be required after June 2011