CONSULTANT’S ORGANIZATION
FIRM’S ORGANIZATION AND CORE BUSINESS
FIRM OVERVIEW
ASTRIK International Ltd is an experienced, privately owned Engineering Consulting
Company with its office based in Kimironko, City of Kigali, Rwanda. Since its incorporation in
January 2014, the Company has entered into partnerships with highly recognized International
Organizations/Institutions, which operate at the forefront of technical excellence in developing
infrastructure solutions around the world.
ASTRIK has been at service to different Clients/Employers in Rwanda and the Region and has
successfully undertaken a different number of projects. The Staff are skilled in providing
consulting services on Engineering infrastructure and operations, for appropriate solutions which
are sustainable and affordable to the public and private sectors as well as transfer of technological
knowledge to the practitioners in Rwanda and beyond.
ASTRIK Management structure is presented as follows;
CORE COMPETENCE
ASTRIK’s core competence in Engineering Infrastructure lie in providing a highly qualified team
of experts both Nationals and Internationals in delivering quality services by utilising best
available resources
Feasibility Studies
Reconnaissance Survey : Problem Identification, Stakeholders consultation,
preliminary studies and assessment of development
potentials, formulation of development concepts,
development strategies and scenarios, initial project
Page -3
appraisal, budgeting and programming of further
investigations.
Field Investigations : Topographic survey, aerial photography (Drone technology)
and mapping, meteorological and hydrological surveys,
geological and hydro-geological surveys, geophysical
survey, materials survey, underground resources
investigation, pedological soil surveys, land use survey, land
classification survey, transportation survey, traffic survey,
demographic survey, socio-economic survey, marketing
survey, Environmental assessment (Negative/positive) and
Mitigation measures
Technical Detailed Design
Engineering detailed
design
: Preliminary design, detailed engineering investigations and
study, material tests, model tests, computer simulation,
detailed engineering design, cost estimate, construction
planning, preparation of prequalification documents,
preparation of bills of quantities (BoQ) and technical
specifications.
Tender Preparation and
Assistance
Tender Documents and
Tender assistance
: Identification of appropriate Project Contracts (FIDIC
rainbow), determination of Particular Conditions, The use of
National Procurement guideline, Assistance in tendering and
contract negotiations and awarding
Rehabilitation, Upgrading and
Construction
Monitoring and Supervision
and Contract Management,
devising Engineering
Advice on Construction
: Construction supervision and management, engineering
advice on construction, inspection and testing.
Operation & Maintenance
Operation & Maintenance : Monitoring on performance, safety audit, Condition
assessment (visual, mechanical, sampling, technical audit),
modeling of operation, post-evaluation.
Maintenance Determine deterioration model, providing maintenance
strategies, budgeting using HDM4 program, devising
appropriate maintenance technology including LBT/HIMO
Training/Capacity Building
Training, Manuals and
Transfer of Technology
: Preparation of tailor made training modules, for the contract
management under FIDIC, Project Management (PMP)
pavement/Asphalt technology for rehabilitation, upgrading
and construction, On-job capacity building/ transfer of
technology for client's personnel, Contractors and Young
Engineers/professionals
Page -4
MAIN FIELD OF SPECIALIZATIONS
ASTRIK is specialised in providing engineering solutions across a wide spectrum of disciplines.
Transportation Building Service and Urbanization
▪ Infrastructure (road network planning and
design for National, Urban, Rural/Feeder
roads)
▪ Building Concept, Modeling
Architectural Designs
▪ Road safety system design and Technical
Audits
▪ Industrial building design and
supervision
▪ Traffic Survey, flows modelling
/operations including Non-motorised
transport (NMT)/Green transport
▪ Urban settlement accessibility
studies
▪ Hydraulic, hydrology design including
geotechnical and landslide protections
investigation and evaluation
▪ Landscaping, greening design and
supervision
▪ Transport policy development and
evaluation
▪ Urban Drainage system design and
supervision
▪ Public transport surveying and planning
▪ Urban Parking design, signage’s
and street lighting
▪ Airport infrastructure design (Runway,
Apron, Taxiway and support infrastructure)
▪ Urban Master plan and settlement
development/Real estate
Water and Sanitation Irrigation and Dams
▪ Water resource investigation and
development
▪ Wetland Irrigation and Drainage
system design and supervision
▪ Water supply system planning, design and
supervision (National, Urban, Rural)
▪ Soil stabilization, Dam/Dyke
structure planning, design and
supervision
▪ Liquid waste/Sewage system planning,
design and Treatment plant equipment ,
disposal and maintenance strategies
▪ Wetland zoning and piping
installations and water supply
▪ Solid Waste Disposal system, transfer
stations and dumping site
▪ SMES development on irrigation
management system design and
supervision
▪ Urban road utilities installation planning
and maintenance management strategies
▪ Dyke maintenance strategies and
Hydraulic modeling using generated
flood profiles and flood scenarios
ASTRIK’s Niche services offered in engineering fields include;
Management Services: Training for Capacity Building:
▪ Project Management planning,
budgeting and life cycle strategies
▪ Community facilitation on road
maintenance
▪ Construction Contract Management
advisory
▪ On-job training on pavement technology,
(materials, recycling for rehabilitation,
upgrading,) NMT, Lab and field testing
▪ FIDIC conditions of contract (red, yellow, green,
silver and pink books)
▪ Project Management for Professional (PMP)
Page -5
▪ Labour Based Technology (LBT) for Road
maintenance, rehabilitation
▪ Road safety and Technical Audit
▪ Construction Equipment and Modern Technology
ASTRIK REGISTRATION WITH PROFESSIONAL BODIES
▪ Registered as a Consulting Engineering firm with Institution of Engineers Rwanda (IER)
professional body, Reg. no A005/REC/ECF/201.
▪ Registered with Rwanda Public Procurement Authority (RPPA)
▪ Registered as a Capacity Building service provider with Rwanda Capacity Building Secretariat,
▪ Trainer’s manager in partnership with FIDIC International for FIDIC contract Modules
(rainbow suits)
ASTRIK ANNUAL TURNOVER FOR THE LAST 5 YEARS
Fiscal Year 2015 2016 2017 2018 2019
Turn Over
Equivalent1(USD)
175,923.00 323,440 86,070.94 166,454.33 99,935
Current Assets2 91,915.42 138,797 39,385.88 90,032.61 67,578
Current Liabilities3 27,082.53 59,169 14,764.71 33,672.22 29,765
Notes:
1The gross inflow of economic benefits (cash, receivables, other assets) generated from the ordinary operating
activities of the ASTRIK (such as sales of goods, services, interest, royalties, and dividends) during the year. 2A balance sheet account that represents the value of all assets that are reasonably expected to be converted into cash
within one year in the normal course of business. Current assets include cash, accounts receivable, inventory,
marketable securities, prepaid expenses and other liquid assets that can be readily converted to cash. 3ASTRIK’s debts or obligations that are due within one year. Current liabilities appear on the company's balance sheet
and include short term debt, accounts payable, accrued liabilities and other debts.
ASTRIK PROFESSIONAL STAFF (PERMANENT AND MOU)
ASTRIK has recruited professionals who are permanent staff and other professionals have signed
project based Memorandum of Understanding with ASTRIK to provide their services as required
by the Terms of Reference on any Particular Tender. The total number of available staff in ASTRIK
for the professional services is 45 as indicated below:
Field of Specialist No. Professional Registered
Professional
Engineer Technologist/Technician
Road/Pavement/Material 4 6 IER
Geology/Geotechnical 3 6 IER
Hydraulic/Bridge 3 IER
Traffic/Road Safety 1
Transport Economics 1 IER
Architectural 2 RIA
Urban Planners 2 IER
Building/Structure 2 IER
Electrical 3 1 IER
Mechanical 2 IER
Page -6
Plumber 1
Quantity Surveyor
/Valuer
2 RIA
Topographic Surveyor 4
Environmentalist 8 RAPEP
Sociologist 3
Irrigation 1 IER
Water and sanitation 1 IER
Legal Expert 1 RBA
Claim/ Contract Expert 1 IER
Procurement Specialist 1
Total 45 14
ASTRIK has established an understating with International Consulting Firms and Research
Institutions to provide specialized technology skills in consulting services and providing backup
to the National Professional Staff for project quality management.
ASTRIK QUALITY MANAGEMENT SYSTEM
We maintain the highest standards in consultancy services during all phases of the project
management (i.e. feasibility, technical design, procurement, monitoring and supervision,
performance and maintenance). We recommend appropriate solutions on Rwandan Made products
which are technically sound and economical viable. We place our end-user first and perform
stakeholder’s consultations and improve services for Client satisfaction. The adopted Quality
Management System comprises of a sustainable cycle with various input activities applied
professionally by the ASTRIK Management.
CODE OF ETHICS FOR ENVIRONMENTAL, SOCIAL, HEALTH
AND SAFETY
ASTRIK has extensive experience of managing assignments in accordance with rigorous
environmental, social, health and safety requirements. The majority of the company’s projects
have been implemented within Rwanda which has a well-regulated environmental, social, labour,
health and safety legislative framework.
The company has experience of working on World Bank, AfDB and other donor financed
assignments, which also require that projects be implemented in accordance with strict health,
safety and environmental procedures.
The company has developed a Code of Ethics for Environmental, Social, Health and Safety to be
adhered to by the Key and non-key Staff while carrying out the assignments from planning,
Page -7
designing, through to construction supervision and operations.
CONSULTANT’S EXPERIENCE
Feasibility Study, EIA Study ,RAP, Detailed Engineering Design, Tender Document Preparation , Design Review and
Construction Supervision of Road Projects
Duration Assignment name & brief
description of the main
deliverables
Name of Client &
Country of
Assignment
Approx.
Contract
Value
Role on the
Assignment
Dec 2019-Jan
2022
Design Review and Supervision
for rehabilitation, upgrading and
multi-year maintenance of
indicative feeder roads in the
Districts of Nyagatare, Gatsibo,
Nyaruguru, Rutsiro, Nyabihu and
Gankenke (448km), including
ESAI/ESMP and RAP)
Rwanda, RTDA/WB USD 5,798,413 JV Partner with
MARISWE Pty
Sept 2019 to Oct
2022
Technical Assistance to Local
Government (LODA) to all districts
including City of Kigali on Urban
planning, road and drainage
infrastructure, building
infrastructure (heath Centre,
markets, schools, offices,
agriculture infrastructure for
postharvest), Capacity building
Rwanda, LODA/KFW EUR 4,000,000 JV Partner with
GOPA
May-July 2019 Technical Study for the
topographic survey and
Geotechnical study for the location
of HIRAX sites in Musha and
Kiziguro areas (including
infrastructure networks)
Rwanda, QLA-AIMS USD,9,000 Sole Consultant
Sept 2017-Setp
2020
Detailed improved design and
supervision for the construction of
Nyandungu wetland eco-Tourism
Park in Kigali City, including ESAI
and ESMP)
Rwanda, REMA/
FONERWA
USD 67 000 Sole Consultant
Oct 2016-Nov
2019
Design review and Supervision
for the Construction of Gabiro
Airstrip (1200m runway, Taxiway,
Apron and building facilities)
Rwanda, GASABO
3D/MoD USD 30 100 JV Partner with
GASABO 3D
May 208-July2099 Detailed Engineering design for
the selected road (28.54Km) in the
settlement in City of Kigali
(including ESAI and ESMP)
Rwanda, CoK USD81,522 JV Partner with
GASABO 3D
May-July 2018 Technical study for data collection
survey on Development of Urban
Transport Services in Kigali City
Rwanda, JICA USD64 275 JV Partner with
NIPPON KOEI
Dec 2017 Technical Study Review and
Contract Management and Claim
for Upgrading of
Base-Rukomo-Nyagatare road,
Phase I Base-Rukomo (51.54Km)
Rwanda, CHICO USD 26 000 Sole Consultant
Oct 2016 Detailed Engineering Design for
the Construction of Gabiro Airstrip
(1200m runway, Taxiway, Apron
and building facilities)
Rwanda, GASABO
3D/MoD
USD 12 600 JV Partner with
GASABO 3D
Page -2
Nov 2016 - Sept
2017
Technical Audit for the value for
money on feeder roads
rehabilitation (162.8Km) and
maintenance (664.2Km) in five (5)
Districts of Burera, Musanze,
Gicumbi, Nyamasheke and Rusizi
Rwanda, KPMG USD 10 080 Sole Consultant
April 2015 Feasibility study and detailed
engineering and landscaping
study of Nyandungu wetland
eco-recreation park (134Ha), City
of Kigali (including ESAI and
ESMP)
Rwanda,
REMA/FONERWA
USD50000 JV Partner with
GASABO 3D
Feb, 2014 Feasibility Study and Detailed
Engineering Design for
development of Urban Transport
Master Plan (road, parking,
NMT, Street lights, drainage) and
Solid waste management and
dumping sites for Nyamagabe
District in Rwanda
Rwanda, GITECH USD 23 000 Sole Consultant
Detailed Design, Integrated Master Plan and Construction Supervision of Building Projects
May 2017 Detailed Architectural and
Structural Design, Supervision
and Contract Management of the
Construction of Wood Factory, road
and parking (9500m2) for JMG
Contractor including ESAI and
ESMP)
Rwanda, JMG
Contractor
USD 43 000 Sole Consultant
May 2017 Detailed Architectural and
structural design for the
rehabilitation and Equipping REB
Video Theatre
Rwanda, Rwanda
Education Board
(REB)
RWF 5, 841,
000
Sole Consultant
Oct 2017 Detailed Engineering Design
(Architectural and Structural
Design), Supervision for the
Construction of Storage Warehouse
and Offices for Heart of Africa,
Industrial Park Kampala. including
ESAI and ESMP)
Uganda, Africa
Logistics Ltd
USD 63 000 Sole Consultant
Aug-Sept 2016 Detailed Architectural interior
design for the Wibura
Audio-Visual Studio and
proposition of the studio
equipment
Rwanda, Wibura
Company Ltd
RWF
8,300,000
Sole Consultant
Dec 2015-Jan 2016 Detailed developing a model
Video Theatre to blended learning
approach, the unmatched art-of-
studio with the use of modern
technologies for OMEGA
Technology
Rwanda, OMEGA
Technology Ltd
RWF 6,500,000 Sole Consultant
June 2015-July
2016
Detailed Architectural and
structural design of the BUCLINO
Audio-Visual Studio
Rwanda, BUCLINO
Company Ltd
RWF 5,800,000 Sole Consultant
June-Sept 2014 Detailed design and construction
supervision of overhead deck for
car parking and Disco theater at
Villa Portfino Hotel , Nyarutarama
Rwanda, Villa Portfino
Hotel
RWF
29,800,000
Sole Consultant
Page -3
Capacity Building Program
July 2018 Training on Contract Management
FIDIC Contract (module 1) for the
Construction Supervision
Rwanda, Construction
Industry
USD 32 700 In Partnership with
FIDIC International
May 2016 Training on Contract Management
FIDIC Contract (module 1 and 2)
for the Construction Supervision
Rwanda, Construction
Industry
USD 34800 In Partnership with
FIDIC International
Assignment Name: Country:
Design Review and Supervision for rehabilitation,
upgrading and multi-year maintenance of indicative
feeder roads in the Districts of Nyagatarre, Gatsibo,
Nyaruguru, Rutsiro, Nyabihu and Gankenke (448km),
including ESAI/ESMP and RAP)
Rwanda
Location within Country: Professional Staff Provided by Bidder (profiles):
Nyagatarre, Gatsibo, Nyaruguru, Rutsiro, Nyabihu and
Gankenke Districts (4448km)
Project Manager, Team Leader,
Resident Engineers,
Environmentalist, Sociologist,
Geotechnical/materials, Hydrologist,
Non-key Personnel etc.
Name of Client: No. of Staff:
Rwanda Transport Development Agency, RTDA Total : 11 (Foreign Only)
ASK : 33 (Nationals)
Address: No. of Staff-Months: Duration of Assignment:
KG 563 St., Queen’s Land House, 1st Floor,
P.O Box 6674, Kigali-Rwanda Total : 37 Months
Start Date: (Month/Year) Completion Date: (Month/Year)
Approx. Value of Services (in Current US$):
12/2019 1/2022 Total : US$5,798,413
Name of Associated Consultants, If Any: No. of Months of Professional Staff Provided by Associated Consultants:
MARISWE Consulting Ltd, South Africa Foreign : 69.1 M/M
Local : 249.9 M/M
Name of Senior Staff (Project Director/Coordinator, Team Leader) Involved and Functions Performed:
Project Manager Foreign (MARISWE) : Dr. Lucas Jan-Ebels
Project Coordinator National (ASTRIK)Manager : Dr. Twagira Elias
Page -2
Narrative Description of Project:
The World Bank has introduced new model on feeder roads execution project in Rwanda under
Output and Performance-based Contracting for Roads (OPRC) which is aimed at increase the
efficiency and effectiveness of road asset management and maintenance. The Contractors were
responsible for carryout design –build and multi-year maintenance (DBM). The Consultant
assignment was to review contractor’s design, management plans and Monitoring and Supervision of
construction works for rehabilitation, and upgrading earth feeder roads to a paved and gravel
standard. Supervision also includes the environmental, social (Sexual Exploitation and Abuse (SEA)
and Gender-Based Violence (GBV, Health and Safety (ESHS) requirements that need to be satisfied by
the Contractors in designing and executing the Works.
Main Components of the Project
Lo
t
Components Descriptions
1 Feeder Roads Nyagatare District Lot 1: 38km, Lot 2: 17Km.
2 Feeder Roads Gatsibo District Lot 1: 385m, Lot 2: 29Km, Lot
3:19km
3 Feeder Roads Nyaruguru District Lot 1: 34m, Lot 2:35Km
4 Feeder Roads in Nyabihu District Lot 1: 34m, Lot 2: 33Km, Lot
3:26km
5 Feeder Roads in Rutsiro District Lot 1: 41Km, Lot 2: 25Km, Lot
3:13km
6 Feeder Roads in Gakenke District Lot 1: 32Km, Lot 2: 18Km, Lot
3:19km
TOTAL 16Lots: 448Km
Page -3
Description of Actual Services Provided by Your Staff:
- Review of the Detailed Design submitted by the Contractors
- Review and approve materials’ quarries; borrow pits and dumping sites proposed by the
contractors
- Review: the (i) Contractors’ Environmental and Social Management Plan (C-ESMP), (ii)
Occupational Health and Safety Management Plan (OHSMP), the (iii) Labor influx,
Gender-Based Violence, Sexual Exploitation and Abuse, and Violence and Abuse against
Children Prevention and Response Action Plan (PRAP), the (iv) Code of Conduct prepared
by the Contractors, and the (v) Emergency Procedures and Contingency Plan presented by
the Contractors, vi) Traffic Management Plan and Capacity Building on the Technology
Transfer
- Monitoring and supervision construction of works for Rehabilitation / Upgrading
- Inspecting Road Condition during maintenance period
- Monitoring the Implementation of RAP and ESMP and ESHS management strategies and
implementation plans during mobilization, construction and maintenance
Assignment Name: Country:
IMPROVING OF DETAILED DESIGN AND
SUPERVISION FOR THE CONSTRUCTION OF
NYANDUNGU WETLAND ECO-TOURISM PARK (130Ha)
IN KIGALI CITY
Rwanda
Location within Country: Professional Staff Provided by Bidder (profiles):
Nyandungu in the City of Kigali Project Manager, Resident Engineer,
Quantity Surveyor, Architecture,
landscape Arch, Botanist, Structural
Materials engineer, Civil Engineer,
Surveyor, Electrical, Mechanical
engineer etc.
Name of Client: No. of Staff:
Rwanda Environment Management Authority (REMA) Total : 11
ASK : 5
Address: No. of Staff-Months: Duration of Assignment:
Page -4
Inyota House, Kacyiru; KG 7Av.
P.O. Box 7436 Kigali, Rwanda Total : 31 Months
Start Date: (Month/Year) Completion Date: (Month/Year)
Approx. Value of Services (in Current US$):
09/2018 09/2021 Total : US$139,266
Name of Associated Consultants, If Any: No. of Months of Professional Staff Provided by Associated Consultants:
Gasabo 3D design Ltd Total : 107 M/M
Name of Senior Staff (Project Director/Coordinator, Team Leader) Involved and Functions Performed:
Project Manager (Design Phase) (ASTRIK) : Dr. Twagira Elias
Project Manager (supervision Phase) Gasabo 3D) :Eng. Ganthil Kangaho
Narrative Description of Project:
In 2015, Rwanda Environment Management Authority, REMA awarded a tender to ASTRIK
International to conduct a conceptual study for the establishment of urban wetland recreation and
eco-tourism park in Nyandungu valley in the City of Kigali. The study recommend a full development
of Nyandungu wetland to address the citizen opinions of ensuring the safe recreation places, offering
cutting-edge services and providing various cultural and educational program as well as contributing
to the well-being of the citizens. In May 2017, REMA contracted Gasabo 3D in Joint Venture with
ASTRIK International to carry out full development of a detailed design, landscaping design and
supervision of the project implementation.
Page -5
Main Components of the Project
Lo
t
Components Descriptions
1 Detailed landscaping design for
ecological and rehabilitation
enhancement (130Ha)
Planting of Selected plants
species, vegetation
2 Detailed design of low ecological
impact landscaping, Including living
machine
Ponds, Flood Control, stream
widening, drainage for waste
infiltration
3 Detailed design of low impact
recreational amenities,
Walkway, wood bridges, benches,
parking, toilets, Info-Centre,
amphitheater
4 Detailed design of educational and
recreational attraction
Botanic garden, birds
observatory, etc
5 Preparation of BOQ List of items to be executed with
related costs
6 Monitoring and Supervision for
Construction of works
Description of Actual Services Provided by Your Staff:
- Improved Detailed landscaping design for ecological and rehabilitation enhancement of the
wetland
- Improved Detailed design of low impact recreational amenities,
- For Monitoring and supervision; Review and approve materials’ quarries; borrow pits and
dumping sites proposed by the contractors
- Review: the (i) Contractors’ Environmental and Social Management Plan (C-ESMP), (ii)
Occupational Health and Safety Management Plan (OHSMP),
- Monitoring and supervision construction of works for ecological and Rehabilitation of the
wetland
Page -6
Assignment Name: Country:
DESIGN REVIEW AND SUPERVISION FOR THE
CONSTRUCTION OF GABIRO AIRSTRIP (1200M
RUNWAY, TAXIWAY, APRON AND BUILDING
FACILITIES
Rwanda
Location within Country: Professional Staff Provided by Bidder (profiles):
Gatsibo District in East province Resident Engineers, Pavement
/materials, Specialist etc.
Name of Client: No. of Staff:
Gasabo 3D Design/Ministry of Defense Total : 9
ASK : 1
Address: No. of Staff-Months: Duration of Assignment:
KG 563 St., Queen’s Land House, 1st Floor,
P.O Box 6674, Kigali-Rwanda Total : 36 Months
Start Date: (Month/Year) Completion Date: (Month/Year)
Approx. Value of Services (in Current US$):
10/2016 11/2019 Total : US$276,664
Name of Associated Consultants, If Any: No. of Months of Professional Staff Provided by Associated Consultants:
Gasabo 3D Design Ltd Local : 220 M/M
Name of Senior Staff (Project Director/Coordinator, Team Leader) Involved and Functions Performed:
Project Manager (Gasabo 3D) : Eng. Genthil Kangaho
Resident Engineer (Team Leader) (ASTRIK): Dr. Twagira Elias
Page -7
Narrative Description of Project:
The Ministry of Defence Rwanda (MoD) contract Gasabo 3D to carryout detailed design of the Gabiro
Airbase (green field) and ASTRIK was sub contracted with G3D as a team leader in the execution of
the project which includes the design and supervision of the Runway 1.4Km, Apron 300m2, taxiway
380m, building facilities, i.e. Administration, Mess, ATC, Fire Fight, hangars (maintenance& storage),
hazardous, accommodations (Senior, Junior and NCOs) power house, fuel shade, water supply,
electrical supply, access road and parking etc
Main Components of the Project
Lo
t
Components Descriptions
1 Runway (paved with AC 110mm) Distance 1400m with 100m
overshoot
2 Taxiway paved with AC110mm Distance 380m
3 Apron Areas 300m2
4 Area for Future extension, Apron,
Taxiway, hangars
Over 2000m2
5 Air Traffic Control (ATC) building G+2 floor
6 Administration building G+1 floor
7 Hangars 35x25M Maintenance and Storages
8 Fire Fight building
9 Perimeter roads, access road, Parking
and Fence
6Km
10 Accommodation (Senior, Junior, NCOs) G+2 and G respectively)
11 Other facilities (mechanical, electrical,
gardening, drainage system, street light
signage’s etc
Page -8
Description of Actual Services Provided by Your Staff:
- Analysis of the runway orientation and any obstacles around the selected new green field site in
accordance with ICAO, IATA and RCAA standards, specifications and guideline
- Detailed engineering design of the pavement structures for the runway, taxiway, and apron,
- Detailed design of the airside and landside access roads, storm water drainage, and fencing
structure
- Soil investigation and materials selections for the embankment construction, pavement
construction for runway, taxiway and apron.
- Preparing technical design report, bills of quantities, and confidential costs estimates
- Monitoring and supervision for the construction activities including contract management and
implementation plans during mobilization, construction and maintenance
Assignment Name: Country:
TECHNICAL REVIEW AND STUDY, CONTRACT
MANAGEMENT AND CLAIM FOR UPGRADING OF,
PHASE I BASE-RUKOMO (51.54KM)
Rwanda
Location within Country: Professional Staff Provided by Bidder (profiles):
Base-Rukomo road in North Province Claim Expert , Pavement Engineer
Name of Client: No. of Staff:
CHINA HENAN INTERNATIONAL COOPERATION GROUP CO. LTD
(CHICO)
Total : 1
Address: No. of Staff-Months: Duration of Assignment:
P.O.BOX 4398, Kigali –Rwanda Total : 12Months
Start Date: (Month/Year) Completion Date: (Month/Year)
Approx. Value of Services (in Current US$):
Jan 2017 Dec, 2017 Total : US$26,000
Name of Associated Consultants, If Any: No. of Months of Professional Staff Provided by Associated Consultants:
N/A Local :12MM
Name of Senior Staff (Project Director/Coordinator, Team Leader) Involved and Functions Performed:
Claim Expert FIDIC contract (ASTRIK) : Dr. Twagira Elias
Page -9
Narrative Description of Project:
CHICO Contractor was awarded a contract by RTDA to carry out construction work for the
Base-Rukomo road (5154Km) under the FIDIC conditions of Contract (Pink Book, AfDB), In order to
ensure that the key staff understand the use of the FIDIC Contract, CHICO contracted ASTRIK to carry
out a detailed technical review of the Employer design and prepared technical report appropriate
actions to be taken by the contractor. Carryout contract management by reviewing the site
instructions, Employers requirement and address all contractual claims raised by the contractor
during execution of works. The road was passing through challenging terrain which necessitated
several variations
Main Components of the Project
Lo
t
Components Descriptions
1 Design Review Pavement, material and
structures
2 Contract Management Analysis of issued site
instructions or change of the
design and preparation of
claims
Description of Actual Services Provided by Your Staff:
− Carryout detailed pavement, bridge structural design review for the proper action to be taken by
the contractor
− Review all instructions issued by the Engineer or Employer on site and advise the contractor for
proper actions
− Preparation Claims response as per the FIDIC (Pink Book) MDB condition of contract
− Review detailed construction drawings
− Review the prepare certificates for any contractor’s claims
Page -10
Assignment name:
Detailed Engineering design of Gabiro Airbase in
Gatsibo District (Green field land with runway
length 1200m)
Approx. value of contract (in currency:
Rwanda francs or freely convertible
currency):
RWF 17, 950,000
Country: Rwanda
Location within country: Eastern Province
Duration of assignment (months):
4
Name of client:
Gasabo 3D Design Ltd
Total no. of staff-months of the assignment:
1
Address:
Telcom House 1st Fl,
Box 7229,
Kigali –Rwanda
Approx. value of services provided by
your consultant under the contract (in
currency: US, RWF, etc.):
RWF 17,950,000
Start date (month/year): February 2016
Completion date (month/year): March 2016
No. of staff-months of professional staff
provided by Associated consultants:
Name of associated consultants, if any:
GASABO 3D
Name of senior professional staff of your
consultant involved and functions
performed (indicate most significant
profiles such as project director
/coordinator, team leader):
▪ Dr. TWAGIRA Elias-Team Leader-
Pavement and materials Engineer
Narrative description of project:
The Ministry of Defence Rwanda (MoD) appointed
Gasabo 3D to carryout detailed design of the Gabiro
Airbase (green field) and ASTRIK as sub consultant
was assigned to carry out the following activities:
− Analysis of the runway orientation and any
obstacles around the selected new green field site
• Carryout analysis of the landing and take-off safe
zones of the selected sites and condition survey on
the site , conducting detailed land surveying and
for the establishment of the reference points
− Detailed engineering design of the pavement
structures for the runway, taxiway, and apron
− Detailed design of the safety features of the
runway, taxiway and apron include proper
location of the Air Traffic Control Tower, Fire fight,
− Detailed design of the airside and landside access
roads, storm water drainage, and fencing structure
Page -11
− Soil investigation and materials selections for the
embankment construction, pavement construction
for both runway, taxiway and apron.
− Preparing technical design report, bills of
quantities, and confidential costs estimates
− Present the technical design to the stakeholders
Description of actual services provided by your staff within the assignment:
Runway orientation, Geotechnical investigation, pavement design, preparation of BoQ and tender
documentation, preparation technical report (draft and final )
Relevance to this assignment:
The ASTRIK experts devised the appropriate solutions on the design implementation of the
runway, taxiway, and apron as per ICAO standard and specifications for the construction of Gabiro
Airbase in the East Province and enhancing the Rwanda military activities. This assignment
demonstrates ASTRIK’s capability to fulfil the scope of works in carrying out designs and technical
audits that meet the client expectations and intended functions to the users.
Assignment name:
Implementation of Urban Transport Master
Plan for Nyamagabe District in Rwanda
Approx. value of contract (in currency: Rwanda
francs or freely convertible currency):
USD 55 000
Country: Rwanda
Location within country: Southern Province
Duration of assignment (months):
5
Name of client:
GITCH/RHA
Total no. of staff-for the assignment:
2
Approx. value of services provided by your consultant under the contract (in currency: US, RWF,
etc.):
USD 55 000
Start date (month/year): February 2014
Completion date (month/year): June 2014
No. of staff-months of professional staff provided by
associated consultants:
N/A
Name of associated consultants, if any:
N/A
Name of senior professional staff of your
consultant involved and functions performed
(indicate most significant profiles such as project
director / coordinator, team leader):
▪ Dr. Twagira Elias-Team Leader / Feeder road
Expert)
▪
▪
Narrative description of project
GITECH Ltd contracted ASTRIK to carryout detailed a master plan design for mobility
management, on the greenfield road network in term of walking, cycling and driving in the pilot
areas in the Nyamagabe District South Province Rwanda. The works involved the following
activities:
− To review the feability strudy on the proposed master plan examining the road network in
terms of walking, cycling and driiving in the selected pilot area Nyamagabe District
Page -12
− Defining the street topologies on the pilot areas the sustainable construction
− Designing Street elements for foot path, cycle path, carriageway, utility, on-street parking and
bus-stops operation
− Designing Safety elements for pedestrian crossing, ,Traffic culming measure, traffic signals,
railing and Bollards, vertical signage, street marking
− Preparing the design report and presentation to the client for validation
Description of actual services provided by your staff within the assignment:
− Field investigation and traffic flow assessment
− Detailed master plan design of transport infrastructure, in the pilot areas in the Nyamagabe
District
− Preparation of the urban transport mobility guideline with typical road typology
− Preparation of the design report.
Relevance to this assignment:
The ASTRIK experts conducted full Implementation of Urban Transport Master Plan for Nyamagabe
District. This assignment demonstrates ASTRIK’s capability to fulfil the required technical audit
works that meet the client expectations.
Assignment Name: Country:
DETAILED ARCHITECTURAL AND STRUCTURAL
DESIGN, SUPERVISION AND CONTRACT
MANAGEMENT OF THE CONSTRUCTION OF WOOD
FACTORY, ROAD AND PARKING (9500M2) FOR JMG
CONTRACTOR
Rwanda
Location within Country: Professional Staff Provided by Bidder (profiles):
Masoro Sector Kigali Economic Free Zone (KSEFZ) Project Manager,
Geotechnical/material,
Structure Engineer,
Architecture, Electrical,
Mechanical, Surveyor, Quantity
Surveyor
Name of Client: No. of Staff:
.M.G Construction & General Trading co. Ltd Total : 8
ASK : 8
Address: No. of Staff-Months: Duration of Assignment:
POBOX 7282. Kigali –Rwanda Total : 15Months
Start Date: (Month/Year) Completion Date: (Month/Year)
Approx. Value of Services (in Current US$):
May, 2017 July, 2018 Total : US$38,700
Page -13
Name of Associated Consultants, If Any: No. of Months of Professional Staff Provided by Associated Consultants:
N/A Local :95MM
Name of Senior Staff (Project Director/Coordinator, Team Leader) Involved and Functions Performed:
Project Manager Design (ASTRIK) : Dr. Twagira Elias
Resident Engineer Supervision (ASTRIK) : Eng. Joseph Ntwali
Narrative Description of Project:
JMG contracted ASTRIK to carryout detailed Master plan, drainage design, architectural,
structural design, Parking and Civil works for the construction of the Wood Factory and Garage in
Masoro-Kigali. The factory was planned to be State of Art Wood factory in Kigali Industrial area.
The 2.5 Ha virgin land were designed based on the KSEFZ guideline and the City of Kigali Master
Plan
Page -14
Main Components of the Project
Lo
t
Components Descriptions
1 Wood Factory Buildings Drying, processing, Storage,
2 Administration and exhibition building Admin and Furniture
exhibitions
3 Parking and garage Vehicles parking, circulation
and maintenance
4 Enumerating a list of equipment
needed for the factory operation
Drying, processing, dust control
etc
Description of Actual Services Provided by Your Staff:
− Feasibility and environmental studies for the factory compliance with the City Master plan
and RDB regulation
− Detailed architectural, interior design of expo room and structural, electrical and mechanical
design, of State of Art Wood factory in Kigali Industrial area
− Preparing detailed technical drawings, Bills and Bills of Quantities and technical
specifications for the construction of factory and Garage
− Enumerating a list of equipment needed for the factory operation
− Designing the Garage and parking configuration, safety plan, light system etc.
− Construction supervision and contract management liaising with the different sub-contractors
Assignment Name: Country:
DETAILED ENGINEERING DESIGN (ARCHITECTURAL
AND STRUCTURAL DESIGN), SUPERVISION FOR THE
CONSTRUCTION OF STORAGE WAREHOUSE AND
OFFICES FOR HEART OF AFRICA, INDUSTRIAL PARK
KAMPALA.
Uganda
Location within Country: Professional Staff Provided by Bidder (profiles):
Industrial Area Kampala-Uganda Project Manager,
Geotechnical/material,
Structure Engineer,
Architecture, Electrical,
Mechanical, Surveyor, Quantity
Surveyor
Name of Client: No. of Staff:
Page -15
Heart of Africa Supply and Logistic Ltd Total : 8
ASK : 8
Address: No. of Staff-Months: Duration of Assignment:
POBOX 27836, Kampala –Uganda Total : 15Months
Start Date: (Month/Year) Completion Date: (Month/Year)
Approx. Value of Services (in Current US$):
Jan, 2016 June 2017 Total : US$63,000
Name of Associated Consultants, If Any: No. of Months of Professional Staff Provided by Associated Consultants:
N/A Local :95MM
Name of Senior Staff (Project Director/Coordinator, Team Leader) Involved and Functions Performed:
Project Manager Design (ASTRIK) : Dr. Twagira Elias
Resident Engineer Supervision (ASTRIK) : Arc. Justine Mwesigwe
Narrative Description of Project:
Heart of Africa in Uganda contracted ASTRIK to carryout detailed, architectural, structural design
and supervision for the construction of the storage warehouse and offices in Kampala Industrial
Area-Uganda. The 1.5 Ha land were designed to provide the required facilities, including
parking, vehicle circulation, drainage system
Page -16
Main Components of the Project
Lo
t
Components Descriptions
1 Ware house Buildings Imported goods Storage,
2 Administration and exhibition building Admin
3 Parking Vehicles parking, circulation
4 Enumerating a list of equipment
needed for the storage, forklifts
Packaging and transportation
Description of Actual Services Provided by Your Staff:
− Detailed architectural, and structural, electrical and mechanical designs of storage
warehouse and offices including parking and drainage
− Preparing detailed technical drawings, Bills of Quantities (BoQ) and technical specifications
for the construction of storage warehouse and Offices
− Enumerating a list of equipment to be used in the warehouse
− Designing the parking and drainage system, safety plan, external light serving system etc.
− Construction supervision for the quality control and monitoring
Assignment Name:
Country:
TRAINING ON CONTRACT MANAGEMENT FIDIC
CONTRACT (MODULE 1) FOR THE CONSTRUCTION
SUPERVISION
Rwanda
Location within Country: Professional Staff Provided by ASTRIK (profiles):
City of Kigali Accredited FIDIC Trainer in
Contract Management
Training Coordinators
Name of Client: No. of Staff:
Construction Industry Practitioners Total : 3
ASK : 2
Address: No. of Staff-Months: Duration of Assignment:
Kigali City Hall, KN 3 Av, Kigali-Rwanda Total : 2 days
Start Date: (Month/Year) Completion Date: (Month/Year)
Approx. Value of Services (in Current US$):
Page -17
13/09/2018 14/09/2018 Total : US$22,880
Name of Associated Consultants, If Any: No. of Months of Professional Staff Provided by Associated Consultants:
FIDIC International Foreign: 2days
Local : 2days
Name of Senior Staff (Project Director/Coordinator, Team Leader) Involved and Functions Performed:
FIDIC Trainer (FIDIC) : Eng. Robert Werth
Training Coordinator (ASTRIK) : Dr. Twagira Elias
Narrative Description of Project:
In Rwanda and Construction Industry in particular, most of the awarded projects are improperly
conceived, under budgeted, not consistence with the design and specifications, which result into
claims and disputes. Therefore, in FIDIC Contracts, there will be Claims. The FIDIC training
Modules aims to address this challenge by providing a practical guide on the use and
management of contract including claims and Dispute Resolution using FIDIC module of Contract
Management and Multi-lateral Development Banks Harmonized Conditions of Contract
Management. The training targeted Construction Industry Practitioners including Employers,
Contractors, Engineers and Legal Advisers, Academicians etc
Main Components of the Project
Lo
t
Components Descriptions
1 Practical use and selection of the types
of FIDIC contracts
FIDC Module 1
2 The Management of Contract Claims
and the Resolution of Disputes
FIDIC Module 2
3 Understanding the FIDIC EPC/Turnkey
Contracts
Special Modules
Page -18
Description of Actual Services Provided by Your Staff:
- Introduction and Principles of FIDIC Contracts
- Responsibility of Main Parties
- Contract Management
- Financial Procedures
- Contractual Risks
- Claims and Contractual Procedures
- Time related Claims by Contractor
- Engineer as DAB, Amicable Settlement & Arbitration
- The Working of the DAB and Procedural Rules (PR)
- Work Exercises for award of FIDIC Certificates