PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Capacity Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
CONTENT
Chapter
No.Titles
I. EXECUTIVE SUMMARY
II. INTRODUCTION
2.1 Project
2.2 Cuddalore Port – Capacity Expansion Project
The Proposed Project
2.3 Need for the Project
2.4 Demand - Supply
2.5 Export Possibility
2.6 Domestic and Export Markets
2.7 Employment Generation
III PROJECT DESCRIPTION
3.1 Project Size and Type
3.2 Location of the Project
3.3 Alternative Sites
3.4 Extent of the Land
3.5 Project Components
3.6 Material Balance
3.7 Resource Optimization
3.8 Waste Treatment and Disposal
3.9 Project Feasibility
IV SITE ANALYSIS
4.1 Connectivity
4.2 Land Survey
4.3 Topography
4.4 Land Use Pattern
4.5 Existing Infrastructures
4.6 Soil Classification
4.7 Climate - Meteorology
4.8 Social Infrastructures
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Capacity Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
V PLANNING BRIEF
5.1 Conceptual Planning
5.2 Population Projection
5.3 Land Use Planning
5.4 Infrastructure Demand
5.5 Amenities / Facilities
VI INFRASTRUCTURES
6.1 Industrial Area
6.2 Residential Area
6.3 Green Belt Development
6.4 Social Infrastructure
6.5 Connectivity
6.6 Sewerage System
6.7 Industrial Waste Management
6.8 Solid Waste
6.9 Power
VII REHABILITATION AND RESETTLEMENT (R &R) PLAN
VIII PROJECT SHEDULE & COST ESTIMATE
IX ANALYSIS OF PROPOSAL
X CORPORATE RESPONSIBILITY PLAN
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Capacity Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
LIST OF TABLES
TableNo.
Title
2.1 Projection of Traffic Volume & Cargo handling
3.1 Capacity Expansion- Proposed Project Activities
LIST OF FIGURES
FigureNo.
Title
1.0 Key Map Cuddalore Port
2.1 Location Map – Google Image (10 km Radius)
2.2 HTL/LTL – CRZ Classification Map
2.3 Conceptual Layout – Cuddalore Port
2.4 Projected Traffic for Cuddalore Port
3.1Location of Proposed Activities towards Capacity Expansion-Cuddalore Port
3.2 Location of Project Area –LISS –III Satellite Imagery
3.3 Alternative Sites – Proposed Capacity Expansion- Cuddalore Port
4.1 LISS-III Raw Image – Project Location/ Cuddalore Port
4.2 Geomorphology – Project Location/ Cuddalore Port
4.3 Land Use – Project Location/ Cuddalore Port
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Capacity Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
LIST OF ANNEXURES
AnnexureNo.
Title
I Notification of Port- Go
II Consent to Operate (CTO) from TNPCB
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Capacity Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
I. EXECUTIVE SUMMARY
Tamilnadu is one of the maritime state of our country, historically known for Ports and
Harbors with its 1100 Km of coastal length. Tamilnadu is also a favorite destination for
tourists for other climatic and developmental features. Coastal Environment of
Tamilnadu is unique with Thirteen districts are representing coastal features out of 32
revenue districts. The coastal and terrestrial attributes complementing to each other.
The state shares a maritime border with the nation of Sri Lanka.
Tamilnadu has 3 major Ports and 1 minor with 5 fishing harbors and every Port is under
expansion mode including the VOC Port, which is the second largest Port of our country.
Chennai Port and Ennore Port are located in North to the project location by 180 Km.
Several Coastal power plants are in pipeline other than significant increase in the bulk
cargo into and outward. Albeit there is a regression in the industrial growth, the cargo
handling requirements through sea route is increasing.
Cuddalore Port is historic as anchorage Port which failed to prosper despite the
potential for development. The location is very suitable for further development as
berths can be constructed in a much better compatible river locations as the location is
a confluence of two rivers viz., Uppanar and Paravanar with Bay of Bengal.
Tamilnadu Maritime Board (TNMB) is the nodal agency of Government of Tamilnadu
and operating the Cuddalore Port. TNMB envisioned a proposal to upgrade and
augment its present capacity of cargo handling into Multi Cargo Handling Port to 5.68
MTPA.
Indian Port Association made a preliminary survey on the feasibility of expansion project
and Department of Ocean Engineering, Indian Institute of Technology-Madras has come
out with a detailed project report on complete planning, engineering design and
operability analysis on the feasibility of the proposed port expansion.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Capacity Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
The present operation of Port is restricted to Uppanar with a wharf of 400 m and
handling 0.37 MTPA of multiple cargos. The operation of Port has been consented by
Tamilnadu pollution Control Board (TNPCB) and a copy of the valid consent order is
presented as Annexure-II.
Presently, the Port has almost no activities in view of the silting and dredging is to be
undertaken to set navigation in the approach channel. TNMB is planned to expand the
Port facilities with redesigned Break Waters and Wharfs with infrastructures to
negotiate a multiple cargo with transit-storage facilities.
Cuddalore, per se, is known for its coastal resources especially fisheries. Uppanar is a
backwater there is a fishing harbor, which is just on the North boundary of the port
limits in the Uppanar. The coastal dependency is significant for the lifestyle of the
fishermen community in the project location is historic and it holds the most important
revenue to Government of Tamilnadu.
Tamil Nadu Maritime Board (TNMB) is keen to develop the possibility of augmenting the
cargo handling capacity at the Cuddalore Port. The Port is situated at the confluence
point of River Uppanar and Paravanar with Bay of Bengal.
Currently, the Port has two Training walls of length 180m in the north and 230m in the
south. If the basic break water infrastructure facilities of the port are not extended, and
if the situation in the river mouth is permitted to continue like this for some more years,
most of the river mouth portion will get silted up. The port users will no longer prefer
this port and the port activities may come to a grinding halt affecting primarily the
fishermen and the cargo operators. However, to cater the global market in current
scenario, the extension of Breakwater both North and South side are quite essential.
The existing wharf facilities are to be developed so as to facilitate larger DWT vessels.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Capacity Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
Port is a listed coastal activity and under the purview of EIA Notification, 2006. The
present project of capacity expansion is to establish two additional berths 120X38.70 m
each in the Paravanar stretch to handle multi cargo pattern of Cargo, Steel, Fertilizer
and Clean cargo like Containers for 5.69 MTPA. A requirement of capital dredging has
been assessed for 17, 30,000 m3.
The proposed project of TNMB is thus categorized under 7 (e) - A, which is mandated for
CRZ Clearance and also Environmental Clearance under the purview of EIA Notification,
2006; or in any amendments thereof.
The Key Map showing the location of the proposed Berths in the Cuddalore Port is
presented in Fig.1.0.
TNMB envisaged the proposed project to optimally use the coastal resources available
within the notified Port Area with a scheme to avail Financial Support from Government
of India.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Capacity Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
FIG.1.0. KEY MAP – CUDDALORE PORT
790 46’ 30”
110
42’ 3
0”N
110
42’0
0”N
790 46’ 30”
790 47’ 00”
790 47’ 00”
110
42’ 3
0”N
110
42’0
0”N
To Chidambaram40 km
To Vridhachalam40 km
To Pondicherry 20 km
NH-7 – 178 kmSH-32 – 1.5 km
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Capacity Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
A reconnaissance survey and the feasibility study on the proposed project of capacity
expansion of Cuddalore Port were already carried out by IIT (M) with detailed coastal
study and Port planning and designing.
The proposed project location was surveyed and assessed for its compatibility to
prevailing coastal environmental conditions. The met-oceanic data pertaining to project
location is learnt to be conducive for the proposed construction of additional two berths.
Coastal Model studies were run to get reassessed for environmental suitability and
sustainability of locating the project in the proposed location.
The location was surveyed through specific GPS protocol and LTL and HTL Mapping was
completed by Institute of Remote Sensing (IRS), Anna University and authenticated Map
was drawn to comply with the requirements and mandates of CRZ Notification, 2006.
Centre for Environment, Health & Safety (CEHS) is an integral part of the Department of
Civil Engineering and offers PG and Doctoral program in Environmental Engineering. CEHS
have several ongoing consultancy works apart from funded research programs from
various agencies like MoEF&CC, DST, MoNES and coastal development projects like
Expansion of VOC Port, Tuna Fishing Harbor and, etc. Annamalai University is state owned
and fully governmental.
CEHS is an accredited EIA Organization by Quality Council of India under National
Accreditation Board for Teaching & Training (NABET) for Ministry of Environment,
Forests & Climate Change (MoEF&CC), Government of India.
II. INTRODUCTION
TNMB prepared the Master Plan for the proposed additional Berths and enhanced Cargo
handling capacity by availing the services of IIT-Madras. The feasibility study by IIT
covered the coastal compatibility and also the types of cargo and its size.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Capacity Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
The expansion of the Cuddalore Port will enable the Coastal Thermal Poer plants in the
near zone to get the Coal from other places. Neyveli Lignite Corporation (NLCIL) is also
likely to avail the services of the Port.
Cuddalore has a major Chemical Industrial Complex and Pondicherry is located on North
by 20 Km. There is a huge demand and it is a long time pending project to ease out the
transportation of fertilizer by road and also Clean and container cargo.
As the proposed additional berths are much within the Port limits, there will not be any
intervention to settlement. The area required to establish additional infrastructures for
cargo transfer, transit-storage and handling is much available readily with TNMB. Hence,
there is no public concern for the project.
TNMB specifically took interest in not to intervene in the fishermen boats in the Uppanar
which has the Fishing Harbor on the North of the Port limit in the Uppanar. TNMB, on the
advice from IIT-M after careful examination on the feasible alternative locations, decided
the project in the proposed location in the Paravanar.
The Project is envisaged to comply with all statutory requirements under CRZ
Notification, 2011 and EIA Notification, 2006 and also as per the Guidelines of Central
pollution Control Board (CPCB). As the present activities in the Port limits are pre-
Notifications, TNMB is very specific to comply with these Notifications and establish the
Berths and other Cargo handling infrastructures as per the specifications of International
Standards as as per the guidelines of CPCB.
The proposed additional berths and cargo handling facilities will add value to Cuddalore
Port, including a positive impact on socio economic status of Cuddalore. With
transportation of cargo by roads have become costlier and time consuming, the present
proposal of augmenting the existing Port facilities for enhanced Cargo handling is a
important project for the state and so, Government of Tamilnadu has special schedules
and interest in completing the project in time.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Capacity Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
2.1 PROJECT
The proposed project is principally additional facility of Cuddalore Port of TNMB.
The site is located along the northern bund of River Paravanar within the tidal influence
Zone from Bay of Bengal in near to the confluence point of Paravanar with sea. The
location of seaside boundary of the notified limits of Cuddalore Port is having
coordinates 11°42’00’’ to 11°42’30’’N and 79°46’30’’ to. 79°47’00’’E
The location of the proposed additional berths and infrastructures on Google image is
presented in Fig.2.1.
The CRZ Map showing the HTL and LTL of the project location, as surveyed and
authenticated by Institute of Remote Sensing, Anna University is presented in Fig 2.2.
The modifications in the breakwaters, approach channel and turning circle are the
waterside infrastructures proposed along with capital dredging. In addition to the
existing godowns, additional storage systems pen and as well closed, are planned on the
land side.
The depth of the approach channel requires a draft of 9m. The under-keel clearance is
required to take care of the heave and pitch of the ship at low water due to wind and
wave action. The net under-keel clearance that is considered necessary is 0.64 m where
the sandy and grit clay and in large parts riverine by characteristics
The breaking wave height of 2.6m is considered for design of breakwaters. Since the
occurrence of breaking wave height would be very frequent, several times each
monsoon, Zero Damage criterion is specified for the breakwaters. In designing the cross-
section of the breakwater, consideration has been given to the availability of suitable
stone armour, from nearby quarries.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
N
FIG.2.1. LOCATION MAP - GOOGLE IMAGE (10 km RADIUS)
790 46’ 30”
110
42’ 3
0”N
110
42’0
0”N
790 46’ 30”
790 47’ 00”
790 47’ 00”
110
42’ 3
0”N
110
42’0
0”N
To Chidambaram40 km
To Vridhachalam40 km
To Pondicherry 20 km
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
FIG.2.2. CRZ MAP – CUDDALORE PORT: EXPANSION PROJECT
TAMILNADU MARITIMEBOARD
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
Considering the demand for bulk cargo handling in the project location, it will have Two
additional berths with 9 m CD draft to accommodate any new age yachts and pleasure
boats. AHOY will have a club house with facilities for holidaying activities. AHOY will make
Goa in the map of International Circuit of Pleasure Sailing Destinations which will
eventually increase the tourism into multifold in Goa.
The conceptual layout of the proposed capacity project of Cuddalore Port is presented in
Fig 2.3.
The layout was envisaged incorporating met ocean conditions and prevailing estuarine
and coastal features of the project location with respect to two monsoons. The
predominant wind, wave and swell conditions were interpreted to plan the berthing
areas with engineered structures like break waters to have sufficient tranquility at 0.30m.
The maneuvering and turning circle area and approach channel width were designed as
per the guidelines of PINAC/IAPH. The traffic volume was assessed to provide necessary
space to accommodate berth requirements.
Necessary Model studies were run on the project area with primary data like bathymetry
and project requirements for assessing dredging requirement for necessary draft. The
dredged material is envisaged to use to reclamation on the landside for cargo storage
area, along the coastline on the northern side of the North Breakwater and also offshore.
The Budgetary Estimate of the project is INR 115Crores.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
FIG.2.3. CONCEPTUAL LAYOUT – CUDDALORE PORT
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
2.2 CAPACITY EXPANSION PROJECT –CUDDALORE PORT
The existing minor Port at Cuddalore is an ancient and historic anchorage Port, with a
fishing harbor in the Uppanar. The location is an estuarine complex with Uppanar and
Paravanar confluence with sea. The coastline is comprised of sandy beaches and exposed
to open sea with backshore elevation about EL. (+) 2.0m CD along most of the coastline.
The Port is currently under the management of Tamilnadu Maritime Board (TNMB). The
port has been evaluated to have a good potential for further growth with a location
advantage of close to major industries, thermal power plants, coal mining and
Puducherry. A survey indicting the potential opportunity and requirement to handle
multipurpose cargo and is strategically located on the South east coast of India to support
Port development activities. The deep counter of 10m is available around 1000m from
the shoreline.
Currently the port has two Training walls of length 180m in the north and 230m in the
south. If the basic break water infrastructure facilities of the port are not extended, and if
the situation in the river mouth is permitted to continue like this for some more years,
most of the river mouth portion will get silted up. The extension of Breakwater both
North and South side are quite essential to sustain the water spread area for ship
movement in the Port. The existing wharf facilities are to be developed so as to facilitate
larger DWT vessels.
The proposed development plan for the modernization and capacity augmentation of this
port is envisaged by extending the existing breakwater to (-) 9.0m CD, carryout capital
dredging, construction of two berths each of dimension 120x 38.70m to facilitate direct
berthing of up to 10,000DWT vessels and by providing land side facilities like stackyard,
godowns, railway lines, internal roads, desalination plants, electrical substation.
The proposed project activities, primarily includes the following;
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
Two numbers of additional Berths/Wharfs
Modification in the Breakwaters
Capital Dredging towards approach channel (-9m) and Turning
Circle (-10m)
Infrastructures for Storage and Handling facilities for Cargo-
Landside development
Dredged material disposal & Management
The detailed scope and specifications of the proposed activities in the capacity expansion
project of Cuddalore Port is presented in Table 1.1.
2.3 NEED FOR THE PROJECT
The existing Port has become defunct for want of required depth of water spread as the
Port has lost the depth to silting in the last two years. Hence, dredging has become
important even to operate barges to negotiate the permitted cargo in the Port.
Nevertheless, Cuddalore district has been in the industrialization pathway in the last one
decade which has seen a coastal thermal power plan, multifold enhancement in the coal
mining capacity of nearby NLCIL( 40 Km, West) and nearby Pondicherry (20km, North)
with multi varied development.
There are atleast three more Coastal thermal power plants and one SEZ for Apparel Park
in pipeline which situation necessitates the presently proposed capacity expansion of
Cuddalore.
It is also general public demand to move into more maritime activities for state wide
water ways and making the cargo transportation through sea ports rather than the
preset practice of roadways. Hence only, Government of Tamilnadu is proposing the
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
proposed project through TNMB with the committed financial aid and support from
Government of India.
TABLE 1.1. SIZING AND SPECIFICATION- PROPOSED PROECT ACTIVITIES,CUDDALORE
PORT
Sl.No Summary of Main Port components
1 Turning Circle
Diameter 300m
Depth (-)10.0m
Approach channel length 1500m
Approach channel width 60m
Approach channel dredge depth (-) 9.0m
Channel slope 1V:5H
2 Berth – 2 Nos.
Length 120m
Width 38.70m
Depth at berthing pocket (-)10.0m
3 Capital dredging in cu.m 17,30,000
4 Breakwater using armor stones & tetra pod
Extension of North breakwater 210m
Extension of South Breakwater 410m
5 Infrastructures
Coal Open Yards 250 X 150 m
Cement Closed Shed
Fertilizer Closed Shed
Clean & Container Cargo- Open Yard
150 X 100 m
Two Yards
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
Perhaps, the construction of wharfs and cargo management may get tendered for
execution on the basis of BOOT with private investment for quicker project
implementation and effective operation and maintenance.
2.4 DEMAND – SUPPLY
Industries in SIPCOT Industrial Estate of Cuddalore, increased mining by NLCIL, newer
coastal thermal power plants, industries in Puducherry and new developments like an
Apparel Park in Perambalur (90Km) were are highly demanding and pressing conditions
for the proposed Port Expansion for enhanced Cargo handling of 5.86 MTPA.
The port is historic and in a coastal compatible environment which is an estuarine
complex of two rivers under tidal impact which confluence with sea. The location is
known for bulk cargo activities, especially for wooden logs and edibles.
TNMB is under compelling situation to put its coastal reserves and resources optimally.
The proposed project will ease out the increasing road traffic in the GST and ECR as it will
serve 5.86 MTPA of multi Cargo through sea which otherwise will have to be on road
making risk of accidents and pollution.
IMPORTS VS INDIGENOUS PRODUCTION
The project will enhance the imports mainly for fertilizers as bulk cargo, coal as bulk cargo
and containers as clean cargo.
2.5 EXPORT POSSIBILITY
The propose Port Expansion will enable to increased export activities for Cement as bulk
cargo and finished goods and machines as Container Cargo.
2.6 DOMESTIC / EXPORT MARKETS
The present expansion will enable to plan for increasing water way transport in this
country and also within Tamilnadu to connect 13 districts directly as Tamilnadu has
almost 1100 Km of coastline in 13 maritime states out of 32 revenue districts.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
The proposed facilities and achievable compatibility will not only pave way for water ways
for passenger travel it also will extend to enhance tourism in the long run.
2.7 EMPLOYMENT GENERATION
The proposed Port Expansion will give job opportunity to 1500 personnel directly in the
operation and management of Port and in Cargo handling.
Indirectly, this will boost the industrial activities around and commercial and domestic
development as downstream impacts will result in producing jjob and new life yearning
activities for more than 10,000 indirectly and off site in the hinterland of Cuddalore,
Nagapatinam, Villupuram and Perambalur district of Tamilnadu and also Puducherry.
III. PROJECT DESCRIPTION
The propose activities are envisaged to enhance the capacity of cargo handling of the
existing Port facility. The establishment of the proposed berths for handling multi cargo of
5.68 MTPA will improve further industrial activities and will enable TNMB to optimal y use
the Cuddalore Port which currently suffers navigation due to insufficient water depth.
The location of the proposed Berth and other infrastructures within the Cuddalore Port is
presented in Fig.3.1.
The project is primarily to establish two berths, each of size 120m X 38.70m, for handling
multi Cargo mix with varied bulk cargo and container cargo for a total handling capacity of
5.68 MTPA.
The development plan will have the entrance channel with dredge depth of (-) 9.0 m to
handle higher capacity vessels of up to 10,000 DWT with maximum draft of 8.0m.
Turning circle of 300m diameter and dredge depth of (-) 10.0m and berth pocket of (-)
10.0m CD is also proposed.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
India
FIG.3.1. LOCATION OF PORT LIMIT
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
The North breakwater and south breakwater extension is proposed for an additional
length of 210m and 410m respectively. The construction material for the breakwater is
armor stones and tetra pods.
The Approach Channel and Turning Circle, primarily and other navigatable water spread
would require 17,80,000 Cu.m of dredging as capital. The dredged material will be
disposed in three prong destinations, strategically for land reclamation, erosion
prevention and offshore as assessed through coastal modeling studies.
An existing rail line is directly connecting the Port which is extended to entire network of
southern railways through Cuddalore OT Station, available at 5Km, North West. Proper
enhancement and augmentation measures shall be adopted before using the rails for
renewed port operations in the Post Project scenario.
Three open stack yards for bulk cargo, especially for coal and four godowns are proposed
to handle the mix of cargo. Two numbers of LHM 120 cranes for each berth is found to be
sufficient for handling cargoes and to be installed by port operators. The installation of
mobile harbor crane, development of stack yard for storage and development of road and
rail infrastructure for handling cargoes is to be developed in PPP mode.
Based on the tranquility study, the number of operable days for berth ONE is 356 and
berth TWO is 307 per annum.
The advection-dispersion study indicates that 4000 dilution take place within 300-500m
around the point of release offshore (12-15m contour) and 5000 dilution takes place
within 200-300m around the point of release near the shore north of north breakwater.
3.1 PROJECT SIZE AND TYPE
The project is envisaged to construct TWO new berths as Wharfs in the Paravanar Estuary
within the Port limit for 120 X 38.5 m, each which is purposefully equipped with required
infrastructures to handle Cargo to the tune of 5.68 MTPA.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
To facilitate the ship movement and manoeuvring, dredging for 17,80,000 cu.m has
become must as assessed by Modelling and bathymetry.
The Breakwaters, both North and South, are envisaged for revamping for additional
construction and for a change of alignment for 210m and 410 m respectively.
3.2 LOCATION OF THE PROJECT
The proposed project is a multi varied activities of constructing berths in Paravanar
estuary, additional constructions of breakwaters and infrastructures and dredging, within
the notified port limits, having coordinates 11°42’00’’ to 11°42’30’’N and 79°46’30’’ to.
79°47’00’’E
The location of the proposed activities in the existing Cuddalore port, based on Satellite
imagery (LISS-III), is presented in Fig.3.2.
The CRZ Map showing the HTL and LTL of the project location has been already surveyed
and authenticated by Institute of Remote Sensing, Anna University.
The location has been already studied in depth by IIT-M for establishing the proposed
facilities in the Port Area and it was concluded as a potential site and environmentally
compatible location within Cuddalore Port waters.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
N
FIG.3.2. LOCATION OF PROJECT – Satellite Imagery- LISS-III
790 46’ 30”
110
42’ 3
0”N
110
42’0
0”N
790 46’ 30”
790 47’ 00”
790 47’ 00”
110
42’ 3
0”N
110
42’0
0”N
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
3.3 ALTERATIVE SITES
IIT-M evaluated potential locations for establishing the proposed project activities as
there is a need for expansion for Cuddalore Port to optimally use the available water
spread area.
The study reportedly concluded with three potential sites within the Port limits, as shown
in the Fig 3.3 to 3.5.
There are three alternative locations for proposed berth is considered.
Option 1: In this option the berth is proposed in front of the existing wharf as shown in
Fig 3.3.To provide the proposed facilities at these location, capital dredging will take up a
portion of land from the nearby village i.e. Akkarai gori. With the facilities in this location,
movement of barges during operation shall hamper the movement of fishing vessels. The
structures and some land mass at the confluence point of two rivers need to be removed
along with land mass north of the confluence point to make access channel.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
FIG.3.3. OPTION 1 FOR BERTH LOCATION
Option 2: In this option, the berth location is considered along the embankment west of
River Paravanar as shown in Fig 3.4 which offers sufficient space for providing suitable
access channel, relatively lesser dredging volumes, offers better land accessibility and
better ease of vessel operations.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
FIG.3.4. OPTION 2 FOR BERTH LOCATION
Option 3: In this option the berth location is proposed along the eastern side
embankment of River Paravanar shown in Fig 3.5 which is similar to option 2. It has
similar advantages as option 2 but its disadvantage is poor access for the evacuation of
cargo which needs construction of bridge across the river. Sufficient storage area behind
the berth is not available.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
FIG.3.5. OPTION 3 FOR BERTH LOCATION
On the basis of these options and detailed ground truthing exercise, IIT-M recommended
the proposed location on the Northern side of the Paravanar for the proposed Berths and
subsequently devised other requirements like Breakwater, storage infrastructures and
dredging.
3.4 EXTENT OF THE LAND
The geo position of the project location on the seaside is as follows:
110 44’ 24”N
790 47’ 24”E
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
110 44’ 24”N
790 50’ 48”E
110 36’ 45”N
790 50’ 48”E
110 36’ 45”N
790 45’ 30”E
Cuddalore Port has around 60 Hectare on landside where the proposed infrastructures
for cargo handling are planned.
The extent of land availability for the present project within Port area is presented in
Fig.3.5.
3.5 PROJECT COMPONENTS
The proposed project is essentially to modernize the existing minor port of Cuddalore
with additional two berths (210 x 38.5 m) for handling multiple cargo of 5.68 MTPA. The
proposed project will also establish required depth for navigation by dredging for a depth
of 9-10m a first level assessment of capital dredging to the tune 0f 17,80,000 m3.
The proposed activities will also include certain changes in the position of breakwaters
with a navigatable approach channel and turning circle.
Also, open storage yards and closed sheds are proposed for handling and storing of Cargo
The buildings, roads and green belt development will be established on the landside
where around 56 Hectare is available and also 5 Hectare more area will be available as
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
reclaimed area, as dredged material is envisaged partly to reclaim area behind the
proposed berths.
3.6 MATERIAL BALANCE
There is no production or manufacturing involved in the proposed project. The Port is
essentially a service industry to facilitate Cargo movements – sea wards.
Water alone is sourced on site, treated and reused.
3.7 RESOURCE OPTIMIZATION
The water spread area and also the landward areas are the most important natural
resources, especially in the project location. Hence, optimal use of available areas in the
notified Port waters will be the principal data for planning and designing the proposed
new activities,
(A) WATER
The requirement of water is assessed for 100 KLD. Water will be sourced from sea by
intake system. A conceptual water balance is presented in Fig 2.7.
Water is also required for facility maintenance, canteen, fresh water to ships and green
belt within the Port area.
A standalone Water Treatment Plant will be installed to source this water requirement by
100 KLD by desalination using RO.
The secondary level requirement of water for facility maintenance is assessed for 75 KLD.
This will be sourced from the installed Wastewater Treatment Plant. Hence, the actual
daily virgin water requirement will be 25KLD only.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
Dual Plumbing Systems will be installed to use recycle water for toilet flushing and
general washing of areas and green belt development.
A conceptual Water Balance for the proposed project of TNMB is presented in Fig. 2.6
(B) POWER
Power is assessed for an additional requirement of 500 HP and it will be ensured from the
available Grid from TANGEDCO. Already an exclusive power line is available and it will be
enhanced for this additional requirement.
3.8 WASTE TREATMENT & DISPOSAL
Effluent
The waste water is assessed for a maximum of flow of 100 KLD as water is used for
domestic consumption and it should be 80 KLD only after deducting 20% through spillage
and evaporation. However, considering significant increase in the near future
requirements, ETP has been decided to install for processing 100 KLD of combined waste
streams.
An exclusive Effluent Treatment Plant (ETP) will be installed with Physico chemical and
membrane based plant to produce 75 KLD of reusable water.
The reclaimed water of 75 KLD will be put into Dual Plumbing System for flushing,
washing and green belt requirements.
Emission
As there is no combustion process involved in the proposed Expansion of Port activities.
Hence, there will not be any process emission.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
The DG sets will have its own in-built emission handling systems as TNMB will install only
CPCB approved DG set for the purpose of alternate power supply.
Solid Waste
Solid waste generated from Office administration, Workers canteen, etc., will be collected
as non-hazardous solid waste and transferred to the approved Municipal Solid Waste
Management facility of Cuddalore or nearby LB facility with exclusive MoU with the
respective government department. This non-hazardous SW is assessed for 1TPD.
The hazardous waste comprises of spent oil/grease/paint, spillages of cargo and other
waste from cargo handling activities is assessed for 5TPD and will be disposed, off site
TSDF, as per the guidelines of TNPCB and CPCB.
3.9 PROJECT FEASIBILITY
The Silting in the existing approach channels is posing serious navigational problems
which made the Port presently defunct. Hence, dredging has become must and important
to regularize the Port activities.
TNMB made strategic studies to optimally use its water spread in an environmentally
compatible way. The proposed Capacity Expansion is very important to make the project
feasible as the dredging requirement is very high and thus costlier. TNMB availed the
services of IIT-M to prepare the Feasibility Study of the project. The present proposal is
just as it was envisioned advised by IIT-M to make the project feasible.
The proposed additional activities of Port are mainly meant for handling coal, container
and agro product commodities. Further the proposed project for the development of
Cuddalore Port, Tamil Nadu, seeks to harness a major economic development
opportunity brought about due to huge projected growth of freight traffic at the sea port
and rail terminals in the upcoming years.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
The proposed Wharf of 240m x 38.70m in dimension will be utilized as given below:
Berth-I of 120m shall be utilized for handling coal,
Berth-II of 120m shall be utilized as multipurpose berth for handling
container, fertilizer, cement, agro products.
The net cargo handling capacity is envisaged for 5.68 MTPA.
The development plan will have the entrance channel with dredge depth of (-) 9.0 m to
handle higher capacity vessels of up to 10,000 DWT with maximum draft of 8.0m. Turning
circle of 300m diameter and dredge depth of (-) 10.0m and berth pocket of (-) 10.0m CD
is also proposed.
The North breakwater and south breakwater extension is proposed for an additional
length of 210m and 410m respectively. The construction material for the break water is
armor stones and tetra pods.
Storage is planned in three stack yards and four godowns to handle the mix of cargo. Two
numbers of LHM 120 cranes for each berth is found to be sufficient for handling cargoes
and to be installed by port operators.
The installation of mobile harbor crane, development of stack yard for storage and
development of road and rail infrastructure for handling cargoes is to be developed in
PPP mode.
Based on the tranquility study, the number of operable days at berth 1is 356 and berth 2
is 307. The advection-dispersion study indicates that 4000 dilution take place within 300-
500m around the point of release offshore (12-15m contour) and 5000 dilution takes
place within 200-300m around the point of release near the shore north of north
breakwater.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
The Budgetary Estimate is done for INR 115 Crore by IIT-M and the financial feasibility
was explained and documented by IIT-M.
IV. SITE ANALYSIS
4.1 CONNECTIVITY
The proposed site for the construction of two berths and is located in the existing
Cuddalore Minor Port. The Proposed site is in the Paravanar Estuarine Complex in the
Port area with Uppanar and Sea. The site is about 3 Km from Cuddalore.
The nearest Railway station and Air Port are as follows (aerial distance);
Nearest Railway Station: 1.5 Kms, Cuddalore OT
Nearest Air Port : 21 Km Puducherry
The connectivity of the sites with Roads is available readily with NH 47-A.
4.2 LAND SURVEY
The proposed land has been done spatial survey using satellite Imagery-Liss-III and the
landward and coastal area were presented.
Satellite Image in LISS III format of the project location as sourced from National Remote
Sensing Agency (NRSA) for the project location is presented in Fig.4.1. LISS III format
image will be processed for Contour and Topography using Image Processing Software,
ERDAS.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
FIG.4.1. LISS-III RAW IMAGE – PROJECT LOCATION
Project Site
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
Necessary coastal survey using satellite, Cadastral maps and detailed CRZ Survey was
already completed through Institute for Remote Sensing, Anna University, Chennai.
This spatial analysis of the project location will be interpreted with field level
environmental due diligence survey, during EIA study.
4.3 TOPOGRAPHY
The Topography of the project site will be evaluated using Map info with the Maps of
Survey of India. GIS based tools will be used during the EIA studies with ground truthing
observations.
4.4 LAND USE PATTERN
The project site is a notified Port area and was allocated for Cuddalore Port and the
proposed additional berths and break waters are much within its command area.
Historically, the project location is known for merchandize port activities and also for
fishing. There will not be any requirement for land use change.
The Geomorphology of the project location, using Image processing software, is
presented in Fig 4.2.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
FIG.4.2. GEOMORPHOLOGY – PROJECT LOCATION
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
The land Use pattern based on LISS-III image is presented in Fig 4.3.
4.5 EXISTING INFRASTRUCTURES
The proposed location is already declared as Port Area and delineated to Cuddalore Port
by Government of Tamilnadu as Minor Port.
The project is well connected to roads, railways and telex-communication systems.
4.6 SOIL CLASSIFICATION
The soil is investigated, on a preliminary site assessment study, as red clayey and along
the estuarine Rivers as clayey sand. Detailed investigations will be carried out during EIA
studies.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
FIG.4.3. LAND USE – PROJECT LOCATION
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
4.7. CLIMATE – METEOROLOGY
The project location is Tropical Wet as per the classification Map of SoI. The predominant
wind direction is NE during NE monsoon and SW during SW monsoon. The average Wind
speed is 9-11 m/sec.
The mean Relative Humidity is learnt to vary for 71-73 %.The average annual rainfall
reported in the project site is 1337 mm.
It falls in Seismic zone III as per the Seismic zone classification of India.
4.8 SOCIAL INFRASTRUCTURES
Significant account of fisherman settlements was observed during Reconnaissance survey
in the Uppanar banks. Tourism and related Hotel industry is not visible in the recent
years.
The Social Frame work in the Villages of project impact area will be taken for a detailed
study in the EIA survey.
V. PLANNING BRIEF
TNMB availed the services of the Department of Ocean Engineering, Indian Institute Of
Engineering-Madras for preparing the feasibility report of the project with engineering
design of the project components. The proposed capacity Expansion for enabling TNMB
to handle additional cargo of 5.68 MTPA of multiple cargo mix has been planned and
designed technically by IIT-M.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
5.1 CONCEPTUAL PLANNING
The proposed Project of additional berths with required dredging for enhanced cargo
handling is being envisaged with four major functional components viz., Two Berths,
Cargo Storage & Handling facilities, Dredging & Augmenting approach Channel and
Modifications in the existing break water structures.
The proposed development plan for the modernization and capacity augmentation of this
port is envisaged by extending the existing breakwater to (-) 9.0m CD, carryout capital
dredging, construction of two berths each of dimension 120x 38.70m to facilitate direct
berthing of up to 10,000DWT vessels and by providing land side facilities like stack yard,
godowns, railway lines, internal roads, desalination plants, electrical substation, etc.
Currently the port has two Training walls of length 180m in the north and 230m in the
south. If the basic break water infrastructure facilities of the port are not extended, and if
the situation in the river mouth is permitted to continue like this for some more years,
most of the river mouth portion will get silted up.
The port users will no longer prefer this port and the port activities may come to a
grinding halt affecting primarily the fishermen and the cargo operators. However, to cater
the global market in current scenario, the extension of Breakwater both North and South
side are quite essential. The existing wharf facilities are to be developed so as to facilitate
larger DWT vessels.
Based on the bathymetry, (-) 15.0 m contour is available at about 3.50km normal to the
shore line and part of the dredge material will be disposed at this contour. The dredging
requirement is assessed for 17,30,000 cu.m and the dredged material will be managed in
three modes viz., land reclamation, erosion prevention and offshore disposal.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
A detailed plan for the management of dredged material will be provided in the EIA
reporting on finalization on its engineering and environmental impacts.
The proposed berths will have dimension of 120 x38.70 m in two numbers on the
northern bund of the Paravanar River.
The design vessel for the proposed port is shown in table below.
Vessel Specifications
Description Vessel size in DWT.
Vessel capacity 6,000 – 10,000 DWT
Draft 6.5 – 8.0 m
Overall Length 100m- 150 m
Width 16 – 18 m
Berthing velocity(m/sec) 0.20
Berthing angle (Deg) 10o
The port has two arms of northern and southern breakwaters. The north and south
breakwaters will be extended up to (-) 7.0m and (-) 9.0m contour respectively keeping
clear distance of 210m between two heads of the breakwater for entrance in to harbor.
The top deck level is proposed as (+) 4.50m for the berths. The harbor basin consists of
entrance channel (-)9m, berthing area (-)10m, and turning circle(-)10m.
An entrance channel connects the port with the deep water of the Bay of Bengal.
Approach channel width is proposed to be 60m with side slope of 1:5 or as per slope
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
achieved during dredging. The dredged depth of (-) 9.0 m CD allows for arrival and
departure of vessels up to a draft of 8 m.
Turning circle diameter is proposed to be 300m diameter for the maneuvering of Tug
assisted vessel during berthing and de-berthing and its dredge/ bed level is to be
maintained at (-) 10.0m CD. The depth of the basin and the berth is such that the vessel is
able to leave the berth for all water levels above CD + 0.7 m and remain in the berth
pocket under all tidal conditions. The depth at the berth pocket is (-) 10.0 m CD.
The stopping distance is 1050m. The clear width of the harbor entrance is 190 m and
necessary arrangements for safe navigation and tranquility requirements are satisfied
.
The complete engineering, estimation, schedule and coastal studies were provided by IIT-
M. TNMB will get it further added value as the project proceeds for implementation.
5.2 POPULATION PROJECTION
The proposed capacity expansion will enable TNMB to support 1500 personnel directly
and 10000 persons indirectly.
A vast number of domestic and international Cargo will get handled to further enhance
the socio economic feasibility of the project as it progress.
Occupational Health & Safety will be monitored with a common monitoring Health
Surveillance System and it will be established with the involvement and support of
TNMB.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
Special incentive coverage for health and life like ESI, Insurance, etc., will be mandated
for all workers population and they will be rendered safe and risk-free in their work
environment.
5.3 LAND USE PLANNING
The project area of about 56.92 Ha on the land side with notified coastal line of water
spread area is within the demarcated and delineated boundary for Cuddalore Port .
The proposed project area is essentially within the existing Port which is in operation one
of the oldest Ports serving the Nation and with pre-Independence history.
The available water spread area and delineated use pattern for Cuddalore Port is the very
basis for the proposed Project expansion by TNMB.
5.4 INFRASTRUCTURE DEMAND
The Cuddalore Port is a Coastal infrastructure serving Cargo handling with Wharfs. TNMB
is proposing to enhance the infrastructures for additional berths, Cargo handling systems
and dredging.
The Capacity Expansion project of TNMB will have
Additional Berths
Cargo Handling & Storage Facilities
Roads/Service roads
Service Yards
Fuelling Yards
Electrical Grid
Telecommunication
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
Water source, storage & supply
Drainage & Sewage treatment plant
Green Belt Development
Rain Water Harvesting Structures
All facilities will be planned and designed to take accreditation with International
Standards for Port and TNMB is committed to accredit for IS 9000 and IS 14000 series of
Standards.
5.5 AMENITIES / FACILITIES
TNMB has the following common facilities for the sustainable operation of the Port
activities;
Water storage & supply
Roads
EB grid
Sewage treatment plant
Rain Water Harvesting Structures
Green Belt in the Peripheral areas and o the road side and Central
meridian
The following Organizational Set Ups will freshly be established by TNMB and
continuously run and monitor the Cuddalore Port:
Environmental Cell
Emergency Management Cell
Common Health Surveillance System
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
TNMB will also continue to commit to continue its coordination with Tamilnadu Pollution
Control Board, District Health Department and District Administration for issues
pertaining to overall Environmental Management and Sustainable Development of the
Project location.
6 INFRASTRUCTURES
6.1 INDUSTRIAL AREA
The entire land has been already allocated through a GO to Cuddalore Port.
A copy of the GO is presented as Annexure-I.
6.2 RESIDENTIAL AREA
There is no area for any exclusive residential area.
6.3 GRREEN BELT DEVELOPMENT
TNMB will provide greenery with suitable trees and plantation that are compatible to
coastal conditions along the sides of the inner plant roads and in all open spaces.
TNMB is committed to enhance the existing greenbelt suitably through exclusive plan of
action to ensure atleast 33% of the area will be covered under green belt development.
6.4 SOCIAL INFRASTRUCTURE
The social infrastructure in the project impact area will be evaluated in EIA studies and in
reporting.
6.5 CONNECTIVITY
The site is about 4 Km from Cuddalore, the district head quarters of the district.
Nearest Railway Station: 1.5 Kms, Cuddalore OT
Nearest Air Port : 21 Km Puducherry
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
The site has direct access with NH 47 –A (Cuddalore-Chidambaram Road). There is a
direct rail line from the Port to Cuddalore OT which is currently defunct as the Port is not
fully operational in the recent times. As the rail lines are available and intact, TNMB will
set it correct through Southern Railways and make it functional before the project
commissioning.
As the location is within the notified Port limits which is well connected historically, the
connectivity of the location with the rest of State is good.
6.6 WATER MANAGEMENT
A stand alone Water Treatment Plant will be installed in the Port area to source the
required water of 100 KLD by desalination using RO.
The secondary level requirement of water for the port is assessed for 75 KLD. This will be
met from treating Wastewater in the advanced effluent Treatment facility with
membrane based plant to reclaim water with quality standards confirming with BIS
10500.
Dual Plumbing Systems will be installed to use recycle water for toilet flushing and
general washing of areas and greenbelt development.
6.7 SEWERAGE SYSTEM
TNMB will lay storm water drainage as open concrete channels, all along the internal
roads for ensuring proper collection of storm water and the same be used for charging
the rain water harvesting structures.
TNMB will have exclusive sewers to collect sewage from the conveniences and rest
rooms. This will be mixed with all other liquid waste streams from washing and service
yard and will be taken to ETP.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
A dual-Plumbing system will be in place to reuse the treated effluent from UF system of
the proposed ETP for flushing, floor cleaning and greenbelt development.
A. EFFLUENT MANAGEMENT
The “Zero Waste Objectives” will be the basis to establish Effluent Treatment plant. The
liquid waste will be managed for no disposal condition and the solid waste be managed
off site in approved facilities.
Effluent Treatment Plant
The ETP will be planned and designed to have state of the art systems for processing 100
KLD of combined stream of wastewater from conveniences and washing area. There is no
process of manufacturing or production and hence no industrial effluent kind of waste
stream from the proposed project. However, the combined waste stream is referred as
Effluent for the purpose of conventional reference.
The Effluent Treatment Plant is envisaged as a Physico Chemical Treatment Plant with a
Two -stage, Pressure Filter Systems (Sand and Activated Carbon) and the filtered water
will be treated in an Ultra Filtration (UF) plant to reclaim water for reuse or recycle..
The combined effluent is assessed to have COD at 900-1500mg/l and BOD of 450- 650
mg/l only. The pH is 6.0 – 8.5. The effluent may have the oil and grease at 50-90 mg/l.
The effluent will be processed in a mechanical system of Oil and Grease trap, with three
compartment tank. The oil, on floatation, can be removed manually.
The oil removed effluent is envisaged for dosage with an alkali solution and
polyelectrolyte for neutralization and particle agglomeration. The chemically treated
effluent will then be processed through a mechanical system of Plate Settlers for the
removal of solids.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
The sludge (Settled solids) will be transferred to Sludge Drying Beds.
The clarified effluent will then be passed through a Twin filter plant having Pressure Sand
Filter and Activated Carbon Filter. The residual solids, color and refractory organics will
be removed in these pressure filter systems.
The filtered effluent will then be, passed through Micron Filter Package, has 50, 25, 10
and 5µ cartridges in series. The MF treated water will be pumped to PLC based Ultra
Filtration (UF) plant to ensure complete removal of solids, color, odor and pathogenic
micro organisms.
Thus, the proposed effluent treatment plant will perform as Zero Liquid Discharge Plant.
There will not be any disposal and the entire treated effluent, as reclaimed as water from
the UF package, will be recycled in the dual plumbing system of Cuddalore Port.
The Schematics of the proposed Effluent Treatment Plant are presented in Fig 3.5.
The water is thus reclaimed from the effluent and envisaged for reuse in washing,
flushing, cleaning and green belt activities.
B. SOLID WASTE
The Spent Oil, Paint and Grease are the hazardous solid waste expected to get generated
from this facility for a maximum of 1 TPD. Such hazardous Solid waste generated from the
residues and spillages of cargo will be collected and transferred to the approved TSDF at
Gummidipoondi, Chennai. An exclusive MoU will be signed to avail the services during
Consent for project operation from State PCB.
The disposal of ship waste, I any at any point of time, will be made responsible to
respective ship operators.
Domestic non-hazardous Solidwaste is assessed for 5TPD from the activities of general
area cleaning, food and office (including brief stay of floating population of
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
clients/visitors) will be collected and transferred to the approved Municipal Solid Waste
Management Facility of Cuddalore.
Cuddalore Port will not have any onsite solid waste management facility
6.9. POWER
The existing power supply from the state Grid will be enhanced suitably. The net power
which is envisaged as requirement for operating the proposed berths & Cargo handling is
estimated for 500 HP.
TNMB will develop corporate policy for non conventional energy systems through coastal
wind mills and Solar Panels in the first two financial years of its operation.
68 REHABILITATION AND RESETTLEMENT (R & R) PLAN
The proposed location does not require any evacuation, as it is much within the
command area of Cuddalore Port. The location is within the Notified Port Area.
No acquisition of any land is involved as the proposed landside infrastructures will be
established in the fully owned land mass of TBMB and partly over the reclaimed area by
dredged material. Hence, there is no requirement for any exclusive RR plan.
During EIA studies, a detailed Socio Economic survey in the project impact area will be
carried out.
69 PROJECT SCHEDULE & COST ESTIMATES
The time schedule of project execution including the dredging and getting the proposed
two berths commissioned is proposed for Thirty Six months (Three Years- scheduled for
commissioning, during March 2020).
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
The budgetary estimate of the project is assessed for INR.115 Crores. The detailed
estimate will be drawn before project execution incorporating cost for Environmental
systems and to comply with the conditions of Environmental Clearance, if any.
Capacity Expansion of Cuddalore Port
S.No Name of WorkTotal
(in Crores)
1 Construction of breakwater (Extension)
a) North Breakwater 210m extension25
b) South breakwater 410m extension
2 Berth
Berth - I (120m X 38.70m) 20.00
Berth - II (120m X 38.70m) 20.00
3 Dredging upto (-) 9.0 m CD
a) Dredging at approach channel (Capital) 50.00
Grand Total (in Crores) 115.00
70 ANALYSIS OF PROPOSAL
A conceptual SWAT analysis was made on the proposed project. A detailed SWAT
analysis will be made as part of EIA and SIA studies.
-
PPRREE--FFEEAASSIIBBIILLIITTYY RREEPPOORRTTCUDDALORE PORT
Expansion Project
TAMILNADU MARITIME BOARDGovernment of Tamilnadu
Centre for Environment, Health & SafetyAnnamalai University
A detailed Environmental Cost Benefit Analysis will be carried out during EIA studies and
documentation.
71 CORPORATE RESPONSIBILITY PLAN
TNMB intend to establish the proposed two berths as wharfs in Cuddalore Port within the
notified Port limits and will have an exclusive plan in place to ensure proper
environmental management with monitoring programs for the listed pollutant
concentrations in air, water, soil and noise, in the ambient environment of the assessed
project impact area of 10Km radius of the location.
TNMB will keep an exclusive monitoring on Coal storage yards for maintenance of
moisture to prevent any fugitive dust emission. Internal roads and transfer vehicles will
be used as Standard to prevent spillage of coal and area pollution and dust emission.
An exclusive monitoring system will be in place for marine environment as will be evolved
after EIA/EMP studies and reports. Special Programs and Implementation systems will be
stressed for Occupational Health and Safety.
A social support package plan will be evolved in consultation with local fisherman
community and local bodies to help improve the socio economic status of the people in
the project impact area.
A detailed, Comprehensive Plan of Social and Environmental Responsibility will be framed
during EIA studies and documentation.
TNMB intends to accredit Cuddalore Port in the International framework Standards of ISO
9000 for Quality Standards and ISO 14000 series for Environmental Management
Systems. TNMB is committed to enable Cuddalore Port to enhance its activities without
any compromise to compliance to any Environmental legal systems.
-