CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE A BOND OVERSIGHT COMMITTEE AGENDA July 20, 2011 Campus Tour: 2:00 p.m. 3:00 p.m. Meeting: 3:00 p.m. 5:00 p.m. Fireside Room-Contra Costa College I. CALL MEETING TO ORDER II. PRESENTATIONS FROM THE PUBLIC III. WELCOME AND INTRODUCTIONS COMMITTEE AND GUESTS A. Acknowledge new Committee members IV. ACTION ITEMS A. Review and approve April 20, 2011 minutes (Attachment) B. Select new Committee Chair C. Select sub-committee for annual report letter V. INFORMATION A. Measure A 2002 update (Attachment) B. Measure A 2006 update (Attachment) VI. REPORTS A. Chancellor (Helen Benjamin) B. Contra Costa College (President McKinley Williams) C. Diablo Valley College (Vice President Chris Leivas) D. Los Medanos College (Interim President Richard Livingston) E. Chief Facilities Planner (Ray Pyle) a. Facilities Planning Staffing Report (Attachement) VII. COMMENTS FROM COMMITTEE MEMBERS A. Future agenda items VIII. COMMITTEE INFORMATION A. Committee membership list (Attachment) IX. ADJOURN

Upload: nguyenquynh

Post on 01-Apr-2018

218 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE A BOND OVERSIGHT COMMITTEE

AGENDA

July 20, 2011 Campus Tour: 2:00 p.m. – 3:00 p.m.

Meeting: 3:00 p.m. – 5:00 p.m. Fireside Room-Contra Costa College

I. CALL MEETING TO ORDER

II. PRESENTATIONS FROM THE PUBLIC III. WELCOME AND INTRODUCTIONS – COMMITTEE AND GUESTS

A. Acknowledge new Committee members

IV. ACTION ITEMS A. Review and approve April 20, 2011 minutes (Attachment) B. Select new Committee Chair C. Select sub-committee for annual report letter

V. INFORMATION

A. Measure A 2002 update (Attachment) B. Measure A 2006 update (Attachment)

VI. REPORTS

A. Chancellor (Helen Benjamin) B. Contra Costa College (President McKinley Williams) C. Diablo Valley College (Vice President Chris Leivas) D. Los Medanos College (Interim President Richard Livingston) E. Chief Facilities Planner (Ray Pyle)

a. Facilities Planning Staffing Report (Attachement)

VII. COMMENTS FROM COMMITTEE MEMBERS A. Future agenda items

VIII. COMMITTEE INFORMATION

A. Committee membership list (Attachment)

IX. ADJOURN

Page 2: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICT

Measure A 2002 and Measure A 2006

Bond Oversight Committee

Quarterly Report

July 20, 2011

Page 3: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

OVERVIEW

2002 Bond

July 20, 2011

Page 4: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

%Remaining Remaining

Campus Allocation Expenses Projection After Projection of Allocation

ProjectsContra Costa College* 44,555,993$ 34,071,048$ 44,375,506$ 180,487$ 0%Diablo Valley College 37,470,446$ 36,990,668$ 37,018,660$ 451,786$ 1%Los Medanos College 41,383,416$ 40,023,288$ 40,607,717$ 775,699$ 2%Total College Allocations 123,409,855$ 111,085,004$ 122,001,883$ 1,407,972$ 1%

District Building Projects 676,933$ 676,933$ 676,933$ -$

2002 Bond Program AllocationAs of May 30, 2011

Contra Costa Community College District

District Building Projects 676,933$ 676,933$ 676,933$ -$ Program Allocation 5,323,067$ 5,274,499$ 5,323,067$ -$

Total Program 129,409,855$ 117,036,436$ 128,001,883$ 1,407,972$ 1%

Approved Bond Revenue 120,000,000$

Interest** 9,409,855$

*Includes contingency and interest**Through February, 2011

C:\Documents and Settings\mkapell\My Documents\2011 Oversight\July 2011\2002 Bond projection & Expenses July 2011.xls

1

Page 5: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

Contra Costa CollegeProject Project # Completion Date Bond Cost

Vocational Technology Remodel C576 December 2006 5,788,062$

ADA Path of Travel C501 May 2007 955,607$

Perimeter Fencing C584 July 2008 214,316$

Library Building Remodel C580 July 2008 6,883,920$

ADA Improvements C520 August 2008 289,292$

Project Admin/CM C599 June 2010 561,900$

AA Roofing M/A C522 July 2010 332,903$

Remodel Student Activities C575 Deferred 1,072,165$

Art Building Seismic C578 Cancelled 332,865$

Total 16,431,029$

Diablo Valley CollegeProject Project # Completion Date Bond Cost

Life/Health Science Remodel D552 January 2006 3,225,167$

Life Science Remodel for Labs D275 August 2006 1,202,608$

Tech Education Swing Space D550 October 2006 513,106$

New Bookstore D551 October 2006 9,334,067$

Tech Education Seismic Upgrade D272 August 2007 158,205$

San Ramon Center D276 November 2007 9,506,168$

Remodel Student Activities D556 Cancelled 336,962$

Total 24,276,283$

Los Medanos CollegeProject Project # Completion Date Bond Cost

Planetarium L570 July 2004 1,005,795$

Remodel College Complex L566 January 2006 107,583$

Information Resource Center L274 February 2007 3,994,216$

Math Building L565 C April 2007 2,861,589$

Brentwood Expansion Phase 1 L567 April 2008 58,374$

Science Building L565 B March 2009 12,630,438$

Site Prep/New Quad Area L565 A April 2009 13,494,099$

Brentwood Expansion Phase 2 L567 March 2010 86,645$

Total 34,238,739$

Contra Costa Community College District

2002 Bond

Projects Completed

As of June, 2011

2

Page 6: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2002 BOND

JULY 2011

PROJECT

PROJECT BUDGET gVariance 0.0%

BudgetFundingStateBondOtherTotal Funding

PROJECT

PROJECT BUDGET gVariance 0.0%

BudgetFundingStateBondOtherTotal Funding

PROJECT

PROJECT BUDGET gVariance 0.0%

BudgetFundingStateBondOtherTotal Funding

PROJECT

PROJECT BUDGET gVariance 0.0%

BudgetFundingStateBondOtherTotal Funding 1,443,028$ 1,443,028$ -$ 1,396,459$

1,443,028$ 1,443,028$ -$ 1,396,459$

-$ -$ -$ -$

1,443,028$

-$ -$ -$ -$

-$ -$ -$ -$ 1,033,998$ 1,033,998$ -$ 1,033,998$

-$ -$ -$ -$

1,033,998$ 1,033,998$ -$ 1,033,998$

1,033,998$ 1,033,998$ -$ 1,033,998$

Revenue Bond Expenses Project # O-902-A

PROJECT DESCRIPTION: Bond issue expense

Budget Est At Completion Paid to Date

-$ -$ -$ -$ 923,721$ 923,721$ -$ 923,721$

-$ -$ -$ -$

923,721$ 923,721$ -$ 923,721$

923,721$ 923,721$ -$ 923,721$

Repair and Renovation

Budget Est At Completion Paid to Date

Project # O-501-519

676,933$ 676,933$ -$ 676,933$

PROJECT DESCRIPTION: Install minor capital improvements and update, repair and replace agedbuilding and site components for the District Office.

-$

-$

676,933$

-$ 676,933$

-$

-$

-$

O-901-A

676,933$

-$

676,933$

676,933$

-$

676,933$

Program Studies Project # O-905-A

PROJECT DESCRIPTION: Programwide studies and reports such as California EnvironmentalQuality Act (CEQA), Facility Assessment and Environmental Impact Report (EIR) reports.

General Services

PROJECT DESCRIPTION: Investment services - bank charges and escrow charges

Budget Est At Completion Paid to Date

Project #

Budget Est At Completion Paid to Date1,443,028$ -$ 1,396,459$

3

Page 7: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2002 BOND

JULY 2011

PROJECT

PROJECT BUDGET gVariance 0.0%

BudgetFundingStateBondOtherTotal Funding 1,922,320$ 1,922,320$ -$ 1,922,320$

1,922,320$ 1,922,320$ -$ 1,922,320$

-$ -$

-$ -$ -$ -$

PROJECT DESCRIPTION: Provide administrative support for the 2002 Bond. Budget will adjust withfunds available from Program Studies if needed.

Budget Est At Completion Paid to Date1,922,320$ 1,922,320$ -$ 1,922,320$

Project Administration Project # O-599-A

4

Page 8: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

DOPrevious Oversight Current Oversight Budget Reason for

Project Name Project # Funding Budget Budget Budget Changes Change

Repair and Renovation O-501-519 State -$ Bond 676,933.00$ 676,933.00$ -$ Other -$ -$ -$

General Services O-901-A State -$ Bond 923,721.00$ 923,721.00$ -$ Other -$ -$ -$

Revenue Bond Expenses O-902-A State -$ Bond 1,033,998.00$ 1,033,998.00$ -$ Other -$ -$ -$

Program Studies O-905-A State -$ Bond 1,443,028.00$ 1,443,028.00$ -$ Other -$ -$

Project Administration O-599-A State -$ -$ -$ Bond 1,922,320.00$ 1,922,320.00$ -$ Other -$ -$

NET CHANGE -$

QUARTERLY REPORT OVERVIEW2002 BUDGET ADJUSTMENTS

5

Page 9: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2002 BOND

JULY 2011

PROJECT - CCC

PROJECT SCHEDULE y Planned Completion: June 2008PROJECT BUDGET g

Budget Est. At Completion Variance 0.0% Paid to Date

Student Services Center Project # C-572-A

PROJECT DESCRIPTION: This project constructed a new student services center building ofapproximately 18,000 gross square feet.

Budget Est. At Completion Variance 0.0% Paid to DateBudgetFundingStateBondOtherTotal Funding

8,997,000$ 8,997,000$ -$ 8,966,728$

-$ -$ -$ -$

-$ -$ -$ -$ 8,997,000$ 8,997,000$ -$ 8,966,728$

8,997,000$ 8,997,000$ -$ 8,966,728$ Total Funding 8,997,000$ 8,997,000$ -$ 8,966,728$ COMMENTS: The building opened for student use in June 2008. The mechanical engineer has designed additional floor vent and controls to address deficient HVAC issues within the building. Construction to repair HVAC was completed at the end of November. Core Controls was hired to provide final programming for the new HVAC system and training for the campus personnel. This project will be financially closed by October 2011.

PROJECT - CCC

This project will be financially closed by October 2011.

Remodel Applied Arts Bldg Project # C-577-A

PROJECT DESCRIPTION: Minor remodeling will be performed to reuse space vacated bydepartments that moved to the new computer technology center and remodeled library building. Theremodeled space will be occupied by the math and speech departments.

PROJECT SCHEDULE g Planned Completion: January 2011PROJECT BUDGET g

Budget Est. At Completion Variance 0% Paid to DateBudgetFundingStateBond

1,655,000$ 1,655,000$ -$ 1,164,248$

-$ -$ -$ -$ 655,000$ 655,000$ -$ 587,142$ Bond

OtherTotal Funding

1,000,000$ 1,000,000$ -$ 577,105$ 655,000$ 655,000$ -$ 587,142$

1,655,000$ 1,655,000$ -$ 1,164,248$ COMMENTS: Project is complete. All spaces remodeled for Speech and Math are occupied. Men's and Women's restrooms on both first and second floors have been completely renovated and are in service. Minor modification of isolated areas of the are in service. Minor modification of isolated areas of the mechanical system are completed.

6

Page 10: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2002 BOND

JULY 2011

PROJECT - CCC

PROJECT SCHEDULE g Planned Completion: June 2012PROJECT BUDGET g

Remodel Music Building Project # C-581-A

PROJECT DESCRIPTION: The existing music building will be renovated to address seismicstrengthening, general interior improvements and data systems upgrades.

PROJECT BUDGET gBudget Est. At Completion Variance 0% Paid to Date

BudgetFundingStateBondOtherTotal Funding

4,675,566$ 355,478$

18,658$ -$ 18,658$ -$ -$ -$ -$

4,675,566$ -$

4,675,566$ 4,675,566$ -$ 355,478$ 4,656,908$ 4,656,908$ -$ 336,820$

18,658$

Total FundingCOMMENTS: Favorable bids were received and a general contractor was selected. SW Allen will be the contractor for the construction work which will start in August 2011.

4,675,566$ 4,675,566$ -$ 355,478$

PROJECT - CCC Smart Classrooms Project # C-517-B

PROJECT DESCRIPTION: Provide "smart classroom" equipment consisting of overhead LCDprojectors for computer graphic and video projection, additional data ports and overhead roll up

PROJECT SCHEDULE g Planned Completion: September 2011PROJECT BUDGET g

Budget Est. At Completion Variance 0.0% Paid to DateBudgetFunding

projectors for computer graphic and video projection, additional data ports and overhead roll upprojector screens in up to 25 classrooms across the campus.

365,000$ 264,287$ 365,000$ -$ FundingStateBondOtherTotal Funding

COMMENTS: Phase I and II have been completed. Phase I converted 11 rooms into smart classrooms and was completed in August 2006. Phase II converted nine rooms into smart

365,000$ -$ 264,287$ -$ -$ -$ -$

365,000$ 365,000$ -$ 264,287$ -$ -$ -$ -$

365,000$

August 2006. Phase II converted nine rooms into smart classrooms and was completed in August 2007. Phase lll construction will take place during Summer 2011. Smart classrooms will be built in 13 rooms in various buildings on the campus.

7

Page 11: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2002 BOND

JULY 2011

PROJECT - CCC

PROJECT SCHEDULE g Planned Completion: On-going

Repair and Renovation Project #501,519,583, 585,587,588, 591, 610

PROJECT DESCRIPTION: Install minor capital improvements and update, repair and replace agedbuilding and site components. Includes baseball field sun screen, bio science HVAC, planetarium,paving rehabilitation and utility upgrade.

PROJECT SCHEDULE g Planned Completion: On-goingPROJECT BUDGET g

Budget Est. At Completion Variance 0.0% Paid to DateBudgetFundingStateBond

5,739,874$ 0$ 5,300,592$

5,634,396$ 5,634,397$ 0$ 5,213,207$ 87,385$ 87,385$ -$ 87,385$

5,739,874$

BondOtherTotal Funding

COMMENTS: BioScience project closed. The remainder of the budget will be used to complete the work on the three currently active projects: Dugout, 12KV and Paving Rehabilitation. The Dugout project will be financially closed by the end of August. We are currently working with DSA in obtaining DSA approval to close

5,634,396$ 5,634,397$ 0$ 5,213,207$

5,739,874$ 5,739,874$ 0$ 5,300,592$ 18,092$ 18,092$ -$ -$

PROJECT - CCC

are currently working with DSA in obtaining DSA approval to close the Paving Rehabilitation project. The construction related to the 12KV project will start in August 2011.

Athletic Field Resurfacing Project # C-605

PROJECT DESCRIPTION: This project consists of resurfacing of the track and football field, as well

PROJECT SCHEDULE g Planned Completion: December 2011PROJECT BUDGET g

Budget Est. At Completion Variance 0.0% Paid to DateBudget

PROJECT DESCRIPTION: This project consists of resurfacing of the track and football field, as wellas associated grading and concrete flatwork, track events, fencing, landscaping and placement ofelectrical and low voltage infrastructure for future work.

629,498$ 629,498$ -$ 629,498$ BudgetFundingStateBondOtherTotal Funding

629,498$ 629,498$ -$ 629,498$

-$ -$ -$ -$ 629,498$ 629,498$ -$ 629,498$

-$ -$ -$ -$ 629,498$ 629,498$ -$ 629,498$

COMMENTS: This project is funded by the 2006 bond with an COMMENTS: This project is funded by the 2006 bond with an additional $629,498 from the 2002 bond to supplement the project funding. Phase I construction occurred July 2008 through May 2009. Phase II design will upgrade visitor bleacher concession area as well as other areas per DSA requirement and is currently in schematic design phase. Construction is planned for Fall 2011.

8

Page 12: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2002 BOND

JULY 2011

PROJECT - CCC

PROJECT SCHEDULE g Planned Completion: September 2010

VA Building Renovation Project # C-585

PROJECT DESCRIPTION: This cosmetic rehabilitation will add metal panel siding to the west andsouth side of the building to match metal panel siding added on the east end as part of the computertechnology center remodel, will replace roll-up doors, will replace the roof, and will paint the north sideof the building, including window frames.

PROJECT SCHEDULE g Planned Completion: September 2010PROJECT BUDGET g

Budget Est. At Completion Variance 0.0% Paid to DateBudgetFundingStateBondOther

609,000$ 609,000$ -$ 578,776$

-$ -$ -$ -$ 609,000$ 609,000$ -$ 578,776$

-$ -$ -$ -$ OtherTotal Funding

-$ -$ -$ -$ 609,000$ 609,000$ -$ 578,776$

COMMENTS: Contract with Southland Construction is complete and was approved for closeout during the September Board meeting. Additional work is planned to modify roll-up doors. New work is currently being developed by Lionakis Architect.

PROJECT - CCC Card Acces Project # C-523

PROJECT DESCRIPTION: Provide card access security for various buildings on CCC campus.

PROJECT SCHEDULE g Planned Completion: December 2011PROJECT BUDGET g

Budget Est. At Completion Variance 0.0% Paid to DateBudgetFunding

PROJECT DESCRIPTION: Provide card access security for various buildings on CCC campus.

205,000$ 205,000$ 25,490$ FundingStateBondOtherTotal Funding

-$ -$ -$ -$ 205,000$ 205,000$ 25,490$

-$ -$ -$ 205,000$ 205,000$ 25,490$

COMMENTS: Scope is being added to the project to incorporate the Software House System as per newly approved District standard. Additional scope to hardwire the entire campus card standard. Additional scope to hardwire the entire campus card access system is under review.

9

Page 13: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2002 BOND

JULY 2011

PROJECT - CCC

PROJECT SCHEDULE g Planned Completion: December 2012PROJECT BUDGET g

College Center Design Project # C-617

PROJECT DESCRIPTION: Provide design for the new campus center, including classroom building,student activity buildings and site development. Construction will be funded with 2006 bond funds.

PROJECT BUDGET gBudget Est. At Completion Variance 0.0% Paid to Date

BudgetFundingStateBondOtherTotal Funding

4,756,544$ 4,756,544$ 1,758,443$

-$ -$ -$ 1,334,000$ 1,334,000$ 1,334,000$ 3,422,544$ 3,422,544$ -$ 424,443$

Total Funding 4,756,544$ 4,756,544$ 1,758,443$ COMMENTS: The DSA collaborative review process continued with a meeting held in October 2010. Project design to include campus IT component. The design budget was increased, because the scope of the project increased during design developement. The architect firm submitted construction documents to DSA for review.

PROJECT - CCC

documents to DSA for review.

Parking Lot 16 Repair Project # C-524

PROJECT SCHEDULE g Planned Completion: December 2011PROJECT BUDGET g

Budget Est. At Completion Variance 0.0% Paid to DateBudget

PROJECT DESCRIPTION: Review and provide engineering analysis and repair damaged parking lot16.

149,380$ 149,380$ 22,232$ BudgetFundingStateBondOtherTotal Funding

149,380$ 149,380$ 22,232$

-$ -$ -$ -$ 149,380$ 149,380$ 22,232$

-$ -$ 149,380$ 149,380$ 22,232$

COMMENTS: A geotechnical report is being reviewed by a civil COMMENTS: A geotechnical report is being reviewed by a civil engineer. Design documents are being prepared for bidding. Construction planned for Fall 2011.

10

Page 14: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2002 BOND

JULY 2011

PROJECT - CCC

PROJECT SCHEDULE g Planned Completion: December 2011

Gym Annex Elevator Project # C-608

PROJECT DESCRIPTION: This project will add an elevator to the gym annex so students withdisability can access the entire building.

PROJECT SCHEDULE g Planned Completion: December 2011PROJECT BUDGET g

Budget Est. At Completion Variance 0.0% Paid to DateBudgetFundingStateBondOther

-$ -$ -$ 250,000$ 250,000$ -$ -$

-$ -$ -$ -$

250,000$ 250,000$ -$

OtherTotal Funding 250,000$ 250,000$ -$

COMMENTS: A prefabricated, ADA approved elevator is being considered by the College to save time and money. The project is in design.

250,000$ 250,000$ -$ -$

PROJECT - CCC Project Admin/CM Project # C-599

PROJECT DESCRIPTION: Provide full-time on-site construction management services to coordinate

PROJECT BUDGET gBudget Est. At Completion Variance 0.0% Paid to Date

Budget

PROJECT DESCRIPTION: Provide full-time on-site construction management services to coordinateand oversee construction projects on the campus throught design, construction and occupancyphases.

561,900$ 561,900$ 561,900$ BudgetFundingStateBondOtherTotal Funding 561,900$ 561,900$ 561,900$

COMMENTS:

561,900$ 561,900$ 561,900$ -$ -$ -$ -$

-$ -$ -$ -$

561,900$ 561,900$ 561,900$

11

Page 15: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2002 BOND

JULY 2011

PROJECT - CCC

PROJECT BUDGET gBudget Est. At Completion Variance 0.0% Paid to Date

Campus Contingency Project # N/A

PROJECT DESCRIPTION: Funds from projects that have been completed and financially closed out.

Budget Est. At Completion Variance 0.0% Paid to DateBudgetFundingStateBondOtherTotal Funding 180,488$ 180,488$ -$

COMMENTS:

118,178$ 118,178$ -$ 62,310$ 62,310$ -$ -$

-$ -$ -$ -$

180,488$ 180,488$ -$

COMMENTS:

12

Page 16: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

2002 Bond Financial Summary May 30, 2011

Budget Estimated at Completion Expenses

Active Projects

Student Services Center 8,997,000.00$ 8,997,000.00$ 8,966,728.21$

Remodel Applied Arts Bldg 1,655,000.00$ 1,655,000.00$ 1,164,247.51$

Remodel Music Building 4,675,566.00$ 4,675,566.00$ 355,477.99$

Smart Classrooms 365,000.00$ 365,000.00$ 264,286.85$

Repair and Renovation 5,652,488.00$ 5,652,488.87$ 5,213,206.84$

Athletic Field Resurfacing 629,498.00$ 629,498.00$ 629,498.00$

VA Building Renovation 609,000.00$ 609,000.00$ 578,776.47$

Card Acces 205,000.00$ 205,000.00$ 25,490.34$

College Center Design 4,756,544.00$ 4,756,544.00$ 1,758,442.58$

Parking Lot 16 Repair 149,380.00$ 149,380.00$ 22,231.66$

Project Admin/CM 561,900.00$ 561,900.00$ 561,900.00$

Campus Contingency 180,487.62$ 180,487.62$ -$

Gym Annex Elevator 250,000.00$ 250,000.00$ -$

Total Active Projects 28,686,863.62$ 28,686,864.49$ 19,540,286.45$

Closed Projects

ADA Path of Travel 955,607$ 955,607.00$ 955,607.00$

ADA Improvements 289,292$ 289,292.00$ 289,292.00$

Remodel Student Activities 1,072,165$ 1,072,165.00$ 1,072,165.00$

Vocational Technology Remodel 5,788,062$ 5,788,062.00$ 5,788,062.00$

Art Building Seismic 332,865$ 332,865.00$ 332,865.00$

Library Building Remodel 6,883,920$ 6,883,919.60$ 6,883,919.60$

AA Roofing M/A 332,903$ 332,903.00$ 332,903.00$

Perimeter Fencing 214,316$ 214,316.00$ 214,316.00$

-$ -$

Total Closed Projects 15,869,129.60$ 15,869,129.60$ 15,869,129.60$

Total 44,555,993.22$ 44,375,506.47$ 35,409,416.05$

CCC 2002 Bond

* Financial close out in process. 13

Page 17: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CCCPrevious Oversight Current Oversight Budget Reason for

Project Name Project # Funding Budget Budget Budget Changes Change

Student Services Center C-572-A State -$ -$ Bond 8,997,000.00$ 8,997,000.00$ -$ Other -$ -$

Remodel Applied Arts Bldg C-577-A State -$ -$ Bond 655,000.00$ 655,000.00$ -$ Other 1,000,000.00$ 1,000,000.00$ -$

Remodel Music Building C-581-A State -$ -$ Bond 18,658.00$ 18,658.00$ -$ Other 4,656,908.00$ 4,656,908.00$ -$

Smart Classrooms C-517-B State -$ -$ Bond 365,000.00$ 365,000.00$ -$ Other -$ -$

Repair and Renovation 501,519,583, 585,587,588, 591, 610State 87,385.00$ 87,385.00$ -$ Bond 5,634,396.00$ 5,634,396.00$ -$ Other 18,092.00$ 18,092.00$

Athletic Field Resurfacing C-605 State -$ -$ Bond 629,498.00$ 629,498.00$ -$ Other -$ -$

VA Building Renovation C-585 State -$ -$ Bond 609,000.00$ 609,000.00$ -$ Other -$ -$

Card Acces C-523 State -$ -$ Bond 205,000.00$ 205,000.00$ -$ Other -$ -$

College Center Design C-617 State -$ -$ Bond 1,334,000.00$ 1,334,000.00$ -$ Other 3,422,544.00$ 3,422,544.00$ -$

Parking Lot 16 Repair C-524 State -$ -$ Bond 149,380.00$ 149,380.00$ -$ Other -$ -$

Gym Annex Elevator C-608 State -$ -$ Bond -$ -$ Other 250,000.00$ 250,000.00$ -$

Project Admin/CM C-599 State -$ -$ Bond 561,900.00$ 561,900.00$ -$ Other -$

Campus Contingency N/A State -$ -$ Bond 118,178.00$ 118,178.00$ -$ Other 62,309.62$ 62,309.62$ (0.00)$

NET CHANGE (0.00)$

QUARTERLY REPORT OVERVIEW2002 BUDGET ADJUSTMENTS

14

Page 18: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2002 BOND

JULY 2011

PROJECT - DVC

PROJECT SCHEDULE g Planned Completion: January 2010PROJECT BUDGET g

PROJECT DESCRIPTION: This project totally renovated the planetarium to include a new starprojector, new seating and improved access for the disabled. The project also converted the lowermuseum space to classrooms.

Planetarium & Museum Project # D-570-A

PROJECT BUDGET gBudget Est. At Completion Variance 0% Paid to Date

BudgetFundingStateBondOtherTotal Funding 2,592,036$ 2,592,036$ -$ 2,580,999$

2,592,036$ 2,592,036$ -$ 2,580,999$

-$ -$ -$ -$

-$ -$ -$ -$

2,592,036$ 2,592,036$ -$ 2,580,999$

Total Funding 2,592,036$ 2,592,036$ -$ 2,580,999$

COMMENTS: All 3 phases of work, comprised of the original contract and 2 phases of remedial work, are complete. DSA is reviewing the final closeout paperwork for certification.

PROJECT - DVC Repair and Renovation Project # D-501-519

PROJECT DESCRIPTION: Install minor capital improvements and update, repair and replace agedbuilding and site components. Includes business foreign language building exterior waterproofing,

COMMENTS:

PROJECT SCHEDULE g Planned Completion: On-goingPROJECT BUDGET g

Budget Est. At Completion Variance 0.0% Paid to DateBudgetFunding

10,784,071$ -$ 10,779,821$

building and site components. Includes business foreign language building exterior waterproofing,LHS ceiling replacement, and parking island landscaping.

10,784,071$

FundingStateBondOther

Total Funding 10,784,071$ 10,784,071$ -$ 10,779,821$

-$ -$ -$ -$

9,690,158$ 9,690,158$ -$ 9,685,909$

COMMENTS: The LHS ceiling replacement project has been completed and only needs closeout with DSA. A proposal for

1,093,913$ 1,093,913$ -$ 1,093,913$

completed and only needs closeout with DSA. A proposal for professional design services for the BFL waterproofing project is still in the review stage due to a change in the scope of work. The parking island landscaping project is complete, and has been accepted by the Governing Board.

15

Page 19: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2002 BOND

JULY 2011

PROJECT - DVC

PROJECT SCHEDULE g Completion Date: January, 2011PROJECT BUDGET g

Gas Line Replacement Project # D-525

PROJECT DESCRIPTION: The 6" diameter main gas line to the campus has pin-hole leaks andneeds replacement.

PROJECT BUDGET gBudget Est. At Completion Variance 26.6% Paid to Date

BudgetFundingStateBondOtherTotal Funding

150,183$ 110,183$ 40,000$ 97,479$

-$

150,183$ 110,183$ 40,000$ 97,479$

-$ -$ -$ -$

Total Funding 150,183$ 110,183$ 40,000$ 97,479$

COMMENTS: This work took place between academic quarters in December and January. A new horizontal directionally-bored plastic line was installed along with a new earthquake valve. This equipment was tested and is fully operational now. This project is in the financial closeout phase.

PROJECT - DVC Project Admin/CM Project # D-559

PROJECT DESCRIPTION: Providing full-time on-site construction management services to

PROJECT BUDGET gBudget Est. At Completion Variance 0.0% Paid to Date

BudgetFunding

PROJECT DESCRIPTION: Providing full-time on-site construction management services tocoordinate and oversee construction projects on campus throughout design, construction andoccupancy phases.

350,000$ 350,000$ -$ 350,000$

FundingStateBondOtherTotal Funding 350,000$ 350,000$ -$ 350,000$

COMMENTS:

350,000$ 350,000$ -$ 350,000$

-$ -$ -$ -$

-$ -$ -$ -$

16

Page 20: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2002 BOND

JULY 2011

PROJECT - DVC

PROJECT BUDGET gBudget Est. At Completion Variance 0.0% Paid to Date

Budget

Campus Contingency Project # N/A

PROJECT DESCRIPTION: Funds from projects that have been completed and financially closed out.

411,786$ 411,786$ -$ -$ BudgetFundingStateBondOtherTotal Funding 411,786$ 411,786$ -$ -$

COMMENTS:

411,786$ 411,786$ -$ -$

-$ -$ -$ -$

-$ -$ -$ -$

411,786$ 411,786$ -$ -$

COMMENTS:

17

Page 21: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

2002 Bond Financial Summary May 30, 2011

Budget Estimated at Completion Expenses

Active Projects

Planetarium & Museum 2,592,036.00$ 2,592,036.00$ 2,580,999.35$

Repair and Renovation 9,690,158.00$ 9,690,158.00$ 9,685,908.56$

Gas Line Replacement 150,183.00$ 110,183.00$ 97,479.00$

Project Admin/CM 350,000.00$ 350,000.00$ 350,000.00$

Campus Contingency 411,786.00$ -$ -$

Total Active Projects 13,194,163.00$ 12,742,377.00$ 12,714,386.91$

Closed Projects

Tech Education Seismic Upgrade 158,205.00$ 158,205.00$ 158,204$

Life Science Remodel for Labs 1,202,607.91$ 1,202,607.91$ 1,202,608$

San Ramon Center 9,506,168.00$ 9,506,168.00$ 9,506,168$

Tech Education Swing Space 513,106.00$ 513,106.00$ 513,106$

New Bookstore 9,334,067.00$ 9,334,067.00$ 9,334,067$

Life/Health Science Remodel 3,225,167.00$ 3,225,167.00$ 3,225,167$

Remodel Student Activities 336,962.00$ 336,962.00$ 336,962$

Total Closed Projects 24,276,282.91$ 24,276,282.91$ 24,276,281.91$

Total 37,470,445.91$ 37,018,659.91$ 36,990,668.82$

DVC 2002 Bond

* Financial close out in process. 18

Page 22: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

DVCPrevious Oversight Current Oversight Budget Reason for

Project Name Project # Funding Budget Budget Budget Changes Change

Planetarium & Museum D-570-A State -$ -$ Bond 2,592,036.00$ 2,592,036.00$ -$ Other -$ -$

Repair and Renovation D-501-519 State 1,093,913.00$ 1,093,912.68$ (0)$ Bond 9,690,158.00$ 9,690,158.00$ -$ Other -$ -$

Gas Line Replacement D-525 State -$ -$ Bond 150,183.00$ 150,183.00$ -$ Other -$ -$ -$

Project Admin/CM D-559 State -$ -$ Bond 350,000.00$ 350,000.00$ -$ Other -$ -$

Campus Contingency N/A State -$ -$ -$ Bond 411,786.00$ 411,786.00$ -$ Other -$ -$

NET CHANGE (0)$

QUARTERLY REPORT OVERVIEW2002 BUDGET ADJUSTMENTS

19

Page 23: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2002 BOND

JULY 2011

PROJECT - LMC

PROJECT SCHEDULE g Planned Completion: September 2010PROJECT BUDGET g

Core Building Remodel Project # L-571-A

PROJECT DESCRIPTION: Remodel of approximately 7,087 assignable square foot, four-story "corebuilding" tower building (formerly known as the learning resource building within the college complex).

PROJECT BUDGET gBudget Est. At Completion Variance 1% Paid to Date

BudgetFundingStateBondOtherTotal Funding

3,795,646$ 3,813,000$

405,973$ 20,027$ 408,646$ 3,387,000$ 3,387,000$ -$ 3,387,000$

3,792,973$ 20,027$

-$ -$ -$ -$ 426,000$

Total FundingCOMMENTS: The project is 100% completed. The District has received DSA Letter of Certication. The Notice of Completion was filed in mid September. All closeout documents have been received by the District office. This project will be financially closed and moved to the Completed Projects list.

3,813,000$ 3,792,973$ 20,027$ 3,795,646$

PROJECT - LMC Art Area Remodel Project # L-573-A

PROJECT DESCRIPTION: Alterations of existing art labs and expansion into adjacent areas toinclude refinishing, repainting of interiors, mechanical, electrical, and fire alarm upgrades.

PROJECT SCHEDULE y Planned Completion: October 2010PROJECT BUDGET g

Budget Est. At Completion Variance 0.0% Paid to DateBudgetFundingState

include refinishing, repainting of interiors, mechanical, electrical, and fire alarm upgrades.

3,948,562$ 3,948,562$ -$ 3,376,461$

2,470,000$ 2,470,000$ -$ 2,470,000$ StateBondOtherTotal Funding

2,470,000$ 2,470,000$ -$ 2,470,000$ 1,478,562$ 1,478,562$ -$ 906,461$

3,948,562$ 3,948,562$ -$ 3,376,461$ -$ -$ -$ -$

COMMENTS: Project is 99% completed. Contractor is working on the last few Punchlist items. Contractor still has to deliver Closeout documents. documents.

20

Page 24: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2002 BOND

JULY 2011

PROJECT - LMC

PROJECT SCHEDULE g Planned Completion: On-going

PROJECT BUDGET g

Repair and Renovation Project #L-501-518, L-521

PROJECT DESCRIPTION: Install minor capital improvements and update, repair, and replace agedbuilding and site components. Includes baseball scoreboard.

PROJECT BUDGET g

Budget Est. At Completion Variance 0.0% Paid to DateBudgetFundingStateBondOther

4,369,443$ 4,369,443$ 0$ 4,369,443$ -$ -$ -$ -$

245,449$ 245,449$ -$ 245,449$

4,614,892$ 4,614,892$ 0$ 4,614,892$

OtherTotal Funding 4,614,892$ 4,614,892$ 0$ 4,614,892$

COMMENTS: There are no repair and renovation projects active at this time.

-$ -$ -$ -$

PROJECT - LMC Project Adm/CM Project # L-599

PROJECT DESCRIPTION: Providing full-time on-site construction management services to

PROJECT BUDGET gBudget Est. At Completion Variance 0.0% Paid to Date

BudgetFunding

PROJECT DESCRIPTION: Providing full-time on-site construction management services tocoordinate and oversee construction projects on campus throughout design, construction andoccupancy phases.

100,000$ 100,000$ -$ 100,000$ FundingStateBondOtherTotal Funding 100,000$ 100,000$ -$ 100,000$

COMMENTS:

100,000$ 100,000$ -$ 100,000$ -$ -$ -$ -$

-$ -$ -$ -$

21

Page 25: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2002 BOND

JULY 2011

PROJECT - LMC

PROJECT BUDGET gBudget Est. At Completion Variance 0.0% Paid to Date

Campus Contingency Project # N/A

PROJECT DESCRIPTION: Funds from projects that have been completed and financially closed out.

Budget Est. At Completion Variance 0.0% Paid to DateBudgetFundingStateBondOtherTotal Funding 755,672$ 755,672$ -$ -$

755,672$ 755,672$ -$ -$ -$ -$ -$ -$

-$ -$ -$ -$

755,672$ 755,672$ -$ -$

Total Funding 755,672$ 755,672$ -$ -$ COMMENTS:

22

Page 26: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

2002 Bond Financial Summary May 30, 2011

Budget Estimated at Completion Expenses

Active Projects

Core Building Remodel 426,000.00$ 405,973.30$ 408,645.74$

Art Area Remodel 1,478,562.00$ 1,478,562.00$ 906,460.99$

Repair and Renovation 4,369,443.00$ 4,369,442.74$ 4,369,442.54$

Project Adm/CM 100,000.00$ 100,000.00$ 99,999.83$

Campus Contingency 755,671.73$ -$ -$

Total Active Projects 7,129,676.73$ 6,353,978.04$ 5,784,549.10$

Closed Projects

Information Resource Center 3,994,216.02$ 3,994,216.02$ 3,994,216$

Math Building 2,861,588.00$ 2,861,588.00$ 2,861,588$

Brentwood Center Phase 1 58,374.00$ 58,374.00$ 58,374$

Brentwood Center Phase 2 86,645.00$ 86,645.00$ 86,645$

Remodel College Complex 107,583.00$ 107,583.00$ 107,583$

Planetarium 1,005,795.00$ 1,005,795.00$ 1,005,795$

Science Building * 12,645,438.00$ 12,645,438.00$ 12,630,438$

Site Prep/New Quad Area * 13,494,099.44$ 13,494,099.00$ 13,494,099$

Total Closed Projects 34,253,738.46$ 34,253,738.02$ 34,238,738.02$

Total 41,383,415.19$ 40,607,716.06$ 40,023,287.12$

LMC 2002 Bond

* Financial close out in process. 23

Page 27: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

LMCPrevious Oversight Current Oversight Budget Reason for

Project Name Project # Funding Budget Budget Budget Changes Change

Core Building Remodel L-571-A State 3,387,000.00$ 3,387,000.00$ -$ Bond 426,000.00$ 426,000.00$ -$ Other -$ -$ -$

Art Area Remodel L-573-A State 2,470,000.00$ 2,470,000.00$ -$ Bond 1,478,562.00$ 1,478,562.00$ -$ Other -$ -$ -$

Repair and Renovation L-501-518, L-521 State 245,449.26$ 245,449.26$ -$ Bond 4,369,443.00$ 4,369,443.00$ -$ Other -$ -$ -$

Project Adm/CM L-599 State -$ -$ Bond 100,000.00$ 100,000.00$ -$ Other -$ -$

Campus Contingency N/A State -$ -$ -$ Bond 755,671.73$ 755,671.73$ -$ Other -$ -$

NET CHANGE -$

QUARTERLY REPORT OVERVIEW2002 BUDGET ADJUSTMENTS

24

Page 28: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

OVERVIEW

2006 Bond

July 20, 2011

Page 29: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

%Remaining Remaining

Campus Allocation Expenses Projection After Projection of Allocation

ProjectsContra Costa College 85,633,334$ 3,912,001$ 85,633,334$ -$ 0%Diablo Valley College 69,833,333$ 8,376,151$ 69,833,333$ -$ 0%Los Medanos College 69,333,333$ 7,834,701$ 69,333,333$ -$ 0%Total College Allocations 224,800,000$ 20,122,853$ 224,800,000$ -$ 0%

District-wide ProjectsEnergy Management 36,080,014$ 35,753,863$ 36,080,014$ -$ 0%IT Infrastructure Upgrades 13,700,000$ 344,761$ 13,700,000$ -$ 0%Program Allocation 26,919,986$ 5,031,775$ 26,919,986$ -$ 0%Total District-wide Projects 76,700,000$ 41,130,399$ 76,700,000$ -$ 0%

Program Allocation Total 301,500,000$ 61,253,252$ 301,500,000$ -$ 0%

Approved Bond Revenue 286,500,000$

Additional RevenueEstimated Actual to Date

*Rebates 8,651,000$ 7,605,851$ Interest 10,000,000$ 3,509,028$ Total Additional Revenue 18,651,000$ 11,114,879$

Total Program 305,151,000$

Unallocated Revenue (estimated) 3,651,000$

Contra Costa Community College District2006 Bond Program Allocation

As of May 30,2011

C:\Documents and Settings\mkapell\My Documents\2011 Oversight\July 2011\2006 Bond Projection & Expenses July 2011.xls

25

Page 30: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

Costra Costa CollegeProject Project # Completion Date Bond Cost

BioSci Remodel for Art N/A Cancelled -$

New Science Bldg Planning C-631 August 2010 91,211$

Total 91,211$

Diablo Valley CollegeProject Project # Completion Date Bond Cost

Athletic Fields D605 April 2009 2,766,668$

Walnut Creek Real Estate Valuation D625 4,900$

Parking Lot Repaving D621 June 2010 1,175,031$

Total 2,771,568$

Los Medanos CollegeProject Project # Completion Date Bond Cost

Athletic Fields L605 May 2009 2,950,744$

Total 2,950,744$

DistrictProject Project # Completion Date Bond Cost

Energy Management

P415,416,

417,607 January 2009 35,734,264$

Total 35,734,264$

Contra Costa Community College District

2006 Bond

Projects Completed

As June 30, 2011

26

Page 31: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2006 BOND

JULY 2011

PROJECT

PROJECT BUDGET Planned Completion: TBD

Budget Est. At Completion Variance 0% Paid to DateBudgetFundingStateBondOtherTotal Funding

PROJECT

PROJECT BUDGET Planned Completion: On-going

Budget Est. At Completion Variance 0% Paid to DateBudgetFundingStateBondOtherTotal Funding

COMMENTS: The District contracted with Western Telecommunications Consultants in April 2008 to assess the Districtwide technology infrastructure and working with our Technology Planning and Implementation team, developed a 7-year Strategic Infrastructure and Telecom - munications Plan. The plan called for an upgrade to our existing network to support our growing data needs and highlighted the need to replace the legacy telephone and voice mail system with a Voice over Internal Protocol system and unified messaging architecture. The District chose to conduct a prequalification process and developed a Request for Qualifications. Six pre-qualified vendors were selected. On June 1, 2010, the District released the Request for Proposal to these vendors and made a final selection in January 2011. DecoTech was and the District developed a design contract with them. DecoTech is currently conducting a detailed review of each site and will be providing their design document by October 2011. Upon receipt, review, and agreement of the design, the District expects to move forward.

-$ -$ -$ -$

IT Infrastructure Project # P-609PROJECT DESCRIPTION: Cost for IT infrastructure/telecommunications strategic planningand implementation.

13,700,000$ 13,700,000$ -$ 344,761$

13,700,000$ 13,700,000$ -$ 344,761$

12,500,000$ 12,500,000$ -$ 344,761$ 1,200,000$ 1,200,000$ -$ -$

Program Studies Project # P-901, P-902

PROJECT DESCRIPTION: Programwide studies and reports, Master Plans for each collegeand other studies that have a districtwide scope such as access control, utility mapping andother standards development initiatives.

3,000,000$ 3,000,000$ -$ 2,037,902$

3,000,000$ 3,000,000$ -$ 2,037,902$

-$ -$ -$ -$ 3,000,000$ 3,000,000$ -$ 2,037,902$

-$ -$ -$ -$

27

Page 32: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2006 BOND

JULY 2011

PROJECT

PROJECT BUDGET Planned Completion:

Budget Est. At Completion Variance 0% Paid to DateBudgetFundingStateBondOtherTotal Funding

PROJECT

PROJECT BUDGET Planned Completion: On-going

Budget Est. At Completion Variance 0% Paid to DateBudgetFundingStateBondOther

Total Funding

PROJECT

PROJECT BUDGET Planned Completion: On-going

Budget Est. At Completion Variance 0% Paid to DateBudgetFundingStateBondOther

Total Funding

343,750$ 343,750$ -$ 19,599$ COMMENTS:

-$ -$ -$ -$ 343,750$ 343,750$ -$ 19,599$

-$ -$ -$ -$

Monitoring Based Commissioning Project # P-632

PROJECT DESCRIPTION: This project will adjust the mechanical system controls on variousbuildings to be more energy efficient.

343,750$ 343,750$ -$ 19,599$

P-599-A

PROJECT DESCRIPTION: Provide administrative support for the 2006 Bond. Primary labor,program level, and consultant services.

Program and Project Management Project #

-$ -$ -$ -$

11,000,000$ 11,000,000$ -$ 2,876,050$

11,000,000$ 11,000,000$ -$ 2,876,050$

11,000,000$ 11,000,000$ -$ 2,876,050$ -$ -$ -$ -$

-$ -$ -$ -$

Other Related Charges Project # P-599-B

PROJECT DESCRIPTION: Expenses for office supplies, equipments, travel andconferences, software licenses and other special studies.

1,700,000$ 1,700,000$ -$ 97,666$

1,700,000$ 1,700,000$ -$ 97,666$

1,700,000$ 1,700,000$ -$ 97,666$ -$ -$ -$ -$

28

Page 33: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2006 BOND

JULY 2011

PROJECT

PROJECT BUDGET

Budget Est. At Completion Variance 0% Paid to DateBudgetFundingStateBondOtherTotal Funding

PROJECT

PROJECT BUDGET

Budget Est. At Completion Variance 0% Paid to DateBudgetFundingStateBondOther

Total Funding

PROJECT

PROJECT BUDGET

Budget Est. At Completion Variance 0% Paid to DateBudgetFundingStateBondOther

Total Funding

1,100,000$ 1,100,000$ -$ -$

-$ -$ -$ -$ 1,100,000$ 1,100,000$ -$ -$

-$ -$ -$ -$

Financing Fees Project # P-925

PROJECT DESCRIPTION: Cost to issue bonds including bond counsel, financial adviser and paying agents.

1,100,000$ 1,100,000$ -$ -$

Contingency Project # P-999

PROJECT DESCRIPTION: Program wide contingency funds held in reserve for unforeseen cost increases.

9,300,000$ 9,300,000$ -$ -$

-$ -$ -$ -$ -$ -$ -$ -$

9,300,000$ 9,300,000$ -$ -$

9,300,000$ 9,300,000$ -$ -$

Energy Conservation Study Project # P-903

PROJECT DESCRIPTION: Professional Services for evaluating energy conservation measures Districtwide and help determine the feasibility and scope of individual projects, construction estimates, return on investment, submit rebate and loan application forms, help write bid specifications, and provide construction administration and commissioning as needed. Consultant contracts will be awarded in phases.

217,971$ 217,971$ -$ 20,157$

217,971$ 217,971$ -$ 20,157$

-$ -$ -$ -$ 217,971$ 217,971$ -$ 20,157$

-$ -$ -$ -$

29

Page 34: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2006 BOND

JULY 2011

PROJECT

PROJECT BUDGET

Budget Est. At Completion Variance 0% Paid to DateBudgetFundingStateBondOtherTotal Funding

Districtwide Future Projects Project # N/A

PROJECT DESCRIPTION: Excess funds that become available when district projects come in under budget.

602,015$ 602,015$ -$ -$

-$ -$ -$ -$ 602,015$ 602,015$ -$ -$

-$ -$ -$ -$ 602,015$ 602,015$ -$ -$

30

Page 35: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

DOPrevious Oversight Current Oversight Budget Reason for

Project Name Project # Funding Budget Budget Budget Changes Change

IT Infrastructure P-609 State -$ -$ -$ Bond 9,700,000.00$ 12,500,000.00$ 2,800,000.00$ Transfer within the project to change the funding Other 4,000,000.00$ 1,200,000.00$ (2,800,000.00)$ source from interest funds into bond funds

Monitoring Based Commissioning P-632 State -$ -$ -$ Bond 343,750.00$ 343,750.00$ -$ Other -$ -$ -$

Program Studies P-901, P-902 State -$ -$ -$ Bond 3,000,000.00$ 3,000,000.00$ -$ Other -$ -$ -$

Program and Project Management P-599-A State -$ -$ -$ Bond 11,000,000.00$ 11,000,000.00$ -$ Other -$ -$ -$

Financing Fees P-925 State -$ -$ -$ Bond 1,100,000.00$ 1,100,000.00$ -$ Other -$ -$ -$

Other Related Charges P-599-B State -$ -$ -$ Bond 1,700,000.00$ 1,700,000.00$ -$ Other -$ -$ -$

Contingency P-999 State -$ -$ -$ Bond 2,800,000.00$ -$ (2,800,000.00)$ Transfer within the project to change the funding Other 6,500,000.00$ 9,300,000.00$ 2,800,000.00$ source from bond and interest to just interest

Energy Conservation Study P-903 State -$ -$ -$ Bond 217,971.00$ 217,971.00$ -$ Other -$ -$

Districtwide Future Projects N/A State -$ -$ -$ Bond 602,015.00$ 602,015.00$ -$ Other -$ -$

NET CHANGE -$

QUARTERLY REPORT OVERVIEWBUDGET ADJUSTMENTS 2006 BOND

31

Page 36: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2006 BOND

JULY 2011

PROJECT - CCC

PROJECT SCHEDULE Planned Completion: December 2011PROJECT BUDGET

Budget Est. At Completion Variance 0% Paid to DateBudgetFundingStateBondOtherTotal Funding

PROJECT - CCC

Athletic Field Project # C-605

PROJECT DESCRIPTION: Work consists of demolition and resurfacing of the track and footballfield, associated grading and concrete flatwork, track events, fencing and landscaping. Site workincludes placement of electrical and low voltage infrastructure for future work.

3,305,950$ 3,305,950$ -$ 2,912,444$

Physical Education Annex Renovation Project # C-608

PROJECT DESCRIPTION: The building will be remodeled to provide a modern circuit traininglaboratory/exercise facility, aerobics, and other physical fitness and wellness instructional spaces.Improvements include utility infrastructure, ADA code improvements and restroom renovations.

-$ -$ -$ -$

-$ -$ -$ -$

3,305,950$ 3,305,950$ -$ 2,912,444$ COMMENTS: This project is funded by the 2006 bond with an additional $629,498 from the 2002 bond to supplement the project funding. Phase I construction occurred July 2008 through May 2009. Phase II will reconstruct entry drive for fire and ADA access compliance, add an entry archway and a football scoreboard. Phase II design is currently in schematic design phase. Construction is planned for Fall 2011.

3,305,950$ 3,305,950$ -$ 2,912,444$

PROJECT SCHEDULE Planned Completion: 2015PROJECT BUDGET

Budget Est. At Completion Variance 0% Paid to DateBudgetFundingStateBondOtherTotal Funding

COMMENTS: This project was previously approved for funding by the California Community College System Office Facilities Planning Unit. However, due to lack of a state bond on the November 2010 election ballot to fund this project, the project was resubmitted for consideration in the 2012/2013 funding year.

-$ -$ -$ -$ 9,235,000$ 9,235,000$ -$ 45,118$

3,792,000$ 3,792,000$ -$ -$ 5,443,000$ 5,443,000$ -$ 45,118$

9,235,000$ 9,235,000$ -$ 45,118$

Improvements include utility infrastructure, ADA code improvements and restroom renovations.

32

Page 37: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2006 BOND

JULY 2011

PROJECT - CCC

PROJECT SCHEDULE Planned Completion: December 2014PROJECT BUDGET

Budget Est. At Completion Variance 0% Paid to DateBudgetFundingStateBondOtherTotal Funding

PROJECT - CCC

-$ -$ -$ -$

College Center Design Project # C-617

PROJECT DESCRIPTION: A new college complex consisting of the new student activities building,the new classroom building and the quad area.

67,618,950$ 67,618,950$ -$ 507,411$

67,618,950$ 67,618,950$ -$ 507,411$ COMMENTS: The DSA collaborative review process continued with a meeting held in October 2010. Project design to include campus IT component. The District is currently reviewing 50% construction documents design phase submittal received in March. The design budget was increased, because the scope of the project increased during design developement.

67,618,950$ 67,618,950$ -$ 507,411$ -$ -$ -$ -$

ADA Improvement Projects Project # N/A

PROJECT DESCRIPTION: Bond funding has been allocated for various projects to remove barriersto access that were identified in an American with Disability Act study and transition plan.

PROJECT SCHEDULE Planned Completion: PROJECT BUDGET

Budget Est. At Completion Variance 0% Paid to DateBudgetFundingStateBondOtherTotal Funding

528,551$ 528,551$ -$ -$

-$ -$ -$ -$ 528,551$ 528,551$ -$ -$

-$ -$ -$ -$ 528,551$ 528,551$ -$ -$

COMMENTS: Projects will be identified by campus leadership.

33

Page 38: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2006 BOND

JULY 2011

PROJECT - CCC

PROJECT SCHEDULE Planned Completion: TBDPROJECT BUDGET

Budget Est. At Completion Variance 0% Paid to DateBudgetFundingStateBondOtherTotal Funding

PROJECT - CCC Seismic Retrofit - Various Buildings Project # N/A

PROJECT DESCRIPTION: This project will seismically retrofit several buildings on campus. Thereare no modernization or upgrades associated with this work.

Infrastructure Improvements Project # N/A

PROJECT DESCRIPTION: Bond funding has been allocated for various projects to upgrade aginginfrastructure such as utilities and parking lots.

1,350,938$ 1,350,938$ -$ -$

1,350,938$ 1,350,938$ -$ -$ COMMENTS: Projects under this allocation may be developed after the new college center project design is complete.

-$ -$ -$ -$ 1,350,938$ 1,350,938$ -$ -$

-$ -$ -$ -$

PROJECT SCHEDULE Planned Completion: TBDPROJECT BUDGET

Budget Est. At Completion Variance 0% Paid to DateBudgetFundingStateBondOther

Total Funding 2,300,000$ 2,300,000$ -$ -$ COMMENTS: This project is in pre-planning. An architect and structural engineering team need to be selected.

-$ -$ -$ -$ 300,000$ 300,000$ -$ -$

2,000,000$ 2,000,000$ -$ -$

2,300,000$ 2,300,000$ -$ -$

34

Page 39: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 40: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2006 BOND

JULY 2011

PROJECT - CCC

PROJECT BUDGETBudget Est. At Completion Variance 0% Paid to Date

BudgetFundingStateBondOtherTotal Funding 954,734$ 954,734$ -$ -$

COMMENTS:

-$ -$ -$ -$ 954,734$ 954,734$ -$ -$

-$ -$ -$ -$

Future Projects Project # C-999

PROJECT DESCRIPTION: Funding for projects in early preliminary planning which have had no expenses yet.

954,734$ 954,734$ -$ -$

36

Page 41: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

2006 Bond Financial Summary

May 30, 2011

Budget Estimated at Completion Expenses

Active Projects

Athletic Field 3,305,950.00$ 3,305,950.00$ 2,912,444.00$

Physical Education Annex Renovation 5,443,000.00$ 5,443,000.00$ 45,118.00$

College Center 67,618,950.00$ 67,618,950.00$ 507,410.68$

ADA Improvement Projects 528,551.00$ 528,551.00$ -$

Infrastructure Improvements 1,350,938.00$ 1,350,938.00$ -$

AA Renovation 2015 2,340,000.00$ 2,340,000.00$ -$

Seismic Retrofit - Various Buildings 2,300,000.00$ 2,300,000.00$ -$

Campus Project Admin/CM 1,700,000.00$ 1,700,000.00$ 355,817.26$

Future Projects 954,734.00$ 954,734.00$ -$

Active & Future Projects 85,542,123.00$ 85,542,123.00$ 3,820,789.94$

Closed Projects

New Science Bldg Planning 91,211.00$ 91,211.00$ 91,211.00$

Total Closed Projects 91,211.00$ 91,211.00$ 91,211.00$

Total 85,633,334.00$ 85,633,334.00$ 3,912,000.94$

CCC 2006 Bond

* Financial close out in process.

37

Page 42: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CCCPrevious Oversight Current Oversight Budget Reason for

Project Name Project # Funding Budget Budget Budget Changes Change

Athletic Field C-605 State -$ -$ -$ Bond 3,305,950.00$ 3,305,950.00$ -$ Other -$ -$ -$

Physical Education Annex Renovation C-608 State 3,792,000.00$ 3,792,000.00$ -$ Bond 5,443,000.00$ 5,443,000.00$ -$ Other -$ -$ -$

College Center Design C-617 State -$ -$ -$ Bond 67,618,950.00$ 67,618,950.00$ -$ Other -$ -$ -$

ADA Improvement Projects N/A State -$ -$ -$ Bond 528,551.00$ 528,551.00$ -$ Other -$ -$ -$

Infrastructure Improvements N/A State -$ -$ -$ Bond 1,350,938.00$ 1,350,938.00$ -$ Other -$ -$ -$

Campus Project Admin/CM C-599 State -$ -$ -$ Bond 1,700,000.00$ 1,700,000.00$ -$ Other -$ -$

Future Projects C-999 State -$ -$ -$ Bond 954,734.00$ 954,734.00$ -$ Other -$ -$

Seismic Retrofit - Various Buildings N/A State -$ -$ -$ Bond 300,000.00$ 300,000.00$ -$ Other 2,000,000.00$ 2,000,000.00$ -$

AA Renovation 2015 N/A State -$ -$ -$ Bond 2,340,000.00$ 2,340,000.00$ -$ Other -$ -$

NET CHANGE -$

QUARTERLY REPORT OVERVIEWBUDGET ADJUSTMENTS 2006 BOND

38

Page 43: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2006 BOND

JULY 2011

PROJECT - DVC

PROJECT SCHEDULE Planned Completion: November 2014PROJECT BUDGET

Budget Est At Completion Variance 0% Paid to DateBudgetFundingStateBondOtherTotal Funding

PROJECT - DVC Soccer Field Renovation Project # D-627

PROJECT DESCRIPTION: Scope of work will include regrading of the soccer field area, drainageimprovements, reseeding, and new fencing.

Commons Area Development Project # D-611

PROJECT DESCRIPTION: New buildings and site improvements for culinary arts program, foodservices, all student services functions and a new central commons area.

-$ -$ -$ -$ 52,020,030$ 52,020,030$ -$ 3,582,033$

52,020,030$ 52,020,030$ -$ 3,582,033$

COMMENTS: The Bid Phase is complete. The Board approved a recommendation to award a contract to the low bidder, Flintco Pacific, Inc., and exectution of that agreement is in process. The Project will now enter the construction phase.

-$ -$ -$ -$ 52,020,030$ 52,020,030$ -$ 3,582,033$

PROJECT SCHEDULE Planned Completion: October 2010 PROJECT BUDGET

Budget Est At Completion Variance 0% Paid to DateBudgetFundingStateBondOtherTotal Funding 530,800$ 530,800$ -$ 455,301$

COMMENTS: Notice of Completion was recorded on June 1, 2011. Project is in financial closeout and we are awaiting the Division of State Architect office to approve a change order and final verified reports. New field is open now for use.

-$ -$ -$ -$ 530,800$ 530,800$ -$ 455,301$

-$ -$ -$ -$

530,800$ 530,800$ -$ 455,301$

39

Page 44: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2006 BOND

JULY 2011

PROJECT - DVC

PROJECT SCHEDULE Planned Completion: TBDPROJECT BUDGET

Budget Est At Completion Variance 0% Paid to DateBudget StateBondOtherTotal Funding

PROJECT - DVC

Engineering Techonology Project # D-628

PROJECT DESCRIPTION: This project renovates the entire Engineering Technology building toupgrade technology space and to support new technology programs.

20,827,000$ 20,827,000$ -$ -$

10,646,000$ 10,646,000$ -$ -$ 9,500,000$ 9,500,000$ -$ -$

681,000$ 681,000$ -$ -$ 20,827,000$ 20,827,000$ -$ -$

COMMENTS: This project was previously approved for funding by the California Community College System Office Facilities Planning Unit. However, due to lack of a state bond on the November 2010 election ballot to fund this project, the project was resubmitted for consideration in the 2012/2013 funding year.

PE Building/Gym/Locker Renovation Project # N/A

PROJECT DESCRIPTION: Renovate physical education spaces.

PROJECT SCHEDULE Planned Completion: TBDPROJECT BUDGET

Budget Est At Completion Variance Paid to DateBudgetFundingStateBondOtherTotal Funding 608,159$ 608,159$ -$ -$

COMMENTS: Future project in very early planning stages. Scope will be dependent upon amount of funding used by other projects.

-$ -$ -$ -$ 608,159$ 608,159$ -$ -$

-$ -$ -$ -$

608,159$ 608,159$ -$ -$

40

Page 45: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2006 BOND

JULY 2011

PROJECT - DVC

PROJECT SCHEDULE Planned Completion: TBD

PROJECT BUDGET

Budget Est At Completion Variance Paid to DateBudgetFundingStateBondOtherTotal Funding

PROJECT - DVC ADA Improvement Projects Project # N/A

PROJECT DESCRIPTION: Bond funding has been allocated for various projects to remove barriersto access that were identified in an American with Disability Act study and transition plan.

Ball Field Restoration Project # N/A

PROJECT DESCRIPTION: Renovation and upgrade of softball and baseball field components suchas dugouts, bleachers, and backstops.

1,500,000$ 1,500,000$ -$ -$

1,500,000$ 1,500,000$ -$ -$ COMMENTS: Project is in early planning phase.

-$ -$ -$ -$ -$ -$ -$ -$

1,500,000$ 1,500,000$ -$ -$

PROJECT SCHEDULE Planned Completion: TBDPROJECT BUDGET

Budget Est At Completion Variance 0% Paid to Date

BudgetFundingStateBondOtherTotal Funding

-$ -$

527,744$ 527,744$ -$ -$ COMMENTS: Projects will be identified by campus leadership.

-$ -$ -$ -$ 527,744$ 527,744$ -$ -$

-$ -$ -$ -$

527,744$ 527,744$

41

Page 46: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICTQUARTERLY PROJECT REPORT 2006 BOND

JULY 2011

PROJECT - DVC

PROJECT BUDGETBudget Est At Completion Variance 0% Paid to Date

BudgetFundingStateBondOtherTotal Funding

PROJECT - DVC

PROJECT BUDGETBudget Est At Completion Variance Paid to Date

Future Projects Project # D-999

PROJECT DESCRIPTION: Funding for projects in early preliminary planning which have had no expenses yet.

1,200,000$ 1,200,000$ -$ 392,218$ COMMENTS:

-$ -$ -$ -$ 1,200,000$ 1,200,000$ -$ 392,218$

-$ -$ -$ -$

Campus Project Admin/CM Project # D-599

PROJECT DESCRIPTION: Providing full-time on-site construction management services tocoordinate and oversee construction projects on campus throughout design, construction andoccupancy phases.

1,200,000$ 1,200,000$ -$ 392,218$

Budget Est At Completion Variance Paid to DateBudgetFundingStateBondOtherTotal Funding -$ -$ -$ -$

COMMENTS:

-$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$ -$

-$ -$ -$ -$

42

Page 47: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

2006 Bond Financial Summary

May 30, 2011

Budget Estimated at Completion Expenses

Active Projects

Commons Area Development 52,020,030.00$ 52,020,030.00$ 3,582,033.36$

Soccer Field Renovation 530,800.00$ 530,800.00$ 455,300.89$

Engineering Technology 9,500,000.00$ 9,500,000.00$ -$

ADA Improvement Projects 527,744.00$ 527,744.00$ -$

PE Building/Gym/Locker Renovation 608,159.00$ 608,159.00$ -$

Ball Field Restoration 1,500,000.00$ 1,500,000.00$ -$

Campus Project Admin/CM 1,200,000.00$ 1,200,000.00$ 392,218.30$

Future Projects -$ -$ -$

Total Active Projects 65,886,733.00$ 65,886,733.00$ 4,429,552.55$

Closed Projects

Athletic Fields 2,766,669.00$ 2,766,669.00$ 2,766,667.73$

Parking Lot Repaving 1,175,031.00$ 1,175,031.00$ 1,175,031.00$

Walnut Creek Real Estate Valuation 4,900.00$ 4,900.00$ 4,900.00$

Total Closed Projects 3,946,600.00$ 3,946,600.00$ 3,946,598.73$

Total 69,833,333.00$ 69,833,333.00$ 8,376,151.28$

DVC 2006 Bond

* Financial close out in process.

43

Page 48: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

DVCPrevious Oversight Current Oversight Budget Reason for

Project Name Project # Funding Budget Budget Budget Changes Change

Commons Area Development D-611 State -$ -$ -$ Bond 52,020,030.00$ 52,020,030.00$ -$ Other -$ -$ -$

Soccer Field Renovation D-627 State -$ -$ -$ Bond 530,800.00$ 530,800.00$ -$ Other -$ -$ -$

Engineering Techonology D-628 State 10,646,000.00$ 10,646,000.00$ -$ This budget transfer was done to fund the Bus Loop Transit projectBond 9,490,000.00$ 9,500,000.00$ 10,000.00$ which now is being funded through parking funds and not bond. ThisOther 691,000.00$ 681,000.00$ (10,000.00)$ decision created a reverse of the budget transfer initially completed

PE Building/Gym/Locker Renovation N/A State -$ -$ -$ Bond 608,159.00$ 608,159.00$ -$ Other -$ -$ -$

Ball Field Restoration N/A State -$ -$ -$ Bond -$ -$ -$ New project funded with Interest fundsOther -$ 1,500,000.00$ 1,500,000.00$

ADA Improvement Projects N/A State -$ -$ -$ Bond 527,744.00$ 527,744.00$ -$ Other -$ -$ -$

Campus Project Admin/CM D-599 State -$ -$ -$ Bond 1,200,000.00$ 1,200,000.00$ -$ Other -$ -$ -$

Future Projects D-999 State -$ -$ -$ Bond -$ -$ -$ Other -$ -$

NET CHANGE 1,500,000$

QUARTERLY REPORT OVERVIEWBUDGET ADJUSTMENTS 2006 BOND

44

Page 49: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICT QUARTERLY PROJECT REPORT 2006 BOND

JULY 2011

PROJECT - LMC

PROJECT SCHEDULE Planned Completion: 2013PROJECT BUDGET

Budget Est At Completion Variance 0% Paid to DateBudgetFundingStateBondOtherTotal Funding

PROJECT - LMC

Student Services Project # L-612

-$ -$ -$ -$

PROJECT DESCRIPTION: Remodel of 27,920 sq.ft. of college complex now containing all of admissions, administration, nursing, business services and central services to accommodate student services. Project to include all architectural and engineering work, DSA coordination, construction and inspections.

18,609,363$ 18,609,363$ -$ 1,326,005$

18,609,363$ 18,609,363$ -$ 1,326,005$ COMMENTS: DSA submittal is scheduled for August 2011. Interim Swing Space remodel projects are under construction for spaces in support of the Student Services Remodel project.

18,609,363$ 18,609,363$ -$ 1,326,005$ -$ -$ -$ -$

Nursing /EMT Remodel Project # L-614

PROJECT DESCRIPTION: Planning, design and construction for the renovation of LMC's nursing complex to accommodate the relocated and expanded nursing and EMT program functions.

PROJECT SCHEDULE Planned Completion: December 2011PROJECT BUDGET

Budget Est At Completion Variance 0% Paid to DateBudgetFundingStateBondOtherTotal Funding

complex to accommodate the relocated and expanded nursing and EMT program functions.

7,873,863$ 7,873,863$ -$ 1,196,427$

7,873,863$ 7,873,863$ -$ 1,196,427$ COMMENTS: Project is under construction and is approximately 45% completed. Rough plumbing, mechanical and electrical systems are in progress. Sheetrock installation is in progress. Exterior improvements at Planetarium and South Entrance into College Complex are in progress.

-$ -$ -$ -$ 7,873,863$ 7,873,863$ -$ 1,196,427$

-$ -$ -$ -$

45

Page 50: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICT QUARTERLY PROJECT REPORT 2006 BOND

JULY 2011

PROJECT - LMC

PROJECT SCHEDULE Planned Completion: August 2010PROJECT BUDGET

Budget Est At Completion Variance 0% Paid to DateBudgetFundingStateBondOther

Total Funding

PROJECT - LMC New Brentwood Center Project # L- 630

PROJECT DESCRIPTION: Acquisition of land and planning, design, and construction of a new campus to replace the Brentwood Center currently housed in the leased space.

COMMENTS: Project is 100% complete. Closeout Phase in progress. Budget will be adjusted to reflect lower than expected expenses. This project will be financially closed and moved to the Completed Projects list.

1,403,909$ 1,403,909$ -$ 896,276$

-$ -$ -$ -$ 1,403,909$ 1,403,909$ -$ 896,276$

-$ -$ -$ -$

Parking Lot B Extension Project # L-626

PROJECT DESCRIPTION: Planning, design and construction for paving of remaining area of Lot B parking lot at Los Medanos College.

1,403,909$ 1,403,909$ -$ 896,276$

PROJECT SCHEDULE Planned Completion: TBDPROJECT BUDGET

Budget Est At Completion Variance 0% Paid to DateBudgetFundingStateBondOtherTotal Funding

COMMENTS: Escrow closed on the purchase of land for the new center. Project proposals will be prepared to request partial state funding for the site development and building.

-$ 1,149,741$ -$ -$ -$ -$

41,292,800$ 41,292,800$ -$ 1,149,741$

41,292,800$ 41,292,800$ -$ 1,149,741$

27,404,025$ 27,404,025$ -$ -$ 13,888,775$ 13,888,775$

46

Page 51: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICT QUARTERLY PROJECT REPORT 2006 BOND

JULY 2011

PROJECT - LMC

PROJECT SCHEDULE Planned Completion: 2014PROJECT BUDGET

Budget Est At Completion Variance 0% Paid to DateBudgetFundingStateBondOtherTotal Funding

PROJECT - LMC Gym Modernization Project # N/A

PROJECT DESCRIPTION: This project will modernize the Gymnasium building to bring it up to modern operational standards and current seismic and ADA codes.

-$ -$ 13,290,000$ 13,290,000$ -$ -$

6,647,000$ 6,647,000$ -$ -$ 6,643,000$ 6,643,000$

COMMENTS: This project was previously approved for funding by the California Community College System Office Facilities Planning Unit. However, due to lack of a state bond on the November 2010 election ballot to fund this project, the project was resubmitted for consideration in the 2012/2013 funding year.

Physical Education Project # L-629

PROJECT DESCRIPTION: This Project will construct a new building to replace three existing portable buildings and to provide additional Physical Education instructional lab, training spaces and Division and Faculty/Staff offices. The new building will provide a modern circuit training laboratory/exercise facility, adaptive physical exercise, cardio vascular conditioning, aerobics and other modern physical fitness and personal wellness instructional spaces.

13,290,000$ 13,290,000$ -$ -$

-$ -$ -$ -$

PROJECT SCHEDULE Planned Completion: 2016PROJECT BUDGET

Budget Est At Completion Variance 0% Paid to DateBudgetFundingStateBondOtherTotal Funding

modern operational standards and current seismic and ADA codes.

3,485,704$ 3,485,704$ -$ -$

-$ -$ -$ -$ 3,485,704$ 3,485,704$ -$ -$

-$ -$ -$ -$ 3,485,704$ 3,485,704$ -$ -$

COMMENTS: This project was submitted for State funding, but did not score high enough for consideration. The project may need to be deferred, the scope reduced, or cancelled.

47

Page 52: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICT QUARTERLY PROJECT REPORT 2006 BOND

JULY 2011

PROJECT - LMC

PROJECT SCHEDULE Planned Completion: TBDPROJECT BUDGET

Budget Est At Completion Variance 0% Paid to DateBudgetFundingStateBondOtherTotal Funding

PROJECT - LMC

ADA Improvement Projects Project # N/A

PROJECT DESCRIPTION: Bond funding has been allocated for various projects to remove barriers to access that were identified in an American with Disability Act study and transition plan.

1,079,100$ 1,079,100$ -$ -$

-$ -$ -$ -$ 1,079,100$ 1,079,100$ -$ -$

-$ -$ -$ -$ 1,079,100$ 1,079,100$ -$ -$

COMMENTS: Projects will be identified by campus leadership.

Infrastructure Improvement Project # N/A

PROJECT DESCRIPTION: Bond funding has been allocated for various projects to upgrade aging infrastructure such as utilities and parking lots.

PROJECT SCHEDULE Planned Completion: TBDPROJECT BUDGET

Budget Est At Completion Variance 0% Paid to DateBudgetFundingStateBondOtherTotal Funding

infrastructure such as utilities and parking lots.

5,886,000$ 5,886,000$ -$ -$

COMMENTS: Project is pending condition analysis.

-$ -$ -$ -$ 5,886,000$ 5,886,000$ -$ -$

-$ -$ -$ -$ 5,886,000$ 5,886,000$ -$ -$

48

Page 53: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICT QUARTERLY PROJECT REPORT 2006 BOND

JULY 2011

PROJECT - LMC

PROJECT SCHEDULE Planned Completion: 2016PROJECT BUDGET

Budget Est At Completion Variance 0% Paid to DateBudgetFundingStateBondOtherTotal Funding

PROJECT - LMC Campus Project Admin/CM Project # L-599

PROJECT DESCRIPTION: Providing full-time on-site construction management services to

Replace Locker Rooms Project # N/A

COMMENTS: This project was submitted for State funding, but did not score high enough for consideration. The project may need to be deferred, the scope reduced, or cancelled.

-$ -$ -$ -$ 4,730,673$ 4,730,673$ -$ -$

-$ -$ -$ -$ 4,730,673$ 4,730,673$ -$ -$

PROJECT DESCRIPTION: This project will replace the men's and women's locker room buildings which are significantly outdated and non-functional to the current day needs of the college. The wood frame and wood sided buildings, as well as building HVAC, plumbing and electrical systems are at the end of their life cycle. Because these buildings comprise a "building complex”, they will be demolished and replaced as one new building.

4,730,673$ 4,730,673$ -$ -$

PROJECT BUDGETBudget Est At Completion Variance 0% Paid to Date

BudgetFundingStateBondOther

Total Funding 1,400,000$ 1,400,000$ -$ 315,507$ COMMENTS:

-$ -$ -$ -$ 1,400,000$ 1,400,000$ -$ 315,507$

-$ -$ -$ -$

PROJECT DESCRIPTION: Providing full-time on-site construction management services to coordinate and oversee construction projects on campus throughout design, construction and occupancy phases.

1,400,000$ 1,400,000$ -$ 315,507$

49

Page 54: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

CONTRA COSTA COMMUNITY COLLEGE DISTRICT QUARTERLY PROJECT REPORT 2006 BOND

JULY 2011

PROJECT - LMC

PROJECT BUDGETBudget Est At Completion Variance Paid to Date

BudgetFundingStateBondOtherTotal Funding 1,000,000$ 1,000,000$ -$ -$

Future Projects Project # L- 999PROJECT DESCRIPTION: Funding for projects in early preliminary planning which have had no expenses yet.

1,000,000$ 1,000,000$ -$ -$

COMMENTS:

-$ -$ -$ -$ -$ -$ -$ -$

1,000,000$ 1,000,000$ -$ -$

50

Page 55: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

2006 Bond Financial Summary

May 30, 2011

Budget Estimated at Completion Expenses

Active Projects

Student Services 18,609,363.00$ 18,609,363.00$ 1,326,005.30$

Nursing /EMT Remodel 7,873,863.00$ 7,873,863.00$ 1,196,427.15$

Parking Lot B Extension 1,403,909.00$ 1,403,909.00$ 896,275.99$

Brentwood Center 13,888,775.00$ 13,888,775.00$ 1,149,741.27$

Physical Education 6,643,000.00$ 6,643,000.00$ -$

Gym Modernization 3,485,704.00$ 3,485,704.00$ -$

ADA Improvement Projects 1,079,100.00$ 1,079,100.00$ -$

Infrastructure Improvement 5,886,000.00$ 5,886,000.00$ -$

Replace Locker Rooms 4,730,673.00$ 4,730,673.00$ -$

Campus Project Admin/CM 1,400,000.00$ 1,400,000.00$ 315,507.41$

Future Projects 1,000,000.00$ 1,000,000.00$ -$

Total Active Projects 66,000,387.00$ 66,000,387.00$ 4,883,957.12$

Closed Projects

Athletic Fields * 3,332,946.00$ 3,332,946.00$ 2,950,743.70$

Total Closed Projects 3,332,946.00$ 3,332,946.00$ 2,950,743.70$

Total 69,333,333.00$ 69,333,333.00$ 7,834,700.82$

LMC 2006 Bond

* Financial close out in process.

51

Page 56: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

LMCPrevious Oversight Current Oversight Budget Reason for

Project Name Project # Funding Budget Budget Budget Changes Change

Student Services L-612 State -$ -$ -$ Bond 18,609,363.00$ 18,609,363.00$ -$ Other -$ -$ -$

Nursing /EMT Remodel L-614 State -$ -$ -$ Bond 7,873,863.00$ 7,873,863.00$ -$ Other -$ -$ -$

Parking Lot B Extension L-626 State -$ -$ -$ Bond 1,403,909.00$ 1,403,909.00$ -$ Other -$ -$ -$

New Brentwood Center L- 630 State 27,404,025.00$ 27,404,025.00$ -$ Bond 13,888,775.00$ 13,888,775.00$ -$ Other -$ -$ -$

Physical Education L-629 State 6,647,000.00$ 6,647,000.00$ -$ Bond 6,643,000.00$ 6,643,000.00$ -$ Other -$ -$ -$

Gym Modernization N/A State -$ -$ -$ Bond 3,485,704.00$ 3,485,704.00$ -$ Other -$ -$ -$

ADA Improvement Projects N/A State -$ -$ -$ Bond 1,079,100.00$ 1,079,100.00$ -$ Other -$ -$

Infrastructure Improvement N/A State -$ -$ -$ Bond 5,886,000.00$ 5,886,000.00$ -$ Other -$ -$

Replace Locker Rooms N/A State -$ -$ -$ Bond 4,730,673.00$ 4,730,673.00$ -$ Other -$ -$

Campus Project Admin/CM L-599 State -$ -$ -$ Bond 1,400,000.00$ 1,400,000.00$ -$ Other -$ -$

Future Projects L- 999 State -$ -$ -$ Bond -$ -$ -$ Additional funding through interestOther -$ 1,000,000.00$ 1,000,000.00$ funds

NET CHANGE 1,000,000$

QUARTERLY REPORT OVERVIEWBUDGET ADJUSTMENTS 2006 BOND

52

Page 57: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 58: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 59: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 60: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 61: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 62: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 63: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 64: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 65: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 66: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 67: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 68: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 69: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 70: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 71: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 72: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 73: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 74: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 75: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 76: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 77: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 78: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 79: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 80: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 81: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 82: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 83: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 84: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 85: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 86: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 87: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 88: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math
Page 89: CONTRA COSTA COMMUNITY COLLEGE DISTRICT MEASURE …€¦ · CONTRA COSTA COMMUNITY COLLEGE DISTRICT . MEASURE A BOND ... 2011 Contra Costa Community College District ... by the math

MEASURE A 2002/2006 COMMITTEE

CCC DVC LMC DO

Foundation member (1/college)

Jagjit Bhambra

James Clay

N/A

Student (1/college)

Rodney Wilson

N/A

Business/community members (2/college)

Ludmyrna

Lopez

Steve Van Wart

N/A

Scott Hanin

Mark Ross

N/A

Taxpayers Association (1/Chancellor)

N/A

N/A

N/A

Mauna Wagner

Senior citizens (1/Chancellor)

N/A

N/A

N/A

John Cottrell

General member (1/Chancellor)

N/A

N/A

N/A

Enrique Ruiz