Page 1: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

Moynihan StationMoynihan Station

Contractor Briefing

Connecting Corridor

January 30, 2013

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G 1

Page 2: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

Project Rolesj• MSDC – Project Sponsor, Grant Holder and Bill Payer• PANYNJ – Project Manager for MSDCPANYNJ Project Manager for MSDC• NYCTA –Facility Owner • STA JV – Construction ManagementSTA JV Construction Management• SOM – Designer of Record• Thatcher Associates – Integrity MonitorThatcher Associates Integrity Monitor

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G2

Page 3: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

Project Stakeholdersj

• Empire State Development CorporationEmpire State Development Corporation • Moynihan Station Development Corporation• MTA – NYCTAMTA NYCTA• Port Authority of New York and New Jersey• Federal Railroad AdministrationFederal Railroad Administration

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G3

Page 4: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

Design Teamg

• Skidmore Owings & Merrill - ArchitectsSkidmore Owings & Merrill Architects• PB – Platform Ventilation• Systra – Transit & Rail SystemsSystra Transit & Rail Systems• Severud - Structural and Blast Engineers• JB&B - MEP EngineersJB&B MEP Engineers• DVS - Security Consulting Engineers• BCA – Historic PreservationBCA Historic Preservation• CCI – Code Consultants

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G4

Page 5: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

Reference Codes

• 2008 New York City Building Code• 2008 New York City Fire Code• 2010 New York State Building Code• 2010 NFPA 130 Standard for Fixed Guideway

Transit and Passenger Rail Systems

• Line of demarcation between reference codes is theFarley Building Slab separating the ConcourseFarley Building Slab separating the Concourse (Street Entry) and Lower Concourse (West End Concourse)

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G5

Page 6: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

Phase 1 MWBE/DBE Program

MSDC adopted a Disadvantaged, Minority and Women-owned Business Enterprise Plan.

htt // d /S b idi i P j t /MSDC/D t /RFP O t iti /Mhttp://www.esd.ny.gov/Subsidiaries_Projects/MSDC/Data/RFPs_Opportunities/MSDC_DBE_MWBEPlan.pdf

MSDC will follow NYS law with regards to encouraging Minority and Women g g g yparticipation in MSDC contracts.

The overall MWBE participation goal requirement for the project shall be no less than 20% of the total value of the project with a Minority Businessless than 20% of the total value of the project, with a Minority Business Enterprise participation goal of 12% and a Women Business Enterprise participation goal of 8%.

MSDC encourages DBE participation and dual certification.

MSDC will report both MWBE and DBE participation to the federal government.

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G6

Page 7: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

Pre-Construction Dates

• January 30, 2013 - Pre-Bid Meeting

February 6 2013 Deadline for Pre Bid Questions• February 6, 2013 - Deadline for Pre-Bid Questions

• February 8, 2013 – Addendum #1

• February 20, 2013 - BIDS DUE

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G 7

Page 8: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

Construction Milestones

• Milestone 1 - Completion of all 33rd Street Closure Work• 21 days after commencement of such work and no

later than August 31 2014later than August 31, 2014

• Milestone 2 – Completion of all HSBC Work• July 15, 2015

• Milestone 3 – Final CompletionMilestone 3 Final Completion• 1,160 days after NTP

• Liquidated Damages for failure to meet these dates• Liquidated Damages for failure to meet these dates

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G 8

Page 9: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

Construction Constraints• Hours of work for working within NYCT spaces

Weekday Nights: 8:00 PM to 5:00 AM Monday through ThursdayWeekday Nights: 8:00 PM to 5:00 AM, Monday through Thursday. Weekends: 8:00 PM Friday to 5:00 AM Monday

• Hours of work for Street and PlazasHours of work for Street and PlazasPlazas / Sidewalks: 7:00 AM to 10 PM, Monday through Friday.9:00 AM to 8:00 PM, Saturday and Sunday

• Schedule Constraints for working within HSBC scopeConstruction allowed from 6-1-2015 to 7-15-2015

• Schedule Constraints for 33rd Street Full Closure (3 weeks)August 2014

• Schedule Constraints for working in WEC AreasConstruction will not be allowed to work in the area of the current WEC C t t til 319 d ft NTP

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G 9

WEC Contractor until 319 days after NTP

Page 10: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

Construction Items to Note

• No work within the train shedNo need for Amtrak/LIRR trainingNo need for Amtrak/LIRR training

• Limited MTA work• Limited MTA workMTA Training required

C C• Coordination with WEC contractorNorth Plaza and within the interface of the WEC and Connecting Corridor

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G 10

Page 11: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

The Project Scope of Work

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G Aerial View 11

Page 12: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

Scope of Work p• Widening the Connecting Corridor between the West End

Concourse and Penn Station• Re-Sloping the Ramps to Comply with ADA• Reconfigure the stairs from the WEC to the Subway Platform

levellevel• Reconfigure the stairs from Subway Platform level to the Street• Relocate the Subway entrance to within the North plaza• Reconfigure the MTA Fare Array and adjacent areas• Reframing the structural support for 33rd street/Subway box roof

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G 12

Page 13: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G 33rd Street Entrance Plaza 13

Page 14: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G West End Concourse Level Scope 14

Page 15: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

Street Level - Staging and Phasing

• Maintain USPS Services and Access

Various Full/Partial Road Closures• Various Full/Partial Road Closures• 33rd Street - impacts due to subway work below

• Approx 3 year period

• Site construction• Plaza Construction• Bollard Curb and sidewalk installations• Bollard, Curb and sidewalk installations

• Approved Contractor Staging Areas

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G 15

Page 16: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G Street Level Staging Plan 16

Page 17: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G 33rd Street Partial Closure North Lane 17

Page 18: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G 33rd Street Partial Closure South Lane 18

Page 19: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G 33rd Street Full Closure 19

Page 20: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G 33rd Street Partial Closure South Lane 20

Page 21: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G 33rd Street Partial Closure North Lane 21

Page 22: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G North Plaza Plan 22

Page 23: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G North Plaza Subway Stair 23

Page 24: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

Connecting Corridor- Staging and Phasing

• Connecting Corridor• Hours of Work

• Weekday Night: 8:00 PM to 5:00 AM, Monday through Thursday.• Weekend: 8:00 PM Friday to 5:00 AM Monday

• Coordination with LIRR and NYCT operations to maintain• Coordination with LIRR and NYCT operations to maintain adequate passenger flow

• Construction Coordination with Current WEC ContractorConstruction Coordination with Current WEC Contractor

• Connection to Penn Station

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G 24

Page 25: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G Connecting Corridor Staging Plan 25

Page 26: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G Connecting Corridor Staging Plan 26

Page 27: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G Fare Array Staging Plan 27

Page 28: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G Subway Platform Staging Plan 28

Page 29: Contractor Briefing Connecting Corridor...Construction Milestones • Milestone 1 - Completion of all 33rd Street Closure Work • 21 days after commencement of such work and no later

Moynihan StationMoynihan Station

Contractor Briefing

Connecting Corridor

January 30, 2013

M O Y N I H A N S T A T I O N / F A R L E Y P O S T O F F I C E B U I L D I N G 29