YINI Student - Azam GhaffarContribution to the Business Awards
1
Nature of Doosan Babcocks BusinessComponent Testing
Nuclear
Civil EngineeringAerospace
Oil and Gas
Thermal Power
Leading provider of engineering and asset management services to energy sector
Builds, maintains and improves power stations, pharmaceutical facilities and gas plants
Component Testing contains a variety of full scale testing rigs
Testing rigs are able to be tailored to clients needs
Structural integrity of components can be qualified before clients assets are deployed
1
2
3
4
5
2
4More testing availabilities
3Increase axial and compressive loads
Ease of access for loading and unloading
1
Safer conditions around rig
2
Project DetailsCentraliser Slippage RigDesign and manufacture a Centraliser Slippage Rig for the department
Current setup is outdated and needs replacedAxial load is causing damage to current test machineLimiting capabilities affect current setup
3
Department performs tests for subsea pipeline components
To become a market leader for subsea pipeline component qualification
Contributes to wider organisation objectives of growth aspirations
Company plans to increase its current turnover of 35 million to 50 million
Component Testing contributes 5 million
Expansion of department allows us to increase our contribution to double within 5 years
Business Case for ProjectSubsea Pipeline Component QualificationExpansion Programme
Real Life Application of CentralisersCentraliser clamps along length of inner pipe
Inner pipe passes through carrier pipe centraliser keeps it central
Centraliser must be able to withstand installation and operational forces
Centraliser is tested to ensure it wont slip when passing over weld
4
DesignPropose ideas that meets project criteria
CalculationsJustify final design
MaterialsSource appropriate materials and components
Manufacture & AssemblyMachine and weld materials to complete assembly
CommissioningConclude finished testing rig works successfully
Initiating the Project Project StagesObserved current test setup
Understood the concept of the test
Understood what issues current setup was experiencing
Understood what changes needed to be made
Helped stimulate ideas on tackling the project
5
Design and CalculationsEstablishing Final Design92
START
1Design
2Calculations
Review MeetingsFinish
Design
Used idea generation techniques
Transferred concept from existing setup
Incorporated external parts into design
Calculations
Structural engineer guided me in right direction
Bolt sizes and lengths, steel thickness and bending moments
Failure to satisfy calculations results in new design required
Review Meetings
Between myself, line managers and senior engineers
Made any design changes
Approval of design led to next stage of project
6
Materials
Choice of materials based on availability and required strengthOver 50 different parts and standard components in the design3 supplier quotation system to ensure cheapest option3D Model and Technical Drawings Implementing Standardised Drawing System
7
Manufacture and AssemblyCentraliser Slippage Rig
Turn this pile of metal into a testing rigTechnical drawings assisted in communicating informationDeveloped knowledge in welding and machining
Step by step process of welding and machining assemblies
Minor design changes occurred
Used problem solving skills to overcome challenges
Assembly of rig is now complete
8
CommissioningCentraliser Slippage RigCentraliser clamped to inner pipe and sits in carrier pipe
750kN Hydraulic Cylinder applies compressive load down onto centraliser
300kN Hydraulic Cylinder applies horizontal axial load and pushes against carrier pipe
CostsCapital Expenditure of Centraliser Slippage RigMaterialsMaterials such as steel and any component parts were purchased from suppliers SubcontractorsParts made for us such as steel profiling, machining and welding of parts.LabourWelders, machinists and fitters tasked to the project had hourly rates when manufacturing and assembling rig
40,286 Budget
1
2311,226
8,124
5,025=15,625 Budget RemainingCost of standard test: - 5,510Additional day testing - 1,562
Current SetupNew SetupRunning Cost40003000Savings per test = 1000Total annual savings = 9000Payback PeriodTesting Rig Cost = 24375243759000= 3 years9 or 10 project completed annually Payback period is 3 years
10
ConclusionDoosan Babcock YINI Placement28Thank you to EDT Scotland and Doosan Babcock for making this placement possible
Project Completion
Ease of access for loading and unloadingSafer conditions around the rigIncrease in compressive and axial loadsMore testing availabilities
Personal Development
Knowledge of engineering both theoretical and practicalCommunication skillsResponsibility and reliability to work independentlyProfessionalism in the workplaceOrganisation and planning
11
Thank You All For ListeningAny Questions?