Crenshaw/LAX Transit Project Westside/Central Service Council Update
April 13, 2016
1
2
• Design-Build Contractors: • Rail Line and Stations - Walsh Shea
Corridor Constructors (WSCC) • Southwestern Yard Maintenance
Facility - Hensel Phelps Herzog • 8.5-mile light-rail line and rail maintenance
facility • Eight new stations:
• Three underground • Four at-grade • One aerial
• Total Project budget: $2.058 billion • Scheduled Completion: 2019
2
Project Overview
3
All six underground structures under construction:
• Expo/Crenshaw Station - Final depth reached at 67’ below street • MLK Station – Final depth reached at 63‘ below street level • Leimert Park Station – Final depth reach at 61’below street level • Crenshaw/Vernon – 1,200’ tunnel portal • Hyde Park – 4,200’ 'cut and cover' tunnel • Aviation Bl – 2,700’ trench/tunnel near LAX
Project Update
4
All six aerial structures under construction: • La Brea Overpass • I-405/La Cienega ( 300'+ main span) • Aviation/Century Aerial Station • 111th Street overpass • Green Line Connection • Manchester Overpass
Recent and Upcoming milestones:
• April 7 - Park Mesa Heights At-Grade construction begins • April 18 – “Harriett” TBM begins tunneling
Project Update
5
Saturday, May 7, 2016, 10 am to 4 pm Leimert Park Village, 4395 Leimert Blvd., Los Angeles, CA 90008 Metro is hosting a community celebration, as we approach the halfway mark on the Crenshaw/LAX Transit Project. We thank the community for your patience and continued support as we achieve this significant milestone. Anticipated activities include: • Performances by local musical artists • Kids zone • Marketplace • Metro and Contractor employment opportunities • Small business resources • Sustainability resources
Northern Segment - Expo/Crenshaw Bl to 67th St Four new stations
• Three underground • One at-grade
One mile at-grade segment Two underground structures
• Duel parallel bored tunnels • “Cut and Cover” tunnel
6
Crenshaw/LAX Transit Project Northern Segment Update
7
• Two parallel one mile long tunnels • Each tunnel is one mile in long • 13 months to bore both tunnels • Tunnels will connect three underground stations • TBM is 21.5’ in diameter and approximately 400’ long • Scheduled start date April 18th, 2016
“Harriet” - Tunnel Boring Machine (TBM)
8
“Harriet” - Tunnel Boring Machine (TBM)
Harriet fully assembled underground at the Expo/Crenshaw Station
9
Winners announced February 2: • Naming Contest Winner:
• Calvin Mosley, City Honors High School in Inglewood
• Artwork Contest Winner: • Brittany Hernandez, 3rd grade,
Dr. Lloyd Owen Knox Elementary School in Los Angeles
“Harriet” - Tunnel Boring Machine (TBM)
TBM Naming and Artwork Contests: • Artwork contest: Pre-k to 5th grade students • Naming contest: 6th to 12th grade students • More than 250 submissions • More than 90,000 votes for top 10 entries
10
Station construction ongoing: • Expo/Crenshaw Station • MLK/Crenshaw Station • Leimert Park Station
Construction work activities:
• Excavation under the street • Concrete pours of station
floors and walls • Installation of station facilities • Grouting work activities
Anticipated completion in 2019
Underground Station Construction
MLK Station chemical grouting
11
Underground Station Construction Expo/Crenshaw Station
View looking down into station Station slab placement
12
Underground Station Construction MLK/Crenshaw Station
Station wall formation
13
Tier level 2 bracing View from train portal into station
Underground Station Construction Leimert Park Station
14
Scope of Work: • New curbs, gutters, sidewalks • Updated/new street lights and
traffic signals • New roadway
surface/rehabilitation • New landscaped medians • Rail safety enhancements • Crenshaw Bl Streetscape Plan
elements: • New sidewalk trees • New lighting • New crosswalks
Park Mesa Heights North and Central Segments: 48th St. to 59th St.
Conceptual Rendering by LA City Planning Department
15
15
Civil Construction • Replacement of the curbs, gutters and
sidewalks • Four stages of construction • Scheduled start date: April 18, 2016
Park Mesa Heights North Segment: 48th St. to 54th St.
Storm Drain Construction • Replacement of storm drain pipes at specific
locations along Crenshaw Blvd. • West side of Crenshaw Blvd. from 48th St. to
52nd St. • Start date: April 7, 2016
Three phases of construction: • Stage A (Current) - Pile installation on
east side of Crenshaw Bl • Stage B – Pile installation on west side of
Crenshaw Bl • Stage C – Excavation in center of
Crenshaw Bl Total construction time: 3 years
16
Park Mesa Heights (59th to 67th St.) Tunnel/Cut and Cover Construction
South Segment: Inglewood to El Segundo Four new stations • Three at-grade • One aerial Five aerial structures One underground structure
17
Crenshaw/LAX Transit Project Southern Segment Update
Aerial structure at Green Line connection
18
Southern Segment Bridge Construction
• Trench near LAX • Located adjacent to
Aviation Bl and LAX runways
19
Southern Segment Underground Construction
• Ongoing construction of bridge supports for (I-405 bridge)
• Century Bl Bridge super structure scheduled
to be complete in May 2016
20
Southern Segment Bridge Construction
La Brea Ave Bridge superstructure completed in April 2016
21
Southern Segment Bridge Construction
Guideway excavation east of La Brea Av Bridge
22
Southern Segment Bridge Construction
23
Southern Segment Southwestern Maintenance Yard
Community Leadership Council (CLC)
24
Economic Development Workgroup- March 3 • Eat Shop Play • Business Assistance • PLA/CCP • Metro Joint Development Community Engagement Workgroup- March 22 • Crenshaw Area Walking Maps
25
Project Labor Agreement (PLA) / Construction Careers Policy (CCP) Update
Report Data Through Feb. 2016 Reporting Period
Project Labor Agreement
No. of Work Hours*
Targeted Economically Disadvantaged Worker Utilization (%) Goal: 40%
Apprentice Utilization (%) Goal: 20%
Disadvantaged Worker Utilization (%) Goal: 10%
1,499,295.08 58.99% 18.11% Based on Total
Apprenticeable Work Hours
11.61%
Executive Order 11246 Demographic Summary No. of Work Hours*
African American Utilization
Asian/Pacific Islander Utilization
Caucasian Utilization
Hispanic Utilization
Native American Utilization
Other/Declined to state
Minority Utilization Goal: 28.3% (rounded)
Female Utilization Goal: 6.9%
1,499,295.08 15.38% 1.12% 23.31% 55.42% 1.16% 3.59% 73.08% 2.95%
*Cumulative Hours Through End of Noted Reporting Period – as Reported by Prime Contractor. Data subject to change to reflect updates or audits.
Percentage Project Complete Based on Worker Hours: 49.98% (rounded)
Report Data Through February 13, 2016
Crenshaw/LAX Transit Corridor Project PLA Targeted Worker Attainment: Prime: Walsh/Shea
Metro Construction Mitigation Programs
Metro Business Interruption Fund (BIF) Metro Business Solutions Center (BSC) Eat, Shop, Play Crenshaw/Inglewood
27
Business Interruption Fund (BIF)
BIF Grant Update – February 29, 2016 • BIF applications submitted: 265 • BIF applications approved/awarded: 126 • BIF applications pending financials: 76 • Total BIF Grant Payments: $2,230,843.62 • Crenshaw/LAX BIF Grants: $1,914,964.21
Program Overview • Financial assistance to small “mom and
pop” businesses directly impacted by Metro construction
• Relevant Metro construction projects: Crenshaw/LAX, Regional Connector and Purple Line Extension, Phase I
• Maximum grant of $50,000 per rolling year
Program Requirements (partial list) • For-profit business or non-religious, non-profit
with 25 or fewer total employees • Businesses located immediately adjacent to
rail corridor and directly impacted by construction
• Businesses must be solvent • Businesses must be in good standing with all
local, state and federal authorities • Ability to provide relevant financial records • Meet other technical qualifications 28
Business Solution Center
• Provides hands-on case management services and business assistance to small businesses between 48th St and 60th St
• Small businesses not in the immediate area have access for business and technical assistance
• BSC Services • Expert business advice and technical assistance • Hands-on Case Management • Business outreach, partner outreach and referral services (e.g. referrals to
BSC Business Partners, financial services providers, business resource providers)
• Partnership with Del Richardson & Associates, Inc. (DRA) and collaborative with Vermont Slauson Economic Development Corporation, Los Angeles Urban League, Urban Design Center and Turning Point Communication
29
Eat, Shop, Play Crenshaw / Inglewood
30
Crenshaw/LAX Transit Project
Anthony Crump Community/Construction Relations Manager
[email protected] 323.903.4152
Connect with us: Hotline: 213-922-2736 Email: [email protected] Web: metro.net/crenshaw Facebook: facebook.com/crenshawrail Twitter: twitter.com/crenshawrail WSCC: www.walsh-shea-corridorconstructors.com
Crenshaw/LAX Transit Project
Questions and Answers