4/11/2013 © Copyright 2013 Anupam Kumar 1 Critical Path Methods Presented by: AnupamKumar Reader SMS Varanasi Critical Path Method (CPM) Critical Path Method was developed by Du Pont In Critical Path Method (CPM) the emphasis is on the trade-off between the cost of the project and its overall completion time e.g. For certain activities it may be possible to decrease their completion times by spending more money How does this affect the overall completion time of the project? Critical Path Method In Critical Path Method (CPM) activities are shown as a network of precedence relationships using activity-on-node network construction. CPM is used in Production management for the jobs of repetitive in nature where the activity time estimates can be predicted with considerable certainty due to the existence of past experience. CPM has Single estimate of activity time Deterministic activity times Illustration 1 A leading company has decided to bring about certain changes in its product design for which the time estimates are as follows . Estimate the time it would take to get the new design implemented. The activity precedence detail is: Activity number must finish before Activity number can start 1 3 2 4 3 5 4 6 5,6 7 7 8 8 9 8 10 9,10 11 Illustration 1 (Contd. ) Activity No. Activity Time (in Weeks) 1 Redesign Product 6 2 RedesignPackaging 2 3 Order & receive component for redesigned product 3 4 Order & receive component for redesigned packaging 2 5 Assemble Product 4 6 Makeup packaging 1 7 Package redesign product 1 8 Test Market redesigned product 6 9 Revise redesigned product 3 10 Reviseredesigned packaging 1 11 Present result toBoard 1 Illustration 2 The time estimates for completing the plant construction project is as shown. Determine the critical path. How much slack time is available in the non critical path? 1 2 4 3 6 5 7 8 12 4 6

Upload: anupam-kumar

Post on 22-Dec-2014

641 views

Category:

Education


1 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Critical path method

4/11/2013

© Copyright 2013 Anupam Kumar 1

Critical Path Methods

Presented by:

Anupam Kumar

Reader

SMS Varanasi

Critical Path Method (CPM)

• Critical Path Method was developed by Du Pont

• In Critical Path Method (CPM) the emphasis is on the

trade-off between

– the cost of the project and

– its overall completion time

• e.g.

– For certain activities it may be possible to decrease their

completion times by spending more money

– How does this affect the overall completion time of the

project?

Critical Path Method

• In Critical Path Method (CPM) activities are shown as

– a network of precedence relationships using

– activity-on-node network construction.

• CPM is used in Production management

– for the jobs of repetitive in nature where the activity time

estimates can be predicted with considerable certainty due

to the existence of past experience.

• CPM has

– Single estimate of activity time

– Deterministic activity times

Illustration 1

• A leading company has decided to bring about certain changes in its

product design for which the time estimates are as follows.

• Estimate the time it would take to get the new design implemented.

• The activity precedence detail is: Activity number

must finish before

Activity number

can start

1 3

2 4

3 5

4 6

5,6 7

7 8

8 9

8 10

9,10 11

Illustration 1 (Contd.)Activity

No.

Activity Time

(in Weeks)

1 Redesign Product 6

2 Redesign Packaging 2

3 Order & receive component for redesigned product 3

4 Order & receive component for redesigned packaging 2

5 Assemble Product 4

6 Make up packaging 1

7 Package redesign product 1

8 Test Market redesigned product 6

9 Revise redesigned product 3

10 Revise redesigned packaging 1

11 Present result to Board 1

Illustration 2

• The time estimates for completing the plant

construction project is as shown.

– Determine the critical path.

– How much slack time is available in the non critical path?

1 2 4

3

6

5

7 812 4 6

Page 2: Critical path method

4/11/2013

© Copyright 2013 Anupam Kumar 2

Crashing CPM Networks

• Project Timelines are crashed for due to

urgent or contingent conditions.

• Crashing of CPM Networks is

– The process to reduce the normal project duration

– to the desired shorter duration

– activities on the critical path are crashed

– by the use of additional resources / expenses.

Time-cost ratio = Increase in cost / Decrease in time

= (crash cost – normal cost) / (normal time – crash time)

Illustration 3

Activity Time in Weeks Cost (Rs.)

Normal Crash Normal Crash

1-2 6 4 10,000 14,000

1-3 4 3 5,000 8,000

2-4 3 2 4,000 5,000

3-5 8 6 9,000 12,000

4-5 7 4 7,000 8,000

Total Cost: 35,000 47,000

• The network details for

a small project is as

given.

– Draw a network diagram

with the normal times.

– What would be the cost

of the project if the non-

critical path is to be

converted to the critical

path through project

time crashing?

Illustration 4

• A company received an order from a reputed

customer.

– As per the contract, from the day 15th the company will

have to pay a penalty of Rs. 10 per day until job is

completed.

– Indirect project costs per day is Rs. 200.

– The data on direct cost and activities are as follows.

• Draw project network diagram.

• What completion date would you recommend?

• Compute project cost after crashing.

Illustration 4 (Contd.)

Activity Normal Time Normal Cost Crash time Crash cost Immediate

Predecessor

A 4 1000 3 1300 None

B 7 1400 4 2000 None

C 5 2000 4 2700 None

D 6 1200 5 1400 A

E 3 900 2 1100 B

F 11 2500 6 4000 C

G 4 800 3 1500 D, E

H 3 300 1 500 F, G