Critical Path Methods
Presented by:
Anupam Kumar
Reader
SMS Varanasi
Critical Path Method (CPM)
• Critical Path Method was developed by Du Pont
• In Critical Path Method (CPM) the emphasis is on the
trade-off between
– the cost of the project and
– its overall completion time
• e.g.
– For certain activities it may be possible to decrease their
completion times by spending more money
– How does this affect the overall completion time of the
project?
Critical Path Method
• In Critical Path Method (CPM) activities are shown as
– a network of precedence relationships using
– activity-on-node network construction.
• CPM is used in Production management
– for the jobs of repetitive in nature where the activity time
estimates can be predicted with considerable certainty due
to the existence of past experience.
• CPM has
– Single estimate of activity time
– Deterministic activity times
Illustration 1
• A leading company has decided to bring about certain changes in its
product design for which the time estimates are as follows.
• Estimate the time it would take to get the new design implemented.
• The activity precedence detail is: Activity number
must finish before
Activity number
can start
1 3
2 4
3 5
4 6
5,6 7
7 8
8 9
8 10
9,10 11
Illustration 1 (Contd.)Activity
No.
Activity Time
(in Weeks)
1 Redesign Product 6
2 Redesign Packaging 2
3 Order & receive component for redesigned product 3
4 Order & receive component for redesigned packaging 2
5 Assemble Product 4
6 Make up packaging 1
7 Package redesign product 1
8 Test Market redesigned product 6
9 Revise redesigned product 3
10 Revise redesigned packaging 1
11 Present result to Board 1
Illustration 2
• The time estimates for completing the plant
construction project is as shown.
– Determine the critical path.
– How much slack time is available in the non critical path?
1 2 4
3
6
5
7 812 4 6
4/11/2013
© Copyright 2013 Anupam Kumar 2
Crashing CPM Networks
• Project Timelines are crashed for due to
urgent or contingent conditions.
• Crashing of CPM Networks is
– The process to reduce the normal project duration
– to the desired shorter duration
– activities on the critical path are crashed
– by the use of additional resources / expenses.
Time-cost ratio = Increase in cost / Decrease in time
= (crash cost – normal cost) / (normal time – crash time)
Illustration 3
Activity Time in Weeks Cost (Rs.)
Normal Crash Normal Crash
1-2 6 4 10,000 14,000
1-3 4 3 5,000 8,000
2-4 3 2 4,000 5,000
3-5 8 6 9,000 12,000
4-5 7 4 7,000 8,000
Total Cost: 35,000 47,000
• The network details for
a small project is as
given.
– Draw a network diagram
with the normal times.
– What would be the cost
of the project if the non-
critical path is to be
converted to the critical
path through project
time crashing?
Illustration 4
• A company received an order from a reputed
customer.
– As per the contract, from the day 15th the company will
have to pay a penalty of Rs. 10 per day until job is
completed.
– Indirect project costs per day is Rs. 200.
– The data on direct cost and activities are as follows.
• Draw project network diagram.
• What completion date would you recommend?
• Compute project cost after crashing.
Illustration 4 (Contd.)
Activity Normal Time Normal Cost Crash time Crash cost Immediate
Predecessor
A 4 1000 3 1300 None
B 7 1400 4 2000 None
C 5 2000 4 2700 None
D 6 1200 5 1400 A
E 3 900 2 1100 B
F 11 2500 6 4000 C
G 4 800 3 1500 D, E
H 3 300 1 500 F, G