current status and future development of coal thermal ... · pdf filecurrent status and future...
TRANSCRIPT
1
Current Status and Future Development of Coal Thermal Power Plant in Indonesia.
1
I Made Ro SakyaHead of System Planning [email protected]
PT PLN (PERSERO)
Presented in Clean Coal Day 2013 International Symposium
Tokyo, September 4th, 2013
Indonesia
2
Area : Land 1,9 M km2, territorial : 5,2 M km2
Population : 247 million; Growth : 1 %
GDP : 900 Billion USD; growth : 6.2 %
PLN is Major Integrated Electric Utility Company in Indonesia
3
Sole owner of transmission and distribution assets with control over majority of
generation assets in Indonesia
Owner of 38 GW Power
Plant
Controls over 85% of
national generation capacity
Main purchaser of electricity
from Independent Power
Producers (IPPs)
Sole responsibility for
power transmission in
Indonesia
Transmission lines with
38 thousands kmc and
72 GVA of power
transformer capacity
Sole distributor of
electricity to end
customers in Indonesia
Distribution lines of
740 thousands kmc and
39 GVA of transformer
capacity, serving around
50 Millions customers, 10
million PrePaid Meters.
Generation Transmission Distribution
Electrification Ratio [2012]
4
PAPUA BARAT: 66.5%
SUMUT: 87.2%
SUMBAR: 76.9%
RIAU:78.4%
SUMSEL: 66.7%
BENGKULU: 71.2%
BABEL: 92.8%
LAMPUNG: 70.0%
DKI: 96.4%
BANTEN: 80.5%
JABAR: 75.9%
JATENG: 77.8%
JAMBI: 70.0%
DIY: 77.8% JATIM: 75.2% BALI:74.5%NTB: 53.3%
NTT: 53.2%
KALBAR: 89.7%
KALTENG: 56.6%
KALSEL:75.9%
KALTIM:75.9%
SULUT: 76.4%
GORONTALO: 60.7%
SULTENG: 66.0%
SULTRA: 68.8%
SULSEL: 81.2%
MALUT: 85.4%
MALUKU: 77.3%
PAPUA: 33.1%SULBAR: 89.3%
NAD: 88.8%
Electrification Ratio 2012
PLN 73.1%
(PLN+ Non PLN) 75.9%
More than 60 million Indonesian people had no
access to electricity
PLN has an extensive generation portfolio with total installed capacity of approximately 36,612 MW across Indonesia
5
Papua
Diesel 242 MW
Hydro 5 MW
Total 247 MW
Peak Load 200 MW
Pop. (mn) 3.8
Elec. Ratio (%) 41
NTT
Diesel 237 MW
Geothermal 3 MW
Hydro 1 MW
Total 241 MW
Peak Load 131 MW
Pop. (mn) 4,8
Elec. Ratio (%) 53
NTB
Diesel 303 MW
Hydro 1 MW
Others 1 MW
Total 305 MW
Peak Load 220 MW
Pop. (mn) 4.7
Elec. Ratio (%) 53
Java-Bali
Hydro 2,392 MW
Geo 375 MW
Steam-turbine 12,990 MW
Combined Cycle 7,896 MW
Gas turbine 2,035 MW
Diesel 256 MW
IPP 5,672 MW
Total 31,616 MW
Peak Load 21,370 MW
Pop. (mn) 145
Elec. Ratio (%) 78.4
Total Indonesia
Hydro 3,514 MW
Geothermal 548 MW
Steam-turbine 14,529 MW
Combined
Cycle
8,814 MW
Gas-turbine 3,590 MW
Diesel 5,613 MW
Others 4 MW
IPP 7,331 MW
Total* 43,943 MW
Peak Load 29.061 MW
Maluku
Diesel 279 MW
Others 0 MW
Total 279 MW
Peak Load 136 MW
Pop. (mn) 2.8
Elec. Ratio (%) 73
Kalimantan
Hydro 32 MW
Steam-turbine 130 MW
Combined Cycle 60 MW
Gas-turbine 200 MW
Diesel 1,308 MW
Others 0 MW
IPP 56 MW
Total 1,786 MW
Peak Load 1,241 MW
Pop. (mn) 14
Elec. Ratio (%) 73.7
Sumatera
Hydro 864 MW
Geothermal 110 MW
Steam-turbine 1,272 MW
Combined Cycle 858 MW
Gas-turbine 1,232 MW
Diesel 1,973 MW
Others 0 MW
IPP 1,106 MW
Total 7,415 MW
Peak Load 4,405 MW
Pop. (mn) 53
Elec. Ratio (%) 77.3
Sumatera
Kalimantan
Sulawesi
Maluku
Papua
NTT
NTB
Java-Bali
As of December 31, 2012.
* Total power generation capacity in Indonesia, of which PLN produces 36GW
Sulawesi
Hydro 219 MW
Geothermal 60 MW
Steam-turbine 137 MW
Gas-turbine 123 MW
Diesel 1,015 MW
Others 3 MW
IPP 497 MW
Total 2,054 MW
Peak Load 1,357 MW
Pop. (mn) 18
Elec. Ratio (%) 71
Indonesia Coal Resources and Reserves
6
Source: Geological Agency, MEMR, 2010
Coal classification (air-dry basis):– Very high rank coal : ≥ 7,100 kCal/kg– High rank (bituminous) coal : 6,100 – 7,100 kCal/kg– Medium rank (sub-bituminous) coal : 5,100 – 6,100 kCal/kg– Low rank (lignite) coal : ≤ 5,100 kCal/kg
Projection of Electricity Demand 2012-2021
7
IB : 10,5%
26
TWh
62
TWh
IT : 11,4%
14
TWh
37
TWh
JB : 7,9%
132
TWh
259
TWh
2012 2021
Average of national electricity demand growth 2012-2021 is 8,65% annually.
Cust: 32.4 millions
Cust: 10.4 millions
Cust: 6.7 millions
Source: RUPTL PLN 2012-2021
New Power Plant Capacity Addition by Owner [Incl. IPP]
8
• Total capacity addition to 2021: approx 55 GW or 5.5 GW per year
• Allocation for IPP and PLN are not firmly defined except those projects already committed.
Source: RUPTL PLN 2012-2021
Total Installed Capacity by Technology[Incl. IPP]
10
REAL PROJECTION• Power plants capacity
increase from 32.1 GW
in 2008 to 40.3 GW in
2012 or additional 1,700
MW per year.
• The biggest capacity is
for CFPP (48%), then
CCPP (23%), HEPP
(10%), GTPP
(9%), dieselPP (7%)
and geoPP (3%).
• From about 18.000 MW
existing CFPP:
− 64% using
subbituminous and
36% lignite. The
lignite share will
increase when FTP1
projects completed.
− 99% pulverized
boiler and 1% CFB.
Fuel Mix for Electricity Production [GWh]Total Indonesia [Incl. IPP]
11
HSD MFO
COAL
GAS
GEOTHERMAL
HYDRO
HSD
LNG
-
50.000
100.000
150.000
200.000
250.000
300.000
350.000
400.000
450.000
2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
GW
h
Impor Biomass Surya/Hybrid HSD MFO LNG Gas Batubara Geothermal Hydro
Hydro
Geothermal
Coal
Gas
LNG
Oil
Energy production in 2012: coal (50%), gas (23%), oil (15%), hydro (6%) and geothermal (5%)
Source: RUPTL PLN 2012-2021
UNIT CAPACITY DISTRIBUTION OF COAL POWER PLANT
13
0
5
10
15
20
25
30
35
40
45
50
50 - 199 200 - 499 500 -899 > 1000
UN
IT
CAPACITY ( MW )
Roadmap of Clean Coal Technology [CCT] in Indonesia
14
2012 2015 2020 2025
SC, = 30-40%
USC, 43%
IGCC45-48%
Central Java (USC 2x1000 MW)Jawa-1 (USC 1x1000 MW)
Indramayu #1(USC 1000 MW)
Indramayu #2(USC 1000 MW)
Jawa-4 (USC 2x1000 MW)Jawa-5 (USC 2x1000 MW)
2000–3000 MW per year
IGCC 1000 MW Class
Jawa-6 (USC 2x1000 MW)
Source: JICA CCT Study, October 2012, with updated projects and schedule by PLN
Super Critical Generation Coal Fired Power Plants (CFPP) in Java-Bali System
15
SURALAYA
CFPP Jawa Tengah#1: 1.000 MW (2017)#2: 1.000 MW (2018)
CFPP Indramayu#4: 1.000 MW (2018)#5: 1.000 MW (2020)
CFPP Adipala (SC)#1: 660 MW (2014)
CFPP Jawa-6#1: 1.000 MW (2021)#2: 1.000 MW (2021)
CFPP Banten#1: 625 MW (2016)
CFPP Jawa-4 #5: 1.000 MW (2019)#6: 1.000 MW (2020)
CFPP Jawa-1 #2: 1.000 MW (2017)
CFPP Jawa-5#1: 1.000 MW (2018)#2: 1.000 MW (2019)
AMPLA
CILEGON
M.TAWAR
CIBATU
CIRATA
SAGULING
BEKASI
TASIKMALAYA
BANDUNG SELATAN
UNGARAN
T.JATI B
PEDAN
KEDIRI PAITON
GRATI
KRIAN
GRESIK
NEW SURALAYA
NGIMBANG
CAWANG
SURALAYA
KEMBANGAN
BANGIL
KESUGIHAN/RAWALO
CILACAP
GANDUL
TAMBUN
CAWANG-2
BANTUL
KAPAL
SURABAYA SELATAN
TANDESCIGERELENG
ADIPALA
DEPOK
HVDC
CIBINONG
M.KARANG PRIOK
CIBATU-2
CISOKAN
INDRAMAYU
UJUNGBERUNG
MANDIRANCAN
JAWA-1 JAWA-3
T.JATI A
MATENGGENG
PEMALANG
JATENG
DURIKOSAMBI
NEW BLRJALENGKONG
BANTEN
HVDC
BOGOR-X
CFPP Jawa-3#1: 660 MW (2017)#2: 660 MW (2018)
CFPP Cirebon (SC)#1: 660 MW (2012)
CFPP Paiton (SC)#3: 815 MW (2012)
CO2 Reduction Effect By Introduction of CCT
16
Source: JICA CCT Study, October 2012
Economical Evaluation of CCT
17
Sub Critical SC USC IGCC Coal Price 4,200 kCal/kg ($/ton)
Total Gross Power 1,000 MW 1,000 MW
1,000 MW 1,000 MW Y2011 Y2020
Plant Efficiency 36% 39% 42% 49% 53.8 107.6Construction Cost 100%
(Base)106.5% 108.5% 130%
Coal Consumption 100% (Base)
90% 84% 75%
O&M Cost 2.5% 3% 3% 3%
Source: JICA CCT Study, October 2012, with updated projects and schedule by PLN
Future Development of Coal Fired PP
18
1. Fuel Supply
• The type of coal that would be used more in electricity generation Indonesia
is low rank coal, due to plentiful availability in Kalimantan and Sumatera and
more economical, thus securing more stable supply, whilst most high rank
coal would be exported to global market.
2. Boiler Type :
• CFB: for small to medium scale CFPP outside Java-Bali system.
• USC: should be introduced for next new CFPP project in Java-Bali system
(2017).
3. Further Development
• Coal gasification – Syngas:
• IGCC: will be introduced around 2025, considering the development
situation in the world.
• CCS: in the early stage of development, and will reduce a significant
amount of CO2 emission. Will be introduced in Indonesia maybe after 2025.
19