cutting costs & changing mindsets (3)

Upload: abilasha-vediappan

Post on 05-Apr-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 Cutting Costs & Changing Mindsets (3)

    1/15

    Cutting costs and changingmindsets

    Case 8.1 Pg 129-131

  • 7/31/2019 Cutting Costs & Changing Mindsets (3)

    2/15

    CUTTING COSTS & CHANGINGMINDSETS

    Together we can was thenew maxim being heardacross RanbaxyLaboratories Limited,Indias largestpharmaceutical company.

    The promise was mademore than a year backwhen project CRUSOE was

    born. Project Crusoe standsfor Creatively Releasing,Unleashing SubstantialOperating Efficiencies.

  • 7/31/2019 Cutting Costs & Changing Mindsets (3)

    3/15

    Why was it started?1. It was started as a cost

    efficiency exercise. Butsoon positioned itself asa change enablingHuman resourceexercise in the company.

    2. It was initiated forreal-business benefits.

    3. It was started foridentifying those sectors

    that needed a re-lookand enable a positivechange in these sectors.

  • 7/31/2019 Cutting Costs & Changing Mindsets (3)

    4/15

    How was project Crusoeimplemented ?

    1. It was implemented in nine phases.2. Each phase incorporating four projects over a period

    of3 months.

    3. The project will concentrate on various important

    areas such as:

    #raw material sourcing.

    # marketing.

    #distribution.#research and development.

    # packaging.

    #ads and promotions .

  • 7/31/2019 Cutting Costs & Changing Mindsets (3)

    5/15

    How was project Crusoeimplemented ?

    4. The director of the company was appointed as theteamleader for the project on a full time basis.

    5. The project Crusoe consisted of many waves, eachconcentrating on different sectors.

    6. Each wave comprised of20-25 executive members withthe youngest member aged 21 and the oldest aged 50.

    7. Each Crusoe crusader was responsible for taking theownership of the project and its implementation.

  • 7/31/2019 Cutting Costs & Changing Mindsets (3)

    6/15

    Works of the team

    1. Challenge everything that

    was accepted as norm.2. The members must

    benchmark, question,examine(ponder), suggestand implement better

    systems within limited time.3. The team members had

    weekly reviews and debatesand constant brainstorminggenerating many new ideaswhich gave birth to conceptsthat could be practically

    applied to business & notjust discussed and shelved.

  • 7/31/2019 Cutting Costs & Changing Mindsets (3)

    7/15

    The Initial step1. Theoretical concepts and mental suggestions were

    experimented with new technologies such as online

    forward auction and reverse auction .

    Forward auction:

    The seller puts an item up for sale and Multiple buyers bid for the item,

    and one or more of the highest bidders buys the goods at a price

    determined at the conclusion of the bidding.

    Reverse auction:

    A buyer puts a contract out for bid and multiple sellers offer bids on

    the item, competing to offer the lowest price that meets all of the

    specifications of the bid.

    RESULT:

    It re-affirmed that e-business delivers cost reduction,

    efficiency and also improves velocity of transactions,

    delivering improved performance. It was proved that e

    sourcing produced 7-8% savings in the cost incurred. Shortcut to3898283_f520(1).jpg.lnk

  • 7/31/2019 Cutting Costs & Changing Mindsets (3)

    8/15

    The Initial step

    2. The company also realizedthat cutting down cost

    can be effected if there is

    a cultural change within

    the business. Project

    Crusoe is infusing a better

    culture cause when there

    is no pain (no downsizing

    of employeesinvolved),

    everybody is enthusiasticto give their best for their

    company.

  • 7/31/2019 Cutting Costs & Changing Mindsets (3)

    9/15

    Functions of the waves The core focus of each wave was

    to challenge the cost of businessoperation.

    While some waves focused on

    bringing about cultural change in

    the way of doing business.

    Some other waves moved a step

    ahead and they brought a change

    in the business models.

    Four such waves identified 5

    different areas of expenditure.

    425 projects were identified

    which were likely to generate a

    savings up to 10%.

  • 7/31/2019 Cutting Costs & Changing Mindsets (3)

    10/15

    Implementation1. The 1st step of

    implementation started atemployee level, so as to

    change their mindsets and

    attitudes towards the various

    changes brought in by the

    projects results.

    2. The initiative of this was

    taken by Power & Fuel team

    who created innovative

    postersto communicate toevery Ranbaxian, the

    benefits of saving power

    and fuel, even in their

    personal lives.

  • 7/31/2019 Cutting Costs & Changing Mindsets (3)

    11/15

    Success of the project in the short

    run

    Short Run:The short run is a period oftime in which the quantity ofat least one input is fixed and

    the quantities of the otherinputs can be varied. And alsothe variations in outputs arepossible only to a certain limit.

    # The success of this project in

    short run is very minimal.Though project Crusoe wouldnot be a complete failure ithas only negative successduring the short run.

  • 7/31/2019 Cutting Costs & Changing Mindsets (3)

    12/15

    Success of the project in the shortrun

    1. The team CRUSOE has identified 425 projects which are

    likely to generate 10% savings. But it is not possible to

    complete all these projects within a short span of time.

    2. The cultural changes at the organisation could not be

    put to practice in a very less time.

    3. The change in the business models and strategies

    cannot be effected in a short term period itself.

    4. The Project Crusoe also experimented with new

    technologies and obtained satisfying results out of it. Butthe level of technology is assumed to remain unchanged

    in a short run.

  • 7/31/2019 Cutting Costs & Changing Mindsets (3)

    13/15

    Success of the project in thelong run

    Long Run:

    The long run is a period oftime in which the quantitiesof all inputs can be varied.Hence in long run all thecost are variable and noneare fixed.

    # The project Crusoe in a longterm would have achievedmost of the expected effect,hence it has more chancesof being a success in thelong run.

  • 7/31/2019 Cutting Costs & Changing Mindsets (3)

    14/15

    Success of the project in thelong run

    1. Any majorcultural changes to be effected in an organization can be

    achieved only by a long term project.

    2. Project Crusoe experimented with new technologies and obtained

    satisfying results through it . Such technologiesalong with the

    methods involved in it can be implemented only in a long term

    project.3. A large expenditure for the assets, land and man power can be

    provided only in the case of a long term project.

    4. Initiating multiple projects in different stages and making them

    successful is only possible during a long run.

    5. The testing methods involved in proceeding with the project iscomparatively cheaper in a long run project than a short run

    project.

    In order to bring even a project of this level into existence it requires a

    long running company which has already stabilized itself in the market.

  • 7/31/2019 Cutting Costs & Changing Mindsets (3)

    15/15

    Can

    we help you ?!