EuCARD-MIS-2013-009 European Coordination for Accelerator Research and Development PUBLICATION D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results has received funding from the European Commission under the FP7 Research Infrastructures project EuCARD, grant agreement no. 227579. This work is part of EuCARD Work Package 1: Management. The electronic version of this EuCARD Publication is available via the EuCARD web site <http://cern.ch/eucard> or on the CERN Document Server at the following URL : <http://cds.cern.ch/record/1710582 EuCARD-MIS-2013-009

Upload: others

Post on 24-Sep-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

EuCARD-MIS-2013-009

European Coordination for Accelerator Research and Development

PUBLICATION

D3.1: 3rd periodic EuCARD report -public version

Koutchouk, J (CERN) et al

20 June 2014

The research leading to these results has received funding from the European Commissionunder the FP7 Research Infrastructures project EuCARD, grant agreement no. 227579.

This work is part of EuCARD Work Package 1: Management.

The electronic version of this EuCARD Publication is available via the EuCARD web site<http://cern.ch/eucard> or on the CERN Document Server at the following URL :

<http://cds.cern.ch/record/1710582

EuCARD-MIS-2013-009

Page 2: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

Copyright © EuCARD Consortium, 2013

Grant Agreement 227579 RESTRICTED 1 / 123

Grant Agreement No: 227579

EuCARD European Coordination for Accelerator Research and Development

Seventh Framework Programme, Capaci t ies Spec i f ic Programme, Research In f rast ructu res,

Combinat ion of Col laborat ive Pro ject and Coord inat ion and Support Act ion

DELIVERABLE REPORT

3RD PERIODIC EUCARD REPORT

DELIVERABLE: D1.3

Document identifier: EuCARD-Period_3_Report_v10

Due date of deliverable: End of Month 54 (September 2013)

Report release date: 15/10/2013

Work package: WP1 Project Management

Lead beneficiary: CERN

Document status: Final

Abstract:

A report of the work performed during period 3 of the EuCARD project (the final 16 months -

1 April 2012 until 31 July 2013) including the work progress and the use of the resources.

Page 3: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 2 / 123

Copyright notice:

Copyright © EuCARD Consortium, 2013

For more information on EuCARD, its partners and contributors please see www.cern.ch/EuCARD

The European Coordination for Accelerator Research and Development (EuCARD) is a project co-funded by the

European Commission in its 7th Framework Programme under the Grant Agreement no 227579. EuCARD began

in April 2009 and will run for 4 years.

The information contained in this document reflects only the author’s views and the Community is not liable for

any use that may be made of the information contained therein.

This document is restricted due to the financial data, a publicly available version will be available from the

EuCARD website via http://cern.ch/EuCARD/about/results/deliverables/

Delivery Slip

Name Partner Date

Authored by J.P. Koutchouk, the EuCARD work package and

task coordinators, S. Stavrev, A. Szeberenyi, C.

Brandt.

CERN 10/09/2013

Edited by A. Szeberenyi CERN 09/10/2013

Reviewed by J.P. Koutchouk, S. Stavrev CERN 13/10/2013

Approved by Project Coordinator and WP Coordinators 14/10/2013

Page 4: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

Copyright © EuCARD Consortium, 2013

Grant Agreement 227579 RESTRICTED 3 / 123

PROJECT PERIODIC REPORT

Grant Agreement number: 227579

Project acronym: EuCARD

Project title: European Coordination for Accelerator Research and

Development

Funding Scheme: Seventh Framework Programme, Capacities Specific

Programme, Research Infrastructures, Combination of

Collaborative Project and Coordination and Support Action

Date of latest version of Annex 1 against which assessment will be made:

20/02/2013

Periodic report: 1st □ 2nd □ 3rd □

Period covered: From Month 37 (April 2012) to Month 52 (July 2013)

Name, title and organisation of the scientific representative of the project's coordinator:

Dr. Jean-Pierre Koutchouk, DG Project Office, CERN

Tel: +41 22 767 3230

Fax: +41 22 767 6595

Email: [email protected]

Project web site address: http://cern.ch/eucard

Page 5: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 4 / 123

Declaration by the scientific representative of the project coordinator

I, as scientific representative of the coordinator of this project and in line with the obligations as

stated in Article II.2.3 of the Grant Agreement declare that:

The attached periodic report represents an accurate description of the work carried out

in this project for this reporting period;

The project (tick as appropriate):

□ has fully achieved its objectives and technical goals for the period;

□ has achieved most of its objectives and technical goals for the period with

relatively minor deviations;

□ has failed to achieve critical objectives and/or is not at all on schedule.

The public website, if applicable

□ is up to date

□ is not up to date

To my best knowledge, the financial statements which are being submitted as part of this

report are in line with the actual work carried out and are consistent with the report on

the resources used for the project (section 3.4) and if applicable with the certificate on

financial statement.

All beneficiaries, in particular non-profit public bodies, secondary and higher education

establishments, research organisations and SMEs, have declared to have verified their

legal status. Any changes have been reported under section 3.2.3 (Project Management)

in accordance with Article II.3.f of the Grant Agreement.

Name of scientific representative of the Coordinator: ...........Jean-Pierre Koutchouk...................

Date: .....15..../ ....10....../ ...2013....

Signature of scientific representative of the Coordinator: ........ .........

Page 6: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 5 / 123

Executive Summary

The 38 partners of EuCARD (European Coordination for Accelerator Research and

Development) are engaged in development of state-of-the-art technologies to upgrade major

particle accelerators in Europe. During the final 12 months, the project has achieved most of its

objectives and technical goals, and published some 150 scientific contributions.

WP2-DCO maintained the project web site with latest project related news, has collected over

500 publications in the publication database. As a result of an initiative over P2, we extended the

scope of the quarterly project newsletter and created a combined newsletter of 4 other projects,

enhancing their synergies. 6 issues have been published during the period and 7 additional

accelerator science monographs. WP3 (neutrino accelerator facilities) has produced reference

documents on scientific policies with respect to research infrastructures that were timely

submitted to the European HEP Strategy sessions. WP4 accelerator networks organized or co-

organized 25 well-attended workshops in various fields of accelerator sciences with concrete

outcome. Two major synthesis documents were produced, defining possible strategies for the

future of frontier accelerators and pointing to the required R&D.

The HiRadMat irradiation facility at CERN (WP5) successfully operated during the beam run

in 2012 and hosted all 7 scheduled TA experiments for data taking. 102.6 access units have been

delivered in P3. Under WP6, the TA activities continued successfully with 1107.7 access units

delivered. Principal goals of the user groups were the development of high precision diagnostics,

which proved successful.

The Joint Research Activities are the project’s backbone and enable or reinforce tight links

between European laboratories, institutes and universities, as well as two SMEs. Achievement

highlights include:

- WP7 (High Field Magnets): to mitigate the high risk of this novel Nb3Sn high field magnet

model development, additional steps have been introduced, leading to a revised calendar. The

progress accomplished gives much hope of final success: The mechanical structure of the magnet

has been completed and tested at LN2 temperature, the coil tooling has been delivered and a test

coil with Cu conductor manufactured. Nb3Sn strand for one magnet is delivered, the cable

designed, showing less than 5% degradation, well within the specification.

The HTS insert magnet components are procured and the YBCO conductor delivery expected

by September. A test coil was constructed and will be tested in September. The insert will be

finished end 2013.

The HTS link was cabled with two cabling machines and is now finished.

Two helical undulators were built and one was tested at LASA where problems indicated the

need for important design modifications.

For the support task the design and construction of all the cryostats and tooling for the irradiations

and sample tests have been completed. The irradiation of all the electrical samples and half of

the mechanical samples has been completed and some conclusions on the suitability of insulation

materials have been formulated. The thermal studies have been completed and HeII cooling

models were produced.

- WP8 (Collimation and Materials) has complemented the theoretical studies on new materials

by irradiation tests at the HiRadMat@CERN facility, with very promising results on Metal-

Diamond and Metal-Graphite composites. An important outcome of this activity has been the

creation of a multi-disciplinary collaboration, the activity of which will continue. In addition to

collimators and cryo-catchers already completed in P2 the optional test of crystal collimation

was carried out, with a measured significant increase of the particle channelling.

Page 7: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 6 / 123

- WP9 (Normal Conducting Linacs) The integration challenge of the CLIC module was

exercised and its thermo-mechanical stability studied by numerical analysis and soon

experimentally after the upgrade of a dedicated test laboratory. The mechanical stabilization to

0.5 nm at 1Hz was demonstrated in an accelerator environment, validating the strategies and

equipment. The even tighter requirements for the final focus are now close to being fulfilled.

Tests in ATF2 (Japan) have allowed developing strategies and instruments for accurate beam

control; the experience gained should direct further developments to reach the accuracy required

by linear colliders. Both the electromagnetic and electro-optical phase monitors reached the goal

of an accuracy of 20 fs, suitable for the synchronization of the drive and main beams in the two-

beam accelerator concept.

- WP10 (Superconducting Radiofrequency technologies): The vertical electro-polishing setup is

completed and in use. The proton linac cavities are in the manufacturing and test process shared

between the manufacturers and the research laboratories. Delays at the manufacturers will delay

the final tests by a few months. The progress in the LHC crab cavities has exceeded the goals of

EuCARD, with the fabrication of a Nb crab cavity. The CLIC crab cavity was fabricated and the

LLRF for both developed. Good progress is achieved on magnetron sputtering, with high RRR

values, uniform films and much reduced deposition time. An EuCARD monograph was

produced on sc RF technologies, including aspects of thin films. The HOMBPM’s on the 3.8

GHz cavities was validated. Modelling and experimental studies show however that the inverse

field problem to identify cavity features from HOM signals is very difficult; nevertheless, results

obtained justify further investigations. The µTCA LLRF was finalized, installed and tested at

FLASH, already yielding a significant improvement of the field stability. Two set-ups for GaAs

cathode preparation showed contamination, and low quantum efficiency after activation. Lessons

learned allow an on-going development of a more advanced state-of-the-art preparation system.

A remarkable progress was the first FEL operation with the SRF gun at ELBE in April 2013.

The design of the automatic coupler cleaning has evolved, and the studies allow a complete

overview, including feasibility and cost.

- In WP11 (Assessment of Novel Accelerator Technologies) the final study of the crab waist

scheme applied to the LHC upgrade was completed, while additional work of the partners have

further consolidated the deliverables already provided during Period 2.

EuCARD management contributed to tightening links between leading actors in accelerator

R&D and creating sustainable European collaborations. A highlight of this activity was the

organization of the workshop “Visions for the future of accelerators”, combined with the

concluding EuCARD annual meeting and EuCARD2 kick-off meeting, attended by more than

180 experts from all around the world.

Page 8: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 7 / 123

TABLE OF CONTENTS

1. PUBLISHABLE SUMMARY ................................................................................................................. 8

2. CORE OF THE REPORT FOR THE PERIOD: PROJECT OBJECTIVES, WORK PROGRESS

AND ACHIEVEMENTS, PROJECT MANAGEMENT ............................................................................ 13

2.1 PROJECT OBJECTIVES FOR THE PERIOD ............................................................................................. 13 2.2 WORK PROGRESS AND ACHIEVEMENTS DURING THE PERIOD ............................................................ 14

1.1.1. WP1: Project management ............................................................................................................ 14 1.1.2. WP2: Dissemination, Communication and Outreach (DCO) ........................................................ 14 1.1.3. WP3: Structuring the accelerator neutrino community (NEu2012) .............................................. 24 1.1.4. WP4: Accelerator Science Networks (AccNet) .............................................................................. 28 1.1.5. WP5: Transnational access HiRadMat@SPS ............................................................................... 34 1.1.6. WP6: Transnational access MICE ................................................................................................ 37 1.1.7. WP7: High Field Magnets (HFM) ................................................................................................. 41 1.1.8. WP8: Collimators and materials (ColMat) ................................................................................... 51 1.1.9. WP9: Technology for normal conducting linear accelerators (NcLinac) ..................................... 54 1.1.10. WP10: superconducting RF Technology for proton accelerators and electron linear accelerators

(SRF) ............................................................................................................................................. 67 1.1.11. WP11: assessment of novel accelerator concepts (ANAC) ............................................................ 82

2.3 PROJECT MANAGEMENT DURING THE PERIOD ................................................................................... 87 1.1.1. Consortium management tasks and achievements ......................................................................... 87 1.1.2. Budget adjustments ........................................................................................................................ 87 1.1.3. Problems and solutions ................................................................................................................. 88 1.1.4. Changes in the consortium and/or legal status of beneficiaries .................................................... 88 1.1.5. Project meetings ............................................................................................................................ 88 1.1.6. Project status ................................................................................................................................. 88 1.1.7. Communication.............................................................................................................................. 90 1.1.8. Coordination of activities between beneficiaries and synergies with other projects ..................... 90

3. DELIVERABLES AND MILESTONES TABLES ............................................................................. 92

3.1 DELIVERABLES ................................................................................................................................ 92 3.2 MILESTONES .................................................................................................................................. 101

4. EXPLANATION OF THE USE OF THE RESOURCES ... ERROR! BOOKMARK NOT DEFINED.

4.1 OVERALL USE OF MAN-POWER AND BUDGET FOR PERIOD 3........ ERROR! BOOKMARK NOT DEFINED. 4.2 OVERALL USE OF RESOURCES BY THE CONSOTRIUM FOR THE FULL PROJECT DURATION (M1-

M52) ERROR! BOOKMARK NOT DEFINED. 4.3 EXPLANATION OF THE USE OF RESOURCES REPORTED ON THE FORMS CERROR! BOOKMARK NOT

DEFINED.

5. FINANCIAL STATEMENTS – FORM C AND SUMMARY FINANCIAL REPORT ....... ERROR!

BOOKMARK NOT DEFINED.

6. ANNEX: LIST OF PUBLICATIONS DURING PERIOD 3 ............................................................ 113

Page 9: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 8 / 123

1. PUBLISHABLE SUMMARY

European Coordination for Accelerator Research and Development

The EuCARD project gathers 38 European partners engaged in state-of the-art technologies to

upgrade major research accelerators. The main components and objectives of the project are:

Networks, focused on communication and dissemination, neutrino physics facilities,

performance of hadron colliders and accelerators, and RF technologies, resulting in 40

leading laboratories worldwide being associated with EuCARD.

Transnational access facilities, offering precision beams and muon cooling setup, and pulsed

irradiation for material testing.

Joint research: 21 R&D tasks grouped under the following themes:

o Investigating the feasibility of new superconducting magnets and electrical links

using Nb3Sn and/or High Temperature Superconductors.

o Investigating the gradient limits for radiofrequency (RF) accelerating structures,

whether normal or superconducting, together with specific issues of linear colliders

such as extreme geometrical stabilization.

o Developing more robust collimators for the protection of accelerators in operational

and exceptional conditions.

o Supporting investigations on novel accelerator concepts, such as crab waist crossing,

fixed field alternating gradient and plasma wave accelerators.

The EuCARD project has fulfilled the vast majority of its

contractual goals, and in some instances of added goals

liable to reinforce the community. The TA’s have

delivered their access units, the NA’s have strongly

stimulated the community and the JRA’s fulfilled its

deliverables with few exceptions: all 63 deliverables are

delivered. One high risk deliverable gave account on the

progress made and of the planned calendar for completion

(1.5 year delay).

The number of

peered-reviewed

journal

publications

peaks during this

P3 period to reach close to one per task.

The communication network (WP2-DCO) has

regularly maintained the project website, provided

support for the Work Packages for using the Intranet and

the CDS publication database. The public website was

further developed to ensure that the JRA’s websites are

linked to the administrative and technical databases and

Figure 1: Deliverables

Figure 2: Accelerating News

Page 10: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 9 / 123

kept archived for the future, especially for the follow-up project, EuCARD-2. The number of

publications has reached the impressive number of 500 and over. The number of PhDs resulting

from the project has also reached 46 during the lifetime of the project and a few are still in

progress. The role of Ph.D. students’ involvement in EuCARD realization is very important and

the contributions are clearly visible in the project final achievements.

The outreach section of the website was also maintained. The quarterly project newsletter has

been replaced with the Accelerating News which extended the scope of the distribution with

more than 1000 subscribers (status on 24 July: 1046). During the period 7 additional volumes

were published under the peer-reviewed Editorial series of accelerator science monographs,

therefore reaching 18 volumes. EuCARD results and developments were reported internationally

at numerable professional conferences in Europe and outside.

The WP3-NEu2012 has finalized three strategy documents defining roadmaps for existing and

future neutrino facilities. An important event, the second EU Neutrino Strategy Workshop was

organized in May 2012, attended by more than 135 neutrino physicists, where the roadmaps were

discussed and endorsed, and submitted to the European Strategy for PP Symposium in Krakow

in July 2012. During this period, existing results came from existing facilities, reassuring the

importance of this branch of HEP, but challenges emerged for the future, with the conclusions

of the EUROnu costing report. Bringing the European and world community together becomes

even more important to face such challenges.

Over the reporting period, 25 workshops, mini-workshops and working meetings were

organized or co-organized by the accelerator networks (WP4-AccNet). Topics addressed

included quench behaviour of superconducting magnets, optics corrections, crab cavities, and

electron-cloud measurements, modeling and mitigation; design parameters for future circular

e+e- or hadron collider Higgs factories and a long-term strategy for high-energy frontier

accelerators; laser-system and FEL options for a future Higgs factory based on a recirculating

linac “SAPPHiRE”; solid-state amplifiers, low-level RF for SC linacs, and RF costing

techniques; and coordinating the plasma-

accelerators community with the purpose of

transiting from demonstrations of principle

to concrete accelerator projects. These

events have attracted world experts and

generated concrete results. A significant

number of expert exchanges have been

supported, including from non-EU

countries. Collaborations of European

accelerator institutes with the European

Space Agency and its partners, with several

Mexican institutes, and with a number of key

universities in Japan (Hiroshima, Kyoto, Tohoku) have been stimulated.

The open access facility HiRadMat@SPS (WP5-TA) successfully operated during the CERN

beam run in 2012, with 7 experiments having completed the data taking. These first experiments

included candidate materials and prototype assemblies of LHC collimators foreseen to operate

at the ultimate LHC beam powers, experiments on vacuum windows, detector calibrations and

target material options for high power proton beam applications. 102.6 access units have been

delivered in P3.

Under WP6, the TA activities continued successfully with 1107.7 access units delivered.

Principal goals of the user groups were the development of high precision diagnostics. The

Figure 3: A possible long-term strategy for High

Energy Physics, emerging from the WP4 AccNet

studies and workshops

PSB PS (0.6 km)

SPS (6.9 km)

LHC (26.7 km)

TLEP (80-100 km,e+e-, up to~350 GeV c.m.)

VHE-LHC (pp, up to 100 TeV c.m.)

LEP3(e+e-, 240 GeV c.m.)

& e (120 GeV) – p (7, 16 & 50 TeV) collisions ([(V)HE-]TLHeC)

HE-LHC (33 TeV)

same detectors!?

Page 11: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 10 / 123

performance and operation of Time-Of-Flight counters has been one of the principal goals of the

TA-supported groups from Bulgaria, Italy and Switzerland. The TOF counters have been

essential both for identification of the beam particle and for momentum measurement. Thanks

to their outstanding performance, it has proved to be possible to use these counters to measure

the momentum of single muons with a resolution of better than 4 MeV/c and systematic error of

< 3 MeV/c. Following earlier tests, the Electron Muon Ranger (EMR) detector was completed,

providing final results on the pion contamination in the muon beam. The TA has in addition

allowed fruitful exchange of information and experience among users.

WP7 (High Field Magnets): to mitigate the high risk of this novel Nb3Sn high field magnet

model development, additional steps have been introduced, leading to a revised calendar. The

mechanical structure of the magnet has been

completed and tested at LN2 temperature, the

coil tooling has been delivered and a test coil

with Cu conductor manufactured. Nb3Sn

strand for one magnet is delivered, the cable

designed, showing less than 5% degradation,

well within the specification.

The HTS insert magnet components are

procured and the YBCO conductor being

delivered. A test coil was constructed and is

being tested. The insert will be finished by end

of 2013.

For the HTS link two cabling machines were

and used. The HTS link construction is

finished.

Two helical undulators were built and one was

tested at LASA where problems indicated the

need for important design modifications.

For the support task the design and construction of all the cryostats and tooling for the irradiations

and sample tests have been completed. The irradiation of all the electrical samples and half of

the mechanical samples has been completed and conclusions on the suitability of insulation

materials have been formulated. The thermal studies have

been completed and HeII cooling models were produced.

WP8-Collimation and Materials managed to finish its main

deliverables ahead of schedule. In this reporting period the

emphasis was the investigation and characterisation of novel

materials for accelerator and collimator applications.

Previously irradiated samples where characterised.

Irradiation tests with novel materials could be done at GSI

and the HighRadMat facility established within the EuCARD

framework. The successful tests lead to the use of these

materials in test collimators for the LHC even beyond the

scope of this project.

Figure 4: Finished HFM structure with dummy Al

coil

Figure 5: Cu-Diamond composite

material sample after irradiation with

144 bunches from the SPS

Page 12: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 11 / 123

WP9-NCLinac concerns a number of studies relevant for Linear Colliders (LC) presently

considered as future energy frontier

machines. Focused on the Compact Linear

Collider (CLIC) study it treats high-gradient

normal-conducting accelerating structures, in

particular their integration of these structures

in the so-called two-beam module and the

resulting limitations and constraints

concerning RF power and phase, breakdown,

higher-order modes, cooling, vacuum,

mechanical tolerances, alignment and

stabilisation and the overall integration. The

stabilisation and alignment question

addressed were treated using a quadrupole

mock-up, which could be successfully stabilized to the required nanometre level in a real

accelerator environment. These results are relevant for both normal-conducting and

superconducting RF based LCs. Also the solutions studied for the demanding beam diagnostics

for a beam delivery system (BPMs and LW), which were implemented and thoroughly tested at

ATF2 and PETRA3, are significant independent of the chosen technology. The exact control of

beam phase to precisions of below 0.01° (of 20 fs) is equally a problem for many future

accelerators, including linear colliders and light sources, but for large linacs it becomes even

more demanding, since phase information from very distant location has to be compared.

NCLinac has advanced this field both for the phase pick-ups as well as for the synchronisation

over long distances.

WP10 (Superconducting Radiofrequency technologies): The vertical electro-polishing setup

is completed and in use.

The proton linac cavities

are in the manufacturing

and test process shared

between the

manufacturers and the

research laboratories.

Delays at the

manufacturers will delay

the final tests by a few

months. The progress in

the LHC crab cavities has exceeded the goals of EuCARD, with the fabrication of a Nb crab

cavity. The CLIC crab cavity was fabricated and the LLRF for LHC and CLIC developed. Good

progress is achieved on magnetron sputtering, with high RRR values, uniform films and much

reduced deposition time. An EuCARD monograph was produced on sc RF technologies,

including aspects of thin films. The HOMBPM’s on the 3.8 GHz cavities was validated.

Modelling and experimental studies show however that, while the beam position can be

accurately extracted, the inverse field problem to identify cavity features from HOM signals is

very difficult; nevertheless, results obtained justify further investigations. The µTCA LLRF was

finalized, installed and tested at FLASH, already yielding a significant improvement of the field

stability. Two set-ups for GaAs cathode preparation showed contamination, and low quantum

efficiency after activation. Lessons learned allow an on-going development of a more advanced

Figure 7 a): β=0.65 bare cavity ready for

field flatness tuning at IPN Orsay

Figure 7 b): µTCA RadFETs

dosimeters for FLASH, DESY

Figure 6: Simulation of the creation of a protrusion

from a void due to stress

Page 13: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 12 / 123

state-of-the-art preparation system. A remarkable progress was the first FEL operation with the

SRF gun at ELBE in April 2013. The design of the automatic coupler cleaning has evolved, and

the studies allow a complete overview, including feasibility and cost.

WP11-ANAC (Assessment of Novel Accelerator Technologies) has provided its last

deliverable: a new concept for the LHC luminosity upgrade, based on flat beams, large Piwinski

angle and crab-waist, inspired by the DAΦNE upgrade, has been shown, quite unexpectedly, to

open new strategies to reach the goal of the LHC upgrade. This new approach requires further

studies to increase the particle stability. Non-

EuCARD work continuing the other tasks of

WP11 (DAΦNE, EMMA and emittance of

beams accelerated by laser-plasma) has further

consolidated the already provided EuCARD

deliverables.

EuCARD

management, beyond running the project, has continued its contribution to tightening links in

the accelerator community and creating sustainable collaborations. The concluding project

meeting was associated to a EuCARD workshop on visions for the future of accelerators and to

the kick-off meeting of EuCARD2, thereby drawing perspective for the immediate and farther

futures.

Figure 8: KLOE2 upgraded IR, LNF, INFN

Figure 9: Final meeting and

workshop

Page 14: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 13 / 123

2. CORE OF THE REPORT FOR THE PERIOD: PROJECT OBJECTIVES, WORK PROGRESS AND ACHIEVEMENTS, PROJECT MANAGEMENT

2.1 PROJECT OBJECTIVES FOR THE PERIOD

In this final period of the project, the contractual objectives include the largest fraction of the

deliverables, as most tasks have the full project duration, while some shorter tasks were late. The

number of milestones naturally decreases, and many are lumped with their corresponding

deliverables.

The management (WP1) objectives have been mainly two-fold: i) create optimal conditions to

favour a successful termination both for the S/T studies and for a major reporting exercise: the

P3 periodic report (D1.3), over 40 deliverable reports for review at a learned journal level and

the final report (D1.4); ii) keep the momentum of the collaboration by attractive project events:

the third annual meeting (M1.4) and a conclusive meeting analysing the results and offering

perspectives (M1.5).

With a series of ambitious communication tools put in place in Periods 1 and 2 (web site,

publication portal, newsletters and monographs), the goals of the dissemination,

communication and outreach network (WP2) are to consolidate them and organize their

transmission to either TIARA or EuCARD2. Presentations on communication aspects, achieved

efficiency and future plans were the goals of the status reviews in two Annual Meetings (MS4,

MS5), with in view the final report summarizing the strategies and results (D2.1.1). The

deliverable foreseen on the use and dissemination of foreground turns out to be strictly redundant

with a chapter of the final report and will refer to it (D2.2.2).

The main goals of the scientific networks (WP3 and WP4) during this period are to finalize and

complete their activities: for WP3, this period is a key with the organization of

meetings/workshops in view of the production of three strategy documents that must meet the

consensus of the community: D3.1.2, D3.2.1 and D3.3.1 and serve as input to the update of the

European HEP strategy. For WP4 AccNet, the goal has been to actively continue the activities

of the three networks (M4.1.4, M4.2.4, M4.3.4) and prepare important deliverables summarizing

the network activities and results, putting forward the specific added value produced (D4.1.2,

D4.2.2, D4.3.3).

Two facilities are open to Trans-National access: the HiRadMat@CERN (WP5) started open

access in the second part of P2, continuing through the largest part of P3. As to MICE@STFC

Coordinator: CERN

Partners: AIT, RHP (AT); EPFL, PSI, UNIGE (CH); HZB, DESY, BHTS, FZD, KIT-G, GSI, UROS (DE);

CIEMAT, CSIC (ES); TUT, UH (FI); CEA, CNRS, UJF (FR); Columbus, INFN, POLITO (IT); UM (MT); IFJ

PAN, IPJ, PWR, TUL, WUT (PL); BINP, RRC KI (RU); UU (SE); HUD, RHUL, SOTON, STFC, ULANC,

UNIMAN, UOXF-DL (UK).

Web site: http://www.cern.ch/EuCARD/

Page 15: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 14 / 123

(WP6), which already had fulfilled its contractual obligation, the goal was to continue the open

access thanks to savings on EC resources and support from the STFC.

For most JRA tasks (WP7-11), the goal of task 1 of each WP has been to follow-up progress,

favouring technical exchanges by WP meetings, review meetings, or coordinator visits.

Reporting is an important aspect of these tasks. A number of milestones were attached to these

activities: M7.1.3&4, M8.1.3&4, M9.1.3&4, M10.1.3&4, except for WP11 that essentially

reached completion.

For WP7 (High Field Magnets), an essential goal is to reassess, with the support of its advisory

committee, the HFM program, schedule and take the steps to organize its full completion planned

after the EuCARD termination. All deliverables related to the model (studies and prototype) are

to be delivered: D7.2.1, D7.2.2, D7.2.3 and D7.3.1 . The WP will conclude as well on the HTS

insert fabrication (D7.4.1), on the construction of a 20m HTS link (D7.5.1) and on a prototype

of a Nb3Sn helical undulator (D7.6.1).

WP8 (Collimation and Materials) being ahead of schedule, it main goal in this period is the

documentation of a CERN deliverable (D8.3.1), and of the WP8 activity.

In WP9 (Normal Conducting Linacs), all milestones were met and the period objective is the

delivery of deliverables all scheduled for the project end (D9.1.1, D9.2.1, D9.2.2, D9.3.1, D9.3.2,

D9.4.1, D9.4.2, D9.5.1, D9.5.2). These deliverables include key aspects of the CLIC collider and

of common issues for ILC and CLIC colliders (RF cavities, geometric stabilization, ultrafast

synchronization, handling of very low emittance beams).

WP10 (Superconducting RF) is the largest WP in terms of number of tasks and deliverables,

funding and spectrum of research topics. Most of its milestones were met in the preceding period,

and all its deliverables except one are to be delivered during P3: D10.1.1 (data handling); D10.2.1

(super-conducting elliptical proton cavities); D10.3.1&2&3 (LHC and CLIC crab cavities,

LLRF for both); D10.4.2&3&4 (aspects of thin film cavities); D10.5.1&2 (use of HOM signals

as beam and cavity diagnostics; D10.6.1 (advanced LLRF for FLASH); D10.7.2 (higher yield

photocathodes); D10.8.1 (automated coupler processing).

WP11 (Assessment of Novel Accelerator Concepts): All other objectives having been met in

Period 2, the only deliverable remaining is D11.2.2.

These objectives of Annex 1 have been complemented by additional objectives in the interest of

the project and to consolidate the accelerator R&D community. They are discussed in the

description of the work progress and the management results.

2.2 WORK PROGRESS AND ACHIEVEMENTS DURING THE PERIOD

In the following text, estimates of the use of resources are given according to the following scale:

++ : more than 140 %

+ : between 110% and 140%

= : between 90% and 110%

- : between 60% and 90%

-- : less than 60%

They are made with respect to the estimated actual needs to produce the deliverables. This section

contains global information about the use of resources. For more detailed information please

refer to Section 2.3.

Page 16: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 15 / 123

1.1.1. WP1: Project management

Please refer to Section 2.3.

1.1.2. WP2: Dissemination, Communication and Outreach (DCO)

The mandate of the Dissemination, Communication and Outreach (DCO) Work Package is to

establish and maintain efficient communication inside the consortium and enhance the

dissemination and outreach outside the consortium towards the scientific community and

beyond. The WP includes two tasks:

Task WP2.1: Coordination and communication,

Task WP2.2: Dissemination and Outreach

1.1.2.1. Task WP2.1: DCO Coordination and communication

Progress towards objectives

The main objectives have been to ensure an effective flow of information within all the Work

Packages, between WP2 and the Management and throughout the whole project. In this period

the DCO team organized 3 face-to-face meetings and 1 video meetings of the DCO team.

The DCO deputy coordinator is also an active member of project coordination meetings in order

to report DCO matters to WP1 Project Management. A network of WP DCO liaisons was

continued, to maintain a clear, two-way communication channel between WP2 and other WPs.

Synergies with other related accelerator projects were further developed and formalized in

Period 3 with the launch of the joined newsletter, Accelerating News1. Due to the newsletter,

EuCARD DCO team has combined efforts with TIARA, HiLumi LHC, EUROnu and CRISP.

For further details, see Section 1.1.7

Contractual milestones and deliverables

The deliverables due in this period (D2.2. and D2.3) have been achieved. The M9 milestone due

in this period has also been achieved.

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

WUT * *

CERN * *

1 http://www.acceleratingnews.eu/

Page 17: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 16 / 123

1.1.2.2. Task WP2.2: Dissemination and communication

Progress towards objectives

EuCARD web site

The project web site was kept up-to-date with events, news and results during P3. Additional

links were added to link the JRA WP websites directly to their administrative and technical

databases, also to archive the know-how for the future, especially for the follow-up project

EuCARD-2.

Figure 10: EuCARD website

The EuCARD website will be archived with the end of the project and visitors of the EuCARD

domain will be redirected to the EuCARD-2 website. The results of the project will be further

accessible under “EuCARD” tab on the EuCARD-2 website. A brief summary will be visible on the

most important results and know-how taken from EuCARD, additionally for more information the EuCARD website will be available under http://cern.ch/eucard-old

Page 18: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 17 / 123

Figure 11: The main results of the EuCARD project will be available from the EuCARD-2 website, under

EuCARD tab

The number of unique visitors and total number of visits heavily fluctuated throughout the

lifetime of the project with relevant peaks around the Annual meetings (April 2012, June 2013).

Figure 12: Number of visits compared to Project members

As the chart below shows, around 1/7th of the total number of visits to the web site comes from

non-partner countries, including India, Japan, Philippines, South Korea and the US.

0

200

400

600

800

1000

1200

1400

1600

Number of uniquevisitors

Total number of visits

Project Members

Page 19: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 18 / 123

Figure 13: EuCARD website visits

Outreach

WP leaders were encouraged to intensify outreach activities within Period 3. As a result, a

number of initiatives took place; the most notable are listed below:

1. The online outreach section on the EuCARD website was updated and enhanced with

educational resources for all ages (<14 years, 14-18 years, >18 years) as well as

definitions for key components of accelerators for the general public.

2. The DCO coordinator organized special EuCARD information and Accelerator

Technology sessions during professional conferences: (30th, 31st and 32nd WILGA

Symposium).All WILGA Symposium Proceedings volumes published in the SPIE Proc.

Series have covers and introduction with EuCARD logos and references. The

conferences were typically attended by 120 to 300 participants, mainly young researchers

from Poland, neighbouring countries and Europe.

Page 20: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 19 / 123

Figure 14: Front page of WILGA 2012 Proceedings volume containing the papers from EuCARD Session on

Accelerator Science and Technology; Published internationally at [spie.org]

3. Other talks on EuCARD of DCO coordinator during professional conferences, during the

P3 period:

o 3rd Polish Optical Conference, Sandomierz, 30 June – 04 July 2013; Poland, 100

participants, Information on EuCARD project;

o ELTE’2013, Electron Technology Conference, 16-20 April 2013, Ryn Castle,

Poland, 500 participants;

o 5th European Workshop on Optical Fiber Sensors; Krakow, Poland, 19-22 May

2013;

o 40th Anniversary Jubilee Conference of IEEE Poland Section; 16 November

2012, WUT, Faculty of R&IT, Warsaw; 150 participants.

o XIV Conference on Optical Fibers and Applications, TAL2012, 8-12 October

2012, Naleczow, Poland; Participants 100 persons;

o TIARA Poland Conference, Kraków, 30 October 2012; Information delivered by

prof.K.T.Pozniak; 40 partcipants;

o Xth National Symposium on Laser Techology, Swinoujscie, 24-28 September

2012; 150 participants;

4. Didactic and teaching activities at WUT during the P3.

Page 21: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 20 / 123

o Lecture on CARE, TIARA and EuCARD topics; 60H lectures with 30H

workshops per year;

o Workshops with students (Dr Maciej Linczuk) specializing in Electronics for

HEP experiments on European HEP, accelerator, and FEL technology related

projects: CARE, EuCARD, TIARA, E-XFEL, EuroNu.

o HEP Experiments and Accelerator Technology Weekly Seminars with Ph.D

students at Faculty of E&IT WUT (R.Romaniuk, K.Pozniak, W.Zabolotny) .

5. Dissemination and outreach activities combined with professional functions and

community involvements of DCO coordinator:

o Polish Academy of Sciences, Department of Technical Sciences and Committee

of Electronics and Telecommunications; annual reports on EuCARD and TIARA

work developments during General Assembly of these bodies.

o Chief Technical Organization - NOT; Association of Polish Electrical Engineers

(SEP), and affiliated with SEP – The IEEE Poland Section; the same as above;

Information about the involvement of national research communities (physicists

and engineers) in European Infrastructural Projects in September 2012 and

November 2012; in presence of key industry and academia decision makers;

o Professional Learned Associations: Polish Physical Society, Photonics Society of

Poland; as above, information about European projects, including EuCARD

during annual meetings of these learned Societies.

6. Annual Science Festival in Warsaw and Museums’ Night (May 2012, May 2013) –

presentations at booths of WUT and NCBJ the achievements of modern accelerator

technology; events predicted for wide public.

7. The project and Transnational Access opportunities were promoted with leaflets during

the ESOF event (Euroscience Open Forum 2012, Dublin, 11-15th July) by the Eurorisnet

+ Network.

Figure 15: ESOF2012 event: TNAs promotion at Eurorisnet+ booth

Page 22: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 21 / 123

Policy events and surveys

The Project Coordinator and administrative manager attended several meetings with EC officials

to discuss project related accelerator R&D topics, strategy in Horizon2020. The Coordinator also

attended and represented the project at the International Conference on Research Infrastructure

(ICRI 2012) conference. He also contributed to the “Consultation on possible topics for future

activities for integrating and opening existing national research infrastructures” issued by the EC

and initiated a coherent response from various branches of the community. The assessment of

this survey2 (published in February 2013) placed the topic of Accelerator R&D in a prominent

position.

Accelerating News (formerly EuCARD Newsletter)

During the period, the EuCARD newsletter was replaced by the Accelerating News, a

collaborative newsletter aimed at the accelerator community. The Accelerating News - first issue

was published on 24 April 2012- is a combined newsletter taking advantage of the synergies

formed between EuCARD and other accelerator projects cofunded by EC FP7. Four projects

were initially part of the newsletter: EuCARD, HiLumi LHC, TIARA and EUROnu. When the

EUROnu project finished in September 2012, the CRISP project was added to the newsletter.

The scope of the Accelerating News was extended over P3: it now covers a larger variety of

fields and targets a wider audience, also in some cases covering accelerator related topics from

life sciences. The number of subscribers rose from 800 to 1046, attesting to the success of the

new format of the newsletter. In order to further improve the Accelerating News, a survey3 was

conducted online and it received positive answers. The newsletter was also used to advertise the

EuCARD monographs, which led to a dramatic increase in orders from all around the world. The

Accelerating news will be continued under TIARA-PP and EuCARD2.

Figure 16: The six issues of the “Accelerating News”, with the first issue published 24 April 2012. The issues from

the EuCARD newsletter are still available in archives.

2 http://ec.europa.eu/research/infrastructures/pdf/final-report-CEI-2013.pdf 3 http://www.surveymonkey.com/s/SFJNCJH

Page 23: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 22 / 123

EuCARD-related Doctorates

46 Ph.D. theses were identified as associated to EuCARD during the whole duration of the

project. The WP leaders were made aware that the Ph.D. theses may be published as EuCARD

booklets. A number of Ph.D. theses related to EuCARD were published in the Monograph Series.

Due to different formal regulations concerning doctorate promotion processes at the European

universities, not all of the relevant theses were published in the Series. They were however

published by the relevant university press. Many of the project related theses are not yet finished.

They will be continued with EuCARD2.

EuCARD publication portal

A user-friendly publication portal is in operation. It has a customized interface of the existing

CERN Documentation System: the publications can be browsed against the type, kind, source

and work package. It automatically handles the needs of the refereeing system, depending on the

type of publication. As of 30 August 2013, the publications logged in the database amount to –

numbers in upper row of the table, but the increase in these numbers for P3 period are shown in

the lower row:

Table 1: Number of publications in P3 compared to the whole duration of the project

Conference

papers

Books Journal

publications

Academic

dissertations

Notes &

reports

Misc.

publications

Oral

presentations Total

250 18 76 8 50 35 76 513

43 7 22 3 15 12 17 119

This large number of publications and oral presentations continues to shows the dynamism of

the project. The management of EuCARD continuously favours open access publications and

journals.

EuCARD Monographs

Seven additional EuCARD monographs have been published in Period P3 (reaching 18 volumes

in total). The monographs are also publicly available via the CDS database. Before distributing

to the partner libraries worldwide, IP and copyright issues have been investigated properly.

Page 24: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 23 / 123

Figure 17: In Period 3, volumes 12, 13, 14, 15, 16, 17 and 18 were published:

Claire Antoine, EuCARD Monograph Series Vol.12: Materials and surface aspects in the development of SRF

niobium cavities, 2011, 130 pages

Matthew Fraser EuCARD Monograph Series Vol.13: Beam Dynamics Studies of the ISOLDE Post-Accelerator for

the High Intensity and Energy Upgrade, 2012, 318 pages

Michal Dziewiecki, EuCARD Monograph Series Vol.14: Beam Dynamics Studies of the ISOLDE Post-Accelerator

for the High Intensity and Energy Upgrade, 2012, 115 pages

Tobias Junginger, EuCARD Monograph Series Vol.15: Investigations of the Surface Resistance of

Superconducting Materials, 2012, 135 pages

Pei Zhang, EuCARD Monograph Series Vol.16: Beam Position Diagnostics with Higher Order Modes in Third

Harmonic Superconducting Accelerating Cavitie , 2013, 242 pages

Anna Wysocka-Rabin, EuCARD Monograph Series Vol.17: Advances in Conformal Radiotherapy, 2013, 158

pages

Krzysztof Czuba, EuCARD Monograph Series Vol.18: RF Phase Reference Distribution System for TESLA

Technology Based Projects, 2013, 137 pages

The distribution of the booklets, remained on stock has been transferred to the CERN Library.

Booklets can be ordered from this page. The monographs are also accessible via the publisher

web site. This is Publishing Office of Warsaw University of Technology.

http://www.wydawnictwopw.pl/index.php?s=karta&id=1143

Page 25: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 24 / 123

Figure 18: Booklet order form on CERN Library site

During the final Annual Meeting of EuCARD and kick-off meeting of EuCARD-2 the editor had

many discussions with the Conference participants concerning the support of this action, and the

interest in this sort of fast but strictly peer reviewed, and nicely printed publications, with ISBN

number. The series will be continued and the relevant discussion will also be continued within

the EuCARD2. The editor sent a few copies of full sets of these monographs to science and

technology financial decision makers with a very positive, even surprisingly positive, response.

A few meetings at the Nat. Ministry of Science and Education, and Ministry of Infrastructure

followed, with possible infrastructural consequences in the future.

DCO coordinator sent out approximately 250 copies of the monographs, separately from the

numbers of copies managed by CERN. These were sent to local libraries at around 20 universities

and the rest went to individual researchers.

Contractual milestones and deliverables: none

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

WUT * *

CERN * *

Page 26: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 25 / 123

1.1.3. WP3: Structuring the accelerator neutrino community (NEu2012)

NEu2012 offers a platform for consolidating the European neutrino community and enhancing

collaborative work and exchanges in view of delivering at the end of 2012 an agreed programme

of neutrino experiments, based on upgrades of existing infrastructures and/or on the proposal of

a new one. WP3 includes 3 tasks:

Task WP3.1: Coordination and communication

Task WP3.2: Getting the most out of existing neutrino facilities

Task WP3.3: Roadmap to the next European accelerator neutrino facility

1.1.3.1. Task WP3.1: Coordination and Communication

Progress towards objectives

The coordination of the WP activity continued by steering meetings and by frequent contacts

among coordinators. They focused on the successful organization of the third annual meeting of

the network (ie the 2nd EU Neutrino Strategy Workshop in May 2012) and on the effort to

assemble its last final road map deliverables.

Discussions with managers of projects closely related to NEu2012 (LAGUNA-LBNO, EUROnu,

IDS-NF as always and now CENF, ESS neutrinos and more) became even more frequent. The

program committee of the Strategy Workshop represents indeed all these components. This

included recently participation to the last EUROnu meeting June 2012, the most recent

LAGUNA meeting in Desy Feb 2013, the most recent IDS-NuFact meeting in RAL Apr 2013

and to the meetings of emerging proposals as NuSTORM (late March 2013) and of an ESS

powered neutrino Superbeam (May 2013).

Dissemination for WP3 remained an important area of work. WP3 steering committee members

were present in many international workshops with plenary and parallel talks confirming the

international visibility of NEU2012 and of the neutrino activities in Europe. The coordinators

were all on the program committee of the international NuFact12 workshop.

Monitoring developments in our research sector also remained very important. The sin213

reactor results in China, Korea and France in Spring 2012 confirmed the hope that CP violation

measurements were possible and called for. They are possible only with long baseline accelerator

neutrino experiments, more than ever a vibrant sector, in spite of all our EU difficulties, those

encountered in US for the approval of the Fermilab project (LBNE) or expected in Japan for their

new T2HK enterprise.

Contractual milestones and deliverables

The M48 milestone (fourth and last WP3 annual meeting) was cancelled, after all WP

deliverables were produced (D3.1.2, D3.2.1 and D3.3.1). Convening the community appeared to

be more appropriate in autumn 2013 after the final formulation of the HEP Strategy and a better

definition of its impact on the community.

Page 27: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 26 / 123

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

INFN * *

CERN * *

UNIGE * *

1.1.3.2. Task WP3.2: getting the most out of existing neutrino facilities

Progress towards objectives

During the reference period the CNGS neutrino beam facility at CERN had its final year of

operation. The facility successfully concluded a cycle of seven years of operation since its start-

up in 2006. In the end 1.8×1020 protons were delivered on target, corresponding to about 80% of

the estimated beam intensity in the approved program. At the same time, the Grand Sasso

experiments advanced in their analysis and the OPERA collaboration announced the discovery

of two more ντ appearance events, thus making three in total, compatible with the expectations.

In the graph below the evolution of the integrated beam intensity for CNGS is shown.

Figure 19: Integrated beam intensity for CNGS

Page 28: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 27 / 123

In 2012, a lot of studies, specific instrumentation and measurements were done to better

understand the timing structure of the beam, such to undoubtedly resolve any issue or source on

the CERN side of errors that may contribute to the miscalculation of the beam timing.

The experience gained by the operation of this high-intensity beam facility over the seven years

from 2006 to 2012 is a very important asset for CERN and Europe. Supported by Neu2012

meetings and discussions occurred in 2012 to prepare the input for the European Neutrino

Community to the Strategy Upgrade Process. The submitted papers included both physics

experiments and schemes for possible upgrade of the CERN accelerator complex towards a next

generation neutrino beams.

In particular, the possibility to provide a higher-intensity proton beam up to 750 kW was outlined

as well as the required R&D program to achieve it. The table below indicates the SPS potential

to provide CNGS-type beam for neutrino facilities after implementation of the LiU upgrades.

Table 2 : Present and future SPS performance in terms of beam power.

OPERATION SPS RECORD AFTER LIU (2020)

LHC CNGS LHC CNGS LHC

(aim)

post-CNGS

(study) SPS beam energy [GeV] 450 400 450 400 450 400

bunch spacing [ns] 50 5 25 5 25 5

bunch intensity/1011 1.6 0.105 1.3 0.13 2.2 0.17

number of bunches 144 4200 288 4200 288 4200

SPS intensity/1013 2.3 4.4 3.75 5.3 6.35 7.0*

PS intensity/1013 0.6 2.3 1.0 3.0 1.75 4.0*

PS cycle length [s] 3.6 1.2 3.6 1.2 3.6 1.2/2.4*

SPS cycle length [s] 21.6 6.0 21.6 6.0 21.6 6.0/7.2

PS beam momentum [GeV/c] 26 14 26 14 26 14

Beam power [kW] 77 470 125 565 211 747/622

The detailed studies are on-going within the LAGUNA-LBNO EU/FP7 Design Study,

addressing SPS but also its injectors in particular PS.

Two scientific proposals were submitted to the SPSC in 2012. The first, from the LBNO

collaboration, describing a staged approach for a CERN-based long-baseline neutrino beam from

CERN to a far detector located at the Pyhasalmi mine in Finland at 2300 km distance. The second

is a combined proposal from the ICARUS and NESSiE collaborations for the study in a short

baseline in the North Area with detectors at 460 and 1600 m distance.

As starting stage for this new generation of beams, the concept of a Neutrino Test Facility in the

SPS North Area is considered to create a neutrino detector R&D area where detector prototypes

could be exposed simultaneously to a neutrino beam and low-energy charged beams of (e, u, û).

The physics reach and performance of the facilities has been the subject of several meetings

organized within EUCARD/Neu2012 and summarized in a one-day workshop organized at

CERN and in the Task 3 report.

Page 29: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 28 / 123

Contractual milestones and deliverables: None

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

CERN * *

INFN * *

1.1.3.3. Task WP3.3: Road map to the next European accelerator neutrino facility

Progress towards objectives

The task has concluded its activity by organizing the Neutrino Town Meeting “European

Strategy for future neutrino physics II”

http://indico.cern.ch/conferenceDisplay.py?confId=176696 from which a community statement

concerning the largest consensus of the community for a future neutrino facility in Europe was

prepared, published and submitted to the European Strategy Group

http://arxiv.org/abs/1208.0512 .

Contractual milestones and deliverables

Task results finalized with delivery of D3.3.1.

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

UNIGE * *

CERN * *

Page 30: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 29 / 123

1.1.4. WP4: Accelerator Science Networks (AccNet)

AccNet is the project platform for exchange, investigations and assessment of accelerator

upgrades, technologies and new infrastructures. It includes three tasks:

Task WP4.1: Coordination and communication

Task WP4.2: EuroLumi network (accelerator performance)

Task WP4.3: RFTech network (RF technologies)

Task WP4.4 EuroNNAc (novel accelerators) : new additional network since 2010.

1.1.4.1. Task WP4.1: Coordination and communication

Progress towards objectives

At the 12th meeting of the EuCARD Steering Committee on 6 December 2012 the status and

plans of AccNet were reported. Since summer of 2012 AccNet-EuroLumi launched and

supported studies on various novel types of Higgs factories, such as circular e+e- colliders (LEP3,

TLEP), collider, a high-luminosity ep collider based on the LHC, as well as higher-energy

hadron colliders (HE-LHC, VHE-LHC), either in the LHC tunnel and in a new 80-100 km tunnel.

Presentations featuring and disseminating results of AccNet studies were given at various

occasions during this period, e.g. at invited seminars at Oxford, KEK, Frascati, Saclay, Orsay,

Sendai, CHIPP, oPAC workshop.

In total 25 AccNet mini-workshops and AccNet co-sponsored conferences were organized, e.g.

on LEP3 and TLEP (5 mini-workshops), on VHE-LHC, on SAPPHiRE, on electron cloud, on

LHC optics, on LLRF for X-FEL, on the use of C for industry and research, and low-level

RF for XFE, and on advanced acceleration concepts.

The AccNet web site was continually updated and enhanced. Budget and manpower plans were

also updated and adjusted.

Contractual milestones and deliverables

The final annual AccNet steering committee (M4.1.4) was held during the parallel sessions of

the EuCARD13 Annual Meeting. The AccNet Strategy for future proton & electron facilities in

Europe (deliverable D4.1.2) was published in the form of a report.

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

CERN * *

CNRS * *

GSI * *

Page 31: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 30 / 123

1.1.4.2. Task WP4.2: EUROLUMI

Progress towards objectives

The topical workshops were organized by EuroLumi either alone or in collaboration with EU

and non EU partners wherever relevant. Amongst important EuroLumi partners from outside

Europe are the consortium of US national accelerator laboratories US-LARP, the KEK

accelerator laboratory and Hiroshima University in Japan, and CINVESTAV Mexico. The goal

of the topical workshops typically was to assemble 30 to 40 world experts for brainstorming on

advanced topics. In most cases, the attendance exceeded this goal, demonstrating the added value

of this format of networking. In all workshops, the fraction of participants originating from

outside EuCARD was significant, typically 25%, sometimes above 50%. Events were often

organized at CERN in view of its numerous facilities, lower costs and easy air flight connections

to most world destinations, and since the main topic of EuroLumi – the LHC upgrade – is directly

linked to CERN.

# Topic Organizers Time Place Registrants Regist.’s/

speakers

1 Electron Cloud INFN-LNF,

INFN-Pisa

CERN LER,

EuroLumi

5-9

Sep.

2012

La Biodola,

Italy

62 from EU,

US, Japan

~1.2

2 Computing in

Accelerator

Physics

U. Rostock,

EuroLumi,

RFTech, CST

19-25

Sep

2012

Warnemünde,

Germany

about 100

from EU,

US, Russia,

and Japan

~1.2

3 LEP3 & TLEP EuroLumi 18

June

2012

CERN ~30 from

EU, US,

Russia,

Japan

~1.7

4 LEP3 & TLEP EuroLumi 23 Oct.

2012

CERN ~30 from

EU, US,

Japan

~2.0

5 HL-LHC EuroLumi,

LARP, HiLumi

LHC

14-16

Dec.

2012

Frascati 130 from

EU, US,

Japan

~1.5

6 TLEP EuroLumi 10 Jan.

2013

CERN ~40 from

EU, US,

Russia,

Japan

~2.2

7 SC Magnet

Quenches

HiLumi LHC,

EuCARD WP7

(HFM),

EuroLumi

15-16

Jan.

2013

CERN 50 from EU,

US, Japan

~3.2

Page 32: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 31 / 123

8 SAPPHiRE EuroLumi 19 Feb.

2013

CERN 25 from EU,

US, Japan,

Russia

1.6

9 VHE-LHC HiLumi,

EuroLumi,

US-Snowmass

21-22

Feb.

2013

CERN ~50 from

EU, US

~2.2

10 TLEP EuroLumi 4 May

2013

CERN 27 from EU,

US, China

1.2

11 Space Charge EuroLumi,

ICFA,

HICforFAIR,

LIU

16-19

Apr.

2013

CERN 83 from EU,

US, Japan,

China,

Mexico,

Russia

1.9

12 Future of

accelerators

EuCARD,

EuroLumi

10-14

Jun

2013

CERN 186 from

EU, US,

Japan, Israel

3.7

13 LHC Optics EuroLumi,

HiLumi

17-18

Jun

2013

CERN 53 from EU,

US

1.7

14 TLEP EuroLumi,

LPC, FNAL

25-27

Jul.

2013

FNAL 60 from US,

EU, Russia,

Japan,

Mexico

2.3

Workshop 3, attended by the CERN Director of Accelerators & Technology as well as by the

KEK “trustee” in charge of strategy, was the first ever workshop discussing the possibility of a

circular Higgs factory in the LHC tunnel or in a new 80 or 100 km tunnel. It was followed by

four similar mini-workshops in 3-month rhythm (workshops 4, 6, 10 and 14), making rapid

progress on the accelerator design. Workshop 8 was the first ever event devoted to a low-cost

Higgs factory, and workshop 9 the first one devoted to 100-TeV pp collider in a new large tunnel.

Together these workshops developed a cost-efficient staged strategy towards delivering highest-

energy highest-luminosity collisions of various species to study the Higgs boson with the best

possible precision and to explore the closure of the standard model and to discover New Physics.

Workshops 1, 5, 7, 11, and 13 addressed important aspects of the HL-LHC design, the LHC

injector upgrade, and FAIR. Workshop 12 (“EuCARD13”) on the visions for the future of

accelerators was co-organized by WP4 EuroLumi. One example outcome of these workshops

was the stronger collaboration with the European space satellite community assembled around

ESA. Another was a novel technique of electron cloud diagnostics, developed by the CERN-GSI

collaboration in the framework of EuroLumi, by which the average electron cloud density around

a storage ring is inferred from the bunch-by-bunch synchronous phase shift. The ratio of

registrants/speakers is included to illustrate the dynamic interactivity. For comparison, at a

typical IPAC this ratio is ~12.

Page 33: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 32 / 123

Several invited talks on the LHC upgrade plans and future high-energy colliders were given at

Oxford, KEK, INFN Frascati, LAL Orsay, CEA Saclay, Sendai/Japan, Sursee/Switzerland, and

CERN.

During the 3rd period, AccNet-EuroLumi supported or organized a number of exchanges of

scientists and joint studies to mutual benefits.

The Mexican doctoral students H. Maury (CINVESTAV/Merida), B. Yee (CINVESTAV/

Mexico City) and C. Valerio (CINVESTAV/Sonora) for simulations of electron-cloud effects in

the LHC arcs and in the HL-LHC, for simulation of HL-LHC crab-cavity failures, and for

contributions to the development of a high-intensity H- source for CERN Linac4, respectively.

The US-LARP physicist C. Bhat (FNAL) for the study of the generation & stability of long flat

bunches, including machine studies.

The Japanese expert K. Ohmi (KEK) for beam-beam, space-charge, and electron-cloud

simulation studies for LHC upgrade and for LEP3 & TLEP.

US specialist M. Bai (BNL) for discussions on optics diagnostics and optics modeling for high-

intensity proton rings.

The Italian surface scientist R. Cimino (INFN-LNF) for new ideas on electron-cloud mitigation,

e.g. using in-situ fullerene coatings.

US specialists T. Sen (FNAL), V. Litvinenko (BNL) and EU specialists D. McGinnis (ESS), S.

Petracca (U. Sannio) and R. Cimino (INFN-LNF) for discussions on highest-energy proton-

proton or proton-antiproton colliders, including specialized topics like metallic foams.

US specialists U. Wienands (SLAC), R. Talman (Cornell), V. Danilov (ORNL), A. Fasso (SLAC

& TJNAF, ret.), and R. Rimmer (TJNAF); Russian specialist V. Telnov (BINP); Chinese

specialist Q. Qin (IHEP); Japanese specialist K. Oide (KEK); and EU experts R. Assmann

(DESY) and M. Boscolo (INFN-LNF) for discussions on circular e+e- Higgs factories.

EU experts K. Moenig (DESY/Zeuthen), F. Zomer (LAL), A. Variola (LAL), L. Corner

(Oxford), Y. Zaouter (Amplitude Systems), and US experts V. Yakimenko (SLAC), V.

Litvinenko (BNL) and J. Gronberg (LLNL) for discussions on a high-power laser system, optical

cavities, and FEL options for SAPPHiRE.

Contractual milestones and deliverables

The annual workshop corresponding to milestone M4.2.4 was replaced by more than ten topical

workshops and a session in a conference, as described in the table of events above. The EuroLumi

Strategy and issues for LHC IR, LHC injector and beam-parameter upgrade path(s), with

comment on longer-term prospects, and for FAIR (deliverable D4.2.2) were published in the

form of a report.

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

CERN * *

Page 34: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 33 / 123

1.1.4.3. Task WP4.3: RFTECH

Progress towards objectives

The RFTech network follows the pattern of events anticipated in the contract, with, in addition,

participation in external events tightly linked to the RFTech objectives, plus a few topical

workshops.

# Topic Organizers Time Place Registrants

1 Integrated Circuits for

Low Level RF

RFTech 24-26 May

2012

Warsaw /

Poland

~300

2 Higher Order Modes

in SC RF

CI, ICFA,

ASTeC, IoP,

RFTech

25-27 Jun

2012

Daresbury/

UK

59

3 Advanced Low Level

RF Control

RFtech 6-8 Aug

2012

Lodz / Poland 43

4 Computing in

Accelerator Physics

U. Rostock,

EuroLumi,

RFTech, CST

19-25 Sep

2012

Warnemünde,

Germany

about 100 from

EU, US,

Russia, and

Japan

5 Low Level RF for

XFEL

RFTech 19-21 Feb

2013

Swierk/

Poland

55

6 4th Annual RFTech

Meeting

RFTech 24-26 Feb

2013

Annecy/

France

33

These workshops provided excellent opportunities to share experience among several fields of

RF technology, from low-level systems to solid-state power amplifiers.

More specifically, the 4th RFTech workshop covered a large range of RF topics, including C-

band RF, X-band RF, reliability, LLRF, RF diagnostics, reliability, costing, breakdown,

operation, klystron lifetime, and RF efficiency; and it also addressed RF issues for many

important present or planned accelerator facilities, e.g. SPIRAL2, MYRRHA/MAX, CLIC,

TESLA, ELI-NP, LHeC ERL, TLEP, LHC, FLASH, PS Booster, MedAustron, and SwissFEL.

Participants came from DESY, CERN, INF-INFN, TUD, UROS, GANIL, PSI, LPSC/CNRS,

UJF, TUL, and ISE-WUT.

RFTech also organized or co-organized several topical workshops related to low-level RF

control, as well as special sessions at the MixDes2012 Conference on Mixed Design for

Integrated Circuits and Systems with applications to accelerator RF systems, and at the ICAP’13

on accelerator RF related computing. Some RFTech experts also attended the IEEE Conference

workshop on Real Time techniques, RT2012, in June 2012.

An important result is a report on strategy/results for cavity design, LLRF & HPRF systems and

design integration, and costing tools.

Page 35: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 34 / 123

Contractual milestones and deliverables

The fourth annual RFTech workshop (M4.3.4) was organized in February 2013 at Annecy

(France), located halfway between CERN/Geneva and ESRF/Grenoble.

The RFTECH results for cavity design, LLRF & HPRF systems and design integration, and

costing tools (deliverable D4.4.3) were published in the form of a report.

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

CERN * *

DESY * *

UJF * *

1.1.4.4. Task WP4.4: EURONNAC

EuroNNAc – a European Network for Novel Accelerators looking at the Next Generation of

Novel Electron Accelerators – was launched in December 2010 on the EuCARD initiative.

Progress towards objectives

The second major EuroNNAc workshop was held at CERN, on 2-4 May 2013. It created four

task forces towards an EU-wide (or even global) coordination of advanced accelerators, defined

strategies and detailed plans for each task force, progressed towards a coherent proposal of one

or a few European and international pilot facilities for advanced accelerators; prepared a written

report on novel acceleration and the EuroNNAc network; approved plans for a European

conference for advanced accelerators (the first one EAAC2013), and prepared an input statement

to European Strategy for Particle Physics ("On the Prospect and Vision of Ultra-High Gradient

Plasma Accelerators for High Energy Physics").

EuroNNAc organized the first ever EAAC workshop, in Italy from 2 to 7 June 2013, with 145

participants. An important practical conclusion is that a substantial extra funding is to be found

to accomplish the EuroNNAc goal of a distributed European test facility.

Contractual milestones and deliverables

The new network fulfilled in the past period all of its voluntary milestones and deliverables.

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Page 36: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 35 / 123

Partner ++ + = - -- ++ + = - --

CERN * *

DESY * *

CNRS * *

Page 37: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 36 / 123

1.1.5. WP5: Transnational access HiRadMat@SPS

HiRadMat (High Irradiation to Materials) is a new facility at CERN designed to provide high-

intensity pulsed beams to an irradiation area where material samples as well as accelerator

component assemblies can be tested. The facility uses a 440 GeV proton beam extracted from

the CERN SPS with a pulse length of 7.2 μsec, to maximum pulse energy of 3.4 MJ. In addition

to protons, ion beams with an energy of 173.5 GeV/nucleon and total pulse energy of 21 kJ can

be used. Over the reference period, the first HiRadMat experiments took place as scheduled and

successfully completed data taking in the beam period from May to November 2012. A detailed

list of experiments is online available at http://cern.ch/hiradmat (section experiments). These

first experiments included candidate materials and prototype assemblies of LHC collimators

foreseen to operate at the ultimate LHC beam powers, experiments on vacuum windows,

benchmarking detector and target material options for use in future high power proton beam

applications.

Figure 20: Photo of the HiRadMat experimental area. The primary beam line with its last equipment is shown on

the left. The three yellow base-supports for the experiments are visible at the centre, with one experiment already

installed in the middle one. The massive beam dump is visible downstream the beam path.

The beam conditions relevant to the experiments: intensity, pulse structure, focusing and spot

size possibilities, beam interlocks conditions etc. are defined and documented in the project web

page: http://cern.ch/hiradmat.

As HiRadMat@SPS is a high-intensity beam area substantial pre-cautions are necessary for the

access and operations with the users. For each experiment three phases are needed: a) preparatory

phase including experiment review by CERN safety officials; typically 6-9 months before the

experiment is scheduled, b) the preparation of the experimental setup outside the irradiation area

and subsequent installation using remote tooling to the area and the exposure to beam, and c) the

final removal of the equipment and inspection at the end of the experiment and some cool-down

period. TA funds were also used to cover the needs of the experimental teams in all three phases.

Table 1 lists the experiment schedule of 2012 for data taking with beam.

Page 38: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 37 / 123

Table 3 HiRadMat TA Operations schedule for 2012

No Dates Experiment

1 31. May HRMT10 (WTHIMBLE)

2 5.-13. July HRMT12 (LPROT)

3 20. Aug – 1. Sept. HRMT04 (BLM)

4 27.-28. September

1.-4. October

HRMT-14 (LCMAT)

5 19.-20. October HRMT-15 (RPINST)

6 31. October HRMT16 (UA9CRY)

7 1.-4. November HRMT01 (TISD)

1.1.5.1. Description of publicity concerning new opportunities for access

Access to the HiRadMat facility has been publicised principally through web pages,

presentations at international conferences, complemented by targeted visits and emails to

potentially interesting communities and laboratories. The HiRadMat web pages, also accessible

through the EuCARD main web, give an overview and the capacity of the facility and provide

information on the rules and regulations for access. Conference presentations include workshops

on future Neutrino Facilities, high-power target development, the International Accelerator

Physics conference and EuCARD meetings. Visits to PSI and RAL laboratories have been

organized to present the facility and its potential.

1.1.5.2. Description of the selection procedures

The HiRadMat Scientific Board assesses the beam and TA requests, by inviting each team to

present the scientific goals, proposed installation and post-irradiation analysis of their

experiment. On positive recommendation by the Scientific Board a beam time slot for the

experiment on the yearly schedule is reserved. This beam slot is then validated after the

experiment is reviewed and positively recommended by the HiRadMat Technical Board

consisting of CERN beam experts and safety officials. The Scientific Board meets typically three

times per year, while the Technical Board upon needs.

Over the reference period the following board meetings took place:

23. April 2012 Scientific Board Meeting

15. June 2012 Technical Board Meeting

27. July 2012 Technical Board Meeting

28. September 2012 Technical Board Meeting

18. October 2012 Scientific and Technical Board Meeting

With the CERN accelerator shut-down beginning December 2012 until end 2014 no more

experiments are scheduled and board meetings were not required anymore.

1.1.5.3. Transnational Access activity

Page 39: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 38 / 123

User-projects

(see MA database for

details) Users supported

(see MA database for

details)

Units of access delivered

(for HiRadMat = 1 8-h-

day @ CERN) Eligible

submissions Selected

In Period P3 (M36-

M52) 7 7 14 102.6

Foreseen for project

(M1-M52) 10 20 50

Note: The unit of access for HiRadMat has been modified from 1 beamhour to 1 8-h-day presence at CERN

including the preparation and dismantling of the experiment. The number of units that are committed remains the

same (50).

Scientific output of TA-supported users at the facility

User meetings

Due to the special nature of the HiRadMat facility and the stringent conditions implied to the

experiments, mainly due to the induced radiation fields from the high-power beams, preparing

for experiments can be rather challenging. Therefore sharing of the information, on experimental

techniques and tooling is vital and heavily promoted to best use the TA funds. During the beam

time period until December 2012 user meetings were scheduled on a bi-weekly basis (Friday

afternoon). This was continued for a few weeks after the start of the CERN shut-down for de-

commissioning activities of the experiments.

Page 40: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 39 / 123

1.1.6. WP6: Transnational access MICE

WP6 provides transnational access to a specialized beam line at the Science and Technology

Facilities Council (STFC) ISIS facility at the Rutherford Appleton Laboratory (RAL). This

beam line, together with its associated infrastructure, was originally referred to as the MICE

facility, but in order to distinguish the facility more clearly from the MICE experiment (see

below), the facility is now designated the Ionisation Cooling Test Facility (ICTF).

The ICTF provides muon beams of either sign, pulsed at 1 Hz, in the momentum range 120

MeV/c to 350 MeV/c, as well as protons, pions and electrons from 100 MeV/c to 400 MeV/c.

The intensity of the muon beam is ~50 particles per pulse. During P3 significant progress has

been made on the installations for the radio-frequency (RF) and Liquid Hydrogen (LH)

systems, which will complete the facility.

The ICTF has been developed in the first instance for the MICE experiment (Muon Ionisation

Cooling Experiment) http://mice.iit.edu/, which is the first experiment to be installed at the

facility. The MICE experiment will allow high-accuracy measurement of emittance, and will

deploy unique absorbers (using the Liquid Hydrogen) and re-acceleration stations (using the

RF) to assess the efficiency of ionization cooling.

1.1.6.1. Description of publicity concerning new opportunities for access

All available TA resources were allocated at the end of P2 (see P2 report), and so access to the

facility was not advertised further during P3.

1.1.6.2. Description of the selection procedures

As reported previously, all available TA funding was allocated just before the end of P2, so the

Selection Panel did not meet during P3.

1.1.6.3. Transnational Access activity

User-projects

(see MA database for

details) Users supported

(see MA database for

details)

Units of access delivered

(for MICE = 1 beam-hour) Eligible

submissions Selected

In Period P3 (M36-

M52) 3 3 11 1107.7

Foreseen for project

(M1-M52) 8 28 3384

Page 41: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 40 / 123

User projects and experiments

All projects are in the field: Physics, Scientific discipline: High energy and particle physics.

(a) MPDI: MICE PID (Particle IDentification) Detectors Improvements.

Milano/Naples/Pavia/Roma group: commissioning and calibration of Time-of-flight (TOF)

system; TA award 1 Apr 2012 – 31 Jul 2013; 6 users, 12 trips, 54 visitor-days, 225.7 access

units (beam-hours).

(b) BGMICE: Bulgarian participation in the MICE experiment.

Sofia group. TA award 1 Apr 2012 – 31 Jul 2013; 2 users, 2 trips, 47 visitor-days, 196.5

access units (beam-hours).

(c) MICE-UNIGE: MICE University of Geneva project.

University of Geneva group. TA award 1 Apr 2012 – 31 Jul 2013; 3 users, 18 trips, 164

visitor-days, 685.5 access units (beam-hours).

A total of 1107.7 transnational access units (beam-hours) were used during period 3.

Scientific output of TA-supported users at the facility

TA-supported users have made wide-ranging contributions to the scientific output from the

facility during P3.

The scientific goals of MICE depend on the measurement of the beam emittance, using a single-

particle method. The Time-of-Flight (TOF) counters have been essential both for identification

of the beam particle and, prior to the availability of magnetic spectrometry in 2015, for

momentum measurement. Thanks to the outstanding performance of the TOF counters (see also

P2 report), it has proved possible to use these counters to measure the momentum of single

muons with a resolution of better than 4 MeV/c and systematic error of < 3 MeV/c. The ability

to measure the longitudinal momentum, pz , to this precision will complement the momentum

measurement of the magnetic spectrometers. For low transverse amplitude particles, the

measurement of pz in the TOF counters is expected to have better resolution than that of the

spectrometers, which are primarily designed for measuring the transverse component of the

momentum.

The performance and operation of the TOF counters has been one of the principal goals of the

TA-supported groups, in P3 as well as in P1 and P2.

Figure 21and Figure 22 (taken from http://arxiv.org/pdf/1306.1509v1.pdf) show the measured

horizontal and vertical emittances, compared to simulations. These results demonstrate that the

beam emittances are highly suitable for the MICE experiment

Page 42: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 41 / 123

Figure 21 Horizontal emittance after correction for measurement resolution and multiple scattering versus mean

pz of the seventeen measured beams. Solid circles µ- data, open black circles µ+ data, solid red triangles µ-

simulation, open red triangles µ+ simulation. The nominal “pz=140” Mev/c beams correspond to momenta in the

range 170-190 MeV/c, “pz=200” to 220-250 MeV/c, and “pz=240” to 250-290 MeV/c.

Figure 22: Vertical emittance after correction for measurement resolution and multiple scattering versus mean pz

of the seventeen measured beams. Solid circles µ- data, open black circles µ+ data, solid red triangles µ-

simulation, open red triangles µ+ simulation. The nominal “pz=140” Mev/c beams correspond to momenta in the

range 170-190 MeV/c, “pz=200” to 220-250 MeV/c, and “pz=240” to 250-290 MeV/c

Further highlights during P3 have been the completion of the Electron Muon Ranger (EMR)

detector, following earlier tests in the ICTF beam, and final results on the pion contamination in

the muon beam, which will be published.

Page 43: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 42 / 123

TA-supported users have also contributed to the running and operation of the MICE experiment

at the facility, and to the fruitful exchange of information and experience with other

collaborators, from across Europe (and elsewhere) present at the facility.

User meetings

1. MICE Collaboration Meeting 33: June 25-29, 2012. Venue: University of Glasgow,

Scotland. Number TA users attending: 5. Overall number of attendees: 44

2. MICE Collaboration Meeting 34: October 17-19, 2012; Venue: Rutherford Appleton

Laboratory, UK. Number TA users attending: 5. Overall number of attendees: 53

3. MICE Collaboration Meeting 35: February 14-16, 2013; Venue: Rutherford Appleton

Laboratory, UK. Number TA users attending: 1. Overall number of attendees: 46

4. MICE Collaboration Meeting 36: June 17-19, 2013; Venue: Illinois Institute of

Technology (IIT) and FermiLab, USA. Number TA users attending: 1. Overall number

of attendees: 47.

Page 44: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 43 / 123

1.1.7. WP7: High Field Magnets (HFM)

The goal of HFM is the development of a new generation of accelerator quality magnets

exceeding the capabilities of the Nb-Ti technology. A synergetic study of using HTS for

superconducting links is associated. The tasks under this WP are:

Task WP7.1: Coordination and communication

Task WP7.2: Support studies (radiation resistance and thermal calculations)

Task WP7.3: High field model

Task WP7.4: Very high field insert

Task WP7.5 High Tc superconducting links

Task WP7.6 Short period helical superconducting undulators

1.1.7.1. Task WP7.1 Coordination and communication

Progress towards objectives

Main activities of the last period were:

Organization of 2 collaboration meetings (18-19 September 2012 at INFN-LASA and

20 March 2013 at CERN)

Organization of External Scientific Advisory Committee (ESAC) review on 27

February - 1 March 2013 at CEA-Saclay for task 3 and 4

A detailed internal review was done for tasks 2, 3, 4, 5 and 6

Budget reshuffling was done for tasks 2 and 4

Several deliverables were redefined

Assistance was provided to the tasks for the production of their deliverables

Resources were organized to continue the unfinished EuCARD task.

Contractual milestones and deliverables

The milestone 7.1.4 (4th annual HFM review meeting) was achieved as planned in M48 (March

2013 at CERN).

The deliverable 7.1.1 (HFM web-site linked to the technical & administrative databases) was

achieved and a report will be released in July 2013.

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

CEA * *

CERN * *

Page 45: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 44 / 123

1.1.7.2. Task WP7.2: Support Studies

Progress towards objectives

Task WP7.2 consists of two sub-tasks:

Sub-task WP7.2.1 (Radiation resistance certification for coil insulation and

impregnation): detailed specification of irradiation at LN2 temperatures, start of

irradiation of samples, determination of mechanical properties measurements, design of

the cryostat for electrical certification measurements at LN2 temperature

Sub-task WP7.2.2 (Thermal models and design): thermal measurements of the un-

irradiated samples, development of steady state and transient thermal model of the

magnet coil, determination of the safe heat load to the magnet coil, cool-down time and

cryogenic system cooling capacity.

Sub-task WP7.2.1 Radiation resistance certification for coil insulation and impregnation

A first series of irradiations at National Centre for Nuclear Research (NCBJ), Swierk, Poland on

the thermal samples was concluded in June 2012 but due to the high dose rate the samples are

not usable due to too large radiation damage. Tests were done to understand this excessive

damage and solutions were found by reducing the dose rate by a factor of two and some cooling

improvements. It was decided to re-schedule the irradiations of the samples such that the ones

with the shortest irradiation times will come first: the electrical samples first, followed by the

mechanical samples and then the thermal samples. At present the irradiation of the electrical

samples and half of the mechanical samples has been completed. The equipment for the

cryogenic electrical and mechanical characterisation tests, e.g. the cryostats, high voltage

equipment and traction equipment was designed, constructed and commissioned. The irradiated

mechanical and electrical samples and the non-radiated reference samples have all undergone

their characterisation tests. A deliverable report was produced in June 2013 and submitted in

July 2013.

Figure 23: Electrical breakdown before and after irradiation with a dose of 50 MGy of 6 MeV electrons

Sub-task WP7.2.2 Thermal models and design

The deliverable 7.2.3 “Superfluid helium transport model for the thermal design of the high field

model magnet” was produced in May 2013. This deliverable covers the work on the construction

of a new numerical finite element model using a simplified formulation of the two-phase theory

for superfluid He for accelerator magnets.

0

10

20

30

40

50

60

70

80

90

100

Mix71 LARP CE-Epoxy Mix 237

Die

lectr

ic s

tren

gth

, kV

/mm

Unirradiated

Irradiated

Bet

ter

than

85

kV

/mm

Criteria 5kV/mm

Page 46: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 45 / 123

Contractual milestones and deliverables

Two deliverables were produced:

Deliverable D7.2.1: “Certification of the radiation resistance of coil insulation material” (M52)

Deliverable D7.2.3: “Superfluid helium transport model for the thermal design of the high field

model magnet” (M50).

Planning, deviations and corrective actions

Sub-task WP7.2.1 – Radiation resistance certification for coil insulation and impregnation

Task on schedule Ahead of schedule Minor delay Significant delay

Sub-task WP7.2.2 - Thermal models and design.

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

1.1.7.3. Task WP7.3: High Field Model

Progress towards objectives

During the period, 23 meetings of the Magnet design working group were held. Furthermore an

External Scientific Advisory Committee (ESAC) review was held in February 2013.

The ESAC review committee acknowledged the progress made and the maturity of the

project. It recommended to carefully get confirmation of the validity of each step of the

construction. It insisted on the need for a test with one or two (out of 4) coils to validate

the concept of flared-end coils.

The strand procurement progressed well and at the end of the period enough strand had

been delivered to construct one full set of coils for the dipole.

The cable for the dipole was developed and the cable design is valid for both PIT and

RRP conductors, which are being procured. The degradation of the critical current due to

the cabling process is less than 5 %.

The mechanical design is complete and the magnet structural components have been

procured and delivered. The structure was assembled with dummy Al pieces in place of

the coils and extensively instrumented with strain gauges. This ‘dummy’ magnet has been

tested at liquid N2 temperature in a purpose-built installation at CERN to verify the

detailed mechanical behavior under cool-down.

Detailed models of several types have been made to calculate the quench protection cases

of the dipole. The conclusion is that the magnet can be protected with a comfortable

Personnel Material

Partner ++ + = - -- ++ + = - --

CEA * *

CERN * *

PWR * *

Page 47: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 46 / 123

margin even in the case of a quench starting in a low field region. A maximum hot-spot

temperature of 140 K can be achieved in a worst-case scenario.

The test facility for the LHe test of the dipole has been designed. The outer vacuum vessel

of the cryostat has been ordered and the delivery is foreseen for summer 2013. The

tendering procedure for the inner He vessel Cryostat has been started and this component

is expected for delivery by June 2014. The cryogenic components (eg. valve boxes and

transfer lines) and the cryogenic controls racks and test instrumentation racks are in an

advanced state of detailed design and will be ready in summer 2014. The test station will

be installed in the CERN vertical tests station in building SM18 where the pit for the

cryostat, the power supply and other auxiliary equipment already exist.

A complete design report has been written. The report covers the electromagnetic and

mechanical design of the magnet, the quench protection, the tooling design, the coil

manufacturing and the assembly procedures. The design report is part of the deliverable

for this task.

A coil of the 3-4 type with Cu conductor has been wound with the final tooling. A small

modification of the reaction tooling will be implemented at the end of the summer after

which a few turn superconducting test coil will be wound and reacted to test the

procedures.

Figure 24: Finished structure with dummy Al coil (left), Cu Coil winding completed (right)

Contractual milestones and deliverables:

Deliverable D7.3.1 accounting for the results obtained and plans for termination was delivered

at the end of July 2013.

Deve

lopm

ent &

Fabr

icatio

n Te

st of

the

Nb3S

n Di

pole

Mag

net F

RESC

A2, 1

7720

13, P

ierre

Man

il, 18

/26

• …Last  turn (40 instead of the nominal 42)

Cu coil winding 2/2

Courtesy of Françoise Rondeaux

Page 48: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 47 / 123

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

The main deliverable (7.3.1 at M48) was rescheduled as more tests and intermediate steps were

introduced to consolidate the design and manufacturing steps of the dipole magnet and due to

the delays in the construction of the test station. The deliverable report can nevertheless be

produced in 4 parts describing the main design and construction steps. This comprises of

Part I: Design report for the dipole magnet

Part II: Dipole magnet structure tested in LN2

Part III: Nb3Sn strand procured for one dipole magnet

Part IV: One test double pancake copper coil made

The magnet with a single superconducting coil will be tested in September 2014 in the new

CERN test station. The completion of the Fresca2 magnet is now part of the CERN and CEA

core activities as it is essential for the development of high field magnets for future proton

colliders and is therefore guaranteed.

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

CEA * *

CERN * *

PWR * *

1.1.7.4. Task WP7.4: Very high field insert

Progress towards objectives:

This last period was mainly devoted to finalize the mechanical design of the dipolar insert, to

finalize the drawings and to launch the orders for all tooling and mechanical part, to order the

conductor and to prepare the final tests.

The design report for the dipolar insert was produced in May 2013. It contains the

following chapters: insert magnet configuration, conductor definition, magnetic study

with the outsert, protection, mechanical structure, assembly, HTS test solenoids. The

report is the object of the deliverable D7.4.1, part I

Protection studied for the 2 magnets powered together: this point is quite important, many

simulations were done with different codes. If the protection of the insert alone is not a

problem, the problem is more crucial when the insert will be powered inside the Fresca2

dipole. It is unclear how high hot spot temperatures can be tolerated in an YBCO coil and

when does the delamination of the conductor really occur. It is expected that a lot of

information will be gained from the tests of the magnet.

Order and delivery of the conductor: the core YBCO conductor was ordered in December

2012. Its delivery is expected in September 2013, with some delay showing the technical

problems when increasing the unit length of YBCO tape

Page 49: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 48 / 123

Study and ordering of mechanical parts: all the studies for the mechanical parts for the

windings and for tooling were finished in June 2013. All the orders were passed until

beginning of July. Delivery is expected until November 2013 (Deliverable D7.4.1, part

III). Realization of a prototype and preparation of its test: a single pancake prototype was

wound at Saclay in July 2013, and has been sent to Grenoble for testing in September

2013. In parallel, a test facility has been prepared to test this insert in a 10 T external field

at Grenoble. A particularity is that it will be possible to change the orientation of the

pancake in the external field to study this effect on the conductor critical current (D7.4.1,

part II).

Figure 25: Cross-section and 3D model of the insert

The protection of the HTS insert remains an issue due to the very low propagation velocities and

the high current densities. The very large magnetic coupling (0.9) with the outer Nb3Sn dipole

makes the protection more difficult. From the study of different quench scenarios we conclude

that a fast discharge of both magnets is mandatory. Another simulation work, based on finite

element codes, gives the space and thermal evolutions of the hot spot. They confirm the very

slow development of the normal zone with two consequences: the difficulty to detect a quench,

and high mechanical stresses due to differential thermal contraction. Highly instrumented coils

with different characteristics (Cu quantity, insulation) have been made to verify these

simulations.

HTS insert, interface with the Nb3Sn dipole

The design of the HTS insert dipole has been studied in detail with 3D electro-magnetic and

mechanical models. The insert will be mechanically independent from the Nb3Sn dipole. The

insert supporting structure is a 3 mm thick stainless steel tube. The magnet is composed of six

flat pancakes wound with a 12 mm wide YBCO conductor.

The conductor is made of two tapes soldered together with a Cu tape. This configuration should

meet the numerous requirements such as mechanical performance, protection, industrial

realization, AC losses etc.. A first length was produced by the tape manufacturer and will be

tested. To get a nominal insert field of 6 T insert with a current of 2800 A two conductors will

be put in parallel with transposition from pole to pole for a balanced current distribution. Central

iron poles are added to reduce the peak fields. A mock-up with dummy Al coils has been made

with the iron poles, the steel pad and the external tube. The pad is machined in two parts and will

be welded together. The external tube will be shrink-fit around the pad.

Page 50: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 49 / 123

Technological implementation, First YBCO solenoids and pancakes

To proceed step-by-step towards a dipole insert of HTS conductor, several HTS solenoid coils

have been made and tested up to their limits in existing high field facilities at partner’s labs. Only

YBCO coils have been realized, as this was the chosen conductor. Tests have been carried out

and protocols have been defined to make low resistance (40 nΩcm2) and reproducible

connexions between YBCO tapes.

In Grenoble, a double pancake carried a current of 400 A at 4.2 K under 18 T before the tape

broke close from a current lead. The engineering current density was 1000 MA/m2 and the hoop

stress overstepped 700 MPa. Another double pancake was tested in Karlsruhe, and showed very

similar results: the breakdown occurred at a hoop stress of 730 MPa, but under 10 T and 700 A

.

In conclusion, after several YBCO coils made with low performance, new coils, both layer and

double pancake type, were successfully made, with a performance close to the conductor intrinsic

limits. Those are higher than the values in the designed YBCO insert.

Figure 26: Design model of the test pancake mounted on the base of the 10 T test insert (left), Photo of the

finished test pancake coil (right).

Contractual milestones and deliverables

Deliverable D7.4.1 has been delivered by the end of July 2013 describing the results obtained

and plans.

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

The final deliverable (7.4.1, M48) will be delayed by approximately 6 months as more tests and

intermediate steps were introduced to consolidate the design and manufacturing steps of the

Page 51: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 50 / 123

insert dipole. The deliverable report can nevertheless be produced in 3 parts describing the main

design and construction steps. This comprises:

Part I: Design report for the HTS dipole insert

Part II: One insert pancake prototype coil constructed with the setup for a high field test

Part III: All insert component ordered

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

CNRS * *

CEA * *

KIT * *

INFN * *

TUT * *

UNIGE * *

PWR * *

1.1.7.5. Task WP7.5: High-Tc superconducting link

Progress towards objectives

The superconducting link task developed and built a 20 m long Superconducting Link made of

HTS (High Temperature Superconducting). Following an intense R&D activity, which included

the study of novel concepts of cables made from HTS tape conductor and the development and

test of prototype units, the final deliverable was successfully assembled at CERN in May 2013.

A five-meter long Superconducting Link containing 25 Twisted-Pair MgB2 cables was

assembled at CERN and successfully tested at the University of Southampton. More

recently, a dedicated campaign of tests was launched at the University of Southampton

with the objective of studying the performance of the cables in case of resistive transition.

Transient behavior in He gas environment was studied.

Following the successful validation of prototype cables, two novel cabling machines

were developed and assembled at CERN. These machines enable respectively a) the

controlled production of long -kilometer length- electrically insulated stacks of tapes and

b) the final twisting and electrical insulation of two stacks of tapes to produce the final

Twisted-Pair unit. The process is applicable to MgB2, YBCO and Bi-2223 conductors

[2].

Twenty-five Twisted-Pair cables, each containing three MgB2 tapes and four copper

strips, were made at CERN using the newly developed cabling machines. The 25

Twisted-Pair cables were then assembled together to form the 20 m long final multi-cable

assembly. The multi-cable assembly was found to have the originally estimated

geometrical characteristics (about 40 mm external diameter when MgB2 tapes are used)

Page 52: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 51 / 123

and a minimum-bending radius of about 1 m. Each Twisted Pair cable in the assembly is

able to transfer 2×±1 kA at 30 K and 2×±2 kA at 20 K

A 20 m long Nexans line with dimensions optimized for hosting the multi-cable assembly

was procured by CERN. A novel test station, which integrates this line has been designed,

constructed and fully commissioned at CERN

Figure 27: Completed 25 Twisted-Pair link cable (left), Test station at CERN with the flexible cable cryostat

(right).

Contractual milestones and deliverables

Deliverable D7.5.1 “Final design report HTS link” has been completed.

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

CERN * *

BHTS * *

COLUMBUS * *

SOTON * *

1.1.7.6. Task WP7.6: Short period helical superconducting undulator

Progress towards objectives

After the selection of the Supercon Nb3Sn wire (see previous periodic report), much of the work

was devoted to the preparation, realization and tests of 2 similar 300 mm long helical undulators.

For the construction of the 2 undulators the former manufacturing steps were modified for

minimizing the risks of failure. A method to alumina- coated the former was developed and

qualified. The vacuum impregnation method was also qualified. Finally, the two undulators were

realized during Q4 2012 at STFC-RAL.

Page 53: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 52 / 123

The test of one undulator was done at LASA. For this an agreement was found with INFN-LASA

laboratory to test the two undulators in their laboratory during Q1 2013. The results were quite

disappointing: one undulator had a very high resistance (broken wire) and could not be tested.

The second one had quenches well below the nominal, and a resistive part was detected on it.

Nevertheless, magnetic measurements were performed at low current. The cause of these

problems was later identified as a break in the conductor. Also, the fractured macor winding

posts indicate that significant tensile force was present in the windings at some stage of the

realization.

Figure 28: Undulator

Contractual milestones and deliverables

Deliverable D7.6.1, “ Final prototype SC helical undulator measured” was completed in May

2013.

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

STFC * *

Page 54: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 53 / 123

1.1.8. WP8: Collimators and materials (ColMat)

The goal of this WP is to improve collimation efficiency by i) a better modelling of the beam

halo, ii) a selection of robust materials compatible with the ultra-high vacuum, iii) prototyping.

Task WP8.1: Coordination and communication

Task WP8.2: Modelling, materials and tests for hadron beams in LHC and FAIR

Task WP8.3: Collimator prototyping and testing for hadron beams in FAIR and LHC.

1.1.8.1. Task WP8.1: Coordination and communication

Progress towards objectives

The progress of WP8 was reported in the EuCARD last annual meeting at CERN. The annual

meeting being the kick-off meeting of EuCARD² as well the results obtained in WP8 were topic

in the highlight talk “R&D on Novel Advanced Collimator Materials: Results and Perspectives”.

Contractual milestones and deliverables

The last ColMat meeting (M8.1.4) was held informal in parallel to the EuCARD2013 meeting at

CERN. The deliverable D8.1.1 was produced.

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

CERN * *

GSI * *

1.1.8.2. Task WP8.2: Modelling, materials and tests for hadron beams

Progress towards objectives

The progress in the various activities is summarized:

1. The MERLIN C++ library for accelerator was improved and benchmarked against other

simulation results.

2. Theoretical studies on accidental beam impact on collimators with finite element codes

and hydrodynamics codes were performed. Experiments for benchmarking these results

have been performed at the HighRadMat facility at CERN.

3. The studies on novel metal diamond and in addition metal graphite composites were

continued very successfully by a joined effort of many WP8 participants. The material

was produced in suitable large pieces for collimators, tested for basic mechanical and

electrical properties. Samples have been irradiated and various pre- and post-irradiation

Page 55: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 54 / 123

tests were performed. Copper-Diamond and Molybdenum-Graphite materials provide

very promising results. They are now used for the construction of a future full scale LHC

collimator, which will be installed in the LHC during the present upgrade. The

experimental and theoretical studies will continue till the end of EuCARD and beyond.

A large new collaboration has been formed by the ColMat efforts on Metal-Diamond and

Metal-Graphite composite materials.

Copper-Diamond144 Buches from SPS

Molybdenum-Copper-Diamond144 Bunches from SPS

Figure 29: Samples of novel materials irradiated at HighRadMat

Contractual milestones and deliverables

No further milestones and deliverables were due in this reporting period.

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

CERN * *

GSI * *

CSIC * *

INFN * *

ULANC * *

UM * *

UNIMAN * *

Page 56: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 55 / 123

AIT * *

EPFL * *

RRC KI * *

POLITO * *

1.1.8.3. Task WP8.3: Collimator prototyping and testing for hadron beams

The goal of task WP8.3 is to design and manufacture prototypes of advanced collimators and to

qualify their performance for usage with high power hadron beams in FAIR and LHC.

Progress towards objectives

The goal of task WP8.3 was to design and manufacture

prototypes of advanced collimators and to qualify their

performance for usage with high power hadron beams

in FAIR and LHC. Both prototypes were produced,

tested and reported in previous reporting periods.

A bent Crystal Collimator has been manufactured at

INFN Ferrara. It was installed and tested with beam in

the SPS. A significant reduction of secondary

interaction compared to a regular absorber could be

observed proving that the primary particles where

channeled through the bent crystal planes.

Contractual milestones and deliverables

The deliverable report D8.3.1 was produced, including the optional crystal collimation studies.

Planning, deviations and corrective actions

Task on

schedule Ahead of

schedule

Minor delay Significant

delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

CERN * *

INFN * *

GSI * *

Figure 30: Strip crystal manufactured in

INFN Ferrara.Bent along 110 planes.

Length about 2 mm.

Page 57: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 56 / 123

1.1.9. WP9: Technology for normal conducting linear accelerators (NcLinac)

The WP focuses on major issues in high-gradient acceleration, beam stabilization, emittance

preservation and beam handling in the final focus.

Task WP9.1: Coordination and communication

Task WP9.2: Normal conducting high gradient cavities

Task WP9.3: Linac and final-focus stabilization

Task WP9.4: Beam delivery system

Task WP9.5 Drive beam phase control

1.1.9.1. Task WP9.1: Coordination and Communication

Progress towards objectives

The coordination between the different tasks has been smooth and natural. Areas that required

some effort were the coordination between task 9.2, looking at the CLIC high-gradient

accelerating and decelerating structures as part of the two-beam module (TBM) with all its

aspects of mechanical precision and tolerances, cooling and temperature control, stability and

the integration into the tunnel, and task 9.3, addressing the linac alignment and in particular the

investigation possibility to align stabilize of a main beam quadrupole mock-up, which of course

is also integrated with the TBM.

The coordination and communication activities also included the organization and planning of

the annual meetings and here in particular the parallel sessions and the satellite meetings, in

which the annual reviews were performed and which gave the possibility to bring representatives

of all tasks together face to face. This was done both in Warsaw in 2012 (see

https://indico.cern.ch/conferenceTimeTable.py?confId=166908#all.detailed) and at CERN in

2013 (https://indico.cern.ch/conferenceTimeTable.py?confId=234798#all.detailed). We

reported in detail on the progress of NCLinac on these meetings, complemented by highlight

talks on selected topics (2012: “Feedback performance, precision alignment and nanometer scale

stabilization of CLIC magnets” by A. Jeremie and “CLIC RF structure precise assembly and

thermo-mechanical modeling in CLIC” by K. Österberg, 2013: “Understanding the breakdown:

new prospects?” by F. Djurabekova and “Linac stabilization” by K. Artoos). Both these meetings

were at the same time used to prepare EuCARD-2, in which parts of NCLinac will find a logical

continuation (in 2 tasks in its work package 12, “RF Technologies”). Initiated also by the

excellent results of NCLinac’s work package 9.3, a special FP7 proposal for an initial training

network on metrology and alignment was very successfully rated and has now started

(http://pacman.web.cern.ch/pacman/). The highlight talks and the contributions by the different

partners to the EuCARD Newsletter, which later became the “Accelerating News”

(http://www.acceleratingnews.eu/) was the outreach created by NCLinac.

With the coordination and communication between the tasks of WP9 well established, but also

with excellent coordination inside EuCARD as a whole and in fact with the other active FP7

instruments in the field of accelerators and accelerator physics (HiLumi-LHC, TIARA,

EuCARD-2), NCLinac brought forward the field quite significantly, reflected also in the quantity

Page 58: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 57 / 123

and quality of the 100 publications created within NCLinac, available via the CERN Document

Server database (http://cds.cern.ch/collection/EuCARD);

Contractual milestones and deliverables

D9.1.1 was delivered.

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

CERN * *

RHUL * *

1.1.9.2. Task WP9.2: Normal Conducting High Gradient Cavities

Progress towards objectives

Double-length PETS – CIEMAT has successfully completed the design, assembly and test of

the first double-length PETS for the CLEX module. The design comprises eight identical copper

bars with damping material and two compact couplers placed at both ends of the bars to extract

the generated power. The first PETS unit was fully assembled (see Figure 31) and tested at low

power. The compact couplers were successfully brazed and electro-beam welded to the so-called

mini-tank. The geometrical control of the eight corrugated copper bars as well as of the compact

couplers was within specification. The measurements were cross-checked and confirmed at

CERN. For the RF characterisation, a dedicated system to measure the S-parameters was

developed by CIEMAT (see Figure 32 and Figure 33). The power transmission efficiency was

obtained by placing between the couplers several copper rings with different lengths

(corresponding to 0°, 60° and 120° phase advance). No significant de-tuning was observed. A

second PETS unit is currently under fabrication and planned to be completed in December 2013.

New companies have been qualified for this production.

Figure 31: PETS unit

Page 59: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 58 / 123

Figure 32: Bead-pull measurement test

bench

Figure 33: Bead-pull measurements results after final assembly

HOM damping – The UNIMAN collaboration is focused on a linac consisting of 26-cell

structures providing a 100 MV/m accelerating field and ensuring sufficient wakefield

suppression by interleaving different structures. The design for a 6-fold interleaved structure is

complete. Following a pre-series phase validated at CERN, the production of the entire structure

has been launched at Morikawa in Japan. The dimensional control of the disks and the

preliminary RF results (see Figure 34 and Figure 35) showed that the disks were acceptable and

that the structure could be tuned to reach the specification. Indeed, only few m errors have been

observed. The assembly consisting in bonding the disk stack and brazing the couplers onto it has

been completed. The cooling circuits will be brazed in September and the RF measurements and

tuning will follow. The structure is foreseen to be tested at high power in the year 2014.

A new cell design has been studied. It features improved overall wakefield suppression and

exhibits a larger 1st dipole bandwidth. An improved HOM coupling from cell to manifolds is

also proposed together with a reduced H-Field value on the cavity walls.

Figure 34: RF measurement test stand

Figure 35: Preliminary RF measurements

Breakdown simulation – UH continues to pursue a multi-scale model to understand electrical

breakdown in accelerating structures. One of the key findings is that dislocations are activated

in the near-surface region of accelerating structures during its operation by the stress. These

11.8 11.85 11.9 11.95 12 12.05 12.1-40

-30

-20

-10

0

Frequency (GHz)

S-P

ara

me

ter

(dB

)

1/2 (S11

+S31

+S13

+S33

)

1/2 (S22

+S24

+S42

+S44

)

Page 60: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 59 / 123

dislocations can contribute strongly in nucleating of rough features, which at a later stage can be

further enhanced by long-term processes such as, for instance, surface diffusion enhanced by

electric field and electro-migration due to high field emission currents. However, the studies

show that a void buried under the surface can initiate the self-reinforcing growth of a protrusion,

if a high electric field is applied to the surface (see Figure 36). This mechanism can be seen

experimentally in the catastrophic growth of field emission currents, measured in the DC setup

at random spots on a seemingly flat surface. These features (field emitters) on a nanometre scale

may lead to breakdown events, giving a possible resolution of the long-standing mystery of

vacuum breakdowns in the absence of sharp surface features.

Figure 36: Simulation of the creation of a protrusion

from a void due to stress

Figure 37: Fits of the breakdown rate as function

of the accelerating gradient

This mechanism is confirmed by the analysis of crater features seen in the high resolution

scanning electron microscope images of spots of breakdown damage.

At a different scale, an analytical model based on thermodynamic consideration of formation of

extended defects in thermodynamic equilibrium gave a solid ground to the experimental

measurements of breakdown rates versus accelerating gradients. The experimental data could be

fitted with comparable quality to the existing empirical fits (see Figure 37), however providing

a physical interpretation to the fit parameters, such as the formation energy to create a dislocation

or void and the volume change due to this dislocation. Moreover, the prediction of this

dependence to be non-linear with decrease of the value of the gradient was confirmed later on in

the experiments conducted at CERN.

A hybrid electrodynamics/molecular dynamics model with the focus on the electronic dynamics

has been developed. The Joule heating of thin protrusions leads to the evaporation of atoms,

assisted by the applied field. This comprises a neutral component necessary for plasma

formation. The results of a 2D particle-in-cell calculations show the necessity of greater flux of

neutral atoms for the plasma to develop until a sustainable stage. The existing 2D particle-in-cell

model was refined to increase the resolution near the source of the neutrals (a tip). This led to

the result indicating the possibility of full small plasma development close to the tip; the plasma

ions sputter the surface at the early stage of full plasma build-up, feeding back the developing

plasma.

Diagnostic equipment – The upgrade program of the two-beam test stand continued with the

installation of the flashbox (see Figure 38). Signals of breakdown were recorded and analysed.

A program was developed to increase the sensitivity of the probe beam position monitors. The

piezo-motor driven stage to investigate in-situ discharges inside an electron-microscope has been

Page 61: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 60 / 123

improved continuously and now permits scanning. Tests have been conducted on different

samples, which were then cut to investigate the presence of voids (see Figure 39).

Figure 38: Installation of flashbox in the two-beam test stand

Figure 39: Observed sub-surface voids

Precise assembly – UH continues the study on the high-precision assembly of RF structures and

several activities are on-going in parallel. The FE model of the two-beam module (see Figure

40) has been remarkably improved. In addition to the gravity, vacuum and RF loads, the

environment conditions (see Figure 41) have been added allowing thus to simulate the thermo-

mechanical response of the module following different ambient temperatures (from 20 ℃ to

40 ℃) and air speed (from 0.2 m/s to 0.8 m/s). The tests on the first module prototype (see Figure

40) started in January 2013. Several CLIC operation conditions have been tested by gradually

heating the different module components. In addition, by measuring the position of the fiducials

on the RF structures with the laser tracker Leica AT401, the alignment of the beam axes is also

derived. At the same time the temperature of the RF structures is monitored and recorded

throughout the tests by means of the sensors attached to them. The experimental results are in

good agreement with the model. Figure 41 shows the measured and predicted transient thermal

response of the accelerating structures by changing the ambient temperature from 20 ℃ to 30 ℃;

to be noted that the experimental transient time, almost twelve hours, is in agreement with the

results of the numerical modelling.

Page 62: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 61 / 123

Figure 40: FEA of the two-beam module

Figure 41: Environmental conditions of the two-beam

module

Figure 42: Prototype two-beam module

Figure 43: Transient thermal response of the accelerating

structures

Contractual milestones and deliverables

Deliverables 9.2.1 and 9.2.2 were delivered on schedule.

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

CIEMAT * *

UH/Simulations * *

UH/Assembly * *

UNIMAN * *

UU * *

Page 63: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 62 / 123

1.1.9.3. Task WP9.3: Stabilisation

Progress towards objectives

A prototype of the final mechanical guidance housing the actuators of the CERN stiff

stabilization system (see previous periodic report for unprecedented stabilization results) further

improved the resolution of the positioning and nano-metrology and increased the lateral stiffness

by a factor 500. A final mechanical design was made for a CLIC Main Beam Quad type 1 (100

kg, 0.5 m) and type 4 (400 kg, 2 m) based on aluminium profiles and plates (Figure 44). Supports

for the alignment sensors and the interface with the alignment system were also included in the

design.

Figure 44: a) Stabilisation system MBQ type 1 b) cut-away view with inclined actuators

A test bench representative of the stabilisation system (Figure 45) was built in order to house

several means to measure the relative displacement of the test mass. This allowed a comparative

study between strain gauges in the actuators, the voltage applied to the actuators, capacitive

gauges, a triple beam LASER interferometer, a broadband seismometer and an optical linear

encoder.

For the pre-alignment system, all the upgraded cam movers were validated successfully on a 1

DOF mock-up. Repeatability below 1μm was obtained throughout the whole measurement range

of 10 mm, and below 0.3 μm was over a reduced stroke of ± 3mm.

Figure 45: a) X-y guide prototype equipped with instrumentation, b) comparative study of sensors

Page 64: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 63 / 123

A 5 DOF mock-up was built for the final validation of cam movers and installed in one of the

most stable places at CERN. It consists of an instrumented rigid chassis, on which additional

loads can be put, installed on 5 cam movers. A mechanical system blocks the 6th degree of

freedom, along the longitudinal Z axis (Figure 46). The following results were obtained:

Movement resolution below 1 μm everywhere in the displacement range, repeatability below 5

μm for the two translation axes (X and Y), and below 5 μrad for the roll (rotation around the Z

axis), the correct position was found in 3 to 5 iterations without additional load (more iterations

were needed when load was added), displacement accuracy depends on the length and

complexity of displacement for example displacements accuracies are in the order of 10-20 μm

and μrad for the first iteration in case of simple movements.

Figure 46: 5-DOF mock-up coordinate system

These results showed that the type 4 cam mover based system meets precision requirements

using an iterative process. A more compact cam system is currently under development for the

alignment of the Main Beam quadrupole type 1. The first compact cam mover has passed 1 DOF

tests successfully.

For the Type 1 and Type 4 Main Beam Quadrupoles, the 2nd Generation iron quadrants of the

Type1 were delivered and mechanically measured at CERN Metrology Lab. The complex pole

shapes are well inside a ± 7µm tolerance and this is an extremely good result. The 2nd Generation

Type1 MBQ is now assembled. The procurement of the quadrants for the 2nd Generation Type4

MBQ (~1800 mm length) is still undergoing, due to the difficulties in finding companies

potentially able to provide ultra-precise machining on long components. The imminent magnetic

field quality measurement results should give an indication, on how these tight achieved

tolerances translate into a “beam optics quality” point of view.

Concerning the Intra-train beam stabilisation feedback prototypes for ILC and CLIC: The

upstream coupled loop feedback system was re-commissioned and its impact on the beam near

the IP was measured. For the purpose of obtaining optimal spatial correlation between bunches

in the extracted bunch train the ATF damping ring was set up to extract 2 bunches with a

separation of 274.4 ns. The upstream system was first set up and the optimal gain was selected.

The system was then operated in an interleaved mode with the feedback applied on alternate

machine pulses With the feedback off the second bunch RMS jitter was measured to be

(3.6 ± 0.2) μm in P2, (3.7 ± 0.2) μm in P3 and (3.9 ± 0.2) μm in IPA. With feedback on the

second bunch RMS jitter was measured to be (1.3 ± 0.1) μm in P2, (1.4 ± 0.1) μm in P3 and (2.6 ± 0.1) μm in IPA. The level of correction upstream is as expected given the bunch to bunch

correlations of 94% measured with the same data. At IPA it is clear that the level of jitter

reduction seen in the upstream system does not propagate downstream fully; work is currently

on-going to improve the propagation of the jitter reduction.

Page 65: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 64 / 123

Concerning the pulse-to-pulse feedback, different ground motion (GM) models have been used.

Simulations combining different controller strategies show that the GM model has an important

influence on the performance in terms of luminosity or offset. On a variety of reasonable GM

models, the scheme allows reaching an IRMS of the beam motion of about 0.2 nm @ 0.1 Hz

combined with other feedbacks leading to an average luminosity loss of less than 1.7%. Even if

some simplifications have been made concerning the transfer functions and the instrumental

resolutions, the results are well within the required performance to have enough margins when

the detailed accelerator component behaviours are known.

Contractual milestones and deliverables

The due deliverables D9.3.1 and D9.3.2 were delivered.

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

CNRS * *

CERN * *

Oxford * *

1.1.9.4. Task WP9.4: Beam Delivery System (BDS)

Progress towards objectives

Over the reporting period, the ATF2 laserwire (LW) program was completed with a

measurement of micron scale beams, resulting in uncertainties in the order of 10%; results have

been reported at IPAC2012 and IBIC2012. Outcome of this work is submitted as an article to

Phys. Rev. Special Topics, Accelerators and Beams. Also the ATF2 cavity BPM system could

be completed and is providing essential diagnostics information for ATF2, which recently

demonstrated focused beam sizes of 70 nm. The development work for advanced low-Q CBPMs

was finalized with a test of a low-Q stainless steel prototype, which showed good agreement

with RF simulations. The main developments for the LW during the reporting period were

conducted at PETRA3, where a fibre laser was used to generate laser pulses to collide with the

electron bunches. The development of this system is now complete and first measurements

completed. Two more weeks long measurement campaigns are planned before final publication

of the PETRA3 results.

Cavity Beam Position Monitors

The cavity beam position monitors (CBPM) installed at ATF2 were designed by KEK, built by

Pohang Accelerator Laboratory (South Korea) and are maintained and operated by RHUL in

collaboration with SLAC and KEK. RHUL provided the main readout and control code and

performed the operational support for the system.

Page 66: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 65 / 123

Figure 47: Photographs of the C- (left) and S-band (right) CBPMs installed inside ATF2 quadrupoles

Prototype cavity beam position systems (three devices) have proven position resolution at 10s of

nanometres. During the reporting period approximately 40 devices were thoroughly used and

tested at a test facility with similar features as a linear collider (LC). The experimental

methodology was elaborated and system performance studies in detail. Figure 47 shows

photographs of the installed C-band (left) and S-band CBPMs installed inside the ATF2

quadrupoles; a more detailed description is available in the deliverable report EuCARD-Del-

D9.4.2.

Laserwire scanner

Laserwires use a focused beam of laser light that interacts with the charged particle beam only

weakly to provide information on the transverse beam size. This method offers higher resolution

that classical methods, does not disrupt the beam but requires a complex high power laser system

and optical focusing.

A laserwire project was initiated at ATF/ATF2 in 2005 and over the last eight years has

progressed towards the final goal of micrometre scale beam size measurements. Royal Holloway

and the University of Oxford have constructed the entire laserwire system (apart from the laser

which was loaned from KEK). During the reporting period the laserwire has achieved its

technical goal measuring 𝟏 μ𝐦 vertical beam sizes, improving the state of the art from (𝟓 ÷ 𝟏𝟎) 𝛍𝐦 at the start of the project. Figure 48 below gives an example from a detailed

nonlinear vertical scan of an electron beam using 61 laser positions and 20 machine samples,

indicating a measurement of a beam size of 𝝈 = 𝟏. 𝟏𝟔 𝛍𝐦; for a detailed description and

complete results please refer to the deliverable report D9.4.2.

Page 67: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 66 / 123

Figure 48: Detailed nonlinear vertical scan of the electron beam

Contractual milestones and deliverables: -

The due deliverables D9.4.1 and D0.4.2 were delivered.

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

Manchester U. * *

RHUL * *

STFC/ASTeC * *

1.1.9.5. Task WP9.5: drive beam phase control

Progress towards objectives

Beam Phase Monitor

Prototypes of the beam phase monitor pickup have been completed and tested. Lab RF

measurements are in good agreement with simulations. In Figure 49 the simulation (plots at the

top) and measurement (bottom) results are compared. The plots on the left are the transmission

response between two of the four coaxial outputs, where the resonance of the volume between

the filters is visible. The plots on the right are the transmission between one coaxial output and

one probe placed at one pipe end. The effect of the notch filter is clearly visible. The additional

resonance at ~12.14 GHz in the bottom right plot is introduced by the measurement system and

it is due to a residual probe misalignment that produces excitation of parasitic modes in the

structure.

Page 68: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 67 / 123

Figure 49: Simulated (top, red) and measured (bottom, blue) pickup frequency responses

Subsequently, two other monitor prototypes have been built and installed at CTF3 in the transfer

line between the chicane and the Delay Loop, where the bunch repetition rate is 1.5 GHz. With

this arrangement, using the detection electronics, the bunch phases along the train have been

measured and the result is reported in the plot of Figure 50.

Figure 50: beam phase signals from two phase monitor in CTF3

Different outputs from the pickups have been observed to test the channel balance. The beam

has been transversally moved to measure the dependence on the beam transverse position. Both

tests have given successful results.

Electro-Optical Monitor

Page 69: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 68 / 123

Within the reporting period the following progress has been achieved:

Two types of beam pick-ups have been characterized with beam. Other than expected the high charge

design worked also best for the low charge regime and will be used for future designs.

The optical front end, which contains the fibre-optical and the opto-mechanical components

necessary to measure the cross-correlation between the laser reference and the electron bunch, was

produced and tested. With the results obtained, a second version was designed with vastly improved

local temperature stabilization to minimize drift effects.

We built a photo receiver and data acquisition using a 12 bit ADC with 500 MS/sec sample rate.

Control and read out were implemented using Matlab scripts.

In extensive beam tests of the full system, the correlation of the drift of the system versus

environmental variables as temperature, humidity and air pressure as well as the machine

parameters as beam charge and size were studied. The obtained time resolution was 20

femtoseconds, corresponding to 0.1° at the CLIC frequency of 12 GHz, which fits well the

required specification.

Contractual milestones and deliverables

The due deliverables D9.5.1 and D9.5.2 were delivered.

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

CERN * *

INFN/LNF * *

PSI * *

Page 70: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 69 / 123

1.1.10. WP10: superconducting RF Technology for proton accelerators and electron linear accelerators (SRF)

The main activities concentrate on two different areas: cavity improvements and beam

experiments. Improved methods for cavity treatment such as vertical electro-polishing or sputter

coating are investigated. Prototype work on superconducting (SC) crab-cavities is initiated with

the goal to increase the luminosity of colliders such as LHC, CLIC or ILC. The second research

activity concentrates on further developing Low Level RF techniques and on new diagnostic

tools based on the analysis of Higher Order Modes (HOM).

Task WP10.1: Coordination and communication

Task WP10.2: SC cavities for proton linacs

Task WP10.3: LHC & CLIC crab cavities

Task WP10.4: Thin film cavities

Task WP10.5: HOM distribution

Task WP10.6: LLRF at FLASH

Task WP10.7: SCRF gun at ELBE

Task WP10.8: Coupler development at LAL

1.1.10.1. Task WP10.1: Coordination and communication

Progress towards objectives

The fourth SRF Annual Review took place on 25-26 and 29 May 2013 as face-to-face meetings

between the Work Package leader and Task leaders, according to the following agenda:

25 May at DESY, for Tasks 10.8, 10.3, 10.5, 10.7 and 10.6

16 May at CERN, for Tasks 10.1 and 10.4

29 May at CEA, for Task 10.2.

This review was used to finalize the agenda of the missing deliverables and preparation of the

EuCARD Final Meeting on June 6, 2013. Only three Deliverables were still missing on May

29th:

D10.2.1: the cavity RF tests are scheduled in August and September 2013. These tests

are critical milestones for CEA and CNRS in view of their contribution to ESS project.

D10.4.2: the magnetron sputtering facility at INFN-Legnaro is operational and

preliminary tests are promising. No cavity was available for the coating and the RF test.

D10.4.4: due to the transfer of its main author to the ESS AB Company and the fact that

recovering from this situation turned out not to be possible, the only option was to re-

orient the study towards materials and surface aspects in the development of SRF

niobium cavities, including the initial focus of thin film cavities. An interesting outcome

is the write-up of a EuCARD Monograph by C. Antoine (CEA) on this specific topic.

Page 71: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 70 / 123

Contractual milestones and deliverables

D10.1.1 The SRF WP legacy is available via the EuCARD2 website http://cern.ch/eucard2

. The survey of all the past, present and projected SRF accelerators in Europe as well as their

basic parameters and the survey of the existing European SRF infrastructures are available on

the TTC home page.

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

CEA * *

CERN * *

1.1.10.2. Task WP10.2: SC Cavities for proton linac

Progress towards objectives

The first activity of this task has consisted in the fabrication follow-up of the two SPL type

elliptical cavities, manufactured respectively at RI and ZANON companies.

For the β=0.65 cavity, the kick-off meeting took place at RI premises in November 2011. The

manufacturing file was provided to IPN Orsay beginning of March 2012 and the official release

for fabrication was given 2 weeks after. The field flatness tuning process with the bare cavity

was originally planned in October 2012 (and delivery of the complete cavity with its tank in

February 2013) but, because mainly of the overload of the RI and subcontractors workshops, the

fabrication was delayed by more than 5 months. Several intermediate RF measurements of the

half-cells, dumbbells and end-groups have been done between January and February 2013 to

match the target frequency. Final measurement of TM010-π mode after welding and leak tightness

test was 703.265 MHz for expected 703.591 MHz. Because of the fabrication delay for this first

phase, we decided to prepare the cavity (field flatness and heavy BCP preparation) and to send

it back to RI for helium vessel welding before any vertical tests. So, we first BCP etched the

cavity surface of about 200 µm, then, we tune the cavity frequency and accelerating field profile.

The bare cavity was sent back mid of April and the delivery of the complete set (cavity with its

Titanium vessel) is foreseen in June 2013. Next step will be the preparation in clean room and

RF test in vertical cryostat at CEA-Saclay this summer.

For the β=1 cavity, the fabrication contract has started in April 2012. A review of the

manufacturing drawings has been done in July 2012. The forming of the cells by deep drawing

was performed in September 2012. Three sets of intermediate RF measurements on the half cells

and dumbbells have been organized at ZANON factory in presence of CEA. Two steps of RF

trimming were done on the four dumbbells and the two endgroups in order to tune each element

close to the target resonant frequency. After the final equator welding, the measured resonant

frequency of the accelerating mode is 703.747 MHz (703.04 MHz expected). Some upgrades of

the RF measurement tooling have been proposed to ZANON in order to improve the whole

procedure of frequency tuning before final welding. The cavity has been delivered to CEA

Page 72: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 71 / 123

without its helium tank in May 2013 for the field flatness tuning. The electropolishing, the clean

room preparation with high pressure rinsing and the test in vertical cryostat is expected before

August 2013.

Figure 51: β=0.65 bare cavity ready for field flatness tuning at IPN Orsay, and β=1 cavity after final welding at

equators

The second main activity of this work package has consisted in the development of the new

Vertical Electro-Polishing (VEP) set-up. Additional experiments on single-cell cavities have

been carried out with new set of parameters. The use of a low voltage (6V) associated with a

high acid flow rate (25 L/min) has improved the surface finishing of the cavity.

Two single-cell cavities have been tested:

- 1AC3 cavity reached an accelerating gradient of 34 MV/m after 250 µm VEP. The

gradient has been limited by quench, with a heating area located at pits which have appeared

during early treatments with unsuitable parameters.

- 1DE1 cavity reached an accelerating gradient of 42 MV/m after 70 µm VEP. This cavity

has been previously treated on a standard Horizontal Electro Polishing (HEP) system and baked.

This result demonstrates that HEP and VEP configurations offer the same performances for this

cavity in term of gradient and improvement after baking.

Page 73: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 72 / 123

Figure 52: RF result of 1DE1 after 70µm VEP and associated inner surface

Furthermore, VEP process with optimal set of parameters has been applied on a nine-cell ILC

type cavity from FERMILAB (initially horizontally electropolished). It was vertically

electropolished with the parameters previously described (~50µm removal). The observed

surface aspect on 1-cell and 9-cell cavities seemed similar. However, the achieved performance

on the 9-Cell cavity is limited due to heavy field emission. New VEP and RF test sequences are

planned to totally remove field emission.

Figure 53: RF ILC cavity installed on the VEP set-up before treatment and VT results

Contractual milestones and deliverables

M10.2.1 Cavity fabrication: completed on M50 for β=1 cavity and M51 for β=0.65 cavity.

D10.2.1 Results of SC proton cavity tests (β = 1 and β = 0.65): delayed to M54 with an

intermediate deliverable report at M52.

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

The fabrication time of the cavities has been further delayed from the 9 months proposed by

companies during the call for tender, to 12 and 16 month delay.

Page 74: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 73 / 123

The preparation and test of the cavity prototypes is planned in September 2013.

Estimate of use of resources

1.1.10.3. Task WP10.3: LHC & CLIC Crab Cavities (CC)

Progress towards objectives

The LHC-CC prototype fabrication at Niowave Inc. (not foreseen in the EuCARD contract) has

been completed and the cavity has been provisionally processed at CERN (see Figure 54 a) and

a first vertical test performed. The testing at SM18 was restricted due to a vacuum leak, however

the low field performance achieved was encouraging with respect to further testing to be

undertaken (see Figure 54 b). An optimised coaxial input power coupler has been developed

which is identical to the existing LHC accelerating mode cavities (see Figure 54 c) and a loop

type coupler has been developed for damping the LOM and HOM impedances (see Figure 54 d)

with integrated optimisation performed to achieve the required mode damping performance

required (see Figure 54 e).

1a) 1b) 1c)

1d) 1e)

Figure 54: a) LHC-CC Preparation @ CERN, b) Testing @ SM18, c) Input Coupler Design, d) LOM Coupler

Design and e) LHC-CC Mode Impedances

Two CLIC-CC prototypes have been manufactured for high gradient testing, one by UK

industry (see Figure 55 a) and the other by CERN (see Figure 55 b) using the same manufacturer

as the main CLIC linac cavities. A conventional dual-feed input coupler has been developed to

transversely symmetrise the deflecting field (see Figure 55 c), with waveguide couplers proposed

to control the lower, same and higher order modes (LOM, SOM, HOM), with the most

threatening SOM requiring a damping to the order of Q ~ 100 (see Figure 55 d).

Personnel Material

Partner ++ + = - -- ++ + = - --

CEA * *

IN2P3 * *

Page 75: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 74 / 123

2a) 2b) 2c) 2d)

Figure 55: a) CLIC crab cavity fabrication by UK industry, b) Prototype CLIC crab cavity being fabricated at

CERN, c) CLIC-CC RF input coupler and d) Mode coupler configurations

For the CLIC-CC timing and synchronisation system, beam pick-up monitors and a suitable

LLRF board have been developed, using standard analogue controllers which already exist at the

CERN high power test stand, to achieve the required CLIC klystron to beam synchronisation

requirement of 5 fs. A control system model has also been developed to assess the performance

requirements for the LHC-CC system in the presence of beam. Beam protection issues

associated with a cavity quench and other failure mechanisms have been investigated and a

performance assessment of the LHC-CC in a de-tuned state compared to its normal RF operating

mode has been performed.

3a) 3b)

Figure 56: a) CLIC-CC LLRF Digital Sampling and b) LHC-CC Detuned Cavity Performance.

Contractual milestones and deliverables

M10.3.3 LHC Input & LOM Coupler Design: amalgamated to Deliverable D10.3.1.

M10.3.6 CLIC Input & Mode Coupler Design: amalgamated to Deliverable D10.3.2.

M10.3.7 LHC CC LLRF Prototype: amalgamated to Deliverable D10.3.3.

D10.3.1 LHC CC Final Report: completed on M47

D10.3.2 CLIC CC Final Report: completed on M47

D10.3.3 LHC and CLIC LLRF Final Report: completed.

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

CERN * *

STFC * *

ULANC * *

I and Q cavity voltages for (RF off, +detune 80 bandwidths, +retune, RF +set point = 10000)

-40000

-30000

-20000

-10000

0

10000

20000

30000

0.0E+00 5.0E+05 1.0E+06 1.5E+06 2.0E+06 2.5E+06 3.0E+06 3.5E+06

Time (ns)

Vo

lts

Revolution Period

Real Amplitude

Imaginary Ampitude

Page 76: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 75 / 123

UNIMAN * *

1.1.10.4. Task WP10.4: Thin films

Progress towards objectives

The different tasks have made good progress. The development of the magnetron sputtering

technique at Legnaro has reached maturity. The RRR of the Nb sputtered samples was increasing

when increasing the power of sputtering. RRR values as high as 22 were obtained. In addition

the Nb film is uniform all over within the cavity. The deposition rate is also very promising: 1

micron in about 15 minutes is more than 10 times faster than the biased diode technique.

Legnaro is now fully ready to test this technique on a real cavity. However, due to the delays in

the production no cavity could be delivered to Legnaro yet. It is expected that the test could occur

after the summer.

The work in Lancaster was discontinued due to the departure of the person in charge. However

the topics have been addressed by Claire Antoine (CEA) in Chapter 5 of her EuCARD report

“Materials and Surface Aspects in the Development of SRF Niobium Cavities” (Vol. XII of

Editorial Series on Accelerator Science), which constitutes the groundwork for the new Thin

Films task of EuCARD2 which will address Hc1 improvements, ALD multilayers and Nb3Sn

thin film production, as well as new thin films test facilities (3rd harmonic Hc1 measurement).

Contractual milestones and deliverables

M10.4.3 QWR sputtering with Nb using the magnetron technique: deposition parameters

have been validated with a stainless steel cathode. Due to the delays in the production no cavity

could be delivered to Legnaro yet but a novel sputtering set-up was thoroughly tested, leading to

a possible patent application.

D10.4.2 RF measurements on thin film deposited QRW prototype: delayed to M48

This deliverable suffered from delayed availability of resources from INFN.

D10.4.4 New thin film techniques for SC cavities and photo cathodes: Final Report:

completed on M47.

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

CERN * *

CEA * *

ULANC * *

DESY * *

INFN * *

Page 77: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 76 / 123

CNRS * *

SINS * *

1.1.10.5. Task WP10.5: HOM distribution

Progress towards objectives

During the 3rd period, we have achieved our final goal within EuCARD of proving that HOM-

based Beam Position Monitors (HOMBPM) can be built for the 3.9 GHz accelerating module

(ACC39) in FLASH.

Sub-task WP10.5.1

Further analysis of the data collected with test electronics in Period 2 and defining the

specifications for the HOMBPM-electronics has been achieved. Although not the same

resolution can be achieved as for the HOMBPMs previously installed at 1.3 GHz in FLASH, we

have shown that the performance achieved with the test electronics, and therefore the one

expected to be achieved with the final one, will be an essential tool in aligning the beam on the

cavity axis, and reducing the beam-excited wakefields. Figure 57 shows the power integrated

around 5.44 GHz measured from each of the 8 HOM couplers as a function of the horizontal and

vertical magnetic steerer current, which is proportional to the beam position. Although each

distribution is different, due to the different ways that the various modes couple to each coupler,

they show a common minimum, which is the aim of the beam alignment procedure. The power

distribution has been studied also with trapped modes in the 5th dipole band. Herewith the

milestone 10.5.1 has been fulfilled.

Figure 57: HOM power around 5.44 GHz for each of the 8 HOM couplers

Based on these results, we decided to build two versions for the HOMBPM-electronics for

FLASH: one based on propagating modes around 5.44 GHz for precise beam position

measurements, and one using trapped modes around 9.06 GHz for localized measurements, both

with a bandwidth of 100 MHz. Two modules of the first type and six of the later will be built at

Fermilab. We expect to get similar or better performance as with the test electronics developed

within the EuCARD project.

Sub-tasks WP10.5.2 and WP10.5.3

Page 78: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 77 / 123

They deal with the simulation of radio-frequency properties of ACC39. After creating and

validating computer models in the previous periods, one focus of the 3rd period was the

construction of model order reduction techniques, which are capable to determine secondary

quantities for multi-cavity structures apart from scattering parameters (external quality factors

or transient system responses). Proofs of principles for these methods have been presented

already for simple superconducting radio frequency structures (see literature). Beside of this

theoretical work, the influence of geometrical variations of individual cells in a nine-cell

resonator on the transmission spectra is investigated. The question whether the location of a

perturbed cell in the resonator is simply determinable by looking at the S-parameters was of

special interest. However, this turned out to be very difficult (inverse field problem) and needs

further investigations. Another focus was the dependency of the transmission spectra on input

coupler reflections (refer to Figure 58). Here it turned out that especially the second dipole

passband is very sensitive with respect to input coupler reflections.

Figure 58: CSC simulation of transmissions from one HOM coupler to the other through the cavity depending on

the complex reflection factor Γ at the input coupler (black: transmission assuming no reflection at input coupler

Γ=0, red: transmission for a reflection factor of Γ ≈ -0.57 +0.3 j at the input coupler)

Contractual milestones and deliverables

M10.5.1 HOM alignment for 3.9 GHz cavity electronics verification: completed on M47.

D10.5.1 HOM electronics and code to probe beam centring on 3.9 GHz cavities:

completed on M50.

D10.5.2 Report on HOM experimental methods and code: completed on M51.

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

DESY * *

Page 79: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 78 / 123

UNIMAN * *

UROS * *

1.1.10.6. Task WP10.6: LLRF at FLASH

Progress towards objectives

After getting first results from system operation some system components were modified and

upgraded.

Multichannel Downconverter

The module performs the role of a field detector in the LLRF system. It has been optimized for

an input frequency of 1.3 GHz, a heterodyne of 1.354 GHz and an intermediate frequency of 54

MHz. High performance (low noise, good linearity, low crosstalk) has been verified in 2102 by

measurements of the final revision of the board (Figure 59).

Improved Vector Modulator

The vector modulator board performs the role of an actuator in an LLRF control system. The

RTM form factor provides enough space for two channels. The second channel will be used in

the future to perform system calibration. After extensive tests and requests for new features a

second revision of the board has been developed in 2012 (Figure 60shows a render).

Figure 59 Final revision of the

downconverter module.

Figure 60: Improved vector

modulator module.

Figure 61: RF backplane

assembled in uTCA crate.

Synthesis and distribution of clock and reference signals in xTCA system

The RF backplane has been developed for the MTCA crate used in the LLRF system in order to

increase reliability and maintainability and to reduce the limitations arising from RF cabling. It

distributes high quality LO (local oscillator) and reference signals as well as low-jitter clock

signals. Low-noise analogue power supply is provided to analogue RTM modules. Final revision

of the board is still under tests. The final board installed in the MTCA crate is shown in Figure

61. In June 2012 the patent application for RF backplane was filled in.

Development of an AMC module with fast radiation sensors

It should be mentioned that on 9.01.2013 the patent was granted for “Solid State Neutron

Detection System” (EP 1 729 149 B1). The EuCARD predecessor CARE project supported this

work. It was a base for current development of the radiation monitoring board. During the

reporting period the AMC module for radiation monitoring has been redesigned to fit into

daughterboard of the FMC module.

Page 80: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 79 / 123

Figure 62: FMC carrier module

dedicated for LLRF Control System

Figure 63: FMC Radiation Monitoring Module with R.E.M (left) and

Tyndall (right) RadFETs dosimeters

The radiation sensors were also calibrated at the FLASH tunnel, during normal accelerator

operation. The obtained results are presented in Figure 64.

Figure 64: Gamma dose and SEU registered in FLASH tunnel during two weeks operation

System installation and performance evaluation

The developed LLRF system has been installed in the FLASH accelerator (Figure 65) and

commissioned during maintenance periods. The integration of the system components were

successful, some appearing difficulties were corrected in the next versions of system

components. The system was tested with and without beam. The example of achieved

performance is presented in Figure 66 where the field stability (with beam presence) was of order

of 10-4.

Page 81: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 80 / 123

Figure 65: LLRF system installation at FLASH tunnel

Figure 66: the RF field stability in the presence of the beam. Distortions are of the order of 10-4.

Contractual milestones and deliverables

M10.6.5 Report on tests and calibration of the radiation dosimeter: completed on M48.

M10.6.10 Report on longitudinal beam parameter studies and their controllability by fast

feedback systems in conjunction with the LLRF system: completed on M37

D10.6.1 Report on system test and performance, delivered.

Additional result: patent application for RF backplane

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

DESY * *

TUL * *

Page 82: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 81 / 123

WUT * *

IFJ-PAN * *

IPJ * *

1.1.10.7. Task WP10.7 SCRF gun at ELBE

Progress towards objectives

Sub-task WP10.7.1: Slice emittance measurements of the SRF gun

This subtask was successfully finished within time. The final report was delivered in month 26.

The work was presented on the DIPAC´11 workshop and the EuCARD 2nd Annual Meeting.

The PhD student, Jeniffa Rudolph, who was responsible for the scientific part in this subtask

defended her thesis “Instruments and techniques for analysing the time-resolved transverse phase

space distribution of high-brightness electron beams” with great success in 2012.

Sub-task WP10.7.2: GaAs photo cathode

The work for the development of an advanced preparation system was continued. In the previous

part of the project (1) the existing system for CsTe cathodes was extended, and later (2) a new

small separate preparation system was build. In both systems the preparation of GaAs

photocathodes was tested, but without success. In the first system, the contamination and the

space for the installation of the components cause major problems. In the second chamber, the

unsatisfied vacuum was the main problem. Activation of GaAs wafers could be performed, but

the quantum efficiency was low and the lifetime was extremely short. The design of the small

preparation chamber and the results of the measurement tests are presented in the final report

D10.7.2. The conclusion of the project results is, to develop a more advance system which

includes the experience of the previous work and state-of-the-art technique in this field:

split of the cathode body and the new plug,

only the plugs are treated in the preparation system,

design of preparation system which can be installed near the electron gun,

using different chambers for cleaning, transfer and preparation.

Furthermore a standard design of the photocathodes, plugs and storage chambers was fixed

between the German institutes HZB, HZDR and University of Mainz. This required a further

redesign but will allow the exchange of photocathodes for tests and characterization between

these institutes in the future. HZDR gives additional funds for investment for this project of 200

k€ in 2012 and 2013. CAD design pictures are shown in Figure 67.

Page 83: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 82 / 123

Figure 67: Design of the new exchangeable cathode plug for GaAs (left) and the new preparation chamber with

the interface to the gun and the transport chamber

Sub-task WP10.7.3: Evaluation of critical Issues of SRF guns

A substantial progress was the delivery of the new two-channel UV driver laser for the gun in

2012. The work in this subtask was aimed to the following topics:

• Bunch compression studies and measurement of the longitudinal phase space applying the

phase scan technique.

• Operation of the gun with high average current and photocathode lifetime studies. With new

driver laser the average current could be increased up to 350 µA. The latest result is the

extraction of >300 C from a Cs2Te photocathode at a typical current of 300 µA.

• The dark current investigations were continued with comparative study for a series of different

photocathodes, and energy spectra were determined.

• A remarkable progress was the first FEL operation with the SRF gun at ELBE in April 2013.

Contractual milestones and deliverables

M10.7.3 GaAs photocathodes produced: amalgamated to Deliverable D10.7.2.

D10.7.2 Results for GaAs Photocathodes: completed on M48.

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

FZD * *

HZB * *

1.1.10.8. Task WP10.8: Coupler Development at LAL

Progress towards objectives

Subtask 10.8.1: Plasma cleaning of couplers

Page 84: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 83 / 123

During the last period, surface treatment tests by plasma discharge were performed on coupler

cold part surfaces. The efficiency of the discharge in surface carbon removal was approved.

However, due to the presence 10% of oxygen in the gas discharge, an increase of oxides in

coupler surface was also observed which leads to the deterioration of coupler performances

(decrease of the RRR parameter). An optimization of gas discharge composition is needed to

avoid such effect. The changes in surface composition cause an increase of its roughness. This

effect is benefic for the RF conditioning process as it causes the lowering of surface secondary

electron emission yield (SEY). This observation must be confirmed by SEY of copper samples

before and after plasma treatment. In addition to an RF conditioning of the coupler part once the

process is fully optimized.

Subtask 10.8.2: Automatic couplers cleaning

After a first study phase providing the machine basic functions and all the components needed

for the cleaning process, a second extensive one was performed to choose the appropriate

technique among available solutions for the different functional steps. Thus, the machine design

evoluate continuously along the study advancement and the fixed choices.

Figure 68: Coupler cleaning machine evolution

Today, the internal and external mechanical structure ensuring functional motions of the system

are defined and its cost is estimated. The same is true for the ultrasonic system representing the

cleaning element. The specifications on hydraulic and air retreatment network are now well

defined, the drawings are ready and the cost is estimated. Further studies are on-going to optimise

the best technical solution for these two items.

Generally speaking, the studies are complete enough to give us a complete overview and

estimation of the feasibility, the process and the cost: the efficiency of the process, as far as the

large mass production is concerned, is undisputed. All the technical functions can be respected

to clean couplers automatically and correctly, without any damage for them.

Contractual milestones and deliverables

M10.8.1 Argon discharge cleaning and HPR results and analysis: amalgamated to D10.81.

M10.8.2 Automatic cleaning procedure: amalgamated to D10.81.

D10.8.1 Test and operation of the coupler preparation procedure: completed on M50.

!WP#10.8.2#

LABORATOIRE DE L’ACCELERATEUR LINEAIRE SERVICE MECANIQUE (SDTM)

Bilan d’avancement : Etat d’avancement au 09/04/13

Rédacteur : Damien LE GUIDEC Date : 09/04/13

Réf. I73-NI-SDTM-001-Avancement_09.04.13 Edms : I-xxx

Page 5 sur 8

!!

LABORATOIRE DE L’ACCELERATEUR LINEAIRE - Campus Universitaire – Bât 200 – BP34 – 91898 ORSAY Cedex Tél. 01 64 46 83 00 – Fax 01 69 07 94 04

II. The automatic cleaning machine : A.L.I.C.E.

(Automate de Lavage Intégré pour Coupleur Electromagnétique)

The automatic process leaded to the next mechanical designs :

!Figure&4&:&A.L.I.C.E.&evolution&

Page 85: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 84 / 123

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

LAL * *

Page 86: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 85 / 123

1.1.11. WP11: assessment of novel accelerator concepts (ANAC)

WP11 ANAC is the ensemble of three R&D tasks of quite different nature and status, all

pertaining to novel accelerator concepts not covered by the other work packages:

Task WP11.1: Coordination and communication

Task WP11.2: Design of interaction regions for high-luminosity colliders

Task WP11.3: Upgrade of the EMMA FFAG Ring

Task WP11.4: Instrumentation for laser-plasma wake-field accelerators

1.1.11.1. WP11.1: coordination and communication

Progress towards objectives

The WP11 web pages have been kept up-to-date with announcements of events, publication of

reports, meetings organized and other useful scientific information

(https://espace.cern.ch/EuCARD/WP11/default.aspx).

The preparation of the last deliverable of the WP was followed up.

Contractual milestones and deliverables

Milestones M11.1.4 was suppressed as not needed.

Planning, deviations and corrective actions

Task on schedule Ahead of schedule Minor delay Significant delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

INFN * *

STFC * *

1.1.11.2. WP11.2: Design of IR for high luminosity colliders

The main purpose of Task 11.2 was to prove the compatibility of large magnetic detectors with

a new collision scheme based on large Piwinski angle, low–β and Crab-Waist compensation of

the synchro-betatron resonances. Subtask 11.2.1 aimed to apply this collision scheme to the new

DAΦNE Interaction Region (IR) for the upgraded KLOE-2 detector running same time Subtask

11.2.2 has studied the possibility to use the Crab-Waist collision scheme for the luminosity

upgrade of the LHC. Both subtasks have been successfully completed.

Progress towards objectives

Sub-task WP11.2.1 development of a high luminosity Interaction Region for the KLOE-2

experiment at DANE

Page 87: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 86 / 123

The work foreseen for this EuCARD Task was successfully completed in April 2011 (P2).

The reminder of the EuCARD period has been aimed at optimizing the collider performances in terms of

luminosity for the data-taking for the KLOE-2 experiment. Figure 69 shows a sketch of the final KLOE2

Interaction region.

Figure 69: KLOE2 upgraded IR

Several hardware upgrades have been done in order to improve the collider performances. Among these,

the installation of “clearing electrodes” in the dipole and wiggler vacuum chambers of the positron ring,

to have an almost complete neutralization of the emitted photo-electrons in the e-cloud instability

formation. The experimental measurements on the electrodes effectiveness in mitigating the electron-

cloud effects have proved that they work in increasing the threshold current at which the instability occurs,

so allowing for a higher injected positron current. In Figure 70 the horizontal instability growth rate as

a function of the electrode voltage, as measured using the bunch-by-bunch feedback, is shown.

Figure 70: Horizontal instability growth rate as a function of the electrode voltage, as measured using the bunch-

by-bunch feedback in the positron ring

Page 88: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 87 / 123

A massive campaign for further hardware upgrades has been conducted during the 2013 shut-down

(required to install the new layers of the KLOE-2 detector), both in the rings and in the injection complex.

This work will continue after the end of the EuCARD project.

Sub-task WP11.2.2 study of a high luminosity Interaction Region for LHC

The work for Subtask 11.2.2 was delayed due to the problem in recruiting manpower at CERN. This

problem was solved and a doctoral student position was awarded starting from November 2010. For these

reasons the Deliverable 11.2.2 (Study of an IR design for LHC upgrade, CERN) was postponed to M48.

An elegant conceptual optics solution for a future LHC luminosity upgrade, combining flat beams, local

chromatic correction, large Piwinski angle and the option of crab-waist collisions. The scheme requires a

non-zero slope of dispersion at the IP and a new single-aperture final focusing element, which combines

dipole and sextupolar field components. The quadrupole feed down field focuses both beams in the

vertical plane. The sextupole component together with the non-zero dispersion is used to correct the

chromaticity locally. Orbit, dispersion and beta functions were matched to the existing LHC arcs.

Dynamic aperture is still a concern. The geometric aberrations could be corrected perfectly by a second

sextupole if the magnets were short. However the double half quadrupole is quite long, which introduces

intrinsic octupolar aberrations in addition to rendering difficult the compensation with a second sextupole.

A segmentation of the final quadrupole, to confine the sextupole field to a shorter region, is proposed as

mitigation. A similar final focus system, for a single beam was designed and qualified for the LHeC.

Possible merits of, and parameters for, applying the described approach at the HE-LHC have also been

investigated. Successful beam experiments testing key concepts, like crab-waist, large Piwinski angle and

flat beams, were conducted, analysed and prepared at DAΦNE and at the LHC, respectively.

Contractual milestones and deliverables

Deliverable 11.2.2 (Study of an IR design for LHC upgrade, CERN) delivered.

Planning, deviations and corrective actions

Sub-task

WP11.2.1

Completed during period P2

Sub-task

WP11.2.2

On schedule Ahead of schedule Minor delay Significant

delay

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

INFN Contribution completed during period 2

BINP Contribution completed during period 2

CERN * *

CNRS Contribution completed during period 1

1.1.11.3. WP11.3: Upgrade of the EMMA ns-FFAG ring

The aims of task WP11.3 was the design and construction of the EMMA diagnostic devices and

the completion, installation and commissioning of the EMMA ring.

Progress towards objectives

The work foreseen for this EuCARD Task was successfully completed in April 2011 (P2).

Page 89: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 88 / 123

In P3, the following experiments have taken place. For the acceleration of muons, the acceptance

of the accelerator and the dependence of the time of flight of a particle around the accelerator on

the distance from the ideal orbit have both been measured. The latter is as expected. The

measured acceptance is ~1 π mm mrad. Further studies of the COD have been made and an

additional source of perturbation in the horizontal plane identified: the stray field from the

injection septum. In the longer term, it can be fixed by replacing this device, but in short term

corrections have been found which reduce the COD both horizontally and vertically.

More general studies have also been undertaken. These include a successful experiment to

demonstrate the principle of phase rotation planned for the PRISM project. Work is also on-

going to study the effect of tune crossings. In particular, it has already been shown that these

crossings have no impact when the beam is accelerated at the fast rate required for muon

acceleration. The question remains how slow the acceleration can be before these crossings

become a problem. This is important for the use of this type of accelerator for the acceleration

of non-relativistic particles, especially protons, for a variety of medical and other applications.

Contractual milestones and deliverables

Contribution completed during period 2.

Planning, deviations and corrective actions

Contribution completed during period 2.

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

STFC Contribution completed during period 2

HUD Contribution completed during period 2

1.1.11.4. WP11.4: instrumentation for novel accelerators

Task WP11.4 aims to study new instrumentation to diagnose parameters, such as emittance or

relative energy spread, of electron beams produced by laser plasma accelerator. An experimental

methodology is needed because of the present produced low shot to shot reproducibility. The

study will take different approaches for measuring the emittance of these electron beam delivered

by laser plasmas accelerators.

Progress towards objectives

The work foreseen for this EuCARD Task was successfully completed in April 2011 (P2).

Studies have continued on the source and influence of the electron angular momentum. This

came as a surprise because injection models predict that electrons should be injected in the

accelerator with a zero angular momentum. The growth of the angular momentum was explained

by the fact that the laser pulse creates an asymmetric plasma cavity (because it is itself

asymmetric). Electrons which are accelerated in this cavity oscillate with different frequencies

along the two transverse directions, inducing an evolution of the electrons' angular momentum

during the acceleration. This explanation for the origin of the angular momentum is supported

by experimental results and simulations, which agree very well. For example, Figure 71 shows

Page 90: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 89 / 123

that for a cavity ellipticity of 20%, a very good agreement between simulations and experiments

is obtained. Thanks to this result, the simulations could be used to estimate the emittance using

both the spatial and spectral measurements. Doing so an emittance of 1 π.mm.mrad was found,

consistent with previous estimates and particle-in-cell simulations. This result comforts the

Deliverable of WP11.4.

Figure 71: Variation of the flatness, the curvature and the ellipticity during the acceleration. The red triangles

correspond to simulations, the blue circle to the experiment

Contractual milestones and deliverables:

Contribution completed during period 2.

Planning, deviations and corrective actions

Contribution completed during period 2.

Estimate of use of resources

Personnel Material

Partner ++ + = - -- ++ + = - --

CNRS Contribution completed during period 2

INFN Contribution completed during period 1

Page 91: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 90 / 123

2.3 PROJECT MANAGEMENT DURING THE PERIOD

In this last project period, the focus of the management has been to simultaneously maximize the

S/T activities outcome, mitigate the exceptional documentation effort requested from all

researchers and coordinators while maintaining a collaborative spirit by organizing a smooth

transition to EuCARD2 and creating a final brainstorming event around the medium term future

of accelerators for research and applications.

1.1.1. Consortium management tasks and achievements

EuCARD has continued benefitting from stable environment and priorities. Even though the

collection of report of activities and of deliverables remains somewhat challenging, the

significant experience accumulated by the management bodies, Governing Board, Steering

Committee and Project Coordinator on one hand, and the standardized project management

instruments on the other hand, now well-known from all participants, have allowed a smooth

P3 exercise.

The P2 periodic report was delivered with a minor delay. One of the report requirements, given

the large scope and number of tasks of the project, is to efficiently summarize the project

activities using a standardized reporting format experimented in P1 and for interim reports. Each

project task, in most cases involving the collaborations of several partners, is allocated a single

page for scientific progress and achievements, ½ page for management information (schedule,

use of resources) plus space for pictures. This compactness requires a special effort from

researchers, task, work package and project coordinators in selecting the essentials for

presentation, in a way respecting the efforts from 38 partners.

Special care was allocated to the concluding EuCARD meeting, with the goal of maintaining the

spirit of collaboration and hand it over to EuCARD2 or other ventures: The first meeting day

was dedicated to the report of EuCARD achievements from a managerial point of view, with a

final assessment by the Governing Board. The next two days were organized as a workshop with

the ambitious theme of ‘visions for the future of accelerators” for the next 50 years. The invited

speakers were for many world experts, with a significant EuCARD participation, and the

response to this challenge was excellent, as well as the attendance of all parts of this

concluding/workshop/kick-off meeting. The scientific organization of this workshop was a

collaboration of the EuCARD and EuCARD2 project coordinators, and of the coordinator of the

very successful EuCARD WP4 “Accelerator networks”. One of its sessions was covered by the

CERN communication team, with an article in the CERN Courier. The technical organization

was carefully prepared by the project assistant, with help and sponsoring from CERN. Always

in the spirit of consolidating collaborations, the project assistant organized the NBI2012

workshop in support of WP3. She equally gave support to the ESGARD committee meetings,

the meetings at CERN of FP7 ICAN and the activity of FP7 CESSAMag.

EuCARD being extended by 4 months with conditions, the Administrative Manager gave support

to many partners in the interpretation of the conditions.

An important dimension of the management activity and results for EuCARD is the external

relations, both to keep EuCARD in line with the trends in the field and to contribute to sustained

collaborations in the community. This is reported in sections 2.3.7 and 2.3.8.

Page 92: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 91 / 123

1.1.2. Budget adjustments

No budget adjustments needed to be carried out during the reference period. The final

distribution of the EC funding to each beneficiary will be decided by the Governing Board after

the submission of the final report, taking into account the estimated full costs incurred by each

partner with respect to the commitments in Annex I.

1.1.3. Problems and solutions

During Period 3, the project has not faced significant problems that could not be essentially

resolved at the task’s level.

1.1.4. Changes in the consortium and/or legal status of beneficiaries

No changes were recorded in this last EuCARD period.

1.1.5. Project meetings

The meetings of the whole project and of its Governing Board and Steering Committee are given

in the next table.

Dates Type of meeting Venue Attendance

24-27/04/2012 3rd EuCARD annual project meeting Politechnila

Warszawska,

Poland

88

6&7/12/2012 Steering Committee (face-to-face and audio) Uppsala & CERN 14

7/03/2013 Steering Committee (audio-conference) CERN, Geneva, CH 13

10-14/06/2013 Concluding EuCARD annual project meeting and

workshop, and kick-off meeting of EuCARD2

CERN 189

10/06/2013 Concluding combined Governing Board and

Steering Committee meeting

CERN

1.1.6. Project status

At the end of the project, almost all milestones have been met, not more than 10% had had to be

rescheduled due to delays, some were fulfilled ahead of schedule and a minor number were either

cancelled for lack of relevance, or combined with their respective deliverables. Milestones have

played an important role in monitoring the progress towards deliverables, as most deliverables

are by essence scheduled at the project end.

Out of 63 contractual deliverables,

59 are delivered as planned.

Page 93: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 92 / 123

one is delivered by another partner of the collaboration, after the resignation of a key

person at the lead partner. This deliverable is as well published in the EuCARD

monograph series.

three important deliverables will be fully documented during the project but will reach

full completion after the project end: one with about a one month delay (super-

conducting proton cavities), another with a five month delay (HTS insert) and the third

one with a delay estimated at 1.5 years. In the first case, the delay is explained by a

delayed order, following an unexpected cost increase, requiring the mobilization of

unplanned partner funds. In the second case, initial technical difficulties in this risky

R&D line are at the origin of the few month delay. All components have been

delivered, but the assembly and test will be carried out in the last part of 2013. In the

last case (High Field magnet model), 50% of the delay is due to the case of force

majeure after the LHC incident, where all magnet engineers were mobilized for the

repairs during one year. The other 50% are explained by additional iterations that

became required, given this new and very challenging technology, in agreement with

the recommendations of an international expert committee. The progress made by the

European team is judged excellent by the US experts, where much larger funds have

been dedicated to the topic over two the last two decades.

The two EuCARD Transnational-Access facilities have fully fulfilled their objectives and

beyond. WP5 had suffered a delay of 2 years due to the LHC incident; its very efficient recovery

has allowed fulfilling the contract. WP6 almost doubles its contractual commitment, by a strict

control of expenses and the donation of the TA management time by STFC.

WP5: HiRadMat@CERN WP6:

MICE@STFC

access units delivered (contract/achieved) 50/75.5 3384/>6000

# of requests (received/accepted) 16/9 12/12

# of users supported (estimated/actual) 20/10 28/40

# of different institutes 4 6

# of publications 30 >18

Finally the networks, beyond their contractual commitments, have systematically shown

significant added value and visible impact, confirming the strategy of increasing their share and

scope in EuCARD2.

Table 4: Status of progress towards deliverables . The HFM model magnet (WP7.3) will be late by 1.5 years. Its

insert HTS coil (WP7.4) requires a few months for completion, while the sc cavities of WP10.2 have been

delivered and will be tested in 2013.

WP 1 2 3 4 5 6 7 8 9 10 11

task 1 2 3 2 3 4 2 3 4 5 6 2 3 2 3 4 5 2 3 4 5 6 7 8 2 3 4

Page 94: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 93 / 123

Bey

ond

cont

ract

* * * * * * *

On

time

* * * * * * * * * * * * * * * * * * * * *

Min

or

dela

y

* * * * *

Larg

e

dela

y

*

Figure 72: profile of delivery of Deliverables

Over this final and shorter 12 month period, the number of publications is larger than during P2,

most notably the number of journal publications and oral presentations.

Table 5: Number and types of publications for P3 on 24/07/2013

Conference

papers

Journal

publications

Academic

dissertations

Notes &

reports

Misc.

publications

Oral

presentations

Books Total

74 27 3 4 10 23 7 144

1.1.7. Communication

Even though the communication activity is conducted in WP2, it is tightly linked to the

management, with the deputy of WP2 being a member of the Coordination Office. The strategic

Page 95: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 94 / 123

extension of the EuCARD Newsletter to three other FP7 accelerator projects, as a first phase

towards extending it to the whole accelerator community has been effective over this period. The

experience is positive and this new electronic publication is taken over by TIARA-PP with the

termination of EuCARD.

1.1.8. Coordination of activities between beneficiaries and synergies with other projects

An essential ingredient of success for EuCARD as a collaborative venture is to remain integrated

in the accelerator R&D programmes carried out on a national or laboratory basis, which provide

2/3 of the project funding. In this respect, the selection of EuCARD tasks and coordinators has

been instrumental. The coordination between beneficiaries is efficiently done at the task level,

with the EuCARD activities embedded in local projects, and providing the added value of a

collaborative venture. One indication is the number of conference publications, signed by authors

within and outside EuCARD.

To further strengthen the links between EuCARD beneficiaries, the face-to-face Steering

Committee meetings and the Annual meetings have been held in different laboratories. On each

of these events, either half a day (for SC meetings) or a full day (for annual meetings) is dedicated

to the host laboratory/state and beyond, including political and scientific talks and discussions,

and visits of accelerator infrastructures. In P3, the steering committee meeting organized in

Uppsala University was only partly faced to face, a snowstorm preventing landing in Stockholm;

the Annual meeting of 2012 took place in Warsaw, hosted by Politechnila Warszawska, , and the

Concluding meeting of 2013 at CERN, as coordinator. Once again, the “host day” in Poland was

a very valuable opportunity to demonstrate the R&D potential of Polish Institutes. ESGARD

organized as well a satellite meeting during these two EuCARD annual meetings.

The network events (mainly topical workshops) are privileged opportunities to create links

between the EuCARD beneficiaries and beyond, especially the US and Japanese partners, who

have been active participants. The WP3 network on neutrino facilities published important

synthesis documents proposing perspective for this branch of physics, used as input in the update

of the European policy for HEP. After setting up collaborations on superconducting crab cavities,

LHC luminosity and energy upgrade and novel acceleration techniques in the former periods,

the WP4 accelerator network has continued to be the birth place or catalyser of collaborative

“start-ups” active on major new perspectives for frontier accelerators, such as TLEP and

VHELHC, gamma colliders,…

The coordinators of EuCARD and EuCARD2 are tightly collaborating, for an optimal

transmission of experience. This is further consolidated by a common coordination office.

Whether on behalf of CERN or ESGARD, in the latter case together with its chairman R.

Aleksan, the coordinator has visited the EC or participated, with the Administrative Manager, to

the CERN delegations hosting visitors from the EC, keeping contact and explaining the

motivations for the R&D in accelerators. The project coordinator represents CERN and

EuCARD in the FP7 ICAN project, creating a link between the laser and accelerator

communities. He coordinates as well the FP7 CESSAMag project, whereby the European

Commission and CERN organize a support to SESAME, in the framework of Euro-

Mediterranean scientific cooperation.

The EuCARD administrative manager, in is duty of head of the CERN EU Office, frequently

visits the EC, keeping an efficient link that profits all EuCARD partners.

Page 96: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 95 / 123

Page 97: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 96 / 123

3. DELIVERABLES AND MILESTONES TABLES

3.1 DELIVERABLES

Year 1

Del. no. Deliverable name V. no.

WP no.

Lead beneficiary

Nature

Dissemination level4

Delivery date from Annex I (proj month)

Actual / Forecast

delivery date

Status Not submitted/ Submitted

Contractual Yes /

No

Comments

D2.2.1 EuCARD web site implementation

1 2 WUT, CERN

O PU M1 (30/04/2009)

07/11/2008 Submitted 29/05/2009

Yes

Website

Report

D4.1.1 Continually updated AccNet web site

1 4 CERN, CNRS

O PU M2 (31/05/2009)

23/04/2009 Submitted 08/07/2009

Yes Three website deliverables: AccNet, EuroLumi and RFTECH grouped into one

report. Final version delayed due to overcoming a firewall issue on CNRS web server.

D4.2.1 Continually updated EuroLumi web site

1 4 CERN O PU M2 (31/05/2009)

Submitted Yes

D4.3.1 Continually updated RFTECH web site

1 4 UJF, TUL

O PU M2 (31/05/2009)

Submitted Yes

4 PU = Public; PP = Restricted to other programme participants (including the Commission Services); RE = Restricted to a group specified by the consortium (including the

Commission Services); CO = Confidential, only for members of the consortium (including the Commission Services). EU restricted = Classified with the mention of the

classification level restricted “EU Restricted”; EU confidential = Classified with the mention of the classification level confidential “EU Confidential”; EU secret = Classified

with the mention of the classification level secret “EU Secret”

Page 98: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 97 / 123

D3.1.1 NEU2012 Website operational

1 3 INFN O PU M6 (30/09/2009)

30/09/2009 Submitted 30/10/2009

Yes

Website

Report

D10.4.1 QE data for Pb/Nb deposited photo cathode samples

1 10 DESY, SINS

R PU M12 (31/03/2010)

31/03/2010

Submitted 27/05/2010

Yes Report

Year 2

Del. no. Deliverable name V. no.

WP no.

Lead beneficiary

Nature

Dissemination level5

Delivery date from Annex I (proj month)

Actual / Forecast

delivery date

Status Not submitted/ Submitted

Contractual Yes / No

Comments

D1.1 1st periodic EuCARD report

1 CERN R PU M20 (30/11/2010)

17/12/2010 Submitted 17/12/2010

Yes See public version of report (with financial data removed)

D4.3.2 Strategy/result for SRF test infrastructures

4 CERN, TUL

R PU M24 (31/03/2011)

31/05/2011 Submitted 14/06/2011

Yes Report & now a booklet

D8.1.2 Collimator specification for LHC upgrade parameters

8 CERN, GSI

R PU M24 (31/03/2011)

31/08/2010 Submitted 14/06/2011

Yes Report

D8.1.3 Collimator specification for FAIR

8 CERN, GSI

R PU M24 (31/03/2011)

30/09/2010 Submitted 01/06/2011

Yes Report

5 PU = Public; PP = Restricted to other programme participants (including the Commission Services); RE = Restricted to a group specified by the consortium (including the

Commission Services); CO = Confidential, only for members of the consortium (including the Commission Services). EU restricted = Classified with the mention of the

classification level restricted “EU Restricted”; EU confidential = Classified with the mention of the classification level confidential “EU Confidential”; EU secret = Classified

with the mention of the classification level secret “EU Secret”

Page 99: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 98 / 123

D10.7.1 Results of slice measurements

10 FZD R PU M24 (31/03/2011)

31/05/2011 Submitted 14/06/2011

Yes Report

D11.2.1 DAFNE IR design for the upgraded KLOE detector

11 INFN R PU M24 (31/03/2011)

31/03/2011 Submitted 30/05/2011

Yes Report

Year 3

Del. no. Deliverable name V. no.

WP no.

Lead beneficiary

Nature

Dissemination level6

Delivery date from Annex I (proj month)

Actual / Forecast

delivery date

Status Not submitted/ Submitted

Contractual Yes / No

Comments

D4.4.1

Organization of founding workshop gathering the PWA community

4 CERN O PU M27 (30/06/2011)

26/09/2012 Submitted 05/11/2011

Yes Event held. Report

D8.3.2 One cryogenic collimator, tested with beam

8 GSI P PU M30 (30/09/2011)

22/11/2011 Submitted 16/12/2011

Yes Report

D4.4.2 Preparation of a proposal for a EC cofunded network in

4 CERN R PU M33 (31/12/2011)

23/11/2011 Submitted 05/11/2012

Yes Report

6 PU = Public; PP = Restricted to other programme participants (including the Commission Services); RE = Restricted to a group specified by the consortium (including the

Commission Services); CO = Confidential, only for members of the consortium (including the Commission Services). EU restricted = Classified with the mention of the

classification level restricted “EU Restricted”; EU confidential = Classified with the mention of the classification level confidential “EU Confidential”; EU secret = Classified

with the mention of the classification level secret “EU Secret”

Page 100: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 99 / 123

the EuCARD2 proposal

D10.2.1 Results of SC proton cavity tests (b = 1 and b = 0.65)

10 CEA R PU M33 (31/12/2011)

M52 Submitted Yes Report

D10.7.2 Results for GaAs photocathodes

10 FZD R PU M33 (31/12/2011)

M52 Submitted Yes Report

D10.8.1 Test and operation of the couplers preparation procedure

10 CNRS R PU M34 (31/01/2012)

M52 Submitted Yes Report

D7.2.2 Thermal model for a dipole Nb3Sn model magnet

7 PWR R PU M36 (31/03/2012)

31/03/2012 Submitted 15/05/2012

Yes Report

D8.2.1 Report on modelling and materials

8 CERN R PU M36 (31/03/2012)

15/05/2012 Submitted 15/06/2012

Yes Report

D10.3.1 LHC crab cavity final report

10 UNIMAN

R PU M36 (31/03/2012)

31/03/2013 Submitted Yes Report

D10.3.2 CLIC crab cavity final report

10 UNIMAN

R PU M36 (31/03/2012)

07/03/2013 Submitted Yes Report

D10.3.3 LHC and CLIC LLRF final reports

10 UNIMAN

R PU M36 (31/03/2012)

01/07/2013 Submitted Yes Report

D10.4.3

Cold test results for the test cavities w/out the deposited lead photo cathode

10 CERN R PU M36 (31/03/2012)

31/03/2012 Submitted Yes Completed in M36 as planned; report delayed to M43.

D10.4.4 New thin film techniques for SC

10 ULANC D PU M36 (30/03/2012)

M52 Submitted Yes Report

Page 101: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 100 / 123

cavities and photo cathodes

D11.2.2 Study of an IR design for LHC upgrade

11 INFN R PU M36 (31/03/2012)

22/07/2013 Submitted Yes Report

D11.3.1

Results from the operation of EMMA using the new diagnostics

11 STFC R PU M36 (31/03/2012)

20/06/2012 Submitted Yes Report

D11.4.1 Preliminary electron beam emittance measurement report

11 CNRS R PU M36 (31/03/2012)

26/04/2012 Submitted 25/05/2012

Yes Report

Year 4

Del. no. Deliverable name V. no.

WP no.

Lead beneficiary

Nature

Dissemination level7

Delivery date from Annex I (proj month)

Actual / Forecast

delivery date

Status Not submitted/ Submitted

Contractual Yes / No

Comments

D1.2 2nd periodic EuCARD report

1 CERN R PU M38 (31/05/2012)

02/07/2012 Submitted 02/07/2012

Yes See public version of report (with financial data removed)

D3.2.1 Performance analysis and physics potential

3 INFN R PU M40 (31/07/2012)

22/04/2013 Submitted 22/04/2013

Yes Report

7 PU = Public; PP = Restricted to other programme participants (including the Commission Services); RE = Restricted to a group specified by the consortium (including the

Commission Services); CO = Confidential, only for members of the consortium (including the Commission Services). EU restricted = Classified with the mention of the

classification level restricted “EU Restricted”; EU confidential = Classified with the mention of the classification level confidential “EU Confidential”; EU secret = Classified

with the mention of the classification level secret “EU Secret”

Page 102: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 101 / 123

of upgrades of existing neutrino facilities

D3.3.1

Proposal of the next global accelerator neutrino facility for Europe to build or help build.

3 INFN R PU M40 (31/07/2012)

16/08/2012 Submitted 16/08/2012

Yes Report

D7.5.1 HTS 20 m 600 A link assembled

7 CERN P PU M40 (31/07/2012)

M51 Submitted Yes Report

D7.2.1 Certification of the radiation resistance of coil insulation material

7 PWR R PU M42 (30/09/2012)

31/07/2013 Submitted Yes Report

D8.3.1

One primary collimator with optional crystal feature, tested with beam

8 CERN P PU M42 (30/09/2012)

M51 Submitted Yes Report

D9.4.1 ATF2 tests and CLIC IR study

9 RHUL R PU M42 (30/09/2012)

30/09/2012 Submitted Yes Report

D10.6.1 Report on system test and performance

10 DESY R PU M42 (30/09/2012)

M52 Submitted Yes Report

D 7.2.3

Superfluid helium transport model for the thermal design of the high field model magnet

7 PWR R PU M43 (31/10/2012)

M51 Submitted Yes Report

D9.5.1 RF phase monitor final report

9 INFN R PU M45 (31/12/2012)

Submitted Yes Report

D9.4.2 Laser Wire and Beam Position Monitor tests

9 RHUL R PU M46 (31/01/2013)

M52 Submitted Yes Report

Page 103: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 102 / 123

D1.3 3rd periodic EuCARD report

1 CERN R PU M48 (31/03/2013)

Submitted Yes Delayed to M51

D1.4 Final project report 1 CERN R PU M48 (31/03/2013)

In progress Yes Delayed to M52

D2.1.1 Final report of WP2 DCO

2 WUT, CERN

R PU M48 (31/03/2013)

M52 Submitted Yes Report

D2.2.2 Final plan for the use and dissemination of foreground

2 WUT, CERN

R PU M48 (31/03/2013)

In progress Yes Delayed to M51 Justification

D3.1.2

Final NEU2012 guidelines for an accelerator neutrino experiments programme

3 INFN R PU M48 (31/03/2013)

M52 Submitted Yes Report

D4.1.2

AccNet Strategy for future proton & electron facilities in Europe

4 CERN, CNRS

R PU M48 (31/03/2013)

M52 Submitted Yes Report

D4.2.2

EuroLumi Strategy and issues for LHC IR, LHC injector and beam-parameter upgrade path(s), with comment on longer-term prospects, and for FAIR

4 CERN R PU M48 (31/03/2013)

31/07/2013 Submitted Yes Report

D4.3.3

RFTECH strategy/result for cavity design, LLRF & HPRF systems and

4 CERN, TUL

R PU M48 (31/03/2013)

M52 Submitted Yes Report

Page 104: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 103 / 123

design integration, and costing tools

D7.1.1

HFM web-site linked to the technical & administrative databases

7 CERN, CEA

O PU M48 (31/03/2013)

M52 Submitted Yes Report

D7.3.1 Dipole model test with one superconducting coil; results analyzed

7 CEA R PU M48 (31/03/2013)

M52 Submitted Yes Report

D7.4.1 A HTS dipole insert coil constructed

7 CNRS D PU M48 (31/03/2013)

M52 Submitted Yes Report

D7.6.1 Final prototype SC helical undulator measured

7 STFC R PU M48 (31/03/2013)

M51 Submitted Yes Report

D8.1.1

ColMat web-site linked to the technical and administrative databases

8 CERN, GSI

O PU M48 (31/03/2013)

M52 Submitted Yes Report

D9.1.1

NCLinac web-site linked to the technical and administrative databases

9 CERN, RHUL

O PU M48 (31/03/2013)

M52 Submitted Yes Report

D9.2.1

Simulation and experimental results with report on the theoretical and scientific aspects of the CLIC module

9 CERN R PU M48 (31/03/2013)

M50 Submitted Yes Report

D9.2.2 Prototypes with descriptive report (technical, design and

9 CERN P PU M48 (31/03/2013)

M50 Submitted Yes Report

Page 105: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 104 / 123

fabrication) of the hardware prepared for the test module.

D9.3.1 CLIC Quadrupole Module final report

9 CNRS R PU M48 (31/03/2013)

M52 Submitted Yes Report

D9.3.2 Final Focus Test Stand final report

9 CNRS R PU M48 (31/03/2013)

M52 Submitted Yes Report

D9.5.2 Electro optical monitor final report

9 INFN R PU M48 (31/03/2013)

M52 Submitted Yes Report

D10.1.1

SRF web-site linked to the technical and administrative databases

10 DESY, CEA

O PU M48 (31/03/2013)

M52 Submitted Yes Report

D10.4.2 RF measurements on thin film deposited QRW prototype

10 CERN R PU M48 (31/03/2013)

M52 Submitted Yes Report is confidential

D10.5.1

HOM electronics and code to probe beam centring on 3.9 GHz cavities

10 DESY R PU M48 (31/03/2013)

M52 Submitted Yes Report

D10.5.2 Report on HOM experimental methods and code

10 DESY R PU M48 (31/03/2013)

M52 Submitted Yes Report

D11.1.1

ANAC web-site linked to the technical and administrative databases

11 INFN O PU M48 (31/03/2013)

M52 Submitted Yes Report

Page 106: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 105 / 123

3.2 MILESTONES

[This table is cumulative, which means that it should always show all milestones from the beginning of the project]

Year 1

Mil. no.

Milestone name WP no

Lead beneficiary

Delivery date from Annex I dd/mm/yyyy

Achieved Yes/No

Actual / Forecast achievement date

dd/mm/yyyy

Comments

M11.3.1 Requirements for electron beam

diagnostics 11 STFC

M2

(31/05/2009)

Yes M2

(31/05/2009) Completed

M11.3.1 Requirements for PWA beam

diagnostics 11 CNRS N/A

Yes M2

(31/05/2009)

Additional milestone not originally

foreseen in Annex 1, see report

M3.1.1.1 Calendar of workshops &

conferences concerning NEU2012 3 INFN

M6

(30/09/2009)

Yes M6

(30/09/2009)

Completed, see NEu2012 website for

details

M9.3.3 Installation of ATF2 final-focus

alignment monitoring system 9 CNRS

M6

(30/09/2009)

Yes M16

(31/07/2010) Milestone objectives met by other means

M1.1 1st annual EuCARD meeting 1 CERN M12

(31/03/2010)

Yes M13

(14/04/2010)

Mid-April date was more suitable, more

details>>

M2.1.1 Annual status of DCO, first year 2 WUT, CERN M12

(31/03/2010)

Yes M13

(14/04/2010)

Presented at the EuCARD 1st Annual

Meeting

M3.1.3.1 NEU2012 first annual workshop 3 INFN M12

(31/03/2010)

Yes M13

(13/04/2010)

Scheduled during the EuCARD 1st Annual

Meeting

Page 107: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 106 / 123

M4.1.1 Annual AccNet steering meeting,

first year 4

CERN,

CNRS

M12

(31/03/2010)

Yes

M8

(30/11/2009)

& M13

(13/04/2010)

Two meetings organized

M4.2.1 Annual EuroLumi workshop,

first year 4 CERN

M12

(31/03/2010)

Yes Before M12

(31/03/2010)

Workshop replaced by several more

focused mini-workshops

M4.3.1 Annual RFTECH workshop,

first year 4 CNRS, TUL

M12

(31/03/2010)

Yes M12

(29/03/2010) Workshops held in DESY on 29/03/10

M7.1.1 1st annual HFM review meeting 7 CERN, CEA M12

(31/03/2010)

Yes M12

(18/03/2010)

Held at Wroclaw Technical University

(PWR)/td>

M7.2.2 Preliminary heat deposition model

for a dipole Nb3Sn model magnet 7 PWR

M12

(31/03/2010)

Yes M12

(31/03/2010) Publication on web, see report

M7.4.1 HTS conductor specifications for

insert coils 7 CERN

M12

(31/03/2010)

Yes M12

(31/03/2010)

Done: first version of the specification for

YBCO and Bi-2212 conductors written

down.

M8.1.1 1st annual ColMat review meeting 8 CERN, GSI M12

(31/03/2010)

Yes M12

(22/03/2010) Held at CERN

M8.2.1 Functional specification LHC of

beam loss and collimator design 8 CERN

M12

(31/03/2010)

Yes M12

(31/03/2010) Simulations and design done.

M8.2.3 Functional specification FAIR of

beam loss and collimator design 8 GSI

M12

(31/03/2010)

Yes M12

(31/03/2010) Simulations and design done.

M9.1.1 Annual NCLinac review first year 9 CERN,

RHUL

M12

(31/03/2010)

Yes M13

(13/04/2010)

Scheduled during the EuCARD 1st Annual

Meeting

M10.1.1 Annual review SRF first year 10 CEA, CERN M12

(31/03/2010)

Yes M13

(07-09/04/2010) Held at the Cockcroft Institute, UK

Page 108: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 107 / 123

M10.2.2 Definition of cryomodule interface 10 CEA M12

(31/03/2010)

Yes M26

(29/06/2011)

Milestone delayed due to change of

strategy, report now available

M10.3.1 LHC crab cavity specifications

completed 10 UNIMAN

M12

(31/03/2010)

Yes M14

(31/05/2010)

Rescheduled following change of goals by

WP4 LHC-CC09 workshop, see report

M10.3.4 CLIC crab cavity specifications

completed 10 UNIMAN

M12

(31/03/2010)

Yes M15

(30/06/2010)

Delay in recruitment of a PDRA, see

report

M10.4.1 Lead deposition on samples for

photocathode development 10 CERN

M12

(31/03/2010)

Yes M12

(31/03/2010)

Samples completed. Deposition system

has been rebuilt and optimised in order to

achieve an efficient and free of micro-

droplets coating.

M10.7.1 Preparation system for GaAs

finished 10 FZD

M12

(31/03/2010)

Yes M12

(31/03/2010) Completed

M11.1.1 1st annual ANAC review meeting 11 INFN M12

(31/03/2010)

Yes M13

(30/04/2010) Done

M11.2.1 DAΦNE beam parameters definition

for KLOE 11 INFN

M12

(31/03/2010)

Yes M12

(31/03/2010)

Preparatory for IR study completed, see

report

Year 2

Mil. no.

Milestone name WP no

Lead beneficiary

Delivery date from Annex I dd/mm/yyyy

Achieved Yes/No

Actual / Forecast achievement date

dd/mm/yyyy

Comments

M11.3.2 Construction of the electron beam

diagnostics completed 11 STFC

M14

(31/05/2010)

Yes M14

(31/05/2010) Completed

Page 109: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 108 / 123

M4.4.1

Get SC and GB support and

agreement of coordinating institute

for minimal funding

4 CERN M18

(30/09/2010)

Yes M18

(30/09/2010) Completed

M9.4.1 Training at ATF3 9 RHUL M18

(30/09/2010)

Yes M18

(30/09/2010) Commissioning at ATF2 done

M9.4.2 LW and BPMs installed 9 RHUL M18

(30/09/2010)

Yes M18

(30/09/2010)

Hardware at ATF2 and PETRAIII done.

First data taking using new systems is

scheduled for November 2010.

M10.4.2 Lead deposition on half cells and 1.5

cell cavities 10 CERN

M18

(30/09/2010)

Yes M19

(29/10/2010) Report and samples completed in M19

M10.6.1 Design and manufacturing of the

carrier board prototypes 10 DESY

M18

(30/09/2010)

Yes M19

(29/10/2010) Completed in M19, see report

M10.6.4 Design and manufacturing of AMC

radiation dosimeter 10 DESY

M18

(30/09/2010)

Yes M19

(29/10/2010) Completed in M19, see report

M10.6.7 Design and manufacturing of high

linearity multichannel downconverter 10 DESY

M18

(30/09/2010)

Yes M19

(29/10/2010) Completed in M19, see report

M10.7.2 Installation spectrometer dipole 10 FZD M18

(30/09/2010)

Yes M18

(30/09/2010)

Installed, first measurement shifts Oct

2010, see report

M11.2.2 Compatibility of new IR scheme and

LHC 11 INFN

M18

(30/09/2010)

Yes M18

(30/09/2010) Preparatory for IR study done.

M8.3.1.1 LHC type collimator designed 8 CERN M20

(30/11/2010)

Yes M18

(30/09/2010) Warm collimator. Done early by Month 18

M11.3.3 Commissioning of EMMA completed 11 STFC M20

(30/11/2010)

Yes M25

(30/04/2011)

Commissioning still underway. Should be

complete April 2011

Page 110: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 109 / 123

M4.4.2

Define the goals and governance

structure of the network: identify 3

coordinators

4 CERN M22

(31/01/2011)

Yes M22

(31/01/2011) Completed. Report

M1.2 2nd annual EuCARD meeting 1 CERN M24

(31/03/2011)

Yes M26

(13/05/2011) Took place 11-13 May 2011

M1.3 Mid-term review 1 CERN M24

(31/03/2011)

Yes M27

(21/06/2011) Took place 21/06/2011

M2.1.2 Annual status of DCO, second year 2 WUT, CERN M24

(31/03/2011)

Yes M26

(11/05/2011)

Presentation made at annual meeting -

11th May

M3.1.2.1

Intermediate review of NEU2012

recommendations on neutrino

experiments

3 INFN M24

(31/03/2011)

Yes M32

Milestone delayed and combined with

corresponding deliverable.

M3.1.3.2 NEU2012 second annual workshop 3 INFN M24

(31/03/2011)

Yes M26

(10/05/2011)

Delayed to coincide with second annual

meeting (10th May)

M3.2.1.1

Intermediate review of NEU2012

recommendations on existing

accelerator neutrino facilities.

3 INFN M24

(31/03/2011)

Yes M32

Milestone delayed and combined with

corresponding deliverable.

M3.3.1.1

Intermediate review of NEU2012

recommendations on new

accelerator neutrino facilities.

3 INFN M24

(31/03/2011)

Yes M37

(30/04/2012) Presented in the 2012 annual meeting

M4.1.2 Annual AccNet steering meeting,

second year. 4

CERN,

CNRS

M24

(31/03/2011)

Yes M26

(10/05/2011)

Delayed to coincide with second annual

meeting (10th May)

M4.2.2 Annual EuroLumi workshop, second

year. 4 CERN

M24

(31/03/2011)

Yes M22

(31/01/2011)

M4.3.2 Annual RFTECH workshop, second

year. 4 CNRS, TUL

M24

(31/03/2011)

Yes M21

(31/12/2010)

Page 111: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 110 / 123

M7.1.2 2nd annual HFM review meeting 7 CERN, CEA M24

(31/03/2011)

Yes M24

(22/03/2011) Link to meeting here

M7.2.3 Engineering heat deposition model

for a dipole Nb3Sn model magnet 7 PWR

M24

(31/03/2011)

Yes M24

(22/03/2011) Presentation at HFM meeting. Report here

M8.1.2 2nd annual ColMat review meeting 8 CERN, GSI M24

(31/03/2011)

Yes M18

(30/09/2010)

Completed early, in September 2010

(M18)

M8.2.2 Upgrade LHC collimator specification 8 CERN M24

(31/03/2011)

Yes M17

(31/08/2010)

Materials characterized and tested.

Review of results and specification.

M8.3.2.1 FAIR type collimator designed 8 CERN M24

(31/03/2011)

Yes M18

(30/09/2010)

cryogenic collimator. Done early by

September 2010 (M18)

M9.1.2 Annual NCLinac review second year 9 CERN,

RHUL

M24

(31/03/2011)

Yes M26

(13/05/2011) Delayed to coincide with annual meeting

M9.2.1 Modification of NCLinac computer

codes and first round of simulations. 9 CERN

M24

(31/03/2011)

Yes M24

(31/03/2011)

M9.2.2 Design of NCLinac hardware for test

module 9 CERN

M24

(31/03/2011)

Yes M24

(31/03/2011)

M9.3.1 Characterization of noise/vibrations

sources in an accelerator 9 CNRS

M24

(31/03/2011)

Yes M24

(31/03/2011)

M9.3.2 Installation of interferometers at

CTF3 Module 9 CNRS

M24

(31/03/2011)

No n/a

M24 milestone suppressed: change of

strategy to reach identical deliverable.

Obsolete

M9.3.4 Installation of ILC prototype FB/FF at

ATF2 9 CNRS

M24

(31/03/2011)

Yes M24

(31/03/2011

M10.1.2 Annual review SRF second year 10 DESY, CEA M24

(31/03/2011)

Yes M26

(13/05/2011) Delayed to coincide with annual meeting

Page 112: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 111 / 123

M10.3.2 LHC model crab cavity completed 10 ULANC M24

(31/03/2011)

Yes M27

(30/06/2011)

Delay after change in strategy in LHCC09.

Model made in month 27, report received.

M10.3.5 CLIC model crab cavity completed 10 UNIMAN M24

(31/03/2011)

Yes M39

(30/06/2012)

Delayed to M38: Fabrication delays

experienced.

M10.6.2

Design and manufacturing of the

AMC modules with fast analogue

and digital IO (at least 100 Ms/s,

14 b).

10 DESY M24

(31/03/2011)

Yes M31

(03/10/2011) Completed in M31, see report

M10.6.3

Design and manufacturing of the

AMC board with ultra fast ADC (at

least 2 Gs/s, 10 b)

10 DESY M24

(31/03/2011)

Yes M31

(03/10/2011) Completed in M31, see report

M10.6.6 Designed and manufactured

Frequency Synthesizer Board (AMC) 10 DESY

M24

(31/03/2011)

Yes M31

(03/10/2011) Completed in M31, see report

M10.6.8 Integration of downconverters and

upconverters in RTM (ATCA) 10 DESY

M24

(31/03/2011)

Yes M31

(03/10/2011) Completed in M31, see report

M10.6.9

Design and fabrication of AMC

modules for controlling step motors,

piezo and waveguide tuners

10 DESY M24

(31/03/2011)

Yes M35

(01/02/2012) Completed in M35, see report

M10.7.3 GaAs photocathodes produced 10 FZD M24

(31/03/2011)

Yes M48

(31/03/2013)

Manpower problems now solved. Linked

to deliverable D10.7.2

M11.1.2 2nd annual ANAC review meeting 11 INFN M24

(31/03/2011)

Yes M26

(13/05/2011)

Delayed to coincide with second annual

meeting

M11.4.1 Electron beam emittance meter

finished 11 CNRS

M24

(31/03/2011)

Yes M24

(31/03/2011) Complete, see report

Page 113: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 112 / 123

Year 3

Mil. no.

Milestone name WP no

Lead beneficiary

Delivery date from Annex I dd/mm/yyyy

Achieved Yes/No

Actual / Forecast achievement date

dd/mm/yyyy

Comments

M8.3.1.2 LHC type collimator constructed 8 CERN M26

(31/05/2011)

Yes M18

(30/09/2010)

Completed early, by Month 18 (September

2010)

M7.2.1

Methodology for the certification of

radiation resistance of coil insulation

material

7 PWR M30

(30/09/2011)

Yes M31

(20/10/2011)

Minor delay due to technical and

scheduling reasons, report available here

M7.4.2 Two HTS solenoid insert coils 7 CERN M30

(30/09/2011)

Yes M36

(07/03/2012)

Delayed for technical reasons, 2 coils

were made but problems with conductor

degradation and splices needed to be

solved. Report available here.

M8.3.1.3 LHC type collimator tested 8 CERN M30

(30/09/2011)

Yes M36

(06/03/2012)

Done, confirmed in Steering Committee

meeting

M9.3.5 Commissioning of CLIC quadrupole

module 9 CNRS

M30

(30/09/2011)

Yes M37

(30/04/2012)

Complete module with girder and

accelerating structure. All magnet

prototypes now available, confirmed in

Steering Committee meeting.

M9.3.6 Quadruple mock-up manufactured

and ready for installation 9 CNRS

M30

(30/09/2011)

Yes M37

(30/04/2012)

Several quadrupole prototypes and short

model assembled.

M10.2.1 Cavity fabrication (proton linac) 10 CEA M30

(30/09/2011)

Yes M42

(30/09/2012) Delay due to cost and tendering

M10.3.7 Development of LHC LLRF system 10 UNIMAN M30

(30/09/2011)

Yes M46

(31/01/2013)

Delayed to M46: CLIC and LHC work

interchanged (amendment 2) and suffering

an additional delay.

Page 114: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 113 / 123

M10.3.8 Development of CLIC LLRF system 10 UNIMAN M30

(30/09/2011)

Yes M25

(30/04/2011) LHC and CLIC work interchanged

M10.4.3 QWR sputtering with Nb using the

magnetron technique 10 INFN

M30

(30/09/2011)

Yes M36

(06/03/2012) Report received, awaiting approval

M10.4.4 Report on new thin film coating

techniques for SC cavities 10 ULANC

M30

(30/09/2011)

Yes M48

(30/09/2012) Delayed due to change of staff

M10.3.3 LHC input and LOM mode coupler

design development finished 10 ULANC

M33

(31/12/2011)

Yes M46

(31/01/2013) Delayed to M46. Report in preparation

M10.3.6 CLIC input and mode coupler design

development finished 10 UNIMAN

M33

(31/12/2011)

Yes M45

(31/12/2012) Delayed to M45. Report in preparation

M7.5.1 Final design report HTS link 7 CERN M34

(31/01/2012)

Yes M45

(31/03/2012) Delayed to M45. Report in preparation

M1.4 3rd annual EuCARD meeting 1 CERN M36

(31/03/2012)

Yes M37

(24/04/2012)

Took place in Warsaw (24)25-30 April, see

here.

M2.1.3 Annual status of DCO, third year 2 WUT, CERN M36

(31/03/2012)

Yes M37

(25/04/2012) Presented during Annual meeting

M3.1.3.3 NEU2012 third annual workshop 3 INFN M36

(31/03/2012)

Yes M38

(24/05/2012) Was part of the Annual meeting

M4.1.3 Annual AccNet steering meeting,

third year. 4

CERN,

CNRS

M36

(31/03/2012)

Yes M37

(24/04/2012) Was part of the Annual meeting

M4.2.3 Annual EuroLumi workshop, third

year. 4 CERN

M36

(31/03/2012)

Yes M27

(20/06/2011)

Replaced by 2 topical mini-workshops:

OMCM, LHC-CC11

M4.3.3 Annual RFTECH workshop, third

year. 4 CNRS, TUL

M36

(31/03/2012)

Yes M33

(11/12/2011) Held

Page 115: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 114 / 123

M7.1.3 3rd annual HFM review meeting 7 CERN, CEA M36

(31/03/2012)

Yes M37

(24/04/2012) Will be part of the Annual meeting

M7.6.1 Short prototype SC helical undulator

fabricated and tested 7 STFC

M36

(31/03/2012)

Yes M48

(31/03/2013)

Milestone will coincide with deliverable.

Deliverable will be produced without

intermediate step.

M8.1.3 3rd annual ColMat review meeting 8 CERN, GSI M36

(31/03/2012)

Yes M37

(24/04/2012) Will be part of the Annual meeting

M8.3.2.2 FAIR type collimator constructed 8 CERN M36

(31/03/2012)

Yes M26

(31/05/2011) Completed early

M9.1.3 Annual NCLinac review third year 9 CERN,

RHUL

M36

(31/03/2012)

Yes M37

(24/04/2012) Will be part of the Annual meeting

M9.2.3 Prototype components for CLIC

module prepared 9 CERN

M36

(31/03/2012)

Yes M36

(06/03/2012)

M9.5.1 RF phase monitor prototype finished 9 INFN M37

(30/04/2012)

Yes M37

(06/04/2012) Prototype ready for test

M10.1.3 Annual review SRF third year 10 DESY, CEA M36

(31/03/2012)

Yes M36

(29/03/2012) Event 29-30 March in HZB

M10.4.5 Improved RF-design of 1.5 cell 10 DESY M36

(31/03/2011)

Yes M43 Delayed to M43.

M10.4.6 Elliptical cavity prototype by HIPIMS 10 CERN M36

(31/03/2012)

Yes M42

(31/09/2012)

M10.5.1 HOM alignment for 3.9 GHz cavity

electronics verification 10 DESY

M36

(31/03/2012)

Yes M45

(31/12/2012)

Delayed due to FLASH beam time

availability

M10.6.5 Report on tests and calibration of the

radiation dosimeter 10 DESY

M36

(31/03/2012)

Yes M46

(31/01/2013) Report in preparation

Page 116: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 115 / 123

M10.6.10

Report on longitudinal beam

parameter studies and their

controllability by fast feedback

systems in conjunction with the

LLRF system

10 DESY M36

(31/03/2012)

Yes M37

M10.7.3 GaAs photocathodes produced 10 FZD M36

(31/03/2012)

Yes M45 Delayed

M11.1.3 3rd annual ANAC review meeting 11 INFN M36

(31/03/2012)

Yes M37

(24/04/2012) Will be part of the Annual meeting

Year 4

Mil. no.

Milestone name WP no

Lead beneficiary

Delivery date from Annex I dd/mm/yyyy

Achieved Yes/No

Actual / Forecast achievement date

dd/mm/yyyy

Comments

M4.4.3 Annual EuroNNAc workshop 2012 4 CERN M39

(30/06/2012)

Yes M44

(05/11/2012) Report

M9.5.2 Electro optical monitor prototype

finished 9 INFN

M40

(31/07/2012)

Yes Combined with corresponding deliverable

M7.3.2 Dipole Nb3Sn model magnet

finished 7 CEA

M42

(30/09/2012)

No

Obsolete milestone after deliverable

modification : should have been

suppressed in Amendment 1.

M9.3.7 Design of nm-level beam

stabilization system for ATF2 9 UOXF-DL

M42

(30/09/2012)

Yes Combined with corresponding deliverable

M7.3.1 Dipole Nb3Sn coils finished 7 CEA M45

(31/12/2012)

No

Obsolete milestone after deliverable

modification : should have been

suppressed in Amendment 1.

Page 117: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 116 / 123

M1.5 Final annual EuCARD meeting 1 CERN M48

(31/03/2013)

Yes M51

M2.1.4 Final status of DCO 2 WUT, CERN M48

(31/03/2013)

Yes M51

M3.1.3.4 NEU2012 final annual workshop 3 INFN M48

(31/03/2013)

Yes M51

M4.1.4 Final AccNet steering meeting 4 CERN,

CNRS

M48

(31/03/2013)

Yes M51

M4.2.4 Final EuroLumi workshop 4 CERN M48

(31/03/2013)

Yes M51

M4.3.4 Final RFTECH workshop 4 CNRS, TUL M48

(31/03/2013)

Yes M51

M7.1.4 Final HFM review meeting 7 CERN, CEA M48

(31/03/2013)

Yes M51

M8.1.4 Final ColMat review meeting 8 CERN, GSI M48

(31/03/2013)

Yes M51

M9.1.4 Final NCLinac review 9 CERN,

RHUL

M48

(31/03/2013)

Yes M51

M10.1.4 Final SRF review 10 DESY, CEA M48

(31/03/2013)

Yes M51

M11.1.4 Final ANAC review meeting 11 INFN M48

(31/03/2013)

Yes M51

Page 118: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 117 / 123

4. ANNEX: LIST OF PUBLICATIONS DURING PERIOD 3

All EuCARD publications, in pre-print or final form, are available in open access mode via the

project’s publication database, implemented via the CERN Document Server:

http://cdsweb.cern.ch/collection/EuCARD.

NO. Type of activities Main leader Title Date

WP2.2 (Period 1,2&3: 64 publications)

1597064 Press article Giampietro, M EuCARD-2 kicks off 2013

1597061 Press article WennersHerron,

A et al

Accelerator physicists take the long view at

EuCARD’13 2013

1597058 Press article Chaudron, M From EuCARD to EuCARD-2 2013

1597053 Press article Del Rosso, A Detectors don’t fear neutrons 2013

1597051 Other/Newsletter Szeberenyi, A et

al Accelerating News Issue 6 2013

1597050 Other/Newsletter Szeberenyi, A et

al Accelerating News Issue 5 2013

1553524 Publication Romaniuk, R

Accelerators for Society - TIARA 2012 Test

Infrastructure and Accelerator Research Area (in

Polish)

2013

1553300 Publication Romaniuk, R Fusion - 2050 perspective (in Polish) 2013

1553299 Publication Romaniuk, R

Advanced Electronic Systems for HEP

Experiments, Astroparticle Physics, Accelerator

Technology, FELs and Fusion; 2013 WILGA

January Symposium (in Polish)

2013

1553232 Publication Romaniuk, R European XFEL (in Polish) 2013

1553229 Publication Romaniuk, R LCLS Laser (in Polish) 2013

1523225 Other/Monograph Czuba, K

RF Phase Reference Distribution System for the

TESLA Technology Based Projects; EuCARD

Editorial Series on Accelerator Science and

Technology (J-P.Koutchouk, R.S.Romaniuk,

Editors), Vol.18

2013

1523223 Other/Monograph Wysocka-

Rabin, A

Advances in Conformal Radiotherapy - Using

Monte Carlo Code to design new IMRT and IORT

accelerators and interpret CT numbers; EuCARD

Editorial Series on Accelerator Science and

Technology (J-P.Koutchouk, R.S.Romaniuk,

Editors), Vol.17

2013

1597054 Press article Duc, C Delving into the heart of materials 2012

1597042 Other/Newsletter Szeberenyi, A et

al Accelerating News Issue 4 2012

1597035 Other/Newsletter Kahle, K et al Accelerating News Issue 3 2012

1597032 Other/Newsletter Kahle, K et al Accelerating News Issue 2 2012

1597029 Other/Newsletter Kahle, K et al Accelerating News Issue 1 2012

Page 119: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 118 / 123

1597023 Press article Cimino, R et al ECLOUD12 sheds light on electron clouds 2012

1523222 Other/Monograph Zhang, P

Beam Position Diagnostics with Higher Order

Modes in Third Harmonic Superconducting

Accelerating Cavities; EuCARD Editorial Series

on Accelerator Science and Technology (J-

P.Koutchouk, R.S.Romaniuk, Editors), Vol.16

2012

1518889 Other/Monograph Dziewiecki, M

Measurement-based characterization of multipixel

avalanche photodiodes for scintillating detectors;

EuCARD Editorial Series on Accelerator Science

and Technology, (J-P.Koutchouk, R.S.Romaniuk,

Editors), Vol.14

2012

1518890 Other/Monograph Junginger, T

Investigation of the surface resistance of

superconducting materials; EuCARD Editorial

Series on Accelerator Science and Technology (J-

P.Koutchouk, R.S.Romaniuk, Editors), Vol.15

2012

1476023 Publication Romaniuk, R Accelerator Technology and High Energy Physic

Experiments, WILGA 2012; EuCARD Sessions 2012

1476020 Publication Romaniuk, R Astronomy and Space Technologies, WILGA 2012;

EuCARD Sessions 2012

1476025 Publication Romaniuk, R Photon Physics and Plasma Research, WILGA

2012; EuCARD Sessions 2012

1476018 Publication Romaniuk, R

WILGA Photonics and Web Engineering, January

2012; EuCARD Sessions on HEP and Accelerator

Technology

2012

WP4.1 (Period 1,2&3:21 publications)

1558692 Presentation Zimmermann, F High-Energy Frontier Circular Colliders 2013

1559323 Presentation Zimmermann, F Summary of EuCARD WP4 Accelerator Science

Networks "AccNet" 2009-2013 2013

1560093 Other/Other Assmann, R et

al

On the Prospect and Vision of Ultra-High

Gradient Plasma Accelerators for High Energy

Physics

2012

1498125 Presentation Zimmermann, F LEP3 and TLEP 2012

WP 4.2 (Period 1,2&3:97 publications)

1566883 Publication Dominguez, O

et al

First electron-cloud studies at the Large Hadron

Collider 2013

1564659 Workshop Bruning, O et al Summary of the 2013 LHC Optics Measurement

and Correction Review 2013

1564655 Scientific report Scandale, W UA9 Results from Crystal Collimation Tests in the

SPS & Future Strategy 2013

1559325 Presentation Zimmermann, F Bending and Focusing with Plasmas and Crystals

- Potential and Challenges 2013

1558694 Presentation Zimmermann, F LHC Status & Plan 2013

1558693 Presentation Zimmermann, F Circular Higgs Factories & Possible Long-Term

Strategy 2013

1556035 Presentation Zimmermann, F HL-LHC Accelerator 2013

1556032 Presentation Zimmermann, F LHC Status & Plan before HL-LHC 2013

Page 120: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 119 / 123

1556031 Presentation Zimmermann, F TLEP - The Machine 2013

1556027 Presentation Zimmermann, F A Circular e+e- Collider to Study H(125)

Properties - Accelerator 2013

1556028 Presentation Zimmermann, F Circular Higgs Factories: LEP3, TLEP and

SAPPHiRE 2013

1554310 Conference Koratzinos, M

et al

TLEP: A High-Performance Circular e+e-

Collider to Study the Higgs Boson 2013

1554306 Conference Ohmi, K et al Simulated Beam-Beam Limit for Circular Higgs

Factories 2013

1554305 Conference Dominguez, O

et al

Electron-Cloud Maps for the LHC Scrubbing

Optimization 2013

1554303 Conference Dominguez, O

et al

Beam Parameters and Luminosity Time Evolution

for an 80-km VHE-LHC 2013

1554302 Conference Maury Cuna, G

H I et al

Synchrotron-Radiation Photon Distributions for

Highest Energy Circular Colliders 2013

1554301 Conference Bruning, O et al Civil Engineering Feasibility Studies for Future

Ring Colliders at CERN 2013

1554300 Conference Yee-Rendon, B

et al

Machine Protection Studies for a Crab Cavity in

the LHC 2013

1552403 Workshop Franchetti, G et

al

Summary of the Space Charge Workshop 2013

(SC-13) 2013

1529710 Workshop Cimino, R et al Joint INFN-CERN-EuCARD-AccNet Workshop on

Electron-Cloud Effects 2012

1558188 Thesis Rijoff, T et al Testing Long-Range Beam-Beam Compensation

for the LHC Luminosity Upgrade 2012

1498122 Presentation Zimmermann, F SAPPHiRE and LHeC 2012

1498115 Presentation Ohmi, K Beam-beam simulations: dynamical effects and

beam-beam limit for LEP3 2012

1498118 Presentation Ohmi, K Beam-beam synchro-betatron resonance at the

LHC 2012

1498096 Presentation Zimmermann, F Circular Higgs Factories: LEP3, TLEP and

SAPPHiRE 2012

1498095 Presentation Zimmermann, F Future Possibilities for Precise Studies of the

X(125) Higgs Candidate-Higgs Factories 2012

1498089 Publication Franchetti, G et

al New Approach to Resonance Crossing 2012

1498088 Presentation Assmann, R Advanced Modeling and Measurements of LHC

Beam Halo and Collimation 2012

1498087 Conference Rijoff, T et al Simulating the Wire Compensation of LHC Long-

Range Beam-beam Effects 2012

1498084 Conference Franchetti, G et

al Space Charge and Electron Cloud Simulations 2012

1498082 Conference Iadarola, G et al Electron Cloud Simulations with PyECLOUD 2012

1498072 Conference Franchetti, G et

al

The Effect of Non-Zero Closed Orbit on Electron-

Cloud Pinch Dynamics 2012

Page 121: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 120 / 123

1498063 Conference Abelleira, J L et

al

Local Chromatic Correction Scheme and Crab-

Waist Collision for an Ultra-Low Beta* at the

LHC

2012

1470615 Conference Blondel, A P et

al

LEP3: A high luminosity e+e- collider in the LHC

tunnel to study the Higgs boson 2012

1451286 Conference Calaga, R et al Proton-beam emittance growth in SPS coasts 2012

1450938 Conference Rijoff, T et al Simulation studies for the LHC long-range beam-

beam compensators 2012

1450932 Conference Maury Cuna, H

et al

Simulation of electron-cloud heat load for the cold

arcs of the Large Hadron Collider 2012

1448194 Publication Maury Cuna, H

et al

Simulations of electron-cloud heat load for the

cold arcs of the CERN Large Hadron Collider and

its high-luminosity upgrade scenarios

2012

1443849 Scientific report Scandale, W UA9 Status Report 2012

WP 4.3 (Period 1,2&3:44 publications)

1498094 Conference Habib, S B et al Development of uTCA Hardware for BAM system

at FLASH and XFEL 2012

1498093 Conference Perek, P et al Image Visualisation and Processing in DOOCS

and EPICS 2012

1498092 Conference Mielczarek, A

et al Image Acquisition Module for uTCA Systems 2012

1498091 Conference Kozak, T et al FMC-based Neutron and Gamma Radiation

Monitoring Module for xTCA Applications 2012

1498081 Conference Koukovini-

Platia, E et al

Electromagnetic Characterization of Materials for

the CLIC Damping Rings 2012

1498079 Conference Niedermayer, U

et al

Numerical Calculation of Beam Coupling

Impedances in the Frequency Domain using FIT 2012

1498077 Conference Zannini, C et al EM Simulations in Beam Coupling Impedance

Studies: Some Examples of Application 2012

1473438 Other/Monograph Fraser, M A

Beam Dynamics Studies of the ISOLDE Post-

Accelerator for the High Intensity and Energy

Upgrade; EuCARD Editorial Series on

Accelerator Science and Technology, (J-

P.Koutchouk, R.S.Romaniuk, Editors), Vol.13

2012

WP 5.2 (Period 1,2&3:1 publication)

1557827 Conference Delonca, M et

al

A Clamped Be Window for the Dump of the

HiRadMat Experiment at CERN 2012

WP7.2 (Period 1,2&3: 7 publications)

1490580 Publication Pietrowicz, S et

al

Thermal conductivity and Kapitza resistance of

cyanate ester epoxy mix and tri-functional epoxy

electrical insulations at superfluid helium

temperature

2012

1451559 Scientific report Pietrowicz, S et

al Thermal models for the Fresca 2 high field magnet 2012

Page 122: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 121 / 123

1417804 Scientific report Polinski, J et al

Methodology for the certification of radiation

resistance of coil insulation material; milestone:

M7.2.1

2012

WP 7.5 (Period 1,2&3: 3 publications)

1451534 Scientific report Ballarino, A et

al Design report of Task 7.5, High-Tc Link 2012

1451261 Conference Yang, Y et al

First Electrical Characterization of Prototype 600

A HTS Twisted-pair Cables at Different

Temperatures

2012

WP8.1 (Period 1,2&3: 19 publications)

1551543 Conference Stadlmann, J et

al

Collimators and materials for high intensity heavy

ion synchrotrons 2012

WP 8.2 (Period 1,2&3: 30 publications)

1556543 Publication Bertarelli, A et

al

An experiment to test advanced materials

impacted by intense proton pulses at CERN

HiRadMat facility

2013

1553473 Publication Tahir, N A et al

Prospects of warm dense matter research at

HiRadMat facility at CERN using 440 MeV SPS

proton beam

2013

1552844 Conference Bertarelli, A et

al

First Results of an Experiment on Advanced

Collimator Materials at CERN HiRadMat Facility 2013

1553717 Conference Peroni, L et al Investigation of the Mechanical Behaviour of

Metal Diamond Composites 2012

1553711 Conference Peroni, L et al

High Strain-Rate Mechanical Behaviour of a

Copper Matrix Composite for Nuclear

Applications

2012

1553489 Publication Tahir, N A et al

Impact of high energy high intensity proton beams

on targets: Case studies for Super Proton

Synchrotron and Large Hadron Collider

2012

1552839 Conference Bertarelli, A et

al

High Energy Tests of Advanced Materials for

Beam Intercepting Devices at CERN HiRadMat

Facility

2012

WP 8.3 (Period 1,2&3: 4 publications)

1463346 Conference Bozyk, L et al Development of a Cryocatcher System for SIS100 2012

1463350 Thesis Bozyk, L

Entwicklung und Test eines Kryokollimator-

Prototypen zur Kontrolle des dynamischen

Vakuums im SIS100

2012

WP 9.2 (Period 1,2&3: 21 publications)

1428134 Scientific report Muranaka, T et

al

A comparative study of field emission properties of

Cu, Cr, and CrN 2012

L. Sánchez et al “Development and Testing of a Double Length

PETS for the CLIC Experimental Area”. Under 2012

Page 123: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 122 / 123

revision. Nuclear Inst. and Methods in Physics

Research A.

A. D’Elia et al

“Enhanced Coupling Design of a Detuned Damped

Structure for CLIC“, PAC12, May 1012, New

Orleans (LA), USA

2012

WP 9.3 (Period 1,2&3: 50 publications)

1519140 Conference Kemppinen, J et

al

CLIC main beam quadrupole active pre-alignment

based on cam movers 2012

1428911 Scientific report Petrone, C et al

Magnetic measurement of the model magnet QD0

designed for the CLIC final focus beam transport

line

2012

1428910 Publication Modena, M et

al

Design and Manufacture of a Hybrid Final Focus

Quadrupole Model for CLIC 2012

1428908 Publication Modena, M et

al

Design and Manufacture of a Main Beam

Quadrupole Model for CLIC 2012

1423022 Scientific report Esposito, M Influence of the Coil and the Magnet Support on

the Modal Behaviour of the CLIC type 4 MBQ 2012

1409458 Conference Christian, G B

et al

Latest Performance Results from the FONT5

Intra-train Beam Position and Angle Feedback

System at ATF2

2012

WP 9.4 (Period 1,2&3: 24 publications)

1436104 Conference Deacon, L C et

al Muon Background Reduction in CLIC 2012

WP 9.5

P.K.

Skowronski et

al

Design of Phase Feed Forward System in CTF3

and Performance of Fast Beam Phase Monitors,

IPAC2013

2013

V.R. Arsov et al First Results from the Bunch Arrival-Time

Monitor at the SwissFEL Test Injector, IBIC2013 2013

WP 10.3 (Period 1,2&3:12 publications)

1439010 Workshop Arduini, G et al 5th LHC Crab Cavity Workshop, LHC-CC11

Workshop Summary Report 2012

WP 10.5 (Period 1,2&3:26 publications)

1553214 Conference Flisgen, T et al A Concatenation Scheme for the Computation of

Beam Excited Higher Order Mode Port Signals 2013

1550988 Conference Zhang, P et al

Status of higher order mode beam position

monitors in 3.9 GHz superconducting accelerating

cavities at FLASH

2013

1553230 Conference Flisgen, T et al Lumped Equivalent Models of Complex RF

Structures 2012

1552917 Scientific report Shinton, I R R

et al

Compendium of Eigenmodes in Third Harmonic

Cavities for FLASH and the XFEL 2012

Page 124: D3.1: 3rd periodic EuCARD report - public version · D3.1: 3rd periodic EuCARD report - public version Koutchouk, J (CERN) et al 20 June 2014 The research leading to these results

3RD PERIODIC EUCARD REPORT

Doc. Identifier:

EuCARD-

Period_3_Public_Report_v10

Date: 15/10/2013

Grant Agreement 227579 RESTRICTED 123 / 123

1550977 Thesis Zhang, P

Beam Position Diagnostics with Higher Order

Modes in Third Harmonic Superconducting

Accelerating Cavities

2012

1550975 Scientific report Zhang, P et al

A Study of Beam Position Diagnostics with Beam-

excited Dipole Higher Order Modes using a

Downconverter Test Electronics in Third

Harmonic 3.9 GHz Superconducting Accelerating

Cavities at FLASH

2012

1550973 Scientific report Zhang, P et al

Higher order mode spectra and the dependence of

localized dipole modes on the transverse beam

position in third harmonic superconducting

cavities at FLASH

2012

1550971 Scientific report Zhang, P et al

Eigenmode Simulations of Third Harmonic

Superconducting Accelerating Cavities for FLASH

and the European XFEL

2012

1550967 Conference Wamsat, T et al

Performance of a downconverter test-electronics

with MTCA-based digitizers for beam position

monitoring in 3.9GHz accelerating cavities

2012

1550966 Publication Zhang, P et al

Statistical methods for transverse beam position

diagnostics with higher order modes in third

harmonic 3.9 GHz superconducting accelerating

cavities at FLASH

2012

1550964 Publication Zhang, P et al

Resolution study of higher-order-mode-based

beam position diagnostics using custom-built

electronics in strongly coupled 3.9 GHz multi-

cavity accelerating module

2012

1550962 Publication Zhang, P et al

A study of beam position diagnostics using beam-

excited dipole modes in third harmonic

superconducting accelerating cavities at a free-

electron laser

2012

1550726 Conference Shinton, I R R

et al

Simulations of Higher Order Modes in the ACC39

Module of FLASH 2012

1550721 Conference Baboi, N et al

HOM Choice Study with Test Electronics for Use

as beam Position Diagnostics in 3.9 GHz

Accelerating Cavities in FLASH

2012

WP 10.7 (Period 1,2&3:14 publications)

1436390 Conference Murcek, P et al Modified SRF Photoinjector for the ELBE at

HZDR 2012

1436382 Conference Teichert, J et al Operation of the superconducting RF photo gun at

ELBE 2012