darryl ackley, secretary, doit mike neitzey, project manager may 25, 2011

10
Statewide Interoperable Radio Communications Internet Transport System (SIRCITS) to the Project Certification Committee Darryl Ackley, Secretary, DoIT Mike Neitzey, Project Manager May 25, 2011

Upload: otto-barker

Post on 02-Jan-2016

22 views

Category:

Documents


2 download

DESCRIPTION

Statewide Interoperable Radio Communications Internet Transport System (SIRCITS) to the Project Certification Committee. Darryl Ackley, Secretary, DoIT Mike Neitzey, Project Manager May 25, 2011. Project History. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Darryl Ackley, Secretary, DoIT Mike Neitzey, Project Manager May 25, 2011

Statewide Interoperable Radio Communications Internet Transport System

(SIRCITS) to the

Project Certification Committee

Darryl Ackley, Secretary, DoITMike Neitzey, Project Manager

May 25, 2011

Page 2: Darryl Ackley, Secretary, DoIT Mike Neitzey, Project Manager May 25, 2011

Project History

SIRCITS grant was awarded in August 2010 under the second round of Broadband Technology Opportunity Program (BTOP) grant solicitations from the Department of Commerce.

The purpose of the grant is to complete the transition of the statewide public safety microwave system from analog to digital allowing broadband access to anchor institutions and allowing the state and its partners (through sharing agreements) to support broadband service in unserved, underserved and tribal areas. A last mile component will deploy 700 MHz public safety broadband service.

Funding includes: $38,699,997 in Federal Funds $5,399,999 in appropriated State Funds $11,600,000 in-kind match

Page 3: Darryl Ackley, Secretary, DoIT Mike Neitzey, Project Manager May 25, 2011

Project Status

Approved by NTIA/Grants Office Baseline Infrastructure Report Baseline Project Plan Budget Amendment 1 Six month+ budget Sole source for legal support

Submitted but not yet approved Overlay maps showing overlap/adjacency to other grant projects

Approved by the State 1511 Certification by the governor Budget by NMORR Three term positions approved by Governor, NMORR, and DFA

are now at State Personnel Office

Page 4: Darryl Ackley, Secretary, DoIT Mike Neitzey, Project Manager May 25, 2011

Project Status

In progressEnvironmental Assessments on the 73 sitesNew Price Agreements for construction of the 59 middle mile sites

To DoFinalize Price Agreements for the DMW constructionIV&V ContractHire Term positionsStart the RFP process for the 700MHz construction

Page 5: Darryl Ackley, Secretary, DoIT Mike Neitzey, Project Manager May 25, 2011

Proposed Budget

$7,175,000 Planning Request$7,000,000

5 DMW contracts for Design and Planning Contractor project management in 5 regions

$175,000 Legal expenses$200,000

Page 6: Darryl Ackley, Secretary, DoIT Mike Neitzey, Project Manager May 25, 2011

Issues

Weather and Fire restrictions play a role in upgrade delays encountered at several remote radio sites. Completion of updated site lease agreements can also cause unexpected delays.

Coordination with Dept of Homeland Security and possible duplication of efforts

Compliance with requirements under 700 MHz lease, including completion of an interoperability plan

Page 7: Darryl Ackley, Secretary, DoIT Mike Neitzey, Project Manager May 25, 2011

Attention Areas

Hiring Technical staff to assist in completion/oversight of the efforts

Having adequate number of contractors to work in different site areas at the same time

Establishing scheduling changes for DoIT staff so they may participate in the upgrade, as providers or overseers.

Network Administration needs resources

Page 8: Darryl Ackley, Secretary, DoIT Mike Neitzey, Project Manager May 25, 2011

Overall Schedule

The draft environmental Assessment is due by the May 31, 2011

Procurement of the IV&V contractor during the 1st quarter of 2012

Construction cannot proceed until the State receives a signed Finding Of No Significant Impact (FONSI)

RFP & Price Agreements for the 700MHz construction completed during the 3rd quarter 2012

The SIRCITS project site upgrades must be substantially completed by June 30, 2013.

Page 9: Darryl Ackley, Secretary, DoIT Mike Neitzey, Project Manager May 25, 2011

Resources DoIT will hire:

a Project Manager, a Business Analyst, and a Financial Coordinator

DoIT will contract for: an engineer to work with DoIT radio technical staff to

oversee contractors’ work on the project IV&V services

DoIT radio technical staff will maintain day to day operations on two-way radio network and all facilities at radio sites during upgrade.

Page 10: Darryl Ackley, Secretary, DoIT Mike Neitzey, Project Manager May 25, 2011

Thank You…….

Questions?