december accomplishments: design and construction continued trenching for and laying of storm drain...
TRANSCRIPT
December Accomplishments:Design and Construction
• Continued trenching for and laying of storm drain pipe in Flower Street from I -110 to 23rd Street
• Started procurement of the 61” water line for Work Package A4, 61” Water Line Relocation
• Received 30% designs from FFP for Work Package C2, Harcourt to Venice Corridor Improvements
• Received 60% designs from FFP for Work Package A2, 23rd Street
to Vermont Corridor Improvements, and A3, Trench Structure
1
December Accomplishments:Construction Progress
2
December Accomplishments:Construction Progress
3
December Accomplishments:Construction Progress
4
December Accomplishments: Community/Government Relations
• Conducted an Urban Design Committee meeting on December 12, 2006
• Provided a tour of the Expo right-of-way for Gloria Jeff, General
Manager, LADOT • Disseminated notices regarding (Tree Removal) activities to
businesses and residents along Flower Street on December 14, 2006
• Met with administrators, parents and teachers in schools to provide construction schedule and safety information tips.
• Met with USC and Expo Park Stakeholders to discuss Urban Design elements for the project
• Conducted business assessments to coordinate access and various other needs prior to start of construction activities.
5
December Accomplishments: Real Estate
• Continued real estate acquisition and lease termination activities.
• Abandonment of Parcel WE-616 completed; Funds returned from the Court. Negotiated attorney’s fees with two of owner’s attorneys.
• One parcel acquired; five offers pending • Continued supplemental hazardous materials investigations along
the Metro right-of-way
6
January Planned Activities:Design and Construction• Complete negotiation of remaining Master Cooperative Agreements
• Complete negotiation of Third Party Annual Work Plans and issue Work Orders
• FFP to submit the System Integration Plan (Final)
• FFP to submit 60% design for Work Packages B1, 2, Harcourt to Venice Corridor Improvements
• FFP to submit 60% design for Work Packages B1, Vermont to Harcourt Utilities, and B2 Vermont to Harcourt Corridor Improvements
• FFP to submit 60% design for Work Package C1, Graphics/Signage
• FFP to submit 85% design for Work Package D2, Track Procurement
7
January Planned Activities: Community/Government Relations • Continue meeting with administrators, parents and teachers
• Host Urban Design Committee Meetings
• Brief LAUSD Board Member in Board District 1
• Continue Business Assessment Coordination
• Briefing for State and Federal Elected Official Deputies
Real Estate
• Continue real estate acquisition and lease termination activities
8
Project Major MilestonesOct 2006 Nov 2006
Authority Actions
Dec 2006 Jan 2007 Feb 2007
Design Build Contract
Community Outreach
DowntownCommunity Meeting & Business
Merchants Meeting
Mar 2007
Legend:Urban Design Committee Meeting
Start Construction
Negotiate Construction Package A4 ( 61” Waterline)
Approve Construction Package A4 (61” Waterline)
Mid-CorridorCommunity Meeting
Downtown and West EndCommunity Meetings
Dorsey H.S. Teachers & Parents Meeting
Approve LTP for Procurement TPSS Prefab Bldg Package D3
Negotiate LTP for Procurement TPSS Prefab Bldg Package D3
Negotiate LTP for Procurement 60” & 48 Pipe Work Package A2
Approve LTP for Procurement 60” & 48 Pipe Work Package A2
Approve NTE for Design of Ballona Creek Bridge & USC/ Expo Park Station
Negotiate NTE for Design of Ballona Creek Bridge & USC/ Expo Park Station
Downtown Project Status Update Meeting
Mid-Corridor Project Status Update Meeting
9
December 2006
• Received and reviewed responses to the RFQ to select Community and Faith-Based Organizations to recruit, screen and train individuals to participate in the Local Jobs Program.
• Hired local workers th10rough PV Jobs for intermittent work to distribute construction notices throughout the Corridor
• Continued to update database of individuals interested in seeking employment with the Expo Local Jobs Program
• Hosted Job Fair at construction field office to recruit employees for Infinity Protection Services, a local firm hired to provide security services along the Expo corridor.
• Hired a Contracts Manager through a DBE firm
Summary of Jobs Program Activities:
10