decision modelling & feasibility study

Upload: salahelgabo

Post on 06-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Decision Modelling & Feasibility Study

    1/119

    Egyptian Electricity Holding Company(EEHC)

    Strategic Planning Sector

    Economical Studies Department

  • 8/3/2019 Decision Modelling & Feasibility Study

    2/119

    Case Study & Cost Benefit Analysis

    Presentation

    in

    Prepared by

    Eng. Mohamed Rashad Mojahed

  • 8/3/2019 Decision Modelling & Feasibility Study

    3/119

    COST-BENEFIT ANALYSIS:

    It determines the expected benefits andsavings from a candidate system andcompare them with costs.

    CostCost Benefit AnalysisBenefit Analysis

    It is a systematic process for calculating

    and comparing benefits and costs of aninvestment.

    In other Word

  • 8/3/2019 Decision Modelling & Feasibility Study

    4/119

    Will the project generate adequate cash flow and profits?

    Will the project withstand the risks it will encounter?

    Will the project remain viable in the long-term?

    Will the project meet the goals of the founders?

    It helps in answering the following questions :

    CostCost Benefit AnalysisBenefit Analysis

  • 8/3/2019 Decision Modelling & Feasibility Study

    5/119

    CostCost Benefit AnalysisBenefit Analysis

    Steps of Cost-Benefit Analysis

    collect enoughdata about

    elements ofcosts andBenefits of

    project

    Predict a cashflow for

    costs&Benefits overthe Project life

    time

    Select adiscount rate

    and CalculateNPV & IRR of

    the project

    Make asensitivity

    analysis

    1 2 3 4

  • 8/3/2019 Decision Modelling & Feasibility Study

    6/119

    Types of Costs Benefit Analysis

    Financial Cost-Benefit

    Analysis

    Economical Cost-Benefit

    Analysis

    CostCost Benefit AnalysisBenefit Analysis

  • 8/3/2019 Decision Modelling & Feasibility Study

    7/119

    It looks at the project fromthe point of view of theimplementing agency.

    It looks at a project fromthe point of view of the

    entire country (society).

    It determine the ability to

    meet its financialobligations and to finance

    future investments.

    It measures the effects ofthe project on the

    economy as a whole.

    It is based on the Market

    prices.

    It is based on the Real prices.

    Financial Cost-Benefit

    Analysis:

    Economical Cost-Benefit

    Analysis:

    CostCost Benefit AnalysisBenefit Analysis

  • 8/3/2019 Decision Modelling & Feasibility Study

    8/119

    Cost-Benefit Analysis forA combined cycle power plant

    the feasibility study for the CCGT containsmost of the assumptions and steps which

    can be used and applied to any other type ofpower plants (thermal Hydro wind

    solar).

    Why the CCGT ?

    CostCost Benefit AnalysisBenefit Analysis

  • 8/3/2019 Decision Modelling & Feasibility Study

    9/119

    A General Description for CCGT:

  • 8/3/2019 Decision Modelling & Feasibility Study

    10/119

    Capital CostCapital Cost

    Items of Cost Benefit AnalysisItems of Cost Benefit Analysis

    Operation and maintenance costsOperation and maintenance costs

    Fuel costsFuel costs

    Project RevenuesProject Revenues

    Cash Flow net incomeCash Flow net income

    Income StatementIncome Statement

  • 8/3/2019 Decision Modelling & Feasibility Study

    11/119

    Capital CostCapital Cost

  • 8/3/2019 Decision Modelling & Feasibility Study

    12/119

    Capital CostCapital Cost

    -It is the costs of equipments andmaterials that will be used in theconstruction process of the power

    plant.

    Components of Capital Cost

    Direct CostsComponents

    Un certaintycomponents

  • 8/3/2019 Decision Modelling & Feasibility Study

    13/119

    Capital CostCapital Cost

    -It is costs which can be traced directly to aspecific object like:

    Direct Costs component:

    Land.Buildings.Construction materials.Equipments.Steam Turbines

    Gas TurbinesSwitch yardsTransformers

  • 8/3/2019 Decision Modelling & Feasibility Study

    14/119

    Risk & Un certainty Components

    Capital CostCapital Cost

    It is the probability that an returnof an investment actual will be

    different than expected.

    Positive Way Wrong Way

    Increase In Profit

    Reduction In Costs

    Decrease In Profit

    Increase In Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    15/119

    Capital CostCapital Cost

    Risk & Un certainty Components

    Causes of Risk & Un certainty:

    Increasing in the prices of raw materialsThe lapsing of deadlines for construction of anew operating facility.

    The change of a political systemNatural disasters

  • 8/3/2019 Decision Modelling & Feasibility Study

    16/119

    Capital CostCapital Cost

    Risk & Un certainty ComponentsThere are some values and components which can betaken into consideration during the estimating of thetotal capital cost of the project to reduce the levels of

    uncertainty and eliminate economic risk as much aspossible.

    WorkingCapital

    PhysicalContingency

    PriceContingency

  • 8/3/2019 Decision Modelling & Feasibility Study

    17/119

    Capital CostCapital Cost

    Risk & Un certainty Components

    Working Capital:

    It is a financial metric which represents operating liquidity

    (liquid money) available to a business, Along with fixedassets such as plant and equipment.

    In other word

    Working capital is an amount of liquid money which is

    adequate to cover costs of operation of the power plantduring its starting operation period in case of the powerplant does not gained profit during that period.

    It equals to (60) day of operation and maintenance costs

    in addition to (30) day of fuel costs.

  • 8/3/2019 Decision Modelling & Feasibility Study

    18/119

    Capital CostCapital Cost

    Risk & Un certainty Components

    Physical Contingency

    The estimated costs of the additional real resources

    expected to be required

    Price Contingency

    It is considered against changes in relative prices of

    project inputs due to general inflation and changes inthe value of monetary units .

  • 8/3/2019 Decision Modelling & Feasibility Study

    19/119

    Capital CostCapital Cost

    Risk & Un certainty Components

    Financial Cost Benefit Analysis:

    All Uncertainty components:

    Working Capital

    Physical contingency

    Price Contingency)

    are added to the Direct Costs of the Capital cost.

  • 8/3/2019 Decision Modelling & Feasibility Study

    20/119

    Capital CostCapital Cost

    Risk & Un certainty Components

    Economical Cost Benefit Analysis:

    Physical Contingency & Working Capital

    Price contingency

    They are not added to the direct capital costs of thepower plant.

    Physical contingency represent expected real costs so itis added to the direct capital costs of the power plant

  • 8/3/2019 Decision Modelling & Feasibility Study

    21/119

    Operation & Maintenance costsOperation & Maintenance costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    22/119

    It includes costs of all various services required to assurethat the power plant will perform the functions it was

    designed and constructed for.

    Operations and maintenance are combined into thecommon term O&M because a facility cannot operate atpeak efficiency without being maintained; therefore the

    two are discussed as one.

    Definition:

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    23/119

    Operation & Maintenance CostsOperation & Maintenance Costs

    Variable O&M Fixed O&M

    Types of Operation & MaintenanceCosts

  • 8/3/2019 Decision Modelling & Feasibility Study

    24/119

    Variable operation & maintenance costsThese costs, defined as $/MWh, which refers to the theoperations and maintenance costs which changes accordingto the changing in the production level of the electrical

    energy by one unit.

    Example:

    Minor unplanned maintenance.

    Periodic maintenance costs.

    Water treatment chemicals.

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    25/119

    Fixed operation & maintenance cost

    These costs, defined as $/kW/year, this type of costs is afixed costs which do not change with changing in theproduction level of electrical energy.

    Example:

    Plant manager's office & employee salaries.

    Technical support costs.

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    26/119

    Financial Cost Benefit Analysis:

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    27/119

    This column represents the total installed capacity

    (MW) of the power plant, which assumed in theideal case to be fixed over the project life time

    Financial Cost Benefit Analysis:

    Total Energy generated per year (GWH)= Total installed capacity (MW) * number of hours per

    year * capacity factor (%)

    Column (D)

    Column (E)

    This column represents the total energy generated

    (GWH) from the power plant at specific capacityfactor

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    28/119

    Financial Cost Benefit Analysis:

    Fixed O&M costs (million $)= Fixed O&M costs ($/KW/yr) * Total installed

    capacity (MW) / 1000

    The Value of Fixed O&M costs ($/KW/yr) year2013 is the escalated value of Fixed O&M costs($/KW/yr) at the base year 2009 (With escalation

    Rate 3%).

    Column (F)

    Note 1: (For Year 2013)

    This column represents the Fixed O&M costs for

    each year over the project life time in (million $).

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    29/119

    Financial Cost Benefit Analysis:

    Note 2:

    An escalation Rate (3%) has been taken intoconsideration in calculating the values of Fixed O&Mcosts Over the project life time.

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    30/119

    Financial Cost Benefit Analysis:

    Column (G)

    Variable O&M costs (million $)= Variable O&M costs ($/GWh)

    * Total generated energy (GWh)

    This column represents the Variable O&M

    costs for each year over the project life timein (million $).

    The Value of Variable O&M costs ($/Mwh)year 2013 is the escalated value of VariableO&M costs ($/KWh) at the base year 2009

    (With escalation Rate 3%).

    Note 1: (For Year 2013)

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    31/119

    Maintenance & Operating ExpensesMaintenance & Operating Expenses

    Financial Cost Benefit Analysis:

    Note 2:

    An escalation Rate (3%) has been taken into

    consideration in calculating the values ofFixed O&M costs Over the project life time.

    Every 5 years, the cost of periodic

    maintenance is added to the Variable O&Mcosts, but with taking into consideration anescalation rate (3%) in the cost of theperiodic maintenance from the base year(2009) to the year of calculation.

    Note 3:

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    32/119

    Financial Cost Benefit Analysis:

    Note 4:

    It will be no periodic maintenance costsadded in the 25th year of commissioning,because it will be total rehabilitation in the 2gas turbines at that year.

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    33/119

    Financial Cost Benefit Analysis:

    Column (H)

    This column represent the Total O&Mcosts (million $) costs for each yearover the project life time in (million $).

    Total O&M costs (million $)

    + Variable O&M costs (million $)

    = Fixed O&M costs (million $)

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    34/119

    Economical Cost Benefit Analysis:

    The financial cost Benefit analysis uses the market pricesfor representing both values of Fixed & Variable O&Mcosts

    So, that market prices are needed to be converted to itsrelative real prices to be suitable for the Economical costBenefit analysis which can be done by using the following

    assumptions.

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    35/119

    Economical Cost Benefit Analysis:

    According to the definition of :

    It is the wages and salaries of the all workers in thepower plant.

    Fixed O&M costs

    The economic costs benefit analysis assumes that theworkers of the power plant are not treated by the same

    way and the skilled worker is different from the unskilledworkers and they both different from the administrators

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    36/119

    Economical Cost Benefit Analysis:

    The values of the Fixed O&M Cost ($/KW) is divided

    into 3 unequal components:skilled workers (60 % of total fixed O&M cost)

    unskilled workers (30 % of total fixed O&M cost)

    Administrators (10 % of total fixed O&M cost)

    SoSo

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    37/119

    Economical Cost Benefit Analysis:

    Account Ratio:

    It is a relative magnitude which used in converting themarket prices of a goods or services to its the real prices.

    = (Real price / Market price)

    skilled workers (account ratio = 2 or 4)unskilled workers (account ratio = 1)

    Administrators (account ratio = 1)

    Multiply each component in its relative appropriateaccount ratio.

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    38/119

    Economical Cost Benefit Analysis:

    Variable O&M costs

    To convert the Variable O&M costs ($/MWH) to its realprices it is multiplied in its a relative account ratio.

    Account ratio For Variable O&M Costs = 0.97 %

    It represents the incremental operations and maintenance

    costs incurred upon increasing the level of production byone unit.

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    39/119

    Economical Cost Benefit Analysis:

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    40/119

    Economical Cost Benefit Analysis:

    This column represents the total installed capacity

    (MW) of the power plant, which assumed in theideal case to be fixed over the project life time

    Total Energy generated per year (GWH)= Total installed capacity (MW) * number of hours

    per year * capacity factor (%)

    Column (D)

    Column (F)

    This column represents the total energy generated

    (GWH) from the power plant at specific capacityfactor

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    41/119

    Column (G, H, I, J& K)

    Those 5 columns represent thecalculation of the Fixed O&M

    costs in the Economical CostBenefit analysis.

    Economical Cost Benefit Analysis:

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    42/119

    Economical Cost Benefit Analysis:

    Column (G)

    This column represents the share of theskilled workers costs (M$) which equal to(60%) from the total Fixed O&M costs overthe project life time.

    = Fixed O&M costs at year 2013 ($/KW) * 60% * totalCapacity (MW)* 60 %

    The costs of the skilled workers at year 2013 (M$)

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    43/119

    Economical Cost Benefit Analysis:

    Note 1: (For Year 2013)The Value of Fixed O&M costs ($/KW/yr)year 2013 is the escalated value of FixedO&M costs ($/KW/yr) at the base year 2009(With escalation Rate 3%).

    Note 2:

    The costs of the Skilled Workers in theeconomical cost benefit analysis is consideredto be fixed in all years over the power plantlife time and equal to the costs of the skilled

    workers at the year of commission.

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    44/119

    Economical Cost Benefit Analysis:

    Column (H)

    This column represents the account ration (2)

    which is required to convert the salaries andwages of the Skilled Workers from its marketvalues to its relative real values.

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    45/119

    Economical Cost Benefit Analysis:

    Column (I)

    This column represents the share ofthe unskilled workers costs (M$)which equal to (30%) from the totalFixed O&M costs over the project lifetime.

    The costs of the unskilled workers at year2013

    =Fixed O&M costs at year 2013 ($/KW)*total Capacity (MW)* 30%

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    46/119

    Economical Cost Benefit Analysis:

    Note 2:

    The costs of the Un Skilled Workers in theeconomical cost benefit analysis is consideredto be fixed in all years over the power plantlife time and equal to the costs of the Unskilled workers at the year of commission

    and that is for

    Note 1: (For Year 2013)

    The Value of Fixed O&M costs ($/KW/yr)

    year 2013 is the escalated value of FixedO&M costs ($/KW/yr) at the base year 2009(With escalation Rate 3%).

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    47/119

    Economical Cost Benefit Analysis:

    Note 3:

    The account ratio of the for the conversion of costs of the

    Unskilled workers from its market prices to its realprices is assumed to be (1)

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    48/119

    Economical Cost Benefit Analysis:

    Column (J)

    This column represents the share of the

    administrator costs (M$) which equal to(10%) from the total Fixed O&M costsover the project life time.

    The costs of the administrator at year 2013

    =Fixed O&M costs at year 2013 ($/KW)* totalCapacity (MW)* 10%

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    49/119

    Economical Cost Benefit Analysis:Note 1: (For Year 2013)

    The Value of Fixed O&M costs($/KW/yr) year 2013 is the escalated

    value of Fixed O&M costs ($/KW/yr)at the base year 2009 (With escalationRate 3%).Note 2:

    The costs of the administrators in theeconomical cost benefit analysis isconsidered to be fixed in all years over thepower plant life time and equal to the costsof the administrators at the year of

    commission.

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    50/119

    Economical Cost Benefit Analysis:

    Note 3:

    The account ratio of the for the conversion of costs of the

    Unskilled workers from its market prices to its realprices is assumed to be (1)

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    51/119

    Column (M)

    This column represents the total

    economical Fixed O&M costs.

    Economical Cost Benefit Analysis:

    = [Skilled workers costs (M$) * account ratioof Skilled workers costs (%)]

    + Un Skilled workers costs (M$)

    + administrators Costs (M$)

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    52/119

    Economical Cost Benefit Analysis:

    Column (L&M)

    Those 2 columns represent the

    calculation of the Variable O&M costsin the Economical Cost Benefitanalysis.

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    53/119

    Column (L)

    This column represents the Variable O&M

    costs in its real prices (M$) over the powerplant life time.

    Variable O&M costs (million $)

    = Variable O&M costs ($/MWh) * Total generatedenergy (GWh) / 1000

    Economical Cost Benefit Analysis:

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    54/119

    Economical Cost Benefit Analysis:

    Note 1: (For Year 2013)

    The Value of Variable O&M costs ($/KW/yr)

    year 2013 is the escalated value of VariableO&M costs ($/KW/yr) at the base year 2009(With escalation Rate 3%).

    Note 2:

    The costs of the Variable O&M costs in theeconomical cost benefit analysis is consideredto be fixed in all years over the power plant lifetime and equal to the costs of the VariableO&M costs at the year of commission.

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    55/119

    Every 5 years, the cost of periodic

    maintenance is added to the Variable O&Mcosts, except for the year of the totalrehabilitation of the 2 gas turbines.

    Note 3:

    Note 4:The costs of the periodic maintenance,which added every 5 years, is considered tobe constant over the power plant life time.

    Economical Cost Benefit Analysis:

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    56/119

    Economical Cost Benefit Analysis:

    Column (M)

    This column represents the account ration

    (0.97) which is required to convert the VariableO&M costs from its market values to itsrelative real values.

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    57/119

    Column (N)

    This column represents the total Variable

    O&M costs in its real values.

    = [Variable O&M costs (M$) * account ratio ofVariable O&M costs (%)]

    Economical Cost Benefit Analysis:

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    58/119

    Economical Cost Benefit Analysis:

    Column (O)

    This column represents the total O&M costs (M$) for each

    year over the project period life time.

    = Total Fixed O&M costs (M$) + Total Variable O&Mcosts (M$)

    Operation & Maintenance CostsOperation & Maintenance Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    59/119

    Fuel CostsFuel Costs

  • 8/3/2019 Decision Modelling & Feasibility Study

    60/119

    Fuel CostsFuel Costs

    It is the costs related to the fuelconsumption process which is requiredfor the generation of electrical energyfrom the power plant.

    Required items for fuel costs calculation:

    Power plant heat rate

    Fuel calorific value (Heat content)

    Fuel Price ($/MMBTU)

  • 8/3/2019 Decision Modelling & Feasibility Study

    61/119

    Fuel CostsFuel Costs

    It is the total amount of heat energy needed by all unitsin the power plant to produce one unit of electricalenergy. (BTU/KWh)

    Power plant heat rate

    The combined cycle power plant consists of 2 gas

    turbines and 1 steam turbine.

    How to calculate the total heat rate for a combinedcycle power plant ?

    The fuel consumption occurs in the 2 gas turbines, wherethe steam turbine depends on the hot exhausted gas fromthe gas turbine in generating the electrical energy.

  • 8/3/2019 Decision Modelling & Feasibility Study

    62/119

    Fuel CostsFuel Costs

    Assume the heat rate of one gas turbine is(1000 BTU/KWH).

    The amount of heat energy needed by the gas

    turbine is (1000 BTU) to produce one (KWH) ofelectrical energy

    Total power plant heat rate 1000 BTU/KWH

    One gas turbine heat rate 1000 BTU/KWH

    It means that

    So, if the power plant works with this gas turbine only

    Then,

  • 8/3/2019 Decision Modelling & Feasibility Study

    63/119

    Fuel CostsFuel Costs

    Total power plant heat rate 1000 BTU/KWH

    One gas turbine heat rate 1000 BTU/KWH

    I

    f the power plant works with 2 gas turbines ,where the heatrate of each one is (1000 /KWH)

    So,

    Two gas turbine heat rate 2 * 1000 BTU/ 2 KWH

    Two gas turbine heat rate 1000 BTU/KWH

    Then,

  • 8/3/2019 Decision Modelling & Feasibility Study

    64/119

    Fuel CostsFuel Costs

    One gas turbine heat rate 1000 BTU/KWH

    when the power plant works with 2 gas turbines and onesteam turbine ,where the steam turbine does not consumesany additional amount of fuel but it depends on the exhaustedgas from the 2 gas turbines to generate electrical energy.

    So,

    Two gas turbine heat rate 1000 BTU/KWH

    2 gas turbine & 1 steam turbine heat rate 2* 1000 BTU/ 3 KWH

    2 gas turbine & 1 steam turbine heat rate (2/3)*1000 BTU/KWH

  • 8/3/2019 Decision Modelling & Feasibility Study

    65/119

    Total power plant heat rate 666.6 BTU/KWH

    Fuel CostsFuel Costs

    It means that,

    Total power plant heat rate (2/3) * 1000 BTU/KWH

    The total amount of heat energy needed by the

    combined cycle power plant is (666.6 BTU) toproduce one (KWH) of electrical energy

    Then,

  • 8/3/2019 Decision Modelling & Feasibility Study

    66/119

    Fuel CostsFuel Costs

    Fuel calorific value (Heat content)

    The calories or the thermal units contained in one unitof fuel and released when that fuel is burned. (BTU/m3)

    The combined cycle power plant it can work with 2 types offuel:

    (Natural Gas) as the main type of fuel.

    (Solar) as the secondary fuel type in case ofunavailability of natural gas .

  • 8/3/2019 Decision Modelling & Feasibility Study

    67/119

    Fuel CostsFuel Costs

    Financial Cost Benefit Analysis:

  • 8/3/2019 Decision Modelling & Feasibility Study

    68/119

    Fuel CostsFuel Costs

    Financial Cost Benefit Analysis:

    Column (D)

    This column represents the total generatedenergy (GWh) from the power plant overthe project life time.

  • 8/3/2019 Decision Modelling & Feasibility Study

    69/119

    Column (E)

    This column represents the total heat rate of

    the power plant (BTU/KWh) over theproject life time.

    Note 1:

    The total heat rate of the power plantincreases over the project life time due toaging and depreciation.

    Fuel CostsFuel Costs

    Financial Cost Benefit Analysis:

  • 8/3/2019 Decision Modelling & Feasibility Study

    70/119

    Fuel CostsFuel Costs

    Financial Cost Benefit Analysis:

    Note 3:

    The changing in the heat rate of the power

    plant over project life time, can be providedfrom the manufacturer of the power plant orfrom a historical data for other combinedcycle power plants in the electrical grid.

    Note 2:

    After each 5 years, the total heat rate of thepower plant is reduces with small value due to

    the periodic maintenance of the power plant.

  • 8/3/2019 Decision Modelling & Feasibility Study

    71/119

    Fuel CostsFuel Costs

    Financial Cost Benefit Analysis:

    Column (F&G)

    This 2 columns represent the prices of(Natural gas) and (Solar) in ($/MMBTU)over the power plant life time.

  • 8/3/2019 Decision Modelling & Feasibility Study

    72/119

    Fuel CostsFuel Costs

    Financial Cost Benefit Analysis:

    In the Financial analysis the represented

    fuel prices over the project life time isconsidered to be the fuel market prices,which can be taken according to:

    Note:

    An agreement between the ministry of

    electricity and the fuel supplier

    By making escalation in the first yearfuel price with suitable and realisticescalation rate.

  • 8/3/2019 Decision Modelling & Feasibility Study

    73/119

    Fuel CostsFuel Costs

    Financial Cost Benefit Analysis:

    Column (H)

    This column represents the total fuel

    costs of the power plant in (million $)over the project life time.

    The total fuel costs (M$)

    = The Natural gas costs (M$) +The Solar costs (M$)

  • 8/3/2019 Decision Modelling & Feasibility Study

    74/119

    Fuel CostsFuel Costs

    Financial Cost Benefit Analysis:

    Note:

    The main fuel type (Natural gas) is considered to berepresenting 95% in the total fuel costs.The secondary fuel type (Solar) is considered to berepresenting 5% in the total fuel costs.

  • 8/3/2019 Decision Modelling & Feasibility Study

    75/119

    Fuel CostsFuel Costs

    Financial Cost Benefit Analysis:

    Then,

    The Natural gas costs (M$)

    =Energy Generated (MWh) * Power Plant Heat Rate(MMBTU/MWh)* Natural Gas Price ($/MMBTU)* 95%

    The Solar costs (M$)

    =Energy Generated (MWh) * Power Plant Heat Rate

    (MMBTU/MWh)* Solar Price ($/MMBTU)* 5%

    The total fuel costs (M$)

    = The Natural gas costs (M$) + The Solar costs (M$)

  • 8/3/2019 Decision Modelling & Feasibility Study

    76/119

    Fuel CostsFuel Costs

    Economical Cost Benefit Analysis:

    The representing of fuel costs in the economical analysis forthe over the project life time is done by the same

    methodology of representing the fuel costs in the financialanalysis.

    except that,

    In the economical analysis the fuel prices is entered in its

    real prices.

  • 8/3/2019 Decision Modelling & Feasibility Study

    77/119

    Project RevenueProject Revenue

    T

    his part represents the revenues from selling theelectrical energy generated from the power plant inthe cash flow analysis.

    jj

  • 8/3/2019 Decision Modelling & Feasibility Study

    78/119

    Project RevenueProject Revenue

    Financial Cost Benefit Analysis:

    P j RP j R

  • 8/3/2019 Decision Modelling & Feasibility Study

    79/119

    Project RevenueProject Revenue

    Financial Cost Benefit Analysis:

    Column (C)

    This column represents the total

    generated energy (GWh) from thepower plant over the project lifetime.

    P j t RP j t R

  • 8/3/2019 Decision Modelling & Feasibility Study

    80/119

    Project RevenueProject Revenue

    Financial Cost Benefit Analysis:

    Column (D)

    This column represents the market pricesfor selling the generated energy ($/KWh),which will be used by the company thatowns the power plant over the power plantlifetime.

    P j t RP j t R

  • 8/3/2019 Decision Modelling & Feasibility Study

    81/119

    Project RevenueProject Revenue

    Financial Cost Benefit Analysis:

    Column (D)

    T

    he Market prices for selling the electricalenergy can be chosen according to :

    energy selling agreement of the ministryof electricity

    by making escalation in the base yearselling price of the generating companywhich owns the power plant.

    P j t RP j t R

  • 8/3/2019 Decision Modelling & Feasibility Study

    82/119

    The Market prices for selling the electricalenergy can be chosen according to :

    An energy selling agreement set by thegenerating company which owns thepower plant.

    By making escalation in the base year

    selling price of the generating companywhich owns the power plant withasuitable escalation rate.

    Project RevenueProject Revenue

    Financial Cost Benefit Analysis:

    P j t RP j t R

  • 8/3/2019 Decision Modelling & Feasibility Study

    83/119

    Project RevenueProject Revenue

    Financial Cost Benefit Analysis:

    Column (E)

    This column represents the total

    revenue from the combined cyclepower plant (million $) which can becalculated by,

    The total revenue (million $)

    = Energy Generated (KWh)*average system price ($/Kwh)

    P j t RP j t R

  • 8/3/2019 Decision Modelling & Feasibility Study

    84/119

    Project RevenueProject Revenue

    Economical Cost Benefit Analysis:

    The economical cost benefit analysis uses the samecalculating methodology of the financial cost benefitanalysis, except that the selling prices is taken as: or the

    Long run marginal cost of electrical energy

    Export selling prices

    The willingness to pay prices:

    The Long run marginal cost of electricalenergy

    T

    he maximum amount of money a person would be willingto pay, in order to receive the required electrical energy.

    I t t tI t t t

  • 8/3/2019 Decision Modelling & Feasibility Study

    85/119

    Income statementIncome statement

    Income statement (also referred to as profit and loss

    statement P&L), It indicates how

    money received

    from the sale ofthe electrical

    energy

    the revenues

    money spent to

    generateelectrical energy

    the costs

    transformed into

    the result afterexpenses havebeen deductedfrom revenues

    The net income

    Income statementIncome statement

  • 8/3/2019 Decision Modelling & Feasibility Study

    86/119

    Financial Cost Benefit Analysis:

    Income statementIncome statement

    Income statementIncome statement

  • 8/3/2019 Decision Modelling & Feasibility Study

    87/119

    Financial Cost Benefit Analysis:

    Income statementIncome statement

    Column (C)

    This column represents the revenues (million

    $) from selling the energy generated fromthe combined cycle power plant.

    Column (D)

    This column represents total O&M costs(million $).

    Income statementIncome statement

  • 8/3/2019 Decision Modelling & Feasibility Study

    88/119

    Financial Cost Benefit Analysis:

    Income statementIncome statement

    Column (E)

    This column represents total Fuel costs

    (million $).

    Column (F)

    This column represents the depreciation

    (million $) of the combined cycle powerplant.

    Income statementIncome statement

  • 8/3/2019 Decision Modelling & Feasibility Study

    89/119

    Financial Cost Benefit Analysis:

    Income statementIncome statement

    Depreciation in the cost benefit analysis isconsidered as the allocation of the cost ofassets to the period in which the assets are

    used.

    Depreciation value of a fixed asset over theasset life time

    =[T

    otal capital cost of the fixed asset (million $)/ asset life time (years)]

    Income statementIncome statement

  • 8/3/2019 Decision Modelling & Feasibility Study

    90/119

    Financial Cost Benefit Analysis:

    Income statementIncome statement

    The combined cycle power plant, consists of 2 gasturbines and one steam turbine, where the 2 gasturbines are replaced after 25 years from the year

    of commissioning of the power plant, so thedepreciation can be calculated as,

    For the first 25 years:

    [CCGT capital cost (million $) with (IDC) gasturbines capital cost (million $) / 40] + [gasturbines capital cost (million $) / 25]

    Income statementIncome statement

  • 8/3/2019 Decision Modelling & Feasibility Study

    91/119

    Financial Cost Benefit Analysis:

    Income statementIncome statement

    For the last 15 years:

    [CCGT capital cost (million $) with (IDC)

    gas turbines capital cost (million $) / 40] + [gasturbines capital cost (million $) / 15]

    With taking into consideration that the gasturbines capital cost used for the last 15years is the escalated value of the gasturbines for 25 years from the base year.

    Income statementIncome statement

  • 8/3/2019 Decision Modelling & Feasibility Study

    92/119

    Financial Cost Benefit Analysis:

    Income statementIncome statement

    Column (G)

    This column represents the taxable income

    (million $) over the project life time.Definition: It is the amount of income that is usedto calculate the power plant income tax due.

    Taxable income (million $)

    = Revenues O&M costs Fuel costs Depreciation

    Taxable income is adjusted calculated after

    adjustment by deducting all costs from the powerplant revenue.

    Income statementIncome statement

  • 8/3/2019 Decision Modelling & Feasibility Study

    93/119

    Financial Cost Benefit Analysis:

    Income statementIncome statement

    Depreciation is assumed to be represented in the cash flowanalysis according to the concept of allocation of the cost ofassets to periods in which the assets are used

    The annual depreciation values will be treated as an annualrequired amount of money deducted from the revenues overthe power plant lifetime to allocate adequate amount ofmoney equal to the capital cost of the power plant at the endof the power plant lifetime.

    It means that

    Income statementIncome statement

  • 8/3/2019 Decision Modelling & Feasibility Study

    94/119

    Financial Cost Benefit Analysis:

    Income statementIncome statement

    According to the following reasons

    the taxes is applied to the income after adjusting costs from

    revenues.

    depreciation as the previous concept can not be treated asa pure revenue.

    So,

    The depreciation is deducted from the revenues tocalculate the taxable income.

    Income statementIncome statement

  • 8/3/2019 Decision Modelling & Feasibility Study

    95/119

    Financial Cost Benefit Analysis:

    Income statementIncome statement

    Column (H)

    This column represents the amount of taxes

    required from the combined cycle powerplant for each year over the project life time.

    Taxes (million $)

    =Taxable income (million $) * tax rate (%)

    Tax rate has been assumed to be (20%).

    Income statementIncome statement

  • 8/3/2019 Decision Modelling & Feasibility Study

    96/119

    Financial Cost Benefit Analysis:

    Income statementIncome statement

    Column (I)

    This column represents the net income from

    the power plant for each year over theproject life time which can be calculated by,

    Net Income (million $)

    = Taxable Income Taxes

    Income statementIncome statement

  • 8/3/2019 Decision Modelling & Feasibility Study

    97/119

    Economical Cost Benefit Analysis:

    Income statementIncome statement

    Income statementIncome statement

  • 8/3/2019 Decision Modelling & Feasibility Study

    98/119

    Economical Cost Benefit Analysis:

    Income statementIncome statement

    the economical cost benefit analysis is done from thecountry point of view, so the taxes is considered as asharing of resources and are not applied to the revenues

    from selling the generated electrical energy from the powerplant.

    Then, there is no requirement in the economical analysis tocalculate the annual values of depreciation or deduct it

    annually from the revenues to estimate the taxable income,where the net income is calculated directly by,

    Net Income (million$)

    = Revenues O&M expenses Fuel expenses

    Internal rate of returnInternal rate of return

  • 8/3/2019 Decision Modelling & Feasibility Study

    99/119

    Internal rate of returnInternal rate of return

    T

    he last sheet of the project includes the calculation of theNet Present Value (NPV) and the internal rate of return(IRR) of the net profit.

    It is the discount rate which makes the net present valueof all cash flows (both positive and negative) from aparticular investment equal to zero.

    Definition of (IRR)

    So,

    This part will represent all negative cash flow (costs)and positive cash flow (revenues) to calculate the powerplant (IRR).

    Internal rate of returnInternal rate of return

  • 8/3/2019 Decision Modelling & Feasibility Study

    100/119

    Internal rate of returnInternal rate of return

    Financial Cost Benefit Analysis:

    Internal rate of returnInternal rate of return

  • 8/3/2019 Decision Modelling & Feasibility Study

    101/119

    Internal rate of returnInternal rate of return

    Financial Cost Benefit Analysis:

    This column represents the years of constructionand the years of operation of the power plant.

    Column (B)

    Internal rate of returnInternal rate of return

  • 8/3/2019 Decision Modelling & Feasibility Study

    102/119

    Internal rate of returnInternal rate of return

    Financial Cost Benefit Analysis:

    Column (C)

    This column represents the payments of

    capital costs during the constructionperiod (assumed to be 5 years) of thepower plant.

    This column represents also the cost of

    rehabilitation of the 2 gas turbine after 25years from the commissioning date of theproject.

    Internal rate of returnInternal rate of return

  • 8/3/2019 Decision Modelling & Feasibility Study

    103/119

    Internal rate of returnInternal rate of return

    Financial Cost Benefit Analysis:

    Column (D)

    This column represents the annualdepreciation values over the project lifetime, which calculated by the same wayused in the Income statement.

    Column (E)

    This column represents the net incomefrom the power plant which calculated inthe income statement after applying thetaxes to the taxable income.

    Internal rate of returnInternal rate of return

  • 8/3/2019 Decision Modelling & Feasibility Study

    104/119

    Internal rate of returnInternal rate of return

    Financial Cost Benefit Analysis:

    Column (F)

    This column represents the net profitover the power plant life time.

    Net profit

    =Net income + Depreciation Capital cost

    The

    IRR is calculated for the net profitof the power plant.

    Internal rate of returnInternal rate of return

  • 8/3/2019 Decision Modelling & Feasibility Study

    105/119

    Internal rate of returnInternal rate of return

    Economical Cost Benefit Analysis:

    The economical cost benefit analysis uses the samemethodology of calculation that used in the financial costsbenefit analysis except that in the economical cost benefit

    the annual depreciation is not calculated so the Net profit iscalculated by,

    Net profit

    =Net income Capital cost

    Dept ServiceDept Service

  • 8/3/2019 Decision Modelling & Feasibility Study

    106/119

    Dept ServiceDept Service

    It is the amount of money required to be paid ona loan in the form of principal & interestrepayments over a period of time.

    principal repaymentsInterest expenses

    Interests Duringconstruction

  • 8/3/2019 Decision Modelling & Feasibility Study

    107/119

    Dept ServiceDept Service

  • 8/3/2019 Decision Modelling & Feasibility Study

    108/119

    Interest During Construction:

    It is the interests that accumulate during the constructionperiod on a loan that finances the construction process of abuilding or a project

    pp

    Example:

    Let us assume a company needs to begin a new projectrequires (1500 million $) total capital cost.

    The company will finance that project by taking a long

    term loan from a specific Bank as installments throughoutthe construction period of the project (4 years)

    Dept ServiceDept Service

  • 8/3/2019 Decision Modelling & Feasibility Study

    109/119

    pp

    Payments & interest rate

    Installments Interest rate

    Year (1) 150 2.1%

    Year (2) 400 3%

    Year (3) 500 4.5%

    Year (4) 450 1.5%

    The Interest during Construction (IDC)= (150 * 2.1%) + (400 * 3%) + (500 * 4.5%) + (450 * 1.5%)= 3.15 + 12 + 22.5 + 6.75= 44.4 million $

    Dept ServiceDept Service

  • 8/3/2019 Decision Modelling & Feasibility Study

    110/119

    Financial Cost Benefit Analysis:

    Representation of Dept Service in the financial cost-benefitanalysis changes according to 3 Cases

    Case 1 Case 2 Case 3

    Un LeverageIRR Leverage

    IRR Capitalization of

    IDC

    pp

  • 8/3/2019 Decision Modelling & Feasibility Study

    111/119

    Dept ServiceDept Service

  • 8/3/2019 Decision Modelling & Feasibility Study

    112/119

    Financial Cost Benefit Analysis:

    (Case 2: leveraged IRR)

    It is calculated, When the financing decisions are madeand it is decided to fund the project with some leverage(loans).

    For this type ofIRR the cash flow stream reflects the

    actual Capital Structure with all Dept Service components(principle repayments, interest expenses & interestsduring construction)

    pp

  • 8/3/2019 Decision Modelling & Feasibility Study

    113/119

    Dept ServiceDept Service

  • 8/3/2019 Decision Modelling & Feasibility Study

    114/119

    Financial Cost Benefit Analysis:

    (Case 3: Capitalization ofIDC)

    pp

    In this case the interests during construction (IDC) is

    assumed to be added to the capital cost directly.

    The

    IDC is a cost for the project; which is calculated onlyfor the years of construction until the project begins to

    generate revenue, and be able to service its debts.

    Dept ServiceDept Service

  • 8/3/2019 Decision Modelling & Feasibility Study

    115/119

    Economical Cost Benefit Analysis:

    In the economical cost benefit analysis the capital costs of theproject is considered to be provided as a loan from thecountry it self.

    So even if that loan required dept services (interestrepayments, principle repayments or interests duringconstruction) it is not included in the economic analysis

    This loan does not represent a use of resources like (fuelconsumption costs) but only a transfer of resources from thepayer to the payee (money inside the country).

    Dept ServiceDept Service

  • 8/3/2019 Decision Modelling & Feasibility Study

    116/119

    It is the minimum return that a company must earnon an existing project to satisfy its creditors, owners,

    and other providers of capital.

    Weighted Average Cost of Capital (WACC)

    Example: Let assume a capital cost of a project equals to(1500 Million $), which will be financed by a

    group of loans from different banks.

    Bank Name Loan (Million $)Bank (1) 400

    Bank (2) 600

    Bank (3) 500

    Dept ServiceDept Service

  • 8/3/2019 Decision Modelling & Feasibility Study

    117/119

    Bank Name Loan (Million $)

    Bank (1) 400

    Bank (2) 600

    Bank (3) 500

    Weighted Average Cost of Capital (WACC)

    Bank NameShare of loan from

    the capital cost

    Bank (1) 26.6 %

    Bank(2) 40 %

    Bank(3) 33.4 %Share of the loan ofBank from the total

    capital cost

    =[Loan ofBank

    / Total Capital Cost] Share of the loan of [Bank 1 (400 M$)]from [the total capital cost (1500 M$)]

    = [400 / 1500]

    =26.6 %

    Dept ServiceDept Service

  • 8/3/2019 Decision Modelling & Feasibility Study

    118/119

    Weighted Average Cost of Capital (WACC)

    Bank NameShare of loan from

    the capital cost

    Bank (1) 26.6 %

    Bank(2) 40 %Bank(3) 33.4 %

    Bank Name Interest

    Bank (1) 3%

    Bank(2) 5%

    Bank(3) 4%

    WACC = [Share of bank (1) * Interest of bank (1)] +

    [Share of bank (2) * Interest of bank (2)] +

    [Share of bank (2) * Interest of bank (2)]

    WACC = [26.6 % * 3 %] + [40 % * 5 %] + [33.4 % + 4 %]

    WACC = 4.1 %

    Discount RateDiscount Rate

  • 8/3/2019 Decision Modelling & Feasibility Study

    119/119

    Financial Cost Benefit Analysis:

    From the financial point of view the weightedaverage cost of capital (WACC) is the appropriate

    discount rate that can be used in discounting thecash flow of the project.

    Economical Cost Benefit Analysis:

    In the economical cost-benefit analysis a realdiscount rate is used for the cash flow.