del rey project in las cruces

6
DEL REY BLVD/ SANDHILL DEL REY BLVD/ SANDHILL ARROYO CROSSING ARROYO CROSSING Bid Award Bid Award City of Las Cruces City of Las Cruces Project No. 09-10-429 Project No. 09-10-429

Upload: scott-krahling

Post on 08-Jul-2015

374 views

Category:

News & Politics


1 download

DESCRIPTION

The AARA funded Del Rey improvements make the Del Rey community safer from floods.

TRANSCRIPT

Page 1: Del Rey Project in Las Cruces

DEL REY BLVD/ SANDHILLDEL REY BLVD/ SANDHILLARROYO CROSSINGARROYO CROSSING

Bid AwardBid Award

City of Las CrucesCity of Las CrucesProject No. 09-10-429Project No. 09-10-429

Page 2: Del Rey Project in Las Cruces

• The City received $2,000,000 in funding from the NMDOTas a result of the American Recovery and Reinvestment Act(ARRA) of 2009 and Statewide Transportation ImprovementProgram (STIP) to construct road improvements on Del ReyBlvd from Starburst Ridge to Settlers Pass.

• The Del Rey Blvd / Sandhill Arroyo Crossing project willinclude the following:– Widen the existing two lane section to a four lane section– Provide sidewalks and bike lanes– Install street lighting– Improve the roadway surface– Upgrade the existing city utilities with in the project limits– Install 15- 5’x10 concrete box culverts across the Sandhill Arroyo

BackgroundBackground

Page 3: Del Rey Project in Las Cruces

DEL REY BLVD. / SANDHILL ARROYO CROSSINGN

EW

S

SANDHILL ARROYO

Page 4: Del Rey Project in Las Cruces

DEL REY BLVD. TYPICAL STREET CROSS SECTION

Page 5: Del Rey Project in Las Cruces

BackgroundBackground

•• Bids Received: 8Bids Received: 8

•• Engineers Base Bid + Add Alt. . . . . . .Engineers Base Bid + Add Alt. . . . . . . $2,596,167.50$2,596,167.50

•• Low Bid Base + Add Alt. . . . . . . . . . . Low Bid Base + Add Alt. . . . . . . . . . . $2,080,859.30$2,080,859.30–– Burn Construction, Inc.Burn Construction, Inc.–– 19.84% Below Engineers Estimate19.84% Below Engineers Estimate

•• Funding Source: ARRA, Flood Control and Utility FundsFunding Source: ARRA, Flood Control and Utility Funds

•• Contract Duration: 180 Working Days.Contract Duration: 180 Working Days.

Page 6: Del Rey Project in Las Cruces

Council OptionsCouncil OptionsDel Rey Blvd / Sandhill Arroyo Crossing ProjectDel Rey Blvd / Sandhill Arroyo Crossing Project

• Option 1– Award contract to Burn Construction Company, Inc.– $2,080,859.30– $2,352,325.39 w/ Tax & Contingency

• Option 2– Reject and Re bid the project

• Option 3– Reject and Re scope the project

• Option 4– Reject and Abandon the project for a later date