delivering a breakthrough rail project by bill henry

19
Reading Station Area Redevelopment Reading Station Area Redevelopment 51°28’90”N 51°28’90”N | 00°59’15”E 00°59’15”E APM APM Conference Conference Bill Henry Bill Henry CIVIL GOVERNMENT SERVICES MINING & METALS OIL, GAS & CHEMICALS POWER

Upload: association-for-project-management

Post on 26-Jan-2015

104 views

Category:

Business


0 download

DESCRIPTION

Presentation led by Bill Henry from Bechtel at the APM Conference 2013

TRANSCRIPT

Page 1: Delivering a breakthrough rail project by Bill Henry

Reading Station Area RedevelopmentReading Station Area Redevelopment

51°28’90”N 51°28’90”N || 00°59’15”E 00°59’15”E

APM ConferenceAPM ConferenceBill HenryBill Henry

CIVIL GOVERNMENT SERVICESMINING & METALSOIL, GAS & CHEMICALS POWER

Page 2: Delivering a breakthrough rail project by Bill Henry

Layout Dated 1899

The Problem – Old Layout

2

Page 3: Delivering a breakthrough rail project by Bill Henry

The Solution

New Depot (relocation of turbo

depot & IEP)

New track & signalling layout

New eastern chord and grade separation

Western Gateline

New elevated railway and grade separation

New northern entrance

New passenger overbridge

Four new northern platforms

Southern tunnel

reopened

Additional southern platform & lengthening

Public Realm Works

3

Page 4: Delivering a breakthrough rail project by Bill Henry

The Outputs - Trains

Increase of 4 trains per hour on mainline

Additional freight capacity

Significant Performance Improvement

Significant Performance Improvement

4

Page 5: Delivering a breakthrough rail project by Bill Henry

Station futureproofed100% capacity growth forecast by 2030

The Outputs - Station

5

Page 6: Delivering a breakthrough rail project by Bill Henry

How it All Fits Together

6

Page 7: Delivering a breakthrough rail project by Bill Henry

Baseline 2009 Timeline of Work

2009

2010

2011

2012

2013

2014

2015

2016

December 2010

Key Output 0Enabling Works

Complete,TVSC operational

May 2013

Key Output 1Improved Station

Capacity

February 2014

Key Output 2New Depot Operational

July 2015

Key Output 3Main Lines

Grade Separation

April 2016

Key Output 4West Country

Grade Separation

7

Page 8: Delivering a breakthrough rail project by Bill Henry

1. More collaborative

2. More efficient in terms of schedule

3. More efficient financially

The 2011 McNulty Report pushed delivery organisations to be:

The Challenge

Our Goal: Demonstrate collaboration

Our Goal: Knock 18 months off

Our Goal: Generate £50m savings

8

Page 9: Delivering a breakthrough rail project by Bill Henry

Key Success Factors to date: Leadership Framework

9

Project DirectorBill Henry

Senior Programme Manager - Stations

Graham Denny

Senior Programme Manager - Depot

Steve Green

Senior Programme Manager - Signalling

Jason Lacey

Senior Programme Manager - TrackJonathan Davies

Deputy Project Director & Senior

SponsorJim Weeden

Senior Programme Commercial

ManagerJohn Spencer

Principal Programme

Controls ManagerRichard Moore

Principal Construction

ManagerSteve Plyler

Personal AssistantSinead Foley

Senior Programme Manager -

EngineeringBen Venables

Head of HSEASteve Womack

Senior Programme Manager - Civils

Kevin Brown

Page 10: Delivering a breakthrough rail project by Bill Henry

Key Success Factors to date: Achievable Plan

10

Page 11: Delivering a breakthrough rail project by Bill Henry

Key Success Factors to date: Beyond Traditional Collaboration

11

Page 12: Delivering a breakthrough rail project by Bill Henry

12

Key Success Factors to date: Value Engineering/Management

Carbon reduction of 15,000 equivalent tonnesSaving = £12M

Page 13: Delivering a breakthrough rail project by Bill Henry

Key Success Factors to date: Quantity Tracking: Earned Value

13

Page 14: Delivering a breakthrough rail project by Bill Henry

14

Key Success Factors to date: Delivery with Safety and Quality

Page 15: Delivering a breakthrough rail project by Bill Henry

15

Key Success Factors to date: Performance Management

Page 16: Delivering a breakthrough rail project by Bill Henry

May 2013

Key Output 1Improved Station

Capacity

Xmas 2014

Key Output 3Main Lines

Grade Separation

The Breakthrough Timeline

2010

2011

2012

2013

2014

2015

2016

December 2010

Key Output 0Enabling Works

Complete,TVSC operational

November 2013

Key Output 2New Depot Operational

April 2015

Key Output 4West Country

Grade Separation

Revised project programme

Combining stages of work: better efficiency

2015 completion (one year earlier than planned)

Fewer periods of engineering works, meaning less impact on your journeys

December 2009

GRIP 3 Sign off'We know our scope'

January 2011

GRIP 4 Sign off'We know what we are building'

December 2011

GRIP 5 Sign off'We have a design

for construction'

16

Page 17: Delivering a breakthrough rail project by Bill Henry

1. More collaborative

Our Goal: Demonstrate collaboration

2. More efficient in terms of schedule

Our Goal: Knock 18 months off

3. More efficient financially

Our Goal: Generate £50m savings

The 2011 McNulty Report pushed delivery organisations to be:

The Challenge

New BS11000 standard achieved

Significant savings to date!

12 months knocked off the schedule so far...

17

Page 18: Delivering a breakthrough rail project by Bill Henry

10/04/23

Transforming the Reading Area

20092013

18

Page 19: Delivering a breakthrough rail project by Bill Henry

19