delivering viable project
DESCRIPTION
Project DevelopmentTRANSCRIPT
Panel Session: Delivering a Viable Anaerobic Digestion Project
Session Panelists
Dan Rathbun Business Development Manager
SEH Food and Beverage
Industry
Nick Rosenberry Business Development Manager
Harris Companies – Industrial
Group
Nick Brancale Pre-Construction Manager
Adolfson & Peterson – Energy
Group
Introduction of Firms
SEH - Our Company
Short Elliott Hendrickson Inc. (SEH®) is an employee-
owned company of engineers, architects, planners, and
scientists serving public and private sector clients.
• In business since 1927
• Experience with designing, constructing, and
commissioning digesters for over 50 years
• Food and Beverage focus on solutions to reduce,
eliminate, or re-use waste streams
Steve, I feel this should have similar text to the website. The format in which info is listed should be consistent w/Harris &AP—sldies 6 & 4
SEH Sample Projects Photos: Update images below w/what I’ve placed in your transfer folder Rice Street Owatonna WWTF aerial (ideally the photo that is in the hallway by the receptionist). If we can’t locate that one the photo to the right will work. CF new office
Owatonna WWTP
A. Wastewater Treatment Plant Owatonna, Minn.
B. TH 36/Rice Street Interchange Ramsey County, Minn
C. SEH office opening June 2014 Chippewa Falls, Wisc.
A. B.
C.
Harris Mechanical - Our Company
Harris Mechanical is a full service mechanical contractor
and EPC firm founded in 1948.
• National presence
• Strong industrial and
process resume
• Safety focused
• Financial Strength
Steve, I feel this should have similar text to the website. The format in which info is listed should be consistent w/Harris &AP—sldies 6 & 4
Harris Mechanical Sample Projects
Otter Tail Ag Ethanol Plant
MET Council Environmental Services
A. Gopher Resources Tampa Bay, FL
B. Otter Tail Ag Ethanol Plant Fergus Falls, MN
C. MET Council Environmental St. Paul, MN
B.
C. A.
Adolfson & Peterson Construction
A&P is national general contractor and EPC firm with
headquarters in Minneapolis, MN and seven regional
offices.
• Founded in 1946
• EPC Contractor
• Anaerobic Digestion
• Pyrolysis
• Gasification
• Solar
• Strong Financial Position
A. New Belgium Brewery Asheville, N.C.
B. Blue Lake Anaerobic Digestion Wastewater Treatment Plant, Shakopee, Minn.
C. EnergyWorks GENRF ELM Gasification
Facility, Gettysburg, Penn.
A. B.
C.
A&P Sample Projects
Project Lifecycle | Selecting Your Team | Project Delivery Method
Setting the Stage
Project Lifecycle
Project Initiation:
Project Initiation
Business Case
Definition Feasibility
Project Design
Project Construction
Project Start Up 1. Identify project conceptual
description, drivers, and
goals.
2. Identify project team,
technology providers, and
potential partners.
3. Perform Fatal Flaws
Analysis.
Business Case
Definition
Feasibility ProjectDesign
ProjectConstruction
ProjectStart Up
Project
Initiation
Business Case Definition:
Project Initiation
Business Case
Definition Feasibility
Project Design
Project Construction
Project Start Up
1. Engage EPC and technology
provider team
2. Identify potential sites, feed
stocks and off takes
3. Develop project pro forma
4. Create project schedule
5. Research potential funding
sources
Business Case
Definition
Project
InitiationFeasibility Project
DesignProject
Construction
ProjectStart Up
BusinessCase
Definition
Feasibility:
Project Initiation
Business Case
Definition Feasibility
Project Design
Project Construction
Project Start Up
1. Develop preliminary general arrangement drawings
(GA) and conceptual basis of design
2. Refine Cost Estimates
3. Refine pro forma
4. Perform site assessments
5. Perform feed stock analysis
Business Case
Definition
Project
Initiation
ProjectDesign
ProjectConstruction
ProjectStart UpFeasibility
Project Initiation
Business Case
Definition Feasibility
Project Design
Project Construction
Project Start Up
1. Develop detail design to establish guaranteed
maximum price (GMP)
2. Complete project responsibility matrix
3. Finalize construction schedule
4. Begin detailed permitting
5. Execute EPC contract Insert Respons. matrix
Project Design:
Business Case
Definition
Project
InitiationFeasibility Project
Construction
ProjectStart Up
Project Design
Project Initiation
Business Case
Definition Feasibility
Project Design
Project Construction
Project Start Up
1. Procure equipment and contract with
key vendors and subcontractors
2. Finalize project design for design
build methodology
3. Value engineer throughout
construction process
4. Achieve substantial completion
Insert digester pics – A-P Blue Lake Project pics
Project Construction:
Business Case
Definition
Project
InitiationFeasibility Project
Design
ProjectStart Up
Project Construction
Project Initiation
Business Case
Definition Feasibility
Project Design
Project Construction
Project Start Up
1. Training of operations staff
2. Commission each system of the facility.
3. Begin system loading / ramp-up.
4. Performance testing.
5. Begin full operations.
Generator Picture and startup training sample testing lab picture Training SOP manual
Keep Solids Sep image Include: green digester that appears on old F&B banner Wstwtr testing lab Training SOP manual (perhaps a generic 3-ring binder w/the word training on it?
Project Start Up:
Business Case
Definition
Project
InitiationFeasibility Project
DesignProject
Construction
Project Start Up
Things to Consider When Selecting the Team
Technology & Equipment Providers
• Track Record
– Based on your feed stocks and off takes
• Warranty / Performance Guarantee
– Strength to financially back
• Ability to Pilot Test
Engineering, Procurement &
Construction (EPC) Team
• Experience / Resume
• Financial Strength
– E&O insurance
– Bonding Capability
– Mechanical Guarantee
• Safety Record – EMR/MOD rating
• Familiarity with Geographic Region
Feedstock & Off-take Partners
• Financial strength
• Contract length
• Guarantee quality, consistency, and
volume
• Impact of regulatory drivers on project
inputs and outputs