demolition of the former dartmouth refinery · • project timeline • q4 2015- q4 2017 • site...
TRANSCRIPT
![Page 1: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/1.jpg)
Demolition of the Former Dartmouth Refinery
RemTech 2017
Ramy Rahbani - Imperial
Chris Ptak- Tervita
![Page 2: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/2.jpg)
Agenda
• Background
• Project Overview
• High Level Approach
• Demolition Summary
• Challenging Scope
• Lessons Learned
• Project Closure
• Questions2
![Page 3: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/3.jpg)
Background
![Page 4: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/4.jpg)
• Extensive global experience
• Imperial/ExxonMobil Global Demolition Centre ofExcellence
• Imperial and ExxonMobilhave executed manydemolition projects throughout the world
• Canada
• United States
• Australia
• Germany
• Italy
• France
Who we are – Imperial
4
![Page 5: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/5.jpg)
• Tervita Environmental Services is an industry leader in Remediation, Demolition and Environmental Construction Services leveraging the largest waste management infrastructure in Canada to service oil and gas, industrial and government clients.
• Major Demolition Projects Include
• Mildred Lake Mine Replacement
• Giant Mine Roaster Decontamination and Dismantlement
• Kitimat Industrial Facility
Who we are – Tervita
5
![Page 6: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/6.jpg)
Site Background
• Refinery overview• Located in Dartmouth, NS
• Start of operations - 1918
• Refinery shut down - 2013
• Refining capacity – 88 KBD
• Property area – ~700 acres
• Marine Terminal operated by Canadian Fuels Operations (CFO)
• Surplus areas transferred to ES in Q4 2014
• Neighbors/surrounding land use
• Water bodies: marine and freshwater
• Residential: 210 houses within 100 m
• Commercial/Industrial
• Superior Propane, CN Rail
• Shearwater – military base and airstrip
![Page 7: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/7.jpg)
Project Overview
![Page 8: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/8.jpg)
Project Scope
8
![Page 9: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/9.jpg)
Project Scope
9
![Page 10: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/10.jpg)
“Nobody gets hurt”
• Minimize disruptionto the surrounding community
• Regulatorycompliance
• Timely execution of project scope
Project Objectives
10
• Project Safety Credos• “Machine before
human”• “Own your zone”• “Clarify, Simplify, Focus”• “It’s not mean to
intervene”
![Page 11: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/11.jpg)
• Project Timeline • Q4 2015- Q4 2017
• Site is divided into :• 8 areas (Block 1 to 8)
• ~ 85 sub-areas
• ~37,000 metric tons of steel
• ~18,000 m3 of residual hazardous and non hazardous material
• Extensive asbestos abatement
• 73 tanks (spherical, concrete, steel, etc.) Surplus Area
Scope of Work Highlights
![Page 12: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/12.jpg)
High Level Approach
![Page 13: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/13.jpg)
13
Where…How…do you begin?
![Page 14: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/14.jpg)
14
Site Division, Block Definition
![Page 15: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/15.jpg)
15
3 phase approach: Verification and Validation, Asbestos Abatement, Demolition
High Level Approach
Verification of zeros
Asbestos Abatemen
t
Demolition of
structures
V&V TeamAbatemen
t TeamDemolitio
n Team
![Page 16: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/16.jpg)
Demolition Summary
![Page 17: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/17.jpg)
Sept 2015Contract awarded to Tervita
Sept-Nov 2015Pre-planning activities
Nov 2015 Mobilization and start of demolition activities
Nov 2015 - PresentProgressive demolition ofin-scope areas and debris removal
Dec 2017Demolition completion and demobilization
High Level Timeline
17
![Page 18: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/18.jpg)
• Workforce consists of 70-80 workers
• 80% of the workforce is local
• Workforce consists of five major contracting organizations
• Extensive safety planning, documentation, and engagement
A day on-site…
18
![Page 19: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/19.jpg)
• Up to 15 excavators/skid steers/rock trucks
• Up to 3-5 vacuum trucks
• Water trucks and other dust suppression activities executed daily
• Specialty demolition excavator attachments
• Extensive controls that restrict access to
Heavy Machinery
19
![Page 20: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/20.jpg)
20
• Work Hours: ~300,000 LTD
• 80-90 people on-site daily at peak
• Zero recordable spills/regulatory violations
• Strong focus on machine/human interface (HEEZ/ADZ), zone control, hand protection and JSAs
• 74 Work Execution Plans
• 65 JSAs
Safety Summary
![Page 21: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/21.jpg)
21
• Cleaning and removal of > 70 Tanks Higher complexity
Steel EFR, Spherical, and concrete tanks
• Successful execution of 72 controlled drops
• ~37,000T of steel processed and shipped
~400 railcars
• ~ 18,000m3 of liquid waste disposed
• ~23,000T of construction debris
• ~1,500T of asbestos abated
Milestones Achieved
Preparation of Steel –Processing
Critical Lift – Stack Removal
![Page 22: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/22.jpg)
Challenging Scope
![Page 23: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/23.jpg)
23
• All types IFRs, EFRs, Hard shell
Spherical Tanks
Concrete Tanks
• All sizes and contents 10,000 to 900,000 bbl
Diameters of 5 – 250 feet
Contained crude, sludge, refined
• Different methodologies: Shearing
Torching
Tanks…73 Removed
![Page 24: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/24.jpg)
24
Tanks 453-454
• 250’ D, 54’ H, ~472,000 bbl
• 2 identical tanks
• Collapsed roof
• Sludge and water
• Methodology
Pump water/sludge mixture out
Pressure water cut door
Drive excavator in, shear roof
Collect remaining sludge
Clean tank
Torch walls
![Page 25: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/25.jpg)
25
Concrete Tanks
![Page 26: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/26.jpg)
26
Brick Stack
• 150 feet, structurally compromised
• Methodologies considered Engineered drop via blasting
Top down mechanical via cricket unit
Top down mechanical via crane
Ultra-high reach excavator
Engineered drop via cable pull
![Page 27: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/27.jpg)
27
• 72 drops: towers, furnaces, stacks
• Height Range: 36 – 200 feet
• Different methodologies: Torching of base structure
Push or pull
Guide wire cutting
• Engineering of drop plans • Protect 3rd parties and live equipment
Drops…72
![Page 28: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/28.jpg)
28
Process Plant
• Extensive network of vessels and piping
• Major focus of V&V program
• Multiple Engineered Drops
![Page 29: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/29.jpg)
29
Process Plant Demolition
![Page 30: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/30.jpg)
30
Engineered Drops – D202
![Page 31: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/31.jpg)
31
Engineered Drops – T102
![Page 32: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/32.jpg)
Processing Steel
32
![Page 33: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/33.jpg)
Lessons Learned
![Page 34: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/34.jpg)
34
Lessons Learned• Regulatory approval received <1 month before execution Ensure all regulatory approvals and demolition permits are
received ahead of time to avoid potential delays and large financial implications
• Major ACM equipment vulnerable to deteriorate Abate deteriorating ACM during decommissioning stages
• Many different color systems between business units Have a color code system for the different states of remaining
surplus equipment. Implement within site orientation.
• Third party expert consultant conducting QA/QC confirming abatement completion allowed for a transparent removal and straightforward process
Have the consultant who conducted the HAZMAT assessment on-site for QA/QC purposes Full circle
• Lesson Recommendatio
n
![Page 35: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/35.jpg)
35
Lessons Learned
• Leaks can occur from improperly decommissioned lines Identify every line, cross reference P&IDs, drill all low points,
and use a level when uncertain. Implement spill mitigation control measures
• Residual product easier to pump out during warmer weather Recover product during summer months to reduce waste
removal costs in both tanks and lines
• ACM suspect materials encountered during demolition were at times treated as ACM and shipped to expedite process
Be prepared to abate during short duration jobs when ACM suspect materials are unexpectedly encountered.
• Successful relationship with community resulted in smooth execution
Ensure to have a pre-established schedule for community meetings, and plans to deal with any inquiries in a timely and effective manner.
• Lesson Recommendatio
n
![Page 36: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/36.jpg)
Project Completion
![Page 37: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/37.jpg)
• Active terminal
• Continued terminaloptimization
• Environmental siteassessmentactivities
• No plans for future development
• Annual communitymeetings
• Continue to play an activerole in the community
Post Demolition
37
![Page 38: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/38.jpg)
Post Demolition
38
![Page 39: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/39.jpg)
39
Process Plant – Before and After
![Page 40: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/40.jpg)
40
Marine Area – Before and After
![Page 41: Demolition of the Former Dartmouth Refinery · • Project Timeline • Q4 2015- Q4 2017 • Site is divided into : • 8 areas (Block 1 to 8) • ~ 85 sub-areas • ~37,000 metric](https://reader033.vdocument.in/reader033/viewer/2022042809/5f9116d1d80c3a4ede1fec53/html5/thumbnails/41.jpg)
41
East Tankfield – Before and After