Departmental Procedure Project Management
DP: PMX (Aligned to Quality Manual and ISO 9001:2008)
This manual is to be returned to Head (PMX) when the individual has no further requirement for it or when he ceases to be an employee of BHEL. Individuals in possession of the Controlled Copies will receive revisions as and when issued.
Issue No. 05
Controlled Copy
Date of Issue: 16.03.2010
Revision No. 00
Issued to:
Effective Date: 16.03.2010
Control Number: DPPM:0001/10
Issued by :
Head/PMX
Bharat Heavy Electricals Limited Power Sector Western Region
Shree Mohini Complex
Nagpur 440001
DEPARTMENTAL PROCEDURE Issue No. : 05
FOR PROJECT MANAGEMENT Rev. No : 00 . Date : 16/03/10 Page : 01 of 01
TABLE OF CONTENTS
S. NO. CHAPTER
IDENTIFICATION DESCRIPTION
NO. OF PAGES
LATEST REV. NO.
EFFECTIVE DATE
01
02
03
DP:PMX
TABLE OF CONTENTS
DEPARTMENTAL
PROCEDURE FOR PMX
SUMMARY OF
REVISIONS
01
17
01
00
00
00
16/03/10
16/03/10
16/03/10
REVIEWED BY APPROVED BY
HEAD (MSX)
HEAD (PMX)
DEPARTMENTAL PROCEDURE FOR Issue No. : 05 Rev. No. : 00
PROJECT MANAGEMENT Date : 16.03.10 Page : 1 of 17 DP: PMX
Reviewed by Approved by Head (MSX) Head (PMX)
BHARAT HEAVY ELECTRICALS LIMITED, POWER SECTOR WESTERN REGION
PS : WR
1.0 SCOPE
This procedure details the processes of the Project Management function , its
organization, responsibilities and activities involved in execution of these
processes to meet requirements of QMS and continually improve its
effectiveness in PSWR.
2.0 PRIMARY DOCUMENTS
2.1 Quality Manual
2.2 Standard Procedures (SP 02,03,06,07,08,09,10,11,12 and 13)
3.0 PROCESS MAPS
The sequence and interaction of processes are shown in process map.
Internal Customers are as indicated in Process map. Their expectations are:
a) Timely availability of inputs and requirements.
b) Completeness of inputs.
4.0 ORGANISATION, RESPONSIBILITY AND DEFINITION OF TERMS USED
The functional organization chart of PMX is enclosed.
4.1 PROJECT CO ORDINATOR - The individual or body with the responsibility
for managing a contracted Project by coordinating project management functions
among Customer, Consultant ,Manufacturing units, engineering centres,
PMG(IO/IS/PS),Marketing and site in the field of Engineering, supplies, Erection,
testing and Commissioning etc in line with CIS and contract documents.
DEPARTMENTAL PROCEDURE FOR Issue No. : 05 Rev. No. : 00
PROJECT MANAGEMENT Date : 16.03.10 Page : 2 of 17 DP: PMX
Reviewed by Approved by Head (MSX) Head (PMX)
BHARAT HEAVY ELECTRICALS LIMITED, POWER SECTOR WESTERN REGION
PS : WR
4.2 ACTIVITY - An operation or a specific action to be completed to aid the fulfillment
of the project as a whole.
5.0 ACTIVITIES
Following activities are performed at PMX.
5.1: Act as the main nodal agency for the region for execution of assigned project and as a communication channel between various concerned agencies.
Receive Contract Information Sheet from Commercial
Head PMX to Nominate Project Coordinator
Receive contract documents from Commercial.
5.2: Preparing Physical and Financial Turn over budget.
Prepare Physical and Financial Turn Over plan for the project for the
current financial year and quarterly for the next financial year in line
with the contractual schedule.
Receive the yearly Budget from ongoing project sites for review and
finalization.
5.3: Monitoring Turnover (Physical & Financial), Billing and Cash collection.
5.4: Monitoring Sub contractors / Vendors progress for corrective action.
5.5: Planning and monitoring of identified inputs for meeting contract Commitments.
Receive approved L-1 schedule from PM
DEPARTMENTAL PROCEDURE FOR Issue No. : 05 Rev. No. : 00
PROJECT MANAGEMENT Date : 16.03.10 Page : 3 of 17 DP: PMX
Reviewed by Approved by Head (MSX) Head (PMX)
BHARAT HEAVY ELECTRICALS LIMITED, POWER SECTOR WESTERN REGION
PS : WR
Prepare L2 schedule for Construction and E & C and submit to PM
for finalization of L-2 Sch.
Receive approved L-2 schedule from PM and forward to site.
Monitor L2 schedule and raise alarm wherever necessary.
Communicate site Opening/Closing.
Finalize packages for sub-contracting, prepare tender specifications,
sub-contracting estimates and place indent on Purchase department.
Finalise Broad billing schedule with customer in association with
commercial / Marketing (Power Sector/ Industry Sector/IO).
5.6 :Site Related coordination
Plan, monitor and control of infrastructure and enabling works
Development and review of installation schedule, identification,
provision & co ordination of major inputs for installation activities at
site.
Planning & providing support services to sites including coordination
within region.
Reviewing site performance with Construction managers and
concerned for corrective action.
5.7: Resolution of customer complaints related to region.
Process customer complaints / Feed back as described in SP08
DEPARTMENTAL PROCEDURE FOR Issue No. : 05 Rev. No. : 00
PROJECT MANAGEMENT Date : 16.03.10 Page : 4 of 17 DP: PMX
Reviewed by Approved by Head (MSX) Head (PMX)
BHARAT HEAVY ELECTRICALS LIMITED, POWER SECTOR WESTERN REGION
PS : WR
5.8: Improvement of Customer Satisfaction
Action planning on perceptions received based on survey for enhancement of customer satisfaction as per SP 13.
5.9: Improvement in cycle time & other areas Critical to Quality (CTQ) 5.10: Facilitating Contract Closing
Expedite liquidation of technical and commercial issues with
Customer pertaining to Region and intimate to Commercial.
6.0 RECEIVE CONTRACT INFORMATION SHEET
Receive Contract Information Sheet (CIS) from commercial in format COM-F07.
7.0 NOMINATION OF PROJECT COORDINATOR
Head (PMX) nominates a Project Coordinator (PC) on receipt of information from
commercial regarding expected contracts and responsibility of Project
Management. and informs -
a. Individual through HOD
b. Commercial Centre (PSCM)
c. Head (Region)
e. All HOF’s
f. Head (IO / Industry Sector / CPMG)
DEPARTMENTAL PROCEDURE FOR Issue No. : 05 Rev. No. : 00
PROJECT MANAGEMENT Date : 16.03.10 Page : 5 of 17 DP: PMX
Reviewed by Approved by Head (MSX) Head (PMX)
BHARAT HEAVY ELECTRICALS LIMITED, POWER SECTOR WESTERN REGION
PS : WR
8.0 RECEIVE CONTRACT DOCUMENTS
PC shall obtain contract documents from Commercial.
9.0 L-2 SCHEDULES
9.1: PC shall prepare L2 schedule for installation and forward to
Project manager.
9.2: PC will obtain consolidated approved L2 schedule from
Project Manager and distribute the same as follows :
i. Construction Manager
ii. HEAD TSX
iii. Head Quality
10.0 PREPARATION OF TENDER SPECIFICATION AND ESTIMATES FOR PLACING INDENT FOR SUBCONTRACTING
10.1: PC to finalise sub contracting packages in consultation with Purchase / TSX/ ISX
for subcontracting purpose.
10.2: PC to collect information and technical details from manufacturing units /
Engineering Centers for preparation of tender specifications.
10.3: PC to prepare tender specification in line with the contract requirements and
furnish the same to Purchase deptt while raising indent.
10.4: PC to prepare detail estimate for the sub packages and get approval from
competent authority.
DEPARTMENTAL PROCEDURE FOR Issue No. : 05 Rev. No. : 00
PROJECT MANAGEMENT Date : 16.03.10 Page : 6 of 17 DP: PMX
Reviewed by Approved by Head (MSX) Head (PMX)
BHARAT HEAVY ELECTRICALS LIMITED, POWER SECTOR WESTERN REGION
PS : WR
11.0 QUALITY PLAN SUBMISSION SCHEDULE 11.0.1: PC shall obtain field quality plan submission schedule from Head (quality) and forward to Customer / Construction / Project Manager. 11.0.2: PC shall monitor the schedule and expedite the approval of Quality plans by Customer/Consultant. 12.0 SUBCONTRACTING 12.1: PC shall identify various subcontracting packages and prepare a
Schedule for award of subcontracts.
12.2: PC shall obtain the tender inputs from various units/engineering centers and
prepare the tender documents.
12.3: PC shall prepare the detailed estimate for respective packages.
12.4: PC shall raise Indents for products and services.
12.5: Technical Bid evaluation for product /services.
12.6 PC shall obtain the list of sub-vendor / Sub- Contractor with credentials from
Purchase for customer approval wherever applicable.
12.7 List of Sub-vendors / Sub-Contractors shall be furnished to Customer for
comments / approval
12.8 PC shall obtain approval from customer and forward to purchase for further
necessary action
DEPARTMENTAL PROCEDURE FOR Issue No. : 05 Rev. No. : 00
PROJECT MANAGEMENT Date : 16.03.10 Page : 7 of 17 DP: PMX
Reviewed by Approved by Head (MSX) Head (PMX)
BHARAT HEAVY ELECTRICALS LIMITED, POWER SECTOR WESTERN REGION
PS : WR
13.0 SITE OPENING / CLOSING 13 1 Project Coordinator shall communicate to the concerned
(Units/Customer etc.) regarding site opening / readiness of site to receive
materials.
13.2 Project Coordinator shall monitor balance work for closing of site.
13.3 Project Coordinator shall communicate to all concerned regarding site
closing.
14 PROGRESS REVIEW AND REPORTING
14.1: Project coordinator shall attend project review meeting with Customer
/ Consultant and concerned units / work centres.
14.2: Review progress with respect to schedules (L1 & L2) and advise the
concerned for corrective action wherever required.
14.3: Project Coordinator shall brief the highlights of the record notes of
meetings to HOD/HOF.
14.4: Head (PMX) or his nominee shall review progress of project with
respect to schedules with PC every month. Head (PMX) shall seek
higher level intervention through Head Region / MCM wherever
required.
14.5: PC shall prepare the list of critical inputs required to achieve planned
turnover / milestone & follow up with the concerned for its timely availability.
DEPARTMENTAL PROCEDURE FOR Issue No. : 05 Rev. No. : 00
PROJECT MANAGEMENT Date : 16.03.10 Page : 8 of 17 DP: PMX
Reviewed by Approved by Head (MSX) Head (PMX)
BHARAT HEAVY ELECTRICALS LIMITED, POWER SECTOR WESTERN REGION
PS : WR
14.6: Head/PMX will communicate the critical issues to PMG for its
liquidation every month through PRE MCM.
14.7: Project Coordinator shall arrange relevant documents required for
execution of work from Engineering Centres/Units.
14.8: Head (PMX) or his nominee shall review the subcontracting
Indent/PO with concerned department and take necessary actions
wherever required.
14.9: Project Coordinator shall monitor progress of enabling
works/Infrastructure facility. Area of concern to be taken up with
concerned dept for corrective action.
14.10: Project Coordinator shall obtain progress report from site and review
with Head PMX on critical issues.
14.11: On receipt of CIS, project coordinator shall give the requirement of
enabling works with other input detail to PMX-Civil for preparation
of tender documents, BOQ, Specification, drawings and
departmental estimate.
14.12: PMX Civil shall prepare all the above details and process a note for
approval of departmental estimate by competent authority.
14.13: On approval of estimate, project coordinator shall place an indent to
Purchase department.
DEPARTMENTAL PROCEDURE FOR Issue No. : 05 Rev. No. : 00
PROJECT MANAGEMENT Date : 16.03.10 Page : 9 of 17 DP: PMX
Reviewed by Approved by Head (MSX) Head (PMX)
BHARAT HEAVY ELECTRICALS LIMITED, POWER SECTOR WESTERN REGION
PS : WR
14.14: Similar procedure shall be followed for main civil packages for EPC
project. In case of EPC Project, BOQ and specification shall be
obtained from engineering division i.e. PEM/PED.
15.0 CUSTOMER COMPLAINT AND FEEDBACK Process customer complaints/feedback as described in SP08.
16.0: CONTRACT CLOSING 16.1: SUB-CONTRACTORS
16.1.1 PC shall co-ordinate with site and other concerned to
liquidate various issues/pending points like balance work, time
extension, Extra item/Additional works, quantity variation, ORC, final
bills etc.
16.1.2: Project coordinator to communicate to concerned for corrective
action.
16..2: CUSTOMER Project Coordinator shall co-ordinate with commercial and site to liquidate
various issues/pending points.
17.0 DOCUMENT CONTROL
Document and data used in the department are controlled as per SP 02.
18.0 PLANNING
18.1: PERFORMANCE PLANNING
18.1.1: Objectives for the function are drawn in line with QM 5 every year.
18.1.2:.Annual individual targets are set, measured and reviewed as per
Performance management system.
DEPARTMENTAL PROCEDURE FOR Issue No. : 05 Rev. No. : 00
PROJECT MANAGEMENT Date : 16.03.10 Page : 10 of 17 DP: PMX
Reviewed by Approved by Head (MSX) Head (PMX)
BHARAT HEAVY ELECTRICALS LIMITED, POWER SECTOR WESTERN REGION
PS : WR
18.2: RESOURCE MANAGEMENT
Resources are deployed so as to improve the effectiveness and enhance
customer satisfaction.
18.3: IDENTIFICATION OF COMPETENCIES
Competencies of individuals are identified as per Performance Management
System.
18.4: IDENTIFICATION OF TRAINING AND DEVELOPMENT NEEDS
18.4.1: Training needs of the department are identified as per SP-11 and
forwarded to HR dept.
18.4.2: On receipt of communication from HR dept, Head (PMX) shall depute
individuals for training programs.
18.4.3: On completion of training evaluation is done by HOF/HOD and sent to
HR dept.
18.5: MEASUREMENT, ANALYSIS AND REVIEW
Monthly review is conducted for the following –
a) Objectives, plan and target
b) Customer complaint feedback
c) Non Conformance Reports/ Audit result
d) Contract closing
e) On going projects
f) Planning
g) Changes in QMS
h) Any other point
DEPARTMENTAL PROCEDURE FOR Issue No. : 05 Rev. No. : 00
PROJECT MANAGEMENT Date : 16.03.10 Page : 11 of 17 DP: PMX
Reviewed by Approved by Head (MSX) Head (PMX)
BHARAT HEAVY ELECTRICALS LIMITED, POWER SECTOR WESTERN REGION
PS : WR
18.6: IMPROVEMENT ACTIVITIES
Improvement areas are identified and reviewed as per SP. 13. Following areas
are given thrust:
18.0.6.1: Customer perception survey
18.0.6.2: Feedback from monthly Review meeting at HQ.
19.0 CONTROL OF NONCONFORMING PRODUCT
For activities performed by deviating from procedure, approval of authority
approving the procedure is taken.
20.0 CORRECTIVE AND PREVENTIVE ACTION
a) Corrective actions on recorded Audit observations shall be as per SP 07.
b) Corrective and preventive actions shall be as per SP06 and SP07
c) Head (PMX) shall initiate preventive measures to avoid recurrence of such non
conformances.
d) Head (PMX) shall communicate to head (Qly) & MR cases which require input
from other units / departments.
e) Head (PMX) / Nominee shall maintain data of all non-conformance and
corrective actions.
21.0 STATUTORY AND REGULATORY REQUIREMENTS
Project Coordinator will coordinate for adherence to statutory and regulatory
requirements at installation sites.
DEPARTMENTAL PROCEDURE FOR Issue No. : 05 Rev. No. : 00
PROJECT MANAGEMENT Date : 16.03.10 Page : 12 of 17 DP: PMX
Reviewed by Approved by Head (MSX) Head (PMX)
BHARAT HEAVY ELECTRICALS LIMITED, POWER SECTOR WESTERN REGION
PS : WR
22.0 RECORDS AND RETENTION PERIOD
SL NO DESCRIPTION OF RECORD RETENTION PERIOD LOCATION
1. Schedule folder Till closure of contract PC
2. Correspondence files Till closure of contract PC
3. Records notes / Minutes of meeting Till closure of contract PC
4. Progress reports Till closure of contract PC
5. DP-PMX master folder Till next issue Head (PMX)
6. Document Control Register (DCR)
7. Non-conformance review records 2 Years HOD
23.0 LIST OF SOFTWARES DEVELOPED/ USED
Softwares provided by IT department are used.
DEPARTMENTAL PROCEDURE FOR Issue No. : 05 Rev. No. : 00
PROJECT MANAGEMENT Date : 16.03.10 Page : 13 of 17 DP: PMX
Reviewed by Approved by Head (MSX) Head (PMX)
BHARAT HEAVY ELECTRICALS LIMITED, POWER SECTOR WESTERN REGION
PS : WR
24.0 FORMATS USED
S. No. Description Format No. Type
01 Non-conformance report PW-021 I
02 Internal quality audit report, observation notes PW-022 I
03 Training needs identifications PW-027 0
04 Indent PW-009 0
05 Contract information sheet COM-F07 I
06 Daily status report of commissioning SOX-F38 I
07 Daily status report of commissioned unit SOX-F39 I
08 Pending points report SOX-F40 I
09 Erectable analysis & Rolling Plan for 3 months SOX-F41 I
DEPARTMENTAL PROCEDURE FOR Issue No. : 05 Rev. No. : 00
PROJECT MANAGEMENT Date : 16.03.10 Page : 14 of 17 DP: PMX
Reviewed by Approved by Head (MSX) Head (PMX)
BHARAT HEAVY ELECTRICALS LIMITED, POWER SECTOR WESTERN REGION
PS : WR
25.0 ABBREVIATIONS USED
ABBREVIATION EXPANSION
ACT Actual
CIS Contract Information Sheet
CONSUL Consultant
CUST Customer
DESGN Designation
DP Departmental Procedure
EC Engineering Centre
HOD Head of the Department
HOF Head of Function
HQ Head Quarters
I Inputs
I/O Input and Output
MSX Management Services
MQC Management Quality Committee
MR Management Representative
O Output
PC Project Co-ordinator
PM Project Manager
PMX Project management
QLY Quality
REV Revision
REV NO. Revision Number
DEPARTMENTAL PROCEDURE FOR Issue No. : 05 Rev. No. : 00
PROJECT MANAGEMENT Date : 16.03.10 Page : 15 of 17 DP: PMX
Reviewed by Approved by Head (MSX) Head (PMX)
BHARAT HEAVY ELECTRICALS LIMITED, POWER SECTOR WESTERN REGION
PS : WR
S. NO. Serial Number
SCH. Schedule
SIGN Signature
PROJ Construction Management
SP Standard Procedure
TSX Technical Services
Q M Quality Manual
DEPARTMENTAL PROCEDURE FOR Issue No. : 05 Rev. No. : 00
PROJECT MANAGEMENT Date : 16.03.10 Page : 16 of 17 DP: PMX
Reviewed by Approved by Head (MSX) Head (PMX)
BHARAT HEAVY ELECTRICALS LIMITED, POWER SECTOR WESTERN REGION
PS : WR
Project Coordinator
Head Project MGMT
(PMX)
DEPARTMENTAL PROCEDURE FOR Issue No. : 05 Rev. No. : 00
PROJECT MANAGEMENT Date : 16.03.10 Page : 17 of 17 DP: PMX
Reviewed by Approved by Head (MSX) Head (PMX)
BHARAT HEAVY ELECTRICALS LIMITED, POWER SECTOR WESTERN REGION
PS : WR
DEPARTMENTAL PROCEDURE FOR Issue No.: 05 PROJECT MANAGEMENT Rev. No . : 00 Date : 16.03.10 Page : 1 of 1
DP: PMX
Reviewed by Approved by Head (MSX) Head (PMX)
BHARAT HEAVY ELECTRICALS LIMITED, POWER SECTOR WESTERN REGION
PS: WR
SUMMARY OF REVISION
Sl. No. Clause/Page/Format No.
Rev. No. Date Nature of Change
01 Table of Content 00 16.03.10 Aligned in line with QM Issues 05 and SP Issue 04
02 DP : PMX 00 16.03.10 Aligned in line with QM Issues 05 and SP Issue 04
03 Summary of Revision 00 16.03.10 Aligned in line with QM Issues 05 and SP Issue 04