design guide 2
TRANSCRIPT
-
8/7/2019 design guide 2
1/49
ISO NEW ENGLAND PLANNING
PROCEDURE NO. 9 APPENDIX B
Transmission Owners and ISO-NE
Substation Bus Arrangement
Guideline Working Group Report
Presented to the NEPOOL Reliability Committee April 4, 2006
February 23, 2006 Revis ion 18
-
8/7/2019 design guide 2
2/49
Contents
Page
INTRODUCTION 2
EXECUTIVE SUMMARY 2
RECOMMENDATIONS 3
RELATIVE BUS ARRANGEMENT COST
COMPARISON 6
FIGURE A 7
APPENDIX 8
SUBSTATION DESIGNS CONSIDERED 9 - 21
FIGURES 1-17 22 - 39
New England Standard Substation Bus Arrangement WorkingGroup
Company Working Group Member
Northeast Uti l i t ies Roger Zaklukiewicz - Chair
Central Maine Power William Sawyer
Central Maine Power Mike Smallwood
ISO-NE David Forrest
National Grid Dean Latulipe
Northeast Uti l i t ies George Becker
NSTAR Swapan Dey
United I l luminat ing Robert Pellegrini
VELCO John Fiske
VELCO Ed McGann
-
8/7/2019 design guide 2
3/49
INTRODUCTION
At the June 10, 2005 Transmission Owners and ISO-NE meeting, a Working Group
was charged to review possible transmission system substation1 arrangements and
develop a substation bus arrangement guideline for New England. The Working
Groups charge was to review all possible transmission grid substation bus
arrangements and develop a guideline for substation arrangements that best meets
the current and future needs of New Englands Transmission Grid.
EXECUTIVE SUMMARY
The Working Groups scope definition statement to develop a standard substation
arrangement for bulk power system substations is:
The guideline for substation arrangements must support and promote the rel iabi l i ty
of the New England Transmission System. It must incorporate a basic design that is
readily expandable and simplifies substation switching to safely isolate facilities andequipment with minimum adverse impact on power flows. It must provide operating
flexibility, allow for efficient and effective maintenance of substation equipment,
provide for a safe working environment, be cost effective and have the support of the
New England Transmission Owners and ISO-NE.
The Working Group recommends that a breaker-and-a-half bus arrangement be
adopted as the ultimate design for substations that might become major substations
operating at 115 kV or higher. The Working Group further recommends that this
design be considered good utility practice in the ISO-NE approval processes for new
substations and major modifications to existing substations . However, the Working
Group recognizes that in specific cases a different design may also represent good
utility practice and thus merit ISO-NE approval as reliable and cost effective.
WORKING GROUP METHODOLOGY
The methodology used to review and evaluate all potential substation arrangements
and to select a design was as follows:
1. The design must provide for worker safety. The design shall promote
switching sequence consistency and eliminate any possible confusion during
switching operations. It must also promote ease of incorporating appropriate
working clearances into the design.
2. The design must promote the rel iabil i ty of the New England Transmission
Grid and be supported by the New England Transmission Owners and ISO-
NE. The design shall be such that the failure of any switching device in
conjunction with a first contingency protective relay operation or a scheduled
1 The term substat ion is sued throughout the report ; however, the term swi tching stat ion or stat ion may be
in terchanged i f the fac i l i t y te rminates on ly t ransmiss ion l i nes. A substa t ion must have an e lement which
transforms vol tages (t ransformer or autotransformers). A swi tching stat ion or stat ion interconnects t ransmission
lines only.
-
8/7/2019 design guide 2
4/49
outage of any one piece of equipment will not result in the interruption of a
critical transmission path.
3. The design must provide operating flexibility and allow for any substation
element or piece of electrical equipment to be safely isolated with minimal
interruption or risk to the flow of power on the transmission grid.
4. The design must allow for future expandability based on site limitations and
land availability. The design shall promote consideration for expansion as
part of the initial design scope and equipment installation.
5. The design must promote the ef f ic ient and ef fect ive maintenance of
substation electrical equipment. The design shall promote familiarity with a
consistent physical design phi losophy and equ ipment arrangement
throughout New England.
6. The design must be cost
effective.
RECOMMENDATIONS
The following recommendations are the result of the Working Groups analysis of
many possible substation arrangements and their advantages/disadvantages with
respect to the methodology outlined above.
General
1. If these guidelines are accepted, then, this Working Group shall draft a
formal Planning Procedure to document their application, and submit it tothe NEPOOL Reliability Committee.
2. The Working Group recommends that this guideline be considered good
utility practice in the ISO-NE approval processes for new substations 115 kV
and above and major modifications to existing substations 115 kV and above.
3. The Working Group recommends that ISO-NE recognize that in specific cases
a different design may also represent g ood uti l i ty practice and thus may
merit approval as reliable and cost effective. These specific cases should be
dealt with in the ISO-NE approval process.
4. The Working Group recommends, where pract ical , that land shal l be
purchased and equipment shall be arranged to al low for a substation
breaker-and-a-half bus configuration when transmission grid expansions
dictate. It is not recommended that in all cases a substation initially be built
with a breaker-and-a-half bus arrangement, only tha t the design of the
substation provides for expansion to a breaker-and-a-half bus arrangement
when the substation might become a major substation.
5. The Working Group recommends the use of air-insulated bus; however, the
use of gas-insulated bus should be considered good utility practice when it is
-
8/7/2019 design guide 2
5/49
required to provide for a substation arrangement that conforms to the
guidelines.
6. The Working Group recommends that, when designing a new substation or
doing a major modification to an existing substation, that the Transmission
Owner consider the potential for the future termination of transmission
elements. For example, if there is vacant space on existing transmission
rights-of-way emanating from the substation or the substation is located in
an area that is or will be deficient in generation, it may be prudent to plan
the substation for additional transmission elements. A discussion of the
ultimate number of transmission elements should be included in the
application (I.3.9) to ISO-NE.
345 kV Substations
1. For 345-kV substations, the Working Group recommends that the major
substation bus arrangement guideline be a breaker-and-a-half bus
arrangement with space provisions for a series tie breaker in each bay. Thisrequirement only applies to major substations, those that have a reasonable
future potential for a total of (4)2 or more transmission lines, 345-kV
autotransformers, and/or Generator-Step-Up transformers. (see Appendix -
Figure A)
2. Where the failure of a tie circuit breaker produces unacceptable operational
consequences, a series t ie breaker posit ion with no switches between
breakers, may be included in the substation design.
3. If a series tie breaker is installed, there is no intention of terminating a
transmission element between the two series tie breakers. Doing so would
resul t in a Breaker-and-a-third arrangement, which is not the
recommended substation bus arrangement. Therefore, the space provision
for the series tie breaker should leave sufficient space for the series breaker
only, and not for termination of an additional transmission element. No
isolating disconnect switches need to be installed between the two series
breakers.
4. The following transmission elements should terminate in a designated bay
position:
a . A t r ansmiss i on l i ne
b. An autotransformer interconnecting the 345kV transmission grid tothe 230-kV or 115kV transmission grids3
2 The elements in the 345-kV grid tend to be extremely crit ical to the transmission grid rel iabil i ty, thus the added
rel iabi l i ty of a breaker-and-a-hal f scheme wi l l be considered good ut i l i ty pract ice i f 4 or more t ransmission
connections are forecasted.
3 The reason 345-kv autotransfomers may not be terminated on the main busses is because of the design problem
imposed by breaker fai lure cont ingencies for breaker-and-a-hal f stat ions containing 3 or more autotransformers.
With 2 autotransformers at a stat ion (1 on each main bus), instal lat ion of the 3r d
is problematic because wherever
the3 r d
autotransformer is terminated, a breaker fai lure contingency could result in a tripping of 2 autotransformers.
Terminat ing the autotransformer in individual bays el iminates this potent ial operat ing problem.
-
8/7/2019 design guide 2
6/49
c. A Large Generator interconnection.
5. Capacitor banks, reactors and load serving transformers (e.g. 345/34.5 kV)
may be connected to the main buses in the breaker-and-a-half bus
arrangement but must have their own 345-kV circuit breaker and their own
protective relaying that trips this circuit breaker.
230 and 115 kV Substations
6. For 230 and 115 kV substations, the Working Group recommends that the
guideline also be a breaker-and-a-half bus arrangement , but with no space
provisions for a series tie b reaker. This breaker-and-a-half requirement
only applies to major substations, those that have a reasonable future
potential for a total of (4) or more transmission lines, 230 kV
autotransformers, and/or Generator-Step-Up transformers.
7. The following transmission elements should terminate in a designated bay
position:
a. A network (non-radial ) t ransmission l ine4
b. An autotransformer interconnecting the 230kV transmission grid to
the 115kV transmission grid
c . A Large Generator i n terconnect ion
Note that 115/69-kV autotransformers may be connected to the 115-kV main
bus.
8. Capacitor banks and reactors may be connected to the main buses in the
Breaker-and-a-half bus arrangement but must have their own circuit
breaker and their own protective relaying that trips this circuit breaker.
9. Load serving transformers (e.g. 115/13.8 kV) may be connected to the main
buses in the Breaker-and-a-half bus a rrangement. These transformers may
be connected to the main bus util izing a circuit breaker, circuit switcher, or
disconnect switch.
69 kV Substations
The working group makes no recommendations for 69-kV substation designs.
4 The intent of the non-radial qualif ier is to al low radial l ines supplying load serving transformers (e.g., 115/13.8
kV) to be connected directly on the main bus.
-
8/7/2019 design guide 2
7/49
RELATIVE BUS ARRANGEMENT COST COMPARISON
The selection of the appropriate station bus arrangement should meet a ll known or
anticipated transmission reliability, operating, and maintenance criteria and future
expansion requirements taking into account recognized acceptable contingencies and
the associated risks to the Transmission Grid.
To assist in the overall evaluation, Table 1 provides a high level cost comparison of
the various substation bus arrangements, should it be necessary to conduct an
economic comparison.
Table 1: Station Bus Arrangement Cost Comparison 5
Bus Arrangement
Approximate RelativeCost Comparison
Single Bus 100%
Sectionalized Bus 122%Main and Transfer Bus 176%
Ring Bus 156%
Breaker-and-a-half 158%
Double Bus - Double Breaker 214%
The comparison is based on the cost to install a four-circuit low-profile outdoor bus
arrangement with power circuit breakers in al l circuits. Power transformer and
land costs are not included in the cost comparison. In schemes uti l izing other
protective devices or different circuit quantities, the relative costs may vary from
those listed.
5 McDonald, John D. Electric Power Substations Engineering CRC Press, New York p. 3-6, 2003
-
8/7/2019 design guide 2
8/49
FIGURE A
-
8/7/2019 design guide 2
9/49
APPENDIX
-
8/7/2019 design guide 2
10/49
SUBSTATION DESIGNS CONSIDERED
TRANSMISSION SUBSTATIONS
In this report, a substation is designated a Transmission Substation when it isdesigned to operate at 115 kV or higher,. Since one transmission substation may
supply several distribution substations and large loads, rel iabi l ity of service and
flexibility of operation are extremely important. The substation design must permit
faci l i t ies and electr ical equipment to be maintained without having to interrupt
other transmission l ines, transformers, or equipment necessary to maintain the
reliability and integrity of the transmission grid. The e mployment of multiple buses,
circuit breakers, and isolating disconnect switches for switching and isolation
provide the required system flexibi l ity. A transmission substation is distinguished
from a transmission switching station in that it incorporates a transformer(s) or
autotransformer(s) which convert the transmission vol tage to ei ther a lower
transmission voltage or a distribution voltage.
TRANSMISSION SWITCHING STATIONS
Transmission switching stations do not change system voltage from one level to
another and therefore do not contain power transformers. Depending on system
voltage, the equipment types and characteristics used in transmission switching
stations are identical to those used in transmission substations. The charge to the
Working Group did not include the detai l engineering design of the substation
faci l i t ies, electrical equipment, control houses, or i ts protection and controls
capabilities and circuitries. As future ISO-NE/Transmission Owner standards are
developed, consideration should be given to the development of such standards to
maximize the reliability of the New England transmission grid, minimize operating
complexities, maximize flexibility, reduce operating risks, and ensure worker safety.
UNIVERSAL SUBSTATION BUS ARRANGEMENTS
The Working Group conducted a paper search and studied each of the bus
arrangements most typically employed for transmission voltages th rough 765 kV in
North America and Western Europe. The Working Group recognized that initially, a
transmission substation or switching station might only terminate two transmission
l ines or terminate into a single transformer/autotransformer. However as the
transmission grid expands to accommodate growing load and additional generation,
that simple substation/switching station could develop into a ful l f ledged faci l i tyhaving signif icantly greater importance and requiring far greater f lexibi l i ty and
complexity. Therefore, the recommendations of the Working Group must
incorporate a stepped approach for those substations/switching stations that initially
are small which permits their expansion in a systematic manner without adversely
impacting the reliability of the transmission grid.
The physical size, type, and arrangement of major equipment, such as power
transformers, circuit breakers, disconnect switches, dimensions of the property
owned by the Transmission Owner, and location of adjacent transmission line rights
-
8/7/2019 design guide 2
11/49
of way and private developments may cause variance in the layouts to suit
individual requirements. However, the construction of the new or expansion of the
existing bus arrangement should not compromise the preferred bus arrangement
guideline. The Working Groups scope includes recommending a preferred
substation/switching station bus arrangement; this does not include detailed
engineering/design of the facility.
SINGLE BUS ARRANGEMENT
A single substation bus arrangement consists of one main bus that is energized at
all times and to which all transmission lines and transformers are connected. Each
transmission line or transformer is electrically connected to the main bus through a
single circuit breaker. This arrangement is the simplest to design and operate, has
the least amount of equipment, but provides the least amount of f lexibi l i ty and
system rel iabi l i ty. Figure 1 depicts a possible single bus station arrangement. It is
not possible to perform maintenance work on the main bus or sections of a
transmission l ine or transformer directly connected to the bus without taking the
entire station out of service. Once in service, the entire station must be de-energizedto extend the main bus or to connect an additional transmission line or transformer
to the main bus.
Any bus fault or failure of a circuit breaker to operate under fault conditions will
result in complete loss of the station. The loss of the entire transmission station
could result in transmission line and equipment overloads, unusual power flows
throughout the transmission grid. Therefore, in both the planning and real t ime
contingency analysis studies, the loss of a single bus station must be a recognized
contingency when the studies are being performed.
On the distribution system, a single bus arrangement is not recommended without
providing circuit breaker bypass switching capability that permits circuit breaker
maintenance while maintaining circuit operation. Switches are provided that, when
closed, parallel two lines to enable one circuit breaker to be removed from service.
The other breaker then protects both circuits. Figure 2 i l lustrates a single bus
station with circuit breaker bypass switches. This arrangement, however, results in
the possible loss of overcurrent or step distance relay protection coordination for the
distribution circuit. A fault occurring on the l ine with the breaker bypassed could
result in the loss of multiple circuits or complete deenergization of the station. Such
operating risks are not acceptable on the transmission grid; therefore, a single bus
arrangement that employs bypass switch facilities should not be installed on the
transmission grid.
Advantages:
1 .Lowes t cos t2 . S m a l l l a n d a r e a r e q u i r e d
3.S imple const ruc t ion
4.S imple in concept and operat ion
5.Relatively simple for the application of protective relaying
Disadvantages:
11
-
8/7/2019 design guide 2
12/49
1. A s ingle bus ar rangement has the lowest re l iabi l i ty
2. Has the least maintenance and operat ing f lex ib i l i ty
3. Circuit breaker maintenance requires opening the transmission line terminal or
removing the transformer from service
4. Highest potential for the loss of the entire station for a bus fault, a fault on any
element directly connected to the main bus or for the failure of a circuit breaker
5. Must remove the entire main bus from service to extend the bus or connect an
additional transmission line or transformer position
6. Circuit breaker bypass facilities do not provide for circuit protection when bypass
facilities are being used
Use of the circuit breaker bypass facilities to support maintenance can compromise
or disable some of the protective relay applications and overall relay coordination
Conclusion:
A single bus arrangement is not a suitable design for a major
transmission station.
SECTIONALIZED BUS ARRANGEMENT
An extension of the single bus configuration is the single bus station with bus
sectionalizing circuit breaker arrangement shown in Figures 3. This arrangement
electrical ly connects two or more single bus schemes with one or more bus
sect ional izing ci rcui t breakers. The sect ional izing ci rcui t breaker(s) may be
operated normally open or closed, depending on system requirements. In this
arrangement, a bus fault or breaker-failure causes only the affected bus section to be
removed from service and thus eliminates the risk of the loss of an entire station.Power flows on the transmission grid under normal and emergency conditions must
be taken into consideration when locating transmission l ines and transformers on
each section of the bus such that load is not separated from its source when the
sectionalizing circuit breaker is opened. This can be accomplished by positioning
interrelated transmission l ines on different bus sections to minimize or el iminate
entirely the possibility of abnormally low voltage or overloaded transmission line
conditions.
A main bus fault or breaker-fai lure condit ion can be isolated to the faulted bus
section without interrupting the entire station. The adverse impact of a bus fault or
breaker-failure on the transmission grid is appreciably less when a sectionalizing
circuit breaker is installed between the buses due to the increased flexibility of this
bus arrangement.
Advantages:
1.Greater operat ing f lexibi l i ty than a single bus arrangement
2.Higher re l iabi l i ty than a s ingle bus ar rangement
3.Abi l i ty to isolate bus sect ions for maintenance
12
-
8/7/2019 design guide 2
13/49
4.S imple const ruc t ion
5.S imple in concept and operat ion
6.Loss of only part of the station fol lowing a bus fault or breaker-fai lure condit ion
7.Relat ively simple for the appl icat ion of protect ive relaying
Disadvantages:
1. A sectionalized bus arrangement has a higher cost than a single bus
arrangement
2. Addi t ional ci rcui t breakers are required for sect ional izing
3. Sectionalizing may cause isolation of source circuits from load circuits for a bus
fault, a fault on any element directly connected to a bus ,or for the failure of a
circuit breaker.
4. Circuit breaker maintenance requires opening the transmission line terminal or
removing the transformer from service
5. Must remove a bus section from service to extend the bus or connect an
additional transmission line or transformer position to that bus section
6. Potential for the loss of the entire station for a bus fault with the failure of thebus tie circuit breaker
Conclusion:
A sectionalize bus arrangement is not a suitable design for a
major transmission station.
MAIN AND TRANSFER BUS ARRANGEMENT
A main and transfer bus arrangement consists of two independent buses, one of
which, the main bus, is normal ly energized. During normal operat ions, al l
transmission l ines and transformers are electrical ly connected to the main bus
similar to that of a single bus station arrangement. When it is necessary to remove a
circuit breaker from service for maintenance or repair, it is possible to switch the
transmission l ine or transformer to the transfer bus such that there is no loss of
service. The isolation switches associated with the bus tie circuit breaker are closed,
the bus t ie circuit breaker is closed energizing the transfer bus, then the bypass
switch for the circuit breaker to be isolated is closed parallel ing the transmission
line or transformer to the main and transfer buses. The bypassed circuit breaker
and its isolation switches are then opened to remove the circuit breaker from
service. The transmission l ine or transformer is then protected by the protective
relaying package associated with the bus tie circuit breaker.
Figure 4 i l lustrates simplif ied main and transfer bus station arrangements. As with
the single bus arrangement it is possible to incorporate one or more sectionalizing
circuit breakers to provide additional operating flexibility and reliability. Figure 5
i l lustrates a main and transfer bus arrangement stat ion incorpo rat ing a
sectionalizing circuit breaker which minimizes the number of transmission lines and
transformers on each bus section. With this arrangement, there is appreciably less
13
-
8/7/2019 design guide 2
14/49
risk that a bus fault or breaker-failure condition would result in the loss of the
entire station. In addition, its possible to incorporate more tailored protection
packages for each bus tie circuit breaker.
Advantages:
1. Ability to perform circuit breaker maintenance while maintaining transmission
line and transformer service
2. Reasonable in cost3 . F a i r l y s m a l l l a n d a re a
4. Where the transmission lines and transformers can be placed on the transfer bus
the main bus can be readily expanded without service interruption
Disadvantages:
1. An addi t ional ci rcui t breaker is required for the bus t ie posi t ion
2. Since the bus tie breaker has to be able to be substituted for any transmissionline or transformer circuit breaker, its associated protective relaying must have
the functional capability of the protective relaying for each element connected to
the bus and relay settings must be changed for each use of the transfer circuit
breaker.
3. Failure of a circuit breaker or a bus fault causes loss of the entire substation4. Somewhat complicated switching is required to remove a circuit breaker from
service for maintenance
5. May have to remove some transmission lines or transformers from service to
extend the bus o r connect an additional transmission line or transformer position
to that bus section
6. Loss of the entire station for a bus fault, a fault on any element directly
connected to the main bus or for the failure of a circuit breaker
Conclusion:
A main and transfer bus arrangement is not a suitable design for a
major transmission station.
RING - BUS ARRANGEMENT
The ring-bus station arrangement is one o f the simplest and most commonly
constructed transmission bus arrangements in existence. In a r ing bus
arrangement, circuit breakers are placed between transmission lines or transformer
position as illustrated in Figure 6; there are always two circuit breakers associated
with each transmission l ine or transformer posit ion. Since each circuit breaker in
the ring is shared, it is possible to perform maintenance on each circuit breaker
without impacting the operation of the transmission line or transformer position on
either side of the circuit breaker.
14
-
8/7/2019 design guide 2
15/49
Bus differential protection packages are not required because there is no designated
main or transfer bus in this arrangement. The section of the ring between circuit
breakers is always protected by the protective relaying package of each transmission
line or transformer position. The philosophy and application of the protection and
controls ci rcui t r ies for ei ther the transmission l ine or t ransformer posi t ion are
similar lending them to an ease of understanding of how each protective relay
package works. The required switching to safely isolate each transmission line or
transformer position is also similar which simplifies operations and should result in
improved system reliability.
Ring buses should be limited in total to four to six transmission line and transformer
positions in order to maximize the flexibility and reliability of this bus arrangement.
This l imi tat ion is dr iven by the two factors. Whenever maintenance is being
performed on a circuit breaker or one of its two isolating disconnect switches one
must open the bus which interrupts the normal flow of power around the ring bus.
In certain operating circumstances, power flows in sections of the bus could exceed
the current ratings of circuit breakers, disconnect switches, or other hardware.
More importantly, should a fault occur on a transmission l ine or transformerconnected to the bus, it is possible that source transmission lines could be isolated
from transmission l ines and transformer posi t ions which are serving load.
Whenever the ring bus must be opened to perform maintenance or during shorter
periods to perform switching, the reliability of the ring bus arrangement decreases
to that of the single bus arrangement with sectionalizing circuit breakers.
When system studies indicate that system rel iabi l i ty degrade s signif icantly when
two transmission l ines or one transmission l ine and one transformer are
simultaneously removed from service they should not share a common circuit
breaker. The most common case occurs whenever two transmission lines are located
on a common transmission structure, determining where be st to connect each
transmission line to the ring bus. If the transmission lines are connected in adjacent
posit ions both transmission l ines wil l be lost for a breaker-fai lure condit ion. If they
do not share adjacent positions in the ring, there is the possibility that the bus will
be split whenever a d ouble circuit transmission line fault occurs. The p robability of
each contingency occurring must be studied and incorporated in the decision of
where to locate each transmission line or transformer on the ring bus.
Once constructed and placed in service, it is difficult to expand the ring bus unless
planned for in the engineering/design phase. Of concern in New England are the
multiple transmission element outages that can occur following a breaker-failure
contingency. If i t is unacceptable to have adjacent posit ions of a ring bus out of
service simultaneously, a possible solution is to install two circuit breakers in seriesas i l lustrated in Figure 7. In this conf igurat ion a breaker-fai lure of the ci rcui t
breakers associated with either Line 1 or Line 2 nearest transformer T1, would not
result in the simultaneous loss of transformer T1. It is not possible to predict how
the transmission gr id wi l l develop; therefore, i f r ing-bus stat ions a re ini t ial ly
instal led it may be prudent to al low for the addit ion of a series circuit breaker on
either side of each circuit breaker. A second alternative would be to design the bus
so that i t can be easily expandable to a breaker-and-a-half arrangement as
i l lustrated in Figure 8.
15
-
8/7/2019 design guide 2
16/49
Advantages:
1 . F l ex i b le opera t ion
2. Ease of understanding zones of protection, controls, and personal safety
3 . H i g h r e l i a b i l i t y
4. Isolation of circuit breakers for maintenance without disrupting transmission
line or transformer operation
5. Double feed to each transmission l ine or t ransformer posi t ion
6 . N o m a i n b u s es
7. Expandable to breaker-and-a-hal f bus ar rangement
8. Lowest cost bus design wi th s imi lar re liabi l i ty and flex ib i l ity
Disadvantages:
1. Ring bus wil l spl i t for faul ts on two transmission l ines on a common
transmission structure or for a fault on a transmission line or transformer
position during breaker maintenance to leave possibly undesirable circuitcombinations (supply/load) on the remaining bus sections.
2. Each circui t has to have i ts own potential source for protect ive relaying.
3. This configuration is usually limited to four circuit positions, although larger
rings are in service. A 6-postion ring bus is usually considered as a maximum
limit for the number of terminals in a ring bus.
4. The protective relaying and controls schemes are more involved since each
circuit breaker has to respond to faults on two circuits.
5. Automatic reclose schemes may be more complex since each circuit breaker may
have different control modes depending upon which transmission l ine or
transformer position trips.
6. Di f f icul t to expand unless ini t ial design incorporates that f lexibi l i ty
Conclusion:
A ring bus arrangement is not a suitable design for a major
transmission station. However a ring bus that can be expanded into a
breaker-and-a-half bus arrangement would be suitable for the
initia l desig n of a substat ion that may become a major substation in
the future.
BREAKER - AND - A - HALF BUS ARRANGEMENT
The breaker-and-a-half bus arrangement is relatively simple and consists of two
main buses, each normally energized. Between each of the main buses are similarly
arranged bays of three circuit breakers configured such that the two transmission
lines or combination transmission l ine and transformer posit ion share the center
circuit breaker as i l lustrated in Figure 9. Each transmission l ine o r transformer
position shares the common center circuit breaker, so there are one-and-a-half
16
-
8/7/2019 design guide 2
17/49
circuit breakers per position; therefore, the designation a breaker-and-a-half bus
arrangement.
The breaker-and-a-half bus arrangement is the most prominently used transmission
substation configuration in North America. It is more rel iable than a ring-bus
arrangement and provides appreciably more operating flexibility.
Similar to a ring-bus configuration, each transmission l ine or transformer posit ion
can be served from two directions. It is possible to maintain one of the two circuit
breakers associated with each transmission l ine or transformer posit ion without
impacting power flow. Since each of the bays connects to a main bus, the breaker-
and-a-half bus arrangement does not have the operating restrictions of a ring bus
arrangement when work is being performed on a circuit breaker as the main buses
are designed to carry appreciably greater current flows than the c ircuit breakers and
buses in any given bay. Simi lar to a r ing-bus conf igurat ion, one should not
electrically connect two transmission lines or a transmission line and a transformer
that cannot be simultaneous out of service to adjacent positions in a given bay. A
breaker-failure of the shared circuit breaker would require the interruption of powerflow to both positions should such a contingency occur. Additionally, faults on either
of the main buses cause no circuit interruptions
The breaker-and-a-half bus arrangement has little advantage over the ring bus
arrangement when there are in total fewer than four t ransmission l ines or
transformer station positions. Breaker-and-a-half stations are more expensive to
construct than ring bus stations; therefore, if the number of positions is to remain
limited well into the future, designing and constructing a ring bus station would be
the more cost effective solution. The breaker-and-a-half arrangement should be
used for stations where there a large number of transmission lines and transformer
positions terminating at that location.
At those locat ions where the number of t ransmission r ight of way corr idors is
l imited and a majority of the transmission l ines must exit on a single transmission
right of way a variation of the basic breaker-and-a-half station may be preferred.
Figure 10, il lustrates such an arrangement. The folded breaker-and-a-half station
arrangement is electrically identical to the bus arrangement in Figure 9; however, it
is designed to assist transmission l ine engineers maximize the number of
transmission lines that can exit the station where limited right of ways exist.
As with ring-bus stations, once a breaker-and-a-half station is constructed and
placed in service, i t is diff icult to place a second breaker in series with a circuit
breaker unless provisions are incorporated during the initial engineering design ofthe station. Transmission grid operating conditions may n ot allow the simultaneous
loss of two transmission l ines or the combination of a transmission l ine and a
transformer posit ion fol lowing a breaker-fai lure. In a breaker-and-a-half station
arrangement, such design provisions only need to be incorporated for the center or
shared circuit breaker position. If one of the circuit breakers directly connected to
ei ther main bus posi t ion were to fai l , only the transmission l ine or t ransformer
posi t ion direct ly connected to the posi t ion would remain impacted. Figure 11
illustrates possible connections of two circuit breakers in the center or shared circuit
breaker position.
17
-
8/7/2019 design guide 2
18/49
Figures 12 and 12A illustrate an autotransformer electrically connected to one of the
main buses through a disconnect switch. Should there be a faul t in the
autotransformer, it would be necessary to trip all circuit breakers directly connected
to that main bus and the transformers low voltage bus circuit breaker(s) to isolate
the fault from the transmission grid. The ISO-NE standard should not al low a
Transmission Owner to electrical ly connect any circuit element to the main bus
without a circuit breaker or a circuit switcher. The reliability of the entire station
decreases when direct connection of a capacitor bank, a transformer or a
transmission l ine to the main bus is permit ted. Operat ing f lexibi l i ty is also
negatively impacted requiring the main bus to remain out of service anytime work
must be performed on the disconnect switch or circuit switcher. The cost to install
the addit ional circuit breaker is not tr ivial; however, the potential negative impacts
to the breaker-and-a-half station outweigh those added costs. It is the working
groups recommendation that such electrical connections not be permitted.
Advantages:
1. Greater operat ing f l ex ibi l i t y than a r i ng bus
2 . H i gher re l i ab i li t y t han a r i ng bus
3. Abi l i ty to isolate ei ther main bus for maintenance without disrupt ing service
4. Can isolate any circuit breaker for maintenance without disrupting service to the
transmission l ine or transformer
5. Double feed to each transmission l ine or t ransformer6. Bus faul t does not interrupt service to any transmission l ine or t ransformer
7 . A l l sw itch ing per formed w i th c i rcu i t b reakers
8. Maintenance of circuit breaker or isolating disconnect switch does not open the
bus should a fault occur during the maintenance period
9. Appreciably less r isk of isolat ing Transmission gr id sources from the load
10. Easy to add a double bus doub le breaker bay
Disadvantages:
1. Greater costs than a r ing bus stat ion ar rangement
2. One-and-a-hal f c ircui t breakers are required per c i rcuit
3. Utilization of different protective relaying and control philosophies within the
station
4. The protective relaying and control schemes are more involved and complex since
the center or common circuit breaker has to respond to faults on two circuits
5. Automatic reclose schemes associated with the center or common circuit
breakers may be more complex since each circuit breaker may have different
control modes depending upon which transmission line or transformer position
trips
6. Each transmission l ine requires i ts own potent ial source for relaying
7. Must remove one of the bus sections from service to extend the bus or electrically
connect another bay to the station
8. Difficult to add a second circuit breaker in series with the center or common
circuit breaker unless space is provided in the original station design
18
-
8/7/2019 design guide 2
19/49
9. A bus fault requires the tripping of one breaker per bay, therefore increasing the
potential for a breaker-failure contingency to occur if there are many bays
Conclusion:
A breaker-and-a half bus arrangement is a suitable design for a
major transmission station.
BREAKER - AND - A - THIRD BUS ARRANGEMENT
The breaker-and-a-third uti l izes four circuit breakers between its main buses and
has two common circuit breakers. The reliability of a breaker and third bay is lower
than the bay of a breaker-and-a-half arrangement; however, i t is better than that of
a ring bus station. A breaker-fai lure of either of the shared circuit breakers wil l
result in the loss of two transmission facilities (line or transformer) similar to that in
a breaker-and-a-half station. The difference being that with a breaker-and-a-thirdbus arrangement the probability that this contingency might occur is twice as great.
Figure 13 il lustrates a breaker-and-a-third bus arrangement.
Advantages:
1. Greater operat ing f l ex ibi l i t y than a r i ng bus
2 . H i gher re l i ab i li t y t han a r i ng bus
3. Abi l i ty to isolate ei ther main bus for maintenance without disrupt ing service
4. Can isolate any circuit breaker for maintenance without disrupting service to the
transmission l ine or transformer
5. Double feed to each transmission l ine or t ransformer
6. Bus faul t does not interrupt service to any transmission l ine or t ransformer7 . A l l sw itch ing per formed w i th c i rcu i t b reakers
8. Maintenance of circuit breaker or isolating disconnect switch does not open the
bus should a fault occur during the maintenance period
9. Appreciably less r isk of isolat ing Transmission gr id sources from the load
Disadvantages:
1. Greater costs than a r ing bus stat ion ar rangement
2. One-and-a- th i rd c i rcui t breakers are required per c i rcui t
3. Utilization of different protective relaying and control philosophies within the
station
4. The protective relaying and control schemes are more involved and complex since
the two center or common circuit breakers h ave to respond to faults on two
circuits
5. Automatic reclosing schemes associated with the two center or common circuit
breakers may be more complex since each circuit breaker may have different
control modes depending upon which transmission line or transformer position
trips
6. Each transmission l ine requires i ts own potent ial source for relaying
19
-
8/7/2019 design guide 2
20/49
7. Must remove one of the bus sections from service to extend the bus or electrically
connect another bay to the station
8. Difficult to add a second circuit breaker in series with either of the center or common
circuit breakers unless space is provided in the o riginal station design
9. The risk of a failure of a shared breaker may be twice as great as that for that of a
breaker-and-a-half bus arrangement.
10. A bus fault requires the tripping of one breaker per bay, therefore increasing the
potential for a breaker-failure contingency to occur if there are many bays
Conclusion:
A breaker-and-a -third bus arrangement is a suitable design for a major
transmission station. In cases where a breaker-and-a-half arrangement
is not feasible, either physical ly, environmental ly, or economical ly,
a breaker-and-a-third bus arrangement may be an acceptable
alternative.
DOUBLE BUS
DOUBLE BREAKER ARRANGEMENT
The double bus - double breaker bus arrangement is employed where ult imate stat ion
rel iabi l i ty is required. This bus arrangement provides the greatest rel iabi l i ty and
flexibi l i ty and has the greates t co st. Th e two main buses are normally energized; in
each designated bay between the main buses are two circuit breakers and, between the
circuit breakers is a transmission line or transformer position as il lustrated in Figure 15.
In the double bus - double breaker arrangement, any circuit breaker can be removed from
service wi thout interrupt ing the power f lows on any transmission l ine, t ransformer
posi t ion or the main bus. A faul t on ei ther main bus has no direct impact on the
power f lowing o n any tran smission l ine or transformer posit ion. Equally important, a
breaker-failure contingency results in the loss of only one transmission line ortransformer position.
The protection and control schemes for each transmission line and transformer
position will be similar minimizing the complexity of the schemes associated with the
center or common b reaker of a b reaker-and-a-half station. The required switching
and tagging for each transmission line or transformer position will be similar, which
should make it easier for the workers to understand and switch.
Use of the double bus - double breaker has tradit ionally been l imited to large
generating stations because of its higher cost. The additional reliability afforded by this
arrangement over the breaker-and-a-half scheme usually cannot be justified for conventional
transmission stations. Occasionally, one bay of a breaker-and-a-half arrangement is used
as a double bus - double breaker arrangement for a generator lead, critica l tran smission
line, o r large autotran sformer, that re quires access to either main bus.
Advantages:
1. Greatest operation f lexibi l i ty
20
-
8/7/2019 design guide 2
21/49
2 . V e r y h i g h re l i a b i l i t y
3. Abi l i ty to isolate ei ther main bus for maintenance without disrupt ing service
4. Can isolate any circuit breaker for maintenance without disrupting transmission
line or transformer operation
5. Double feed to each transmission l ine or t ransformer posi t ion
6. Bus fault does not interruption service to any transmission l ine or transformer
7. Loss of only one transmission line or transformer position following a breaker-
failure contingency
8. No need to place two circuit breakers in series to negate the negative impacts of
a breaker-failure contingency
9. Maintenance of circuit breaker or isolating disconnect switch does not open the
bus should a fault occur during the maintenance period
10. A l l swi tching pe r formed wi th c i rcu i t breakers
11. Least r isk of isolat ing Transmission gr id sources from load
12. Similar protective relaying and control schemes for each bay
13. Switching for each transmission l ine or t ransformer posi t ion is simi lar
Disadvantages:
1. This bus conf igurat ion has the highest cost
2. Two circuit breakers are required for each transmission line or transformer
position
3. Utilization of different protective relaying and control philosophies within the
station
4. Each transmission line or transformer position requires its own potential source
for relaying
5. Must remove both of the main buses from service to extend the bus or electrically
connect another bus to the station
6. Requi res more land than a breaker-and-a-hal f stat ion
7. A bus fault requires the tripping of one circuit breaker per bay, therefore
increases the potential for a breaker-failure contingency to occur if there are
many bays
Conclusion:
Under normal c ircumstances, a double-bus-double-breaker bus
arrangement is too costly a design to be considered good utility
practice for a major transmission substation. However there may be
specific cases where the use of this bus arrangement may be
prudent, to address real estate constraints or the need for greater
reliability.
21
-
8/7/2019 design guide 2
22/49
FIGURES 1-17
22
-
8/7/2019 design guide 2
23/49
-
8/7/2019 design guide 2
24/49
0-- LINE 1
LINE 2
i
FIGURE 2 : SINGLE BUSARRANGEMENT WITHBREAKER BYPASSSWITCHES
-
8/7/2019 design guide 2
25/49
L I N E 4 - u L I N E 3
T2--, LINE 2
LINE 1
_LINE 4
_LINE 2
_ T1
_- LINE 1
FIGURE 3 :SINGLE BUS STATIONSWITH SECTIONALIZING
BREAKER
-
8/7/2019 design guide 2
26/49
/
- _ -LINE 2E E___/ i1.--- LINE 1
MAINBUS
E E
E E
TRANSFER MAIN
BUS BUS
T,_
][ 1 ---
L_
-
8/7/2019 design guide 2
27/49
TRANSFERBUS
FIGURE4 :MAIN&TRANSF
ERBUSARRANGEMENTS
-
8/7/2019 design guide 2
28/49
L INE 4
1.-- LINE 3
'''''',....______.-
------____.
__'
'I'*s..............
_1.- LINE 2
T1
,--- LINE 1
MAIN TRANSFERBUS BUS
FIGURE 5 :MAIN & TRANSFERARRANGEMENT WITH BUSSECTIONALIZING BREAKERS
-
8/7/2019 design guide 2
29/49
a
/1
0
/ LINE 4
0
/
E 2
E 3
.
FIGURE 6 :RING-BUS ARRANGEMENT
-
8/7/2019 design guide 2
30/49
LINE 4 / LINE 5
/ LINE 1LINE 3
LINE2
1
A
I
II
Le
L e/),
-
8/7/2019 design guide 2
31/49
)
1 _
_ _
_ _
E l
/.-
L
j [nT1
R
-
8/7/2019 design guide 2
32/49
ING-BUSARR
ANGEMENTWI
THFIGURE7:
-
8/7/2019 design guide 2
33/49
PROVISIONS
FORTWOBRE
AKERSINSER
-
8/7/2019 design guide 2
34/49
IES.
-
8/7/2019 design guide 2
35/49
LINE1 [ T 1
---0---L---0---1 \--0----.
LINE 2 LINE 3-... ...-
.-,-0------E1---L--0----.
L I N E 5 F LINE 41I II I\ i
---D-- --i---D--- --- .....-
FIGURE 8 : RING-BUS EXPANDABLE TO BREAKERAND-A-HALF BUSARRANGEMENT
-
8/7/2019 design guide 2
36/49
LINE 51.--LINE 2
LINE T1
LINE 3 LINE
FIGURE 9 : BASIC BREAKER-AND-A-HALFBUS ARRANGEMENT
-
8/7/2019 design guide 2
37/49
LINE 1 LINE 2 LINE 3 T1 LINE 5
F IGURE 10 :FOLDED BREAKER-AND-A-HALF BUS
ARRANGEMENT
-
8/7/2019 design guide 2
38/49
LINE 3 LINE 4
LINE 1 T1
LINE 2 LINE 5
FIGURE 1 1 : BREAKER-AND-A-HALF BUS ARRANGEMENT
WITH PROVISIONS FOR TWO
BREAKERS IN SERIES
-
8/7/2019 design guide 2
39/49
LINE 4
LINE 3
L
LOW VOLTAGEBUS
LOW VOLTAGEBUS
LINE 2 LINE 5
FIGURE 12A :BREAKER-AND-A-HALF BUS ARRANGEMENTWITH AUTO TRANSFORMER CONNECTED TO A MAIN
BUS
-
8/7/2019 design guide 2
40/49
LINE 4
LINE 3
LINE 1 LINE 6
LINE 2 LINE
LOW VOLTAGE LOW VOLTAGEBUS BUS
FIGURE 12A :BREAKER-AND-A-HALF BUS ARRANGEMENTWITH AUTO TRANSFORMER CONNECTED TO A
MAIN BUS
-
8/7/2019 design guide 2
41/49
LINE 4
LINE 7 LINE 8
LINE 1
LINE
2
__LINE
5
LINE 3
LINE 6
-
8/7/2019 design guide 2
42/49
GURE1
3:COMBINA
TIONBREAKER-AND-A-
HALFANDB
R
-
8/7/2019 design guide 2
43/49
EA
KER-AND-A-
THIRDBUSARRANGEME
NT
-
8/7/2019 design guide 2
44/49
FIGURE 14 :DOUBLE BUS-DOUBLE BREAKER BUS ARRANGEMENT
-
8/7/2019 design guide 2
45/49
LINE 4..-LINE 1
LINE 3.-INE 2
CRITICAL LINE or AUTOTRANSFORMER
-0--,---1--0---
i---E3--
- 1 = 1 - - - - - - - - E 1 - -
L - - E 1 -
-
8/7/2019 design guide 2
46/49
FIGURE 15 :COMBINATIONDOUBLE BUSDOUBLE BREAKERAND BREAKERANDAHALF BUSARRANGEMENT
-
8/7/2019 design guide 2
47/49
FIGURE 16 : CROSSED-RING-BUS ARRANGEMENT
-
8/7/2019 design guide 2
48/49
LINE 1,LINE 8
LINE 2,LINE 7
LINE 3
LINE 4,
LIN
E 6
LINE 5
-or
FIGURE 17 : RING-
BUS
-
8/7/2019 design guide 2
49/49
ARRANGEMENTWITHBRIDGINGCIRC
UITBREAKER